Professional Documents
Culture Documents
978-1-4244-8417-1/11/$26.00 ©2011
2
behavior of an HPWH is depicted in Fig. 1. This model amount of hot water in the tank Etank is calculated by (1).
consists of three units; control unit, start unit and thermal
storage unit. The parameters are shown in Table I. The Etank Einitial Euse Eheated (1)
condition of COPs of the HPWHs in this paper is presented in
section III and IV. The input of this model is the control signal where Einitial is the initial hot water amount and Euse is the
to an HPWH whereas the output is the power consumption of amount of used hot water which is the integral of the amount
an HPWH. In the previous research [3], the frequency analysis of hot water used per second Puse.
was performed by the numerical simulation based on a The excess of Euse over the sum of Einitial and Eheated is
number of the detailed HPWH models. It was assumed that considered as the shortage of hot water Eshortage. The
hot water demand was different from customer to customer occurrence of shortage of hot water Eshortage is assumed not to
and that all the HPWHs had the same rated power make any impact on the amount of used hot water Puse and Euse
consumption, capacity of hot water tank, and value of COP. later. The criterion of customers’ convenience in this paper is
Control Unit 0.1PHP Rhp whether the shortage of hot water Eshortage occurs or not and
Control Signal
1
Thpcs+1
1
Tims+1 whether the requested amount of hot water Erequest is
Control Delay -0.1PHP Rate Limiter Delay of IM completed to be heated or not.
Start Unit 0.9PHP
1
Start Reference Tstarts+1
0 Start Delay III. LUMPED HPWH MODEL
Emax
Einitial A. HPWH Control System
Euse k>0
Puse 1
s
KN Etank min
Power Figure 2 shows the HPWH control system assumed in this
Consumption
1 KN
0
0
Erequest k<0 paper [3]. It is a hierarchical control system which consists of
s 0
Normalization
-1 Eshortage two hierarchies, i.e. local control centers and a central load
Eheated dispatching center. The control area of each local control
1
Thps+1
COP center is the same size as that of each distribution substation.
Conversion Delay A number of HPWHs are under the control of the local control
Thermal Storage Unit
centers. A two-way communication network is assumed. A
Fig. 1. Detailed HPWH model.
lumped model proposed in this paper is designed to simulate
TABLE I the behavior of a number of HPWHs under the control of one
PARAMETERS OF DETAILED HPWH MODEL local control center.
P HP Rated Power Consumption [kW] 1.0 / 1.3
E max
Each local control center collects the information on its
Thermal Capacity of Hot Water Tank [kWh] 20 / 26
T start Start Delay [s] 300
HPWHs and sends it to the central load dispatching center.
T hpc Control Delay [s] 30 Based on the information, the central load dispatching center
R hp Rate Limiter [%kW/s] 1 generates a LFC signal for the whole HPWHs and sends it to
T ig Delay of Induction Motor [s] 1 the HPWHs via the local control centers. The LFC signal is
T hp Conversion Delay [s] 300 generated based on the coordinated LFC method proposed in
KN Nomalization Coefficient [h/s] 1/3600 the previous research [3] [4]. As is shown in Fig. 3, the LFC
signal is dispatched not only to the conventional power plants
The start unit is modeled for operation from zero to the (LFC generators) but also to the BESS and the HPWHs
steady-state power consumption, 90% of the rated power according to the magnitude and period of the Area
consumption here, which is approximated by the first-order Requirement (AR).
model with the time delay of 300 seconds on the basis that the
power consumption of an air conditioner for home use Local
ControlCenter
becomes stable 0.25 [h] after start.
The control unit is designed on the assumption that the 䞉
HPWH HPWH 䞉䞉䞉 HPWH HPWH
power consumption of an HPWH can be controlled in the
䞉
䞉
that is consumed without the input control signal, and that ± CentralLoad
DispatchingCenter
[MW]
to input LFC signal.
BESS
HPWH
local control center. The total power consumption on start-up
Period
[s] or [min]
is approximated by a ramp function which is to be 90 % of the
Fig. 3. Conceptual image of LFC dispatching method. total rated power consumption of the HPWHs at 0.5 [h] after
B. Control Method of HPWHs start. The change of the total power consumption after the
HPWHs begin to stop heating is approximated by the normal
The HPWHs are controlled by each local control center.
distribution function based on the average value TAVG and the
Each local control center grasps the information on the
standard deviation TSD of the estimated heating period Theat
number of its HPWHs with several kinds of rated power
calculated by (3). The lumped HPWH model developed here
consumption and tank capacity. Therefore, the central load
is used in numerical simulations in this paper. In addition, it is
dispatching center grasps the total number and the total rated
assumed that this model is used by the central load
power consumption of the HPWHs in each local control
dispatching center for the estimation of the dynamic behavior
center. The local control center collects the information on the
of the total power consumption and controllable capacity of
requested amount of hot water Erequest of the controlled
the HPWHs.
HPWHs in advance of the control. Based on that information, Cestimated(t) Rhp
it calculates the expected heating period Theat of each HPWH Control Signal
1 1
Thpcs+1 Tims+1
by (2). The power consumption of an HPWH in this Control Delay -Cestimated(t) Rate Limiter Delay of IM
calculation is considered as 90 % of the rated power Pinstalled*
1 1 Power
consumption because the power consumption of each HPWH 0.5 [h]
0.9
Tstarts+1 Consumption
is controlled in the range of 90 ± 10 % of the rated power Ramp 0 Start Delay
(NHP: The number of the HPWHs controlled by the local Distribution * Pinstalled : Total Rated Power Consumption of Installed HPWHs
i
Erequest The total controllable capacity Cestimated(t) is calculated by
i
Theat (2)
0.9 P COP
i * (4).
HP estimated
0 , if 0 t 0.25 [h]
Each local control center calculates the average value TAVG °
and the standard deviation TSD of the expected heating period C estimated t ®0.1 Poperating t 0.25 , if 0.25 t 0.75 [ h] (4)
°
Theat of the HPWHs by (3) and sends them to the central load ¯0.1 Poperating t , if 0.75 t [ h]
dispatching center. Not only the transmission of the
information between each local control center and its where Poperating(t) is the total rated power consumption of the
customers but also that between the central load dispatching operating HPWHs shown in Fig. 4.
center and the local control centers is carried out once a day.
The time t = 0 is when the first one of the HPWHs starts.
The upstream information communication to the central load
The time t = 0.75 [h] is when the power consumption of the
dispatching center does not have to be in real-time.
last starting HPWH, which starts at t = 0.5 [h], becomes stable.
As long as all the HPWHs are operating, Poperating(t) does not
¦ T
N HP N HP
¦T
2
i
heat
i
heat TAVG change after t = 0.5 [h] because the HPWHs do not start any
TAVG i 1
, TSD i 1 (3)
N HP N HP more. It is assumed that no HPWHs stop operating from
t = 0.5 [h] to t = 0.75 [h] and that Poperating(t) is constant during
According to the statistical information, the central load that period. Cestimated(t) changes in proportion to Poperating(t)
dispatching center estimates the change of the total power after t = 0.75 [h] because all the operating HPWHs are
consumption of the HPWHs as a normal distribution, controllable.
determines the start time and the control period, and sends the
start time and the control signal (LFC signal) to the HPWHs IV. EVALUATION OF DYNAMIC BEHAVIOR OF LUMPED MODEL
via the local control centers. Each local control center starts its Numerical simulations are carried out to compare between
HPWHs at random in 0.5 [h] so as to avoid a great impact of the output of a lumped model responding to the input LFC
the simultaneous start of a number of HPWHs on the power signal and that of a number of detailed models and to verify
system. Each HPWH changes its power consumption in the whether the proposed lumped model can well approximate the
4
䣎䣈䣅䢢䣵䣫䣩䣰䣣䣮䢢䣝䣲䢰䣷䢰䣟
HPWHs controlled by one local control center is 1,000 and 䢲
that there are two kinds of HPWHs which are different in the 䢯䢲䢰䢲䢷
rated power consumption and the capacity of tank. The data of
䢯䢲䢰䢳
the installed HPWHs used in the simulation is shown in Table 䢲 䢳 䢴 䢵 䢶 䢷 䢸 䢹
II. 䣖䣫䣯䣧䢢䣝䣪䣟
In this paper, each customer sets the requested amount of Fig. 6. LFC signal to one machine.
hot water Erequest for 1-day use everyday and each HPWH B. Simulation Results
keeps operating until the requested amount is completed to be The total power consumption and the total controlled
heated. The requested amount of hot water Erequest used in the power of the HPWHs of both the lumped model and a
simulation is determined on each customer using the hot water thousand of the detailed models in the simulation period are
demand in the Tokyo metropolitan area in winter [6] for shown in Fig. 7. The actual average value COP* is 4.0 which
reference. The histogram of the requested amount of hot water is the same value as COP*estimated estimated by the central load
Erequest of 1,000 customers is shown in Fig. 5. dispatching center.
The estimated average COP in the simulation, which is Figure 7 (a) shows the total power consumption of the
described as COP*estimated in (2), is determined to be 4.0. The HPWHs. The total controlled power of the HPWHs shown in
actual average COP is denoted by COP*, which is a parameter Fig. 7 (b) changes within the controllable capacity shown in
in the simulation. The COPs of 1,000 HPWHs are statistically Fig. 7 (d), which stands for the power consumption controlled
distributed as a normal distribution (average value: COP*, within ± 10 % of the total rated power consumption of the
standard deviation: 5.0 %). Although COP changes with time HPWHs. Figure 7 (c) is a close-up of Fig. 7 (b) from t = 3.0 to
actually, it is assumed to be constant. It is sufficient to t = 5.0 [h]. It can be seen in Fig. 7 that the output of the
consider COP as constant at the average value in the lumped model almost agrees with that of the detailed models
simulation period because the heated amount of hot water is from t = 1.0 to t = 3.0 [h], and that there is a difference
calculated as the integral of the power consumption multiplied between the two outputs from t = 3.0 to t = 5.0 [h]. The reason
by the COP as shown in Fig. 1. Table III shows the average of the difference is because the lumped model is designed on
value TAVG and the standard deviation TSD of the estimated the assumption that the distribution of the heating period of
heating period calculated by (3) using the data shown in Fig. 5. the HPWHs is an exact normal distribution and that the power
The LFC signal to one machine in the simulation period is consumption is constant at 90 % of the rated power
shown in Fig. 6. The simulation period is 7 hours. The consumption during the control period. However, during the
HPWHs starts heating from t = 0 to t = 0.5 [h]. The LFC period that the lumped model well approximates (from t = 1.0
signal is sent from t = 0.25 to t = 6.0 [h]. The HPWHs respond to t = 3.0 [h]), almost all the HPWHs are operating and the
to the LFC signal as long as they are operating. controllable capacity of the HPWHs is large enough to
TABLE II contribute to the frequency control. It can be said that the
DATA OF INSTALLED HPWHS lumped model can approximate the detailed models while the
Type A Type B frequency control by use of the HPWHs is effective.
Rated Power Consumption [kW] 1.0 1.3 Figure 8 shows the RMS value of the error between the
Rated Thermal Output [kW] 4.5 6.0
total controlled power of HPWHs represented by the lumped
Capacity of Hot Water Tank [l ] 370 460
model and that by the detailed models. It is calculated by (5)
Capacity of Hot Water Tank [kWh] 20 26
Instration Rate [%] 70 30
hourly.
䢴䢷䢲 PRMS
1 N i
¦ PLM PDMi
N i1
2 (5)
䣐䣷䣯䣤䣧䣴䢢䣱䣨䢢䣥䣷䣵䣶䣱䣯䣧䣴䣵
䢴䢲䢲
䢳䢷䢲
where N is the sample number, PLM is the total controlled
䢳䢲䢲
power of the HPWHs represented by the lumped model, and
䢷䢲 PDM is that by the detailed models.
䢲
䢳 䢵 䢷 䢹 䢻 䢳䢳 䢳䢵 䢳䢷 䢳䢹 䢳䢻 䢴䢳 䢴䢵 䢴䢷 The RMS of the error is large not only in the period from
䣔䣧䣳䣷䣧䣵䣶䣧䣦䢢䣣䣯䣱䣷䣰䣶䢢䣱䣨䢢䣪䣱䣶䢢䣹䣣䣶䣧䣴䢢䣝䣭䣙䣪䣟
Fig. 5. Histogram of requested amount of hot water.
t = 3.0 to t = 5.0 [h] but also in the period from t = 0 to
5
䣔䣏䣕䢢䣸䣣䣮䣷䣧䢢䣱䣨䢢䣧䣴䣴䣱䣴䢢䣝䣭䣙䣟
䢷䢰䢲
HPWHs. However, the RMS of the error is small in the period 䢴䢰䢲
䣆䣧䣶䣣䣫䣮䣧䣦䢢䣯䣱䣦䣧䣮䣵
䢳䢲䢲䢲 䣎䣷䣯䣲䣧䣦䢢䣯䣱䣦䣧䣮 COPs of the detailed models are stochastically determined
䢺䢲䢲 based on the average value of the COPs. There is a possibility
䢸䢲䢲 that the response of the actual HPWHs is different from that
䢶䢲䢲
of the lumped model if COP* (actual average value) is
different from COP*estimated (estimated average value).
䢴䢲䢲
Figure 9 shows the change of the controllable capacity of
䢲䢢
䢲 䢳 䢴 䢵 䢶 䢷 䢸 䢹 HPWHs in the three cases; 0, +5 %, and -5 % in the estimated
䣖䣫䣯䣧䢢䣝䣪䣟
error of COP*. The smaller COP*, the slower decrease in the
(a)
controllable capacity. It is because the smaller the COP is, the
䢢
longer it takes to complete to heat the water.
䢳䢲䢲 䣆䣧䣶䣣䣫䣮䣧䣦䢢䣯䣱䣦䣧䣮䣵
䣖䣱䣶䣣䣮䢢䣥䣱䣰䣶䣴䣱䣮䣮䣧䣦䢢䣲䣱䣹䣧䣴䢢䣝䣭䣙䣟
䢢
䣎䣷䣯䣲䣧䣦䢢䣯䣱䣦䣧䣮 䢳䢲䢲 䣅䣑䣒䢬䢿䢵䢰䢺
䣅䣱䣰䣶䣴䣱䣮䣮䣣䣤䣮䣧䢢䣥䣣䣲䣣䣥䣫䣶䣻䢢䣝䣭䣙䣟
䢷䢲
䣅䣑䣒䢬䢿䢶䢰䢲
䢷䢲
䢲 䣅䣑䣒䢬䢿䢶䢰䢴
䢲
䢯䢷䢲
䢯䢷䢲
䢯䢳䢲䢲
䢢
䢲 䢳 䢴 䢵 䢶 䢷 䢸 䢹 䢯䢳䢲䢲
䢢
䣖䣫䣯䣧䢢䣝䣪䣟 䢲 䢳 䢴 䢵 䢶 䢷 䢸 䢹
(b) 䣖䣫䣯䣧䢢䣝䣪䣟
Fig. 9. Control capacity of HPWHs.
䢢
䢳䢲䢲 䣆䣧䣶䣣䣫䣮䣧䣦䢢䣯䣱䣦䣧䣮䣵 Figure 10 shows the RMS value of the error between the
䣖䣱䣶䣣䣮䢢䣥䣱䣰䣶䣴䣱䣮䣮䣧䣦䢢䣲䣱䣹䣧䣴䢢䣝䣭䣙䣟
䣎䣷䣯䣲䣧䣦䢢䣯䣱䣦䣧䣮
䢷䢲 total controlled power of the HPWHs represented by the
lumped model and that by the detailed models in the five
䢲
cases; 0, ± 5 %, ± 10 % in the estimated error of COP*.
䢯䢷䢲 䢴䢷 䢢
䣅䣑䣒䢬 䢿䢵䢰䢸
䣔䣏䣕䢢䣸䣣䣮䣷䣧䢢䣱䣨䢢䣧䣴䣴䣱䣴䢢䣝䣭䣙䣟
䢺䢮䢲䢲䢲
Minimum Load
Fig. 11. Frequency analysis model.
䢹䢮䢲䢲䢲
TABLE V
PARAMETERS OF LUMPED HPWH MODEL IN THE SIMULATION
P installed [MW] 458
T AVG [h] 3.45
T SD [h] 0.67
Nuclear
Thermal
B. Simulation Results
Fig. 12. 8-machine system model. The simulation results are shown in Figs. 15 and 16. The
7
total power consumption of the HPWHs is depicted in Fig. 15. Statistical HPWH Model in Power system with a Large Penetration of
Renewable Energy Sources," in Proc. 2010 International Conference on
It can be seen from this figure that the total power Power System Technology, Hangzhou, China, Oct. 2010.
consumption is controlled responding to the control signal [4] H. Irie, A. Yokoyama, and Y. Tada, "System Frequency Control by
during the control period. Coordination of Batteries and Heat Pump based Water Heaters on
Customer Side in Power System with a Large Penetration of Wind
Power Generation," IEE Japan Trans. Power and Energy, vol. 128, no. 3,
䣖䣱䣶䣣䣮䢢䣲䣱䣹䣧䣴䢢䣥䣱䣰䣵䣷䣯䣲䣶䣫䣱䣰䢢䣱䣨䢢䣊䣒䣙䣊䣵䢢䣝䣏䣙䣟
䢷䢲
䢶䢻䢰䢺
Akihiko Yokoyama (Member) received B.S., M.S.,
䢶䢻䢰䢸 䢢 and Dr. Eng from The University of Tokyo, Tokyo,
䢴䢵 䢲 䢳 䢴 䢵 䢶 䢷 䢸 䢹 䢺 䢻 䢳䢲
䣖䣫䣯䣧䢢䣝䣪䣟 Japan in 1979, 1981 and 1984, respectively. He has
Fig. 16. Frequency. been with Department of Electrical Engineering, The
University of Tokyo since 1984 and currently a
professor in charge of Power System Engineering. He
VI. CONCLUSION is a member of IEEJ, IEEE and CIGRE.
In this paper, a lumped HPWH model has been designed to
approximate the dynamic behavior of a number of HPWHs
considering not only the uncertainty of the customers but also
that of the machine characteristics. The response of the
Yasuyuki Tada (Member) received the Ph.D. degree
proposed lumped model to the LFC signal has been evaluated in engineering from the University of Tokyo, Tokyo,
in comparison with that of the detailed models. It has also Japan, in 1998. Currently, he is a Researcher in the
been manifested by the frequency analysis simulation that the Power System Technology Group, Electric Power
Engineering R&D Center, Tokyo Power Electric
frequency control method by use of the HPWHs can be Company (TEPCO), where he has been since 1981.
effectively designed. Hence, the proposed lumped HPWH
model can well approximate the behavior of the actual
HPWHs as long as the central load dispatching center
generates and sends the LFC signal in the period that the
frequency control is expected to be effective. In the future
work, we will develop a coordinated LFC method by use of
not only HPWHs but also EVs.
VII. REFERENCES
[1] Leehter Yao and Hau-Ren Lu, "A Two-Way Direct Control of Central
Air-Conditioning Load Via the Internet," IEEE Trans. Power Delivery,
vol. 24, no. 1, pp. 240-248, Jan. 2009.
[2] J.R.Pillai and B.Bak-Jensen, "Integration of Vehicle-to-Grid in the
Western Danish Power System," IEEE Trans. Sustainable Energy, vol. 2,
no. 1, pp. 12-19, Jan. 2011.
[3] T. Masuta, A. Yokoyama, and Y. Tada, " System Frequency Control by
Heat Pump Water Heaters (HPWHs) on Customer Side Based on