You are on page 1of 1

CONSTRUCTION OF INTERNAL ROADS AND INFRASTRUCTURE FOR 354 RESIDENTIAL PLOTS IN 

SHAKHBOUT CITY

PROCUREMENT LOG REGISTER OF LONG LEAD MATERIALS
Expected date of delivery  Expected date of delivery 
Potable Water Material Submittal Date Material Approval Date Lot 1 Lot 2

1 Valves (Gate , Washout , Air release Valves) 13‐Jul‐17 3‐Aug‐17 13‐Jan‐18 14‐Mar‐18

2 DI Pipe and Fitting 16‐Jul‐17 6‐Aug‐17 16‐Jan‐18 17‐Mar‐18

3 Fire hydrant 20‐Jul‐17 10‐Aug‐17 20‐Jan‐18 21‐Mar‐18

4 DI Cover & Frame 29‐Jul‐17 19‐Aug‐17 24‐Jan‐18 25‐Mar‐18

5 Flange Adaptor & Dismantling Joint 29‐Jul‐17 19‐Aug‐17 24‐Jan‐18 25‐Mar‐18


Material Submittal  Material Approval  Expected date of  Expected date of 
Street Lighting Date Date delivery Lot 1 delivery Lot 2

1 Light poles & Accessories 18‐Oct‐17 8‐Nov‐17 14‐Jun‐18 NA

2 Lanterns & LED luminaries 11‐Oct‐17 1‐Nov‐17 7‐Jun‐18 NA

3 Lighting fixtures for Substations 11‐Oct‐17 1‐Nov‐17 7‐Jun‐18 NA

4 Remote terminal units & DMS integration 4‐Aug‐17 25‐Aug‐17 7‐Jun‐18 NA


Material Submittal  Material Approval  Expected date of  Expected date of 
Power Package  Date Date delivery Lot 1 delivery Lot 2

1 Transformers 4‐Aug‐17 25‐Aug‐17 23‐Apr‐18 22‐Jul‐18

2 Electrical QRM 4‐Aug‐17 25‐Aug‐17 7‐May‐18 11‐Aug‐18

3 LV Distribution Boards 18‐Oct‐17 8‐Nov‐17 12‐May‐18 10‐Aug‐18

4 GPRS & Antenna 23‐Oct‐17 13‐Nov‐17 13‐May‐18 11‐Aug‐18

5 Substation RTU 25‐Aug‐17 15‐Sep‐17 19‐May‐18 2‐Aug‐18

You might also like