After deduction 22.51 m3 4100 ₹92,292.

23

3 Solid block masonry(10cm thick)


in CM 1:5 .Using good quality Solid
block(30x10x15cm) .Including the
cost of all materials and labour etc.
Inside 1 43.5 0.15 2.8 18.27
18.27
Deductions
D1 4 0.9 0.2 2.1 1.512
D2 3 0.8 0.2 2.1 1.008
2.52
After deduction 15.75 m3 4100 ₹64,575.00

4 Reinforced cement concrete 1:1.5:3 for


beam and lintel .Using 20mm aggregate.
Including the cost of all materials and
labour etc. complete. But excluding
the cost of reinforcement.
Lintel 1 92.3 0.2 0.2 3.692
Beams 3 2 0.2 0.3 0.36
5 1.5 0.2 0.3 0.45
2 3.8 0.2 0.45 0.6901
5 2.7 0.2 0.45 1.2258
4 4.6 0.2 0.6 2.208
8.6259 m3 9000 ₹77,632.92

5 Reinforced cement concrete 1:1.5:3 for


slab .Using 20mm aggregate.
Including the cost of all materials and
labour etc. complete. But excluding
the cost of reinforcement.
Slab 1 11.4 11.4 0.12 15.636
Stair 2 3.15 0.9 0.12 0.6804
16.317 m3 9000 ₹146,849.76

6 Reinforcement for R.C.C works bent,tied


and placed in position . Using HYSD steel
including the cost of binding wire, all
materal and labour etc.complete.
Say item no 3,6,9,11 and 12 .Qty 29.983 m3
Say29.98 m3/100.00 kg 2998.3 kg 60 ₹179,895.12

7 Plastering CM 1:4.Using good


quality sand including the cost of
all materials and labour etc. complete.
Column 18 1.2 3.3 71.28
Walls 2 92.3 3.3 609.18
Beam 3 2 1 6
5 1.5 1 7.5

S3 7/9