You are on page 1of 67

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 50.0 T/Jam
4. Alat Baru : a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 1,917,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 1,500.0 Jam
c. Harga Alat (*) B' 1,917,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 191,700,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.19925 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 229,179.72 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 2,556.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 231,735.72 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H1 104,812.50 Rupiah


Bahan Bakar Pemanasan Material = 12 x 0.7Cp x Ms H2 2,347,800.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 29,250.00 Rupiah

3. Perawatan dan = (12,5 % - 17,5 %) x B' K 159,750.00 Rupiah


perbaikan W'
4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah
5. Pembantu Operator = ( 3 Orang / Jam ) x U2 M 17,250.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 2,667,076.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 2,898,812.51 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN


A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER
2. Tenaga Pw 47.0 HP
3. Kapasitas Cp 40.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 835,450,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 835,450,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 83,545,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.26424 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 99,340.53 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 835.45 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 100,175.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 32,841.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 9,165.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 52,215.63 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 108,186.17 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 208,362.14 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER
2. Tenaga Pw 15.0 HP
3. Kapasitas Cp 800.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 120,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 120,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 12,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 16,109.04 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 120.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 16,229.04 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 10,481.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 2,925.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 7,500.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 34,870.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 51,099.58 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER 100-150 HP
2. Tenaga Pw 140.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 762,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 762,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 76,200,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 102,292.40 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 762.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 103,054.40 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 97,825.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 27,300.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 47,625.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 186,714.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 289,768.69 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR 4000-6500 L\M
2. Tenaga Pw 50.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 91,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 91,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 9,100,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 12,216.02 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 91.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 12,307.02 Rupiah


C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 34,937.50 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 9,750.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 5,687.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 64,339.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 76,646.31 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3
2. Tenaga Pw 15.0 HP
3. Kapasitas Cp 500.0 Liter
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 102,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 102,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 10,200,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.35027 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 16,077.18 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 102.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 16,179.18 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 10,481.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 2,925.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 6,375.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 33,745.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 49,924.72 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan CRANE 10-15 TON
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 15.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 423,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 423,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 42,300,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 56,784.37 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 423.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 57,207.37 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 104,812.50 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 29,250.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 26,437.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 174,464.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 231,671.66 Rupiah


E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3-4 M3
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 6.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 204,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 204,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 20,400,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 27,385.37 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 204.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 27,589.37 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 69,875.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 19,500.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 12,750.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 116,089.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 143,678.66 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 273,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 273,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 27,300,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 36,648.07 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 273.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 36,921.07 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 87,343.75 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 24,375.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 17,062.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 142,745.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 179,666.61 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT


No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP
2. Tenaga Pw 80.0 HP
3. Kapasitas Cp 0.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 600,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 600,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 60,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 80,545.20 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 600.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 81,145.20 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 55,900.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 15,600.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 37,500.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 122,964.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 204,109.49 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan FLAT BED TRUCK 3-4 M3
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4.0 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 210,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 210,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 21,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 28,190.82 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 210.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 28,400.82 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 69,875.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 19,500.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 13,125.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 116,464.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 144,865.11 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan GENERATOR SET
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 125.0 KVA
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 255,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 255,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 25,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 34,231.71 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 255.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 34,486.71 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 122,281.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 34,125.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 15,937.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 186,308.04 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 220,794.75 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 675,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 675,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 67,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 90,613.35 Rupiah
W'
b. Asuransi, dll = 0.002 x B' F 675.00 Rupiah
W'

Biaya Pasti per Jam = (E+F) G 91,288.35 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 87,343.75 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 24,375.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 42,187.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 167,870.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 259,158.89 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan TRACK LOADER 75-100 HP
2. Tenaga Pw 90.0 HP
3. Kapasitas Cp 1.6 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 567,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 567,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 56,700,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 76,115.21 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 567.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 76,682.21 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 62,887.50 Rupiah


2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 17,550.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 35,437.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 129,839.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 206,521.50 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3
2. Tenaga Pw 105.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 564,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 564,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 56,400,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 75,712.49 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 564.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 76,276.49 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 73,368.75 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 20,475.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 35,250.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 143,058.04 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 219,334.53 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan THREE WHEEL ROLLER 6-8 T
2. Tenaga Pw 55.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 205,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 205,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 20,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 27,519.61 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 205.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 27,724.61 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 38,431.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 10,725.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 12,812.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 75,933.04 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 103,657.65 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T.
2. Tenaga Pw 50.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 396,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 396,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 39,600,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 53,159.83 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 396.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 53,555.83 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 34,937.50 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 9,750.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 24,750.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 83,401.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 136,957.62 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER 8-10 T.
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,800.0 Jam
c. Harga Alat B 441,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 1,800.0 Jam
c. Harga Alat (*) B' 441,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 44,100,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 65,778.58 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 490.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 66,268.58 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 41,925.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 11,700.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 30,625.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 98,214.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 164,482.87 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN


A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T.
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp 7.0 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 450,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 450,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 45,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.35027 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 70,928.73 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 450.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 71,378.73 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 52,406.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 14,625.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 28,125.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 109,120.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 180,499.27 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE VIBRATOR
2. Tenaga Pw 10.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 7,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 1,000.0 Jam
c. Harga Alat (*) B' 7,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 700,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.35027 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 2,206.67 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 14.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 2,220.67 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 6,987.50 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 1,950.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 875.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 23,776.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 25,997.46 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan STONE CRUSHER
2. Tenaga Pw 220.0 HP
3. Kapasitas Cp 50.0 T/Jam
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 983,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 983,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 98,300,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 131,959.88 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 983.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 132,942.88 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 153,725.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 42,900.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 61,437.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 2 Orang / Jam ) x U2 M 11,500.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 277,776.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 410,719.67 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 7,500,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 7,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 750,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.61512 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 2,076.02 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 7.50 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 2,083.52 Rupiah


C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 4,192.50 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 1,170.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 468.75 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 19,795.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 21,879.06 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L.
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 99,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 99,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 9,900,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 13,289.96 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 99.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 13,388.96 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 69,875.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 19,500.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 6,187.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 109,526.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 122,915.75 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan PEDESTRIAN ROLLER
2. Tenaga Pw 11.0 HP
3. Kapasitas Cp 0.980 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 130,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 130,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 13,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.35027 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 20,490.52 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 130.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 20,620.52 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 7,686.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 2,145.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 8,125.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 31,920.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 52,541.06 Rupiah


E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan TAMPER
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 0.170 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 7,500,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 1,000.0 Jam
c. Harga Alat (*) B' 7,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 750,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.35027 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 2,364.29 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 15.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 2,379.29 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 3,493.75 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 975.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 937.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 19,370.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 21,749.83 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan JACK HAMMER
2. Tenaga Pw 3.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 10,500,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 1,000.0 Jam
c. Harga Alat (*) B' 10,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 1,050,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.35027 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 3,310.01 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 21.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 3,331.01 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 2,096.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 585.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 1,312.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 17,958.04 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 21,289.05 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT


No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan FULVI MIXER
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 209,300,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 209,300,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 20,930,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 28,096.85 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 209.30 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 28,306.15 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 52,406.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 14,625.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 13,081.25 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 94,076.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 122,382.94 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE PUMP
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 8.00 M3
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 315,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 315,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 31,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.26424 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 37,455.58 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 315.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 37,770.58 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 69,875.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 19,500.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 19,687.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 123,026.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 160,797.37 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan TRAILER 20 TON
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 10.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 243,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 243,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 24,300,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.26424 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 28,894.31 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 243.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 29,137.31 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 122,281.25 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 34,125.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 15,187.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 185,558.04 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 214,695.35 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan PILE DRIVER + HAMMER
2. Tenaga Pw 25.0 HP
3. Kapasitas Cp 2.50 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 129,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 129,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 12,900,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 17,317.22 Rupiah
W'
b. Asuransi, dll = 0.002 x B' F 129.00 Rupiah
W'

Biaya Pasti per Jam = (E+F) G 17,446.22 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 17,468.75 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 4,875.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 8,062.50 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 44,370.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 61,816.76 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan CRANE ON TRACK 35 TON
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 35.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 696,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 696,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 69,600,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.26424 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 82,759.00 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 696.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 83,455.00 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 87,343.75 Rupiah


2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 24,375.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 43,500.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 169,183.04 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 252,638.04 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan WELDING SET
2. Tenaga Pw 40.0 HP
3. Kapasitas Cp 250.00 Amp
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 24,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 24,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 2,400,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.29832 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 3,221.81 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 24.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 3,245.81 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 27,950.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 7,800.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 1,500.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 51,214.29 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 54,460.10 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan BORE PILE MACHINE
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 2,000.00 Meter
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 4,992,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam
c. Harga Alat (*) B' 4,992,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 499,200,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.26424 -


(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 593,581.79 Rupiah
W'

b. Asuransi, dll = 0.002 x B' F 4,992.00 Rupiah


W'

Biaya Pasti per Jam = (E+F) G 598,573.79 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 104,812.50 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 29,250.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 312,000.00 Rupiah


perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 8,214.29 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 5,750.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 460,026.79 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 1,058,600.58 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 8,214.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 5,750.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 5,590.00 Liter
6. Minyak Pelumas Mp 19,500.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
KET. TENAGA KAPASITAS HARGA
ALAT ALAT ALAT

E01
(HP) - (Tahun)
No. JENIS PERALATAN KODE
ALAT

Alat baru
Alat baru HP Cp B
Alat baru 1 2 2a 3 4 5

1. ASPHALT MIXING PLANT E01 150.0 50.0 T/Jam 1,917,000,000


2. ASPHALT FINISHER E02 47.0 40.0 Ton 835,450,000
3. ASPHALT SPRAYER E03 15.0 800.0 Liter 120,000,000
4. BULLDOZER 100-150 HP E04 140.0 - - 762,000,000
5. COMPRESSOR 4000-6500 L\M E05 50.0 - - 91,000,000
6. CONCRETE MIXER 0.3-0.6 M3 E06 15.0 500.0 Liter 102,000,000
7. CRANE 10-15 TON E07 150.0 15.0 Ton 423,000,000
8. DUMP TRUCK 3-4 M3 E08 100.0 6.0 Ton 204,000,000
9. DUMP TRUCK E09 125.0 8.0 Ton 273,000,000
10. EXCAVATOR 80-140 HP E10 80.0 0.5 M3 600,000,000
11. FLAT BED TRUCK 3-4 M3 E11 100.0 4.0 M3 210,000,000
12. GENERATOR SET E12 175.0 125.0 KVA 255,000,000
13. MOTOR GRADER >100 HP E13 125.0 - - 675,000,000
14. TRACK LOADER 75-100 HP E14 90.0 1.6 M3 567,000,000
15. WHEEL LOADER 1.0-1.6 M3 E15 105.0 1.5 M3 564,000,000
16. THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 205,000,000
17. TANDEM ROLLER 6-8 T. E17 50.0 8.0 Ton 396,000,000
Khusus AMP 18. TIRE ROLLER 8-10 T. E18 60.0 10.0 Ton 441,000,000
19. VIBRATORY ROLLER 5-8 T. E19 75.0 7.0 Ton 450,000,000
20. CONCRETE VIBRATOR E20 10.0 - - 7,000,000
21. STONE CRUSHER E21 220.0 50.0 T/Jam 983,000,000
22. WATER PUMP 70-100 mm E22 6.0 - - 7,500,000
23. WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 99,000,000
24. PEDESTRIAN ROLLER E24 11.0 1.0 Ton 130,000,000
25. TAMPER E25 5.0 0.2 Ton 7,500,000
26. JACK HAMMER E26 3.0 - - 10,500,000
27. FULVI MIXER E27 75.0 - - 209,300,000
28. CONCRETE PUMP E28 100.0 8.00 M3 315,000,000
29. TRAILER 20 TON E29 175.0 10.00 Ton 243,000,000
30 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 129,000,000
31. CRANE ON TRACK 35 TON E31 125.0 35.00 Ton 696,000,000
32. WELDING SET E32 40.0 250.00 Amp 24,000,000
33. BORE PILE MACHINE E33 150.0 2,000.0 Meter 4,992,000,000
34.
KETERANGAN : 1. Tingkat Suku Bunga
4,780.00 2. Upah Operator / Sopir / Mekanik
4,950.00 3. Upah Pembantu Operator/Sopir/Mekanik
21,500.00 4. Harga Bahan Bakar Bensin
5. Harga Bahan Bakar Solar
6. Minyak Pelumas
7. Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lem
8. Khusus AMP, biaya bahan bakar ditambah (untuk peman

KET.
E02

Alat baru
Alat baru
Alat baru

KET.

E03

Alat baru
Alat baru
Alat baru

KET.

E04

Alat baru
Alat baru
Alat baru
Pertamina

KET.

E05

Alat baru
Alat baru
Alat baru
KET.

E06

Alat baru
Alat baru
Alat baru
KET.

E07

Alat baru
Alat baru
Alat baru
KET.

E08

Alat baru
Alat baru
Alat baru

SPBU
SPBU
KET.

E09

Alat baru
Alat baru
Alat baru

SPBU
SPBU
KET.

E10

Alat baru
Alat baru
Alat baru

KET.

E11
Alat baru
Alat baru
Alat baru

KET.

E12

Alat baru
Alat baru
Alat baru
KET.

E13

Alat baru
Alat baru
Alat baru
KET.

E14

Alat baru
Alat baru
Alat baru
KET.

E15

Alat baru
Alat baru
Alat baru
KET.

E16

Alat baru
Alat baru
Alat baru
KET.

E17

Alat baru
Alat baru
Alat baru
KET.

E18

Alat baru
Alat baru
Alat baru

KET.
E19

Alat baru
Alat baru
Alat baru

KET.

E20

Alat baru
Alat baru
Alat baru

KET.

E21

Alat baru
Alat baru
Alat baru
KET.

E22

Alat baru
Alat baru
Alat baru
KET.

E23

Alat baru
Alat baru
Alat baru
KET.

E24

Alat baru
Alat baru
Alat baru
KET.

E25

Alat baru
Alat baru
Alat baru
KET.

E26

Alat baru
Alat baru
Alat baru
KET.

E27

Alat baru
Alat baru
Alat baru

KET.

E28
Alat baru
Alat baru
Alat baru

KET.

E29

Alat baru
Alat baru
Alat baru
KET.

E30

Alat baru
Alat baru
Alat baru
KET.

E31

Alat baru
Alat baru
Alat baru
KET.

E32

Alat baru
Alat baru
Alat baru
KET.

E33

Alat baru
Alat baru
Alat baru
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA

ALAT YANG DIPAKAI NILAI FAKTOR BIAYA PASTI PER JAM


JAM SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PEL
UMUR KERJA HARGA ALAT BALIAN PENGEM- DAN BIAYA BAHAN
ALAT 1 TAHUN ALAT MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR
MODAL
(Tahun) (Jam) (Rp.) (Rp.) - (Rp.) (Rp.) (Rp.) Lt/HP/Jam

i(1+i)^A (B - C) x D 0.002 x B 0.125


(10% X B) ----------- ----------- ----------- (e1 + e2) s/d
(1+i)^A-1 W W 0.175

A W B C D e1 e2 E f1
6 7 8 9 10 11 12 13 14

10.0 1,500.0 1,917,000,000 191,700,000 0.19925 229,179.72 2,556.00 231,735.72 0.1250


6.0 2,000.0 835,450,000 83,545,000 0.26424 99,340.53 835.45 100,175.98 0.1250
5.0 2,000.0 120,000,000 12,000,000 0.29832 16,109.04 120.00 16,229.04 0.1250
5.0 2,000.0 762,000,000 76,200,000 0.29832 102,292.40 762.00 103,054.40 0.1250
5.0 2,000.0 91,000,000 9,100,000 0.29832 12,216.02 91.00 12,307.02 0.1250
4.0 2,000.0 102,000,000 10,200,000 0.35027 16,077.18 102.00 16,179.18 0.1250
5.0 2,000.0 423,000,000 42,300,000 0.29832 56,784.37 423.00 57,207.37 0.1250
5.0 2,000.0 204,000,000 20,400,000 0.29832 27,385.37 204.00 27,589.37 0.1250
5.0 2,000.0 273,000,000 27,300,000 0.29832 36,648.07 273.00 36,921.07 0.1250
5.0 2,000.0 600,000,000 60,000,000 0.29832 80,545.20 600.00 81,145.20 0.1250
5.0 2,000.0 210,000,000 21,000,000 0.29832 28,190.82 210.00 28,400.82 0.1250
5.0 2,000.0 255,000,000 25,500,000 0.29832 34,231.71 255.00 34,486.71 0.1250
5.0 2,000.0 675,000,000 67,500,000 0.29832 90,613.35 675.00 91,288.35 0.1250
5.0 2,000.0 567,000,000 56,700,000 0.29832 76,115.21 567.00 76,682.21 0.1250
5.0 2,000.0 564,000,000 56,400,000 0.29832 75,712.49 564.00 76,276.49 0.1250
5.0 2,000.0 205,000,000 20,500,000 0.29832 27,519.61 205.00 27,724.61 0.1250
5.0 2,000.0 396,000,000 39,600,000 0.29832 53,159.83 396.00 53,555.83 0.1250
5.0 1,800.0 441,000,000 44,100,000 0.29832 65,778.58 490.00 66,268.58 0.1250
4.0 2,000.0 450,000,000 45,000,000 0.35027 70,928.73 450.00 71,378.73 0.1250
4.0 1,000.0 7,000,000 700,000 0.35027 2,206.67 14.00 2,220.67 0.1250
5.0 2,000.0 983,000,000 98,300,000 0.29832 131,959.88 983.00 132,942.88 0.1250
2.0 2,000.0 7,500,000 750,000 0.61512 2,076.02 7.50 2,083.52 0.1250
5.0 2,000.0 99,000,000 9,900,000 0.29832 13,289.96 99.00 13,388.96 0.1250
4.0 2,000.0 130,000,000 13,000,000 0.35027 20,490.52 130.00 20,620.52 0.1250
4.0 1,000.0 7,500,000 750,000 0.35027 2,364.29 15.00 2,379.29 0.1250
4.0 1,000.0 10,500,000 1,050,000 0.35027 3,310.01 21.00 3,331.01 0.1250
5.0 2,000.0 209,300,000 20,930,000 0.29832 28,096.85 209.30 28,306.15 0.1250
6.0 2,000.0 315,000,000 31,500,000 0.26424 37,455.58 315.00 37,770.58 0.1250
6.0 2,000.0 243,000,000 24,300,000 0.26424 28,894.31 243.00 29,137.31 0.1250
5.0 2,000.0 129,000,000 12,900,000 0.29832 17,317.22 129.00 17,446.22 0.1250
6.0 2,000.0 696,000,000 69,600,000 0.26424 82,759.00 696.00 83,455.00 0.1250
5.0 2,000.0 24,000,000 2,400,000 0.29832 3,221.81 24.00 3,245.81 0.1250
6.0 2,000.0 4,992,000,000 499,200,000 0.26424 593,581.79 4,992.00 598,573.79 0.1250

= 15.00 % per-tahun
= 8,214 Rupiah per-orang/jam
= 5,750 Rupiah per-orang/jam
= 0 Rupiah per-liter
= 5,590 Rupiah per-liter
= 19,500 Rupiah per-liter
N) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
kar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom
M KERJA

BIAYA OPERASI PER JAM KERJA


BAHAN BAKAR & PELUMAS PERBAIKAN & PERAWATAN UPAH TOTAL
MINYAK OPERATOR PEMBANTU BIAYA
PELUMAS BIAYA KOEF. BIAYA / SOPIR OPERATOR OPERASI
/ SOPIR / JAM
Ltr/HP/Jam (Rp.) - (Rp.) (Rp.) (Rp.) (Rp.)
f1 x HP x 1 Orang 1 Orang
0.01 Harga BBM 0.125 (g1 x B') Per Per
s/d + s/d ----------- Jam Kerja Jam Kerja F+G+H+I
0.02 f2 x HP x 0.175 W = =
Harga Olie Rp8,214.3 Rp5,750.0
f2 F g1 G H I J
15 16 17 18 19 20 21

0.0100 2,481,862.50 0.1250 159,750.00 8,214.29 5,750.00 2,655,576.79


0.0100 42,006.25 0.1250 52,215.63 8,214.29 5,750.00 108,186.17
0.0100 13,406.25 0.1250 7,500.00 8,214.29 5,750.00 34,870.54
0.0100 125,125.00 0.1250 47,625.00 8,214.29 5,750.00 186,714.29
0.0100 44,687.50 0.1250 5,687.50 8,214.29 5,750.00 64,339.29
0.0100 13,406.25 0.1250 6,375.00 8,214.29 5,750.00 33,745.54
0.0100 134,062.50 0.1250 26,437.50 8,214.29 5,750.00 174,464.29
0.0100 89,375.00 0.1250 12,750.00 8,214.29 5,750.00 116,089.29
0.0100 111,718.75 0.1250 17,062.50 8,214.29 5,750.00 142,745.54
0.0100 71,500.00 0.1250 37,500.00 8,214.29 5,750.00 122,964.29
0.0100 89,375.00 0.1250 13,125.00 8,214.29 5,750.00 116,464.29
0.0100 156,406.25 0.1250 15,937.50 8,214.29 5,750.00 186,308.04
0.0100 111,718.75 0.1250 42,187.50 8,214.29 5,750.00 167,870.54
0.0100 80,437.50 0.1250 35,437.50 8,214.29 5,750.00 129,839.29
0.0100 93,843.75 0.1250 35,250.00 8,214.29 5,750.00 143,058.04
0.0100 49,156.25 0.1250 12,812.50 8,214.29 5,750.00 75,933.04
0.0100 44,687.50 0.1250 24,750.00 8,214.29 5,750.00 83,401.79
0.0100 53,625.00 0.1250 30,625.00 8,214.29 5,750.00 98,214.29
0.0100 67,031.25 0.1250 28,125.00 8,214.29 5,750.00 109,120.54
0.0100 8,937.50 0.1250 875.00 8,214.29 5,750.00 23,776.79
0.0100 196,625.00 0.1250 61,437.50 8,214.29 11,500.00 277,776.79
0.0100 5,362.50 0.1250 468.75 8,214.29 5,750.00 19,795.54
0.0100 89,375.00 0.1250 6,187.50 8,214.29 5,750.00 109,526.79
0.0100 9,831.25 0.1250 8,125.00 8,214.29 5,750.00 31,920.54
0.0100 4,468.75 0.1250 937.50 8,214.29 5,750.00 19,370.54
0.0100 2,681.25 0.1250 1,312.50 8,214.29 5,750.00 17,958.04
0.0100 67,031.25 0.1250 13,081.25 8,214.29 5,750.00 94,076.79
0.0100 89,375.00 0.1250 19,687.50 8,214.29 5,750.00 123,026.79
0.0100 156,406.25 0.1250 15,187.50 8,214.29 5,750.00 185,558.04
0.0100 22,343.75 0.1250 8,062.50 8,214.29 5,750.00 44,370.54
0.0100 111,718.75 0.1250 43,500.00 8,214.29 5,750.00 169,183.04
0.0100 35,750.00 0.1250 1,500.00 8,214.29 5,750.00 51,214.29
0.0100 134,062.50 0.1250 312,000.00 8,214.29 5,750.00 460,026.79

) x Harga BBM Solar , (kolom 16)


DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

TOTAL No. URAIAN KO HP KAP.


BIAYA DE
SEWA ALAT
PER
JAM KERJA 1. ASPHALT MIXING PLANT E01 150.0 50.0 T/Jam
(Rp.) KET. 2. ASPHALT FINISHER E02 47.0 40.0 Ton
3. ASPHALT SPRAYER E03 15.0 800.0 Liter
4. BULLDOZER 100-150 HP E04 140.0 - -
E+J 5. COMPRESSOR 4000-6500 L\M E05 50.0 - -
6. CONCRETE MIXER 0.3-0.6 M3 E06 15.0 500.0 Liter
7. CRANE 10-15 TON E07 150.0 15.0 Ton
K L 8. DUMP TRUCK 3-4 M3 E08 100.0 6.0 Ton
22 23 9. DUMP TRUCK E09 125.0 8.0 Ton
10. EXCAVATOR 80-140 HP E10 80.0 0.5 M3
2,887,312.51 Alat baru 11. FLAT BED TRUCK 3-4 M3 E11 100.0 4.0 M3
208,362.14 Alat baru 12. GENERATOR SET E12 175.0 125.0 KVA
51,099.58 Alat baru 13. MOTOR GRADER >100 HP E13 125.0 - -
289,768.69 Alat baru 14. TRACK LOADER 75-100 HP E14 90.0 1.6 M3
76,646.31 Alat baru 15. WHEEL LOADER 1.0-1.6 M3 E15 105.0 1.5 M3
49,924.72 Alat baru 16. THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton
231,671.66 Alat baru 17. TANDEM ROLLER 6-8 T. E17 50.0 8.0 Ton
143,678.66 Alat baru 18. TIRE ROLLER 8-10 T. E18 60.0 10.0 Ton
179,666.61 Alat baru 19. VIBRATORY ROLLER 5-8 T. E19 75.0 7.0 Ton
204,109.49 Alat baru 20. CONCRETE VIBRATOR E20 10.0 - -
144,865.11 Alat baru 21. STONE CRUSHER E21 220.0 50.0 T/Jam
220,794.75 Alat baru 22. WATER PUMP 70-100 mm E22 6.0 - -
259,158.89 Alat baru 23. WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter
206,521.50 Alat baru 24. PEDESTRIAN ROLLER E24 11.0 0.98 Ton
219,334.53 Alat baru 25. TAMPER E25 5.0 0.17 Ton
103,657.65 Alat baru 26. JACK HAMMER E26 3.0 - -
136,957.62 Alat baru 27. FULVI MIXER E27 75.0 - -
164,482.87 Alat baru 28. CONCRETE PUMP E28 100.0 8.00 M3
180,499.27 Alat baru 29. TRAILER 20 TON E29 175.0 10.00 Ton
25,997.46 Alat baru 30. PILE DRIVER + HAMMER E30 25.0 2.50 Ton
410,719.67 Alat baru 31. CRANE ON TRACK 35 TON E31 125.0 35.00 Ton
21,879.06 Alat baru 32. WELDING SET E32 40.0 250.00 Amp
122,915.75 Alat baru 33. BORE PILE MACHINE E33 150.0 200.0 Meter
52,541.06 Alat baru
21,749.83 Alat baru
21,289.05 Alat baru
122,382.94 Alat baru
160,797.37 Alat baru
214,695.35 Alat baru
61,816.76 Alat baru
252,638.04 Alat baru
54,460.10 Alat baru
1,058,600.58 Alat baru
LATAN PER JAM KERJA PERHITUNGAN ALAT UTAMA
STONE CRUSHER
BIAYA
HARGA SEWA KET.
ALAT ALAT/JAM No. URAIAN
(di luar PPN)

1,917,000,000 2,898,812.51 Alat baru I BERAT JENIS BAHAN


835,450,000 208,362.14 Alat baru
120,000,000 51,099.58 Alat baru 1. Agregat Base
762,000,000 289,768.69 Alat baru 2. ATB / ATBL / AC / HRS
91,000,000 76,646.31 Alat baru 3. SBST / DBST
102,000,000 49,924.72 Alat baru
423,000,000 231,671.66 Alat baru II TEBAL RATA-RATA HAMPARAN PADAT
204,000,000 143,678.66 Alat baru
273,000,000 179,666.61 Alat baru 1. Agregat Base
600,000,000 204,109.49 Alat baru 2. Asphalt Concrete (AC)
210,000,000 144,865.11 Alat baru 3. Hot Rolled Sheet (HRS)
255,000,000 220,794.75 Alat baru 4. SBST
675,000,000 259,158.89 Alat baru 5. DBST
567,000,000 206,521.50 Alat baru
564,000,000 219,334.53 Alat baru III VOLUME PEKERJAAN
205,000,000 103,657.65 Alat baru
396,000,000 136,957.62 Alat baru 1. Agregat Kelas A
441,000,000 164,482.87 Alat baru 2. Agregat Kelas B
450,000,000 180,499.27 Alat baru 3. ATB
7,000,000 25,997.46 Alat baru 4. ATBL
983,000,000 410,719.67 Alat baru 5. AC
7,500,000 21,879.06 Alat baru 6. HRS
99,000,000 122,915.75 Alat baru 7. SBST
130,000,000 52,541.06 Alat baru 8. DBST
7,500,000 21,749.83 Alat baru
10,500,000 21,289.05 Alat baru IV VOLUME PEKERJAAN ALAT
209,300,000 122,382.94 Alat baru
315,000,000 160,797.37 Alat baru 1. Agregat Kelas A = v1 x D1 x 80% x 1.05
243,000,000 214,695.35 Alat baru 2. Agregat Kelas B = v2 x D1 x 80% x 1.05
129,000,000 61,816.76 Alat baru 3. ATB = v3 x D2 x 1.05
696,000,000 252,638.04 Alat baru 4. ATBL = v4 x 1.05
24,000,000 54,460.10 Alat baru 5. AC = v5 x t2 x D2 x 1.05
4,992,000,000 1,058,600.58 Alat baru 6. HRS = v6 x t3 x D2 x 1.05
7. SBST = v7 x t4 x D3 x 1.05
8. DBST = v8 x t4 x D3 x 1.05

Total Volume Pekerjaan Alat = w1 + . . . + w8

V PERHITUNGAN KAPASITAS ALAT


1. Masa Mobilisasi / Demobilisasi
2. Waktu Produksi (Di luar masa Mobilisasi & Hari Libur)
3. Jumlah hari kerja efektif / bulan
4. Jumlah jam kerja efektif / hari
5. Faktor efisiensi alat

Kapasitas alat yang diperlukan = W


T x Te1 x Te2 x Fa

VI. ALAT YANG DIPAKAI


Kapasitas alat yang dipakai pada proyek ini

PERHITUNGAN ALAT UTAMA


ASPHALT MIXING PLANT

No. URAIAN
I BERAT JENIS BAHAN

1. Agregat Base
2. ATB / ATBL / AC / HRS
3. SBST / DBST

II TEBAL RATA-RATA HAMPARAN PADAT

1. Agregat Base
2. Asphalt Concrete (AC)
3. Hot Rolled Sheet (HRS)
4. SBST
5. DBST

III VOLUME PEKERJAAN

1. Agregat Kelas A
2. Agregat Kelas B
3. ATB
4. ATBL
5. AC
6. HRS
7. SBST
8. DBST

IV VOLUME PEKERJAAN ALAT

1. Agregat Kelas A = v1 x D1 x 80% x 1.05


2. Agregat Kelas B = v2 x D1 x 80% x 1.05
3. ATB = v3 x D2 x 1.05
4. ATBL = v4 x 1.05
5. AC = v5 x t2 x D2 x 1.05
6. HRS = v6 x t3 x D2 x 1.05
7. SBST = v7 x t4 x D3 x 1.05
8. DBST = v8 x t4 x D3 x 1.05

Total Volume Pekerjaan Alat = w1 + . . . + w8

V PERHITUNGAN KAPASITAS ALAT


1. Masa Mobilisasi / Demobilisasi
2. Waktu Produksi (Di luar masa Mobilisasi & Hari Libur)
3. Jumlah hari kerja efektif / bulan
4. Jumlah jam kerja efektif / hari
5. Faktor efisiensi alat

Kapasitas alat yang diperlukan = W


T x Te1 x Te2 x Fa

VI. ALAT YANG DIPAKAI


Kapasitas alat yang dipakai pada proyek ini
GAN ALAT UTAMA
NE CRUSHER

KODE KOEF. SATUAN KET.

D1 2.20 Ton/M3
D2 2.30 Ton/M3
D3 2.00 Ton/M3

t1 0.150 M
t2 0.040 M
t3 0.030 M
t4 0.020 M
t5 0.030 M

v1 M3
v2 M3
v3 M3
v4 Ton
v5 M2
v6 M2
v7 M2
v8 M2

w1 Ton
w2 Ton
w3 Ton
w4 Ton
w5 Ton
w6 Ton
w7 Ton
w8 Ton

W Ton

Tm 3.00 Bulan
T 2.50 Bulan
Te1 25.00 Hari/Bln
Te2 7.00 Jam/Hari
Fa 0.70 -

SC 0.00 Ton/Jam

SCa 50.00 Ton/Jam OK

GAN ALAT UTAMA


T MIXING PLANT

KODE KOEF. SATUAN KET.


D1 2.20 Ton/M3
D2 2.30 Ton/M3
D3 2.00 Ton/M3

t1 0.150 M
t2 0.040 M
t3 0.030 M
t4 0.020 M
t5 0.030 M

v1 - M3
v2 - M3
v3 0.00 M3
v4 0.00 Ton
v5 0.00 M2
v6 0.00 M2
v7 0.00 M2
v8 0.00 M2

w1 #VALUE! Ton
w2 #VALUE! Ton
w3 0.00 Ton
w4 0.00 Ton
w5 0.00 Ton
w6 0.00 Ton
w7 0.00 Ton
w8 0.00 Ton

W #VALUE! Ton

Tm 3.00 Bulan
T 2.50 Bulan
Te1 25.00 Hari/Bln
Te2 7.00 Jam/Hari
Fa 0.70 -

SC #VALUE! Ton/Jam

SCa 50.00 Ton/Jam #VALUE!