End User’s Guide

End User’s Guide


PP

Team:
Process status:
PP

Updates
Date Version Author Comment

This document is related to


SAP systems/client Version
PRO SAP ECC 6.0

Pre-requisite

Document1 Page 1 of 75
End User’s Guide

Table of Contents
I. General Introduction.............................................................................................................................. 3
II. Create process order ...................................................................................................................... 4
III. Consumption of component for SFG .............................................................................................. 11
IV. Process Order Confirmation of SFG ............................................................................................... 13
V. Good receipt for Process order SFG ............................................................................................... 16
VI. Consumption of component of FG ................................................................................................. 24
VII. Order Confirmation of FG ............................................................................................................. 30
VIII. Good receipt of FG ................................................................................................................... 33
IX. Production report ......................................................................................................................... 44
X. Rework management (for Ice cream) ............................................................................................ 50
a. Rework declaration ...................................................................................................................... 50
b. Rework consumption .................................................................................................................... 59
XI. Cancel a consumption .................................................................................................................. 66
XII. Cancel a confirmation ................................................................................................................... 69

Document1 Page 2 of 75
End User’s Guide

I. General Introduction

This document treats PP topics

Document1 Page 3 of 75
End User’s Guide

II. Create process order

SAP Logon 720


Menu: Observations
Transaction: COR1
STEP 1 : Process order creation. TCODE COR1

Put the material number.


Put the production plant (1000).
Put the process order type (NA01).

Enter

Document1 Page 4 of 75
End User’s Guide

Put the planned total quantity and the start date of production.

Go to MasterData.

Document1 Page 5 of 75
End User’s Guide
Select a production Version

Then go to Materials.

Document1 Page 6 of 75
End User’s Guide
Select the materials for which you want to enter a batch.

Execute batch determination by clicking on .

Document1 Page 7 of 75
End User’s Guide

Choose the batch you want to use and Click on copy for all materials.

Document1 Page 8 of 75
End User’s Guide
Click on the flag (release process order).

New screen appears.

Click on release order.

Document1 Page 9 of 75
End User’s Guide
Save

Process order created.

Document1 Page 10 of 75
End User’s Guide

III. Consumption of component for SFG


SAP Logon 720
Menu: Observations
Transaction:
STEP 1 : Consumption of componemt TCODE MB1A, movement code 261

The components are in the picking area (process seen in the WM user
guide)

Put the Plant 1000, mvt type = 261

Click on To Order ( it is a good issue to process order)

Document1 Page 11 of 75
End User’s Guide

Put the process order number

validate

Put the actual quantity consumed and not the standard.

If you need to modify the batch number of the component, please ask
the supply planner to update it in the process order.

Save

Document1 Page 12 of 75
End User’s Guide

IV. Process Order Confirmation of SFG

Step 1 : TCODE : COR6

Enter the process order number

Document1 Page 13 of 75
End User’s Guide

The system shows the operations.

Select the operation you want to declare quantity and hours

Click on detail icon

(repeat this steps for all operations)

Document1 Page 14 of 75
End User’s Guide

Put the quantity produced by this operation and time of labor and
machine

You have to provide fixed time and operating time for labor and
machine.

Put final confirmation if it is and clear reservation button.

Document1 Page 15 of 75
End User’s Guide

V. Good receipt for Process order SFG

Step 1 : Process the Good receipt TCODE : MB31 , movement type 101

Put the movement type = 101

Put the process order number involved by the GR

Put the plant

Document1 Page 16 of 75
End User’s Guide

Select the line and click on Adopt+details icon

Document1 Page 17 of 75
End User’s Guide

Put the quantity

Check the storage location = Z001

Put the Batch number:

 for SFG :you could enter a batch number by mixing lot ( as usual) eg
: 123/1

for FG : take the same batch number of the SFG as usual

The batch number will be provided by Quality team as usual

Put delivery completed status if it is

Put the manufacturing date  the expiry date will be calculated


automatically by the system

Document1 Page 18 of 75
End User’s Guide

The system does the classification of the batch  shelf life calculated

Save

Step 2 : perform the stock placement of the SFG TCODE LB10

Convert the TR created into TO

Put the Warehouse number =N01

Document1 Page 19 of 75
End User’s Guide
Validate

Select the TR to be converted

The requirement number is the process order number

Click in the TO creation in Foreground

Document1 Page 20 of 75
End User’s Guide

Click on the icon

Select the destination storage type and BIN

For each tank, there is a specific bin

Document1 Page 21 of 75
End User’s Guide

Save the creation of the TO

Step 3 : confirm the TO TCODE LT12

Put the TO number + validate

Document1 Page 22 of 75
End User’s Guide

Check the quantity and save.

Document1 Page 23 of 75
End User’s Guide

VI. Consumption of component of FG

Step 1a : check the process order T Code : COR3

Put the process number and validate

Document1 Page 24 of 75
End User’s Guide

You could see the components involved by this process order

Step 1b : transfer the Stock of the SFG to the Picking area of the FG T Code : LT10
Select the corresponding
bin of the SFG and
transfer to the correct
storage type destination

Storage type destination


= 504
Bin = Pr Order number
(here 0001000098)

Document1 Page 25 of 75
End User’s Guide

Document1 Page 26 of 75
End User’s Guide

Step 2 : consume the components TCODE : MB1A , mvt 261

Put the process order number involved and movement type 261

Click on To order icon to put the Pr Order number

Document1 Page 27 of 75
End User’s Guide

Document1 Page 28 of 75
End User’s Guide

Check the quantity consumed and save

Document1 Page 29 of 75
End User’s Guide

VII. Order Confirmation of FG

Step 1 : declare the quantity and time for each operation TCODE : COR6

Put the process number + validate

Document1 Page 30 of 75
End User’s Guide

The system shows the operations.

Select the operation you want to declare quantity and hours

Click on detail icon

(repeat this steps for all operations)

Document1 Page 31 of 75
End User’s Guide

Put the quantity produced by this operation and time of labor and
machine

You have to provide fixed time and operating time for labor and
machine.

Put final confirmation if it is and clear reservation button.

Document1 Page 32 of 75
End User’s Guide

VIII. Good receipt of FG

Step 1 : perform the GR of the FG TCODE : MB31

Put the process order number and movement type = 101

Document1 Page 33 of 75
End User’s Guide

Select the line and Click on details icon

Document1 Page 34 of 75
End User’s Guide

Put the quantity

Check the storage location = Z001

Put the Batch number:

for FG : take the same batch number of the SFG as usual

The batch number will be provided by Quality team as usual

Put delivery completed status if it is

Put the manufacturing date  the expiry date will be


calculated automatically by the system

Document1 Page 35 of 75
End User’s Guide

The system does the classification of the batch  shelf life


calculated

Document1 Page 36 of 75
End User’s Guide

Save

Step 2 : convert the TR into TO for the stock placement TCODE : LB10

Put the warehouse number and validate

Document1 Page 37 of 75
End User’s Guide

Select the TR to be converted

The requirement number is the process order number

Click in the TO creation in Foreground

Click on the icon

Document1 Page 38 of 75
End User’s Guide

Select the destination storage type and BIN

For each cold room, there is a specific bin

Document1 Page 39 of 75
End User’s Guide

Save the creation of the TO

Do the stock placement according the TO.

Step 3: confirm the TO TCODE LT12

Put the TO number + validate

Document1 Page 40 of 75
End User’s Guide

Document1 Page 41 of 75
End User’s Guide

Check the quantity and save

Step 4 : check the Stock WM TCODE : LX02

Put the Warehouse number and the storage type you want to
check

Execute

Document1 Page 42 of 75
End User’s Guide

This report could be printed and transferred to Excel

Document1 Page 43 of 75
End User’s Guide

IX. Production report

Step 1 : check the production planning TCODE : COOISPI

Put the selection criteria according the search

The criteria could be at :

 header level
 operation level
 component level
 on date

Document1 Page 44 of 75
End User’s Guide

You could add some field, modify or display the process


order selected

Step 2: check the load and capacity machine

Document1 Page 45 of 75
End User’s Guide

Document1 Page 46 of 75
End User’s Guide

TCODE : CM01

You see the load and capacity machine per week

You could have the detail of each week

Document1 Page 47 of 75
End User’s Guide

Document1 Page 48 of 75
End User’s Guide

You see the requirement of the week

The requirement will disappear from this resource until


the confirmation will be done.

Document1 Page 49 of 75
End User’s Guide

X. Rework management (for Ice cream)

a. Rework declaration

Step 1 : check the Process order TCODE : COR3

You see the rework component 15 000 060.

We could make the rework declaration during the


production of the FG.

Declaration will be done at the 1st operation of the


process of the FG when we will confirm the operation.

Rework component is defined in the BOM of the FG.

Step 2 : declare the Rework TCODE : COR6

Put the process order and validate

Document1 Page 50 of 75
End User’s Guide

Document1 Page 51 of 75
End User’s Guide

Select the 1st operation

Click on detail

Document1 Page 52 of 75
End User’s Guide

Put the time and quantity as defined previously.

Click on Goods Movement to declare the rework.

Document1 Page 53 of 75
End User’s Guide

Put the manufacturing date and validate

Put the correct quantity of the rework

Put the batch of the rework  same batch of the FG

You see the manufacturing date entered just before, the


expiry date will be calculated by the system upon quality
input.

Click on the green arrow

Document1 Page 54 of 75
End User’s Guide

Save

Finish the confirmation process as usual.

The rework is created.

Step3 : check the stock WM TCODE LS24

Put the Warehouse number + the material code +


validate

Document1 Page 55 of 75
End User’s Guide
The stock is in the storage type 901 which is a technical
storage type.

Now we have to convert the TR into TO and confirm it


after.

Step4: convert the TR into TO TCODE LB10

Select the TR and convert it in backgroung

Step5: confirm the TO TCODE LT12

Document1 Page 56 of 75
End User’s Guide
Put the TO number

Save the TO

Step 6 : check the stock WM TCODE LS24

The stock is in the storage type 500 corresponding to


Rework stock.

Document1 Page 57 of 75
End User’s Guide

Document1 Page 58 of 75
End User’s Guide

b. Rework consumption

Step 1 : creation of process order of the SFG by supply planner TCODE COR1

Order type = NA02 for Rework

Update the quantity of the BOM with the rework component The new formula with the rework must be
validated/provided by the quality team.

The system will ask to which operation should


assign the component rework.

Document1 Page 59 of 75
End User’s Guide

Put the batch of the rework to consume and finish


the process order creation process as usual.

Step 2: consume the rework TCODE MB1A, mvt code 261

Put the process order to consume the component

Document1 Page 60 of 75
End User’s Guide

Document1 Page 61 of 75
End User’s Guide

Put the quantity of the component and adopt (as


defined before)

Document1 Page 62 of 75
End User’s Guide

Here we do not already consume the rework.

We need to add it to the list

Document1 Page 63 of 75
End User’s Guide

Put the process order

Put the detail of the rework component :

 Material code
 Quantity
 Unit
 Batch

Save

The consumption is done for the process order :


usual component and the rework.

Step3 : check the consuption of the process order TCODE : COOISPI

Select the list

Put the Process order + execute

Document1 Page 64 of 75
End User’s Guide

You have all consumption on the process order

You see the rework consumption :

 Movement type = 261 for consumption (


262 for cancel)
 Quantity = 1kg
 Batch
 Material document of the consumption

Document1 Page 65 of 75
End User’s Guide

XI. Cancel a consumption

Step 1 : put the material docuement TCODE : MBST

Take the material document number of the consumption


via COOISPI 9 as seen previously)

Check the date  posting date must be in the same


month of the consumption

Step 2: Select the component to ba cancel Select the item to be cancelled + save

You could see the movement type is 262 (the reverse of


261)

Document1 Page 66 of 75
End User’s Guide

Step3 check the consumption TCODE COOISPI

You see for each item, we have movement type 261 and
262  it means no consumption is done for the process
order

Document1 Page 67 of 75
End User’s Guide

Document1 Page 68 of 75
End User’s Guide

XII. Cancel a confirmation

Step1 : check the confirmation TCODE COOISPI

Put the Process number

Choose the list “Confirmations”

execute

Here the synthesis of the confirmation for the process


orders.

Let us cancel the operation 11 and confirm it again


updating the fix machine time

Step2: cancel the confirmation TCODE CORS

Document1 Page 69 of 75
End User’s Guide

Put the process order number

Put the operation to cancel

validate

Document1 Page 70 of 75
End User’s Guide

Save the cancellation

The system is asking for a reason of this cancellation 


you could add q comment in order to explain this
cancellation

Document1 Page 71 of 75
End User’s Guide

Step3 : confim the operation with the updating data TCODE COR6

Document1 Page 72 of 75
End User’s Guide

Document1 Page 73 of 75
End User’s Guide

Put the updating data and save as usual

Step4: check the confirmation in the report TCODE :COOISPI

Document1 Page 74 of 75
End User’s Guide

You have the history of the confirmation

Document1 Page 75 of 75