CÁLCULO DE LOS VÓLUMENES DE LAS ACTIVIDADES DE LA
CIMENTACIÓN
Limpiar el terreno_________________________________________________m2
23.562 m x 29.552 m = 696.24 m2
696.24 m2
Replanteo________________________________________________________ml
6.87 m + 2 m = 8.87 m
10.70 m + 2 m = 12.70 m
8.87 m + 12.70 m = 21.33 m
21.33 m x 2 m = 43.10 m
43.10 ml
Excavación de Zanja_______________________________________________m3
o Sección Tipo 1
1. 0.20 m x 0.25 m = 0.05 m2
2. 0.10 m x 0.10 m / 2 = 0.005 m 2
0.5 m2 + 0.005 m2 = 0.055 m2
0.055 m2
9.65 ml + 10.70 ml + 13.70 ml + 1.05 ml = 35.10 ml
35.10 ml
0.055 m2 x 35.10 ml = 1.9305 m3
1.9305 m3
o Sección Tipo 2
1. 0.20 m x 0.25 m = 0.05 m2
2. 0.10 m x 0.10 m / 2 = 0.005 m2
3. 0.10 m x 0.10 m / 2 = 0.005 m2
0.05 m2 + 0.005 m2 + 0.005 m2 = 0.06 m2
0.06 m2
9.65 ml + 3.00 ml + 6.85 ml + 3.35 ml + 3.50 ml = 26.35 ml
26.35 ml
0.06 m2 x 26.35 ml = 1.581 m3
1.581 m3
1.9305 m3 + 1.581 m3 = 3.5115 m3
3.5115 m3
Colocación del Plastico_____________________________________________m2
3.5115 + 3.695 = 7.2065 m2
Desencofre_______________________________________________________m2
3.695 m2