TRANSMISSION & DISTRIBUTION

First HTS FCL goes into a US grid

Zenergy’s California FCL installation

In March this year Southern California Edison completed the installation of Zenergy’s proprietary HTS fault current
limiter into its electricity grid in Southern California, a national first for the technology. It is also the beginning
of a larger programme of investigation into the value of such devices for support of the grid nationwide.

Zenergy’s HTS fault current limiter, like all The full list of benefits is said to include:
Leonard Sanford FCLs, is designed to protect power grid • suppression of overloads, while the
equipment against damaging power surges downstream power supply is maintained
without any interruption, and at its regular

T
he Zenergy HTS prototype is designed to caused, for example, by short circuits or lightning
help prevent blackouts in electricity strikes, and prevents the tripping of major plant strength
transmission systems and is the first such at such times. The advantage of HTS switching • improved operational reliability of fully
device ever to be installed, activated and lies in the inherent qualities of an HT stretched grids greatly reducing the risk of
operated in the United States grid. Following superconductor. As the current rises in a fault large scale blackout due to cascading grid
successful testing for medium voltage power condition a point is reached when failures following a local defect
grids in the USA at the end of 2008, superconductivity switches off and DC • cost-efficient protection of transformers and
implementation in Californian MV grids was resistance is restored, automatically limiting the other power grid equipment against power
placed under a California Energy Commission current flow. This happens more or less instantly, surge damage
project with the result that the FCL is now online at any rate sufficiently quickly to prevent a • simplified integration of an increasing number
and operating in real-time to provide protection transient overcurrent, significantly reducing the of decentralised power generation systems into
to the distribution circuit of the power grid. Its risk of power grid failures and interruptions to the network infrastructure.
maker Zenergy is an HTS specialist with a couple power supplies compared to a standard FCL.
of world firsts already under its belt – first to Zenergy’s product is of the saturated core type – In a smart market
install an HTS hydro-generator (for E.ON’s grid, an HTS coil wound on an iron core – and utilises The significance of being the first company to
due in 2009) and first with an HTS applications the extremely high magnetising current available install and operate such a device into the US
for offshore wind power. and the wide range of permeability of magnetic electricity grid is particularly apparent in the
materials. A high permeability core allows a low light of the severe problems that utility
The firewall for power grids impedance during normal operation and a very companies are facing in coping with increasing
An FCL is a series device installed in the high impedance during fault current events. power demands from consumers while
electricity supply line, and acts like a firewall. Once the fault current subsides, the FCL again attempting to satisfy the publicly stated demand
allows standard levels of current to flow, protecting for distributed power generation (including
California Energy the system automatically without human wind and solar power) from government
intervention. It is entirely a passive device and authorities. Combined, these factors are leading
Commission specification needs no resetting or post-operation maintenance. to an increased occurrence of electrical
Line voltage 12 kV These properties of speed and automatic blackouts which recent research estimates to be
resetting will be even more applicable to the costing commercial businesses in the United
Steady state current 1200 A ‘smarter’ grids of the future which will make States over US$100 billion per annum.
Prospective fault current 22.4 kA great demands on the reliability, speed and As is widely reported, these escalating costs,
Fault current reduction 33% repeatability of equipment to maintain supply along with security concerns, efficiency
and improve the resilience and flexibility that demands and increased renewable energy
Steady state impedance <1%
constantly changing and reversible flows will production are creating a determined effort to
render necessary. bring about the evolution of a national `smart

www.modernpowersystems.com May 2009 Modern Power Systems 53


TRANSMISSION & DISTRIBUTION

Current levels as controlled by an FCC must be co-ordinated with system funding. Testing is provisionally scheduled
protection to allow breakers to safely interrupt the fault current for 2010.
At the end of 2007 Zenergy successfully fault-
Unlimited peak tested its prototype FCL, and in 2008 entered a
short-circuit period of extensive modelling, computer
current Prospective current simulation, and experimental verification when
it designed and built its first CEC FCL, designed
Peak let-through its second FCL under DoE funding, and
current identified a prospective host utility for the
FCL with current interruption working prototype.
During 2009 it intends to assemble the
subsystems for its second distribution class DoE
FCL, third Party test the DoE FCL, install and
Rate current operate the 26kV FCL in the electrical grid, start
(max. load current)
design work on a transmission class FCL, and
FCL without current interruption
evaluate commercially available 2G wire for
suitability in a saturated core FCL design.
Normal operation Short-circuit
Funding
The scale of official interest can be gauged from
grid' in the United States. And not just in the USA the need to install higher-capacity breakers than the DoE’s willingness to support the technology
– the global market for FCLs alone is expected already exist. They can more readily with grants. In 2007 Zenergy received $11
to be worth up to US$ 5 bn per annum as it accommodate fault current contributions from million to support its five year programme to
approaches maturity. new generation, especially renewables plants design, build, and test a transmission class
This ongoing investment would represent a that come on-line in transmission-constrained saturable core reactor FCL, with the intermediate
significant modernisation of the existing grid areas. And they avoid SF6 issues with high- goal of achieving a viable distribution-class unit
system and the adoption of a number of devices capacity breakers. with a core wound with 1G wire.
from different technology areas, FCLs being SCE’s project is intended to evaluate the Meanwhile it has had $0.5m from the
prominent among them, that will lead to a more current technology status of FCCs, develop test California Energy Commission to install an HTS
demand managed, efficient and stable electricity protocols and testing plans for each prototype grid stability device into their grid. It is that
distribution system. Recent estimates prepared technology, and develop evaluation criteria – installation that has just been completed.
for the US Department of Energy have shown performance, cost, maintenance issues,
that a reduction in greenhouse gases equivalent manufacturing requirements, installation issues, Smart FCL for New York
to taking 53 million (working) cars of the road expected reliability, and others. Zenergy Power has now been contracted by Con
could be achieved by just a 5% improvement in Controlled (factory or lab) and ‘real-world’ (at Edison to build and test a single phase FCL for
overall grid efficiency. These efficiencies will the SCE Avanti substation) field testing will be installation in New York City's power grid.
also drive substantial cost savings. performed on what are regarded as the three Con Edison has authorised the project in the
This being so, it is no surprise that Zenergy has leading technologies (EPRI and SC Power in expectation that it would be applicable to a
been invited to work together with a number of Phase 1, AMSC in Phase 2) followed by an number of substations within the utility’s
the utility companies in the US throughout the assessment of the potential for migration of the electrical systems. Zenergy expects to deliver the
development of its FCL, and has also participated technology to transmission-level applications. prototype by the end of August.
on projects funded by the Department of Energy, Pat Duggan, project manager and FCL
California Energy Commission and the The technologies specialist at Con Edison, commented ‘Fault
Department of Homeland Security. EPRI’s solid state fault current limiter (SSFCL) current limiters will be an essential element of
is based on a new generation of advanced the smart grid to maintain reliability and improve
Testing fault current controllers thyristor technology. Testing is scheduled for its resilience and flexibility. This is especially
The future success and operational power of mid-2009. Zenergy’s HTS fault current limiter important as the load grows, including the move
supergrids will be derived in large part from grid uses HTS elements in combination with a to electricity as a preferred source for new uses
control devices like fast acting FCLs, and in saturable iron core. Testing started in late 2008. such as plug-in hybrid vehicles.’
pursuit of the best technology, trials of three The third device, an FCC being made by a The tests are to ensure the device can protect
prototype FCL installations are planned by SCE, collaboration of Siemens and American equipment from fault currents in the utility's
to be carried out at its Circuit of the Future test Superconductor, also an HTS design, is still the 13.8 kV feeder system. Zenergy expects to
bed. Of the three units on trial, one is a solid state subject of negotiations between Siemens/AS extend its designs to other FCLs for higher
device developed by EPRI, while the other two and the DoE on project scope, schedule and voltage lines of up to 138kV and beyond. MPS
are both high temperature superconducting
devices, made by Zenergy and American 3-phase Zenergy FCL.
Superconductor respectively. The programme is One HTS coil
already underway and is expected to take five saturates all
years in all. Phase I will come to completion in six cores
2010, Phase II two years later.
Fault currents are beginning to exceed the
capabilities of circuit breakers to safely and
reliably interrupt the faults. This can result in
catastrophic breaker failure and exposure of
transformers and other critical equipment to
damaging fault currents. An alternative (though
not fully satisfactory) solution is to split
substation buses to redistribute the fault currents
to safe levels; this approach negatively impacts
system reliability and flexibility of operation. A
better alternative is to protect under-rated circuit
breakers so they can continue in use.
The use of FCLs suggests several likely
benefits. They can greatly reduce the destructive
forces of high fault currents on transformers and
other equipment. They limit the necessary
modifications to existing protection systems and