Work plan for upcoming days:

Friday 12/01.2018

Civil works

- Floor demolition in room 1 for sewage installations


- Taking out elements from the kitchen and storage in room 1 phase I – This can cause work
delays in room 1 (to many elements to go around during installation of insulation, HVAC and
electrical installations
- Securing the rest of equipment in the kitchen from damage using old insulation and PVC foil
- Roof demolition
- Dismantling the HVAC in room 1 and disposal to landfill
- Start of placing the thermal insulation on the façade walls (Behind Alu-bond)

Electrical works

- Grounding on the roof installations – if weather permits


- Dismantling the electrical installations in the roof of the kitchen
- Container connection
- Maintenance of the electrical installations

Saturday 13/01.2018

Civil works

- Placing the thermal insulation on the façade walls (Behind Alu-bond)


- Floor demolition for electrical installations in room 1
- Dismantling the HVAC in room 1, in kitchen and disposal to landfill
- Tiles demolition in kitchen
- Tiles repair works in hallway

Electrical works

- Grounding on the roof installations – if weather permits


- Installation of power line supports in room 1
- Dismantling the electrical installations in rest of area 4
- Maintenance of the electrical installations
Sunday 14/01.2018

Civil works

- Placing the thermal insulation on the façade walls (Behind Alu-bond)


- Dismantling the HVAC in kitchen and disposal to landfill
- Tiles demolition in kitchen and disposal to landfill
- Demolition of walls in kitchen for water and electrical installations
- Cleaning the site with disposal to landfill

Monday 15/01.2018

Civil works

- Water and sewage installations in room 1 and in kitchen


- Placing the thermal insulation on the façade walls (Behind Alu-bond)
- Start of placing the thermal insulation below the roof metal sheets

HVAC works

- Installation of supports for the HVAC canals’

Electrical works

- Installation of power line supports in room 1


- Dismantling the electrical installations
- Maintenance of the electrical installations

Tuesday 15/01.2018

Civil works

- Water and sewage installations in room 1 and in kitchen


- Closing the openings for water and sewage installations in room 1 and in kitchen
- Placing the thermal insulation on the façade walls (Behind Alu-bond)
- placing the thermal insulation below the roof metal sheets

HVAC works

- Installation of supports for the HVAC canals’

Electrical works

- Installation of power line supports in kitchen


- Dismantling the electrical installations
- Maintenance of the electrical installations
Wednesday 16/01.2018

Civil works

- Closing the openings for water and sewage installations in room 1 and in kitchen
- Placing the thermal insulation on the façade walls (Behind Alu-bond)
- placing the thermal insulation below the roof metal sheets two teams
- Wall tiles installation in the kitchen

HVAC works

- Installation of the HVAC canals’ (If possible)

Electrical works

- Installation of power lines in room 1


- Maintenance of the electrical installations

Thursday 17/01.2018

Civil works

- Wall tiles installation in the kitchen


- placing the thermal insulation below the roof metal sheets two teams
- Wall tiles installation in the kitchen

HVAC works

- Installation of the HVAC canals’ (If possible)

Electrical works

- Installation of power lines in room 1


- Maintenance of the electrical installations

Friday 18/01.2018

Civil works

- Wall tiles installation in the kitchen


- placing the thermal insulation below the roof metal sheets two teams
- Wall tiles installation in the kitchen

HVAC works

- Installation of the HVAC canals’ (If possible)

Electrical works
- Installation of power lines in room 1
- Maintenance of the electrical installations