You are on page 1of 105

NANDED WAGHALA CITY MUNICIPAL

CORPORATION, NANDED

Detailed Project Report for


Improvement of Movement Network in Nanded

(Package 3B- Structures)

Volume II
Cost Estimates
February - 2007

IL&FS TRANSPORTATION NETWORKS LIMITED

CONSULTING ENGINEERING SERVICES (I) PRIVATE LIMITED


NEW DELHI MUMBAI KOLKATA
NANDED WAGHALA CITY MUNICIPAL
CORPORATION, NANDED

Detailed Project Report for


Improvement of Movement Network in Nanded

(Package 3B- Structures)

Volume II
Cost Estimates
February - 2007

IL&FS TRANSPORTATION NETWORKS LIMITED

CONSULTING ENGINEERING SERVICES (I) PRIVATE LIMITED


NEW DELHI MUMBAI KOLKATA
CONTENTS
• Summary of Costs

• Bill of Quantities
– Bridge across Godavari River
– RoB at Hingoli Gate

• Rate Analysis

• Measurement Sheets
– Bridge across Godavari River
– RoB at Hingoli Gate
SUMMARY OF COSTS
DPR FOR IMPROVEMENT OF MOVEMENT NETWORKS IN NANDED

SUMMARY OF COST ESTIMATES - PACKAGE 3B (STRUCTURES)

Amount (Rs.)
Sl. Part Description RoB at Hingoli
Godawari Bridge Total
Gate
1 1.0 Preliminary Works 1,547,248.20 1,998,712.00

2 2.0 Foundations & Sub-structures 90,725,538.75 85,132,750.65

3 3.0 Superstructure 90,154,275.67 82,092,241.55

4 4.0 Miscellaneous Items 41,838,560.70 17,358,944.98

5 5.0 Solid Approaches / Reinforced Earth Retaining Wall 122,880,054.00 6,672,347.00

Total Base Cost (from Part 1.0 to 5.0) 347,145,677.32 193,254,996.18 540,400,673.50

Contingencies (@ 5% over 1.0 to 5.0) 17,357,284.00 9,662,750.00 27,020,034.00

Sub-Total Cost including Contingencies 364,502,961.32 202,917,746.18 567,420,707.50

Overhead (@ 8%) - as per MoRTH 29,160,237.00 16,233,420.00 45,393,657.00

Sub-Total Cost including Contingencies & Overhead 393,663,198.32 219,151,166.18 612,814,364.50

Cost Escalation (@ 10% per annum) 39,366,320.00 21,915,117.00 61,281,437.00

GRAND TOTAL COST (including Cont., Overhead & Cost Esc.) 433,029,518.32 241,066,283.18 674,095,801.50
BILL OF QUANTITIES
BOQ

BRIDGE ACRROSS GODAVARI RIVER


SUMMARY OF COST ESTIMATES - PACKAGE 3B (STRUCTURES)

SUMMARY OF COST ESTIMATES - GODAVARI BRIDGE

Sl. Part Description Amount (Rs.)

1 1.0 Preliminary Works 1,547,248.20

2 2.0 Foundations & Sub-structures 90,725,538.75

3 3.0 Superstructure 90,154,275.67

4 4.0 Miscellaneous Items 41,838,560.70

5 5.0 Solid Approaches / Reinforced Earth Retaining Wall 122,880,054.00

Total Base Cost (from Part 1.0 to 5.0) 347,145,677.32

Contingencies (@ 5% over 1.0 to 5.0) 17,357,284.00

Sub-Total Cost including Contingencies 364,502,961.32

Overhead (@ 8%) - as per MoRTH 29,160,237.00

Sub-Total Cost including Contingencies & Overhead 393,663,198.32

Cost Escalation (@ 10% per annum) 39,366,320.00

GRAND TOTAL COST (including Cont., Overhead & Cost Esc.) 433,029,518.32
Improvement of Movemnt Network IN Nananded under JNNURM
Summary of Bill of Quantities for River Bridge on Godavari

Sl. Unit Rate in Amount in


Item No. Item Description Unit Qty
No. (Rs.) (Rs.)
PART - 1. PRELIMINARY WORKS
1 1.01 Clearing and grubbing road land including uprooting all
vegetation, grass, bush shrubs, saplings and trees of girth
upto 300 mm, removal of stumps of trees of girth of all sizes Ha 4.20 16,461.00 69,136.20
including removing stumps of trees cut earlier and disposal of
unserviceable
2 1.02 Installation of a steel portable barricade with horizontal rail
300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal Nos 160.00 1,522.00 243,520.00
rail painted (2 coats) with yellow and white stripes, 150 mm in
wid
4 1.04 Dismantling of structures and sorting of the dismantled
material, disposal of unserviceable material and stacking
serviceable materials as directed by Engineer with all leads -
and lifts etc. complete as per specification and as per site
requirements.
a) Dismantling bricks / stone masonry, Cum. 200.00 138.00 27,600.00
PCC Kerb median -
b) Dismantling of Concrete Structures Cum. 100.00 144.00 14,400.00
Soil Investigation -
5 1.05 Taking one 100 mm bore hole at each foundation location of
ROB proper and one each in approaches on each side by
using double tube boring machine and carrying out tests to -
determine Engineering Properties of soil and to ascertain
rock levels / qualities
a) Boring in all strata excluding -
hard rock. Rmt. 608.00 1,474.00 896,192.00
b) Drilling in hard rock. Rmt. 152.00 1,950.00 296,400.00
PART - 2. FOUNDATIONS & SUBSTRUCTURES -
1 2.01 Excavation for foundation of structures and staircase
including existing pavement surfaces including dewatering,
shoring and strutting as necessary and backfilling the -
trenches with suitable excavated material in layers of 15 to
20 cms and disposing of re
i) a) Soils of all types upto 3m depth Cum. 5,009.00 81.00 405,729.00
including ordinary earth, sand dry / wet soil, marine clay,
boulders, kankars, soft murrum, hard murrum, etc. -

b) Soils of all types greater than 3m depth Cum. 1,711.00 90.00 153,990.00
ii) Excavation foundation of structure in rock by wedging /
chiselling / controlled blasting or line drilling and
mechanical means including shoring and struting as cum 1,249.00 426.00 532,074.00
necessary and disposing of excavated stuff as directed or
stacked etc.complete by engine
2 2.02 Providing Trial Pits to find out the utilities in the proposed
alignment. The Location details shall be submitted by the -
Contractor as directed by the Engineer.
a) Soils of all types upto 3m depth cum 432.00 81.00 34,992.00
including ordinary earth, sand dry / wet soil, marine clay,
boulders, kankars, soft murrum, hard murrum, etc. -

b) Soils of all types greater than 3m depth cum - 95.00 -


3 2.03 Providing and laying in situ M15 grade bedding concrete in
foundation ,annular fillingbelow pile cap including dewatering,
shuttering, mixing in mechanised batch mix plant, Cum. 478.00 2,364.00 1,129,992.00
compacting, curing etc. complete true to level and position as
directed by Enginee
4 2.04 Providing and casting in situ controlled cement concrete M
30 for RCC bored pile including necessary dewatering,
formwork, mixing in mechanised batch mix plant, -
transporting, compacting, vibrating,curing and finishing
including all leads & lifts Includ
1.0 m Dia Pile Rmt - 6,521.00 -
1.2 m Dia pile Rmt 1,450.00 7,385.00 10,708,250.00
1
Improvement of Movemnt Network IN Nananded under JNNURM
Summary of Bill of Quantities for River Bridge on Godavari

Sl. Unit Rate in Amount in


Item No. Item Description Unit Qty
No. (Rs.) (Rs.)
5 2.05 Carrying out load test on any pile as per standard procedure
laid down in the IS:2911 specification including construction
of test cap, dismantling the cap after test and cleaning the -
site and maintaining complete records of load settlement as
directed by
a) Initial Load Test on test pile for 2.5 times the pile for 2.5
times the design load specified in drgs. in non-working
MT 750.00 312.00 234,000.00
areas, in the vicinity ofof the bridge site, including cost of
test pile.
b) Routine pile load test on working piles for 1.5 times the
MT 900.00 300.00 270,000.00
design load specified in the drg.
c) Horizontal pile load test on working piles for 1.5 times the
MT 45.00 5,000.00 225,000.00
design load specified in drgs.
6 2.06 Providing and laying 600 mm thick filter media behind
abutment as per detailed drawing & specifications complete. cum 136.00 333.00 45,288.00

7 2.07 Providing and laying in-situ RCC M30 grade concrete in


foundations of piers, abutments and staircase etc. including
centering, shuttering , mixing in mechanised batch mix plant, Cum. 967.00 2,847.00 2,753,049.00
compaction, curing and dewatering if necessary, excluding
reinforcement as p
8 2.08 Providing and laying M30 grade cement concrete for cast-in-
situ piers, abutments,Retaining Wall ,dirt walland columm of
staircase etc. as per approved design and drawings, with Cum. 3,116.00 4,418.00 13,766,488.00
necessary centering, shuttering with asthetic finishes mixing
in mechanised ba
9 2.09 Providing and laying in situ controlled M30 grade cement
concrete for RCC caps and pedestal over piers and
abutments including necessary scaffolding formwork, Cum 1,294.00 4,528.00 5,859,232.00
centering, mixing in mechanised batch mix plant,
transporting, placing, compacting by mechanical
10 2.10 Providing & fixing in position HYSD Fe415 steel bars of
various diameters for all RCC works in Piles, Piles Caps ,well
steining,well curb,foundations ,Pier, Pier Cap, Abutment wall,
Dirt wall, Pedestals as per detailed design & drawings and
schedule including cutting, bending, hooking the bars,
binding with 18 SWG wires or tack welding (only for piles) MT 935.00 35,491.05 33,184,131.75
and supporting as required with all lifts and leads etc.
complete including all laps, chairs, spaces etc. and cost of all
labour, materials, tools, plants, equipments etc. all complete
as directed by Engineer and as per specification.

11 2.11 Providing and applying one coat of zinc-rich epoxy primer


and two coats of coal tar epoxy paint of reqd. thickness as
per specifications to all concrete surfaces in contact with
earth in foundation and substructure including all cost of
material, labour, transportation and preparing the surfaces by Sqm. 2,620.00 117.00 306,540.00
cleaning, washing, brushing, sand / grit blasting etc.
complete as directed by Engineer and as per specification.
(Paint shall be got tested from approved laboratory).

12 2.13 Dewatering including diversion of stream providing cofferdam


bunds etc. as may be necessary for foundation and other
parts and bailing out and pumping out water below the actual
-
initial natural water level for start of that particular component
till completion of bridge etc. complete as directed by
Enginner
non perenial river cum 5,561.00 191.00 1,062,151.00
perenial river cum - 445.00 -
13 2.14 Sinking of well foundation in all types of soil and murum etc.
which can be removed by grabbing and chiselling with large
scale dewatering or in proper setting of wells including all Rmt 38.00 127,831.00 4,857,578.00
method excepts pneumatic sinking . Diameter =10m and
depth = 20m

2
Improvement of Movemnt Network IN Nananded under JNNURM
Summary of Bill of Quantities for River Bridge on Godavari

Sl. Unit Rate in Amount in


Item No. Item Description Unit Qty
No. (Rs.) (Rs.)
14 2.15 Providing and laying in situ M20 cement concrete in well
steining including compacting by vibrating , rodding ,finishing
cum 995.00 2,527.00 2,514,365.00
and curing etc complete(excluding reinforcement )as directed
by engineer
15 2.16 Providing and laying in situ M25 reinforced cement concrete
well curbs including necessary shuttering compacting by
cum 178.00 3,283.00 584,374.00
vibrating finishing and curing etc. complete (excluding
reinforcement ) as directed by Engineer
16 2.17 Providing fabricating and setting out mild steel cutting edges
for reinforced cement concrete well curbs as shown on the
MT 6.00 38,535.00 231,210.00
detailed drawing etc. complete as directed by Engineer

17 2.18 Providing and laying in situ M30 reinforced cement concrete


well caps / pile caps including necessary shuttering
compacting by vibrating finishing and curing etc. complete cum 1,578.00 2,839.00 4,479,942.00
(excluding reinforcement ) as directed by Engineer

18 2.19 Providing and filling in well with sand /rubble and sand
/shingle and sand including compaction between the top plug
cum 1,721.00 513.00 882,873.00
and bottom plug and in footpath etc.complete as directed by
engineer
19 2.20 Providing and laying in situ M15 reinforced cement concrete
for the bottom plugs of well in dry under water including
compacting by vibrating finishing and curing etc. complete cum 340.00 2,389.00 812,260.00
(excluding reinforcement ) as directed by Engineer

20 2.21 Providing and laying in situ M15 reinforced cement concrete


for the Top plugs of well including compacting by vibrating
cum 26.00 2,255.00 58,630.00
finishing and curing etc. complete (excluding reinforcement )
as directed by Engineer
21 2.22 Providing and installing 6 / 8 mm MS liner for bored-cast-in-
situ concrete piles including applying protective coating as
MT 150.00 37,556.00 5,633,400.00
per drawing and specification and as directed by Engineer
(excluding reinforcement).
PART - 3. SUPERSTRUCTURE -
1 3.01 Providing 12.7 / 15.2 mm nominal dia. high tensile
prestressing steel conforming to low Relaxation prestressing
steel strands as per IS:14268 strands - CI. II of specified MT 196.00 93,334.00 18,293,464.00
ultimate strength, including cutting, cleaning, forming cables
etc and further incl
2 3.02 Providing and laying controlled cement concrete of M40
grade in post-tensioned precast 'I' Girders including
necessary casting yard, casting trough, centering, formwork, Cum 3,901.00 4,625.00 18,042,125.00
mixing by using admixture in mechanised batch mix plant,
transporting, placing, compa
3 3.03 Providing and fixing POT cum PTFE bearing to the true line
and level and in position as per drawings and BS:5400, Sec.
9.1 & 9.2 so as to impart full and even bearing on the seats -
and free movements / restraints as specified including cost of
all material
a) POT fixed bearing -
125 T CAPACITY Nos 144.00 15,125.00 2,178,000.00
b) POT cum PTFE bearing -
125 T CAPACITY Nos 144.00 15,125.00 2,178,000.00
4 3.04 Providing and laying controlled in-situ cement concrete of
M40 grade in RCC deck slab and diaphragm including
necessary scaffolding, centering, formwork, mixing by using Cum. 3,827.00 4,946.00 18,928,342.00
admixture in mechanised batch mix plant, transporting,
placing, compacting by mechani
5 3.06 Providing and fixing in position HYSD Fe415 reinforcing bars
of various diameters for all RCC works of Superstructure as
per detailed design and drawings and schedule including MT 853.00 35,491.05 30,273,865.65
cutting, bending, hooking the bars, binding with 18 SWG
wires, including all
3
Improvement of Movemnt Network IN Nananded under JNNURM
Summary of Bill of Quantities for River Bridge on Godavari

Sl. Unit Rate in Amount in


Item No. Item Description Unit Qty
No. (Rs.) (Rs.)
6 3.09 Providing and carrying out load test on bridge deck with
simulated loading including provision, placing and removal of
loading, supplying, fixing and removing deflection measuring Nos 1.00 100,000.00 100,000.00
instruments etc. complete with platforms for fixing the
instruments etc. co
7 3.10 Providing and laying in-situ RCC M30 grade concrete in waist
slab , beams ,landing slab ,steps including centering,
shuttering, mixing in mechanised batch mix plant, cum 41.00 2,966.00 121,606.00
compaction, curing and dewatering if necessary, excluding
reinforcement as per specificat
8 3.11 Providing and fixing 150 x 100 mm non skidding precast
chequred tiles 25 mm thick of approved quality in traffic
island and where ever necessary in city suburban limit over sqm 149.00 260.89 38,873.02
18 mm thick C.M 1:3 including curing etc.complete as per
drawing and as directed
PART - 4. MISCELLANEOUS ITEMS -
1 4.01 Providing and casting RCC Crash Barrier in M40 controlled
concrete with cast-in-situ or precast members as per detailed
drawings including necessary scaffolding, centering, Rmt. 431.00 3,825.00 1,648,575.00
formwork, mixing by using admixture in mechanised batch
mix plant, transporting,
2 4.02 Providing and laying 100 mm HDPE,DWC pipe as per
IS;14930 part-II mark in true inside the crash barrier and
below footpath for the conduits for electrification and Rmt. 5,706.00 144.00 821,664.00
services including fixtures, specials etc. complete as per
specification and as directe
3 4.03 Providing and laying in-situ M25 grade cement concrete in
RCC Median Verge Kerb, Railing Beam and footpath cover
slab including formwork, transporting, placing, compacting, Cum. 550.00 2,817.00 1,549,350.00
finishing, curing, etc. complete with all leads and lifts as per
drawing & specifi
4 4.04 Providing and fixing in position HYSD Fe415 reinforcing bars
of various diameters for the above all RCC works in Crash
Barrier as per detailed designs and drawings and schedule MT 31.00 35,491.05 1,100,222.55
including cutting, bending, hooking the bars, binding with 18
SWG wires with
5 4.06 Providing and fixing 100 mm dia. G.I. Drainage spouts,
including grating with suitable clean out fixtures including all
No. 216.00 354.00 76,464.00
leads and lifts etc. complete as per specification, design &
drawings and as directed by Engineer.
6 4.08 Providing and fixing 150 mm dia. PVC down take pipes
including cost of all materials, labour, fixing in true line and
level, including bends, fixtures, specials etc. complete with all Rmt. 432.00 320.00 138,240.00
lifts and leads etc. as per specifications and as directed by
Engineer.
7 4.09 Providing and constructing catch pit 0.90 m x 0.45 m x 1.2 m
deep in BB masonry including excavation, backfilling in soil,
100 mm thick M-15 grade PCC below and covered with 100 No. 2.00 2,033.00 4,066.00
mm thick RCC M-25 slab, reinforcement, M.S. covering,
smooth finish from insi
8 4.10 Providing and fixing precast concrete 300 mm dia. pipes,
type NP3, granular and concrete bedding below pipe,
encasing pipe with M-30 concrete, including cost of all Rmt. 30.00 624.00 18,720.00
materials, labour, etc. complete with all lifts and leads etc. as
per specifications and a
9 4.11 Providing and fixing in position elastomeric Stripseal
expansion joint for movement of + and - 40 mm as per
specification and detailed drawing including cost of all Rmt. 377.00 7,523.00 2,836,171.00
materials, fixtures, welding, preparing surface for receiving
joints, testing of all ma

4
Improvement of Movemnt Network IN Nananded under JNNURM
Summary of Bill of Quantities for River Bridge on Godavari

Sl. Unit Rate in Amount in


Item No. Item Description Unit Qty
No. (Rs.) (Rs.)
10 4.12 Providing and applying primer coat using bituminous
emulsion or cut back primer over prepared surface of deck
slab with emulsion preheated to a temperature between 20 - Sqm. 8,559.00 31.00 265,329.00
60OC and applying a uniform coat with the aid of self
propelled bitumen pressure spray
11 4.13 Providing and applying tack coat using bituminous emulsion
or cut back primer over primed / black top surface with
emulsion preheated to a temperature between 20 - 60OC and Sqm. 8,559.00 16.00 136,944.00
applying a uniform coat with the aid of self propelled bitumen
pressure sprayer wi
12 4.14 Providing and laying mastic asphalt water proof coat with
composition of bitumen 30/40 penetration grade conforming
to MOST specification with the bitumen of 14% to 17% -
weight of total mix including cleaning the surface, testing of
materials in approved l
a) 6 mm thick Sqm. - 95.00 -
b) 12 mm thick Sqm. 8,559.00 190.00 1,626,210.00
13 4.15 Providing and laying 40-100 mm thick hot mix hot laid dense
bituminous macadam on prepared surface using 30 - 40
grade bitumen with bitumen content of 4.5% of weight of total Cum. 4,280.00 4,307.00 18,433,960.00
mix including cleaning the surface, providing necessary
aggregate with specified
14 4.16 Providing and laying Bituminous Concrete in a single layer of
25mm to 50 mm compacted thickness on prepared surface
using bitumen of grade approved by the engineer 30-40 Cum 2,140.00 5,090.00 10,892,600.00
grade @ 5.5% of bitumen by weight of mix including
providing necessary aggregates wi
15 4.17 Providing & fixing discontinuous M25 PCC precast kerb
stonesof size 600 x 300 x 1200 mm at a spacing of 1200 mm
c/c on road side parallel to the retaining wall of reinforced No. 400.00 608.42 243,366.15
structure at a distance of 1000 mm from the face of retaining
wall including tran
16 4.18 Providing and fixing four pillars, one at each corner of each of
the bridge of approved architectural design with pedestals to
house the granite tablets as per details approved by the Sqm. 8.00 3,611.00 28,888.00
Corporation, including transportation, placing etc. complete
with all l
17 4.20 Providing & fixing in position 100 mm Dia. A.C. pipes as
weep holes in Abutments and Return Walls completed in all
Nos 100.00 60.00 6,000.00
respect as per specification and as directed by Engineer.

18 4.21 Providing & fixing in position MS Railing over RCC Crash


Barrier, staircase including Support Angle/Fixtures as per
Rmt. 483.00 1,371.00 662,193.00
Detailed Drawing and Specifications and as directed by the
Engineer.
19 4.22 Providing & Fixing Bituminous Filler Pad material 20 mm thk.
Rmt. 571.00 262.00 149,602.00
between two carriageways
20 4.24 Construction of RCC railing of M20 Grade in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of
vertical RCC post not to exceed 1 in 500, centre to centre RM 951.00 1,220.00 1,160,220.00
spacing between vertical post not to exceed 1000 mm,
leaving adequate space
21 4.25 Back filling behind abutment ,wing wall and return wall
cum 226.00 176.00 39,776.00
complete as per drawing and technical specification
22 4.26 Providing and fixing Neoprene bearing as per standard cu.centim
- 1.29 -
specification etc.complete( as per IRC-83 Part-11) eter
PART - 5. SOLID APPROACHES / REINFORCED EARTH RETAINING WALL -
1 5.01 Excavation for foundation of structures including dewatering,
shoring and strutting as necessary and backfilling the
trenches with excavated material in layers of 15 to 20 cms -
and disposing of remaining unsuitable material with all leads
and lifts as dir

5
Improvement of Movemnt Network IN Nananded under JNNURM
Summary of Bill of Quantities for River Bridge on Godavari

Sl. Unit Rate in Amount in


Item No. Item Description Unit Qty
No. (Rs.) (Rs.)
a) Soils of all types including ordinary earth, sand, dry / wet
soil marine clay, boulder, kankar, soft murrum, hard murrum Cum. 58,140.00 81.00 4,709,340.00
etc
2 5.02 Providing and laying in situ PCC M30 grade bedding concrete
below facia element / foundation including dewatering,
shuttering, mixing in mechanised batch mix plant, Cum. 44.00 2,828.00 124,432.00
compacting, curing etc. complete true to level and position as
directed by Engineer and as
3 5.03 Providing & fixing of precast facia elements in RCC M30
grade for reinforced soil embankment for approach returns
and abutment as per specifications given in the Tender with Sqm. 951.00 1,091.00 1,037,541.00
suitable as specified in tender document including all
materials, connections, j
4 5.04 Providing and laying in-situ RCC M-30 grade friction slab /
coping beam on top of facia wall concrete, necessary
shuttering, centering, compaction by vibrating, curing, joints Cum. 207.00 3,074.00 636,318.00
etc.complete in all respect with cast in-situ expansion gap at
50 m interval as
5 5.05 Providing and fixing in position HYSD Fe415 reinforcing bars
of various diameters for the above all RCC works of Friction
Slab as per detailed designs and drawings and schedule MT 20.00 35,491.05 709,821.00
including cutting, bending, hooking the bars, binding with 18
SWG wires with
6 5.06 Providing earth work in embankment by using mechanical
means with approved material obtained from borrow areas
having 4 days soaked CBR equal to or more than 6%, laying Cum 6,541.00 191.00 1,249,331.00
in layers not exceeding 200 mm, breaking clods, dressing to
the required lines, curves
7 5.18 Providing and fixing of mechanically woven Double Twisted
Hexagonal shaped wire mesh Gabian boxes of required
section , Garware steel Gabian or equivalent , Mesh type -
10x12, wires Zn+pvc coated , mesh wire dia.
2.7mm/3.7mm(I.D/O.D), edges of meshes mechan
Gabian boxes - 1.0m height cum 41,360.00 1,863.00 77,053,680.00
Gabian boxes - 0.5m height cum - 2,281.00 -
8 5.19 Backfilling Inside the Gabbion Wall for approach embakment
by using mechanical means with approved material obtained
from borrow areas having 4 days soaked CBR equal to or
more than 6%, laying in layers not exceeding 200 mm,
breaking clods, dressing to the required lines, curves grades,
and watering to OMC and compacting to 95% modified Cum 119,001.00 191.00 22,729,191.00
proctor density with vibratory roller having minimum 80 - 100
kN static weight including all lifts and leads etc. complete as
directed by Engineer and as per specification. including
Excavation ,dewatering etc complete

9 5.20 Ground Improvement by removing unsitable soil and


backfilling with murrum with approved material obtained from
borrow areas having 4 days soaked CBR equal to or more
than 6%, laying in layers not exceeding 200 mm, breaking
clods, dressing to the required lines, curves grades, and
watering to OMC and compacting to 95% modified proctor cum 57,600.00 254.00 14,630,400.00
density with vibratory roller having minimum 80 - 100 kN
static weight including all lifts and leads etc. complete as
directed by Engineer and as per specification. including
Excavation ,dewatering etc complete

Total 347,145,677.32

366,258,627.32

19,112,950.00

6
BOQ

ROB AT HINGOLI GATE


SUMMARY OF COST ESTIMATES - PACKAGE 3B (STRUCTURES)

SUMMARY OF COST ESTIMATES - ROB AT HINGOLI GATE

Sl. Part Description Amount (Rs.)

1 1.0 Preliminary Works 1,998,712.00

2 2.0 Foundations & Sub-structures 85,132,750.65

3 3.0 Superstructure 82,092,241.55

4 4.0 Miscellaneous Items 17,358,944.98

5 5.0 Solid Approaches / Reinforced Earth Retaining Wall 6,672,347.00

Total Base Cost (from Part 1.0 to 5.0) 193,254,996.18

Contingencies (@ 5% over 1.0 to 5.0) 9,662,750.00

Sub-Total Cost including Contingencies 202,917,746.18

Overhead (@ 8%) - as per MoRTH 16,233,420.00

Sub-Total Cost including Contingencies & Overhead 219,151,166.18

Cost Escalation (@ 10% per annum) 21,915,117.00

GRAND TOTAL COST (including Cont., Overhead & Cost Esc.) 241,066,283.18
Improvement of Movemnt Network IN Nananded under JNNURM
Summary of Bill of Quantities for RoB at hingoli gate

Sl. Item No. Item Description Rate in Amount in


Unit Quantity
No. (Rs.) (Rs.)
PART - 1. PRELIMINARY WORKS
1 1.01 Clearing and grubbing road land including uprooting all
vegetation, grass, bush shrubs, saplings and trees of girth
upto 300 mm, removal of stumps of trees of girth of all sizes
including removing stumps of trees cut earlier and disposal Ha 2 16461 32,922.00
of unserviceable materials and stacking of serviceable
materials as directed by Engineer with all leads and lifts etc.
complete as per specification.
2 1.02 Installation of a steel portable barricade with horizontal rail
300 mm wide, 2.5 m in length fitted on a 'A' frame made
with 45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white Nos 620 1522 943,640.00
stripes, 150 mm in width at an angle of 450, 'A' frame
painted with 2 coats of yellow paint, complete as per
IRC:SP:55-2001
3 1.04 Dismantling of structures and sorting of the dismantled
material, disposal of unserviceable material and stacking
serviceable materials as directed by Engineer with all leads Cum. 300 138 41,400.00
and lifts etc. complete as per specification and as per site
requirements.Dismantling PCC Kerb Median
b) Dismantling of Concrete Structures Cum. 144 -
Ref: Sr.No. 1.04 b) Of RA as per MORT&H -
4 1.05 Soil Investigation -
Taking one 100 mm bore hole at each foundation location
of ROB proper and one each in approaches on each side by
using double tube boring machine and carrying out tests to
determine Engineering Properties of soil and to ascertain
-
rock levels / qualities of strata at each location and
submitting the soil investigation report with necessary
interpretation of the test results as directed by Engineer and
as per specification. a
a) Boring in all strata excluding hard rock. Rmt. 500 1474 737,000.00
b) Drilling in hard rock. Rmt. 125 1950 243,750.00
PART - 2. FOUNDATIONS & SUBSTRUCTURES
1 2.01 Excavation for foundation of structures and staircase
including existing pavement surfaces including dewatering,
shoring and strutting as necessary and backfilling the
trenches with suitable excavated material in layers of 15 to
20 cms and disposing of remaining unsuitable material with -
all lifts and lead as directed and preparation of bed for
concreting of foundations etc. complete as directed by
Engineer and as per specification.

i) a) Soils of all types upto 3m depth Cum. 4500 81 364,500.00


including ordinary earth, sand dry / wet soil, marine clay,
boulders, kankars, soft murrum, hard murrum, etc. -

b) Soils of all types greater than 3m depth Cum. 90 -


ii) Excavation foundation of structure in rock by wedging /
chiselling / controlled blasting or line drilling and
mechanical means including shoring and struting as
Cum. 300 426 127,800.00
necessary and disposing of excavated stuff as directed or
stacked etc.complete by engineer with all leads and lifts .

2 2.02 Providing Trial Pits to find out the utilities in the proposed
alignment. The Location details shall be submitted by the
-
Contractor as directed by the Engineer.

a) Soils of all types upto 3m depth Cum. 1300 81 105,300.00


including ordinary earth, sand dry / wet soil, marine clay,
boulders, kankars, soft murrum, hard murrum, etc. -

1
Sl. Item No. Item Description Rate in Amount in
Unit Quantity
No. (Rs.) (Rs.)
b) Soils of all types greater than 3m depth Cum. 0 90 -
3 2.03 Providing and laying in situ M15 grade bedding concrete in
foundation, Annular filling bollow pile cap including
dewatering, shuttering, mixing in mechanised batch mix
Cum. 268 2364 633,552.00
plant, compacting, curing etc. complete true to level and
position as directed by Engineer and as per specification.

3 2.04 Providing and casting in situ controlled cement concrete M


30 for RCC bored pile including necessary dewatering,
formwork, mixing in mechanised batch mix plant,
transporting, compacting, vibrating,curing and finishing
including all leads & lifts Including Chipping and dressing of
the RCC piles upto cut-off level (Min. 1D) including cleaning -
of reinforcement and removal of dismantled materials
(Excluding Reinforcement) complete as per detailed
specifications. Note: 10% additional cement to be added
over and above the quantities required as per designs.

1.0 m Dia Pile Rmt 3600 6521 23,475,600.00


1.2 m Dia pile Rmt 900 7385 6,646,500.00
4 2.05 Carrying out load test on any pile as per standard procedure
laid down in the IS:2911 specification including construction
of test cap, dismantling the cap after test and cleaning the
-
site and maintaining complete records of load settlement as
directed by Engineer and as per specification, and
submission of records.
a) Initial Load Test on test -
pile for 2.5 times the design load specified in Drawings -
1.0 m Dia Pile (2% of 252 piles in total) = 6 Nos. ( Load
MT 3000 312 936,000.00
per Pile = 200 t x 2.5 = 500.0 t) x 6 Nos.
1.2 m Dia Pile (2% of 64 piles in total) = 2 Nos.( Load per
MT 1500 312 468,000.00
Pile = 300 t x 2.5 = 750.0 t) x 2 Nos.
b) Routine pile load test on -
pile for 1.5 times the design load specified in Drawings -
1.0 m Dia Pile (2% of 252 piles in total) = 6 Nos.( Load
MT 1800 300 540,000.00
per Pile = 200 t x 1.5 = 300.0 t) x 6 Nos. =
1.2 m Dia Pile (2% of 64 piles in total) = 2 Nos.( Load per
MT 900 300 270,000.00
Pile = 300 t x 1.5 = 450.0 t) x 2 Nos.
c) Horizontal pile load test on -
pile for 1.5 times the design load specified in Drawings -
1.0 m Dia Pile (2% of 252 piles in total) = 6 Nos.( Load
MT 180 5000 900,000.00
per Pile = 20 t x 1.5 =30.0 t) x 6 Nos. =
1.2 m Dia Pile (2% of 64 piles in total) = 2 Nos. ( Load
MT 90 5000 450,000.00
per Pile = 30 t x 1.5 = 45.0 t) x 2 Nos.
5 2.06 Providing and laying 600 mm thick filter media behind
abutment as per detailed drawing & specifications complete. Cum 130 333 43,290.00

6 2.08 Providing and laying M30 grade cement concrete for cast-in-
situ piers, abutments,Retaining Wall ,dirt walland columm of
staircase etc. as per approved design and drawings, with
necessary centering, shuttering with asthetic finishes mixing
in mechanised batch mix plant, scaffolding, transporting, Cum. 1040 4418 4,594,720.00
placing, compacting by mechanical vibrators, finishing,
curing etc. complete excluding reinforcement as directed by
Engineer and as per specification.

7 2.09 Providing and laying in situ controlled M30 grade cement


concrete for RCC caps and pedestal over piers and
abutments including necessary scaffolding formwork,
centering, mixing in mechanised batch mix plant,
Cum 685 4528 3,101,680.00
transporting, placing, compacting by mechanical vibrators,
finishing and curing etc. complete excluding reinforcement,
as directed by Engineer and as per specification.

2
Sl. Item No. Item Description Rate in Amount in
Unit Quantity
No. (Rs.) (Rs.)
8 2.10 Providing & fixing in position HYSD Fe415 steel bars of
various diameters for all RCC works in Piles, Piles Caps
,well steining,well curb,foundations ,Pier, Pier Cap,
Abutment wall, Dirt wall, Pedestals as per detailed design &
drawings and schedule including cutting, bending, hooking
the bars, binding with 18 SWG wires or tack welding (only MT 913 35491 32,403,328.65
for piles) and supporting as required with all lifts and leads
etc. complete including all laps, chairs, spaces etc. and cost
of all labour, materials, tools, plants, equipments etc. all
complete as directed by Engineer and as per specification.

9 2.11 Providing and applying one coat of zinc-rich epoxy primer


and two coats of coal tar epoxy paint of reqd. thickness as
per specifications to all concrete surfaces in contact with
earth in foundation and substructure including all cost of
material, labour, transportation and preparing the surfaces Sqm. 1800 117 210,600.00
by cleaning, washing, brushing, sand / grit blasting etc.
complete as directed by Engineer and as per specification.
(Paint shall be got tested from approved laboratory).

10 2.18 Providing and laying in situ M30 reinforced cement concrete


well caps / pile caps including necessary shuttering
compacting by vibrating finishing and curing etc. complete cum 2680 2839 7,608,520.00
(excluding reinforcement ) as directed by Engineer

11 2.22 Providing and installing 6 / 8 mm MS liner for bored-cast-in-


situ concrete piles including applying protective coating as
MT 60 37556 2,253,360.00
per drawing and specification and as directed by Engineer
(excluding reinforcement).
PART - 3. SUPERSTRUCTURE -
1 3.01 Providing 12.7 / 15.2 mm nominal dia. high tensile
prestressing steel conforming to low Relaxation
prestressing steel strands as per IS:14268 strands - CI. II of
specified ultimate strength, including cutting, cleaning,
forming cables etc and further including providing and laying
corrugated HDPE sheathing of specified dia., anchorages,
stagewise stressing, grouting testing of materials Class II
MT 147 93334 13,720,098.00
for I- Girder / Box Girder and specified dia., anchorages,
stagewise stressing, grouting, testing of materials and all
enabling work for post tensioning of steel etc. including
provision of coupler wherever requiredcomplete including all
lifts and leads as per specification and approved design and
drawings and as directed by Engineer.

2 3.02 Providing and laying controlled cement concrete of M40


grade in post-tensioned precast 'I' Girders including
necessary casting yard, casting trough, centering,
formwork, mixing by using admixture in mechanised batch
mix plant, transporting, placing, compacting by mechanical
vibrators, finishing, curing etc. complete including inserts, if
Cum 2802 4625 12,959,250.00
any, epoxy mortar filling, lifting, shifting, transporting 'I'
girder to the actual pier location and erecting in correct
alignment on temporary bearings over the pier caps etc.
complete as directed by Engineer and as per specification,
excluding reinforcement and HTS strands.

3
Sl. Item No. Item Description Rate in Amount in
Unit Quantity
No. (Rs.) (Rs.)
3 3.03 Providing and fixing POT cum PTFE bearing to the true line
and level and in position as per drawings and BS:5400, Sec.
9.1 & 9.2 so as to impart full and even bearing on the seats
and free movements / restraints as specified including cost
of all materials, fixtures, preparing surface for receiving
bearings, grouting of sleeves in pier caps / superstructures
-
with non-shrink high early strength grout of flowable
consistency, load testing of all bearings as per design and
drawings and specification, removing clamps provided for
transportation and handling etc. complete including all leads
and lifts as directed by Engineer.

a) POT fixed bearing -


2) 180 Ton capacity each Nos 66 12100 798,600.00
3) 200 Ton Capacity each Nos 6 24200 145,200.00
4) 260 Ton capacity each Nos 4 31460 125,840.00
b) POT cum PTFE bearing -
2) 180 Ton capacity each Nos 126 12100 1,524,600.00
3) 200 Ton Capacity each Nos 6 24200 145,200.00
4) 260 Ton capacity each Nos 4 31460 125,840.00
4 3.04 Providing and laying controlled in-situ cement concrete of
M40 grade in RCC deck slab and diaphragm including
necessary scaffolding, centering, formwork, mixing by using
admixture in mechanised batch mix plant, transporting,
Cum. 3940 4946 19,487,240.00
placing, compacting by mechanical vibrators finishing and
curing etc. complete as per specification and as directed by
Engineer, excluding reinforcement.

5 3.05 Providing and laying controlled in-situ cement concrete of


M40 grade in Box Girders including necessary centering,
formwork, mixing by Using Admixture in mechanised batch
mix plant, transporting, placing, compacting by mechanical
vibrators, post threading of cables, finishing, curing etc. Cum. 470 5867 2,757,490.00
complete including inserts if any, epoxy mortar filling in
anchorages, etc. complete as directed by Engineer and as
per specification, excluding reinforcement and HTS strands.

6 3.06 Providing and fixing in position HYSD Fe415 reinforcing


bars of various diameters for all RCC works of
Superstructure as per detailed design and drawings and
schedule including cutting, bending, hooking the bars,
binding with 18 SWG wires, including all laps, chairs, MT 851 35,491.05 30,202,883.55
spacers etc. and cost of all labour, materials, tools, plants,
equipment, supporting as required with all lifts and leads
etc. all complete as per specification and as directed by
Engineer.
7 3.07 Providing and applying one coat Epoxy Phenolic primer of
DFT 50 micron and two coats of Epoxy Phenolic coating of
DFT 100 microns each or any other equivalent epoxy
coating system to all concrete surfaces exposed to
atmosphere in superstructure including cost of material,
Sqm. 0 132 -
labour, transportation, scaffolding and preparing the
surfaces by cleaning, washing, brushing, sand / grit blasting
etc. complete and as directed by Engineer and as per
specification. (Paint shall be got approved from Engineer
and tested from approved laboratory).
8 3.08 Providing and applying 3 coats of water based cement paint
of approved quality to the inner concrete surfaces of Box
Girder in superstructure including cost of all materials,
labour, transportation, scaffolding and preparing the
Sqm. 0 114 -
surfaces by cleaning, washing, brushing, sand / grit blasting
etc. complete, as directed by Engineer and as per
specification. (Paint shall be got tested from approved
laboratory).

4
Sl. Item No. Item Description Rate in Amount in
Unit Quantity
No. (Rs.) (Rs.)
9 3.09 Providing and carrying out load test on bridge deck with
simulated loading including provision, placing and removal
of loading, supplying, fixing and removing deflection
measuring instruments etc. complete with platforms for
Nos 1 100000 100,000.00
fixing the instruments etc. complete as per the details
supplied and specification and as directed by Engineer and
including submission of required results in triplicate after
satisfactory completion of the load test.
PART - 4. MISCELLANEOUS ITEMS -
1 4.01 Providing and casting RCC Crash Barrier in M40 controlled
concrete with cast-in-situ or precast members as per
detailed drawings including necessary scaffolding,
centering, formwork, mixing by using admixture in
mechanised batch mix plant, transporting, placing, Rmt. 1530 3825 5,852,250.00
compacting, finishing, curing, etc. complete including
providing and fixing of inserts if any with all leads and lifts
as per drawing & specification and as directed by Engineer,
excluding reinforcement.
2 4.02 Providing and laying 100 mm HDPE pipe in true line and
level inside the crash barrier and drain for the conduits for
electrification and services including fixtures, specials etc. Rmt. 1530 144 220,320.00
complete as per specification and as directed by Engineer.

3 4.03 Providing and laying in-situ M25 grade cement concrete in


RCC Median Verge Kerb, Railing Beam and footpath cover
slab including formwork, transporting, placing, compacting,
Cum. 185 2817 521,145.00
finishing, curing, etc. complete with all leads and lifts as per
drawing & specification and as directed by Engineer.(
Excluding Reinforcement)
4 4.04 Providing and fixing in position HYSD Fe415 reinforcing
bars of various diameters for R.C.C. Crash Barrier, Median
Kerbs as per detailed designs and drawings and schedule
including cutting, bending, hooking the bars, binding with 18
SWG wires with all laps, chairs, spacers etc. and cost of all MT 9.5 35,491.05 337,164.98
labour, materials, tools, plants, equipments, supporting as
required with all lifts and leads etc. all complete as per
specification and as directed by Engineer.

5 4.06 Providing and fixing 100 mm dia. G.I. Drainage spouts,


including grating with suitable clean out fixtures including all
leads and lifts etc. complete as per specification, design & No. 339 354 119,829.00
drawings and as directed by Engineer.

6 4.07 Providing and fixing 150 mm diameter PVC longitudinal


runner pipes / under drain along soffit of deck slab including
cost of all materials, labour, fixing in true line and level,
Rmt. 1010 320 323,040.00
including bends, fixtures, specials etc. complete with all lifts
and leads etc. as per specifications and as directed by
Engineer.
7 4.08 Providing and fixing 150 mm dia. PVC down take pipes
including cost of all materials, labour, fixing in true line and
level, including bends, fixtures, specials etc. complete with Rmt. 940 320 300,800.00
all lifts and leads etc. as per specifications and as directed
by Engineer.
8 4.11 Providing and fixing in position elastomeric Stripseal
expansion joint for movement of + and - 40 mm as per
specification and detailed drawing including cost of all
materials, fixtures, welding, preparing surface for receiving
Rmt. 172 7523 1,293,956.00
joints, testing of all materials in approved laboratory
including all leads and lifts etc. complete in deck slab and
crash barrier at the joints as per specification, drawings and
as directed by Engineer.

5
Sl. Item No. Item Description Rate in Amount in
Unit Quantity
No. (Rs.) (Rs.)
9 4.12 Providing and applying primer coat using bituminous
emulsion or cut back primer over prepared surface of deck
slab with emulsion preheated to a temperature between 20 -
60OC and applying a uniform coat with the aid of self
propelled bitumen pressure sprayer with self heating
Sqm. 7580 31 234,980.00
arrangement and spraying bar with nozzles of constant
volume for pressure system at 10 kg/10 sqm including all
materials, labour, machinery etc. complete with all leads
and lifts as directed by Engineer and as per specification.

10 4.13 Providing and applying tack coat using bituminous emulsion


or cut back primer over primed / black top surface with
emulsion preheated to a temperature between 20 - 60O
and applying a uniform coat with the aid of self propelled
bitumen pressure sprayer with self heating arrangement and
Sqm. 7580 16 121,280.00
spraying bar with nozzles of constant volume for pressure
system at 5 kg/10 sqm including all materials, labour,
machinery etc. complete with all leads and lifts as directed
by Engineer and as per specification.

11 4.14 Providing and laying mastic asphalt water proof coat with
composition of bitumen 30/40 penetration grade conforming
to MOST specification with the bitumen of 14% to 17%
weight of total mix including cleaning the surface, testing of -
materials in approved laboratory etc. complete on the deck
slab of the flyover as required and as directed by Engineer.

a) 6 mm thick Sqm. 95 -
b) 12 mm thick Sqm. 7580 190 1,440,200.00
12 4.15 Providing and laying 40-100 mm thick hot mix hot laid dense
bituminous macadam on prepared surface using 30 - 40
grade bitumen with bitumen content of 4.5% of weight of
total mix including cleaning the surface, providing necessary
aggregate with specified gradation, mixing with mechanical
means in hot mix plant of suitable capacity of preferably
batch mix type and electronically controlled mixing to the
specified temperature, transporting and laying the mix with
self propelled paver finisher with electronic sensor device
Cum. 580 4307 2,498,060.00
and initial compaction with min. 80 - 100 kN static weight
vibratory roller / pneumatic tyred roller having min. 150 - 250
kN weight having a tyre pressure of at least 0.7 Mpa and
finished with min. 60 - 80 kN weight smooth wheeled
tandem roller to achieve desired density including all
materials, labour, machinery etc. complete with all leads
and lifts as per specification and as directed by Engineer,
excluding tack coat.

13 4.16 Providing and laying Bituminous Concrete in a single layer


of 25mm to 50 mm compacted thickness on prepared
surface using bitumen of grade approved by the engineer
30-40 grade @ 5.5% of bitumen by weight of mix including
providing necessary aggregates with specified gradation
mixing with mechanical means in hot mix plant of suitable
capacity of batch mix type and electronically controlled
mixing to the specified temperature, transporting and laying
the mix with self propelled paver finisher with electronic
sensor device in full width and initial compaction with Cum 290 5090 1,476,100.00
minimum 80 - 100 KN static weight smooth wheeled roller
followed by intermediate rolling with minimum 80 - 100 KN
static weight vibratory roller / pneumatic tyred roller having
minimum 150 - 250 KN weight having a tyre pressure of
atleast 0.7 MPa and finished with minimum 60 - 80 KN
weight smooth wheeled tandem roller to achieve desired
density including all material, labour, machinery with all
leads and lifts etc. complete (excluding tack coat) and
including cement filler @2% by weight of mix.
6
Sl. Item No. Item Description Rate in Amount in
Unit Quantity
No. (Rs.) (Rs.)
14 4.20 Providing & fixing in position 100 mm Dia. A.C. pipes as
weep holes in Abutments and Return Walls completed in all
Nos 48 60 2,880.00
respect as per specification and as directed by Engineer.

15 4.21 Providing & fixing in position MS Railing over RCC Crash


Barrier including Support Angle/Fixtures as per Detailed
Rmt. 1530 1371 2,097,630.00
Drawing and Specifications and as directed by the
Engineer.
16 4.22 Providing & Fixing Bituminous Filler Pad material 20 mm
Rmt. 505 262 132,310.00
thk. between two carriageways
17 4.26 Providing and fixing Neoprene bearing as per standard
cm3 300000 1.29 387,000.00
specification etc.complete( as per IRC-83 Part-11)
PART - 5. SOLID APPROACHES / REINFORCED EARTH RETAINING WALL -
1 5.01 Excavation for foundation of structures including
dewatering, shoring and strutting as necessary and
backfilling the trenches with excavated material in layers of
15 to 20 cms and disposing of remaining unsuitable material
-
with all leads and lifts as directed and preparation of bed
for concreting of foundations etc. complete as directed by
Engineer and as per specification.

a) Soils of all types including ordinary earth, sand dry / wet


soil, marine clay, boulders, kankars, soft boulders, kankars, Cum. 175 81 14,175.00
soft etc
2 5.02 Providing and laying in situ PCC M30 grade bedding
concrete below facia element / foundation including
dewatering, shuttering, mixing in mechanised batch mix
Cum. 565 2828 1,597,820.00
plant, compacting, curing etc. complete true to level and
position as directed by Engineer and as per specification.

3 5.03 Providing & fixing of precast facia elements in RCC M30


grade for reinforced soil embankment for approach returns
and abutment as per specifications given in the Tender with
suitable as specified in tender document including all
materials, connections, joints, fittings and erection of facia
and reinforcing etc. complete in all respect, as directed by
Engineer and as per specification, including casting and Sqm. 2210 1091 2,411,110.00
erection of PC units along with necessary insitu concrete
works for foundations as well as coping and providing
weepholes, perforated drain pipes behind the wall for
necessary drainage arrangement etc. complete as
specified/manufacturer's requirement.

4 5.04 Providing and laying in-situ RCC M-30 grade friction slab /
coping beam on top of facia wall concrete, necessary
shuttering, centering, compaction by vibrating, curing, joints
etc.complete in all respect with cast in-situ expansion gap at Cum. 400 3074 1,229,600.00
50 m interval as directed by Engineer and as per
specification and drawing, excluding reinforcement.

5 5.05 Providing and fixing in position HYSD Fe415 reinforcing


bars of various diameters for the above all RCC works of
Friction Slab as per detailed designs and drawings and
schedule including cutting, bending, hooking the bars,
binding with 18 SWG wires with all laps, chairs, spacers MT 40 35491 1,419,642.00
etc. and cost of all labour, materials, tools, plants,
equipments, supporting as required with all lifts and leads
etc. all complete as per specification and as directed by
Engineer.
Total 193,254,996.18

7
RATE ANALYSIS
DEVELOPMENT OF CITY ROADS IN NANDED UNDER JNNURM
RATES OF MATERIALS

*Allowed Royalty Rates


Rates of Material As per DSR (06-07) Max.Lead Lead Lead Charges charges including

lead/Royalty
Sr.No. Material Unit Rate in Km in Km in Rs in Rs in Rs

1 Sand Per cum 206 18 13 149.32 17.67 372.99

Metal

2 40 mm Per cum 303 18 18 187.46 17.67 508.13

3 25 mm Per cum 303 18 18 187.46 17.67 508.13

4 20 mm Per cum 303 18 18 187.46 17.67 508.13

5 12 mm Per cum 303 18 18 187.46 17.67 508.13

6 10 mm Per cum 303 18 18 187.46 17.67 508.13

7 6 mm Per cum 303 18 18 187.46 17.67 508.13

8 Stone dust Per cum 275 18 18 187.46 17.67 480.13

Source : As per schedule of rates 2006-2007 (P.W.D.Nanded)


* : 5 Km initial lead Built in SSR Deducted
Rates of As per Market
Material Rate

Sr.No. Material Unit Rate

1 *Cement Per MT 3,990.00

2 *Bitumen
Grade 30/ 40
Bulk Per MT 24,693.00
*Modified
3 Bitumen
PMB 40 Per MT 28,959.00

Source : Rates collected from authorized Dealers in Nanded

* : Inclusive of all taxes


D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Sec 1 Preliminary Works
1.01 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes,
shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier
and disposal of unserviceable materials and stacking of serviceable material to be
used or auctioned, up to a lead of 1000 metres including removal and disposal of top
organic soil not exceeding 150 mm in thickness.

By Mechanical Means
In area of light jungle
a) Labour
Mate day 0.160 130.00 20.8
Mazdoor day 4.000 120.00 480.0
b) Machinery
Dozer 80 HP with attachment for removal of trees & stumps hour 10.000 1423.00 14230
Tractor-trolley hour 1.000 234.00 234.00
c) Contractor's profit @ input on (a+b) 1496.48
Rate per Hectare = a+b+c 16461.28
say 16461

1.02 Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in
length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in
height, horizontal rail painted (2 coats) with yellow and white stripes, 150 mm in width
at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 130.00 2.60
Mazdoor day 0.250 120.00 30.00
Painter day 0.500 130.00 65.00
Welder day 0.250 130.00 32.50
b) Material
Angle iron 45 x 45 x 5 mm kg 25.000 30.00 750.00
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 30.00 450.00
Paint litre 0.500 105.00 52.50
Add 2 per cent of cost of steel for welding consumables, nuts & bolts and drilling
1.10
holes
c) Contractor's profit @ input on (a+b) 138.37
Rate per barricade = a+b+c 1522.07
say 1522

1.03 Supplying and fixing the necessary sign boards as per site requirements and as
directed by Engineer.
a) Information sign boards
As per DSR 2005-06( Page No.183 Sr.No. 772 ) Nos 10000
Add Corporation Charges @5% 500
Total 10500

b) Cautionary sign board


As per DSR 2005-06( Page No.180 Sr.No. 766 ) Nos 3500
Add Corporation Charges @5% 175
Total 3675

c) Mandatory and directional sign boards


As per DSR 2005-06( Page No.181 Sr.No. 769 ) Nos 3275
Add Corporation Charges @5% 164
Total 3439

1
Sr No Description Unit Quantity Rate Rs Cost Rs
1.03 d) Road Delineators
Supplying and installation of delineators (road way indicators, hazard markers, object
markers), 80-100 cm high above ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels
at the top, buried or pressed into the ground and conforming toIRC-79 and the
drawings.
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 130.00 5.20
Mazdoor for fixing day 1.000 120.00 120.00
b) Material 30.000 550.00 16500.00
Cost of approved type of delineators from ISI certified firm as per the standard
each 1650.00
drawing given in IRC - 79
Add 10 per cent cost of material for installation 831.26
c) Contractor's profit @ 10 % on (a+b) 1910.65
Cost for 30 Nos. delineators = (a+b+ c) 21017.11
Rate per delineators = (a+b+c) /30 say 701

1.03 e) Traffic Cone


Provision of red fluorescent with white reflective sleeve traffic cone made of low
density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm
and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873
Unit = Running metre
Taking output = 68 Nos.
a) Labour
Mate day 0.020 130.00 2.60
Mazdoor day 0.500 120.00 60.00
b) Material
Traffic cones with 150 mm reflective sleeve each 68.000 600.00 40800.00
c) Machinery
Tractor-trolley hour 0.100 234.00 23.40
d) Contractor's profit @ input on (a+b+c) 4088.60
Cost for 68 Nos. = a+b+c+d 44974.60
Rate per metre = (a+b+c+d)/68 661.39
say 661
1.04 a) Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all lifts and lead of
1000 metres
Unit = cum
Taking output = 1.25 cum
Brick ,Masonary
In cement mortar
a) Labour
Mate day 0.030 130.00 3.90
Mazdoor for dismantling, loading and unloading day 0.750 120.00 90.00
b) Machinery
Tractor-trolley hour 0.270 234.00 63.18
c) Contractor's profit @ input on (a+b) 15.71
Cost for 1.25 cum = a+b+c 172.79
Rate per cum = (a+b+c)/ 1.25 138.23
say 138

1.04 b) Dismantling of flexible pavements , Cement Concrete Structure and Footpath and
disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable
and unserviceable materials separately
Unit = cum
Taking output = 1 cum
2
Sr No Description Unit Quantity Rate Rs Cost Rs
By Mechanical Means
Bituminous course
a) Labour
Mate day 0.010 130.00 1.30
Mazdoor day 0.300 120.00 36.00
b) Machinery
Tractor-trolley hour 0.380 234.00 88.92
Farm tractor with ripper @ 60 cum per hour hour 0.017 252.00 4.28
c) Contractor's profit @ input on (a+b) 13.05
Rate per cum = a+b+c 143.55
say 144
1.05 Taking one 100 mm bore hole at each foundation location of ROB proper and one
each in approaches on each side by using double tube boring machine and carrying
out tests to determine Engineering Properties of soil and to ascertain rock levels /
qualities of strata at each location and submitting the soil investigation report with
necessary interpretation of the test results as directed by Engineer and as per
specification.
a) Boring in all strata excluding
hard rock.
As per DSR 2005-06( Page No.213 Sr.No. 16 ) Rmt 1404
Add Corporation Charges @5% 70.2
Total 1474
b) Drilling in hard rock.
As per DSR 2005-06( Page No.213 Sr.No. 18 ) Rmt 1857
Add Corporation Charges @5% 92.85
Total 1950

3
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Sec 2 Foundation and Substructures
2.01 Excavation for Structures
Earth work in excavation of foundation of structures as per drawing and
technical specification, including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.
Unit = cum
Taking output = 10 cum
Depth upto 3 m
a) Labour
Mate day 0.14 140.00 19.60
Mazdoor day 3.50 110.00 385.00
c) Contractor's profit @ 10% on (a+b) 40.46
1. Cost of dewatering may be added 10 per cent of labour cost . 40.46
Cost for 10 cum = a+b+c 485.52
Rate per cum = (a+b+c)/10 48.55
The cost of shoring and shuttering, may be added @ 1 per cent on cost 0.49
of excavation for open foundation.
Disposing Of Unsuitable Material Upto 3Km and lift 32.00
Rate per cum 81.04
say 81.00
Depth Above 3 m
a) Labour
Mate/Supervisor day 0.18 140.00 25.20
Mazdoor day 4.50 110.00 495.00
b) Contractor's profit @10% on (a) 52.02
Cost of dewatering may be added where required upto 15 per cent of 78.03
labour cost.
Cost for 10 cum = a+b+c 572.22
Rate per cum = (a+b+c)/10 57.22
The cost of shoring and shuttering, may be added @ 1 per cent on cost 0.57
of excavation for open foundation.
Disposing Of Unsuitable Material Upto 3Km and lift 32.00
Rate per cum 89.80
say 90.00

Plain/Reinforced Cement Concrete in Open Foundation complete as per


2.03
Drawing and Technical Specifications.
PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.70 3990.00 18753.00
Coarse sand cum 6.75 372.99 2517.68
20 mm Aggregate cum 8.10 508.13 4115.85
10 mm Aggregate cum 5.40 508.13 2743.90
b) Labour
Mate day 0.86 140.00 120.40
Mason day 1.50 195.00 292.50
Mazdoor day 20.00 110.00 2200.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00
Generator 63 KVA hour 6.00 240.00 1440.00
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2206.00
d) Add Contractors Profit @ 10 % 2370.59
Cost for 15 cum = a+b+c+d 35453.93
Rate per cum = (a+b+c+d)/15 2363.60
say 2364.00

1
Sr No Description Unit Quantity Rate Rs Cost Rs
2.04 RCC M30 Pile 1M / 1.2M dia
Using Batching Plant, Transit Mixer
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 53.50 3990.00 213480.96
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
Admixture Kg 172.80 80.00 13824.00
b) Labour
Mate day 0.88 140.00 123.20
Mason day 3.00 195.00 585.00
Mazdoor day 18.00 110.00 1980.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in tonne.km 300L 6.00 9000.00
Kilometer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2813.00
Add 5 per cent of cost of material and labour towards cost of forming 15250.63
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe..
d) Contractor's profit @ 10% on (a+b+c) 27770.38
cost of 120 cum = a+b+c+d 380493.67
Rate per cum = (a+b+c+d)/120 3170.78
say 3171.00

Bored cast-in-situ M30 grade R.C.C. Pile excluding Reinforcement


complete as per Drawing and Technical Specifications and removal of
excavated earth with all lifts and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
RCC Grade M30 cum 7.85 3170.78 24890.63
Rate for concrete may be adopted same as for bottom plug vide
item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia. 1244.53
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power unit and hour 7.80 3525.00 27495.00
complete accessories including shifting from one bore location to
another.(Extra 30% added for embedment in rock)
Hire and running charges of light crane for lowering reinforcement hour 0.50 230.00 115.00
cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 520.00 208.00
Tipper 5.5 cum capacity for disposal of muck from pile bore hole hour 0.40 200.00 80.00
Bentonite kg 350.00 20.00 7000.00
c) Labour
Mate/Supervisor day 0.16 130.00 20.80
Mazdoor day 4.00 120.00 480.00
Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 120.00 120.00
d) Contractor's profit @10% on (b+c) 3551.88
Cost for 10 m = a+b+c+d 65205.84
Rate per metre (a+b+c+d)/10 6520.58
6521.00

2
Sr No Description Unit Quantity Rate Rs Cost Rs
Bored cast-in-situ M30 grade R.C.C. Pile excluding Reinforcement
complete as per Drawing and Technical Specifications and removal of
excavated earth with all lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 10 m
a) Materials
RCC Grade M30 cum 10.17 3170.78 32246.84
Rate for concrete may be adopted same as for bottom plug vide
item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia. 1612.34
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power unit and hour 7.80 3525.00 27495.00
complete accessories including shifting from one bore location to
another.(Extra 30% added for embedment in rock)
Hire and running charges of light crane for lowering reinforcement hour 0.50 230.00 115.00
cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 520.00 260.00
Tipper 5.5 cum capacity for disposal of muck from pile bore hole hour 0.50 200.00 100.00
Bentonite kg 385.00 20.00 7700.00
c) Labour
Mate/Supervisor day 0.18 130.00 23.40
Mazdoor day 4.50 120.00 540.00
Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 120.00 120.00
d) Contractor's profit @10% on (b+c) 3635.34
Cost for 10 m = a+b+c+d 73847.92
Rate per metre (a+b+c+d)/10 7384.79
say 7385.00

Pile Load Test on single Vertical Pile in accordance with IS:2911(Part-IV)


2.05
Unit = 1 MT
Taking output = 1 MT
a) Initial load test tonne 600.00 300.00 180000.00
Including The cost of pile 7385.00
Rate per MT=a/600 312.00

b) routine load test tonne 375.00 300.00 112500.00


Rate per MT=b/375 300.00

c) Lateral load test tonne 20.00 5000.00 100000.00


Rate per MT=c/20 5000.00

2.06 Providing and laying 600 mm thick filter media behind abutment as per
detailed drawing & specifications complete.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 130.00 41.60
Mazdoor for filling, watering, ramming etc. day 7.00 120.00 840.00
Mazdoor (Skilled) day 1.00 125.00 125.00
b) Material
Filter media of stone aggregate conforming to clause 2504.2.2. of cum 12.00 167.65 2011.80
MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 200.00 12.00
d) Contractor's profit @10% on (a+b+c) 303.04
cost for 10 cum of Fiter Media = a+b+c+d 3333.44
3
Sr No Description Unit Quantity Rate Rs Cost Rs
Rate per cum = (a+b+c+d)/10 333.34
say 333.00

2.07 RCC Grade M30 (Pile caps, Foundation)


Unit = cum
Taking output = 15 cum

Using Batching Plant, Transit Mixer


a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 140.00 117.60
Mason day 3.00 195.00 585.00
Mazdoor for concreting day 18.00 120.00 2160.00
Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 120.00 120.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 125 KVA hour 6.00 450.00 2700.00
Loader (capacity 1 cum) hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 6.00 9000.00
Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, 12206.96
b) Labour and c) Machinery
d) Contractor's profit @10% on (a+b+c) 24236.16
Cost for 15 cum = a+b+c+d 341617.22
Rate per metre (a+b+c+d)/15 2846.81
say 2847.00

2.08 RCC Grade M30 (Pier,Abutment)


Using Batching Plant, Transit Mixer
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00

Concrete pump hour 6.00 165.00 990.00


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2549.00
Add 3.5 % for extra lift 96352.20
d) Formwork @ 14 per cent on cost of concrete i.e. cost of material, 42817.70
labour and machinery
e) Contractor's profit @ 10% on (a+b+c+d) 36999.11
cost of 120 cum = a+b+c+d+e 482009.71
Rate per cum = (a+b+c+d+e)/120 4016.75
add 10% for asthetic finshesh 401.67
4
Sr No Description Unit Quantity Rate Rs Cost Rs
Rate per cum 4418.42
say 4418.00

2.09 RCC Grade M30 For Pier Caps and pedestal)


Using Batching Plant, Transit Mixer
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.88 130.00 114.40
Mason day 3.00 130.00 390.00
Mazdoor day 19.00 120.00 2280.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00
Concrete Pump hour 6.00 165.00 990.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 305966

Add 3.5 % for extra lift 107088.10


Height 5m to 10m
d) Formwork and staging (a+b+c) 23.00 42835.24
e) Contractor's profit @10% on (a+b+c+d) 38086.97
Cost for 120 cum = a+b+c+d+e 493976.21
Rate per cum = (a+b+c+d+e)/120 4116.47
add 10% for asthetic finishesh 411.65
4528.12
say 4528.00

Providing and fixing in position HYSD Fe415 reinforcing bars of various


diameters for all RCC works of Superstructure as per detailed design and
drawings and schedule including cutting, bending, hooking the bars,
2.10 binding with 18 SWG including all laps, chairs, spacers etc. and cost of all
labour, materials, tools, plants, equipment, supporting as required with all
lifts and leads etc. all complete as per specification and as directed by
Engineer.
As per DSR 2005-06( Page No.205 Sr.No. 874 ) MT 33801.00
Add Corporation Charges @5% 1690.05
Total 35491

Providing and applying 2 coats of Coal tar epoxy paint to all concrete
2.11
surface in contact with earth .
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 130.00 1.30
Painter day 0.25 130.00 32.50
Mazdoor (Skilled) day 0.25 125.00 31.25
b) Material
Coal tar epoxy paint of approved quality for cement concrete surface Litres 5.00 200.00 1000.00

c) Contractor's profit @ 10% input on (a+b) 106.51


Cost for 10 sqm (a+b+c) 1171.56
Rate per sqm (a+b+c)/10 117.16
5
Sr No Description Unit Quantity Rate Rs Cost Rs
say 117.00

Providing and applying single coat epoxy phenolic primer of DFT-50


2.12 micron and two coats of epoxy phenolic coating of DFT-100 micron each
to surfaces of substructure exposed at atmosphere.
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy paint with primer litre 5.00 200.00 1000.00
b) Labour
Painter each 0.60 130.00 78.00
Mazdoor each 1.00 120.00 120.00
Add 10% Contractor's profit 119.80
Rate Per 10 M2 1317.80
Rate Per M2 131.78
Say 132.00

Sinking of well foundation in soil and murum etc. which can be removed Rm 76090.00
by grabbing and chiselling with large scale dewatering or in proper
2.14
setting of wells including all method excepts pneumatic sinking ( Dia 10 m
depth 20 M)
(As per DSR page no.199 and Sr.No.845)
Add 60% extra for depth upto 20 m 45654.00
add corporation charges @5% 6087.20
Rate per Rmt 127831.00

Providing and laying in situ M20 cement concrete in well staining


2.15 including compacting by vibrating , rodding ,finishing and curing etc
complete(excluding reinforcement )as directed by engineer
With Batching Plant, Transit Mixer
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 3990.00 166223.40
Coarse Sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Lead beyond 1 km, L-lead in km tonne.km 300L 6.00 9000.00
Concrete Pump hour 6 165.00 990.00
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2312.00
d) Formwork @ 10 per cent on cost of concrete i.e. cost of material, 20233.26
labour and machinery
e) Contractor's profit @ input on (a+b+c+d) 5634.25
Cost for 120 cum = a+b+c+d+e 303219.61
Rate per cum = ( a+b+c+d+e )/120 2526.83
say 2527.00
Providing and laying in situ M25 reinforced cement concrete well curbs
including necessary shuttering compacting by vibrating finishing and
2.16
curing etc. complete (excluding reinforcement ) as directed by Engineer

Using Batching Plant, Transit Mixer

6
Sr No Description Unit Quantity Rate Rs Cost Rs
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 3990.00 193036.20
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00

Concrete Pump hour 6.00 165.00 990.00


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2535.00
d) Formwork @ 20 per cent on cost of concrete i.e. cost of material, 60832.98
labour and machinery
e) Contractor's profit @ input on (a+b+c+d) 28997.84
cost of 120 cum = a+b+c+d+e 393995.72
Rate per cum = (a+b+c+d+e)/120 3283.30
say 3283.00

Providing fabricating and setting out mild steel cutting edges for
2.17 reinforced cement concrete well curbs as shown on the detailed drawing
etc. complete as directed by Engineer
As per DSR 2006-07( Page No.197 Sr.No. 838 ) MT 36700
add Corporation Charges @5% 1835
Rate per MT 38535
say 38535.00

Providing and laying in situ M30 reinforced cement concrete well caps/
pile caps including necessary shuttering compacting by vibrating finishing
2.18
and curing etc. complete (excluding reinforcement ) as directed by
Engineer
Using Batching Plant, Transit Mixer
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 3990.00 194672.10
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader (capacity 1 cum) hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00
Concrete Pump hour 6.00 165.00 990.00
Formwork @ 3.5 per cent of (a+b+c) 10703.03
d) Contractor's profit @ 10% on (a+b+c) 24148.43
7
Sr No Description Unit Quantity Rate Rs Cost Rs
cost of 120 cum = a+b+c+d 340652.26
Rate per cum = (a+b+c+d)/120 2838.77
say 2839.00

Providing and filling in well with sand /rubble and sand /shingle and sand
2.19 including compaction betwwen the top plug and bottom plug etc.complete
as directed by engineer
unit= 1 cum
Taking output = 1 cum
a) Material
sand ( assuming 20per cent voids) cum 1.20 372.99 447.59
b) Labour
Mate day 0.01 130.00 1.30
Mazdoor day 0.30 120.00 36.00
3.73
Rate per cum 513.05
say 513.00

Providing and laying in situ M15 reinforced cement concrete for the
bottom plugs of well in dry under water including compacting by vibrating
2.20
finishing and curing etc. complete (excluding reinforcement ) as directed
by Engineer
Using Batching Plant, Transit Mixer
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 33.04 3990.00 131829.60
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
Admixture Kg 148.80 80.00 11904.00
b) Labour
Mate day 0.88 130.00 114.40
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in tonne.km 300L 6.00 9000.00
Kilometer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2116.00
Add 5 per cent of cost of material and labour towards cost of forming 6724.70
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe..
d) Contractor's profit @10% on (a+b+c) 26060.22
cost of 120 cum = a+b+c+d 286662.42
Rate per cum = (a+b+c+d)/120 2388.85
say 2389.00

Providing and laying in situ M15 reinforced cement concrete for the Top
plugs of well including compacting by vibrating finishing and curing etc.
2.21
complete (excluding reinforcement ) as directed by Engineer

PCC Grade M15


Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 33.04 3990.00 131829.60
Coarse sand cum 54.00 372.99 20141.46
8
Sr No Description Unit Quantity Rate Rs Cost Rs
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
Admixture Kg 148.80 80.00 11904.00
b) Labour
Mate day 0.86 130.00 111.80
Mason day 1.50 130.00 195.00
Mazdoor day 20.00 120.00 2400.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in tonne.km 300L 6.00 9000.00
Kilometer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 15520.00
d) Contractor's profit @10% on (a+b+c) 16699.64
Cost for 15 cum = a+b+c+d 270619.54
Rate per cum = (a+b+c+d)/120 2255.16
say 2255.00

2.22 Providing and installing 6 mm MS liner for upper 2.5m depth of bored-
cast-in-situ concrete piles including applying protective coating as per
drawing and specification and as directed by Engineer (excluding
reinforcement).
Unit = MT
Mild steel liner in pile ( 6 mm)
Unit - 1 MT
a)Material
Steel Plate MT 1.05 24960.0 26208.00
b)Labour
Mate day 1.24 130.0 161.20
Fitter day 6.00 130.0 780.00
Blacksmith day 5.00 130.0 650.00
Welder day 5.00 130.0 650.00
Mazdoor day 10.00 120.0 1200.00
Electrodes , cutting gas and other consumable @5% of a) 1310.40
Transportation MT 1.00 1000.0 1000.00
Erection MT 1.00 2500.0 2500.00
c) contractors Profit @10% 3095.96
Rate per MT(a+b+c) 37555.56
say 37556.00

9
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Sec 3 SuperStructure
High tensile steel wires/strands including all accessories for stressing,
3.01/3.06 stressing operations and grouting complete as per drawing and Technical
Specifications
Unit = 1 MT
Taking output = 0.282 MT
Details of cost for 12T13 strand 30 m long cable (weight = 0.282 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for wastage and extra tonne 0.29 44000.00 12656.16
length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra length 30 x 1.05 = metre 31.50 125.00 3937.50
31.5 m.
Tube anchorage set complete with bearing plate, permanent wedges etc each 2.00 2000.00 4000.00

Cement for grouting including 3 per cent wastage @ 3.00 kg/m = 3 x 1.03 tonne 0.093 3870.00 359.91
x 30 = 92.7 kg (say, = 93 kg)
Add 0.50 per cent cost of material for Spacers, Insulation tape and 1047.68
miscellaneous items
b) Labour
i) For making and fixing cables, anchorages
Mate day 0.16 130.00 20.80
Blacksmith day 1.00 130.00 130.00
Mazdoor day 3.00 120.00 360.00
ii) For prestressing
Mate/Supervisor day 0.05 130.00 6.50
Prestressing operator / Fitter day 0.25 130.00 32.50
Mazdoor day 1.00 120.00 120.00
iii) For grouting
Mate/Supervisor day 0.05 130.00 6.50
Mason day 0.25 130.00 32.50
Mazdoor day 1.00 120.00 120.00
c) Machinery
Stressing jack with pump hour 2.50 83.00 207.50
Grouting pump with agitator hour 1.00 50.00 50.00
Generator 33 KVA. hour 3.50 240.00 840.00
d) Contractor's profit @ input on (a+b+c) 2392.75
Cost for 0.282 MT (a+b+c+d) 26320.30
Rate per MT = (a+b+c+d)/0.282 93334.41
say 93334.00

3.02 PSC Grade M-40 Precast Girder


Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3990.00 205884.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
Admixture @ 0.4 per cent of cement kg 223.20 80.00 17856.00
b) Labour
Mate day 0.94 130.00 122.20
Mason day 3.50 130.00 455.00
Mazdoor day 20.00 120.00 2400.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300*5 6.00 9000.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 334197.00

For formwork and staging add the following:


1
Sr No Description Unit Quantity Rate Rs Cost Rs
For T-beam & slab 23-33 per cent of cost of concrete.
Height Above 10m
Formwork and staging (a+b+c) 33% 26.00 110284.91
(e) Placement of girders in position over pier caps including placement of sand
jacks, channel, levelling etc.
Add for(Loading and machinary hire charges )construction at precast yard @ 33419.70
10%
Add for transportation and Launching of Girder in position @ 10% 33419.70
f) Contractor's profit @ input on (a+b+c+d+e) 43630.15
Cost for 120 cum = a+b+c+d+e+f 554951.16
Rate per cum = (a+b+c+d+e+f)/120 4624.59
say 4625.00

Supplying, fitting and fixing in position true to line and level POT-PTFE bearing
consisting of a metal piston supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust seals, PTFE surface
sliding against stainless steel mating surface, complete assembly to be of cast
3.03 steel/fabricated structural steel, metal and elastomer elements to be as per
IRC: 83 part-I & II respectively and other parts conforming to BS: 5400, section
9.1 & 9.2 and clause 2006 of MoRTH Specifications complete as per drawing
and approved Technical Specifications.

Unit: one tonne capacity


POT Cum PTFE Bearing
1) 90 Tonne Capacity each. 1.00 9900.00 9900.00
Contractor's profit @ 10% 990.00
cost for 90 tonnes capacity bearing 10890.00

1) 125 Tonne Capacity each. 1.00 13750.00 13750.00


Contractor's profit @ 10% 1375.00
cost for 100 tonnes capacity bearing 15125.00

1) 260 Tonne Capacity each. 1.00 28600.00 28600.00


Contractor's profit @ 10% 2860.00
cost for 260 tonnes capacity bearing 31460.00

3.04 RCC Grade M-40 ( Deck Slab and Diaphragm)


Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3990.00 205884.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
Admixture @ 0.4 per cent of cement kg 223.20 80.00 17856.00
b) Labour
Mate day 0.94 130.00 122.20
Mason day 3.50 130.00 455.00
Mazdoor day 20.00 120.00 2400.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00
Concrete Pump hour 6.00 165.00 990.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 335187.00

add for lift 3.5% 129047.00


For formwork and staging add the following:
For solid slab/voided slab super-structure, 18-28 per cent of cost of concrete
(a+b+c)
Above 10m
D) Formwork and staging per cent of (a+b+c) 21.00 93852.28
2
Sr No Description Unit Quantity Rate Rs Cost Rs
e) Contractor's profit @ input on (a+b+c+d) 35401.95
Cost for 120 cum = a+b+c+d+e 593487.92
Rate per cum = (a+b+c+d+e)/120 4945.73
say 4946.00

3.05 RCC Grade M-40 ( Box Girder)


Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3990.00 205884.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
Admixture @ 0.4 per cent of cement kg 223.20 80.00 17856.00
b) Labour
Mate day 0.94 130.00 122.20
Mason day 3.50 130.00 455.00
Mazdoor day 20.00 120.00 2400.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00
Concrete Pump hour 6.00 165.00 990.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 335187.00

Add 3.5% for extra lift 129047.00


For formwork and staging add the following:
For cast-in-situ box girder, segmental construction and balanced cantilever, 36-
58 per cent of cost of concrete.
d) Formwork and staging 58 per cent of (a+b+c) 46.00 194408.29
e) Contractor's profit @ input on (a+b+c+d) 45457.55
Cost for 120 cum = a+b+c+d+e 704099.53
Rate per cum = (a+b+c+d)/120 5867.50
say 5867.00

Providing and applying 3 coats of water based cement paint to unplastered


3.08 concrete surface after cleaning the surface of dirt, dust, oil, grease,
efflorescence and applying paint @ of 1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 130.00 1.30
Painter day 0.25 130.00 32.50
Mazdoor (Skilled) day 0.25 125.00 31.25
b) Material
Water based paint of approved quality for cement concrete surface Litres 5.00 125.00 625.00
C)Contractor's profit @ input on (a+b) 69.01
Cost for 10 sqm (a+b+c) 759.06
Rate per sqm (a+b+c)/10 75.91
add rate for 1 coat 37.95
Rate per sqm 113.86
say 114.00
3.10 Providing and laying in-situ RCC M30 grade concrete in waist slab including
centering, shuttering, mixing in mechanised batch mix plant, compaction,
curing and dewatering if necessary, excluding reinforcement as per
specification and as directed by Engineer.
RCC Grade M30 For waist slab
Using Batching Plant, Transit Mixer
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3990.00 194712.00
3
Sr No Description Unit Quantity Rate Rs Cost Rs
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.88 130.00 114.40
Mason day 3.00 130.00 390.00
Mazdoor day 19.00 120.00 2280.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00
Concrete Pump hour 6.00 165.00 990.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 304976

Add 3.5 % for extra lift 10674.16


Height 5m to 10m
d) Formwork and staging (a+b+c) @ 4.5% 23.00 13723.92
e) Contractor's profit @10% on (a+b+c+d) 25534.45
Cost for 120 cum = a+b+c+d+e 355898.43
Rate per cum = (a+b+c+d+e)/120 2965.82
say 2966.00
3.11 Providing and fixing 150*100 mm non skidding precast chequred tiles 25 mm
thick of approved quality in traffic island and where ever necessary in city
suburban limit over 18 mm thick C.M 1:3 including curing etc.complete as per
drawing and as directed by Engineer.

Unit = 10 Sqm

a) Material

Chequared Tile Sqm 11.00 130.00 1430.00


Cement Mortar 1:3 Sqm 0.18 2467.74 444.19
1874.19
Cement Mortar 1:3 (sub Analysis)
Unit =Cum
Taking Output =1cum
Material
Cement MT 0.51 3990.00 2034.90
Sand Cum 1.05 372.99 391.64
Mate day 0.04 130.00 5.20
Mazdoor day 0.30 120.00 36.00
Total = (A+B) 2467.74
b) Labour
Mason day 2.16 130.00 280.80
Mazdoor day 2.16 120.00 259.20
540.00
Sundries 15.00
c) Contractor's profit @ input on (c) 55.50
Rate per 10 sqm = a+b+c 2484.69
Rate per sqm = (a+b+c)/10 260.89
say 261

4
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Sec 4 Miscallaneous Items
4.01 RCC Grade M-40 ( Crash Barrier)
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3990.00 205884.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
Admixture @ 0.4 per cent of cement kg 223.20 80.00 17856.00
b) Labour
Mate day 0.94 130.00 122.20
Mason day 3.50 130.00 455.00
Mazdoor day 20.00 120.00 2400.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 334197.00
cum
add for lift 3.5% 140362.74
e) Contractor's profit @ input on (a+b+c+d) 25917.72
Cost for 120 cum = a+b+c+d+e 500477.16
Rate per cum = (a+b+c+d+e)/120 4170.64
say 4171.00
Unit = Linear metre
Taking output = 10 m
a) M 40 grade concrete
cum 6.457 4171.00 26932.15
b) Labour
Mate day 0.040 130.00 5.20
Mazdoor day 1.000 120.00 120.00
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 35491.00 9937.48
Pre-moulded asphalt filler board sqm 0.320 700.00 224.00
e) Contractor's profit @ input on (b+c+d) 1028.67
Cost for 10 metre = a+b+c+d+e 38247.50
Rate per metre = (a+b+c+d+e)/10 3824.75
say 3825.00

4.02 Providing 100mm dia PVC pipe in footpath / crash barrier for utility

Unit - m
1) Cost of 100mm dia PVC pipe M 1.000 125.00 125.00
2) Labour for laying - 5% 6.25
Add 10% Contractor's profit 12.50
Rate per m 143.75
say 144.00
4.03 Kerb M-25
With Batching Plant, Transit Mixer
Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 3990.00 193036.20
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22

1
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Cost of Water Kl 270.00 100.00 27000.00
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Kerb Casting Machine @ 60meter/hour Hour 6.00 200.00 1200.00
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2638.00 316555.00

d) Contractors Profit @ 10 % (b+c) 21453.54


cost of 120 cum = a+b+c+d 338008.54
Rate per cum (a+b+c+d)/120 2816.74
say 2817.00

4.06 Providing and fixing in position 100mm dia drainage spout with GI
grating
Unit - Each
a) Material
Cost of MS grating including hopper No. 1.00 100.00 100.00
Cost of 100mm dia GI pipe M 1.00 135.00 135.00
Cost of anti-corrosive / bituminous paint LS 50.00
b) Labour
Mason day 0.10 130.00 13.00
Mazdoor day 0.20 120.00 24.00
Add Contractor's Profit @10% 32.20
Total Say 354.00

4.07/4. Providing and fixing 150mm dia runner and downtake PVC pipe
08
150mm dia PVC pipe m 1 148 148
Fixture, clamps, etc. LS 25 25
Bends No. 0.5 135 67.5
Labour for fixing LS 50 50
Add Contractor's Profit @10% 29.05
Rate per m 319.55
Say 320.00

4.09 Providing and constructing catch pit 0.90 m x 0.45 m x 1.2 m deep in
BB masonry including excavation, backfilling in soil, 100 mm thick M-
15 grade PCC below and covered with 100 mm thick RCC M-25 slab,
reinforcement, M.S. covering, smooth finish from inside etc. complete
as per drawing and as directed by Engineer.
Unit = Nos
AS per DSR 2005-06 Page No. 126 Sr.No.538 No 1.00 1850.00 1942.50
Deduct PCC M15 Rate 0.06 1692.00 93.06
Deduct RCC Cover M25 Rate 0.03 2929.00 88.97
Total 1760.47
Excavation of Catchpit 0.94 61.00 57.10
Add Rate of Concrete PCC M15 0.06 1895.00 104.23
Add rates of Concrete RCC Cover M25 0.03 2492.00 75.69
Add for Steel 0.0010 35491.00 35.93
Rate Per No 2033.00

4.10 Providing and fixing precast concrete 300 mm dia. pipes, type NP3,
granular and concrete bedding below pipe, encasing pipe with M-30
concrete, including cost of all materials, labour, etc. complete with all
lifts and leads etc. as per specifications and as directed by Engineer.

2
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length each )

1000 mm dia
a) Labour
Mate day 0.180 130.00 23.40
Mason day 0.500 130.00 65.00
Mazdoor day 4.000 120.00 480.00
b) Material
Sand at site cum 0.070 372.99 26.11
Cement at site tonne 0.050 3990.00 199.50
RCC pipe NP-3 300 mm dia /prestressed concrete pipe including metre 12.500 312.00 3900.00
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 480.13 2160.59
c) Encasement of pipes with M30 Concrete cum 0.094 2505.00 235.97
d) Contractor's profit @ input on (a+b+c) 709.06
Cost for 12.5 metres = a+b+c+d 7799.62
Rate per metre = (a+b+c+d)/12.5 623.97
say 624.00
Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per
approved drawings and standard specifications to be installed by the
4.11
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.05 130.00 6.50
Mazdoor day 1.00 120.00 120.00
Mazdoor (Skilled) day 0.25 125.00 31.25
b) Material
Supply of complete assembly of strip seal expansion joint metre 12.00 6500.00 78000.00
comprising of edge beams, anchorage, strip seal element and
complete accessories as per approved specifications and
drawings.
Add 5 per cent of cost of material for anchorage reinforcement, 3907.89
welding and other incidentals.
c) Contractor's profit @ input on (a+b) 8206.56
Cost for 12 m = (a+b+c) 90272.20
Rate per m = (a+b+c)/12 7522.68
say 7523.00

4.12 Providing and applying primer coat using bituminous emulsion or cut
back primer over prepared surface of granular base with emulsion
preheated to a temperature between 20OC - 60OC and applying a
uniform coat with the aid of self propelled bitumen pressure sprayer
with self heating arrangement and spraying bar with nozzles of
constant volume for pressure system at 10 kg/10 sqm including all
materials, labour, machinery etc. complete with all leads and lifts as
directed by Engineer and as per specification.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 130.00 10.40
Mazdoor day 2.000 120.00 240.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 230.00 644.00
Air compressor 250 cfm hour 2.800 206.00 576.80

3
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 692.00 1384.00
Water tanker 6 KL capacity hour 1.000 200.00 200.00
c) Material
Bitumen emulsion @ 1 kg per sqm tonne 3.500 25426.10 88991.35
Add Lead Charges for asphalt for 625 Km@Rs2.9/T. 6343.75
d) Contractor's profit @ input on (a+b+C) 9839.03
Cost for 3500 sqm = a+b+c+d 108229.33
Rate per sqm = (a+b+c+d)/3500 30.92
say 31.00

4.13 Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.50 kg per sqm on the
prepared bituminous/granular surface cleaned with mechanical
broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 130.00 10.40
Mazdoor day 2.000 120.00 240.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 230.00 644.00
Air compressor 250 cfm hour 2.800 206.00 576.80
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 692.00 1384.00
c) Material
Bitumen emulsion @ 0.5 kg per sqm tonne 1.750 25426.10 44495.68
Add Lead Charges for asphalt for 625 Km@Rs2.9/T. 3171.88
d) Contractor's profit @ input on (a+b+C) 5052.28
Cost for 3500 sqm = a+b+c+d 55575.03
Rate per sqm = (a+b+c+d)/3500 15.88
say 16.00

4.14 Providing and laying 6 mm thick mastic asphalt wearing course on top
of deck slab excluding prime coat with paving grade bitumen meeting
the requirements given in table 500-29, prepared by using mastic
cooker and laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated fine
grained hard stone chipping of 9.5 mm nominal size at the rate of
0.005cum per 10 sqm and at an approximate spacing of 10 cm center
to center in both directions, pressed into surface when the
temperature of surfaces not less than 100 deg. C, protruding 1 mm to
4 mm over mastic surface, all complete as per clause 515.

Unit = sqm
Taking output = 145 sqm (2 tonnes)(0.869 cum) assuming a
density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 130.00 63.70
Mazdoor day 11.00 120.00 1320.00
Mazdoor (Skilled) day 1.25 125.00 156.25
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 230.00 13.80
Air compressor 250 cfm hour 0.06 206.00 12.36
Mastic cooker 1 tonne capacity hour 6.00 40.00 240.00
Bitumen boiler 1500 litres capacity hour 6.00 128.00 768.00
Tractor for towing and positioning of mastic cooker and bitumen hour 1.00 234.00 234.00
boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent

4
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific case)

i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent by weight tonne 0.280 25426.10 7119.31
of mix. 2 x 14.0/100 = 0.204
add Lead Charges for Bitumen 625 Km 507.50
ii) Crusher stone dust @ 31.9 per cent by weight of mix = 2 x cum 0.39 480.13 187.25
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate content not less tonne 0.36 5000.00 1800.00
than 80 per cent by weight @ 17.92 per cent by weight of mix =
2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cent cum 0.55 508.13 279.47
by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55

v) Pre-coated stone chips of 9.5 mm nominal size for skid cum 0.036 480.13 17.28
resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight = 0.036 kg 1.05 25.43 26.70
x 1.456 x 2/100 = 0.001048MT = 1.05kg
#REF! 1047.89
Cost for 145 sqm = a+b+c+d 13793.51
Rate per sqm = (a+b+c+d)/145 95.13
say 95.00

Providing and laying 12 mm thick mastic asphalt wearing course on


b) top of deck slab

a) for 6 mm thick 13793.51


rate per sqm
b) for 12 mm thick mastic asphalt
rate per sqm (a)/72.5) 190.26
say 190.00

Providing and laying dense graded bituminous macadam with 100-


120 TPH batch type HMP producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading, premixed
with bituminous binder @ 4.5 per cent by weight of total mix and
filler, transporting the hot mix to work site, laying with a hydrostatic
4.15
paver finisher with sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and tandem rollers
to achieve the desired compaction as per MoRTH specification clause
No. 507 complete in all respects.

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 130.00 109.20
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 120.00 1920.00
asphalt cutter and assistance for setting out lines, levels and
layout of construction
Skilled mazdoor for checking line & levels day 5.000 125.00 625.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 7150.00 42900.00
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 1725.00 10350.00

Generator 250 KVA hour 6.000 1285.00 7710.00


Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
Tipper 10 tonne capacity tonne.km 450 x 3 1.60 2160.00

5
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 297.00 1158.30

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 994.00 3876.60
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 6.00x0.65* 738.00 2878.20
c) Materials
Bitumen @ 4.5 per cent of weight of mix tonne 20.250 25426.10 514878.53
Aggregate
Add Lead Charges for asphalt for 625 Km@Rs2.9/T. 37968.75
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 508.13 43780.48
10 - 5 mm 28 per cent cum 80.430 508.13 40868.90
5 mm and below 40 per cent cum 114.900 508.13 58384.14
Filler @ 2 per cent of weight of aggregates. tonne 8.620 480.13 4138.72
d) Contractor's profit @ on (a+b+c) 62965.46
Cost for 195 cum = a+b+c+d 839792.27
Rate per cum = (a+b+c+d)/195 (For Grading-II) 4306.63
say 4307.00

Providing and laying bituminous concrete with 100-120 TPH batch


type hot mix plant producing an average output of 75 tonnes per hour
using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.5 per cent of mix and filler, transporting the
4.16 hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in
all respects
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 130.00 109.20
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 120.00 1920.00
asphalt cutter and assistance for setting out lines, levels and
layout of construction
Skilled mazdoor for checking line & levels day 5.000 125.00 625.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 7150.00 42900.00
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 1725.00 10350.00

Generator 250 KVA hour 6.000 1285.00 7710.00


Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
Tipper 10 tonne capacity tonne.km 450 x 3 1.60 2160.00
Smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 297.00 1158.30

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 994.00 3876.60
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 6.00x0.65* 738.00 2878.20
c) Material
i) Bitumen@ 5.5 per cent of weight of mix tonne 24.750 25426.10 629295.98
Add Lead Charges for asphalt for 625 Km@Rs2.9/T. 44859.38
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 24.75 tonnes
Weight of aggregate = 450 -24.75 = 425.25 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum

6
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 508.13 43445.12
10 - 5 mm 25 per cent cum 71.250 508.13 36204.26
5 mm and below43 per cent cum 122.550 508.13 62271.33
Filler @ 2 per cent of weight of aggregates. tonne 8.620 480.13 4138.72
for Grading-II(13 mm nominal size)
d) Contractor's profit @ on (a+b+c) 75096.27
Cost for 191 cum = a+b+c+d 972118.34
Rate per cum = (a+b+c+d)/191 (For Grading-II) 5089.62
say 5090.00

b) Providing and laying bituminous concrete with 100-120 TPH batch


type hot mix plant producing an average output of 75 tonnes per hour
using crushed aggregates of specified grading, premixed with (PMB
40)Modified bituminous binder @ 5.5 per cent of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve
the desired compaction as per MORTH specification clause No. 509
complete in all respects

Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 130.00 109.20
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 120.00 1920.00
asphalt cutter and assistance for setting out lines, levels and
layout of construction
Skilled mazdoor for checking line & levels day 5.000 125.00 625.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 7150.00 42900.00
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 1725.00 10350.00

Generator 250 KVA hour 6.000 1285.00 7710.00


Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
Tipper 10 tonne capacity tonne.km 450 x 3 1.60 2160.00
Smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 297.00 1158.30

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 994.00 3876.60
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 6.00x0.65* 738.00 2878.20
c) Material
i) Modified Bitumen@ 5.5 per cent of weight of mix ( PMB 40) tonne 24.750 28959.32 716743.17

Add Lead Charges for asphalt for 625 Km@Rs2.9/T. 44859.38


ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 24.75 tonnes
Weight of aggregate = 450 -24.75 = 425.25 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 508.13 43445.12
10 - 5 mm 25 per cent cum 71.250 508.13 36204.26
5 mm and below43 per cent cum 122.550 508.13 62271.33
Filler @ 2 per cent of weight of aggregates. tonne 8.620 480.13 4138.72
for Grading-II(13 mm nominal size)
d) Contractor's profit @ on (a+b+c) 83840.98
Cost for 191 cum = a+b+c+d 1068310.26
Rate per cum = (a+b+c+d)/191 (For Grading-II) 5593.25
say 5593.00

7
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs

Providing & fixing discontinuous M25 PCC precast kerb stonesof size
600 x 300 x 1200 mm at a spacing of 1200 mm c/c on road side
parallel to the retaining wall of reinforced structure at a distance of
4.17
1000 mm from the face of retaining wall including transportation,
excavation etc. complete with all leads as per specification and as
directed by Engineer.
Unit = Nos
Rate of M25 Concrete Cum 0.216 2816.74 608.42
Sr.No.4.03
Rate Per Nos 608

Providing traffic lane line strips 10 cm wide with approved road


4.19 marking paint in two coats as per specification and as directed by
Engineer.
a) With hot applied thermoplastic paint Sqm 600
for yellow edge line
As per DSR 2005-06( Page No.185 Sr.No. 778 ) 30
Add Corporation Charges @5% 630
Total

b) With hot applied thermoplastic paint 600


for white strips. Sqm
As per DSR 2005-06( Page No.185 Sr.No. 778 ) 30
Add Corporation Charges @5% 630
Total

Providing & fixing in position 100 mm Dia. A.C. pipes as weep holes
4.20 in Abutments and Return Walls completed in all respect as per
specification and as directed by Engineer.
As per DSR 2005-06( Page No.196 Sr.No. 834 ) Nos 57
Add Corporation Charges @5% 2.85
Total 60

Providing, fitting and fixing mild steel railing complete as per drawing
4.21
and Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 25000.00 73650.00
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 25000.00 25300.00
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 25000.00 4500.00
4) MS bolts, nuts and washers tonne 0.15 31500.00 4725.00
Add @ 5 per cent of cost of material for painting one shop coat 5408.75
with red oxide primer and three coats of synthetic enamel paint
and consumables to safeguard against weathering and
corrosion.
Add for cost of concrete for fixing vertical posts in the performed 1081.75
recess @ 1 per cent of cost of material.
Add for electricity charges, welding and drilling equipment, 1081.75
electrodes and other consumables @ 1 per cent of cost of
material.
b) Labour
Mate day 2.80 130.00 364.00
Mazdoor (Skilled) day 30.00 125.00 3750.00
Mazdoor day 40.00 120.00 4800.00
#REF! 12466.13
Cost for 100 m steel railing = a+b+c 137127.38
Rate per metre (a+b+c)/100 1371.27
say 1371.00

8
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Providing & fixing 20 mm thick compressible fibre board in expansion
4.22 joint complete as per drawing & Technical Specification.

Unit = Running meter


Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 130.00 1.04
Mazdoor day 0.10 120.00 12.00
Mazdoor (Skilled) day 0.10 125.00 12.50
b) Material
20 mm thick compressible fibre board 12 m long x 25 cm deep. sqm 3.00 945.00 2835.00

Area = 12 x 0.25 = 3 sqm


c) Contractor's profit @ input on (a+b) 286.05
Cost for 12 m = (a+b+c) 3146.59
Rate per m = (a+b+c)/12 262.22
say 262.00

4.23 M30 FACIA PANNEL


Using Batching Plant, Transit Mixer
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in tonne.km 300L 6.00 9000.00
Kilometer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2541.00

d) Formwork @ 3.5 per cent of cost of concrete i.e. cost of 10669.77


material, labour and machinery
f) Contractor's profit @ input on (a+b+c+d+e) 24050.10
cost of 120 cum = a+b+c+d+e+f 339570.57
Rate per cum (a+b+c+d+e+f )/120 2829.75
say 2830.00

4.24 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal


size aggregate, true to line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing between vertical post
not to exceed 1000 mm, leaving adequate space between vertical
post for expansion, complete as per approved drawings and technical
specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum

9
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 410.53 26602.37
10 mm Aggregate cum 43.20 410.53 17734.91
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader hour 6.00 520.00 3120.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 6.00 9000.00

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 294310.00 2452.58
cum
Cement concreteM30 Grade Refer relevant item of concrete cum 4.250 2452.58 10423.48
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of
vertical post 0.25x0.275 = 0.069sqm, Concrete in vehicle posts =
0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m,
External area = 0.170 x 0.175 = 0.03 sqm, Concrete in hand rails
= 0.03 x 72 = 2.16 cum, Total Concrete = 1.932 + 2.16 = 4.092
cum. (Refer MoRTH SD / 202).

Add 12 per cent of above cost for form work. 1250.82


HYSD bar reinforcement Rate tonne 0.87 25000.00 21625.00
c) Contractor's profit @ input on (a+b) 25270.70
Rate for 48 m (a+b+c) 58570.00
Rate per metre (a+b+c)/48 1220.21
say 1220.00
4.25 Back filling behind abutment, wing wall and return wall complete as
per drawing and Technical Specification
Unit = cum
Taking output = 10 cum
Granular material
a) Labour
Mate day 0.28 130.00 36.40
Mazdoor day 7.00 120.00 840.00
b) Material
Granular material cum 12.00 44.00 528.00
c) Machinery
Plate compactor/power rammer hour 2.50 75.00 187.50
Water Tanker hour 0.05 200.00 10.00
d) Contractor's profit @ input on (a+b+c) 160.19
Cost for 10 cum of granular backfill = a+b+c+d 1762.09
Rate per cum = (a+b+c+d)/10 176.21
say 176.00
4.26 Providing and fixing Neoprene bearing as per standard specification
etc.complete( as per IRC-83 Part-11)
As per DSR 2005-06 (Sr.No. 878 Page.No. 206) cu.centi
meter 1.23
Add Corporation Charges @ 5% 0.0615
Rate per cu.centimeter 1.29

10
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs

Sec 5 Solid Approaches / Reinforced Earth Retaining Wall

5.02 PCC M30 For Facia Element


Using Batching Plant, Transit Mixer
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.30 508.13 32672.76
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 6.00 9000.00
in Kilometer
Per Cum Basic Cost of Labour, Material & Machinery 2539.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost 10660.88
of material, labour and machinery
#REF! 24049.21
cost of 120 cum = a+b+c+d+e 339306.73
Rate per cum (a+b+c+d+e )/120 2827.56
say 2828.00
5.03 M30 FACIA PANNEL
Using Batching Plant, Transit Mixer
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 6.00 9000.00
in Kilometer
Per Cum Basic Cost of Labour, Material & Machinery 2541.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost of 10669.77
material, labour and machinery
f) Contractor's profit @ input on (a+b+c+d+e) 24050.10
cost of 120 cum = a+b+c+d+e+f 339570.57
Rate per cum (a+b+c+d+e+f )/120 2829.75
say 2830.00
1
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Facing elements of RCC M30
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 130.00 23.40
Mazdoor day 3.000 120.00 360.00
Mazdoor skilled day 1.500 125.00 187.50
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 230.00 1380.00
c) Material
Pre-cast RCC M-35 facing elements of size as per design cum 13.500 2830.00 38205.00
and 18 cm thick for 75 sqm. (Refer Item 12.8 (H))

HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 34042.00 12935.96
Add 2 per cent of cost of facia pannels, for all necessary 1022.82
temporary form work, scaffolding and provision of loops/lugs
for lifting of pannels and joining the reinforcing elements.

#REF! 195.09
Cost for 75 sqm = a+b+c+d 54309.77
Rate per sqm = (a+b+c+d)/ 75 724.13
say 724.00
With reinforcing elements of synthetic geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 130.00 46.80
Mazdoor day 6.000 120.00 720.00
Mazdoor skilled day 3.000 125.00 375.00
b) Material
Synthetic Geogrids as per clause 3102.8 and approved sqm 300.000 300.00 90000.00
design and specifications.
Add 10 per cent of the cost of reinforcing elements 9000.00
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing elements
with the facia pannels, overlaps and other protective
elements for synthetic geogrids.
#REF! 10014.18
Cost of 300 sqm of Synthetic geogrids = a+b+c 110155.98
Rate per sqm = (a+b+c)/ 300 367.19
say 367.00
Total of 5.03 say 1091.00

5.04 Providing and laying in-situ RCC M-30 grade friction slab /
coping beam on top of facia wall concrete, necessary
shuttering, centering, compaction by vibrating, curing, joints
etc.complete in all respect with cast in-situ expansion gap at
50 m interval as directed by Engineer and as per specification
and drawing, excluding reinforcement.
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3990.00 194712.00
Coarse sand cum 54.00 372.99 20141.46
20 mm Aggregate cum 64.80 508.13 32926.82
10 mm Aggregate cum 43.20 508.13 21951.22
b) Labour
2
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Mate day 0.84 130.00 109.20
Mason day 3.00 130.00 390.00
Mazdoor day 18.00 120.00 2160.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1440.00 8640.00
Generator 100 KVA hour 6.00 450.00 2700.00
Loader 1 cum capacity hour 6.00 520.00 3120.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 6.00 9000.00
in Kilometer
Per Cum Basic Cost of Labour, Material & Machinery 2541.00
(a+b+c)
Add for lift 3.5% 26680.50
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost of 10669.77
material, labour and machinery
e) Contractor's profit @ input on (a+b+c+d) 26718.15
cost of 120 cum = a+b+c+d+e 368919.12
Rate per cum (a+b+c+d+e )/120 3074.33
say 3074.00

5.06 / Providing earth work in embankment by using mechanical


5.07 means with approved material obtained from borrow areas
having 4 days soaked CBR equal to or more than 6%, laying in
layers not exceeding 200 mm, breaking clods, dressing to the
required lines, curves grades, and watering to OMC and
compacting to 95% modified proctor density with vibratory
roller having minimum 80 - 100 kN static weight including all
lifts and leads etc. complete as directed by Engineer and as
per specification.
As per DSR 2005-06( Page No.205 Sr.No. 874 ) Cum 45.00
Add lead charges for 18 Km 102.00
Royalty charges for murrum cum 35.10
Rate per cum 182.10
Add Corporation Charges @5% 9.11
Total 191.00

5.08 Construction of granular sub-base (structural Layer)by


providing close graded Material, mixing in a mechanical mix
plant at OMC, carriage of mixed Material to work site,
spreading in uniform layers with motor grader on prepared
surface and compacting with vibratory power roller to achieve
the desired density, complete as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 130.00 52.00
Mazdoor skilled day 2.000 125.00 250.00
Mazdoor day 8.000 120.00 960.00
b) Machinery
Electric generator 125 KVA hour 6.000 450.00 2700.00
Water tanker 6 KL capacity 5 km lead with one trip per hour 4.500 200.00 900.00
hour
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
Tipper 10 tonne tonne.km 450 1.60 2160.00
Motor Grader 110 HP hour 6.000 1545.00 9270.00
Vibratory roller 8-10 t hour 6.000 994.00 5964.00
c) Material
Close graded Granular sub-base Material as per table 400-1

3
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 508.13 51219.50
9.5 mm to 2.36 mm @ 25 per cent cum 72.000 508.13 36585.36
2.36 mm below @ 40 per cent cum 115.200 480.13 55310.98
Cost of water KL 27.000 100.00 2700.00
Rate per cum for grading-II Material
d) Contractor's profit @ input on (a+b) 2537.60
Cost for 225 cum = a+b+c+d 173729.44
Rate per cum = (a+b+c+d)/225 772.13
say 772.00

5.09 Construction of granular sub-base( drainage layer) by


providing coarse graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with vibratory
roller to achieve the desired density, complete as per clause
401.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 130.00 52.00
Mazdoor skilled day 2.000 125.00 250.00
Mazdoor day 8.000 120.00 960.00
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 1545.00 9270.00
Vibratory roller 8 -10 tonne hour 6.000 994.00 5964.00
Water tanker 6 KL capacity hour 3.000 200.00 600.00
c) Material
For coarse graded Granular sub-base Materials per table 400-
2
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 508.13 146341.44
2.36 mm below @ 25 per cent cum 96.000 480.13 46092.48
Cost of water KL 18.000 100.00 1800.00
Rate per cum for grading-II Material
d)Contractor's profit @ input on (a+b) 1709.60
Cost for 300 cum = a+b+c+d 213039.52
Rate per cum = (a+b+c+d)/300 745.64
say 746.00

5.10 Construction of dry lean cement concrete Sub- base over a


prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed 15:1,
aggregate gradation after blending to be as per table 600-1,
cement content not to be less than 150 kg/ cum, optimum
moisture content to be determined during trial length
construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a
paver with electronic sensor, compacting with 8-10 tonnes
vibratory roller, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 130.00 145.60
Mazdoor skilled day 6.000 125.00 750.00
Mazdoor day 22.000 120.00 2640.00
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
4
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 2000.00 12000.00
Electric generator 100 KVA hour 6 450 2700.00
Paver with electronic sensor hour 6 1850 11100.00
Vibratory roller 8-10 t capacity hour 8.000 994.00 7952.00
Water tanker6 KL capacity hour 8.000 200.00 1600.00
Tipper tonne.km 990 x 5 1.60 7920.00
Add 10 per cent of cost of carriage to cover cost of loading 792.00
and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5 mm cum 405.000 508.13 205792.65
nominal sizes graded as per table 600-1 @ 0.90 cum/cum
of concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of concrete cum 203.000 372.99 75716.97

Cement @ 150 kg/cum of concrete tonne 67.500 3870.00 261225.00


Cost of water KL 48.000 100.00 4800.00
d) Contractor's profit on (a+b+c) 5071.96
Cost for 205 cum = a+b+c+d 603326.18
Rate per cum = (a+b+c+d)/450 1340.72
say 1341.00

5.13 Construction of un-reinforced, dowel jointed, plain cement


concrete pavement over a prepared sub base with 43 grade
cement @ 350 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a fixed form
or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant, debonding
strip, dowel bar, tie rod, admixtures as approved, curing
compound, finishing to lines and grades as per drawing

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 130.00 260.00
Mazdoor skilled day 15.000 125.00 1875.00
Mazdoor day 35.000 120.00 4200.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 230.00 644.00
Front end loader 1 cum bucket capacity hour 18.000 520.00 9360.00
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 3500.00 21000.00
(effective output)
Electric generator 250 KVA hour 6.000 1285.00 7710.00
Slip form paver with electronic sensor hour 6.000 9500.00 57000.00
Water tanker6 KL capacity hour 36.000 200.00 7200.00
Transit truck agitator 5 cum capacity. tonne.km 2415x5 1.60 19320.00
Add 10 per cent of cost of carriage to cover cost of loading 1932.00
and unloading
Concrete joint cutting machine . hour 12.00 200.00 2400.00
Texturing machine . hour 12.00 50.00 600.00
c) Material
Crushed stone coarse aggregates of 25mm and 12.5mm cum 945 508.13 480182.85
nominal size @ 0.90 cum/cum of concrete conforming to
clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @ cum 473 372.99 176424.27
0.45 cum/cum of concrete
5
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
Cement 43 grade @ 350 kg/cum of concrete Rate tonne 368 3870 1424160.00
32 mm mild steel dowel bars of grade S 240 tonne 9.45 25000 236250.00
16 mm deformed steel tie bars of grade S 415 tonne 1.17 25000 29250.00
Separation Membrane of impermeable plastic sheeting sqm 3675 50 183750.00
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 16.33 8000 130640.00

Joint sealant kg 875 80 70000.00


Sealant primer kg 116.67 285 33250.95
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 200 9334.00
Curing compound liter 1850 70 129500.00
Super plastisizer admixture IS marked as per 9103-1999 Kg 2070 80 165600.00
@ 0.5 per cent by weight of cement
Cost of water KL 216 100 21600.00
Add 1 per cent of material for cost of miscellaneous 30899.42
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor
equipments like scabbling machine, threads, ropes, guide
wires and any other unforeseen items.

contrators profit @ 10% 259773.54


Cost for 1050cum = a+b+c+d 3514116.03
Rate per cum = (a+b+c+d)/1050 3346.78
say 3347.00

Wet Mix Macadam


5.16 Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 130.00 62.40
Mazdoor skilled day 2.000 125.00 250.00
Mazdoor day 10.000 120.00 1200.00
b) Machinery hour
Wet mix plant of 75 tonne hourly capacity hour 9.000 1296.00 11664.00
Electric generator 125 KVA hour 6.000 450.00 2700.00
Front end loader 1 cum capacity hour 6.000 520.00 3120.00
Paver finisher hour 6.000 629.00 3774.00
Vibratory roller 8 - 10 tonne hour 6x0.65 994.00 3876.60
Water tanker 6 KL capacity hour 3.000 200.00 600.00
Tipper tonne.km 495 x 3 1.60 2376.00
Add 10 per cent of cost of carriage to cover cost of 237.60
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 508.13 45274.38
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 508.13 60365.84
2.36 mm to 75 micron@ 30 per cent cum 89.100 480.13 42779.58
Cost of water KL 18.000 100.00 1800.00
d) Contractor's profit @ input on (a+b) 2986.06
Cost for 225 cum = a+b+c+d 183066.47
Rate per cum = (a+b+c+d)/225 813.63
6
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
say 814.00

Analysis for 1200 mm dia NP4 Pipe


5.17 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement mortar
1:2 but excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets .

Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length each
)
1200 mm dia
a) Labour
Mate day 0.280 130.00 36.40
Mason day 1.000 130.00 130.00
Mazdoor day 6.000 120.00 720.00
b) Material
Sand at site cum 0.090 372.99 33.57
Cement at site tonne 0.070 3870.00 270.90
RCC pipe NP-4/prestressed concrete pipe including collar metre 12.500 9350.00 116875.00
at site
Granular material passing 5-6 mm sieve for class bedding cum 5.000 480.13 2400.65

d) Contractor's profit @ on (a+b+c) 11776.14


Cost for 12.5 metres = a+b+c+d 132242.66
Rate per metre= (a+b+c+d)/12.5 10579.41
say 10579.00

5.18 Providing and fixing gabion of required section including boxes


of size 1.5 m x 1m x 1m or as per shown in approved drawing
made of mechanically woven hexagonal shape wire mesh of
type 10 cm x 12 cm. Edges mechanically salvaged made of
heavily (Zinc+PVC) coated GI wire as per BS 433 mesh wire
3.4 mm dia and feed with supplying and providing 20 to 50 Kg
weight traps stones and Geotextile including conveying with all
leads and lifts and placing at required line,level,slope section
laying of geotextile between wall and backfill as per
specification and approved drawing and as directed by
Engineer.
As per Maharashtra State PWD Coastal Engineering Division
Mumbai (DSR 2005-06) ( Ref: Item.No. Rd 23 Page No. 10)
cum 1426
Trap stones cum 258.17
Geotextile m2/m3 90
Rate per cum 1774.17
Add Corporation Charges @ 5% 88.7085
Rate per cum 1862.9
say 1863.00

7
D. P. R. FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM
RATE ANALYSIS
Sr No Description Unit Quantity Rate Rs Cost Rs
5.20 Ground Improvement by removing unsitable soil and backfilling
with murrum with approved material obtained from borrow
areas having 4 days soaked CBR equal to or more than 6%,
laying in layers not exceeding 200 mm, breaking clods,
dressing to the required lines, curves grades, and watering to
OMC and compacting to 95% modified proctor density with
vibratory roller having minimum 80 - 100 kN static weight
including all lifts and leads etc. complete as directed by
Engineer and as per specification. including Excavation
,dewatering etc complete
Excavation including dewatering cum 85
Backfilling with murrum cum 33
Lead charges for murrum 18 Km cum 102.0
Royalty charges for murrum cum 35.1
Rate per cum 254.1
say 254.00

8
MEASUREMENT SHEETS
MEASUREMENT SHEET

BRIDGE ACRROSS GODAVARI RIVER


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

PART 1. PRELIMINARY WORKS

1 1.01 Clearing and grubbing road land


including uprooting all vegetation, grass,
bush shrubs,………………………. APPROCH 1

1 120 24 SQ M 2880
APPROCH 2
1 1600 24 SQ M 38400
TOTAL 41280

Ha 4.128

say Ha 4.2
2 1.02 Installation of a steel portable
barricade......................... 2 80 - - NO 160

3 1.03 Supplying and fixing the necessary sign


boards……………(QTY. considered in
road work)
- - - - - 0

4 1.04 Dismantling of structures and sorting of


the dismantled
material,……………………….(provisiona
l qty)

a) Dismantling bricks / stone masonry,


cum 200

b) Dismantling of Concrete Structures


cum 100

5 1.05 Taking one 100 mm bore hole at each


foundation location of flyover proper and
one each in approaches…………….

a) Boring in all strata.


38 16 - - RM 608

b) Drilling in hard rock.


38 4 - - RM 152

Consulting Engineering Services (I) Pvt. Ltd. 1


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

PART 2 FOUNDATION AND SUBSTRUCTURE


SR NO. ITEM NO DESCRIPTION NO. L B D UNIT QTY.
1 2.01 Earthwork in Excavation for
foundation for Structures in all types
of Strata other than rock …………

1) a) Soils of all types upto 3m open


foundation

G.L.
1x(10x2)=20 9.1 4.7 3 cum 2566.2
3 M
Anular 0.75
filli 5M
3.46 M
0.75 1
Pile
0.75 2 1.5 M
foundation
8M
0.1 M
ELEVATION 1m 1x(6x2)=12 8.7 5.2 2.4 cum 1302.91

abutment
1x(2x2)=4 10 6.2 2.4 cum 595.20
4.5
total 1898.11

PLAN well
fig. 1 open foundation
foundation
G.L.

0.5 m
1x(1x2)=2 10 10 2.6 cum 520.00
1.8 m

stair case
ELEVATION
4 2 2 1.5 cum 24.00
1.2 φ

total 5008.31

8.5
say 5009.00

5M

PLAN

fig. 2 pile foundation (pier)

Consulting Engineering Services (I) Pvt. Ltd. 2


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

b) Soils of all types greater than 3m


depth
open foundation
pier
1x(10x2)=20 9.10 4.70 2.00 cum 1710.80
say 1711.00

2) Excavation foundation of
structure in rock by wedging /
chiselling / controlled blasting or
1x(10x2)=20 9.1 4.7 1.46 cum 1249.00
line drilling and mechanical means
including………………..

2 2.02 Providing Trial Pits to find out the

utilities…………………………….

a) Soils of all types upto 3m depth


2 24 3 3 cum 432.00
b) Soils of all types greater than 3m
depth - - - - cum 0.00

3 2.03 Providing and laying in situ M15 grade volume of excavation up to 1.5m depth
bedding concrete in foundation ,annular =64.16m3
fillingbelow pile cap including……….

volume of foundation up to 1.5m depth


a) annular filling =48.96m3
1x(10x2)=20
Hence volume of annular filling
=15.2m3 cum 304.00
b) 100 mm th. p.c.c. for open
foundation foundation
1x(10x2)=20 8.2 4.7 0.1 cum 77.08
Pile
foundation
pier
1x(6x2)=12 8.7 5.200 0.1 cum 54.29
abutment
1x(2x2)=4 10.0 6.200 0.1 cum 24.80
well
foundation
1x(1x2)=2 @ area= 78.500 0.1 cum 15.70
stair case

4 2 2.0 0.1 cum 1.60

total 477.47

say 478.00

Consulting Engineering Services (I) Pvt. Ltd. 3


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

4 2.04 Providing and laying in situ M-30 grade pier


reinforced cement concrete in piles of
diameter 1.2m including shuttering @ area=
,compacting,curing e.t.c………. 6(6x2)=72 13.50 1.13 cum 1098.75

abutment

@ area=
8(2x2)=32 14.93 1.13 cum 540.06

total 1638.81

72 13.50 RM 972.00

32 14.93 RM 477.76

total 1449.76

say 1450.00

5 2.05 carrying out load


test…………………………..

a) Initial Load Test 1x750=750 - - - MT 750.00


b) Routine pile load test 2x450=900 - - - MT 900.00

c) Horizontal pile load 1x45=45 MT 45.00


- - -
6 2.06 Providing and laying in situ 600mm th behind
filter media behind abutments and return abutments
walls………… 1x(2*2)=4 9.3 0.60 5.397 cum 120.46
behind returns
1x(2*2)=4 1.2 0.60 5.397 cum 15.54
total 136.00
7 2.07 Providing and laying in situ M-30 gradeopen foundation
reinforced cement concrete in
foundations of piers , abutments and portion 2
staircase including dewatering 1x(10x2)=20 8 4.50 0.75 cum 540.00
,shuttering ,compacting,curing
e.t.c………..(ref.fig 1) portion 1
1x(10x2)=20 @ area=27.75
0.75 cum 416.25
stair case

4 1.800 1.800 0.8 cum 10.37


total 966.62
say 967.00

Consulting Engineering Services (I) Pvt. Ltd. 4


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

8 2.08 Providing and laying in situ M-30 grade


pier on open
reinforced cement concrete in RCC
piers,abutments,staircase column, RE foundation
wall,dirt wall etc…………...……
PORTION 1
2x(10x2)=40 VOLUME=(a1+a2+sqrt(a1xa2))xh/3=18.80 cum 752.00

1 3m
PORTION 2
avg.
2 16.22
1x(10x2)=20 volume =89.48 cum 1789.60
1 3m

pier on pile
0.75 foundation
3.5m

a1=7.017 PORTION 1
a1
3m
1.5 a2=5.517 1x(6x2)=12 VOLUME=(a1+a2+sqrt(a1xa2))xh/3=18.80 cum 225.60
a2

0.75m PORTION 2
2.5m

open foundation 1x(6x2)=12 volume =9.114 cum 109.37

por. 1

a1=7.017 pier on well


3m
1 foundation
a2=5.517
PORTION 1
2 1.652 VOLUME=(a1+a2+sqrt(a1xa2))xh/3=18.80 cum 37.60
PORTION 2
1x(1x2)=2 volume =5.686 cum 11.37
staircase
pile foundation
4 13 0.400 0.400 cum 8.32

ABUTMENT
a1=7.017
3m 1x(2*2)=4 9.8 1.2 2.8 cum 131.71
1
a2=5.517
RETANING WALL

2 1.031 m 1x(2*2)=4 1.8 0.50 5.397 cum 19.43


DIRT WALL
1x(2*2)=4 9.8 0.30 2.597 cum 30.54
well foundation
Total 3115.54
say 3116.00

Consulting Engineering Services (I) Pvt. Ltd. 5


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

9 2.09 Providing and laying in situ M-30 grade


RCC caps and pedestal over pier and
abutment………
9M pier caps
0.6M
1 PORTION 1
2
1.2M
1x(17*2)=34 9 3.00 0.600m CUM 550.80
5M
front view PORTION 2
3m
1x(17*2)=34 VOLUME=(a1+a2+sqrt(a1xa2))xh/3=20.63 cum 701.42

side view
pier cap
1.8m pedestal
0.4

0.6 1x(144x2)=288 0.60 0.60 0.40 CUM 41.47


0.6
pedestal total 1293.69
say 1294.00
10 2.10 providing and fixing H.Y.S.D. Steel bars
of various dimeter in foundation of
R.C.C. In piles, piles
caps,foundations,pier caps,abutment
wall, dirtwall ,pedastal as
per.....................

1) foundation of pier/column
@ 80 kg/m3 MT 77.36
2) pier/column, pier cap, abutment,dirt
wall, Retaning wall
@ 120 kg/m3 MT 524.19
3) RCC piles
@ 80 kg/m3 MT 131.10
4) pile caps
@ 100 kg/m3 MT 134.20
5) well caps
@ 120 kg/m3 MT 28.32
6) pedestal
@ 80 kg/m3 MT 3.32
7) well staning
@ 20 kg/m3 MT 19.90
8) well curb
@ 80 kg/m3 MT 14.24
total 932.63
say 935.00

11 2.11 Providing and applying one coat of zinc-


rich epoxy primer and two coats of coal
tar epoxy paint of reqd. thickness as per
specifications to all concrete surfaces in SQ-M 2620.00
contact with earth……………….

Consulting Engineering Services (I) Pvt. Ltd. 6


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

12 2.12 Providing and applying one coat Epoxy


Phenolic primer of DFT 50 micron and
two coats of Epoxy Phenolic coating of
DFT 100 microns each or any other
equivalent epoxy coating system to all
concrete surfaces exposed to
atmosphere in superstructure and SQ-M 0.00
substructure
including.............................(not
considered)

- - - -
13 2.13 Dewatering including diversion of stream
providing cofferdam bunds
etc………………………..

non perinial river 10x2=20 9.1 4.70 6.5 cum 5560.10

perinial river - - - - cum 0.00

say 5561.00
14 2.14 Sinking of well foundation in all types of
soil and murum dia.10m and depth up
to 20 m etc. ……………………. 1x(1x2)=2 19 RM 38.00

15 2.15 Providing and laying in situ M-20 grade


reinforced cement concrete in well
steining including shuttering 1x(1x2)=2 14.00 @ area= 35.51 cum 994.38
,compacting,curing e.t.c………..

say 995.00
16 2.16 Providing and laying in situ M-25 grade
reinforced cement concrete in well
1x(1x2)=2 @ area= 35.5134 2.5 cum 177.57
curb including shuttering
,compacting,curing e.t.c………..
say 178.00

17 2.17 Providing and setting out mild steel


cutting edge in well curb in situ ,
e.t.c……….. @
1x(1x2)=2 perimeter= 31.4 @ 90 kg/m MT 5.65
say 6.00

Consulting Engineering Services (I) Pvt. Ltd. 7


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

18 2.18 Providing and laying in situ M-30 grade pile cap


reinforced cement concrete in pile cap/
well cap including dewatering pier
,shuttering ,compacting,curing
1x(6x2)=12 8.5 5.00 1.8 cum 918.00
e.t.c………..(ref.fig 1)
abutment
1x(2x2)=4 9.8 6.00 1.8 cum 423.36
total 1341.36
say 1342.00
well cap
1x(1x2)=2 @ area= 78.50 1.50 cum 235.50
say 236.00
total 1578.00
19 2.19 Providing and filling in well sand/rubble
in situ ,compacting,curing e.t.c………..
1x(1x2)=2 @ area= 42.9866 13.4 cum 1152.04
1x(18x2)=36 31.7 1.5 0.332 cum 568.32
total 1720.36
say 1721.00
20 2.20 Providing and laying in situ M-15 grade
reinforced cement concrete in bottom
1x(1x2)=2 @ area= 60.7433 2.8 cum 340.16
plug ,compacting,curing e.t.c………..
say 340.00

21 2.21 Providing and laying in situ M-15 grade


reinforced cement concrete in top plug
1x(1x2)=2 @ area= 42.9866 0.3 cum 25.79
,compacting,curing e.t.c………..
say 26.00

22 2.22 Providing and installing 6 mm MS liner


for bored-cast-in-situ concrete piles
72+32=104 8 @ 180 kg/m MT 149.76
including………………………

say 150.00

Consulting Engineering Services (I) Pvt. Ltd. 8


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

PART 3
SUPERSTRUCTURE
1 3.01 Providing and fixing 12.7/15.2 mm
diameter low relaxation "prestressing
steel strands" conforming to class II @ 50 Kg/m3 MT 195.05
of IS;14268 for post tensioned girder
including say 196.00
cutting…………………………….

2 3.02 Providing and laying in position M-40


grade P.S.C. girder…………………..

1000
200 MID SECTION
100 1x(72x2)=144 30.1 @ AREA= 0.838 CUM 3630.06
1800 300 1050
200 ARING SECTION
250
650 1x(72x2)=144 0.6 @ AREA= 1.044 CUM 90.20
MID SPAN SECTION
END SECTION
1000

200 1x(72x2)=144 1 @ AREA= 1.25 CUM 180.00


60
1800
1540

TOTAL 3900.26
650
SECTION AT END

say 3901
3 3.03 Providing and fixing POT cum P.T.F.E. a) POT fixed
bearing to true line and bearing
position………………
144 CAPACITY =12 NO 144.00
) POT cum PTFE
144 CAPACITY =12 NO 144.00
4 3.04 Providing and laying in situ 240 mm
thick M-40 grade Reinforced cement DECK SLAB
concrete deck slab and 1x(18x2)=36 31.7 9.90 0.24 CUM 2711.49
diaphragm………………..

Intermediate diaphram (300mm th).


1x(72x2)=144 0.3 @ AREA= 10.45 CUM 451.44
End diaphram (600mm th.) 1x(72x2)=144 0.5 @ AREA= 9.21 CUM 663.12
TOTAL 3826.05
say 3827.00
5 3.05 Providing and laying controlled in-situ
cement concrete of M40 grade in Box
Girders including……………………(no
box girder) - - - - cum 0.00

Consulting Engineering Services (I) Pvt. Ltd. 9


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

6 3.06 Providing and fixing H.Y.S.D. Fe-415


steel bars of various diameter for all RCC
work in superstructure …...

1) psc girder @ 100 kg/m3 MT 390.10


2)deck slab, diphrams @ 120 kg/m3 MT 459.24
3) waist slab, landing slab @ 80 kg/m3 MT 1.793
4) r .c.c. beams @ 120 kg/m3 MT 1.43
TOTAL 852.56
say 853.00
7 3.07 Providing and applying one coat of
phenolic primer ….. ..(QTY. not
considered)
- - - - SQ-M 0.00

8 3.08 Providing and applying 3 coats of water


based cement paint of approved quality
to the inner concrete - - - - SQ-M 0.00
surfaces…………….

9 3.09 providing and carrying out load


test………
1 - - - NO 1
@ 120T ,SUPERIMPOSED

10 3.10 providing and laying RCC M-30 in waist


slab,landing slab,rcc beams………..

waist slab
16.0 2.891 1.500 0.150 cum 10.41
steps
2X9X8=144 1.5 @ AREA= 0.030 cum 6.48
landing slab
16.000 3 1.0 0.250 cum 12.00

rcc beams 20.000 4.400 0.230 0.350 cum 7.08


20.000 3.000 0.230 0.350 cum 4.83

total 40.80

say 41.00
11 3.11 providing and fixing chequired
tiles………….. 16.00 9.3m2 sq. m 148.80
plan area =
say 149.00

Consulting Engineering Services (I) Pvt. Ltd. 10


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

PART 4 MISCELLANEOUS
1 Providing and casting RCC Crash
4.01 Barrier in M40 controlled concrete with 1(1x2)=2 215.1 RM 430.2
cast-in-situ or precast members as per
detailed drawings
including……………………. SAY 431

2 4.02 Providing and laying 100 mm HDPE


pipe in true line and level inside
the…………

10x18=180 31.7 5706


3 4.03 providing and laying M-25 grade slab
RCC in ………

1) footpath cover slab


1x(18x2)=36 31.70 1.50 0.100 cum 171.18
2) median
1x(18x2)=36 31.70 0.6 0.302 cum 206.79
3) edge beam/railing beam
1x(15x2)=30 31.70 0.3 0.362 cum 103.28
4) road kerb
1x(18x2)=36 31.70 @ area = 0.0604 cum 68.93

TOTAL 550.17

say 550.00
4 4.04 Providing and fixing H.Y.S.D. Steel bars
of various diameter ………

1) footpath cover slab @ 50 kg/m3 MT 8.56


2) edge beam @ 75 kg/m3 MT 7.75
3) road kerb @ 50 kg/m3 MT 3.45
4) Median @ 50 kg/m3 MT 10.34
TOTAL 30.09

say 31.00
5 4.05 Providing and applying one coat Epoxy
Phenolic primer of DFT 50 micron and
two coats of Epoxy Phenolic coating of
SQ-M 0.00
DFT 100 microns each or any other
equivalent epoxy coating system to all
concrete surfaces exposed to
atmosphere in superstructure and
……….......

Consulting Engineering Services (I) Pvt. Ltd. 11


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

6 4.06 Providing and fixing G.I. Drainage spouts


of 100 mm dia including grating with
suitable clean out fixtures including 6x(18x2)=216 NOS 216.00
……………………

7 4.07 Providing and fixing G.I. Longitudinal


runner pipe 150mm. - - RM 0.00
dimeter………………...

SAY 0.00
8 4.08 Providing and fixing 150 mm dia. GI
down take pipes including…………….
216 2.00 - - RM 432.00

9 4.09 Providing and constructing catch pit


0.90 m x 0.45 m x 1.2 m
2 - - - NOS 2.00
deep……………………….

10 4.10 Providing and fixing precast concrete


300 mm dia. pipes, type
NP3,…………………………. 2 15.00 - - RM 30.00

11 4.11 Providing and fixing in position strip seal


type expansion joints as per detailed
drawing and approved specifications for
19 19.80 RM 376.2
movement up to 40mm…………………..

SAY 377
12 4.12 Providing and applying primer coat using
bituminous emulsion……………………
1x(18x2)=36 31.70 7.5 - sq-m 8559

13 4.13 Providing and applying tack coat using


bituminous emulsion or cut back primer
over primed / black top surface 1x(18x2)=36 31.70 7.5 - sq-m 8559
………………..

14 4.14 providing and laying mastic asphalt coat


@12mm th. over the prepeard surface of 1x(18x2)=36 31.70 7.5 - sq-m 8559
deck slab.

15 4.15 providing and laying dense bituminous


macadam @ 50mm thick………………
1x(18x2)=36 31.70 7.5 0.50 cum 4279.50

SAY 4280.00
16 4.16 providing and laying bituminous
concrete @25mm 1x(18x2)=36 31.70 7.5 0.25 cum 2139.75
thick……………………

SAY 2140.00

Consulting Engineering Services (I) Pvt. Ltd. 12


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

17 4.17 Providing & fixing discontinuous M25


PCC precast kerb stonesof size 600 x 400 - - - NOS 400.00
300 x 1200 mm……………….

18 4.18 Providing and fixing four pillars,one at


each corner of each of the bridge of
approved architectural…………….. 4 @ 2 m2 - sq-m 8.00

19 4.19 Road Markings………(considerd in road


work) - - - - - 0.00

20 4.20 Providing & fixing in position 100 mm


Dia. A.C. pipes as……………………. 100 - - - NOS 100.00

21 4.21 Providing & fixing in position MS Railing


over RCC Crash Barrier and for
staircase including…………….

1) crash barrier
1(1x2)=2 215.1 RM 430.2
2) staircase
52 RM 52.00

total 482.20

SAY 483.00
22 4.22 Providing & Fixing Bituminous Filler
Pad………………… 18 31.7 - - RM 570.60

SAY 571.00
23 4.23 Providing and casting RCC Facia
pannel in M30 - - - - - 0.00
controlled……………………..
24 4.24 Construction of RCC railing of M20
Grade in-situ with 20 mm nominal size
aggregate…………………. 1x(15x2)=30 31.7 RM 951.00

25 4.25 Providing and filling behind abutment


and return wall with selected fill of
approved quality ……………………… 1x(2*2)=4 8.7 1.20 5.397 cum 225.38

SAY 226.00

26 4.26 Providing and fixing Neoprene bearing cu.centi


…………………….. meter
- - - - 0.00

Consulting Engineering Services (I) Pvt. Ltd. 13


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

PART 5 APPROACHE
1 5.01 S
Excavation for foundation of structures
including dewatering, shoring and
strutting as necessary and backfilling the R. E. WALL 120x2=240 1.5 1.5 cum 540
trenches with
………………………………..
Gabian wall 1600 24 1.5 cum 57600
total 58140
2 5.02 Providing and laying in situ PCC M30
grade bedding concrete below facia 1x(2x1)=2 120 0.6 0.3 cum 43.2
element / foundation
including………………………… SAY 44
3 5.03 Providing & fixing of precast facia
elements in RCC M30 grade for 1x(1*2)=2 120 avg.ht= 3.963 SQ-M 951
reinforced soil embankment for
approach ……………………….

4 5.04 Providing and laying in-situ RCC M-30


grade friction
1x(2*1)=2 120 3.45 0.25 cum 207.00
slab…………………………..

say 207.00
5 5.05 Providing and fixing in position HYSD
Fe415 reinforcing bars of various
diameters for the above all RCC works @ 100 kg/m3 MT 20.7
f F i ti Sl b
say 20.0
6 5.06 Providing earth work in embankment by
using mechanical means with approved
material obtained from
borrow……………………………….

1) R.E.WALL R. E. WALL 120 18.4 2.962 cum 6540.10

say 6541.00
7 5.07 Providing 300mm thick layer of earth
work in embankment by using
mechanical - - - - cum 0
means…………….(considered in road
work)

8 5.08 Providing and laying Granular Sub Base


(Structural layer ) Close Graded
conforming ……………….(considered in - - - - cum 0
road work)

Consulting Engineering Services (I) Pvt. Ltd. 14


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

9 5.09 Providing, laying,spreading and


compacting specified graded crush
stone in Granular Sub Base course
(drainage layer) - - - - cum 0
including……………………(considered
in road work)

10 5.10 Providing and laying Dry Lean Concrete


base including providing coarse and fine
aggregate……………….. (considered in
road work) - - - - cum 0

11 5.11 Providing and applying tack coat using


bituminous emulsion or cut back primer
over primed / black top
surface……………(considered in road - - - - cum 0
work)

12 5.12 Providing and applying tack coat using


bituminous emulsion or cut back primer
over primed / black top surface with
emulsion………………..(considered in - - - - cum 0
road work)

13 5.13 Providing and laying Pavement Quality


Concrete of M 35 grade obtained from
approved including
……………..(considered in road work) - - - - cum 0

14 5.14 Providing and laying 40-100 mm thick


compacted Dense Bituminous Macadam
layer using B.T. chips
- - - - cum 0
…………………(considered in road
work)

15 5.15 Providing and laying Bituminous


Concrete in a single layer of 25mm to 50
mm compacted thickness on prepared
surface using modified bitumen of grade
- - - - cum 0
approved by…………………(considered
in road work)

Consulting Engineering Services (I) Pvt. Ltd. 15


DPR FOR ROAD DEVELOPMENT IN NANDED UNDER JNNURM
(ROAD NO.-10 )
(From Ch: 0+460 TO 2+750 )
MEASUREMENT SHEET
REF.DRG. NO.-2006069/BS/GAD-11/12 DATE:17/02/07

SR NO.
ITEM
DESCRIPTION NO. L B D UNIT QTY.
NO

16 5.16 Providing, laying,spreading and


compacting specified graded stone
aggregate to Wet mix macadam in layer
of not exceeding 200 mm thk - - - - cum 0
compacted
including…………….(considered in road
work)
17 5.17 Providing and laying in position precast
RCC pipes NP4 prestressed concrete
pipes for
- - - - cum 0
culverts………………………(considered
in road work)

18 5.18 Providing and fixing of mechanically up to 6.5m ht.


woven Double Twisted Hexagonal
shaped wire mesh Gabian boxes of 2 480 16 m3/m cum 15360
required section up to 5.5m ht.
…………………………………………..(
note - +/- 0.5m variation in G.L. is 2 760.0 12.25 m3/m cum 18620
considered in calculating quantities) up to 4.5m ht.
2 410.0 9 m3/m cum 7380
total 41360

19 5.19 Backfilling in Gabian wall wall with vol. Of filling = total vol. At respective ht. - vol. Of gabian at that ht.
approved material……….
up to 6.5m ht.

1 480 21.3 ( 6.5 - 1) = 5.5 cum 40872


up to 5.5m ht.
1 760.0 21.3 ( 5.5 - 1) = 4.5 cum 54226
up to 5.5m ht.
1 410.0 21.3 ( 4.5 - 1) = 3.5 cum 23903

total 119001

20 5.20 Ground Improvement by removing


unsitable soil and backfilling with murrum
1 1600.0 24 1.5 cum 57600.0
……………………….

Consulting Engineering Services (I) Pvt. Ltd. 16


MEASUREMENT SHEET

ROB AT HINGOLI GATE


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

1.01 Clearing & Grubbing the


2
Project Area 764.750 24.000 m 18354.00
Say , 19000.00
i.e. Ha 2.00

1.02 Barricade on both sides of


Bridge during construction
at a distance of 2.5 m
2 764.75 / 2.5 + 1 Nos. 614
Say , 620

1.03 Signage Boards (Already covered in Road Works)

1.04 Dismantling existing


Structures

Existing P.C.C. Median Kerb


for a length equal to
Viaduct portion which
covers existing road 3
500.000 1.200 0.500 m 300.00
alignment

1.05 Soil Investigations -

Boring in all strata except


A Rock 22 20.000 440.00
Say , 500.00

B Drilling in Hard Rock 22 5.000 110.00


Say , 125.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 1 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.01 Excavation -

2.01.- i In Soil -

A Abutment Pile Caps 2x2 9.650 5.600 2.150 m3 464.74


Say , 465.00

B Pier Pile Caps -

1 P10 & P11 (Railway Span) 2x2 7.800 7.800 2.450 m3 596.23
Say , 600.00

2 P14 & P15 (42.5m Span) 2x2 7.800 7.800 2.450 m3 596.23
Say , 600.00

3 P1, P2, P5, P8, P12, P16 and


P19 (fixed Piers) m
3
2x7 6.600 5.600 2.150 1112.50
Say , 1115.00

4 P3, P4, P6, P7, P9. P13, P17,


P18 & P20 (free Piers) m
3
2x9 6.600 6.600 2.150 1685.77
Say , 1690.00

Total = 4470.00
Say , 4500.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 2 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.01.- ii In Rock -

Nominal Quantity (5% of


3
Quantity for Soil) 0.05 * 4500 = m 223.50
Say , 300.00

3
2.02 Trial Pit - 6 24.000 3.000 3.000 m 1296.00
Say , 1300.00

2.03 M15 Levelling course (150


thk.) below Pile Cap

3
2.03.1 Abutment Pile Caps 2x2 9.650 5.600 0.150 m 32.42

2.03.2 Pier Pile Caps -

1 P10 & P11 (Railway Span) 2x2 7.800 7.800 0.150 m3 36.50

2 P14 & P15 (42.5m Span) 2x2 7.800 7.800 0.150 m3 36.50

3 P1, P2, P5, P8, P12, P16 and


P19 (fixed Piers) m
3
2x7 6.600 5.600 0.150 77.62

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 3 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

4 P3, P4, P6, P7, P9. P13, P17,


P18 & P20 (free Piers) m
3
2x9 5.600 5.600 0.150 84.67
Say , 85.00

Total = 268.05
Say , 268.00

2.04 Drilling / Boring &


Concrete in R.C.C. Piles
(for 14.0m Length above
founding level)

2.04.1 1000 mm Dia. Piles -

(Considering 3 x Dia. Of
Piles = 3.0m Additional
length of Embedment
below founding level)

A P1, P2, P5, P8, P12, P16 and


P19 (fixed Piers)
2x8x7 14.000 Rm 1568.00
Say , 1568.00

B P3, P4, P6, P7, P9. P13, P17,


P18 & P20 (free Piers)
2x6x9 14.000 Rm 1512.00
Say , 1512.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 4 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

C Abutments - A1 and A2 2x8x2 14.000 Rm 448.00


Say , 448.00

Subtotal = 3528.00
Say , 3600.00

2.04.2 1200 mm Dia. Piles

(Considering 3 X Dia. Of
Piles = 3.6m Additional
length of Embedment
below founding level)

A P10 & P11 (Railway Span) 2x8x2 14.000 Rm 448.00


Say , 450.00

B P14 & P15 (42.5m Span) 2x8x2 14.000 Rm 448.00


Say , 450.00

Subtotal = 900.00
Say , 900.00

2.06 600 Thick Filter Media


behind Abutments 2x2 8.600 0.600 6.187 m3 127.70
Say , 130.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 5 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.08 M30 Grade concrete in


R.C.C. Abutment Walls,
Dirt Walls and Pier shafts

3
2.08.1 Abutment Walls 2x2 8.600 1.500 3.250 m 167.70
Say , 170.00

3
2.08.2 Piers - Straight Portion 2 x 20 Plan Area = 2.517 m2 4.500 m 453.06
Say , 454.00

2.08.3 Flare Portion Common for all 2 x 20 Avg. Plan Area of


Piers at Top of variable Area 2.517 m2 At Base &
of 2.0m Height 7.142 m2 At Top = 3
2.000 m 386.36
Say , 387.00

Subtotal = 1011.00
Say , 1015.00

2.08.4 Dirt Walls 2x2 8.600 2.381 0.300 m3 24.57


Say , 25.00

Total = 1040.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 6 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.09 M30 Grade concrete in


R.C.C. Abutment Caps,
Pier Caps & Pedestals

3
2.09.1 Abutment Caps 2x2 8.600 1.500 0.200 m 10.32
Say , 11.00

2.09.2 Pier Caps

3
A For Piers except Piers of 2 x 18 C.S. Area = 6.6 m2 2.6 m 617.76
Say , 618.00

B Piers of Portal Frame 2x2 8.600 1.000 1.200 m3 41.28


Say , 42.00

Subtotal = 660.00

2.09.3 Pedestals on Abutment Cap 2x2x3 0.500 0.500 0.300 m3 0.90


Say , 1.00

2.09.4 Pedestals on Pier Cap -

3
1 On Pier P1 of Span A1-P1, for 2 x 3 x 19 0.500 0.500 0.300 m 8.55
Say , 9.00

2 For Span P14-P15 2x2 0.500 0.500 0.300 m


3
0.30
Say , 1.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 7 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

3 For Span P1-P2, P2-P3 and


3
Span P3-P4 2x5x3 0.500 0.500 0.300 m 2.25
Say , 3.00

Subtotal = 14.00

Total = 685.00

2.10 HYSD Reinforcement in


Diff. Structural Members
mentioned under -

Rerring Concrete Quantities,


3
Concrete Quantity kg/m HYSD Qty. in 'kg'

2.10.1 R.C.C. Piles

A 1000 mm Dia. Piles 0.785 m2 3600.000 100 282743

B 1200 mm Dia. Piles 1.131 m2 900.000 100 101788

Subtotal = 384531
Say , 385000

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 8 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.10.2 R.C.C. Pile Caps 2680.000 125 335000


Say , 335000

2.10.3 R.C.C. Abutment Walls,


Straight and Flared Portion
of R.C.C. Piers 1015.000 100 101500
Say , 102000

2.10.4 R.C.C. Abutment Caps 11.000 80 880


Say , 1000

2.10.5 R.C.C. Pier Caps 660.000 125 82500


Say , 83000

2.10.6 R.C.C. Pedestals on


Abutment Cap and Pier Cap 14.000 80 1120
Say , 1200

2.10.7 R.C.C. Dirt Wall 25.000 80 2000


Say , 2000

Total = 909200
Say , 913000

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 9 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.11 Coal Tar Epoxy Paint for


Structures below Ground
Level or in contact with
the Earth

2
2.11.1 Abutments 2x2 8.600 6.187 m 212.83
Say , 220.00

2
2.11.2 Piers 2 x 20 Perimeter = 5.712 m 0.500 m 114.24
Say , 120.00

2.11.3 Abutment Pile Caps - Top 2x2 9.350 5.300 m2 198.22


Say , 200.00

2.11.4 Pier Pile Caps - Top

1 P10 & P11 (Railway Span) 2x2 7.800 7.800 m2 243.36


Say , 250.00

2 P14 & P15 (42.5m Span) 2x2 7.800 7.800 m2 243.36


Say , 250.00

3 P1, P2, P5, P8, P12, P16 and


P19 (fixed Piers) m
2
2x7 5.600 5.600 125.44
Say , 130.00

4 P3, P4, P6, P7, P9. P13, P17,


P18 & P20 (free Piers) m
2
2x9 5.600 5.600 125.44
Say , 130.00

2.11.5 Abutment Pile Caps - Sides 2 x 2 Perimeter = 28.9 m 0.500 m2 57.80

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 10 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

Say , 60.00

2.11.6 Pier Pile Caps - Sides

1 P10 & P11 (Railway Span) 2 x 2 Perimeter = 30.0 m 0.500 m2 60.00


Say , 60.00

2 P14 & P15 (42.5m Span) 2 x 2 Perimeter = 30.0 m 0.500 m2 60.00


Say , 60.00

3 P1, P2, P5, P8, P12, P16 and


P19 (fixed Piers) 0.500 m
2
2 x 7 Perimeter = 23.2 m 162.40
Say , 170.00

4 P3, P4, P6, P7, P9. P13, P17,


P18 & P20 (free Piers) 0.500 m
2
2 x 7 Perimeter = 21.2 m 148.40
Say , 150.00

Total = 1800.00
Say , 1800.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 11 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.18 M30 Grade concrete in


R.C.C. Pile Cap

3
2.18 - i Abutment Pile Caps 2x2 9.350 5.300 1.500 m 297.33

2.18 - ii Pier Pile Caps -

3
1 P10 & P11 (Railway Span) 2x2 7.800 7.800 1.800 m 438.05

2 P14 & P15 (42.5m Span) 2x2 7.800 7.800 1.800 m3 438.05

3 P1, P2, P5, P8, P12, P16 and


P19 (fixed Piers) m
3
2x7 5.600 5.600 1.500 658.56

4 P3, P4, P6, P7, P9. P13, P17,


P18 & P20 (free Piers) m
3
2x9 5.600 5.600 1.500 846.72

total of above = 2678.71


Say , 2680.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 12 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

2.22 6 mm thick M.S. Liner

For 1200 mm Dia. Piles for


Pier P10 & P11 supporting
Perimeter
31.25m Railway Span upto
= ( 3.142 *
founding level
2x8x2 10.100 1.216 m 0.006 MT 58.16
Say , 60.00

3.01 H.T. Steel in PSC Girders

3.01.1 PSC I - Girders + Diaphragms Conc. Quantity = 2802 m3 45 = 126090

3.02.2 PSC Box Girders + Diaphragms Conc. Quantity = 462 m3 45 = 20790

Total = 146880
Say , 147000

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 13 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

3.02 M40 Grade concrete in


P.S.C. I - Girders & Diaph.

To account for Web


thickening, future
prestressing blocks, etc.C.S.
Area of Girder is increased by
20% for Quantity
Calculations.

3.02.1 For 23.50 m Span

3
A PSC I Girders 2x3x6 23.400 0.801 m2 x 1.20 m 809.71

B End Diaphragms 2x2x6 8.297 m2 0.500 m3 99.56

C Intermediate Diaphragms 2x1x6 9.500 m2 0.300 m3 34.20

Subtotal = 943.48

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 14 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

3.02.2 For 24.50 m Span

A PSC I Girders 2 x 3 x 10 24.400 0.801 m2 x 1.20 m3 1407.20

B End Diaphragms 2 x 2 x 10 8.297 m2 0.500 m3 165.94

3
C Intermediate Diaphragms 2 x 1 x 10 9.500 m2 0.300 m 57.00

Subtotal = 1630.14

3.02.3 For 31.25 m Span

A PSC I Girders 2x3x1 31.150 0.875 m2 x 1.20 m3 196.25

B End Diaphragms 2x2x1 9.508 m2 0.500 m3 19.02

C Intermediate Diaphragms 2x2x1 10.974 m2 0.300 m3 13.17

Subtotal = 228.43

Total = 2802.05
Say , 2802.00

3.03 Bearings -

A POT PTFE Bearings -

a) Vertical Capacity - 180 t 126 Nos. 126


b) Vertical Capacity - 200 t 6 Nos. 6
c) Vertical Capacity - 250 t 4 Nos. 4

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 15 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

B POT Bearings -

a) Vertical Capacity - 180 t 66 Nos. 66


b) Vertical Capacity - 200 t 6 Nos. 6
c) Vertical Capacity - 250 t 4 Nos. 4

3.04 M40 Grade concrete in


R.C.C. Deck Slab over PSC
I -Girders & in 15.0m Span
Superstructure for Span
P1-P2, P2-P3 & P3-P4

3
3.04.1 For 23.50 m Span 2x6 23.500 8.600 0.250 m 1818.90
Say , 1819.00

3.04.2 For 24.50 m Span 2 x 10 24.500 8.600 0.250 m3 1053.50


Say , 1054.00

3.04.3 For 31.25 m Span 2x1 31.250 8.600 0.250 m3 134.38


Say , 135.00

Subtotal = 3008.00
Say , 3010.00

3.04.4 Superstructure for 15.0m


Typical Span P1-P2, P2-P3
& P3-P4 2x3 15.000 8.600 1.200 m
3
928.800
Say , 930.00

Total = 3940.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 16 OF 24


LAYOUT OF DIFFERENT TYPES OF BEARINGS AND DESIGN VERTICAL LOAD

Bearing Type of Abutment Side w.r.t. Bearings per No. of Total No.of Vertical Load
Notation Bearing / Pier No. C.L. of Pier Carriageway Carriageways Bearings Capacity "t"

FR - 200 POT PTFE A1 Hingoli 3 2 6 200.0


FX - 200 POT P1 Hingoli 3 2 6 200.0
E - 150 Elastomeric P1 Banda 5 2 10 150.0
E - 150 Elastomeric P2 ----- 5 2 10 150.0
E - 150 Elastomeric P3 ----- 5 2 10 150.0
E - 150 Elastomeric P4 Hingoli 5 2 10 150.0
FR - 200 POT PTFE P4 Banda 3 2 6 200.0
FX - 200 POT P5 Hingoli 3 2 6 200.0
FX - 200 POT P5 Banda 3 2 6 200.0
FR - 200 POT PTFE P6 Hingoli 3 2 6 200.0
FR - 200 POT PTFE P6 Banda 3 2 6 200.0
FR - 200 POT PTFE P7 Hingoli 3 2 6 200.0
FR - 200 POT PTFE P7 Banda 3 2 6 200.0
FX - 200 POT P8 Hingoli 3 2 6 200.0
FX - 200 POT P8 Banda 3 2 6 200.0
FR - 200 POT PTFE P9 Hingoli 3 2 6 200.0
FR - 200 POT PTFE P9 Banda 3 2 6 200.0
FR - 200 POT PTFE P10 Hingoli 3 2 6 200.0
FR - 250 POT PTFE P10 Banda 3 2 6 250.0
FX - 250 POT P11 Hingoli 3 2 6 250.0
FR - 200 POT PTFE P11 Banda 3 2 6 200.0
FX - 200 POT P12 Hingoli 3 2 6 200.0
FX - 200 POT P12 Banda 3 2 6 200.0
FR - 200 POT PTFE P13 Hingoli 3 2 6 200.0
FR - 200 POT PTFE P13 Banda 3 2 6 200.0
FR - 200 POT PTFE P14 Hingoli 3 2 6 200.0
FR - 300 POT PTFE P14 Banda 2 2 4 300.0
FX - 300 POT P15 Hingoli 2 2 4 300.0
FR - 200 POT PTFE P15 Banda 3 2 6 200.0
FX - 200 POT P16 Hingoli 3 2 6 200.0
FX - 200 POT P16 Banda 3 2 6 200.0
FR - 200 POT PTFE P17 Hingoli 3 2 6 200.0

TAKE OFF_HINGOLI ROB_2/18/2007 3:02 PM


Bearing Type of Abutment Side w.r.t. Bearings per No. of Total No.of Vertical Load
Notation Bearing / Pier No. C.L. of Pier Carriageway Carriageways Bearings Capacity "t"

FR - 200 POT PTFE A1 Hingoli 3 2 6 200.0


FX - 200 POT P1 Hingoli 3 2 6 200.0
E - 150 Elastomeric P1 Banda 5 2 10 150.0
E - 150 Elastomeric P2 ----- 5 2 10 150.0
E - 150 Elastomeric P3 ----- 5 2 10 150.0
E - 150 Elastomeric P4 Hingoli 5 2 10 150.0
FR - 200 POT PTFE P17 Banda 3 2 6 200.0
FR - 200 POT PTFE P18 Hingoli 3 2 6 200.0
FR - 200 POT PTFE P18 Banda 3 2 6 200.0
FX - 200 POT P19 Hingoli 3 2 6 200.0
FX - 200 POT P19 Banda 3 2 6 200.0
FR - 200 POT PTFE P20 Hingoli 3 2 6 200.0
FR - 200 POT PTFE P20 Banda 3 2 6 200.0
FR - 200 POT PTFE A2 Hingoli 3 2 6 200.0

QUANTITY OF BEARINGS

FR - 200 POT PTFE 63 2 126


FX - 200 POT 33 2 66
E - 150 Elastomeric 20 2 40
FR - 250 POT PTFE 3 2 6
FX - 250 POT 3 2 6
FR - 300 POT PTFE 2 2 4
FX - 300 POT 2 2 4

Total = 252

LOCATION OF EXPANSION JOINTS

A1 P1 P4 P7 P10
10 Nos . X 17.20 m = 172.0 m
P11 P14 P15 P18 A2

TAKE OFF_HINGOLI ROB_2/18/2007 3:02 PM


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

Say , 3940.00

3.05 M40 Grade concrete in


PSC Box Girder for 42.50
m.Span P14-P15

To account for Web


thickening, future
prestressing blocks, etc.C.S.
Area of Girder is increased by
20% for Quantity
Calculations.

3
3.05.1 PSC Box Girder 2x1 42.500 4.800 m2 x 1.20 m 408.00
Say , 408.00

3.05.2 End Diaphragms 2x2x1 12.635 m2 0.600 m3 30.32


Say , 31.00

3.05.3 Intermediate Diaphragms 2x3x1 12.635 m2 0.300 m3 22.74


Say , 23.00

Total = 462.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 17 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

3.06 HYSD Reinforcement in


Diff. Structural Members
mentioned under -

Rerring Concrete Quantities,


3
Concrete Quantity kg/m HYSD Qty. in 'kg'

3.06.1 PSC I - Girders + Diaphragms 2802.000 100 280200


Say , 280200

3.06.2 PSC Box Girder & Diaphragms 462.000 150 69300


Say , 69300

3.06.3 R.C.C. Deck Slab


Superstructure 930.000 150 139500
Say , 139500

3.06.4 R.C.C. Deck Slab on PSC I


Girders 3010.000 120 361200
Say , 362000

Total = 851000
Say , 851000

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 18 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

4.01 RCC Anticrash barrier

For both sides of deck 2 504.75 +


120 + 140
= 764.75 Rm 1529.50
Say , 1530.00

4.02 100 mm HDPE pipe inside


Crash Barrier Rm 1529.50
Say , 1530.00

4.03 R.C.C. Median Kerbs 2 0.300 0.600 504.750 m


3
181.71
Say , 185.00

4.04 HYSD Reinforcment

B R.C.C.Median Kerbs 185.000 50 kg/m3 9250


Say , 9500

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 19 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

4.06 Drainage Spouts -

For 3.0m c/c spacing, 2 504.75 / 3.0 +1 Nos. 339

4.07 Longitudinal Runner Pipes -

Along Viaduct Length 2 505 Rm 1010

4.08 Downtake Pipes -

From Deck to Pier Cap Top 339 + 2.0 + 0.500 = 2.75 m Rm 930.88
Say , 940.00

4.11 Expansion Joint (Strip


Seal)

For Movement above 50 mm 10 17.200 Rm 172.00

4.12 Primer coat using


2
bituminous emulsion …. 2 504.750 7.50 m 7571.250
Say , 7580.00

4.13 Tack Coat 2 504.750 7.50 m


2
7571.25
Say , 7580.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 20 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

4.14 Mastic Asphalt ( 12mm thick) 2 504.750 7.50 m


2
7571.250
Say , 7580.00

4.15 D.B.M. (50mm thick) 2 764.750 7.50 0.05 m


3
573.56
Say , 580.00

4.16 B.C. (25mm thick) 2 764.750 7.50 0.025 m


3
286.78
Say , 290.00

4.20 100 Dia Weep Holes -

For 2.0m c/c spacing, 2 x 24 Nos. 48

4.21 M.S. Railing on Crash


Barrier Rm 1529.50
Say , 1530.00

4.22 20 mm thick filler


material between 2 Decks 504.750 Rm 504.750
Say , 505.00

4.26 Elastomeric Bearings


Vertical Capacity - 200 t 40 40.000 25.000 7.5 cm3 300000

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 21 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

5.01 Excavation for Bedding for


R.E. Walls

On Hingoli side 2 120.000 0.900 0.600 m3 129.60


Say , 130.00

On Banda Ghat side 2 120.000 0.600 0.300 m3 43.20


Say , 45.00

Total = 175.00
Say , 180.00

5.02 R.C.C. Bedding Concrete in


footing of R.E. Wall

On Hingoli side 2 120.000 0.600 1.800 m3 259.20

3
On Banda Ghat side 2 140.000 0.600 1.800 m 302.40

Total = 561.60
Say , 565.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 22 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

5.03 Reinforced Earth Wall


(Facia Panel Area)

Including Reinf., C.S. Area.


Considering Average Ht. of
0.50m to 5.00m above
Ground Level = 2.75 + 1.5 =
4.25 m

On Hingoli side 2 120.000 4.250 m2 1020.00


Say , 1020.00

On Banda Ghat side 2 140.000 4.250 m2 1190.00


Say , 1190.00

Total = 2210.00
Say , 2210.00

5.04 R.C.C. Concrete in friction


Slab

On Hingoli side 2 120.000 2.500 0.300 m2 180.00


Say , 180.00

On Banda Ghat side 2 140.000 2.500 0.300 m2 210.00


Say , 210.00

Total = 390.00
Say , 400.00

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 23 OF 24


DETAILED PROJECT REPORT FOR DEVELOPMENT OF NANDED CITY ROADS UNDER JNNURM

Calculated by : M.M.Phatak
Checked by : P.P. Kundargi
R.O.B. AT HINGOLI Date : September 2006

Item No. Description No. Length Breadth Depth Unit Quantity

5.05 HYSD Reinforcment in


friction Slab

On Hingoli side 180.000 100 kg/m3 18000


Say , 18000

On Banda Ghat side 210.000 100 kg/m3 21000


Say , 21000

Total = 39000
Say, = 40000

TAKE OFF_HINGOLI ROB_2/18/2007 3:01 PM 24 OF 24

You might also like