Progress Report of APDRP works of VARANAS

Sl Details of work Tender Name of the firm Qty Cost of Total Physical progress
No Spec No to whom work Pack age made.
order (Rs in Lacs) During
placed/Date of the
contract month.
1 2 3 4 5 6 7
1 LT & HT Accu check meters APDRP/0 M/s secure 1HT+1LT 2.46
3-04/10 meters . Ltd
Solan.
2 Cable Fault locating APDRP/0 M/s PCI New 1 40.78+0.78 1
system. 3-04/42 Delhi.
3 Oil Certrifuging machines. APDRP/0 M/s CEE DEE 1 3.30 1
3-04/19 Vacuum Eqpt
pvt ltd, Pune.
4 Increasing Capacity of DTs APDRP/0 M/s Awadh 113No.DTs. 559.37+56.00=
& metering of all DTs. 3-04/52 Transformers upgradation 616.00
P.Ltd.Sultanpur +metering of
1088 DTs.
5 New 33/11 KV - S/Ss& APDRP/0 M/s 7Nos.1x5 2362.48+25.96
associated 33KV and 11KV 3-04/40 Instrumentation MVA new =2388.44
Lines. Ltd Lko S/S &
connected
33KV &11
KV lines

6 R&M of 33/11kv S/S APDRP/0 M/s 17Nos.33/11 614.96+13.61=


3-04/34 Instrumentation kv S/S of 628.57
Ltd Lko Varanasi
Town

7 Replacement of LT APDRP/0 M/s Fabricator 10Kms. 87.92


Conductors by ABC. 3-04/48 (India)Varanasi
8 GIS mapping, indexing APDRP/0 M/s KLG Systel 1job 409.63
billing etc. 3-04/37 Gurgaon

9 Civil wing 7 Nos.New 224.00


construction of control UPPPCL. S/Ss.
room building and allied
Civil Works including cost of
land for new 33/11 KV s/ss.

10 R & M of building old Civil wing 10Nos. 36.00


33/11KV S/s. UPPPCL.
11 lnstallation of single Phase M/s Elymer 60850 486.90
Electronic meters
12 LT reconductoring Local Firms 54Ckt Km 102.00+30

13 TVMs. EAV- M/S genus 416


07/05-06 Electricals Ltd.
Jaipur
14 Electronic Meter Testing -do- -do- 2
Bench
15 Constructionl of 33KV lines -do- -do- 30cktkm
Weasel/ Rabbit 1184.03

16 New 11/0 4 Kv s/ss 400 -do- -do- 80+105=185


+225006 KVA
17 New LT line -do- -do- 30cktkm
18 Solid Earthing -do- -do- 300 nos.
19 Increasing capacity of DTS -do- -do- 45+20 353.45
from 45 x(400-630 KVA)+20
x (250-40KVA) with solid
earthing of 800 N0s.
Transformer
20 Reconductoring 33 Kv lines -do- -do- 32 Ckt Km. 58.82

21 Reconductoring 311Kv lines -do- -do- 40 Ckt Km 86.40


22 L.T line Reconductoring -do- -do- 190 Ckt Km 446.20

23 Replacement of -do- -do- 300 30.05+25.00


DamagedSTP
24 Constructionl of new 33KV -do- -do- 17 Ckt km 222.73
linesO/H 15 Kms.U/G 2
Kms.

25 Conversion of 33 KV lines -do- -do- 6Ckt Km 89.75


from Dog to Panther from O/H+1Ckt
Manduadih to Bhadani S/S. Km U/G
26 33 KV U/GH cable 3x300 -do- -do- 3.5 Ckt Km 75.03
SQ MM XLPE from Konio
to M achhodary
27 Renobatin of old 33 /11 Kv -do- -do- 10 9.00
Switchyard
28 36 N0s. Outsourced -do- -do- 36 162.00
Computerised bill collection
centres
29 HVDS 306.01
30 Jyoti Breaker for 12Nos 80.00
Kashividyapeeth& Beniya
33/11 KV S/S
Total 8385.25
Sacntioned under the 8478.00
Scheme
Balance 93.00
P works of VARANASI TOWN ( 30/04/2006)
Physical progress Expenditure outstanding Present Status
made. incured.(Rs. In liability at the
cumulative Duringlacs)
cumulati end of the
up to the the ve up to month (Rs. In
month. month. the lacs)
8 9 month.
10 11 12
1HT+1LT 2.46 Material received and 100% payment made.

40.78+0 do
.78
3.31 Material received and 90% payment made.

560.17 The firm has supplied 70 Nos 400 KVA transformers out of
+25.77+ which 70 Nos have since allredy been installed at site.33 No
7.70=59 250 KVA Transformer has also been installed.Out of 113 DTs
3.64 boring for earthing on 113Nos Transformer has since been
completed earthing of 70Nos 400 KVA and 32 Nos,250KVA
+2.78
Transformer has since been completed. The firm has
supplied TVm Cts and L.T. XLPE cable for 1088 Dts 1088
NO. Metering cubicals has since been received sofar and
balance are still awaited. The work of installation 1085 Nos of
TVM on DTs has since been completed.so far balance is
under progress.
1078.75 The work of construction of 33Kv lines on Panther conductor
+138.85 from 132 KV Cantt. S/S to Kashi
+312.78 Vidyaapeeth all 90 poles has already been errected,
+85.00+ stringing work complete. 75% cable work complete,Railway
permission awaited and in 33 KV. Sarnath- Konia line out of
29.67+2
120 poles, all have already been errected. Fitting and stay
18.35 wire 100% complete +stringing complete.
=1863.4 Out of 2.9 Km cable laying 1.8 Km work complete. PWD &
0 Railway permission awated expected
+146.29 to be cleared by 31.5.06 for balance cable work. All 105
poles of 11 KV Dafi-Bhagwanpur line has
since been errected, stringing complete. cable laying
complete conected to S/S. energised
on 30/09/05 Construction of 33KV Sahupuri- Ram Nagar line
all 189 poles errected, strigning complete. Charged on 23-2-
06 Lenghth of line 7.5 Km, 11 KV Lohata-Kurauta line all 31
poles erected lenght 2 Kms-fiting +stay rod & stringing
complete. For Sigra S/S. 33 KV line on Dog complete. DPH-
Lohata 33 Kv line - 1.5 Kms- all 21 Poles erected. 604 Mtr. cabling
work complete, stringing complete. M/s I.L., Lucknow have supplied
11 KV XLPE cable, 33 KV CTs & PTs & Isolators etc.
Supply of 7 Nos. 33/11 Kv. 5 MVA T/F has been received.
33 KV VCBs supply complete and 11 KV VCBs are
received. The work of laying of earth mats at new 33/11 KV.
S/Ss at Ram Nagar,Lohta and Ordaly Bazar & Sigra has
already been completed. 33/11 KV S/S Ramnagar & Ardaly
Bazar energised on 23-2-06 & Sigra & Lohta have been
energisedon 27-2-06 & 5-3-06. respectively The payment
of Rs. 69.90 Lacs has been made to EE (Transmission),
Varanasi towards Bay charges for New 33 KV lines.

611.31 The firm has so far supplied 33 KV. C.Ts. And P.Ts. And Fire
Fighting Equipments against this contract. 1 Nos. 10 MVA
Transformer Installed at Bhadaini & energised on 7.9.05 work
of installation of C.Ts. LAS etc. completed. Installation of 8
MVA T/F at Shankuldhara completed on 16/11/05.
Installation of 10 MVA T/F in place of 8 MVA
completed on 28/12/05 at PannaLal Park. 33/11 kV s/s.
Machhodari 8 MVA T/F installed in place of 5 MVA on 31-1-06
At Pandaypur installation of 10 MVA T/F in place of 8 MVA
completed and energised on 12-4-06.

69.78+3 The firm has already supplied ABC cables and 70 sqmm.
.43+4.6 Dropper cables & Junction boxes in our store. The work of
9 erection of 100 km ABC completed.
+7.96
32.97 GIS mapping, Sequencing Linking work has since been
+4.14 comleted. Survey work of consumers has also been
+4.895 completed. The work for billing of consumers of UEDD-III,
Machhodari has been started from 8/12/05. Work of UEDD-IV
Chetmani has start from 18-1-06.
23.04+4 The construction of control Room buildings at Ram Nagar
.77=27. and Ordaly Bazar & Lohata and Sigra are 100% complete.
81+4.50 The land for Alaipur is expected to be available in 5/06.
+8.39
=40.70

Work under progress Tender of remaining job under


finalisation.
76.00 76.00 12500 Meters already received, balance expected shortly.
Work of installation under progress.
4.80+7 4.80+7. Reconductoring Work about 40 Km complete.
.89 89+104.
97+14.0
0
+8.00+1
0.19
=149.85
+13.42+
1.17

_ Agreement executed work of erection to be started shortly.

_ -do-

135.00 135 _ Agreement executed


+402.83
+173.69
_ _ Agreement executed

_ Agreement executed
Agreement executed work to be started shortly.
_ _ Agreement executed.work to be started shortly
GTP of T/F approved Inspection call given.

Agreement executed. Line chart prepared, BOQ finalised.


GTP of conductor poles and insulator approved.

_ _ Agreement executed.GTP of 11 KV insulators. & Poles


approved.
_ _ Agreement executed.GTP of Conductor & Poles approved.

_ 16.12 _ To EE (Store) GTP of Poles approved

14.00 Agreement executed. Line chart prepared, BOQ finalised.


GTP of pols,conductor poles and insulator approved. Raja Ka
Talab- DPH Line Construction started on 27-2-06

_ Agreement executed. Line chart prepared, BOQ finalised.


GTP of Pols conductor poles and insulator approved

_ _ Agreement executed. Line chart prepared, BOQ finalised.


GTP of 33 KV cable approved .

_ _ Agreement executed work of erection to be started shortly.

_ _ Tendering under process. At G.M. (MM) level.

_ _ Tendering under process.


_ _ Tendering under process.

4737.00