IPCC DEVELOPMENTS

The road to IPCC

In advance of our 24-26 October IPCC event in Bali,


Paul Moore looks at a range of projects that are using or
looking at using these types of systems; as well as
reviewing some news from the major OEMs involved Fully mobile ThyssenKrupp IPCC
systems during commissioning

number of projects worldwide at the reductions are possible.” The Hawsons iron ore IPCC has been shown to significantly reduce

A feasibility or initial development stage


have factored in IPCC into their plans,
whether in terms of waste handling or ore
project is located 60 km southwest of Broken
Hill and includes an inferred magnetite resource
of 1.4 billion tonnes. A prefeasibility study
capital and operating costs, decreasing manning
requirements, and reducing on-site emissions.
The proposal being considered would reduce
mining. This includes those being advanced by evaluating a 20 Mt/y concentrate production the peak number of trucks required to haul ore
juniors, but also some of the world’s largest option with a three year, 5 Mt/y start-up option and waste by 35. The median fuel consumption
groups, including Goldcorp, Cerrejon and Vale was completed in May 2011. for the Komatsu 930E haul truck at Penasquito
amongst others. The following gives an overview In established mines, developments include is 228 litres/h. This generates some 560 kg of
of the progress and plans of some of the newer the selection of IPCC by Goldcorp for the CO2e/h, or 3,700t CO2e per year. While the IPCC
projects as they relate to IPCC. Other companies Penasquito mine in Mexico. The Penasquito option would require an increase in grid power,
looking at IPCC include Stanmore Coal, which is mine has an average daily mining rate of it is estimated that over the life of the mine the
investigating its potential for waste transport; approximately 500,000 t throughout the 23-year greenhouse gas emission savings would be in
Marengo Mining for its Yandera project in Papua life of the project. Utilising Komatsu 930E haul the order of 2.2 Mt CO2e. The Penasquito IPCC is
New Guinea, as part of an ongoing definitive trucks requires an increase in haul trucks from now going ahead, with FLSmidth delivering the
feasibility study; and Iron Road for its Central the current 57 operating trucks to 119 haul semi-mobile sizer system.
Eyre iron ore project on the Eyre Peninsula of trucks over the next 15 years. The current Construction of the huge S11D project by Vale
South Australia. operating fleet provides sufficient hauling is already well underway. Vale’s multi-billion
In November 2011, Australia’a Carpentaria capacity until the end of 2012. dollar S11D project is a world-class 90 Mt/y iron
Exploration announced a significant rise in the Studies confirmed the economic feasibility of ore processing facility located approximately
estimated NPV of its flagship Hawsons iron ore installing an IPCC system, which would lower 1,940 km north of Sao Paulo, part of the Carajas
project to A$3.2 billion, based on lower the truck fleet requirements. A crusher would be mining complex. Snowden recently announced
projected operating costs used in a recent located at a central, strategic location in the pit, that Vale has awarded a contract to Snowden
mining option study. The increased NPV which would reduce the requirement to haul Brazil for the implementation of the long term
represented a rise of 14% from the pre- waste material long distances to the waste planning and implementation of the IPCC
feasibility study, and was based on modelling of dumps. solution. Snowden services will include, in a
in-pit crushing and conveying by GHD with With the growth in reserves on the site since first phase, the support of Vale in the
significantly reduced mining cost estimates the initial feasibility study, additional land is development of the long term mine plan
compared to conventional truck haulage. The required for the disposal of overburden. Land adopting an IPCC solution. Snowden has already
definitive feasibility study is being completed in close to the pit which would be suitable for facilitated a workshop with the Vale's Long Term
2012. truck haulage is known to be more expensive, Planning and Operational Readiness teams. The
Carpentaria's Executive Chairman, Nick more difficult to purchase and would require the IPCC system will be implemented in the Serra
Sheard, said at the time: "In-pit crushing and relocation of approximately 140 home sites. A Sul (S11D) block, a ridge of land 30 km long and
conveying is an established mining method and cheaper alternative is available to the west of around 1.8 km wide. The core equipment is the
well suited to the Hawsons deposit, importantly the tailings dam, which would be suitable for Sandvik PF200-9500 fully mobile IPCC system,
it has not yet been optimised and further cost conveyor transportation. of which four will be employed at the mine. This

18 International Mining | MAY 2012


IPCC DEVELOPMENTS

comments: “As a result of the boom and bust


cycle in Australia’s mining industry, it has
traditionally had a truck and shovel mining fleet,
which has a high emphasis on short-term
flexibility as opposed to looking at a project’s
long term optimisation. A lot of mining
companies put in place a traditional operation
because they are looking for low risk, early
payback on their investment and to make hay
while the sun shines. One of the problems with
the Australian mining industry is that for too
RCR is a leading Australian materials handling and further exploration drilling have boosted long there has been a reluctance to put the right
equipment manufacturer. In the IPCC arena it reserves estimates. amount of initial investment into a project so
has developed the specialised Mobile Mining
and Process Plant (MUP), which uniquely Elsewhere, IPCC was factored into the that it is more financially stable. If you go to
features combinations of feeding screening, feasibility study for the 2.73 billion tonne East other parts of the world, they’re not afraid to
crushing and processing plant mounted on a Kutai Coal Project as an option to lower costs. heavily invest in the right infrastructure for the
single self-propelled mobile platform
However, joint venture owners Churchill Mining long term. The benefit is that once they go into
and Ridlatama may have their mining licences production, their operating costs are low, so
design is a variant of the PF300 and has the revoked pending a decision in the Indonesia they can keep mining, even when commodity
same fundamental four crawler design. Supreme Court. prices drop. The IPCC concept has been well
Snowden has also conducted an IPCC versus In addition, IM has already highlighted proven across the globe by many major mining
conventional truck and shovel mining study for FLSmidth’s contract to supply Adaro Energy, one companies…studies have demonstrated that
the Moatize coal operation in Mozambique. In of Indonesia’s leading thermal coal producers, operating costs can be significantly reduced
addition to Sandvik, ThyssenKrupp has secured with an overburden handling solution to assist which shows that if you’re prepared to outlay
an IPCC order for handling the hardest rock at with overburden removal at its Tutupan open pit that extra money upfront, there is the potential
the S11D project (see OEM section). mine. The project is part of the continuous for large savings in the long run.” He adds:
SKM is also a key players in the S11D project. expansion of Adaro’s mining operations, and is “Back in the early days of FMG, we
It has just announced that is has a new $76 Adaro’s first venture into mechanised mining recommended the use of a surface miner. It was
million contract for the project, under which systems. new technology for the iron ore industry,
SKM will provide engineering for the truckless The current operation moves up to 1 Mbcm everyone else was still focused on drill and
system, procurement support, project execution per day, with plans to increase this in the future. blast, truck and shovel. It was leading edge,
planning and project management services in a The proposed system, at a rated capacity of Fortescue implemented it and it worked. The
deal that it says will be the cornerstone of its 12,000 t/h, will account for some 10% of total IPCC system isn’t leading edge, it’s well
mining business in Brazil. "SKM continues to overburden production. Adaro’s long-term established and should be considered.”
build on its relationship with Vale, utilising our strategy is to increase the amount of overburden
global engineering and project execution moved by mechanised systems to 40% of the Exeter Resource – Caspiche
capabilities. The Carajas project is currently the total or higher. Supply includes FLSmidth Exeter Resource announced in January this year
biggest private initiative in the world in the RAHCO overland conveyors (four each – total that the prefeasibility study for its Caspiche
development of iron ore mining. We are excited length 10km – 12,000 t/h); FLSmidth RAHCO project in northern Chile predicts an average
to be chosen as partners in this important project, mobile stacking conveyor: (one each – 411 m – annual production over the 19 year mine life of
and are committed to its successful delivery in 12,000 t/h); FLSmidth RAHCO spreading 696,000 oz of gold, 244 Mlb of copper and
order to assist Vale in realising its business conveyor: (one each – 50 m boom – 12,500 t/h); 844,000 oz of silver. Overall copper recovery is
objectives," SKM’s CEO Santo Rizzuto said. two ABON 13/300 CCTD sizers with two 335 kW 85.6% and gold recovery 67.6%. The study was
Indonesia was selected as the location for our drives – each 6,000 t/h; and two FLSmidth completed by Aker Solutions (now Jacobs
forthcoming IPCC 2012 event, and with good apron feeders – each 6,000 t/h. The system Engineering), and evaluated three mining and
reason. In a February 28th analyst briefing, incorporates the dumping of overburden hauled processing options, all of which included an
Banpu-owned Indominco indicates that it is by trucks into crushers at the pit perimeter, and open pit to mine the near surface heap
looking at installing IPCC systems at both its conveying the overburden to a disposal area leachable ore. The preferred development
Indominco East Block and Bharinto coal mines. some 6 km distant. This will significantly reduce option is an open pit operation processing
The company states that installing an IPCC the overburden haulage requirements at the 150,000 t/d of sulphide ore and a heap leach
system means: “it will be economic to go deeper mine, saving manpower and fuel, and reducing operation at an initial design production rate of
and mine more resources”, adding “IPCC truck fleet size. According to Garibaldi Boy 72,000 t/d. The study envisages that the heap
facilitates cheaper and quicker overburden Thorir, President Director of PT Adaro Energy, leach operation will start before the main
removal costs from deeper pits, enabling overall the Out of Pit Crusher and Conveyor (OPCC) concentrator with the leachable ore being
overburden costs per bcm to remain project will boost the efficiency by which the removed as part of the pre-stripping operation.
competitive.” Exploration work has boosted large amount of overburden is transported. Total proven and probable ore reserves,
reserves at Indominco’s East Block in 2011, and However, in addition to all of this activity, generated from an updated resource estimate
the company states that further reserves there can still be an inherent reluctance to for the Super Pit are 1.091 billion tonnes
upgrades are planned based on additional commit to IPCC. In the case of Australia, for containing 19.3 Moz of gold, 4.62 billion pounds
exploration and mining studies. At Bharinto, example, Scott McEwing, a mining engineer and of copper, and 41.5 Moz of silver.
engineering studies (including those on IPCC) a Principal Consultant with SRK Consulting A key component is the inclusion of high

20 International Mining | MAY 2012


IPCC DEVELOPMENTS

tonnage IPCC systems for the movement of


waste rock. This achieves greater efficiencies in
the movement of the pit overburden, not only to
address rising operating costs for mining waste,
but also the capital and operating costs involved
in the construction of tailings dam walls using
conventional methods.
The early implementation of IPCC allowed the
open pit development to be tailored to the
needs of the system and has resulted in
significant reduction in projected mining costs.
NCL acted as mining consultants to Exeter, and
estimated that the cost saving per tonne of total
material moved by using the IPCC system
instead of a large truck fleet is in the order of
$0.25 /t or approximately $0.80 /t of ore mined.
In addition to the operational savings, Exeter
estimates an initial and sustainable capital
saving of approximately $1 billion by building
the tailings dam wall largely from a conveyor-
stacker system rather than using conventional
truck haulage for material movement. The waste Star-Orion South diamond project footprint movement of waste rock. These include the
dump would form the backbone of an Collahuasi, Escondida and Chuquicamata mines.
engineered tailings dam face and provide a recognising early in the study process that the Exeter has relied on the experience of Sandvik
significant margin of safety in the event of an inclusion of in-pit crushing and conveying Mining and Construction, one of the leaders in
earthquake or other event. systems could provide significant reductions in IPCC technology to design a suitable system for
Exeter Chairman Yale Simpson stated: “We both capital and operating costs. In Caspiche. Sandvik recently installed two 8,000
are very pleased to have completed such a high implementing IPCC in the prefeasibility study, t/h systems in Boliden’s Atik mine and two
quality study within a relatively short timeframe. Exeter is following the lead of several copper 10,000 t/h units in Vale’s Carajas mine in Brazil.
The study benefited markedly by us having an operations in Chile and Peru which are utilising With the PFS to hand we will now proceed with a
excellent engineering team capable of or developing high tonnage IPCC systems for the stand-alone heap leach project feasibility study,

MAY 2012 | International Mining 21


IPCC DEVELOPMENTS

One waste rock crushing plant will be located


outside the pit and the two other crushing
plants will be located at the same truck pad
inside the pit (one for ore and one for waste).
However, each crushing plant can be used to
handle either ore or waste rock depending on
the operational requirements. It should be
noted that since the waste rock handling
capacity will be about 34% higher than ore
handling capacity, different main shafts will be
required for ore and waste rock application.
The waste rock stacking system will consist of
shiftable conveyors, travelling tripper and
spreader. A starter pile, which will be stacked by
truck and located in the east side of the North
Waste Rock Dump area, is proposed as the
starting point for the stacking system. To reduce
A semi-mobile in-pit crushing solution from ore will be transferred to the coarse ore downtime due to equipment relocation, the
Takraf with external surge bin stockpile by the belt conveyors. In the waste height of the starter pile will be the same as the
rock handling system, the rock will need to be final dump height and stacking will be
hydrological mapping and geotechnical crushed so that it can be handled by the down- developed using downcast mode. The selected
evaluations, an Environmental Impact Study stream belt conveyors and stacking system. stacking mode will be carried out by radial
submission, and metallurgical and process The crusher installation will be divided into advance stacking by shifting the conveyor
optimisation studies. The Company treasury is three phases. In Phase 1, a crusher will be around a pivot point.
more than adequate for the continued constructed on the exit point of the ultimate pit
advancement of the project.” design (out-pit crusher). This particular crusher Hancock Coal – Alpha
will initially be used as an ore crusher and can Hancock’s Alpha coal project is the most
KGHM Ajax be switched to be waste or ore crusher when the advanced coal project in Australia’s Galilee
The Ajax project is a proposed open-pit copper- in-pit crushing system is in place. The crusher Basin. It has a JORC compliant resource of 3.6
gold mine located near and partly within the city will remain on its location until the end of mine billion tonnes, with 2 billion tonnes reserves in
limits of Kamloops, British Columbia. KGHM is a life. During Phase 2, two in-pit crushers will be the measured + indicated categories. The
joint venture between Vancouver-based Abacus constructed at the 796 m elevation early in Year completed bankable feasibility study outlines
Mining (49%) and KGHM Polska Miedz (51%), 7 and will be ready to be operated in the middle the development of an open pit mine which will
the leading Polish copper and silver producer of Year 7. The two crushers will handle ore and produce over 30 Mt/y of high grade thermal coal
through its three flagship mines – Lubin, Rudna waste material. During Phase 3, the two in-pit for export to markets within Asia. First coal
and Polkowice-Sierszowice. According to the crushers will be relocated from the 796 m production is expected by the end of 2014. In
KGHM Ajax 2011 feasibility study carried out by elevation to the 700 m elevation. The relocation September 2011, Indian infrastructure major
Knight Piesold, the Ajax mine is expected to of both in-pit crushers will be done in Year 13 so GVK Power, part of the GVK Group, acquired
produce 109 Mlb of copper and 99,000 oz of that they can be used by the beginning of Year 14. Hancock Coal for $1.26 billion, in one of the
gold annually over its 23-year mine life. Conveyors will handle ore material from the largest overseas acquisitions by an Indian
IPCC is an important part of the mine’s plan ore crushers to the plant, and the waste company. GVK said the deal, which includes
as outlined in the study. Following the material will be handled from the waste crusher acquiring majority holding in coal resources and
prefeasibility study, IPCC was identified as a to the North Dump equipped with a stacking railway line and port infrastructure projects of
potential cost reduction implementation for the system. Conventional conveyors were selected Hancock Coal, will offer the Hyderabad-based
Ajax project when compared with a truck-haul for the IPCC system. The conveyors will be company option for long term coal supply
option only. At the time, the mine plan was constructed on the south and west side of the contracts for the purchase of up to 20 Mt/y. This
completed using conventional truck-haul with ultimate pit limit. The conveyors will have to can support around 7,500 MW of power
and without IPCC for comparison. cross a shallow portion of the lake on the west generating capacity.
The feasibility study envisages a combined side of the pit where a protection berm will be SKM conducted a study for Hancock on the
IPCC system with out-pit gyratory primary constructed to help prevent water flow into the potential application of IPCC systems for the
crushing system. Two potential locations for the pit. The overland conveyor on the west side will Alpha project bankable feasibility study. The
IPCC system were assessed, on the north wall, utilise this protection berm for its foundation. Alpha project involves a significant amount of
and on the south wall; and the south wall site An overall availability of 70% was selected to overburden removal – with an IPCC system set
was selected. In general, the IPCC system will size equipment. For the crusher design capacity, to be installed to remove the upper overburden
consist of three semi-mobile crushing plants no design factor was considered. A design factor bench. This will operate in front of a dragline
and corresponding belt conveyors. The crushers of 1.15 was considered for the belt conveyor and operation followed by actual coal removal.
will be mounted on concrete pontoons and can the stacking system design capacities to handle Initially the IPCC systems will convey the
be relocated from time to time according to the possible higher crushing capacity due to finer overburden out of the pit to dump areas but
mine development schedule. In the ore handling and softer ROM fed to the crusher. The crushing later in the mine life it with be dumped in-pit.
system, the ore will be crushed to the size which plant will consist of a truck dump pocket, Two IPCC systems will be operated at the mine –
meets the process requirements. The crushed gyratory crusher, surge pocket and belt feeder. system 1 in mining pits 2 and 3 South. System 2

22 International Mining | MAY 2012


IPCC DEVELOPMENTS

study; rather, a currently available


crusher/feeder system (60 x 89 in gyratory)
capable of handling the projected material size
and tonnage rate (4,000 t/h) was used as an
example and quotes were requested for systems
of similar capabilities. The example system was
used to determine the dimensions of the
crusher pocket needed and the feed and
dumping area needed by the ore truck fleet.
Conetic Resources was asked by Tetra Tech to
evaluate the conveyor requirements for the
Pumpkin Hollow Project.
The initial development of the in-pit
conveying system is the construction of the
plant ore stacker conveyor. It rises to a height of
105 ft above the 120,000 t plant ore stockpile
and would be there for the duration of the North
and the South Pit mining operations. The plant
ore reclaim system is part of the mill processing
MMD has a long and successful working via a conveyor system. All waste material is system and is discussed in that area of the
relationship with Pinghsuo, dating back to the hauled by truck out of the pit and directly to the report. The North Pit conveyors are developed in
installation of two 4,000 t/h plus sizing stations
waste dump (mine rock storage facility or three distinct phases as the mining progresses
in 1992 at the An Tai Bao mine
MRSF). into the open pit. The first phase of conveyor
will operate in 3 North and 4. Overall, the Alpha Pit slope configurations used in designing the development includes the plant ore stacker and
mine has six separate pits that will run north to Pumpkin Hollow pits were based on information the North Pit Phase 1 conveyor, which connects
south, each separated by bridge and truck contained in a report from Golder Associates. the In-pit crushing system with the plant ore
ramps. The overburden horizons in question are Recommended slopes considered the drill core stacker. The North Pit Phase 1 conveyor is on the
15-30 m deep, generally uniform and data, analysis of structural data, and point load North Pit crest surface as the open pit is
geometrically simple. testing. The ultimate pit design utilises developed. North Pit Phase 2 conveyor
The two IPCC systems will be identical in switchbacks to maintain the road and ramp operations include the addition of new
terms of equipment and function. Each will system on the north side of the North Pit while conveyors to link together in a saw tooth
utilise an electric rope shovel, Caterpillar D11 the South Pit maintains the haul road system on fashion to remove the crushed ore from the pit
dozer and mobile sizer rig with twin roll sizer. the south side of the pit. This allows for better economically and avoid steeper inclines. The
The dozer and shovel will be used to mine the traffic flow between pit phases and allows the final phase of the North Pit operations is called
upper overburden layer, with the dozer pushing IPCC system to be installed in the inactive or Phase 3 and Ultimate. This operation requires
material to the shovel that will feed the mobile less active portions of the pits with no haul the construction of five conveyors for ore
sizing rig, which will reduce the lump size and road/conveyor crossing areas. The pit designs haulage from the in-pit crushing system to the
feed a face conveyor. Nominally, the shovel will were created to use a 40-ft single bench and 80- plant ore stacker conveyor.
remove an 18 m bench with the dozer pushing ft double bench designs. The conveyor alignments in the South Pit for
an extra 12 m of material to the shovel, allowing Near the start of the feasibility study, Nevada Phase 1 have two conveyors. Conveyor 1 would
an overall 30 m high bench to be removed. Copper requested a trade-off study which be in place for the life of the South Pit Mining
There will be two face conveyors for each mining compared cost differences for various methods operation. Conveyor 2 would be the only
system, with the system moving between face of material transport from the surface mine pits conveyor purchased in the Phase 1 operation.
conveyors as the mine advances to the north. at the proposed Pumpkin Hollow Project. The This allows the mining operations to open the
The face conveyors will feed cross-pit conveyors study focused on costs related to the use of a pit. The South Pit Phase 2 conveying system is
and finally the dump conveyors. All will be truck fleet and/or in IPCC of mined material to intended to be constructed from the conveyors
relocatable. its final ex-pit destination. Different previously used in the North Pit and the South
combinations of truck and/or belt transport Pit.
Nevada Copper – Pumpkin Hollow were explored for the study. The study A stockpile of ore uncovered and removed
The open-pit mine is planned as a 60,000 t/d of conclusions showed that the parameters which during the initial pre-stripping period of waste
ore open-pit truck and shovel operation. The had the greatest impact on the relative NPV in movement from the North Pit area would be
open-pit mining method considers the use of this trade off study were that a reduced truck located near the coarse ore stockpile. This pile
electric blast hole drills, large haul trucks, both fleet for ore transport, combined with a mid- would initially contain approximately 1.3 Mt of
cable and hydraulic shovels, and in-pit ore cash flow capital expense of an IPCC system, above cut-off ore material hauled directly from
crushing and conveying capabilities “to achieve generated increased value for the project. the mining areas by truck. Approximately 1 Mt of
the most reasonable cost benefits and Additionally, the study showed that value was this material would be fed into the processing
selectivity for this type of deposit.” The mine not added by utilising the IPCC to transport plant as part of the initial mill production. The
phases were designed with a series of in-pit ore waste and ore; the highest value was obtained remainder would be used as a “surge pile” to
crusher locations over the life of the mine. All by utilising the IPCC to haul ore only. smooth out small production bumps during
mined ore is hauled by truck to the in-pit Project time constraints did not allow for a regular production periods of the open pit mine.
crusher, crushed, and transported out of the pit detailed and comprehensive in-pit crusher Blasthole drilling for both ore and waste

24 International Mining | MAY 2012


IPCC DEVELOPMENTS

and clay pre-stripping All of these key groups continue to highlight the
excavators and haul economic benefits of IPCC in the form of higher
trucks, road graders, production performance with reduced capital
and field maintenance costs (particularly when compared to
and service vehicles discontinuous truck operations), but also its
including all-terrain huge potential for reducing operations related
cranes. The proposed CO2 emissions, thus providing a greener
IPCC stripping system footprint as continuous mining equipment is
is a waste excavation powered exclusively by electricity. All of these
/ conveying / stacking areas will again be addressed in the IPCC 2012
system. It will initially event in Bali from 24-26 October.
include three One of the leading players, ThyssenKrupp has
electrically-powered developed a modular series of devices which
shovels, each having a run in single and multiple bench operation. The
fully-mobile sizer and company states: “This array of products allows
a fully-mobile transfer the company to create individual solutions to
MMD’s initial entry into IPCC was an conveyor; two semi-mobile across-bench every customer request.”
installation at the Meirama operation in Spain,
that was acquired to complement a gyratory conveyor assemblies; twin inclined conveyors on The group’s first fully mobile crushing system
crusher which it eventually replaced the Star Phase 1a pit access ramp; an overland of its new design was delivered to the YiminHe
conveyor with conveyors and a waste stacker at coal mine in China in 2007. The crushing plant
material is expected to utilise Caterpillar 6540 the overburden stockpile; and an auxiliary waste processes ROM coal at a design rate of 3,500
electric drills. Primary mine waste production is stacker. The IPCC system will be progressively t/h. ThyssenKrupp adds: “This successful
achieved using Caterpillar 7495 electric rope expanded as the pit is developed. IPCC in-pit operation in YiminHe led to a further order for
shovels loading Caterpillar 795 haul trucks. equipment will move between the Star and four fully mobile crushing systems for the
Primary ore movement will be with Caterpillar Orion South pits as required by the mine Baiyinhua coal field in China. Three of the four
6060 hydraulic excavators loading 795 haul schedule. The overland conveyor between the systems will be used to remove overburden,
trucks which haul the ore to the in-pit crushing Star pit and the overburden stockpile will be each having a design capacity of 6,900 t/h. One
and conveying system, for which no equipment relocated to serve the Orion South pit. It is 3,500 t/h system will be used for coal
selection was indicated in the study. assumed that the tills to be excavated by the processing.”
system will be free-digging material. The IPCC In 2010 ThyssenKrupp states that it received
Shore Gold – Star-Orion South system will commence operations in the Star another order for two fully mobile crushing
This represents a large accessible diamond Phase 1a pit and will then be relocated to the systems for overburden handling in an iron ore
resource in central Saskatchewan, Canada for Star Phase 1b pit. The IPCC system will be used open pit mine in Brazil. Each crushing plant is
which the feasibility Study was completed in to sequentially strip Star pit phases 1a to 3 and equipped with a double-roll crusher and
August 2011 that envisages a 20 year mine life Orion South pit phases 1a to 2. The IPCC system operates in the mine together with a shovel
producing 34.4 Mct from a reserve of 279 Mt of has a capacity of 117 Mwt/y. Three Takraf TMCS crushing overburden at a rate of up to 3,900 t/h.
kimberlite, with a production cost of $242/ct. 8400 (8,400 t/h) mobile sizer are being A particular challenge here was the planning
The open pit mining will employ three methods: considered as the core machine along with three and realisation of such a system for a mine type
a conventional truck and shovel for removal of Komatsu electric PC8000 hydraulic excavators, which typically extend downwards with fairly
overlying sand and clay, in preparation for an six 8,400 t/h capacity conveying bridge steep pit walls, in comparison to coal mines,
IPCC system; the IPCC system with a large conveyors; two 8,400 t/h capacity inclined which typically have relatively wide benches.
capacity overland conveyor for the majority of conveying bridge conveyors and two 16,800 t/h This was followed in the summer of 2011 by a
overburden and in-pit waste; and a hybrid truck capacity shiftable in-pit conveyors. Each delivery contract with Inner Mongolia Datang
and shovel with IPCC for ore haulage to the shiftable conveyor will be equipped with two International Xilinhot Mining for three fully
process plant. The mining rate is expected to be hopper cars to enable one or two fully mobile mobile crushing systems for their Shengli East
14.3 Mt/y with an overall strip ratio of 6.35:1 sizers to discharge to an in-pit shiftable No 2 open pit coal mine in China. ThyssenKrupp
waste to ore. The current mine plan exposes 2 conveyor. The in-pit
years of ore in the beginning phases for Star shiftable conveyors
and Orion South, prior to processing first ore. will discharge to the
The proposed IPCC system will be used to up-ramp conveyor
excavate, size, convey and stack the overburden feeding the overland
in the designated overburden stockpile. A waste conveyor.
20,000 t/h capacity IPCC system will be used to
strip the till and underlying Colorado shale and System provider
occasional siltstone, sandstone and clay updates
materials. The key OEMs
The IPCC system will be operated and providing IPCC
maintained by Shore with the assistance of a solutions continue to
maintenance contractor. Operations will be refine designs and Waste stacking, in this case a
supported by drilling and blasting equipment, work towards solution from Sandvik, remains
a key part of the IPCC market
bulldozers and wheel dozers, the surficial sand delivering contracts.

26 International Mining | MAY 2012


IPCC DEVELOPMENTS

states: “These plants will be the first of its kind On the fully mobile front, FLSmidth is
in fact they are equipped with an patent developing new hydraulic excavator based
pending integrated conveyor bridge to forward undercarriage designs for its sizer stations that
the material directly from the crushing system offer extreme robustness and manoeuverability
to the shiftable face conveyor. The three fully as well as spare part commonality with end-
mobile double roll crusher plants will be used users' mobile mining equipment. Finally, the
to remove overburden, each having a design company reports that industry interest in the
throughput of 10,000 t/h.” FLSmidth Dual Truck Sizer Station has been
ThyssenKrupp highlights one of its latest extremely positive and several major global
innovations in the in-pit crushing area as what resource companies have expressed interest in
is states as the first fully mobile crushing rig trialling the technology for use in future
equipped with a large jaw crusher, in this case projects.
a type EB 20 x 15. The company told IM: “This
newly developed design enables the High angle conveying
employment of fully mobile crushing While crushing/sizing technology is a core part
equipment in open pit mines where material of the IPCC equation, some would argue that
with highly compressive strength up to 250 advanced conveying technologies which could
MPa can be handled. This was an important greatly benefit IPCC solutions, especially in
step for ThyssenKrupp to extend the field of hard rock open pits, have been overlooked.
operation of its fully mobile equipment.” One solution to optimising IPCC systems in
An order for this design was received in steeper pits is employing high capacity, high
January 2012 from Vale for the already angle conveying to take overburden or ore
discussed S11D project in Brazil. This consists directly out of the open pit. But though there
of three crushing plants, each with a design have been examples of steep conveyor flights
capacity of 2,500 t/h; each plant will working in in the industry such as at Chuquicamata,
combination with two mobile conveyor modules The RTB Bor Majdanpek high angle conveyor Cananea, Majdanpek and Kovdor, this method
mounted on wheels. on the whole remains underutilised. Companies
MMD’s initial entry into the IPCC market was more than 20 years. The first MMD IPCC units offering steep and/or high-angled conveying
in Spain with a ground-breaking semi-mobile supplied to Pingshou were two 4,000 t/h plus solutions include P&H MinePro’s (former
sizer unit that introduced the in-ground hopper sizing stations delivered to their An Tai Bao mine Continental Conveyor) HAC solution, FLSmidth,
to the industry, installed in 1989. It was acquired in 1992. The results achieved with these units; Takraf, ThyssenKrupp, Sandvik and others such
to complement a gyratory crusher, which it which were later relocated, led the company to as Dos Santos International with its high-angle
ended up replacing once it proved capable of place a number of subsequent orders for a sandwich conveyors.
handling up to 4,000 t/h of a mixed overburden series of semi-mobile units; the most recent With their high efficiency and low
containing significant quantities of both clay having been delivered in 2011. maintenance costs, steeper belt conveyors can
and granite. The MMD unit’s ability to handle FLSmidth says it is “continuing to lead the yield substantial benefits and open up the
high volumes of difficult material, together with industry with innovative technologies and possibility of IPCC utilisation in deeper pits. Dos
its capability of being re-located quickly and solutions for in-pit crushing and conveying.” Santos for its part believes that its high
easily have remained key attributes of the The large FLSmidth ABON 16/350 CCTD low capacity, sandwich belt-type high angle
group’s delivered machines and updated speed sizer in the Takraf fully mobile IPCC conveyors facilitate a direct high angle path to
designs ever since. Another example of MMD system is entering its third year of successful the surface, along the mine wall, without
success with IPCC innovation were the initial operation at the Rio Tinto Clermont coal mine in additional unproductive excavation. The
three semi-mobile installations at the Mae Moh Australia and according to the company “has company tells IM: “Many portable and mobile
lignite mine in Thailand that were delivered in proven itself to be more than capable of conveyor systems become cumbersome when
1993, whose performance led to a subsequent crushing both extremely hard competent ores as attempting to elevate the material along the low
order for a further set of four similar updated well as sticky difficult to handle ores at high conventional angles. The compact, high angle
units in 2001, all of which are still operating. throughputs.” As stated earlier, FLSmidth is also conveyor is to solution to the interferences
The company points to synergies developed currently busy shipping the major components posed by conventional systems. This affords
between MMD and its customers, epitomised by of what it believes will be the world's largest not only an economic benefit, but an
events at China’s Pingshou Coal, which is sizer station to date, at Goldcorp's Penasquito environmental one as well. The high angle
awaiting delivery of MMD’s latest contribution mine in Mexico. This semi-mobile sizer station conveyor has a small footprint, both physically
to the development of IPCC, the fully mobile will also incorporate an ABON 16/350 CCTD low and environmentally.” Its early 1990s
MMD LPMS unit, which is currently under speed sizer as well as a 3.15 m-wide D11 low installation at RTB Bor’s Majdanpek copper mine
construction in China (along with three 9,000 angle apron feeder capable of delivering up to in Serbia displaced 12 200 t trucks. This
t/h semi mobile IPCC rigs for Datang) and due to 12,500 t/h throughput. FLSmdith is also extended the mine life as the space of the final
go into operation later this year. However, what manufacturing one of the world's largest pit would not accommodate the truck-only
is generally not known is that MMD’s receipt of gyratory crushers for a new copper mine in Peru. traffic. Designed to elevate 250 mm minus
the order was not simply due to Pingshou’s The counterbalanced and compact design of the copper ore at 4,000 t/h, the 2,000 mm wide
seeking to install a fully mobile IPCC system, new 63 in x 118 in flagship top service gyratory sandwich belt high angle conveyor lifted the
but represents the culmination of a long and crusher is “ideal for installation in one of our material 93.5 m to the pit perimeter along the
successful relationship with MMD going back semi-mobile crushing stations”, says FLSmidth. 35.5° pit wall during ten years of service. IM

28 International Mining | MAY 2012