Professional Documents
Culture Documents
AC UPS Sizing
From Open Electrical
Contents
1 Introduction
1.1 Why do the calculation?
1.2 When to do the calculation?
2 Calculation Methodology
2.1 Step 1: Collect the AC UPS Loads
2.2 Step 2: Load Profile, Design Load and Design Energy
2.3 Step 3: Battery Sizing
2.3.1 Nominal Battery (or DC Link) Voltage
2.3.2 Number of Cells in Series
2.4 Step 4: UPS Sizing
2.4.1 Overall UPS Sizing
2.4.2 Rectifier / Charger Sizing
2.4.3 Inverter Sizing
2.4.4 Static Switch Sizing
3 Worked Example
3.1 Step 1 and 2: Collect the AC UPS Loads and Construct Load Profile
3.2 Step 3: Battery Sizing
3.3 Step 4: UPS Sizing
3.3.1 Overall Sizing
3.3.2 Rectifier Sizing
3.3.3 Inverter and Static Switch Sizing
4 Computer Software
5 What next?
Introduction
This calculation deals with the sizing of an AC uninterruptible power supply (UPS) system (i.e. rectifier, battery
bank and inverter). In this calculation, it is assumed that the AC UPS is a double conversion type with a basic
system topology as shown in Figure 1.
An external maintenance bypass switch and galvanic isolation transformers are other common additions to the
basic topology, but these have been omitted from the system as they are irrelevant for the sizing calculation.
An AC UPS system is used to support critical / sensitive AC loads. It is typically a battery-backed system which
will continue to operate for a specified amount of time (called the autonomy) after a main power supply
interruption. AC UPS systems are also used as stable power supplies that provide a reasonably constant voltage
and frequency output, independent of voltage input. This is particularly useful for sensitive electrical equipment on
main power supplies that are prone to voltage / frequency fluctuations or instability.
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 1/6
2/8/2018 AC UPS Sizing - Open Electrical
Calculation Methodology
The calculation procedure has four main steps:
The first step is to determine the type and quantity of loads that the AC UPS system will be expected to support.
For industrial facilities, this will typically be critical instrumentation and control loads such as the DCS and ESD
processor and marshalling hardware, critical workstations and HMI's, telecommunications equipment and sensitive
electronics. The necessary load data should be available from the instrumentation and control engineers.
For commercial facilities, UPS loads will mainly be server, data / network and telecommunications hardware.
Refer to the Load Profile Calculation for details on how to construct a load profile, calculate the design load (Sd )
and design energy (Ed ). The "Autonomy method" for constructing load profiles is typically used for AC UPS
systems.
The autonomy time is often specified by the Client (i.e. in their standards). Alternatively, IEEE 446, "IEEE
Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications"
has some guidance (particularly Table 3-2) for autonomy times. Sometimes a single autonomy time is used for the
entire AC UPS load, which obviously makes the construction of the load profile easier to compute.
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 2/6
2/8/2018 AC UPS Sizing - Open Electrical
Refer to the Battery Sizing Calculation for details on how to size the battery for the AC UPS system. The following
sections provide additional information specific to battery sizing for AC UPS applications.
The nominal battery / DC link voltage is often selected by the AC UPS manufacturer. However, if required to be
selected, the following factors need to be considered:
DC output voltage range of the rectifier – the rectifier must be able to output the specified DC link
voltage
DC input voltage range of the inverter – the DC link voltage must be within the input voltage
tolerances of the inverter. Note that the battery end of discharge voltage should be within these
tolerances.
Number of battery cells required in series – this will affect the overall dimensions and size of the
battery rack. If physical space is a constraint, then less batteries in series would be preferable.
Total DC link current (at full load) – this will affect the sizing of the DC cables and inter-cell battery
links. Obviously the smaller the better.
In general, the DC link voltage is usually selected to be close to the nominal output voltage.
The number of battery cells required to be connected in series must be between the two following limits:
Vdc (1 + Vi,max )
(1) Nmax =
Vf
Vdc (1 − Vi,min )
(2) Nmin =
Veod
The limits are based on the input voltage tolerance of the inverter. As a maximum, the battery at float voltage (or
boost if applicable) needs to be within the maximum input voltage range of the inverter. Likewise as a minimum,
the battery at its end of discharge voltage must be within the minimum input voltage range of the inverter.
Select the number of cells in between these two limits (more or less arbitrary, though somewhere in the middle of
the min/max values would be appropriate).
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 3/6
2/8/2018 AC UPS Sizing - Open Electrical
Most of the time, all you need to provide is the overall UPS kVA rating and the UPS vendor will do the rest. Given
the design load (Ed in VA or kVA) calculated in Step 2, select an overall UPS rating that exceeds the design load.
Vendors typically have standard UPS ratings, so it is possible to simply select the first standard rating that exceeds
the design load. For example, if the design load 12kVA, then the next size unit (e.g. 15kVA UPS) would be
selected.
The rectifier / charger should be sized to supply the inverter at full load and also charge the batteries (at the
maximum charge current). The design DC load current can be calculated by:
S
IL,dc =
Vdc
C kl
Ic =
tc
Idc = IL,dc + Ic
Select the next standard rectifier / charger rating that exceeds the total minimum DC current above.
Inverter Sizing
The inverter must be rated to continuously supply the UPS loads. Therefore, the inverter can be sized using the
design AC load current (based on the selected UPS kVA rating).
S
IL =
–
√3Vo
S
IL =
Vo
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 4/6
2/8/2018 AC UPS Sizing - Open Electrical
Select the next standard inverter rating that exceeds the design AC load current.
Like the inverter, the static switch must be rated to continuously supply the UPS loads. Therefore, the static switch
can be sized using the design AC load current (as above for the inverter sizing).
Worked Example
Step 1 and 2: Collect the AC UPS Loads and Construct Load Profile
Overall Sizing
Given the design load of 768 VA, then a 1 kVA UPS would be appropriate.
Rectifier Sizing
Given a nominal dc link voltage of 120Vdc, the design DC load current is:
S
IL,dc =
Vdc
1, 000
= = 8.33 A
120
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 5/6
2/8/2018 AC UPS Sizing - Open Electrical
Suppose the minimum battery recharge time is 2 hours and a recharge efficiency factor of 1.1 is used. The
maximum battery charging current is:
C kl
Ic =
tc
50 × 1.1
= = 27.5 A
2
Idc = IL,dc + Ic
Suppose the nominal output voltage is 240Vac. The design AC load current is:
S
IL =
–
√3Vo
1, 000
=
–
= 2.406 A
√3 × 240
Computer Software
Preliminary sizing is normally done manually. Notwithstanding this, many AC UPS manufacturers provide sizing
tools as part of their service package (for example, see the APC online UPS selector tool (http://www.apc.com/tool
s/ups_selector/index.cfm?)).
What next?
Using the results of the UPS sizing calculation, the approximate dimensions of the batteries and UPS cabinet can
be estimated based on typical vendor information. This will assist in developing the equipment / room layouts.
Preliminary budget pricing can also be estimated based on the calculation results.
Category: Calculations
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 6/6