PROJECT: DOUBLE STOREY HOUSE

ELEMENT PILE CAP

PILE CAP

Excavation Excavation
(m3) (m3) Concrete Formwork 50mm thk lean
LEVEL
(m3) (m2) concrete (m2)
exc 1.5m bt not
not exc 1.5m
exc 3m

CONNER 4.57 0.81 2.18 15.48 3.05

INTERMEDIATE 3.81 0.73 1.88 12.78 2.54

END 4.57 0.81 2.18 15.48 3.05

Total 12.96 6.24 43.74 8.64


Rebar (kg) Total
poundage
(kg/m3)
T12 T16 R10

64.18 277.62 25.05 366.85 168.28

18.34 277.62 19.99 315.95 168.06

64.18 277.62 25.05 366.85 168.28

146.71 832.85 70.09 1,049.65 168.21


PROJECT: DOUBLE STOREY HOUSE
SUBJECT: COLUMN - CONCRETE, FORMWORK, REBAR
concrete cover: 0.050 m
* remarks:- 50mm concrete cover - tension lap: D

Excavation Excavation Lean REINFORCEMENT


Conc
ITEM REFERENCE LEVEL NO HEIGHT DIMENSION exc 1.5 but not FWK concrete ANNOTATION SIZE NO LENGTH T10 T12 T14 T16
not exce 1.5m
WDTH LGTH Grade 25 exc 3 OF SPACIN OF OF X1 X2 X3
m m m m3 m3 m3 m2 m2 BARS BARS BARS(M)
50mm thk
DO NOT USE THIS FORMULAE CONTROL ROW

1 P1 G/L B1/1 1 1 0.750 0.600 0.600 0.27 0.540 0.108 1.80 0.36 TOP T16 8 1.65 1 1 1 13.20
BOTTOM T16 8 1.73 1 1 1 13.84
LK R10 2 2.24 1 1 1

2 P1 G/L B-D/2A 1 4 0.750 0.600 0.600 1.08 2.160 0.432 7.20 1.44 TOP T16 8 1.65 1 4 1 52.80
BOTTOM T16 8 1.73 1 4 1 55.36
LK R10 2 2.24 1 4 1

3 P1 G/L A-C/3 1 3 0.750 0.600 0.600 0.41 0.810 0.162 2.70 0.54 TOP T16 8 1.65 0.5 3 1 19.80
BOTTOM T16 8 1.73 0.5 3 1 20.76
LK R10 2 2.24 0.5 3 1

4 P1A G/L A-D/1 1 3 0.600 0.450 0.450 0.36 0.911 0.091 3.24 0.61 TOP T12 8 1.25 1 3 1 30.00
BOTTOM T12 8 1.33 1 3 1 31.92
LK R10 2 1.64 1 3 1

5 P1A G/L D/3 1 1 0.600 0.450 0.450 0.06 0.152 0.015 0.54 0.10 TOP T12 8 1.25 0.5 1 1 5.00
BOTTOM T12 8 1.33 0.5 1 1 5.32
LK R10 2 1.64 0.5 1 1

12 TOTAL 2.18 4.57 0.81 15.48 3.05 TOTAL LENGTH (M) - 72.24 - 175.76
TOTAL WEIGHT (KG) - 64.18 - 277.62

factor: 0.617 0.888 1.209 1.580


poundage 168.28 kg/m3
LINKS
T20 T25 T28 R06 R08 R10 R12

13.20 13.20 -
13.84 13.84 -
4.48 4.48 4.48 -
-
52.80 52.80 -
55.36 55.36 -
17.92 17.92 17.92 -
-
19.80 19.80 -
20.76 20.76 -
6.72 6.72 6.72 -
-
30.00 30.00 -
31.92 31.92 -
9.84 9.84 9.84 -
-
5.00 5.00 -
5.32 5.32 -
1.64 1.64 1.64 -
288.60 288.60 -
- - - - - 40.60 - 288.60
- - - - - 25.05 - 366.85

2.468 3.856 4.837 0.222 0.395 0.617 0.888


PROJECT: DOUBLE STOREY HOUSE
SUBJECT: COLUMN - CONCRETE, FORMWORK, REBAR
concrete cover: 0.050 m
* remarks:- 50mm concrete cover - tension lap: D

Excavation Excavation Lean REINFORCEMENT


Conc
ITEM REFERENCE LEVEL NO HEIGHT DIMENSION not exce exc 1.5 but FWK concrete ANNOTATION SIZE NO LENGTH T10 T12 T14 T16
WDTH LGTH Grade 25 1.5m not exc 3 OF SPACIN OF OF X1 X2 X3
m m m m3 m3 m3 m2 m2 BARS BARS BARS(M)
50mm thk
DO NOT USE THIS FORMULAE CONTROL ROW

1 P1 G/L B-D/1 1 4 0.750 0.600 0.600 0.54 1.080 0.216 3.60 0.72 TOP T16 8 1.65 0.5 4 1 26.40
BOTTOM T16 8 1.73 0.5 4 1 27.68
LK R10 2 2.24 0.5 4 1

2 P1 G/L B-D/2A 1 3 0.750 0.600 0.600 0.81 1.620 0.324 5.40 1.08 TOP T16 8 1.65 1 3 1 39.60
BOTTOM T16 8 1.73 1 3 1 41.52
LK R10 2 2.24 1 3 1

3 P1 G/L A-C/3 1 3 0.750 0.600 0.600 0.41 0.810 0.162 2.70 0.54 TOP T16 8 1.65 0.5 3 1 19.80
BOTTOM T16 8 1.73 0.5 3 1 20.76
LK R10 2 2.24 0.5 3 1

5 P1A G/L D/3 1 1 0.600 0.450 0.450 0.06 0.152 0.015 0.54 0.10 TOP T12 8 1.25 0.5 1 1 5.00
BOTTOM T12 8 1.33 0.5 1 1 5.32
LK R10 2 1.64 0.5 1 1

5 P1A G/L A/1 1 1 0.600 0.450 0.450 0.06 0.152 0.015 0.54 0.10 TOP T12 8 1.25 0.5 1 1 5.00
BOTTOM T12 8 1.33 0.5 1 1 5.32
LK R10 2 1.64 0.5 1 1

12 TOTAL 1.88 3.81 0.73 12.78 2.54 TOTAL LENGTH (M) - 20.64 - 175.76
TOTAL WEIGHT (KG) - 18.34 - 277.62

factor: 0.617 0.888 1.209 1.580


poundage 168.06 kg/m3
LINKS
T20 T25 T28 R06 R08 R10 R12

26.40 26.40 -
27.68 27.68 -
8.96 8.96 8.96 -
- -
39.60 39.60 -
41.52 41.52 -
13.44 13.44 13.44 -
- -
19.80 19.80 -
20.76 20.76 -
6.72 6.72 6.72 -
- -
5.00 5.00 -
5.32 5.32 -
1.64 1.64 1.64 -
- -
5.00 5.00 -
5.32 5.32 -
1.64 1.64 1.64 -
228.80 228.80 -
- - - - - 32.40 - 228.80 -
- - - - - 19.99 - 315.95

2.468 3.856 4.837 0.222 0.395 0.617 0.888


PROJECT: DOUBLE STOREY HOUSE
SUBJECT: COLUMN - CONCRETE, FORMWORK, REBAR
concrete cover: 0.050 m
* remarks:- 50mm concrete cover - tension lap: D

Excavation Excavation Lean REINFORCEMENT


Conc
ITEM REFERENCE LEVEL NO HEIGHT DIMENSION not exce exc 1.5 but FWK concrete ANNOTATION SIZE NO LENGTH T10 T12 T14 T16
WDTH LGTH Grade 25 1.5m not exc 3 OF SPACIN OF OF X1 X2 X3
m m m m3 m3 m3 m2 m2 BARS BARS BARS(M)
50mm thk
DO NOT USE THIS FORMULAE CONTROL ROW

1 P1 G/L B1/1 1 1 0.750 0.600 0.600 0.27 0.540 0.108 1.80 0.36 TOP T16 8 1.65 1 1 1 13.20
BOTTOM T16 8 1.73 1 1 1 13.84
LK R10 2 2.24 1 1 1

2 P1 G/L B-D/2A 1 4 0.750 0.600 0.600 1.08 2.160 0.432 7.20 1.44 TOP T16 8 1.65 1 4 1 52.80
BOTTOM T16 8 1.73 1 4 1 55.36
LK R10 2 2.24 1 4 1

3 P1 G/L A-C/3 1 3 0.750 0.600 0.600 0.41 0.810 0.162 2.70 0.54 TOP T16 8 1.65 0.5 3 1 19.80
BOTTOM T16 8 1.73 0.5 3 1 20.76
LK R10 2 2.24 0.5 3 1

4 P1A G/L A-D/1 1 3 0.600 0.450 0.450 0.36 0.911 0.091 3.24 0.61 TOP T12 8 1.25 1 3 1 30.00
BOTTOM T12 8 1.33 1 3 1 31.92
LK R10 2 1.64 1 3 1

5 P1A G/L D/3 1 1 0.600 0.450 0.450 0.06 0.152 0.015 0.54 0.10 TOP T12 8 1.25 0.5 1 1 5.00
BOTTOM T12 8 1.33 0.5 1 1 5.32
LK R10 2 1.64 0.5 1 1

12 TOTAL 2.18 4.57 0.81 15.48 3.05 TOTAL LENGTH (M) - 72.24 - 175.76
TOTAL WEIGHT (KG) - 64.18 - 277.62

factor: 0.617 0.888 1.209 1.580


poundage 168.28 kg/m3
LINKS
T20 T25 T28 R06 R08 R10 R12

13.20 13.20 -
13.84 13.84 -
4.48 4.48 4.48 -
-
52.80 52.80 -
55.36 55.36 -
17.92 17.92 17.92 -
-
19.80 19.80 -
20.76 20.76 -
6.72 6.72 6.72 -
-
30.00 30.00 -
31.92 31.92 -
9.84 9.84 9.84 -
-
5.00 5.00 -
5.32 5.32 -
1.64 1.64 1.64 -
288.60 288.60 -
- - - - - 40.60 - 288.60 -
- - - - - 25.05 - 366.85

2.468 3.856 4.837 0.222 0.395 0.617 0.888