You are on page 1of 152

Power Distribution Systems 1.

0-1
August 2017
Sheet 01 001

Contents
Power Distribution
Systems
i
Power Distribution Systems System Protection Considerations
System Design Overcurrent Protection ii
Basic Principles. . . . . . . . . . . 1.1-1 and Coordination . . . . . . . . 1.5-1
Trends in Systems Design . . 1.1-1 Grounding/Ground Fault Protection
Goals of System Design . . . 1.1-2 Grounding—Equipment, 1
Designing a Distribution System System, MV System,
Development of a System LV System . . . . . . . . . . . . . . 1.6-1
One-Line . . . . . . . . . . . . . . . 1.2-1 Typical Power System Components 2
Importance of a System Typical Power System
One-Line . . . . . . . . . . . . . . . 1.2-2 Components . . . . . . . . . . . . 1.7-1 3
Power System One-Line . . . 1.2-4 Transformers . . . . . . . . . . . . . 1.7-4
Standardized Drawing Generators and
Symbols . . . . . . . . . . . . . . . 1.2-6 Generator Systems . . . . . . . 1.7-13 4
Types of Systems Generator Short-Circuit
Types of Systems . . . . . . . . . 1.3-1 Characteristics . . . . . . . . . . . 1.7-16
Power System Analysis Generator Set Sizing 5
Systems Analysis . . . . . . . . . 1.4-1 and Ratings. . . . . . . . . . . . . 1.7-20
Generator Set Installation
Short-Circuit Currents—
and Site Considerations . . . 1.7-21 6
General . . . . . . . . . . . . . . . . 1.4-1
Fault Current Waveform Capacitors and
Power Factor . . . . . . . . . . . . 1.7-22
Relationships . . . . . . . . . . . 1.4-3
Motor Power Factor
7
Fault Current Calculations
and Methods Index . . . . . . 1.4-4 Correction . . . . . . . . . . . . . . 1.7-23
Fault Current Calculations Typical Application by Facility Type 8
for Specific Equipment— Healthcare Facilities . . . . . . 1.8-1
Exact Method . . . . . . . . . . . 1.4-5 Quick Connect Generator
Application Quick Check and Load Bank 9
Table . . . . . . . . . . . . . . . . . . 1.4-8 Capabilities . . . . . . . . . . . . 1.8-7
Medium-Voltage Fuses—
Fault Calculations . . . . . . . 1.4-11
Power Quality  10
Low-Voltage Power Power Quality Terms Technical
Circuit Breakers— Overview. . . . . . . . . . . . . . 1.9-1
Fault Calculations . . . . . . . 1.4-12 Other Application Considerations  11
Molded-Case Breakers Seismic Requirements . . . . 1.10-1
and Insulated Case 12
Reference Data
Circuit Breakers—
Fault Calculations . . . . . . . 1.4-13 Codes and Standards . . . . . 1.11-1
Low-Voltage Circuit Breaker Suggested IEEE Designations 13
Interrupting Derating for Suffix Letters. . . . . . . . 1.11-6
Factors . . . . . . . . . . . . . . . . 1.4-13 Ampacities for Conductors
Short-Circuit Calculations— Rated 0–2000 V. . . . . . . . . 1.11-12 14
Shortcut Method . . . . . . . . 1.4-14
Determining X and R
Values from Transformer 15
Loss Data . . . . . . . . . . . . . . 1.4-17
Voltage Drop . . . . . . . . . . . . . 1.4-20
16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.0-2 Power Distribution Systems
August 2017
Sheet 01 002

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-1
August 2017 System Design
Sheet 01 003

Basic Principles Trends in Systems Design The growing impact of adverse weather
i
conditions such as hurricanes and
The best distribution system is one There are many new factors to flooding is now driving incoming
that will, cost-effectively and safely, consider in the design of power service and distribution equipment
supply adequate electric service to distribution systems. rooms to be located out of basements ii
both present and future probable and other low lying areas. Regions
loads—this section is intended to aid Federal and state legislation has been prone to these storms often experience
in selecting, designing and installing introduced to reduce the output of downed utility power lines and/or 1
such a system. carbon emissions into the environment; flooded manholes, resulting in a loss
the intent being the reduction of their of power to thousands of customers.
The function of the electric power impact on climate change. In order to In order to quickly return power to 2
distribution system in a building or address the subsequent need for clean these facilities, additional on-site
an installation site is to receive power power, there has been an accelerating backup generation is being included in
at one or more supply points and trend toward the incorporation of solar both new designs and as upgrades to 3
to deliver it to the lighting loads, and other sustainable energy sources existing sites. This trend for resiliency
motors and all other electrically into existing and new building designs. is increasing among grocery stores,
operated devices. The importance Energy storage systems (ESS) are now large chain stores and other distribution 4
of the distribution system to the making renewable energy a more facilities requiring refrigeration to keep
function of a building makes it viable option by helping to stabilize products from spoiling as well as large
imperative that the best system be power output during transient dips or multifamily dwelling complexes in low 5
designed and installed. interruptions to power production. lying flood plain areas.
In order to design the best distribution Utility deregulation has also provided Building costs continue to rise and 6
system, the system design engineer financial incentives for building rentable or usable space is now at a
must have information concerning the owners and facility managers to premium. To solve both problems,
loads and a knowledge of the types participate in peak demand load many design and construction firms 7
of distribution systems that are shaving programs. These programs are looking at off-site prefabrication
applicable. The various categories of are intended to reduce load on the of key elements. Forest City Ratner’s
buildings have many specific design
challenges, but certain basic principles
utility grid in response to a 1 hour or
1 day ahead signal from the utility.
32-story residential complex adjacent 8
to Barclay's Arena in Brooklyn, NY,
are common to all. Such principles, The users shedding or cycling of non- advanced the modular concept
if followed, will provide a soundly essential loads is generally initiated by with individual building sections 9
executed design. a building management system (BMS) constructed at a factory off-site and
in conjunction with power monitoring erected by crane into place. Resiliency
The basic principles or factors requiring
consideration during design of the
and lighting control equipment. To from storms and floods involving the 10
ensure uninterrupted operation of key relocation of electrical equipment out
power distribution system include: customer loads, incorporation of other of flood prone areas is costly, time
■ Functions of structure, present types of distributed generation such as consuming and takes up precious floor 11
and future fuel cells and diesel or natural gas fired space in a building. Electro Centers or
reciprocating generator sets may be Integrated Power Assemblies (IPA) can
■ Life and flexibility of structure
■ Locations of service entrance and
desired or required. be fitted out with a variety of electrical 12
distribution equipment, locations Hospital complexes and college distribution equipment and shipped to
and characteristics of loads, campuses are increasingly adopting the the site in preassembled modules for
locations of unit substations design of central utilities plants (CUPs). mounting on elevated foundation 13
In lieu of a separate boiler plant, piles, building setbacks or rooftops.
■ Demand and diversity factors
cogeneration is used to produce
of loads
electricity and the wasted heat from
Finally, the need to have qualified 14
■ Sources of power; including building electrical operators,
the combustion process is recaptured maintenance departments and facility
normal, standby and emergency
to provide hot water for the campus.
(see Tab 40)
Large cogeneration plants (3 MW and
engineers has collided with growing 15
■ Continuity and quality of power expectations for improved productivity
above) often include large turbines or and reduced overall operating costs.
available and required (see Tab 33) reciprocating engines as their prime
■ Energy efficiency and management movers for the generators. To enhance
The increasing proliferation of smart 16
devices and enhanced connectivity
■ Distribution and utilization voltages service continuity, these generators with power distribution equipment
use a continuous source of natural
■ Busway and/or cable feeders
gas as their fuel supply. Cogen plants
has expanded facility owner’s 17
(see Tab 24) options. These capabilities allow for
generally have higher power conver- automated communication of vital
■ Distribution equipment and
sion efficiencies and produce lower power system information including 18
motor control
carbon emissions. energy data, equipment wellness and
■ Power and lighting panelboards
and motor control centers predictive diagnostics, and electrical
(see Tabs 22, 23 and 29) equipment control. 19
■ Types of lighting systems
■ Installation methods 20
■ Power monitoring systems
(see Tabs 2 and 3)
■ Electric utility requirements 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-2 Power Distribution Systems
System Design August 2017
Sheet 01 004

The future “Internet of Things” provided, for speeding up the OSHA has qualified a number of
i promises to add millions of more clearing time of a circuit breaker Nationally Recognized Testing
sensors and other devices to collect that can be set to trip at 1200 A or Laboratories (NRTL) to demon-
operational data and send it through above. Eaton’s Arcflash Reduction strate and certify “product
ii the Internet to “cloud-based” comput- Maintenance System™ is avail- conformance to the applicable
ing services. There, information from able in various electronic trip product safety test standards.”
multiple devices can be analyzed and units for molded-case and power Among the oldest and most
1 actions can be taken to optimize circuit breakers to improve clear- respected of these electrical
performance and reduce downtime. ing time and reduce the incident product testing organizations is
energy level. Underwriters Laboratories (UL),
2 Various sections of this guide cover which was founded in 1894.
the application and selection of such The National Electrical Code®
systems and components that may (NEC®), NFPA® 70 and NFPA 70E, It is the responsibility of the design
3 be incorporated into the power as well as local electrical codes, engineer to be familiar with the
equipment being designed. Also provide minimum standards and NFPA and NEC code requirements
see Tabs 2, 3, 4, 23, 38, 39 and 41 requirements in the area of wiring as well as the customer’s facility,
4 for specific application details. design and protection, wiring process and operating procedures
methods and materials, as well in order to design a system that
as equipment for general use with protects personnel from live electri-
5 Goals of System Design the overall goal of providing safe cal conductors and uses adequate
When considering the design of an electrical distribution systems circuit protective devices that will
electrical distribution system for and equipment. selectively isolate overloaded or
6 a given customer and facility, the The NEC also covers minimum
faulted circuits or equipment as
electrical engineer must consider quickly as possible.
requirements for special occupan-
alternate design approaches that cies including hazardous locations In addition to NFPA and NEC
7 best fit the following overall goals. and special use type facilities such guidelines, the design professional
1. Safety: The No. 1 goal is to design as healthcare facilities, places of must also consider International
assembly, theaters and the like, Building Code (IBC) and local
8 a power system that will not
as well as the equipment and municipality, state and federal
present any electrical hazard to
the people who use the facility, systems located in these facilities. requirements. The United States
9 and/or the utilization equipment Special equipment and special Department of Energy, for example,
fed from the electrical system. conditions such as emergency mandates minimum efficiencies for
It is also important to design a systems, standby systems and transformers and other equipment.
10 system that is inherently safe for communication systems are also
covered in the code. Many of these regulatory codes
the people who are responsible for reference ANSI/ASHRAE/IES
electrical equipment maintenance 2. Regulatory Requirements: Standard 90.1-2013 “Energy
11 and upkeep. Over the course of the past Standard for Buildings Except
The Occupational Safety and century, electrical product safety Low-Rise Residential Buildings”.
and performance standards have Section 8.1 covers power and
12 Health Administration (OSHA)
is a federal agency whose been developed in cooperation includes receptacle load control.
“mission is to assure safe and between various agencies such Subsection 8.4.3 is titled Electrical
as: American National Standards Energy Monitoring and covers
13 healthful workplaces by setting
Institute (ANSI) as well as industry metering and monitoring systems
and enforcing standards, and by
providing training, outreach, groups such as the Institute that notify building tenants and
of Electrical and Electronics engineers of the increased use of
14 education and assistance.” OSHA’s
Engineers (IEEE) and the National electric power. Section 9.1 covers
electrical requirements are covered
under several categories, the Electrical Manufacturers Associa- lighting and lighting control
tion (NEMA). These are often system requirements.
15 broadest being 1910 Subpart 10
referenced together with specific
Electrical including references to Other building standards organiza-
the National Fire Protection Agency test standards developed in
conjunction with Underwriters tions that offer certifications,
16 (NFPA) 70 and 70E.
Laboratories (UL). As an example, such as the U.S. Green Building
To address the concerns for low-voltage switchgear falls under Council’s LEED Accreditation,
personnel safety from arc flash ANSI C37.20.1 and is tested in require measurement and
17 hazards, the 2014 Edition of the compliance with UL 1558. verification that actual energy
NEC as well as the 2015 Edition and water use meet initial building
of NFPA 70E have enhanced the The 2014 National Electrical Code design criteria. The U.S. Green
18 requirements for personnel (NEC) Article 110.2 states that: Building Council has teamed
protection when working on or “The conductors and equipment with ANSI and ASHRAE to
near live equipment. The 2014 required or permitted by this produce ANSI/ASHRAE/USGBC/
19 NEC introduces new arc flash Code shall be acceptable only if IES Standard 189.1-2014 titled,
labeling requirements. approved.” The informational “Standard for the Design of
note references the definitions High-Performance Green Build-
20 Additionally, Article 240.87 offers a in Article 100 for Approved, ings Except Low Rise Buildings”.
number of prescriptive alternative Identified, Labeled and Listed.
methods for arc flash energy
21 reduction; one of which must be

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.1-3
August 2017 System Design
Sheet 01 005

Finally, utility incoming service Typically, service continuity and Power monitoring communication
standards for customer intercon- reliability can be increased by: systems connected to electronic i
nects are key elements in the metering can provide the trending
selection of both the incoming A. Supplying multiple utility power and historical data necessary to
service voltage and the protection sources or services. ensure future capacity for growth. ii
required for this equipment. B. Supplying multiple connection
Knowledge of these standards 6. Maximum Electrical Efficiency
paths to the loads served.
is particularly important when (Minimum Operating Costs): 1
incorporating renewable energy C. Using short-time rated power Electrical efficiency can generally
or distributed generation circuit breakers. be maximized by designing
resources into a design. 1
D. Providing alternate customer-
systems that minimize the losses 2
in conductors, transformers and
1 Contact Eaton’s local application engineer owned power sources such as utilization equipment. Proper
for assistance with design compliance. generators or batteries supplying voltage level selection plays a 3
Energy Storage Systems or key factor in this area and will
3. Minimum Initial Investment: uninterruptable power supplies. be discussed later.
The owner’s overall budget for
first cost purchase and installation E. Selecting the highest quality elec- Selecting equipment, such as
4
of the electrical distribution trical equipment and conductors. transformers, with lower operating
system and electrical utilization losses, generally means higher
equipment will be a key factor
F. Using the best installation
first cost and increased floor space
5
methods, including proper
in determining which of various requirements. Thus there is a
system grounding design.
alternate system designs are to be balance to be considered between
selected. When trying to minimize G. Designing appropriate system the owner’s long-term utility cost
6
initial investment for electrical alarms, monitoring and diagnostics. for the losses in the transformer or
equipment, consideration should other equipment versus the initial
be given to the total cost of H. Selecting preventative mainte- budget and cost of money.
7
the installation. This includes nance systems or equipment to
reducing on-site assembly time alarm before an outage occurs. 7. Minimum Maintenance Cost:
and cost by prefabricating various Usually the simpler the electrical 8
5. Maximum Flexibility and system design and the simpler
electrical components into a single Expandability: In many industrial
deliverable system and reducing the electrical equipment, the lower
floor space and possible extra
manufacturing plants, electrical the associated maintenance costs 9
utilization loads are periodically and operator errors. As electrical
cooling requirements. relocated or changed requiring systems and equipment become
4. Maximum Service Continuity: changes in the electrical distribu- more complicated to provide 10
The degree of service continuity tion system. Consideration of greater service continuity or
and reliability needed will vary the layout and design of the flexibility, the maintenance costs
depending on the type and use electrical distribution system to and chance for operator error 11
of the facility as well as the loads accommodate these changes must increases.
or processes being supplied by the be considered. For example, pro-
electrical distribution system. For viding many smaller transformers When designing complex systems, 12
example, for a smaller commercial or loadcenters associated with a the engineer should consider add-
office building, a power outage given area or specific groups of ing an alternate power circuit to
of considerable time, say several machinery may lend more flexibility take electrical equipment (requiring 13
hours, may be acceptable, whereas for future changes than one large periodic maintenance) out of
in a larger commercial building or transformer; the use of plug-in service without dropping essential
industrial plant only a few minutes busways to feed selected equip- loads. Use of drawout type protec- 14
may be acceptable. In other facilities ment in lieu of conduit and wire tive devices such as breakers and
such as hospitals, many critical may facilitate future revised combination starters can also
loads permit a maximum of equipment layouts. minimize maintenance cost and 15
10 seconds outage and certain out-of-service time. Utilizing sealed
In addition, consideration must be equipment in lieu of ventilated
loads cannot tolerate a loss of
power for even a few cycles.
given to future building expansion, equipment may minimize mainte- 16
and/or increased load require- nance costs and out-of-service time
ments due to added utilization as well.
equipment when designing the 17
electrical distribution system.
In many cases considering trans-
formers with increased capacity 18
or fan cooling to serve unexpected
loads as well as including spare
additional protective devices and/ 19
or provision for future addition of
these devices may be desirable.
Also to be considered is increasing 20
appropriate circuit capacities to
assure future capacity for growth.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.1-4 Power Distribution Systems
System Design August 2017
Sheet 01 006

8. Maximum Power Quality: Summary This revision of Tab 1 includes updates


i The power input requirements
It is to be expected that the engineer
based on changes to the 2014 National
of all utilization equipment has Electrical Code (NEC), 2015 NFPA 99 and
to be considered, including the will never have complete load infor- other pertinent ANSI/IEEE Standards. It
ii acceptable operating range of mation available when the system is
designed. The engineer will have to
also includes a significant revision in
the equipment. Consequently, the the flow of the material presented.
electrical distribution system has expand the information made avail- Additional new information has been
1 to be designed to meet these able to him or her on the basis of added to the document in recognition
needs. For example, what is the experience with similar projects. that users will be at differing levels of
required input voltage, current, Of course, it is desirable that the engi- experience. For those engineers either
2 power factor requirement? neer has as much definite information beginning their careers or early into
Consideration to whether the as possible concerning the function, them, guidance is provided for the
loads are affected by harmonics requirements, and characteristics of design and development of Power
3 (multiples of the basic 60 Hz sine the utilization devices. Systems One-Line Diagrams.
wave) or generate harmonics must
be taken into account as well as The engineer should know whether cer- An expanded section on voltage
4 transient voltage phenomena. tain loads function separately or selection, including both service and
together as a unit, the magnitude of the utilization voltages, has been added.
The above goals are interrelated and demand of the loads viewed separately This narrative discusses consider-
5 in some ways contradictory. As more and as units, the rated voltage and ations for utility metering at medium
redundancy is added to the electrical frequency of the devices, their physical and low voltages. However, the
system design along with the best location with respect to each other description of types of systems and
6 quality equipment to maximize service and with respect to the source and the diagrams used to explain the types
continuity, flexibility and expandability, the probability and possibility of the of systems on the following pages
and power quality, the more initial relocation of load devices and addition omit the location of utility revenue
7 investment and maintenance are of loads in the future. metering equipment for clarity.
increased. Thus, the designer must Further pages address short-circuit
weigh each factor based on the type Coupled with this information, a calculations, coordination, overcurrent
8 of facility, the loads to be served, the knowledge of the major types of electric protection, voltage drop, ground fault
owner’s past experience and criteria. power distribution systems equips the protection, motor protection and
engineers to arrive at the best system application considerations for typical
9 design for the particular building. equipment utilized in a power system.
It is beyond the scope of this guide to
present a detailed discussion of loads
10 that might be found in each of several
types of buildings. Assuming that the
design engineer has assembled the
11 necessary load data, the following
pages discuss some of the various
types of electrical distribution systems
12 that can be used.

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-1
August 2017 Designing a Distribution System
Sheet 01 007

Development of a A System One-Line may start out in Moving into the Construction
i
the Design Development Phase of Document Phase of a project,
System One-Line a project as a basic concept. Other alterations are made to the Design
information can be added throughout Development Electrical Drawing set.
Power system designers communicate the design cycle. It can then be copied ii
At some level of completion (typically
their design requirements through a and modified to create a number of 90%), these drawings are sent out
combination of drawings, schedules alternate drawings showing different to finalize budgetary estimates and
and specifications. system approaches. This permits the narrow the field of contractors to be 1
One of the key tools in developing power system designer to analyze the included in the selection process.
and documenting an electrical power impact of each arrangement on cost, During the push from 90% to 100%
system is the System One-Line (also redundancy and projected physical completion of the construction 2
called a Single Line Diagram). This space requirements. documents, the construction
drawing starts with the incoming manager or the general contractor
power source from the utility service
The System One-Line takes on is asked to provide a Guaranteed 3
increasingly more importance as the Maximum Price (GMP).
and/or on-site generation and their project evolves through the Design
associated distribution equipment.
It then follows the power flow down
Development Phase. Input from the During the Bid or Negotiation Phase 4
other architectural, mechanical, of a project, Bid Document Drawing
through the various conductors as well plumbing, electrical and fire Sets are sent out to a list of potential
as any voltage transformations to feed
distribution equipment buses for the
protection professionals on the contractors. Estimators at these 5
design team helps to better define contractors review the Bid Package
key loads served. the various equipment loads and and tabulate the value of the electrical
Initially, the System One-Line provides develop the power system one-line equipment, conduit and cable costs 6
a framework for the incorporation of to accommodate them. plus manpower necessary to build out
different types of required information the project.
At some point in this stage, a
such as: construction manager may be
7
1. Incoming service voltage and brought in to assist the owner and
utilization voltages required. architect in assessing the design’s 8
constructability. Various improve-
2. Electrical distribution equipment ments that could increase energy
ampacity and short-circuit ratings. efficiency and/or reduce construction
costs are often suggested.
9
3. Overcurrent/short-circuit
protection. Moving toward the end of the Design
Development Phase, the One-Line 10
4. Conductor types (i.e., cable or
and associated drawings such as
busway) and sizes. (Cable lengths
equipment room elevations and floor-
may also be estimated to determine
plans are provided to the client for 11
voltage drop and any upsizing
their review and approval. At this
necessary.)
point, both the client’s comments and
5. Transformer kVA sizes, ampacity, the construction manager’s additional 12
impedance and voltages. inputs are integrated into the design.
This final set of approved design
6. Generator kW sizes and voltages. development drawings, which include 13
7. Motor loads and voltages. the Power System One-Line, are used
as the basis for the development of the
8. Other power quality equipment construction drawings. 14
such as surge protection devices,
power factor correction capacitors
or uninterruptible power supplies. 15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-2 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 008

i Importance of the Other requirements such as: Zone The System One-Line is the common
Selective Interlocking of breakers, 100% map that all the other project
System One-Line rated breakers, drawout or electrically documents must reference and be
operated breakers and key interlock checked against. To ensure consistency
ii It is important for the power system
designer to ensure the System One-
schemes can be overlooked if they are and avoid conflicts after a project is
not documented on a One-Line and awarded to a contractor, distribution
Line and other design documents coordinated in the specifications. panelboard schedules and specifica-
1 contain as much information as
tions also need to include the correct
possible, to assure that bidding Finally, electrical equipment is subject information about details such as the
contractors include all the correct to environmental issues such as enclosure type required.
2 requirements in their pricing. Errors wet areas and may require specific
and/or omissions on the construction enclosure types to be provided. For these reasons, it is critical that
contract documents can lead to Nomenclature on the One-Line, such the engineer be vigilant and take a
3 expensive contractor change orders as 3R or 4X, adjacent to these items proactive role in identifying changes
and project cost overruns after the can clarify what enclosure type is to and updating the System One-Line
contract is awarded. be provided. and associated design documents
4 During the various stages of a project The proper use of notes on the One-Line
appropriately and consistently.
design, changes are made often to can further define the requirements. The One-Line diagram on the following
reflect the client’s preferences and As an example, a note can be added pages is an example developed for
5 budget. As the design process clarifying that all NEMA 4X rated illustrative purposes only and was
continues, coordination between enclosures are to be of 316 stainless developed to show a wide range of
the MEP (Mechanical, Electrical and steel versus the less expensive 304 product applications. This diagram
6 Plumbing) design disciplines become Grade. The difference between these will be referenced throughout the
more critical. two grades is critical as 316 Stainless is remainder of this section.
far more resistant to saltwater, sulfuric
7 If the design professionals are not acid and chlorides, and is preferred in The references to external drawings is
synchronized on these changes, a several applications including pharma- for illustration only and not referencing
previously unanticipated piece of ceutical manufacturing and wastewater actual documents within this section
8 equipment may be chosen or added treatment plants. or elsewhere.
to the project. As an example, where
an engineer had previously allocated
9 a 250 A circuit breaker to feed the
DSB-DF2A
anticipated load, as a result of an 480 V, 600 A,
equipment change, a 400 A breaker 3Ø, 3W, 65 KAIC
10 must now be provided. The impact of
this change can result in a contractor 150AF 150AF 150AF 150AF
bid that does not include both the 15AT 90AT 15AT 90AT
11 correct breaker AND the correct cable
sizes to feed the larger load.
12 Oftentimes, requirements such as
electronic trip units or their protective 2 4X
functions such as Long, Short, FUEL HVAC HEAT COMFORT
13 Instantaneous and Ground (LSIG) PUMP
FOP-1
AHU-1,2,3,4 REJ.
UNITS
COOLING
CH-1
or Ground Alarm (LSIA) are not HRU-1,2,3,4
indicated on the One-Line. This can
14 lead to equipment being supplied Figure 1.2-1. Example of Notes on One-Line
with standard thermal-magnetic
trip units that may lack the setting
15 capabilities to achieve the proper
selective coordination required.

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-3
August 2017 Designing a Distribution System
Sheet 01 009

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-4 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 010

i
UTILITY FEEDER #1 UTILITY FROM PSG-2A (SEE DWG E102) BUSWAY RISER
13.8 kV, 3Ø, + GND 60Hz METERING 4.16 kV, 3Ø, 60Hz (SEE DWG E106)
M
ii SPLICE IN PROPERTY LINE MANHOLE M1
M1-00 RBP-F3A T5-RBP-F3A
4 6

PXM6000
N.O. (3)
(3) SINGLE PHASE POTHEADS (1/Ø) P=208A S=1804A METER
USG-1A "POINT A" 11.65KA SCA
M. H A PT'S
AVAILABLE FROM UTILITY AL 480V:120V
13.8kV, 1200A, 8
1 50 kA SYM S.C.
(15kV - 95KV BIL RATED)
(4) GROUND STUDS (3-Ø, 1-GND)
(2) UTILITY PT's
LO 300E
250KA
/Ø.SPD
MAIN CB
(6) LIVE LINE INDICATORS (2/Ø) 14,400:120V 10A "RBS-F3A"
N.C.
E.O.
M. H P 2000 AF
7 1500kVA 1800 AT
2 TRIP M1
TRIP S1
LO F3D 4.16kV-480/277V
5.75% Z
LSG
(3) 2000:5
UTILITY
(3) PT'S CT's (2)
500:5 RHBP-F3A T4-RHBP-F3A
14,400:120V N.O.
3 27 59
(3)
120:1
(3)
M. H
6
A
P=104A S=2082A
AL
TS RESIDENCE
M1 M1 VFI-3A
(3) (3) HALL B
SB 600A
(3) 800:5 (SEE DWG E105)
4 STD (C100) M. H
5
P
N.C.

SELECTOR SWITCH
750kVA FR3 VFI PADMOUNT
55/65C 5.75% Z
EDR-5000-M1 1 TRIP M1 W/SURGE+LIGHTNING 4.16kV-60KV BIL
G R A TRIP S1 ARRESTERS 208/120V-20KV BIL
52-M1
M1A LO
1200A N.C.
5 (1) (3)
86
(1)
TRIP M1
C/S
52
M1-L
(1) N.O.
DFP-F3A T3-DFP-F3A
P=139A S=1203A
50/51N 50/51 A
86 M. H
M1 M1 M1 TRIP S1 4 AL
T1
LO 200E DINING
TS SB
6 (3) 800:5
STD (C100)
TS
N.C.
FACILITY
(SEE DWG E104)
(1) (3) M. H P
51G 87 1000kVA
PXM6000 3
(3) 600:5 MR T1 T1 LO F3B 4.16kV-480/277V
METER

7 (4) GROUND STUDS


Set at 350:5
TS TS
ETR-5000-T1
TS
5.75% Z

(3-Ø, 1-GND)
RHAP-F3A T2-RHAP-F3A
N.O. P=104A S=2082A
TRANSFORMER "T1" M. H A

8 PRIMARY UNIT SUBSTATION STYLE


13.8KV DELTA PRIMARY - 95KV BIL H2
M1-00
63
(1)
2
"POINT C" F3A - VFI-2A
AL
RESIDENCE
P/FA=479A 11.32KA SCA HALL A
4.16/2.4KV GROUNDED WYE - 60KV BIL T1 600A
WITHOUT MOTOR (SEE DWG E103)
EATON "PEAK" 55C/65C/75C H1 H3 N.C.
CU 71 49 SCA & CABLE Z TO M. H P
750kVA FR3 VFI PADMOUNT
9 7500/8400/9156 KVA KNAN
9375/10500/11445 KVA KNAF X1
X0
X3

S/FA=1589A
T1
(1)
T1
(1)
T1 & T2-RHAP 1
SELECTOR SWITCH
W/SURGE+LIGHTNING
55/65C 5.75% Z
4.16kV-60KV BIL
"POINT D" - 40,400 SCA
WITH UNLIMITED PRIMARY SCA
FR-3 FLUID FILLED, 6.5% MINIMUM Z X2 ARRESTERS 208/120V-20KV BIL & 50% MOTOR CONTRIBUTION
WITH SURGE + LIGHTNING ARRESTERS (1) 600:5 SEE XFMR TABLE 1.6-7 FOR
2000A BUSWAY M1-03
HI (C200) T2 ESTIMATING PURPOSES.
10 PSG-1A (4) GROUND STUDS "POINT B" T1 - 11.32KA (4) GROUND STUDS
CHILLER #1
(3-Ø, 1-GND) SCA WITHOUT MOTOR SCA, (3-Ø, 1-GND)
"BUS A" 4.16KV, CUP
2000A, 60KV BIL, SB CABLE % Z TO T1 & SB
(3) 2000:5 (3) 2000:5 (SEE DWG E107)
BUSWAY % Z
11 40KA SC RATED

EDR
STD (C200) STD (C200)
M
1 (3) 600:5 MR
3000-S1 G R A PXM6000 Set at 600:5 M1-04
52-S1 EDR
(3) (1) S1A LO METER
TRIP S1 2000A N.C. 52 3000-F3
12 TRIP F1
TRIP F2
51
S1
86
S1
TRIP S1
C/S
S1-L
50/51N
(1)
VFD-F2A
F3 G R A
TRIP F3 52-F3
TS SB F3A LO N.C.
(3) 2000:5 1200 52
TS 50/51 86 C/S DRAW-OUT
F3-L
13 86
(1)
87
EBR
3000 (3) 2000:5
STD (C200) F3
(3)
F3
(1)
TRIP F3

(3) 600:5
DC TO AC
INVERTER
B1 B1 -B1 STD (C200) STD (C100)
(3) SB TS SB

14 TS AC TO DC
CONVERTER
TS SB TS SB
(3) 600:5 (3) 600:5 INTEGRAL
STD (C100) STD (C100) 24 PULSE
(3) (3)
15 50/51
F1 G R A
50/51
F2 G R A
XFMR

(1) 52-F1 (1) 52-F2


F1A LO LO
1200A N.C.
F2A
52 (3) PT'S 1200 N.C. 52 CONTACTOR
50/51N 86 C/S 50/51N 86 C/S
TRIP F1 F1-L 4200V: TRIP F2 F2-L
F1 F1 F2 F2
16 EDR
(1)
120V
35:1 EDR
(1)

3000-F1 (3) 600:5 MR 3000-F2 (3) 600:5 MR


(3) 400A
Set at 400:5 Set at 300:5
PXM6000 PXM6000

17 METER
(3) 2000:5
STD (C200)
METER
(3) 2000:5
STD (C200)
E
ISOLATION
SWITCH
SB SB
(4) GROUND STUDS (4) GROUND STUDS SC9000EP
(3-Ø, 1-GND) (3-Ø, 1-GND) MV-VFD

18 M1-02

M1-02

19 Figure 1.2-2. Power System One-Line (Continued on Next Page)

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-5
August 2017 Designing a Distribution System
Sheet 01 011

i
FROM PSG-2A (SEE DWG E102) DRAWING NOTES
4.16 kV, 3Ø, 60Hz
1 Provide M1 Electrical Interlock With S1 Breaker. M1 Cannot Close if S1 is

ENGINE
ii

DIESEL
Open. S1 Cannot Close Until M1 is Closed. Include Key Interlocks as Shown.
N.O. CUP-F1A Provide MB-F1A Key Interlock With Generator Breaker "GB" and Tie Breaker
2
M. H A "LTA". Only the Single "MGTA" Key Can be Used to Close Any of these Breakers.
10
LO Provide Priority Load Shed Controls for Feeder Breakers in SUS-F1A Switchgear.

M. H P
N.C.
FDR
G
3
Provide Interface With Generator Breaker "GB" to Enable Operation When Non-
Priority Loads have Been Shed.
(SEE DWG E108)
1
9 "G" Provide All Magnum Breakers in SUS-F1A & RBS-F3A Switchgear With DT1150+
LO F1A 4 4000A BUSWAY TO
CLE 2000AF Trip Units Including Zone Selective Interlocking (ZSI) and Arc Flash Reduction
2000AT TIE CB "LTB" IN
600A
PORTABLE
LOAD BANK
Maintenance System (ARMS) in Compliance with Article 240.87 of the 2014 NEC.
Provide Remote Touchscreen Panel With "Switchgear Dashboard Interface" to
"SUS-F1B" 2
P FA=461A 5 Monitor Operational Variables and Enable Arc Flash Reduction Maintenance Mode.
XFMR "ST-F1A"
CU 2500/3333kVA Wire All DT1150+ Trip Units Communications Ports to an Ethernet Gateway With
TOUCH 6

S FA=4000A
115C AA/FA
4.16KV-480/277V
Z=5.75%
SCREEN
5 BACnet IP Connectivity. BMS Vendor Will Provide Field Wiring and Integrate Into
BMS System on a Separate Contract. 3
2 3 2

MGTA
LO E.O.
MAIN CB
"MB-F1A"
4000 AF
(3) PT'S
480V:
120V
EG BACNET IP
TO BMS LO E.O.
"GB"
2000AF
SECONDARY UNIT SUBSTATION "SUS-F1A"
LO E.O.
TIE CB
"LTA"
4000 AF
4
4000 AT 2000AT 4000 AT
N.C. PXM6000 TO DT1150 N.O. LSG N.O.
LSG LSG
METER ETHERNET TRIP UNITS "DF5A"
01B (3) 4000:5
01D 02A 02B
GATEWAY
02C 02D 03A
MAIN SWGR. BUS "A" 85KA, 480/277V, 4000A, 3-PH, 4W

03B 03C 03D 04A 04B 04C 04D


5
"DF1A" "DF2A" "DF3A" "DF4A" "DF6A" "DF7A" "DF8A" "DF9A" "DF1OA" "DF11A" "DF12A"

250KA/Ø
SPD
E.O. 800AF
600 AT
LSIG
E.O. 800AF
600 AT
LSIG
E.O. 1600AF
1600 AT
LSIG
E.O. 1600AF
1600 AT
LSIG
E.O. 800AF
800 AT
LSIG
E.O. 800AF
400 AT
LSIG
E.O. 800AF
600 AT
LSIG
E.O. 1600AF
1600 AT
LSIG
E.O. 800AF
400 AT
LSIG
E.O. 800AF
500 AT
LSIG
E.O. 800AF
500 AT
LSIG
6
SPARE SPARE SPARE SPARE
(SEE DWG E109)
FROM GEN A 7
NORMAL ATS-A GENERATOR
SOURCE SOURCE
BYPASS ATC-900
1600AF
1600AT
DSB-DF4A
480V, 1600A,
SEE SCHEDULE DSB-DF4A
FOR LOADS PP-DF6A
ISOLATION
ATS
TRANSFER
CONTROL
8
3Ø, 4W, 65 KAIC 480V, 600A,
120KA/Ø 800AF 3Ø, 3W, 65 KAIC
SPD 800AT

225AF 400AF 800AF 600AF 400AF 225AF 400AF 480/277V, 800A,


MAINTENANCE
ISOLATION
9
175AT 250AT 800AT 600AT 250AT 200AT 250AT 3Ø, 4W, 65 KAIC BYPASS
MBP BIB RIB
SPARE SPACE 2X
SEE SCHEDULE PP-DF6A
FOR LOADS
UPS1
300KVA
10
1600A MCC-DF3A FREEDOM FLASHGARD MCC
MLO 120KA/Ø 480V, 1600A,
SPD 3Ø, 3W, 65 KAIC 11
400A 150A 150A 150A 150A 400A 400A 150A 150A 150A 150A 150A 150A
FR10 SIZE4 SIZE4 SIZE4 SIZE4 SIZE5 SIZE5 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4
261A FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR FVNR MIS 12
18 2S2W 2S2W 2S2W 2S2W
PULSE SSRV SSRV Eaton 9395 UPS
SS0L SS0L SS0L SS0L SS0L SS0L SS0L SS0L SS0L SS0L
VFD W/GFP W/GFP W/GFP W/GFP W/GFP W/GFP
W/GFP W/GFP W/GFP W/GFP

DC-DS-A
13
3R 3R 3R 3R
6 POLE 6 POLE 6 POLE 6 POLE
200 75 75 75 75 150 150 75 75 75 75 75 75
NCHWP-1
240FLA
CWP-1
96FLA
CWP-2
96FLA
CWP-3
96FLA
CWP-4
96FLA
CHWP-1
180FLA
CHWP-2
180FLA
CT-1
96FLA
CT-2
96FLA
CT-3
96FLA
CT-4
96FLA
SA-1
96FLA
EF-1
96FLA
BAT-A
14
PDU-1
480V-3Ø 600AF 120KA/Ø
IFS-DF7A
600AF
600AT DSB-DF2A
400AF
400AT 150A
P=361A
3W,65kA 500AT
SPD 15
120KA/Ø 480V, 600A, XFMR-DF8A P=361A
SPD 3Ø, 3W, 65 KAIC XFMR-DF7A P=90A 300KVA XFMR-UPS1
225A 75KVA 480-208/120V 300KVA

150AF 150AF 150AF 150AF 150AF 150AF 150AF


"DF7AP"
480-
208/120V S=208A
S=833A
S=833A
480-208/120V

208/120V, 3Ø, 4W
16
40AT 15AT 90AT 100AT 90AT 100AT 100AT RP-DF8A
480/277V 225A
SPARE SPACE 2X 3Ø, 4W, 65KA 225A
1200AF 400AF 400AF
POW-R-COMMAND
LIGHTING CONTROL 208/120V, 225A,
3Ø, 4W, 10 KAIC
1000AT 400AT 400AT
17
POW-R-COMMAND 208/120V, 1200A, CDP-A CDP-B
10 2 4X 4X 3Ø, 4W, 65 KAIC 42 Circuit 42 Circuit
RECEPTACLE CONTROL
GYCOL FUEL HVAC HEAT COMFORT HEAT
PUMP
GCP-1
PUMP
FOP-1
AHU-1,2,3,4 REJ.
UNITS
COOLING
CH-1
REJ.
UNITS SEE SCHEDULE IFS-DF7AP & DF7AS SEE SCHEDULE RP-DF8A SEE SCHEDULE PDU-1
18
HRU-1,2,3,4 HRU-5-9 FOR NORMAL & CONTROLLED LOADS FOR LOADS FOR CRITICAL LOADS

Figure 1.2-2. Power System One-Line (Continued)


19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-6 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 012

Standardized Drawing Symbols Medium-voltage circuit breakers half of the system one-line on
i shown on a one-line typically incorpo- Page 1.2-4 shows “T1” as Eaton
In the North American market, the rate the Basic Square Breaker symbol “Peak” Style Triple Temperature Rated,
American National Standards Institute with the ANSI Device Number 52 7.5 MVA, FR3 Envirotemp™ Fluid Filled,
ii or ANSI for short, in cooperation with inside. Medium-voltage breakers may Power Transformer. The transformer’s
the Institute of Electrical & Electronics be either fixed mount (square with kVA ratings are indicated at the KNAN,
Engineers has developed standardized device number inside) or drawout as (Natural Air Cooled by Convection—
1 drawing symbols and nomenclature to shown in Figure 1.2-3 as well as the Over 300C Fire Point Fluid Filled)
represent common devices represented system one-line on Page 1.2-4. and KNAF (Forced Air Cooled Over
on one-lines, control schematics and 300C Fire Point Fluid Filled) ratings.
2 other electrical drawings. The existing
It is important to develop a naming See Tab 16 for details.
convention so personnel working
Standard for North America (including
on or responding to an event on the The “T1” transformer is described as
the Canadian Standard CSA Z99) is IEEE
3 315-1975 (Reaffirmed 1993)/ANSI Y32.2.
power system can readily identify “Delta” Primary, “Wye” Secondary
the equipment experiencing any configuration in the text as well as
This version recognizes that “Electrical problems. This naming convention is further depicted by the relationship of
4 diagrams are a factor in international also useful for those doing preventa- the “H1, H2 and H3” connections to the
trade: the use of one common symbol tive maintenance in documenting X1, X2, X3 and X0 symbols adjacent
language ensures a clear presentation which specific switchgear, breaker, to it. Similarly, the verbiage in the
5 and economical diagram preparation transformer or protective relay they text calls for surge and lightning
for a variety of users.” Consequently, need to address. protection. Symbols for the arrester
the Standards Coordinating Committee and the capacitor are shown connected
Transformers are common compo-
6 has added various International
nents of a power system and are used
to the incoming terminations. Their
Electrotechnical Commission (IEC) actual ratings should be defined on
on both medium-voltage and low- the drawing or in the specifications.
symbols that are in use worldwide.
voltage applications to step a voltage
7 Item A4.1.1 of IEEE 315 defines a up or down to a desired level. They Both the transformer’s primary and
Single-Line or (One-Line) Diagram as: are available in a variety of winding secondary amps are included as a
8 “A diagram which shows, by means of configurations as detailed in the reference for sizing the conductors.
single lines and graphic symbols, the “Typical Components of a Power This is useful to determine the quantity
course of an electric circuit or system System” in Section 1.6 of this Tab 1 and size of the MV cables per NEC
9 of circuits and the component devices document.) Article 310.60. While medium-voltage
or parts used therein.” conductors are available in 90C (MV90)
Because there are many types and or 105C (MV105) ratings, the actual
Components such as those represent- configurations of transformers terminations in the transformer or
10 ing circuit protective devices like fuses available, it is necessary to properly switchgear cable compartments are
and circuit breakers are indicated in document the specific requirements limited to 90C. When sizing the MV
their most basic form. Device repre- on the One-Line. Primary unit cables, the NEC derating factors must
11 sentations can be created by adding substation transformers are used also be applied depending on the
other components and nomenclature to convert a medium voltage to type of raceway or duct bank that
to the base component drawing. another medium voltage. See Tab 13
12 Low-voltage <1000 V circuit breakers for details.
will be required.
are represented by the first two of Where higher transformer secondary
Secondary Unit Substation currents are involved, a busway flange
the following symbols shown in
13 Figure 1.2-3.
Transformers transform a Medium and non-segregated busway can be
Voltage to a Low Voltage Level, supplied to connect it to the down-
generally under 1000 Vac. They are stream MV switchgear (as shown
14 LOW LOW MEDIUM
available in Fluid-Filled and Dry-Type in Figure 1.2-4). Proper selection and
styles. See Tab 14 for details. application of the busway requires that
VOLTAGE VOLTAGE VOLTAGE
Both types of unit substation trans- the rated short time and short circuit
15 formers can be supplied with fans to withstand current values be specified.
increase the transformer’s kVA ratings. See Tab 11 for details.
16 52 Figure 1.2-4 from the medium-voltage

17 FIXED DRAW-OUT DRAW-OUT TRANSFORMER “T1”


MOUNT POWER POWER PRIMARY UNIT SUBSTATION STYLE M1-00
(1)
CIRCUIT CIRCUIT CIRCUIT 13.8 KV DELTA PRIMARY - 95KV BIL H2 63
18 BREAKER BREAKER BREAKER 4.16/2.4 KV GROUNDED WYE - 60KV BIL
P/FA = 479A
T1
EATON “PEAK” 55C/65C/75C H1 H3 71 49
CU
Figure 1.2-3. Circuit Breaker Symbols 7500/8400/9156 KVA KNAN X3
19 9375/10500/11445 KVA KNAF X1
X0 T1 T1

FR-3 FLUID FILLED, 6.5% MINIMUM Z


S/FA = 1589A (1) (1)
X2
WITH SURGE + LIGHTNING ARRESTERS (1) 600:5
20 P/FA = CURRENT RATING. PRIMARY, FORCED AIR. 2000 A BUSWAY HI (C200)
S/FA = CURRENT RATING. SECONDARY, FORCED AIR.

21 Figure 1.2-4. Transformer Information and Symbols

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-7
August 2017 Designing a Distribution System
Sheet 01 013

Short-circuit values are critical in INCOMING SERVICE CALCULATIONS


the design and specification of all i
electrical equipment in a power Megawatts Required 8.17 MW KW = 8170 KVA = 10,213
KVA Conversion = Kilowatts x Power Factor PF = 0.8
system. The transformer’s Impedance,
(often abbreviated as %Z) must be
NUMBER OF INCOMING SERVICES PARALLELED
Contingency =
Transformers Must Be Sized to have:
0 Feeders
1 Carry Entire Load. Min KVA Each =
1

10,213
ii
shown on the One-Line in order
to calculate the required ratings of
downstream equipment as indicated
Primary
Voltage KV
Temp Rise
Rating
% Capacity
Increase KVA Rating
Primary Secondary
Current Voltage
Secondary
Current
%
Impedence
Available
Sec SC * 1
13.8 55C KNAN Base Rating 7500 313.8 4.16 1040.9 6.5 16014
in Figure 1.2-5. 13.8 65C KNAN 12.0% 8400 351.4 4.16 1165.8
13.8 75C KNAN 22.1% 9158 383.1 4.16 1271.0
It is important to remember that 13.8
13.8
55C KNAF
65C KNAF
25.0%
40.0%
9375
10500
392.2
439.3
4.16
4.16
1301.2
1457.3
2
all transformers designed to ANSI 13.8 75C KNAF 52.6% 11445 478.8 4.16 1588.5
standards have a plus and minus Transformer Available Amps for Contingency Conditions =
Calculated Required Amps for Contingency Conditions =
1588.5
1417.4
7.5% tolerance for impedance. If a 3
transformer requires an absolute SHORT CIRCUIT CALCULATIONS AND SWITCHGEAR MVA SELECTION CRITERIA
minimum impedance to ensure the
If Known SC= 11650 Available Primary SC Fault Current
secondary short-circuit level does 5kV
Breaker
Max
KA Rating f= 2.4132649 FORMULA = (SC*PV*1000*1.732*Z)/(100000*KVA) 4
not exceed a critical value, it must be 50 VCP-W 25 25 M= 0.2929746 FORMULA = 1/(1+f)
50 VCP-W 40 40 I2 = 11323 FORMULA = (PV/SV)*M*SC
noted on the One-Line and in the 50 VCP-W 50 50 # of Services Paralleled = 1
accompanying project specifications. 50 VCP-W 63 63
Available Secondary Short Circuit Current
With Known SC Current
11,323
* Unlimited short circuit
16014 5
Consideration must also be given to NOTE: CALCULATION DOES NOT INCLUDE DOWNSTREAM MOTOR CONTRIBUTION

the types of cable terminations based


on the available short-circuit ratings.
6
Figure 1.2-5. Incoming Service Calculation
Where the available short-circuit
This is done to indicate to the equip-
exceeds 12.5 kA, medium-voltage
molded rubber deadfront termina-
ment manufacturer or installing 7
contractor that the CT inputs to the
tions are generally not an option. In
relay should not be grounded in
these cases, the type of terminations 8
more than one location.
must be specified. Stress Cone cable
OR
terminations are available in either Hot CTs generally are wired to shorting ter-
Shrink or Cold Shrink configurations. minal blocks as indicated by the “SB” 9
Porcelain terminators or potheads are in the box shown in Figure 1.2-7. These
a more expensive option, but often are used to short out the secondary of
have higher short-circuit ratings. the CTs prior to equipment installation 10
OR
or when servicing them.
Current transformers are used in both
low- and medium-voltage applications
as sensing devices for protective 11
relays and meters. They are available (3) PT'S
UTILITY
CT’s (2)
in “donut” style, which encircle the Figure 1.2-6. Current Transformer Symbols 14,400:120 V
500:5

conductor, as well as bar style, which (3) 120:1 (3) 13.8 kV, 1200 A, 50 kA SYM S.C.
(15 kV - 95 KV BIL RATED)
12
is bolted in series with the load In the case of Differential Protection (3) 800:5
SB

conductors. Both styles work on Circuits such as the 87-T1 Transformer STD (C100)

the principal of electromagnetic Differential or the 87-B1 Bus Differential, 1


52-M1
G R A
TRIP M1
TRIP S1
13
coupling; a current flowing through the CTs are oriented in opposing (1)
M1A LO
1200 A N.C.
C/S
52
M1-L
(1)
the conductor they surround induces directions as illustrated in Figure 1.2-7. 86 TRIP M1

a proportional isolated low level This permits the Differential Relays


M1 TRIP S1

SB
(3) 800:5
86
T1

TS
14
signal (either 1 A or 5 A) that can be to measure the current going into a STD (C100)
(1)
87
(3)
51G
measured by an electromechanical or transformer or busbar and deduct the T1 T1

electronic device. current flowing out of it. When more (4) GROUND STUDS
(3) 600:5 MR
Set at 350:5
TS TS
ETR-5000-T1
TS
15
(3-Ø, 1-GND)
current is flowing into the zone of
Current transformers may be shown protection than is proportionally M1-00
in several formats as indicated in flowing out, the relay senses the H2
P/FA=479 A
63
T1
(1)
16
Figure 1.2-6. “differential” and trips the circuit X3
H3 CU 71 49
X0 T1 T1
breakers at high speed to protect 1
S/FA=1589 A (1) (1)
The dots, X’s or boxes are used to
against a fault anywhere in the zone.
X2

2000 A BUSWAY
(1) 600:5 17
denote the instantaneous polarity HI (C200)

orientation of the CT. The polarity Note the “Y” symbol, as well as the
(4) GROUND STUDS
(3-Ø, 1-GND)
“POINT B” T1 - 11.32 KA
SCA WITHOUT MOTOR SCA,
marks on the conductor generally face quantity “(3)” next to the CTs. This
SB
(3) 2000:5
STD (C200)
CABLE % Z TO T1 &
BUSWAY % Z 18
toward the source of the current flow. represents three CTs configured in a 1
The polarity mark on the CT winding three-phase grounded wye arrange- (1) S1A LO
52-S1
G R A
2000 A N.C. 52
represents the relationship of the ment. While most of the CTs on the 86
S1
TRIP S1
C/S
S1-L
19
CT’s X1 secondary terminal to the H1 system one-line on Page 1.2-4 are TS SB
(3) 2000:5
medium-voltage terminal on bar type shown this way, the CTs on the output STD (C200)

CTs or its input orientation for donut side of the 2000 A breaker S1A are
(3) 2000:5
STD (C200) SB
20
style CTs. not grounded. “BUS A” 4.16 KV, 2000 A, 60 KV BIL, 40 KA SC RATED

Figure 1.2-7. Example of Differential Circuit 21


with Current Transformer Symbols

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-8 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 014

It is highly recommended that the Standard for Device Function


i design engineer show Test Switches Numbers, Acronyms and Contact
on the System One-Line and include Designations.
them in the specifications. These are
ii shown on the one-line as a box with See Table 1.11-1 in Power Distribution
“TS” in it. Test switches are used (3) PT’S Systems Reference Data Section of
4200 V:
during protective relay testing to 120 V
35:1
this document for Device Function
1 provide an alternate path to inject Number information.
current and voltage from a test set, These element numbers are shown in
when commissioning these devices a circle on the One-Line. A given relay
2 in the field. may have multiple voltage and current
When designing a power system, it Figure 1.2-8. Voltage Transformer Symbol elements shown in a common box,
such as the EDR 5000-M1 protecting
3 is necessary to select the ratio and The secondary output of both voltage
the 52-M1 breaker in Figure 1.2-9.
the accuracy class for the CT’s. For and current transformers are measured
protective relaying, the CT must be by protective relays and used in calcula- The numbers in parenthesis define the
4 sized to ensure they do not saturate tions involving preset thresholds. quantity of each specific element. In
under fault conditions. This may result many cases this quantity is (3); one
in a higher accuracy class with more Voltage monitoring elements of
for each of the three phases. In some
5 physical mass or a higher CT ratio protective relays compare the input
cases, such as the 50/51N function,
being specified. Most of the CTs from the VTs against a desired set-
this is shown as a quantity of (1).
shown on Figure 1.2-7 are Standard point to see if the system voltage is
The symbol to the right of this relay
6 Accuracy Class for the ratios selected. over or under that nominal value. If
represents a transition from (3)
The exception is the single 600:5 CT the value exceeds a plus or minus
individual phase elements to a single
in transformer T1’s Neutral to Ground tolerance band around the set-point,
residual neutral protective element.
7 Connection. This is shown as a high an output contact or contacts in the
relay change state to signal an alarm
accuracy CT. The output of each protective function
or trip the circuit breaker open. is shown with a dashed line and arrow
8 When selecting CTs for metering indicating what action is to be taken if
purposes, such as those connected Microprocessor-based relays offer
the relay determines the monitored
to the Eaton PXM-6000 Power Quality tremendous functionality over the
values exceed the preset thresholds.
Meter (see Tab 3 for details) it is older electromechanical and solid-
9 best to use the CT ratio as close to state predecessors. Many of these
The EDR-5000-M1 Relay’s 50/51
Elements (Instantaneous Overcurrent
the actual load as possible. This is devices offer multiple types of voltage
and Time Overcurrent respectively)
done to increase the accuracy at the and current protective elements.
10 low end of the range because the CT’s
are shown tripping a high-speed 86-M1
Protective relay elements are generally Lockout Relay. The elements of the
excitation begins to deteriorate at denoted by a number or characters ETR-5000-T1 Transformer Differential
11 about 10% of its ratio setting. As an as defined in the ANSI/IEEE C37.2 Relay are shown similarly, also tripping
example, a 600:5A fixed ratio CT an 86-T1 lockout relay.
would begin to lose accuracy at 60 A.
12 Where loads are light, during
construction or during early build out USG-1A (3) SINGLE PHASE POTHEADS (1/Ø) “POINT A” 11.65 KA SCA
AVAILABLE FROM UTILITY
stages, the actual current that must be
13 measured by the meter may be only
(4) GROUND STUDS (3-Ø, 1-GND)
(2) UTILITY PT’s
(6) LIVE LINE INDICATORS (2/Ø) 14,400:120 V
100 A. Multi-ratio CTs are frequently 10 A

used to set the maximum ratio lower.


14 If set at 100:5A, this would improve TRIP M1
accuracy down to 10 A for a 100 A TRIP S1 UTILITY
CT’s (2)
load. Conversely, as the end loads (3) PT’S
15 grow, the maximum ratio setting can 14,400:120 V
500:5

(3) 120:1 (3) 13.8 kV, 1200 A, 50 kA SYM S.C.


be easily increased by changing the 27 59
(15 kV - 95 kV BIL RATED)
TS
CT tap settings. M1 M1
16 (3) (3)
(3) 800:5
SB
Voltage transformers are used to step STD (C100)
higher voltages down to safe levels
17 for inputs to relays and meters. EDR-5000-M1 1
52-M1
G R A
TRIP M1
TRIP S1
Traditionally, voltage transformers M1A LO
1200A N.C.
52
(1) (3) (1) C/S
(VTs) utilize a higher primary voltage M1-L
(1)
18 winding that is a fixed ratio to the
50/51N
M1
50/51
M1
86
M1
TRIP M1
TRIP S1 86
T1
120 Vac secondary winding. Examples TS SB
(3) 800:5
shown on the One-Line are TS
19 14,400 V:120 V (a ratio of 120:1) or
STD (C100)
51G
(1)
87
(3)
4200 V:120 V (a ratio of 35:1). Voltage PXM6000
METER (3) 600:5 MR T1 T1
transformers are often referred to as Set at 350:5 ETR-5000-T1
20 potential transformers or PTs. They are (4) GROUND STUDS
(3-Ø, 1-GND)
TS TS TS
illustrated symbolically as shown in
Figure 1.2-8.
21
Figure 1.2-9. Protective Relay Element Symbols

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-9
August 2017 Designing a Distribution System
Sheet 01 015

In both cases, the associated (86)


lockout relay then trips the incoming i
main breaker “M1” and the transformer EDR-5000 1

secondary breaker “S1”. Lockout relays 27

are used to multiply the tripping


74 50
A
59
ii
Metering and
contacts for a given function so they TC 46 50R 51R BF 50P 51P 67P 67N LOP A Statistics
can be wired into multiple breaker’s 59N Current and volt.:

separate control circuits as indicated 3


CTS SOTF CLPU
unbalance
%THD and THD 1
Fund. and RMS
for the 86-B1 device on the System 25 min./max./avg.
angles
One-Line. Their primary function, 1
47 55

however, is to require a manual reset


3
A/D
Power:
Fund. and RMS
2
of the Lockout Relay mechanism by MVA, Mwatt, Mvar,
PF
trained personnel after the cause of the 27
M
59
M
81
U/O 81R 78V 50X 51X 51V 67G 32 32V

fault is determined and corrected. Event recorder 3


IRIG-B00X Zone Interlocking Breaker Wear Disturbance recorder Fault recorder
The 27 and 59 functions shown in the
EDR-5000 relay monitor undervoltage 4
and overvoltage respectively. Their Figure 1.2-10. EDR-5000 Protective Relay Elements Available
outputs are shown combined into a
single dashed line directly tripping both Figure 1.2-9 shows some additional One such requirement is the breaker’s 5
the incoming main breaker “M1” and important information about the close and latch rating. Where higher
the transformer secondary breaker equipment required in the dashed fault current values exist, some
“S1”. This reflects the engineer’s desire box that comprises utility switchgear utilities specify this value at 130 kA 6
to have only one output contact for “USG-1A”. This switchgear is defined peak, which is more in line with the
both the 27 and 59 functions. Because as 15 kV Class with a 95 kV basic older 1000 MVA rated design. Because
two breakers need to be tripped, this impulse rating. The bus is rated to the 40 kA K=1 design’s close and latch 7
will only require two separate relay handle 1200 A even though the actual rating is only 104 kA, the 130 kA close
contacts instead of four individual ampacity flowing through it will be and latch rating for the 50 kA breaker
output contacts otherwise necessary. under 500 A. The equipment will be would dictate it being used instead. 8
operating at 13.8 kV and have a short- It is very important to be cognizant of
The direct trip shown on the System circuit rating of 50 kA Symmetrical. nuances in all utility specifications
One-Line purposely does not use an See Tab 5 for details. to avoid costly problems or delays 9
86 lockout relay, as this under or over in energization.
voltage disturbance is anticipated to Because this One-Line is for educational
be caused by the utility and not a fault purposes, a hypothetical short-circuit Certain utilities mandate the type
on the end user’s power system. In value at “Point A” from the Utility is of cable termination that must be
10
these instances, a separate contact shown for reference at 11.65 kA. In provided in the switchgear such as the
from the relay may be allocated to actuality, this value would be part of a (3) single-phase pot-heads illustrated
start a backup generator or to initiate short-circuit study. If using a program on Figure 1.2-9.
11
a Main-Tie-Main Transfer Scheme. such as SKM to calculate the down-
stream short-circuit values, the cable Utilities may also require neon glow
The EDR-5000 Relay and the ETR-5000 lengths and conduit types as well as the tubes or other live line indicators to 12
Relay are programmable multi-function transformer impedance would factor be located on all three incoming
devices with many protective elements into the calculations. phases. These devices are intended to
that can be utilized simultaneously. caution personnel that the incoming 13
In a more fully developed protection The “USG-1A” switchgear on the circuit may be energized.
scheme, certain protective elements One-Line is shown with a 50 kA rating
(such as the 50/51 functions) can when other lower ratings such as 14
be used in both relays to back each 40 kA and 25 kA are available at 15 kV.
other up in the event of a failure. This has been done as an example to
Figure 1.2-10 shows the many future design engineers who may be 15
protective elements available in the involved in urban areas with medium-
EDR-5000 Feeder Protective Relay. voltage services. These MV services
(See Tab 4 for further details.) typically have higher available short- 16
circuit capacity. In most cases, the
Eaton’s “E Series” relays include an serving utility may have specific
ANSI 74 element to monitor the trip specifications for the switchgear and 17
coil of the circuit breaker or lockout breakers used as medium-voltage
relay they are tripping. This circuit service equipment.
ensures the integrity of the device to 18
operate correctly when a trip signal is
applied. The example One-Line should
show the relay circle with the “74” in 19
it next to the “86” lockout relay and
breaker “52” symbols. These were
purposely not shown on the drawing 20
as it would make it more crowded
and difficult to read.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-10 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 016

However, it is always best to follow Key interlocks are also used in the Drawing Notes are extremely important
i Occupational Safety and Health Main-Generator-Tie “Bus A” half as they describe specific functional
Administration (OSHA) approved of double-ended 480/277 Vac requirements. In Figure 1.2-13, Note 3
practices and assume that the circuit is secondary unit substation as shown above switchgear “SUS-F1A” describes
ii live until a calibrated voltage reading in Figure 1.2-11 and Figure 1.2-12. This an additional requirement for a Priority
probe attached to a hot-stick deter- scheme permits only one source to Load Shed Scheme to ensure the
mines otherwise. feed “Bus A” of the double-ended generator is not overloaded. The
1 switchgear at a time. details of this scheme would need to
Most utilities and institutions involved be coordinated with the generator
in the distribution of medium-voltage This arrangement, while functional in manufacturer and further defined in
2 power use portable ground cables physically blocking multiple sources the switchgear specifications.
that are applied only after no voltage such as “MB-F1A”, “GB” and “MB-F1B”
presence has been confirmed. from being paralleled, does not permit Note 4 calls for DT1150+ electronic
3 This requires that ground studs be Bus “B” of the double-ended substation breaker trip units that include an
mounted in the switchgear in order to be alternately fed from the “MV-F1A” Arcflash Reduction Maintenance Mode.
to facilitate their OSHA compliant breaker or the “GB” breaker. This may This feature limits arc flash energy in
4 grounding procedure. or may not be the intent of the design compliance with Article 240.87 of the
engineer. In either case, the engineer 2014 NEC by using an alternate high-
As shown on the System One-Line, must think through the intent of the speed analog instantaneous trip setting
there are ground studs on the incom-
5 ing and outgoing sides of both the
key interlock scheme and develop the to reduce arcing time. Note 5 requires
logic accordingly. a touchscreen panel to monitor the
“USG-1A”, (13.8 kV) and “PSG-1A” operating variables as well as be used
(4.16 kV) switchgear. Applying these Key interlocks are available in a variety
6 portable ground cables requires a safe of configurations including transfer
to activate the Arcflash Reduction
Maintenance Mode remotely. This
disconnection of power in the zone blocks to capture keys from multiple permits personnel who will be working
to be grounded to ensure personnel sources. They are often used as part
7 safety. Consequently, a Key Interlock of Lockout and Tag-Out procedures.
on the equipment to be in a safe
location outside of the arc flash zone
Scheme would be required to prevent It is recommended that the design when enabling the Arcflash Reduction
8 grounding unless the respective engineer refer to a key interlock Maintenance Mode.
breakers in the zone were withdrawn manufacturer such as Kirk or Superior
from their connected position and for further documentation and specific Note 4 also requires Zone Selective
9 locked open. operational details. Interlocking. This feature permits higher
speed tripping of the Main breaker, if it
The symbol representing the key does not receive a restraining signal
interlock shown on the One-Line next from a downstream feeder breaker that
10 to the “M1” and “S1” breaker is the it is tripping to clear a fault.
box with the circle and the letters “LO”
inside it. The “LO” nomenclature
11 indicates that the key “M1A” or key FROM PSG-2A (SEE DWG E102) BUSWAY RISER
“S1A” respectively is only removable 4.16 kV, 3Ø, 60Hz (SEE DWG E106)

when the device (breaker or fused 4 6

12 switch) is in the Locked Open position. N.O.


RBP-F3A T5-RBP-F3A
P=208A S=1804A
(3)
PXM6000
METER
PT’S
M.H A 480 V:120 V
8 AL
250 KA
Key interlocks are also shown on the LO 300E /Ø.SPD

13 MVS switches in two of the (4) Primary


P
N.C.
MAIN CB
E.O. “RBS-F3A”
2000 AF
Selective Step-Down substations fed M.H
7 1500 kVA 1800 AT
LO F3D 4.16 kV-480/277 V LSG
from MV Feeder Breaker F3A, as well 5.75% Z (3) 2000:5
14 as on the medium-voltage switch RHBP-F3A T4-RHBP-F3A
“CUP-F1A”. This is done to prevent M.H A
N.O. P=104A S=2082A
AL
paralleling of the two different sources 6

15 involved in the Primary Selective VFI-3A


600 A
RESIDENCE
HALL B
(SEE DWG E105)
Scheme. See Tab 8 for details. M.H
5
P
N.C.
750 kVA FR3 VFI PADMOUNT
SELECTOR SWITCH 55/65C 5.75% Z
W/SURGE+LIGHTNING 4.16 kV-60 KV BIL

16 The 750 kVA pad-mounted transformers


on the One-Line, feeding “Residence
ARRESTERS 208/120 V-20 KV BIL

DFP-F3A T3-DFP-F3A
N.O.
Hall A” and “B”, are shown with internal M.H A
P=139A S=1203A
AL
4

17 vacuum fault interrupters (VFIs) as their LO 200E DINING


FACILITY
overcurrent protection. The VFIs offer N.C.
(SEE DWG E104)
many of the benefits of a circuit breaker, M.H
3
P
1000kVA

18
LO F3B 4.16kV-480/277V
such as disconnection of all three 5.75% Z

phases simultaneously, and may be


RHAP-F3A T2-RHAP-F3A
used with external protective relays M.H A
N.O. P=104A S=2082A

19 such as EDR-3000 Distribution or 2


“POINT C” F3A -
AL
RESIDENCE
ETR-3000 Transformer Differential 11.32 KA SCA
VFI-2A
600 A
HALL A
WITHOUT MOTOR (SEE DWG E103)
Relay. The VFI option is available SCA & CABLE Z TO M.H P
N.C.
750 kVA FR3 VFI PADMOUNT
1 “POINT D” - 40,400 SCA
20 for fluid-filled transformers in both T1 & T2-RHAP SELECTOR SWITCH
W/SURGE+LIGHTNING
ARRESTERS
55/65C 5.75% Z
4.16 kV-60 KV BIL
208/120 V-20 KV BIL
WITH UNLIMITED PRIMARY SCA
& 50% MOTOR CONTRIBUTION
pad-mounted and unit substation M1-03
SEE XFMR TABLE 1.6-7 FOR
T2 ESTIMATING PURPOSES.
configurations. See Tab 17 for Ratings
21 and Construction details.
Figure 1.2-11. Drawing Notes and Key Interlock Scheme in LV Switchgear

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-11
August 2017 Designing a Distribution System
Sheet 01 017

Note 6 adds a requirement for BACnet of the switchgear. This avoids bottom As outlined in Tab 24 of this Consulting
communications functionality to a exiting cables from covering access to Application Guide, Eaton's low-voltage i
future Building Management System. the lugs for the spare and generator busway can be supplied in ratings of
It also provides a point of demarcation breakers. Consequently, it permits 6–30 cycles. The 4000 A busway shown
between the scope of work to be room to terminate the future cables, has a 200 kA 6 cycle rms symmetrical ii
provided by the installing contractor coming into the top of the switchgear, short-circuit rating that exceeds the
and what portion of the wiring and easily at a later date. 85 kA rating of the “SUS-F1A” switch-
interface will be required of the gear bus on the drawing. 1
BMS vendor. It is always wise to include spare
breakers of important frame and trip The calculated short-circuit rating
Each of the circuit breaker symbols sizes in a drawout switchgear lineup. required for the “SUS-F1A” switchgear 2
in the “SUS-F1A” switchgear are These spare breakers can either allow is dependent on a number of factors
surrounded by double arrows signify- for future load growth or provide a including: the available short circuit
ing that these breakers are drawout readily available backup that can be upstream, the inclusion of the cable 3
versus fixed mount. Additionally, the used in the event that an active breaker and transformer impedances feeding it,
“E.O.” nomenclature in the middle requires maintenance or service. as well as the short-circuit contribution
of the breaker symbol represents
Note that interference interlocks
from the motors downstream. 4
“Electrically Operated”. This function
makes it easier to open and close the are supplied on breakers and in In actuality, the short-circuit current
switchgear compartments where available may be lower than the 85 kA
breaker. It also enables the opportunity
the compartments are of the same shown on the drawing, permitting a
5
for remote control from a handheld
pendant operating station or a wall- physical size. This rejection feature potential cost and space savings, if the
ensures that an insufficient short rating required is dropped to 65 kA or
mounted control panel.
circuit or incorrect ampacity rated below. A short-circuit study would
6
Each circuit breaker is named and its breaker cannot be inserted into the need to be done to confirm this.
Frame Size (AF), Trip Rating (AT) and wrong size cell. See Section 1.3 of this tab for further
protective functions such as Long, information on short circuit and power
7
Short and Ground (LSG) or Long, As an example, a 1600 A breaker systems analysis.
Short, Instantaneous and Ground cannot be used in a cell configured
(LSIG) are noted accordingly. Since for 800 A as it would not likely protect Consequently, it is very important to 8
this equipment is drawout UL 1558 the cell bus runbacks and outgoing indicate the actual breaker short-circuit
switchgear, the 4 cell high structure cables appropriately. Likewise, a 65 kA rating as well as the switchgear bus
number and associated breaker cell short circuit rated breaker could not be ratings on the One-Line. These also 9
are illustrated. inserted into a switchgear cell rated need to be consistent with other
for 85 kA. schedules and drawings, as well as
“Spare” breakers have been located in in the equipment specifications. This 10
the top “A” cells 02A and 04A as well Figure 1.2-12 shows the main bus for can prevent a bidder from incorrectly
as cells 04B and 4C in structure #4. The the switchgear rated at 4000 A with an quoting 85 kA rated switchgear with
generator breaker is also located in top 85 kA short-circuit rating. A busway 65 kA rated breakers. See Tab 20 for 11
cell 03A of structure #3, for cable and symbol is illustrated above the tie further information on Low-Voltage
conduit egress out the top. In this breaker, indicating that it is connecting Metal-Enclosed Drawout Switchgear.
example, all other breaker cables to the other half of a double-ended 12
“feeding loads exit out the bottom switchgear lineup.

13
PSG-2A (SEE DWG E102) DRAWING NOTES
4.16 kV, 3Ø, 60Hz
Provide M1 Electrical Interlock With S1 Breaker. M1 Cannot Close if S1 is 14
ENGINE
DIESEL

1
Open. S1 Cannot Close Until M1 is Closed. Include Key Interlocks as Shown.
N.O. CUP-F1A Provide MB-F1A Key Interlock With Generator Breaker “GB” and Tie Breaker
2
A “LTA”. Only the Single “MGT” Key Can be Used to Close Any of these Breakers.
LO
G
3
Provide Priority Load Shed Controls for Feeder Breakers in SUS-F1A Switchgear.
Provide Interface With Generator Breaker “GB” to Enable Operation When Non- 15
N.C. Priority Loads have Been Shed.
P FDR (SEE DWG E108)
“G” Provide All Magnum Breakers in SUS-F1A & RBS-F3A Switchgear With DT1150+
LO F1A 4 4000 A BUSWAY TO
CLE 2000AF Trip Units Including Zone Selective Interlocking (ZSI) and Arc Flash Reduction
600 A
PORTABLE
LOAD BANK
2000AT Maintenance System (ARMS) in Compliance with Article 240.87 of the 2014 NEC.
Provide Remote Touchscreen Panel With “Switchgear Dashboard Interface” to
TIE CB “LTB” IN
“SUS-F1B” 16
P FA=461 A 5 Monitor Operational Variables and Enable Arc Flash Reduction Maintenance Mode.
XFMR “ST-F1A”
CU 2500/3333 kVA Wire All DT1150+ Trip Units Communications Ports to an Ethernet Gateway With
TOUCH 6

S FA=4000 A
115C AA/FA
4.16 KV-480/277 V
Z=5.75%
SCREEN
5 BACnet IP Connectivity. BMS Vendor Will Provide Field Wiring and Integrate Into
BMS System on a Separate Contract. 17
2 3 2
MAIN CB TIE CB
MGT
LO
“MB-F1A”
E.O. 4000 AF
(3) PT’S
480 V:
120 V
EG BACNET IP
TO BMS LO E.O.
“GB”
2000AF
SECONDARY UNIT SUBSTATION “SUS-F1A”
LO E.O.
“LTA”
4000 AF 18
4000 AT 2000AT 4000 AT
N.C. PXM6000 TO DT1150 N.O. LSG N.O.
LSG LSG
METER ETHERNET TRIP UNITS “DF5A”
01B (3) 4000:5 GATEWAY MAIN SWGR. BUS “A” 85 KA, 480/277 V, 4000 A, 3-PH, 4W, (ALL BREAKERS RATED SC AT 85 KA)

01D
“DF1A”
02A
“DF2A”
02B
“DF3A”
02C
“DF4A”
02D 03A
“DF6A”
03B
“DF7A”
03C
“DF8A”
03D
“DF9A”
04A
“DF1OA”
04B
“DF11A”
04C
“DF12A”
04D 19
250KA/Ø E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 800AF
SPD 600 AT 600 AT 1600 AT 600 AT 800 AT 400 AT 600 AT 600 AT 400 AT 500 AT 500 AT

SPARE
LSIG LSIG LSIG LSIG LSIG LSIG LSIG
SPARE
LSIG
SPARE
LSIG
SPARE
LSIG LSIG
20

Figure 1.2-12. Drawing Notes and Key Interlock Scheme in LV Switchgear


21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-12 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 018

The System One-Line shows the Typical loads are shown, however, for Motor control centers are used to
i incoming surge protective device the various motors being fed out of group overcurrent protection and
(SPD) in “SUS-F1A” is rated at 250 kA motor control center MCC-DF3A. Each different starter types for the motors
per phase. As shown in Figure 1.2-13, motor’s designation and full load in a portion of a power system. They
ii SPDs in the other downstream amps are shown below the motor may also contain associated control
equipment are rated at 120 kA per symbol that contains the motor’s and distribution equipment as well
phase. This surge protection scheme horsepower rating. as connectivity interfaces to industrial
1 as shown is applied in a tiered control or Building Management
approach per the IEEE Emerald Book. Safety switch symbols are shown Systems (BMS). Motor starters, and
In this arrangement, the highest level between the MCC and the motor motor protective overload relays are
2 of surge protection is at the incoming symbol. Safety switches are used to available in both electromechanical
source. Downstream switchboards electrically isolate the motor during and electronic solid-state configura-
or panelboards closer to the loads maintenance or to ensure it does not tions. See Tab 30 for details.
3 provide the next of surge protection. start unexpectedly when personnel are
See Tab 34 for further information on working on or in the equipment it is In a motor control center application,
surge protection. powering. The operating handles of the starter is provided with either a
4 safety switches have provisions for thermal-magnetic circuit breaker or
There is a considerable amount of applying a lock-out tag-out device. high magnetic circuit protector (HMCP)
distribution equipment illustrated on They are generally provided with selected to permit the high inrush
5 the example System One-Line. For that fuse protection to ensure adequate current of the motor while starting.
reason, reference is made to other short-circuit ratings for the application. Either type of overcurrent protective
drawings and schedules that would For those situations requiring a short- device provided must be selected to
6 comprise the hypothetical bid package. circuit rating of 10 kA or less, a non- coordinate with the motor overload
As an example, 1600 A distribution fused safety switch may be specified. protection relay.
switchboard DSB-DF4A has a note to See Tab 28 for details.
7 see schedule DSB-DF4A for the end
loads. The same is true for power
panel PP-DF6A.
8
4000 AT 2000AT 4000 AT
N.C. PXM6000 TO DT1150 N.O. LSG SECONDARY UNIT SUBSTATION “SUS-F1A” N.O.
LSG LSG
9 01B (3) 4000:5
METER ETHERNET
GATEWAY
TRIP UNITS “DF5A”
MAIN SWGR. BUS “A” 85 KA, 480/277 V, 4000 A, 3-PH, 4W

01D 02A 02B 02C 02D 03A 03B 03C 03D 04A 04B 04C 04D
“DF1A” “DF2A” “DF3A” “DF4A” “DF6A” “DF7A” “DF8A” “DF9A” “DF1OA” “DF11A” “DF12A”

250 KA/Ø E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 1600AF E.O. 800AF E.O. 800AF E.O. 800AF E.O. 1600AF E.O. 800AF E.O. 800AF 800AF
10 SPD 600 AT
LSIG
600 AT
LSIG
1600 AT
LSIG
1600 AT
LSIG
800 AT
LSIG
400 AT
LSIG
600 AT
LSIG
1600 AT
LSIG
400 AT
LSIG
500 AT
LSIG
E.O.
500 AT
LSIG
SPARE SPARE SPARE SPARE
(SEE DWG E109)

11 NORMAL
SOURCE
ATS-A
FROM GEN A
GENERATOR
SOURCE
BYPASS ATC-900
1600AF DSB-DF4A SEE SCHEDULE DSB-DF4A ISOLATION TRANSFER
1600AT 480V, 1600A, ATS CONTROL
FOR LOADS PP-DF6A
12 120 KA/Ø
SPD
3Ø, 4W, 65 KAIC
800AF
800AT
480 V, 600 A,
3Ø, 3W, 65 KAIC

480/277V, 800A, MAINTENANCE


225AF 400AF 800AF 600AF 400AF 225AF 400AF ISOLATION
3Ø, 4W, 65 KAIC
175AT 250AT 800AT 600AT 250AT 200AT 250AT BYPASS

13 SPARE SPACE 2X
MBP BIB RIB

UPS1
SEE SCHEDULE PP-DF6A
FOR LOADS 300 KVA

1600 A MCC-DF3A FREEDOM FLASHGARD MCC


14 MLO 120 KA/Ø
SPD
480 V, 1600 A,
3Ø, 3W, 65 KAIC

400 A 150 A 150 A 150 A 150 A 400 A 400 A 150 A 150 A 150 A 150 A 150 A 150 A
FR10 SIZE4 SIZE4 SIZE4 SIZE4 SIZE5 SIZE5 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4 SIZE4
15 18
261A FVNR FVNR FVNR FVNR FVNR FVNR FVNR

2S2W
FVNR

2S2W
FVNR

2S2W
FVNR

2S2W
FVNR FVNR MIS

PULSE SSRV SSRV Eaton 9395 UPS


SS0L SS0L SS0L SS0L SS0L SS0L SS0L SS0L SS0L SS0L
VFD W/GFP W/GFP W/GFP W/GFP W/GFP W/GFP
W/GFP W/GFP W/GFP W/GFP

16 3R
6 POLE
3R
6 POLE
3R
6 POLE
3R
6 POLE
DC-DS-A

200 75 75 75 75 150 150 75 75 75 75 75 75


BAT-A
NCHWP-1 CWP-1 CWP-2 CWP-3 CWP-4 CHWP-1 CHWP-2 CT-1 CT-2 CT-3 CT-4 SA-1 EF-1
240FLA 96FLA 96FLA 96FLA 96FLA 180FLA 180FLA 96FLA 96FLA 96FLA 96FLA 96FLA 96FLA
17 PDU-1
480V-3Ø 600AF 120 KA/Ø
600AF 400AF IFS-DF7A 3W,65 kA 500AT
150 A SPD
600AT DSB-DF2A 400AT
P=361A
120KA/Ø 480V, 600A, XFMR-DF8A P=361A

18 SPD 3Ø, 3W, 65 KAIC


225 A
XFMR-DF7A
75KVA
480-
P=90A 300 KVA
480-208/120 V
XFMR-UPS1
300 KVA
480-208/120 V
208/120 V S=833A
150AF 150AF 150AF 150AF 150AF 150AF 150AF S=208A S=833A
“DF7AP” 208/120 V, 3Ø, 4W
40AT 15AT 90AT 100AT 90AT 100AT 100AT RP-DF8A
480/277 V 225A
SPARE SPACE 2X 225A
19 3Ø, 4W, 65KA
POW-R-COMMAND
LIGHTING CONTROL 208/120 V, 225 A,
1200AF
1000AT
400AF
400AT
400AF
400AT

3Ø, 4W, 10 KAIC


208/120 V, 1200 A, CDP-A CDP-B
POW-R-COMMAND
10 2 4X 4X 3Ø, 4W, 65 KAIC 42 Circuit 42 Circuit
RECEPTACLE CONTROL

20 GYCOL
PUMP
GCP-1
FUEL
PUMP
FOP-1
HVAC
AHU-1,2,3,4
HEAT
REJ.
UNITS
COMFORT
COOLING
CH-1
HEAT
REJ.
UNITS SEE SCHEDULE IFS-DF7AP & DF7AS SEE SCHEDULE RP-DF8A SEE SCHEDULE PDU-1
HRU-1,2,3,4 HRU-5-9 FOR NORMAL & CONTROLLED LOADS FOR LOADS FOR CRITICAL LOADS

21 Figure 1.2-13. Distributor Equipment Downstream of the SUS-P1A Switchgear

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-13
August 2017 Designing a Distribution System
Sheet 01 019

This combination starter is mounted in Electromechanical overload relays Many two-speed starters are applied
a removable “bucket”. Lower ampacity sense an overcurrent by directing the on motor loads such as cooling i
buckets are wired to stabs on the rear current through a melting eutectic towers, where the fan needed to run
of the bucket and manually plugged element or a heater pack. The heat is at a lower speed or higher speed, to
directly onto the vertical power bus proportional to the amount of current optimize the heat transfer and main- ii
bars in the MCC. flowing. When the eutectic element tain water temperature in the return
melts or the bimetal bends due to the supply to the chiller.
Note: Larger hp starter sizes may be
physically hardwired to the bus.
heat from the heater pack, the relay 1
opens the control circuit. ASHRE 90.1 is recommending the
use of variable frequency drives in
Eaton’s FlashGard™ motor control
center “bucket” shown in Figure 1.2-14
The “SSOL” nomenclature next to the applications where they can reduce 2
overload relay shows these particular energy consumption and improve the
adds an additional level of personnel starters as having solid-state overload performance of the equipment they are
safety. The FlashGard design incorpo-
rates a RotoTract™ lead screw assembly
relays. The text “W/GFP” calls for powering. As an example, in lieu of 3
ground fault equipment protection. two-speed motors on cooling towers,
that withdraws the stab assembly off In the past, this would have had to be VFDs are being used to maximize
the energized bus bars and into the
bucket. A spring-loaded shutter then
added as a separate relay, however, efficiency of the cooling process. In 4
many of the new overload relays use these cases, a sensor is placed in the
automatically closes off access to the microprocessors to monitor a number wet well of the cooling tower to
bus bars. See Tab 29 for details. of variables including voltage to the monitor the temperature of the water. 5
The 75 hp Circulating Water Pump motor. Eaton’s C440, C441 and C445 A set-point controller in the VFD
motors CWP1 through CWP4 shown all include phase loss and ground utilizes the output signal from a sensor
in Figure 1.2-13 are examples of full fault protection. mounted in the return water pan as 6
voltage non-reversing starters (FVNR). feedback to modulate the speed of
Eaton’s solid-state overload relays also the fan.
The drawing documents these as have the ability to communicate status
having a full load amp (FLA) rating including current per phase and other The 150 hp CHWP-1 and CHWP-2
7
of 96 A. Based on rating of 96 A key operational variables back to a chilled water pumps in MCC-DF3A
(75 hp), which would require a control system. See Tab 4 for details. are shown being fed from solid-state
NEMA Size 4 combination starter. reduced voltage starters (SSRV). These
8
Motors are available in a number SSRV starters reduce the motor inrush
The starter symbol shown on the of winding styles and performance
drawing includes a normally open and ramp them up smoothly to their 9
characteristics. The 75 hp CT-1 through full running speed. SSRV Starters
contactor. This is followed by an over- CT-4 motors shown fed from MCC-DF3A
load relay symbol. The overload relay can be used to reduce the “water
are of the two-speed, two-winding hammer” effect where the pipes in
measures the current flowing through variety. Note that six-pole disconnects the system experience a sudden thrust
10
the starter contacts to the motor and are required for two-speed, two-wind-
calculates when an extended overload of pressure.
ing motors. Because the cooling towers
condition is present that will damage are typically located outdoors on a roof, Recent declines in the cost of VFDs 11
the motor. A contact from the overload a NEMA 3R drip-proof safety switch and their associated energy savings
relay is wired into the control circuit of would be required. capability have led to their growing
the starter, which deenergizes the con- popularity in a number of HVAC 12
tactor coil in the event of an overload. applications. While VFDs still have
a higher initial purchase cost than
standard starters or solid-state 13
reduced voltage starters, they have
a relatively short payback period.
Racking Tool Receiver Unit Latch
A savvy building owner and design 14
Power Stab engineer will recognize that the total
Position cost of ownership and energy savings
■ Connected Internal must be considered when electing to 15
■ Disconnected Shutter specify VFDs.
Position
■ Open Figure 1.2-13 illustrates a Clean Power, 16
Handle ■ Close (18 Pulse) VFD in the MCC-DF3A
Mechanism feeding NCHWP-1, a 200 hp motor.
This VFD contains a phase shifting 17
transformer that feeds an AC to DC
Breaker converter. This DC voltage is main-
Pilot Device
tained in capacitors on its DC Bus. 18
Island
Insulated Gate Bipolar Transistors
■ Start, Stop,
(IGBTs) are switched ON and OFF
Starter Auto/Man at a high frequency to simulate an 19
AC sinusoidal output waveform.

20

Figure 1.2-14. Freedom FlashGard FVNR Starter


21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-14 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 020

The output voltage and frequency of Medium-voltage VFDs are used to start As soon as generator power is
i this VFD can be set by a digital signal and control the speed of high horse- available, the ATS will transfer to
from the keypad or an external analog power motors in sewage and fresh the generator source and begin to
signal such as 4–20 mA. A set-point water pumping applications. They are feed the UPS’s inverter section.
ii controller in the VFD can also be used also used on medium-voltage high hp
to maintain a temperature, flow rate or HVAC chillers. See Tab 10 for details. In this arrangement, consideration
pressure level by utilizing an external would need to be given to generator
1 feedback signal from a sensor. Below the MCC in Figure 1.2-13 is stability. An ATS or generator failure
IFS-DF7A. This is an assembly that would potentially result in the UPS
The use of VFDs in heating, ventilating, allows several pieces of electrical running on batteries until they were
2 air conditioning (HVAC) has been distribution equipment to be pre- out of reserve power.
popularized due to the VFD’s ability wired into a switchboard at Eaton’s
to save energy. When motors on manufacturing facility. As shown, If this approaches is utilized, the ATS
should be of the BYPASS/ISOLATION
3 centrifugal fans and pumps are oper- the IFS includes a 480/277 V main
design as indicated on the One-Line.
ated at reduced speeds, the energy breaker feeding a 480/277 Vac 225 A
required to produce the torque at lighting control panelboard. See Eaton’s contactor-based BYPASS/
ISOLATION transfer switch is available
4 motor's output shaft is reduced by Tab 23 for details.
with removable contactors. This
the cube of the speed. See Eaton
Application Paper IA04003002E A 75 kVA 480 V to 208/120 V transformer permits them to be interchanged with a
is also part of the IFS switchboard. It spare or the alternate source contactor
5 for details.
feeds a 208/120 V panelboard with during maintenance and testing.
This type of centrifugal load is best remote control breakers to feed various
served by a variable torque VFD that receptacle loads.
6 optimizes the volts per hertz relation-
ship throughout the speed range. In The Integrated Facility System 2

addition to the dramatic energy savings Switchboard (IFS) arrangement, TIE CB

7 that can be experienced below 80% of as shown in Figure 1.2-15 is a great LO E.O.
“LTA”
4000 AF
4000 AT
the motor’s base speed, VFDs ensure a alternative to traditional wall-mounted N.O.
LSG

soft motor start and acceleration panelboards and floor or trapeze SWITCHGEAR “SUS-F1A”
8 throughout the speed range. mounted transformers. Because all of 04C 04D
“DF11A” “DF12A”
this equipment comes as a prewired
Eaton’s CPX Clean Power (18 Pulse) assembly, it generally takes less floor E.O. 800AF E.O. 800AF
9 VFDs are available in low voltage for and wall space than traditional con-
500 AT
LSIG
500 AT
LSIG

operation with 208 V, 230 V, 480 V and struction methods. It also reduces
575 V motors. See Tab 31 for details. installation time and labor costs. (SEE DWG E109)
10 See Tab 21 for details. FROM GEN A

As illustrated on the Power System NORMAL


SOURCE
ATS-A GENERATOR
SOURCE
One-Line on Page 1.2-4, a medium- Figure 1.2-16 shows one possible BYPASS ATC-900

11 voltage Clean Power VFD is available application of an Eaton 9395 ISOLATION


ATS
480 V, 600 A,
TRANSFER
CONTROL

for use with 4.16 kV motors. The input uninterruptable power supply (UPS-1) 3Ø, 3W, 65 KAIC
voltage can be either 4.16 kV or its being fed through automatic transfer
12 internal phase shifting transformer can switch (ATS-A). This arrangement UPS1
be configured to step-down a higher addresses a potential loss of power MBP BIB RIB
300 KVA

input voltage, such as 13.8 kV, to from switchgear SUS-F1A.


13 power a 4.16 kV motor.
During normal operation, power flows
from the “Preferred” Normal source
14 from breaker DF12A in switchgear
SUS-F1A, through the ATS feeding
the inputs to the rectifier input
15 breaker (RIB) and manual isolation MIS
switch (MIS).
Eaton 9395 UPS

When power is lost at the input


16 to ATS-A, the ATS sends a run DC-DS-A

command to Generator A. While


the generator is starting and no
17 power is available to the UPS, the
LOAD
BAT-A

UPS inverter will use the DC energy


stored in its batteries to generate an Figure 1.2-16. UPS-1 Connection Option 1
18 AC sine wave to feed the loads.

19

20
Figure 1.2-15. Integrated Facility
System Switchboards
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-15
August 2017 Designing a Distribution System
Sheet 01 021

A second option for feeding the UPS This would provide an alternate In a data center application, a UPS
would be to avoid providing the ATS path to supply the UPS during a may be used to feed power to one i
and feed the “MBP” and “BIB” from maintenance event, such as servicing or more power distribution units
one breaker in switchgear SUS-F1A a breaker or cable termination. (PDUs). These PDUs are similar in
and the “RIB” input breaker from one Unfortunately, in the event of a power functionality to an IFS Switchboard. ii
breaker in switchgear SUS-F1A and outage to the “SUS-F1A” switchgear, They incorporate an integral trans-
the “BIB” input breaker from another due to substation transformer failure former to step down the incoming
as shown in Figure 1.2-17. or maintenance, power to both the 480 V UPS feed to a 208/120 V supply. 1
UPS Inverter and static switch would The end utilization voltage is distrib-
be lost. Since the purpose of the static uted through integrated panelboards
2
bypass is to operate in the event of a out to the various computer loads. 2
TIE CB downstream fault, the UPS inverter Individual circuits have CTs so each
“LTA”
would not be capable of responding can be monitored on the common
LO

N.O.
E.O. 4000 AF
4000 AT to faults of this nature. It would, touchscreen display. 3
LSG
SWITCHGEAR “SUS-F1A” however, continue to use battery
power to feed the loads until the Eaton PDUs can be provided in a
“DF11A”
04C
“DF12A”
04D
batteries were fully discharged. variety of configurations including 4
other larger frame breakers that can
800AF 800AF
E.O.
500 AT
E.O.
500 AT Because most UPS battery systems are feed remote power panels (RPPs).
LSIG LSIG
not intended to provide long periods See Tab 33 for details. 5
of standby power under the aforemen-
tioned condition, resumption of Normal
power from the “SUS-F1A” switchgear 6
would need to be done quickly. This
may be difficult as personnel would
need to first open the 4000 A “MB-F1A” 7
main breaker. They would then need
to manually operate the Key Interlock
UPS1
300 KVA Scheme to enable a second source, 8
MBP BIB RIB
such as the 2000 kW generator or the
tie breaker to the other half of the
double-ended switchgear. 9
To ensure a quick resumption of power,
transfer switches are also used in a 10
number of healthcare and mission-
MIS
critical applications to automatically
connect to an alternate source should 11
Eaton 9395 UPS main power fail. While UPSs are
traditionally used to back up sensitive
DC-DS-A servers and data processing equip-
ment, there are many other places they
12
BAT-A are utilized. In healthcare, they ensure
Figure 1.2-18. Power Distribution Unit
LOAD a continuous source of reliable power 13
is available for electronic imaging
Figure 1.2-17. UPS-1 Connection Option 2 equipment. See Tab 25 for details.
Larger kVA UPSs are used in industrial 14
applications such as microprocessor
chip manufacturing operations. They
are also used to power ultraviolet 15
purification equipment at fresh
water pumping stations. See Tab 33
for details. 16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-16 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 022

i Additional Drawings, The 310.15(B) (3) from the National The equipment ground sizes are per
Electrical Code defines the Allowable NEC Table 250.122 based on the trip
Schedules and Ampacities of Insulated Conductors rating of the overcurrent device pro-

ii Specifications rated 0-90 degrees C. While details of tecting the phase and neutral conduc-
this table are included in the reference tors. Note that they do not take voltage
While a Power System One-Line is the section of this chapter, it should drop into consideration.
basis for defining the interrelation- be noted that Listed Distribution
1 ships between the various types of Equipment is provided with Table 1.2-1. Ampacity of CU Conductors
distribution equipment, there is often terminations rated at 75 °C. Conductor Ampacity (Copper)
more information that needs to be Conductor Amperes Conductor Amperes
2 conveyed. From a pragmatic standpoint, this Sjze at 75 ºC Size at 75 ºC
means that the equipment could be
Because the end loads and the fed from conductors rated at either 14 15 3/0 200
3 conductors feeding them are the basis 60 °C or 75 °C. Derating would be 12 20 4/0 230
for proper selection and application required for the conductor ampacity 10 30 250 255
of the circuit breakers, a valuable step at 60 °C making it less practical. It also 8 50 300 285
4 in the selection process is developing means that the equipment could be
6 65 350 310
a schedule. fed from 90 °C conductors, but only if
4 85 400 335
applied at the 75 °C ratings due to the
The overcurrent protection of many
5 loads, such as motors and distribution
limitations of the equipment ratings. 3 100 500 380
2 115 600 420
transformers, must conform to the The following tables are adjusted in
1 130 700 460
requirements of Articles 240, 430 and accordance with NEC 240.4(D) to show
6 450 of the National Electrical Code. the actual allowable ampacities of 1/0 150 750 475
Particular consideration needs to copper and aluminum conductors 2/0 175 1000 545
be given to the length and type of terminating in electrical distribution
7 conductors that will need to connect assemblies. Table 1.2-2. Ampacity of AL Conductors
the distribution equipment. Conductor Ampacity (Aluminum)
A schedule based on the allowable
8 As cable length increases, so does its ampacity of copper conductors in
Conductor
Size
Amperes Conductor
at 75 ºC Size
Amperes
at 75 ºC
resistance in the circuit leading to a Table 1.2-1 is shown in Figure 1.2-19. It
drop in the voltage at the end of the includes the relevant requirements for 14 — 3/0 155
9 conductor run feeding the loads. Cable secondary unit substation “SUS-F1A” 12 15 4/0 180
lengths exceeding 100 feet generally shown on the One-Line. This schedule 10 25 250 205
need to be upsized to offset for voltage outlines the breaker frame sizes, trip
10 drop concerns. settings and particulars of the trip
8 40 300 230
6 50 350 250
units required.
Cable length, size and the raceway they 4 65 400 270
11 are installed in, also have an impact on It also annotates the names for the 3 75 500 310
the impedance of the conductor in the breakers as well as their circuit 2 90 600 340
circuit. Greater impedance helps to nameplate designations. The cable
1 100 700 375
12 reduce the available short circuit at the sizes and quantities are determined
1/0 120 750 385
terminals of the distribution equipment by utilizing the tables in the NEC,
or end load. (as condensed into Table 1.2-1). 2/0 135 1000 445
13
SECONDARY UNIT SUBSTATION "SUS-F1A"
14 4000A, 480/277VAC, 3-PH, 4W, 85kA Rated Switchgear and Circuit Breakers
BUS Structure Breaker Trip Poles, N bar Conduit Conduit Cable Entry Position
Location Cell # Name Frame Size Trip Size Function connection Circuit Nameplate Feeder Size Quantity Size into Unit Substation

15
1C MB-F1A 4000 4000 LSG + ZSI MAIN BREAKER "MB-F1A" Close Coupled
2A DF1A 800 600 LSIG + ZSI 3N SPARE Future OVERHEAD
2B DF2A 800 600 LSIG + ZSI 3N DSB-DF2A (2) sets (4)#350MCM +(1)#1G 2 3" UNDERGROUND
16 2C
2D
DF-3A
DF-4A
1600
1600
1600
1600
LSIG + ZSI
LSIG + ZSI
3
3N
MCC-DF3A
DSB-DF4A
(4) sets (3)#600MCM + (1)#4/0G
(4) sets (3)#600MCM + (1)#4/0G
4
4
4"
4"
UNDERGROUND
UNDERGROUND
3A DF-5A 800 600 LSIG + ZSI 3N SPARE Future OVERHEAD
SUS - F1A

3B DF6A 800 800 LSIG + ZSI 3N PP-DF6A (2) sets (4)#600MCM + (1)#1/0G 2 3.5" UNDERGROUND
3C DF7A 800 400 LSIG + ZSI 3N IFS-DF7A (1) set (4)#600MCM + (1)#3G 1 3.5" UNDERGROUND
17 3D
4A
DF8A
DF9A
800
800
600
600
LSIG + ZSI
LSIG + ZSI
3
3N
XFMR-DF8A
SPARE
(2) sets (4)#350MCM +(1)#1G
Future
2 3" UNDERGROUND
OVERHEAD
4B DF10A 800 400 LSIG + ZSI 3N SPARE Future OVERHEAD
4C DF11A 800 500 LSIG + ZSI 3N SPARE Future OVERHEAD
18 4D
5C
DF12A
LTA
800
4000
500
4000
LSIG + ZSI
LSG + ZSI
3
3N
UPS1-INPUT-DF12A
TIE CB "LTA"
(2) sets (3)#250MCM +(1)#2G
4000A Busway
2 2" UNDERGROUND
OVERHEAD

Note 1: Looking at the front of the Unit Substation; Right of the Main Breaker is BUS 1. The TIE Breaker is on the far Right of the Lineup and connects to
Switchgear "SUS-F1B" Through 4000A Busway
19
Figure 1.2-19. Unit Substation Cable Entry Position

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-17
August 2017 Designing a Distribution System
Sheet 01 023

In order to provide an effective ground On other occasions, the room does not There is an expectation that further
fault path as required by 250.4(A)(5) have enough height to accommodate advances will enable the potential to i
and 250.4(B)(4) of the 2014 NEC, standard equipment. In these cases, integrate maintenance, spare parts
upsizing of the equipment ground special reduced height switchboards and actual performance data into
conductors are required by Article or switchgear may be provided. these BIM models. Eaton offers a suite ii
250.122(B) “when the ungrounded of BIM component models ranging
conductors are increased in size from While this equipment may not be from automatic transfer switches to
the minimum size that has a sufficient documented as standard, Eaton can panelboards and switchboards that 1
ampacity for the intended installation”. provide assistance in developing are available from the Eaton website.
a reduced height alternative solution. Larger manufactured to order switch-
In these cases, “wire-type equipment
As design and drafting tools have gear BIM models are available from 2
grounding conductors, where installed, your local Eaton application engineer
shall be increased in size proportionally evolved, the push to include 3D
drawings has subsequently evolved or sales office.
according to the circular mil area of the
into an enhanced technology called 3
ungrounded conductors”.
Building Information Modeling (BIM).
When developing schedules, it is BIM drawings include the 3D aspect but
important to remember that conductor also include the capability to assign
4
sizing is also impacted by the derating equipment performance parameters
tables for ambient temperature and interdependencies. This permits
and conductor fill when installed architects and construction firms to
5
in raceways. be alerted to potential “collisions”
between incoming/outgoing conduits
There are a number of ways to create and other potential obstructions such
6
cable schedules, the most common of as existing conduits/busduct, HVAC
which is to name the conductor as is duct or plumbing in the space above
shown on the medium-voltage portion or below the equipment.
7
of the One-Line on Page 1.2-4.
Schedules are most often used to 8
define requirements for low-voltage TOP VIEW
switchboards and panelboards. They 36.00 30.00
may also be utilized to enumerate the 9
various automatic transfer switches AIRWAY

and the cables connecting them to the 30.00 OUTGOING


CONDUIT AREA
normal and emergency sources as
Figure 1.2-21. BIM 3D Model Top View
10
well as the end load.
Other drawings that are necessary FRONT VIEW

to produce the installation package


11
PANEL PA3
are floor plans that include room
dimensions, equipment locations PRIMARY MCB 12
allocated within the space, appropriate
clearances per code requirements and
means of egress from the area where 13
the equipment is located.
90.00
These drawings have been done
primarily in 2D CAD programs with 225 KVA
14
boxes showing equipment dimensions
on the floorplan. A front view of the
equipment is also used to detail the CONTACTOR
15
elevation requirements. Equipment & RELAY
COMPARTMENT
occasionally requires top-hats or
pullboxes that add height above the 16
switchboard or switchgear.
17
Figure 1.2-20. Equipment Floorplan
and Elevation
18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-18 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 024

i Power System Voltages The 2014 National Electrical Code has Excessively high megawatt loads such
ushered in a change to the definition as those required by large wastewater
The System One-Line on Page 1.2-4, of low voltage. The NEC elevated the treatment plants or complex process
shows an Incoming utility primary maximum voltage threshold for this facilities like petrochemical refining
ii service feeding different types of category from 600 V maximum to will typically exceed the utility’s infra-
distribution equipment at each of the 1000 V maximum. This was done to structure to serve the end customer
various utilization voltages necessary accommodate the growing solar at low-voltage. In these instances, a
1 to power the actual loads. market where voltages up to 1000 V medium voltage service at 34.5, 33 kV,
are becoming more commonplace. 26.4 kV, 13.8 kV, 13.2 kV, 12.47 kV or
The One-Line illustrates a number of 4.16 kV will be mandated. Extremely
2 voltage transformations and is a good In general, the voltage classes above large loads may even involve a utility
example of the types of choices and medium voltage are utilized for trans- interconnect at the 69 kV or high
challenges a power systems design mission of bulk power from generating voltage level.
3 engineer faces today. stations to the utilities substations that
transform it to the distribution voltage The System One-Line on Page 1.2-4 is
used on their system. an example of a power system for a
4 Voltage Classifications hypothetical college campus with a
A power system design engineer design load over 8 megawatts at a
ANSI and IEEE® standards define should attempt to familiarize them- 0.8 power factor. This would require a
various voltage classifications for selves with the application of all
5 single-phase and three-phase systems. equipment available in the various
Utility service of over 400 A at 13.8 kV.
The terminology used divides voltage voltage classes. This is particularly The most common service voltage
classes into: true if they are involved in designing arrangements are in the low-voltage
6 industrial facilities or campus arrange- range (<600 Vac). Normal residential
■ Low voltage
ments that may be served by a utility services are at 240/120 three-wire,
■ Medium voltage at medium or high voltage. (two phases each at 240 and a Neutral
7 ■ High voltage Conductor). Connection from each
■ Extra-high voltage 240 V phase to neutral provides 120 V
Incoming Service Voltage for the lighting and plug loads.
8 ■ Ultra-high voltage
When designing a new power A three-phase, four-wire low-voltage
Table 1.2-1 presents the nominal system distribution system, the engineer
voltages for these classifications. service is generally provided for
9 needs to be knowledgeable of the commercial customers. It includes
Table 1.2-1. Standard Nominal System local utility requirements including a neutral and may be provided at
Voltages and Voltage Ranges the service voltage that is available to 208/120 Vac wye, 240/120 Vac wye or
10 (From IEEE Standard 141-1993) be provided for their client. Meeting 480 /277 Vac wye.
Voltage Nominal System Voltage with the utility’s customer service
Class representative responsible for the Typical applications for the commercial
Three-Wire Four-Wire
11 installation site, early in the design category of three-phase low-voltage
Low 240/120 208Y/120 process, can help set expectations services are small commercial
voltage 240 240/120 for both parties and avoid subsequent buildings, department stores, office
12 480
600 —
480Y/277 delays. buildings, kindergarten through
12th grade schools and light
Medium 2400 4160Y/2400 Most utilities will require a load letter manufacturing facilities.
13 voltage 4160
4800
8320Y/4800
12000Y/6930
when requesting a new service or
There are a number of other older
upgrade to an existing utility service.
6900 12470Y/7200 The letter must include calculated service configurations utilized in rural
13,200 13200Y/7620
14 values for the types of continuous locations such as Delta Hi Leg. These
13,800 13800Y/7970
23,000 20780Y/12000 and non-continuous loads that will were used as an inexpensive way to
34,500 22860Y/13200 be served. supply 240 V three-phase and 240 V or
15 46,000 24940Y/14400 120 V single-phase from a single-pole
69,000 34500Y/19920 Article 220 of the NEC covers branch- mount transformer.
High 115,000 — circuit, feeder and service calculations.
voltage 138,000 — It also includes references to other As a general rule, the serving utility
16 161,000 — articles that pertain to specific types will offer a basic service option that is
230,000 — of installations requiring special outlined in the tariff documents that
Extra-high 345,000 — calculation considerations. have been approved by the governing
17 voltage 500,000 — authority or agency that regulates the
765,000 — The determination of the utility utility. This basic service option is one
Ultra-high 1,100,000 — service voltage is driven by a that minimizes the utility costs and
18 voltage combination of factors including best accommodates their system
the engineers initial load letter, requirements.
prevailing utility standards and the
19 type of facility being served.

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-19
August 2017 Designing a Distribution System
Sheet 01 025

The utility may alternately offer to


upcharge the client for extending or APPLICATION ZONES OF ARTICLE 230 - SERVICES PARTS I - VII & ASSOCIATED APPLICABLE NEC ARTICLES i
reinforcing cable connections to a UTILITY OWNED POLE MOUNT UTILITY OWNED PADMOUNT TRANSFORMER
location on their overhead or under- TRANSFORMER OR UNDERGROUND DISTRIBUTION

ground grid where they can supply the Part II - Overhead Service Conductors
230.24 - Clearances
Part III - Underground Service Conductors
230.32 - Depth of Burial & Protection
ii
service the user is requesting. In major
Service Head Terminal Box, Meter or Other Enclosure
cities where the serving utility utilizes
underground spot networks, the
Part IV - Service Entrance Conductors

Part V - Service Equipment General Utility


1
option to select a voltage other than Article 250 - Grounding & Bonding
Meter

that available is either limited or


extremely expensive.
Part VI - Service Equipment Disconnecting Means

Part VII - Service Equipment Overcurrent Protection


1000 A & Above Main CB at 2
480/277 Vac to be Provided with
230-95 - Ground Fault Protection of Equipment Equipment Ground Fault Protection
Utility metering requirements vary Article 408 - Switchboards, Switchgear & Panelboards
from one serving entity to another 3
and are more complex for medium- Article 240 - Overcurrent Protection

voltage switchgear used as service Articles 215 & 225 - Feeders

equipment. Articles 210 & 225 - Branch Circuits 75 kVa


480–208/120 V 4
HVAC
Commercial low-voltage utility Distribution Distribution Lighting
metering (<600 V) is more common Panel Panel Panelboard

and includes standardized designs


5
that can be provided in various low-
voltage switchboard and drawout Figure 1.2-22. Application Zones of 2014 NEC Articles Related to Incoming Utility Services
switchgear configurations. (Metering
6
These include application of the Space allocation should be considered
compartments for switchboards grounding electrode conductor in when laying out equipment in a service
that meet individual utility design
requirements are shown in Tab 21).
Section 250.50 to its sizing in accor- room. Both low- and medium-voltage 7
dance with Table 250.66. Requirements utility metering typically adds an
for bonding of service equipment additional equipment structure, or
Incoming Service begins in Section 250.90. Sizing of structures, to an incoming service 8
the main bonding jumper and system lineup. These are used to accommo-
Considerations bonding jumper are also covered in date the current transformers and
Article 230 of the National Electrical
Table 250.102(C)(1). potential taps or voltage transformers 9
necessary for the external utility
Code: “covers service conductors Note: A more in-depth discussion of
revenue meter to calculate usage.
and equipment for the protection grounding and equipment ground fault
of services and their installation protection can be found in Section 1.5 of Article 110 of the NEC covers a broad
10
requirements”. Figure 1.2-22 provides this Tab 1 document. range of requirements for electrical
the scope of pertinent references that installations. It includes provisions
apply to incoming service equipment. The NEC Article 230 does not specifi-
that govern the construction and
11
These range from conductor types cally require that electrical service
spatial requirements for egress,
from overhead service utility drops to rooms be fire rated rooms or that
clearances and working space in 12
underground utility feeds and their sprinklers be provided. However,
rooms containing electrical distribu-
proper installation. survivability requirements for fire
tion and service equipment.
pump disconnects in local building
Parts V, VI and VII of Article 230 spell code requirements, in addition to Table 1.2-2 includes combined tables 13
out the common requirements for NEC Article 450 or additional utility from NEC Article 110, showing the
low-voltage service equipment specifications may require fire rated minimum “depth of the working
<1000 Vac. These parts cover locations rooms, particularly if medium-voltage space in the direction of live parts” 14
permitted, various marking require- service is being supplied. required in front and behind medium-
ments including Section 230.66 that voltage equipment and low-voltage
requires service equipment be listed equipment. 15
and marked as Suitable for Use as
Service Equipment, (SUSE). Also Table 1.2-2. NEC Minimum Depth of Clear Working Space at Equipment
included is Section 230.71, which limits Minimum Depth of Clear Working Space at Electrical Equipment 16
the number of incoming main service Combined NEC Tables 110.26 (A) & 110.34 (A)
disconnects to a maximum of six. Nominal (Phase) Typical Condition 1 Condition 2 Condition 3
to Ground Voltage System Live Parts to Live Parts to Live Parts to 17
Section 230.95 of this Article requires Voltage Ungrounded Grounded Live Parts
equipment ground fault protection Surfaces Surfaces
for service disconnect(s) 1000 A Feet Feet Feet 18
and above when applied on solidly
grounded wye services, where the 0–150 V 208/120 V 3 ft 3 ft 3 ft
151–600 V 480/277 V 3 ft 3 ft 6 in 4 ft
phase to ground voltage exceeds 150 V. 601–2500 V 4160 V 3 ft 4 ft 5 ft 19
Article 250 of the NEC contains the 2501–9000 V 13,800 V 4 ft 5 ft 6 ft
requirements for grounding and 9001–25,000 V 34,500 V 5 ft 6 ft 9 ft
bonding of electrical systems. Specific NEC Definition of Live Parts: “Energized conductive Components.”
20
details pertaining to grounding for NEC Definition of Energized: “Electrically Connected to, or is a source of voltage.”
MV Transformers with Snubber Capacitors or MV EPR Cables holding a capacitive charge are
the incoming service equipment begin considered “Live” until the voltage is bled off by grounding procedures. 21
at Section 250.24.

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-20 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 026

i
Additional work space may need Utilization Voltage Selection In higher motor hp applications, a
to be allocated for OSHA required motor’s 4.16 kV utilization voltage
grounding practices, prior to servicing Very large inductive loads such as may be the same as the 4.16 kV service
deenergized medium-voltage equip- higher horsepower motors used on voltage. In these cases, the service
ii ment. As an example, 6-foot-long HVAC chillers, sewage treatment equipment would need to feed
insulated hot sticks are typically used pumps and in process or other power through cables or busway to
to keep personnel at a safe distance, Industries can draw tremendous a medium-voltage starter or variable
1 while applying portable ground cables. amounts of power. Motors also frequency drive. (See Tab 10 for
This procedure is utilized to discharge inherently have high inrush currents more information.)
any residual capacitive voltage present during full voltage starting, which can
2 on cables terminating in a medium- cause a significant voltage dip on the
However, in installations where there
voltage transformer primary cable are many long cable runs that are
power system feeding it. As a result,
compartment or in the rear cable feeding other large loads, the medium-
many utilities have limitations on the
3 compartment of medium-voltage maximum horsepower motor that
voltage distribution may have a higher
switchgear. service voltage such as 13.8 kV. In this
can be line started directly from
case, the service voltage would need
their system.
4 to be stepped-down to the 4.16 kV
To limit the impact of this phenomena, utilization voltage through a primary
a variety of techniques can be used unit substation transformer as
5 to reduce the motor's starting inrush illustrated by the System One-Line
current. These generally involve the on Page 1.2-4. See Tab 13 for
use of electromechanical or solid- further details.
6 state reduced voltage starters. Variable
Conversely, small end loads, short
frequency drives in both low and
runs and a high percentage of lighting
medium voltage are also available
and/or receptacle loads would favor
7 as shown on the System One-Line
lower utilization voltages such as
on Page 1.2-4. See Components
208 Y/120 V. If the incoming service
of a Power System section for
8 was at 13.8 kV, as noted in the previous
further details.
example, secondary unit substations,
As renewable energy or cogeneration pad-mounted transformers or unitized
are added, power systems are
Voltage Recommendations power centers could be used to step-
9 becoming more complex and so too is by Motor Horsepower down to the 208 Y/120 V utilization
their service interface for utility power. Some factors affecting the selection voltage required. See Tabs 14 and 15
10 Many Public Service Commissions of motor operating voltage include: for details.
have adopted Standard Interface
Requirements (SIR) for Distributed ■ Motor, motor starter and cable This approach is often used to reduce
first cost or offset voltage drop issues on multi
11 Energy Resources (DER) based on
IEEE 1547. These are intended to building sites such as college or
■ Motor, motor starter and cable
protect the utility system from user- hospital campuses. It is also used
installation cost
in large single building sites like
12 owned generation back-feeding into ■ Motor and cable losses distribution warehouses and high
a fault or dead cable on the utility grid.
■ Motor availability rise “skyscraper” buildings.
Utilities may have their own specifica- ■ Voltage drop
13 tions and tariffs for the interconnection ■ Qualifications of the building
Note: Section 1.3 of this document
illustrates a number of power system
of this Dispersed or Distributed operating staff; and many more designs that improve reliability and
Generation (DG). These include uptime during maintenance or service
14 capacity limitations and/or the addition The following table is based in part outages. Among these schemes are a
of charges for the “spinning reserves” on the above factors and experience. variety of configurations showing medium-
they must keep on hand, should the Because all the factors affecting the voltage sources feeding substation or
15 user’s DG assets fail or load increase. selection are rarely known, it is only pad-mounted transformers that step it
an approximate guideline. down to the appropriate low voltage for
Consequently, the design engineer end load utilization.
16 must be aware that special relaying Table 1.2-3. Selection of Motor Horsepower
protection may need to be included Ratings as a Function of System Voltage A problem can arise, however, when a
in the design. Also, additional analysis Motor Voltage Motor System low-voltage service is the only utility
17 of the utility tariffs and rate structures (Volts) hp Range Voltage service option and cable distances
may be necessary to validate the between the incoming service and the
460 up to 500 480 utilization loads are great. In these
projected payback of participation in 2300 250 to 2000 2400
18 peak demand reduction programs 4000 250 to 3000 4160
instances, a practical way to offset for
using owner-supplied generation. the voltage drop to the end utilization
4600 250 to 3000 4800
13,200 above 2000 13,800 loads is the use of low-voltage
19 busway in lieu of cable. See Tab 24
for details.

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.2-21
August 2017 Designing a Distribution System
Sheet 01 027

Another technique to address voltage Low-Voltage Utilization The National Electrical Code permits
drop concerns for long cable runs is
With most low-voltage services, the
voltage up to 300 V to ground on i
to use a step-up and step-down circuits supplying permanently installed
transformer arrangement. service voltage is the same as the electric discharge lamp fixtures, provided
utilization voltage. However, when the luminaires do not have an integral ii
To accomplish this, a step-up trans- the engineer is faced with a decision manual switch and are mounted at
former is added after the low-voltage between 208Y/120 V and 480Y/277 V least 8 ft (2.4 m) above the floor.
service. The transformer primary is secondary distribution for commercial This permits a three-phase, four-wire, 1
configured in a delta and is fed by the and institutional buildings, the choice solidly grounded 480Y/277 V system
grounded and bonded low-voltage depends on several factors. The most to supply directly all of the fluorescent
incoming utility service. The step-up important of these are the size and and high-intensity discharge (HID) 2
transformer wye secondary is often at types of loads (motors, fluorescent lighting in a building at 277 V, as well
medium voltage, typically at 4.16 kV, lighting, incandescent lighting, as motors at 480 V.
with the transformers wye secondary receptacles) and length of feeders. 3
grounded. In general, power system designs with Technical Factors
HVAC equipment with a significant The principal advantage of the use of
A 4.16 kV delta primary step-down
transformer is then located near the
quantity of motors, predominantly higher secondary voltages in buildings 4
fluorescent lighting loads, and long is that for a given load, less current
served load and has its wye secondary feeders, will tend to make 480Y/277 V
grounded in accordance with NEC means smaller conductors and lower
Article 250.30 to create a separately
more economical. voltage drop. Also, a given conductor 5
derived system. This step-down Industrial installations with large size can supply a large load at the
transformer’s secondary voltage may motor loads are almost always 480 V same voltage drop in volts, but a lower
be the same as the incoming service, or resistance grounded, wye systems percentage voltage drop because of 6
it may be at higher utilization voltage. (see further discussion on grounding the higher supply voltage. Fewer or
in Section 1.6). smaller circuits can be used to transmit
Caution must be taken when selecting the power from the service entrance 7
the step-up transformers to be used Practical Factors point to the final distribution points.
in this type of application. Step-up Because most low-voltage distribution Smaller conductors can be used in
transformers, particularly designs equipment available is rated for up to many branch circuits supplying 8
that are not optimized for step-up 600 V, and conductors are insulated for power loads, and a reduction in the
purposes, such as a reverse-fed 600 V, the installation of 480 V systems number of lighting branch circuits is
standard transformer, exhibit extremely uses the same techniques and is usually possible. 9
high inrush during energization. essentially no more difficult, costly It is easier to keep voltage drops within
or hazardous than for 208 V systems.
Unless the step-up transformers are
The major difference is that an arc
acceptable limits on 480 V circuits than 10
specifically wound for low inrush, the on 208 V circuits. When 120 V loads are
magnetizing current during initial of 120 V to ground tends to be self- supplied from a 480 V system through
extinguishing, while an arc of 277 V
energization, may exceed the 6X make
to ground tends to be self-sustaining
step-down transformers, voltage drop 11
capabilities of a low-voltage fused in the 480 V supply conductors can
bolted pressure switch. This can result and likely to cause severe damage. be compensated for by the tap adjust-
in a condition where a portion of the For this reason, Article 230.95 of the ments on the transformer, resulting 12
switch contact surface can weld before National Electrical Code requires in full 120 V output. Because these
full engagement. The current passing ground fault protection of equipment transformers are usually located close
through the smaller contact area will on grounded wye services of more to the 120 V loads, secondary voltage 13
then eventually cause the switch to than 150 V to ground, but not exceeding drop should not be a problem. If it is,
overheat and fail. 600 V phase-to-phase (for practical taps may be used to compensate by
Many step-up transformer applications purpose, 480Y/277 V services), for any raising the voltage at the transformer. 14
involve a 208 Vac incoming service service disconnecting means rated The interrupting ratings of circuit
stepping this voltage up to the 1000 A or more. breakers and fuses at 480 V have
utilization voltage of 480 Vac for HVAC increased considerably in recent
15
Article 215.10 of the NEC extends this
motor loads in a building. The design equipment ground fault requirement years, and protective devices are now
engineer must be aware of some to feeder conductors and clarifies available for any required fault duty 16
potential pitfalls and plan ahead when the need for equipment ground fault at 480 V. In addition, many of these
involved in this type of application. protection for 1000 A and above, protective devices are current limiting,
Larger step-up transformers offer feeder circuit protective devices on and can be used to protect down-
stream equipment against these
17
fewer transformer voltage taps, if the 480/277 Vac secondary of trans-
formers. Article 210.13 has been high fault currents.
any at all. They also exhibit poor
voltage regulation when experiencing added to the 2014 NEC, essentially 18
transient shock loads, such as motors recognizing the same need for
starting. When designing power equipment ground fault protection
systems utilizing step-up transformers on 1000 A branch circuits being fed 19
to feed motor loads, a Motor Starting from the 480/277 Vac secondary
Analysis should be performed to of transformers.
ensure that the motors will start and 20
operate as intended.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.2-22 Power Distribution Systems
Designing a Distribution System August 2017
Sheet 01 028

Economic Factors
i Utilization equipment suitable for
principal loads in most buildings
is available for either 480 V or 208 V
ii systems. Three-phase motors and
Elevator
Panel
their controls can be obtained for
Typical
either voltage, and for a given
1 horsepower are less costly at 480 V.
LED lighting as well as earlier Typical Emergency
HVAC Lighting Panel
technologies including fluorescent,
2 HID and high pressure sodium can
Panel (Typical Every
Third Floor)
all be applied in either 480 V or 208 V
systems. However, in almost all cases,
3 the installed equipment will have a
480Y/277 V
Panel
208Y/120 V
Panel
Typical

lower total cost at the higher voltage. Dry Type Transformer


480Δ-208Y/120 V
4 (Typical Every Floor)
HVAC Busway Emergency Elevator
Feeder Riser Lighting Riser
Riser
5
Building and Typical Typical

6 Miscellaneous
Loads
Typical

7 Typical Typical
Spare

1 1 1 1 1 1 1
8
Automatic
9 1 4000 A
Main CB
Transfer Switch
Gen. CB
Utility Emergency
CTs Metering or Standby
10 PTs Generator
Utility 4000A at 480Y/277V
Service 100,000A Available Fault Current

11
Figure 1.2-23. Typical Power Distribution and Riser Diagram for a Commercial Office Building
1 Include ground fault trip.
12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-1
August 2017 Types of Systems
Sheet 01 029

Types of Systems This makes it possible for the utility Additionally, a fault on the Service
i
to minimize the installed transformer Switchgear or Switchboards low-
In many cases, power is supplied by capacity. However, if capacity require- voltage bus will cause the main
the utility to a building at the utilization ments grow, the voltage regulation overcurrent protective device to
voltage. In these cases, the distribution and efficiency of this system may be operate, interrupting service to all ii
of power within the building is achieved poor because of the low-voltage loads. Service cannot be restored
through the use of a simple radial feeders and single source. Typically, until the necessary repairs have been
distribution system. the cost of the low-voltage feeder made. A fault on a low-voltage feeder 1
circuits and their associated circuit circuit will interrupt service to all the
Simple Radial System breakers are high when the feeders loads supplied by that feeder.
In a conventional low-voltage radial
are long and the peak demand is 2
above 1000 kVA. An engineer needs to plan ahead for
system, the utility owns the pole- these contingencies by incorporating
mounted or pad-mounted transformers
that step their distribution voltage down
Where a utility’s distribution system is backup power plans during the initial 3
fed by overhead cables, the likelihood design of the power system. Resiliency
from medium voltage to the utilization of an outage due to a storm, such as from storms, floods and other natural
voltage, typically 480/277 Vac or 208/ a hurricane or blizzard, increases disasters can be accomplished with 4
120 Vac. In these cases, the service dramatically. Wind or ice formation the addition of permanently installed
equipment is generally a low-voltage can cause tree branches to fall on standby generation, or by including
main distribution switchgear or switch- these suspended cables, causing an a provision in the incoming Service 5
board. Specific requirements for service unplanned power outage. The failure equipment for the connection of a
entrance equipment may be found in of pole-mounted utility transformers portable roll-up temporary generator.
NEC Article 230, Services. can result in an outage lasting a day Note: See Generator and Generator 6
or more. Systems in Section 1.7 for further
Low-voltage feeder circuits are run
details.
from the switchboard or switchgear
assemblies to panelboards that are 7
located closer to their respective loads
as shown in Figure 1.3-1. Each feeder is Utility
connected to the switchgear or switch-
Medium-Voltage 8
Distribution
board bus through a circuit breaker or
other overcurrent protective device. A
relatively small number of circuits are
Utility Owned 9
Utility Pole or Padmount
used to distribute power to the loads. Meter Transformer
Because the entire load is served from
a single source, full advantage can be 480/277 Vac
10
(VT’s or Tap by Utility)
taken of the diversity among the loads. Service Entrance
Equipment (CT’s by Utility)
11

12

13
75 kVA
480–208/120 V
HVAC 14
Distribution Distribution Lighting
Panel Panel Panelboard
15
Figure 1.3-1. Low-Voltage Radial System
16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-2 Power Distribution Systems
Types of Systems August 2017
Sheet 01 030

Figure 1.3-2 shows a typical incoming It is important to consider the ground- If the three-phase generator neutral
i service switchboard with the addition ing of the generator neutral when using is brought back through the transfer
of a key interlocked generator breaker. automatic transfer switches in power switches and grounded at the service
In this design, the breaker pair shares system design. If the generator neutral entrance, a three-pole transfer switch
ii a single key that can only be used to is grounded at the generator, a sepa- with solid neutral should be provided.
close one breaker at a time. This rately derived system is created. This
Note: See Automatic Transfer Switches in
arrangement ensures against parallel- requires the use of four-pole transfer Tab 25 for details.
1 ing with the utility but requires manual switches for a three-phase system.
intervention in the event of an outage.

2 In a typical standby generation


Utility
arrangement, automatic transfer
Medium-Voltage
switches are used to feed either Nor-
Distribution
3 mal utility power or an alternate gener-
ator source of backup power to the
critical loads. The transfer switches Utility Owned
Utility Pole or Padmount G
4 sense the loss of power from the Nor- Meter Transformer
mal source and send a run command
to the generator to start. 480/277 Vac (VT’s or Tap by Utility)
5 Once the generator is running, the
Service Entrance
Equipment (CT’s by Utility)
transfer switches sense that voltage
K1 K1
is available and automatically open
6 the Normal contactor and close the
Generator contactor. When the Normal
source returns, the transfer switch
7 opens the Generator contactor and
closes the Normal source contactor.
8 The location and type of the transfer 75 kVA
switches depends on the Utility and 480–208/120 V
HVAC
the overall design intent. Transfer
9 switches can be Service Entrance Distribution
Panel
Distribution
Panel
Lighting
Panelboard
Rated and used as the main Service
Disconnect feeding all the loads
10 downstream. See Figure 1.3-3. Figure 1.3-2. Typical Incoming Service Switchboard
Transfer switches can be also be incor- Note: See Roll-Up Generator Switchboard Connections in Tab 21.
11 porated into the service switchboard
as an integral part of the assembly.

12 Alternately, they can be located down- Typical Transfer Switch Installation


stream of the incoming service and Typical Transfer Switch Installation Rated for Service Entrance
applied only to the individual loads Utility Service Utility Service
13 they are feeding. This approach of
isolating only those critical loads
that must function during a power
outage can reduce the generator kVA Service Service
14 necessary. This can reduce space and Disconnect Disconnect
cost requirements. G
G Generator
15 Generator ATS Breaker
ATS
Breaker

16 Load Load

17 Figure 1.3-3. Main Service Disconnect Feeding Downstream

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-3
August 2017 Types of Systems
Sheet 01 031

In cases where the utility service Each secondary unit substation is an are reduced, voltage regulation is
voltage is at some voltage higher assembled unit consisting of a three- improved, feeder circuit costs are i
than the utilization voltage within the phase, liquid-filled or air-cooled reduced substantially, and large low-
building, the system design engineer transformer, an integrally connected voltage feeder circuit breakers are
has a choice of a number of types primary fused switch, and low-voltage eliminated. In many cases the inter- ii
of systems that may be used. This switchgear or switchboard with circuit rupting duty imposed on the load
discussion covers several major types breakers or fused switches. Circuits circuit breakers is reduced.
of distribution systems and practical are run to the loads from these low- 1
modifications of them. voltage protective devices. This modern form of the simple radial
system will usually be lower in initial
1. Simple medium-voltage radial Because each transformer is located investment than most other types of 2
within a specific load area, it must primary distribution systems for build-
2. Loop-primary system— have sufficient capacity to carry the ings in which the peak load is above
radial secondary system peak load of that area. Consequently, 1000 kVA. A fault on a primary feeder 3
3. Primary selective system— if any diversity exists among the load circuit or in one transformer will cause
secondary radial system area, this modified primary radial an outage to only those secondary
system requires more transformer loads served by that feeder or trans- 4
4. Two-source primary— capacity than the basic form of the former. In the case of a primary main
secondary selective system simple radial system. However, bus fault or a utility service outage,
5. Sparing transformer system
because power is distributed to the service is interrupted to all loads until 5
load areas at a primary voltage, losses the trouble is eliminated.
6. Simple spot network
7. Medium-voltage distribution
6
system design Primary Fused Switch
In those cases where the customer 7
Transformer
receives his supply from the primary
system and owns the primary switch
and transformer along with the 600V Class 8
Switchboard
secondary low-voltage switchboard
or switchgear, the equipment may take
the form of a separate primary switch, 9
separate transformer, and separate Distribution
Dry-Type
low-voltage switchgear or switch-
board. This equipment may be
Transformer 10
combined in the form of an outdoor Distribution MCC Distribution Lighting
pad-mounted transformer with Panel Panel Panelboard
internal primary fused switch and 11
secondary main breaker feeding an
indoor switchboard.
Figure 1.3-4. Simple Radial System 12
Another alternative would be a
secondary unit substation where the
primary fused switch, transformer and 13
secondary switchgear or switchboard 52 Primary Main Breaker
are designed and installed as a close-
coupled single assembly. 14
A modern and improved form of the 52 52 52 52 52 52 Primary Feeder Breakers
conventional simple medium-voltage 15
radial system distributes power at a
primary voltage. The voltage is stepped
down to utilization level in the several 16
load areas within the building typically
through secondary unit substation
transformers. The transformers are 17
usually connected to their associated
load bus through a circuit breaker, as Secondary Unit
shown in Figure 1.3-5. Primary Substation 18
Cables

19
Figure 1.3-5. Primary and Secondary Simple Radial System
20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-4 Power Distribution Systems
Types of Systems August 2017
Sheet 01 032

Reducing the number of transformers 2. Loop Primary System— utilizing three on-off switches or a
i per primary feeder by adding more
Radial Secondary System four-position sectionalizing switch and
primary feeder circuits will improve vacuum fault interrupter (VFI) internal
the flexibility and service continuity This system consists of one or more to the transformer saving cost and
ii of this system; the ultimate being one “PRIMARY LOOPS” with two or more reducing footprint.
secondary unit substation per primary transformers connected on the loop.
feeder circuit. This of course increases This system is typically most effective When pad-mounted compartmental-
1 the investment in the system but when two services are available from ized transformers are used, they are
minimizes the extent of an outage the utility as shown in Figure 1.3-6. Each furnished with loop-feed oil-immersed
resulting from a transformer or primary loop is operated such that one gang-operated load break sectionalizing
2 primary feeder fault. of the loop sectionalizing switches is switches and Bay-O-Net expulsion fuses
kept open to prevent parallel operation in series with partial range back-up
Primary connections from one secondary of the sources. current-limiting fuses. By operating the
3 unit substation to the next secondary appropriate sectionalizing switches, it is
unit substation can be made with When secondary unit substations are possible to disconnect any section of
“double” lugs on the unit substation used, each transformer may have its the loop conductors from the rest of
4 primary switch as shown, or with load own duplex (2-load break switches with the system. In addition, it is possible
break or non-load break separable load side bus connection) sectionalizing to disconnect any transformer from
connectors made in manholes or other switches and primary load break fused the loop.
5 locations. See Eaton’s Cooper Power™ switch as shown in Figure 1.3-7 or
series Molded Rubber Medium
Voltage Connectors on Eaton's website
6 for more details.
Depending on the load kVA connected
to each primary circuit and if no ground Primary Main Breaker 1 52 52 Primary Main Breaker 2
7 fault protection is desired for either the
primary feeder conductors and trans- 52
formers connected to that feeder or Tie
8 the main bus, the primary main and/or 52 52 Breaker 52 52 Loop Feeder Breaker
feeder breakers may be changed to
9 primary fused switches. This will sig- Loop A
nificantly reduce the first cost, but also Loop B
decrease the level of conductor and
10 equipment protection. Thus, should NC NO NC NC
a fault or overload condition occur, Fault Sensors
downtime increases significantly and
11 higher costs associated with increased
damage levels and the need for fuse
replacement is typically encountered.
12 In addition, if only one primary fuse on
a circuit opens, the secondary loads are
then single phased, causing damage to
13 low-voltage motors.
Another approach to reducing costs
is to eliminate the primary feeder NC NC NO NC NC NC
14 breakers completely, and use a single
primary main breaker or fused switch
for protection of a single primary
15 feeder circuit with all secondary unit
substations supplied from this circuit.
Although this system results in less ini-
16 tial equipment cost, system reliability is
reduced drastically because a single
fault in any part of the primary conductor
17 would cause an outage to all loads
Secondary Unit Substations Consisting of:
within the facility. Duplex Primary Switches/Fused Primary Switches/
Transformer and Secondary Main Feeder Breakers
18
Figure 1.3-6. Loop Primary—Radial Secondary System
19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-5
August 2017 Types of Systems
Sheet 01 033

Loop Loop Primary Metal-Clad i


Feeder Feeder
Switchgear Lineup
Load Break 52 52 Primary Main Breaker
Loop Switches ii
Bus A 52 Bus B

52 52 52 52 Primary Feeder Breaker 1


Fused Feeder A1 Feeder B1 Feeder B2
Disconnect
Feeder A2
To Other
Substations
2
Switch
NO
3
NC

4
NO Typical Secondary Unit
Substation Duplex Primary
Switch/Fuses
NC Transformer/600V Class 5
Figure 1.3-7. Secondary Unit Substation Secondary Switchgear
Loop Switching
NO
6
Main Source Alternate Source NC

3-Position 7
Selector Switch
Figure 1.3-10. Basic Primary Selective—Radial Secondary System
Vacuum Fault
Interrupter (VFI) A key interlocking scheme is normally When a primary feeder conductor fault 8
recommended to prevent closing all occurs, the associated loop feeder
sectionalizing devices in the loop. Each breaker opens and interrupts service
primary loop sectionalizing switch and to all loads up to the normally open 9
the feeder breakers to the loop are primary loop load break switch
interlocked such that to be closed they (typically half of the loads). Once it is
require a key (which is held captive determined which section of primary 10
until the switch or breaker is opened) cable has been faulted, the loop
and one less key than the number of sectionalizing switches on each
key interlock cylinders is furnished. side of the faulted conductor can be
11
Figure 1.3-8. VFI / Selector Switch An extra key is provided to defeat the opened, the loop sectionalizing switch
interlock under qualified supervision. that had been previously left open can
Combination
In addition, the two primary main then be closed to all secondary unit
12
breakers, which are normally closed, substations while the faulted conduc-
and primary tie breaker, which is tor is replaced. If the fault should occur
Loop Feeder Loop Feeder
normally open, are either mechanically in a conductor directly on the load side
13
or electrically interlocked to prevent of one of the loop feeder breakers, the
paralleling the incoming source lines. loop feeder breaker is kept open after
4-Position For slightly added cost, an automatic tripping and the next load side loop
14
T-Blade
Partial Range throw-over scheme can be added sectionalizing switch manually opened
Current-Limiting Fuse Sectionalizing
Load-Break between the two main breakers and so that the faulted conductor can be 15
Bay-O-Net Switch tie breaker. During the more common sectionalized and replaced.
Expulsion Fuse event of a utility outage, the automatic
Note: Under this condition, all secondary
transfer scheme provides significantly unit substations are supplied through the 16
reduced power outage time. other loop feeder circuit breaker, and thus
all conductors around the loop must be
The system in Figure 1.3-6 has higher
costs than in Figure 1.3-5, but offers
sized to carry the entire load connected to
the loop. Where separable load break or
17
increased reliability and quick restora- non-load break connectors are used, they
tion of service when 1) a utility outage too must be sized to handle the entire
occurs, 2) a primary feeder conductor load of the loop. Increasing the number 18
Figure 1.3-9. Pad-Mounted Transformer fault occurs, or 3) a transformer fault of primary loops (two loops shown in
Loop Switching or overload occurs. Figure 1.3-10) will reduce the extent of the
outage from a conductor fault, but will also 19
Should a utility outage occur on one of increase the system investment.
the incoming lines, the associated pri-
mary main breaker is opened and the 20
tie breaker closed either manually or
through an automatic transfer scheme.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-6 Power Distribution Systems
Types of Systems August 2017
Sheet 01 034

When a transformer fault or overload transformer includes a fuse assembly This means limited cable space
i occurs, the transformer primary fuses with fuses. Mechanical and/or key especially if double lugs are
open, and the transformer primary interlocking is furnished such that furnished for each line as shown
switch manually opened, disconnecting both switches cannot be closed at in Figure 1.3-10. The downside is that
ii the transformer from the loop, and the same time (to prevent parallel should a faulted primary conductor
leaving all other secondary unit operation) and interlocking such have to be changed, both lines would
substation loads unaffected. that access to either switch or fuse have to be de-energized for safe
1 assembly cannot be obtained unless changing of the faulted conductors.
A basic primary loop system that both switches are opened.
uses a single primary feeder breaker A second alternative is utilizing a
2 connected directly to two loop feeder three-position selector switch internal
switches which in turn then feed the to the transformer, allowing only
Primary
loop is shown in Figure 1.3-11. In this Feeders one primary feeder to be connected to
3 basic system, the loop may be normally the transformer at a time without the
operated with one of the loop section- need for any interlocking. The selector
Load Break
alizing switches open as described Switches switch is rated for load-breaking. If
4 above or with all loop sectionalizing overcurrent protection is also required,
switches closed. If a fault occurs in the a vacuum fault interrupter (VFI), also
basic primary loop system, the single internal to the transformer, may be
5 loop feeder breaker trips, and secondary
Fuses
utilized, reducing floor space.
loads are lost until the faulted conductor
is found and eliminated from the loop In Figure 1.3-10 when a primary
feeder fault occurs, the associated
6 by opening the appropriate loop
feeder breaker opens and the
sectionalizing switches and then
reclosing the breaker. transformers normally supplied from
the faulted feeder are out of service.
7 Then manually, each primary switch
connected to the faulted line must be
8 opened and then the alternate line
Figure 1.3-12. Duplex Fused Switch in primary switch can be closed connect-
52 Two Structures ing the transformer to the live feeder,
9 One alternate to the duplex switch thus restoring service to all loads.
Loop A Loop A Note that each of the primary circuit
arrangement, a non-load break selector
switch mechanically interlocked with conductors for Feeder A1 and B1 must
10 a load break fused switch can be used be sized to handle the sum of the loads
In cases where only one primary line
is available, the use of a single primary as shown in Figure 1.3-13. The non- normally connected to both A1 and B1.
breaker provides the loop connections load break selector switch is physically Similar sizing of Feeders A2 and B2,
to the loads as shown here. etc., is required.
11 located in the rear of the load break
Figure 1.3-11. Single Primary Feeder— fused switch, thus only requiring one If a fault occurs in one transformer,
Loop System structure and a lower cost and floor the associated primary fuses blow
12 space savings over the duplex and interrupt the service to just
3. Primary Selective System— arrangement. The non-load break the load served by that transformer.
switch is mechanically interlocked to Service cannot be restored to the loads
13 Secondary Radial System prevent its operation unless the load normally served by the faulted
The primary selective—secondary break switch is opened. The main transformer until the transformer
radial system, as shown in disadvantage of the selector switch is is repaired or replaced.
14 Figure 1.3-10, differs from those that conductors from both circuits are
previously described in that it employs terminated in the same structure. Cost of the primary selective—
at least two primary feeder circuits in secondary radial system is greater
15 each load area. It is designed so that than that of the simple primary radial
when one primary circuit is out of ser- Primary system of Figure 1.3-4 because of the
Feeders additional primary main breakers, tie
vice, the remaining feeder or feeders
16 have sufficient capacity to carry the breaker, two-sources, increased number
total load. Half of the transformers are Non-Load Break of feeder breakers, the use of primary-
Selector Switches duplex or selector switches, and the
normally connected to each of the two
17 feeders. When a fault occurs on one of
Inter-
lock
greater amount of primary feeder
Load Break cable required.
the primary feeders, only half of the Disconnect
load in the building is dropped.
18 Fuses The benefits from the reduction in
Duplex fused switches as shown the amount of load lost when a
in Figure 1.3-10 and detailed in primary feeder is faulted, plus the
19 Figure 1.3-12 may be utilized for this quick restoration of service to all or
type of system. Each duplex fused most of the loads, may more than
switch consists of two load break offset the greater cost.
20 three-pole switches each in their own
separate structure, connected together
by bus bars on the load side. Typically,
21 the load break switch closest to the Figure 1.3-13. Fused Selector Switch in
One Structure

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-7
August 2017 Types of Systems
Sheet 01 035

Having two sources allows for either This means each primary feeder The double-ended unit substation
manual or automatic transfer of the conductor must be sized to carry the arrangement can be used in conjunction i
two primary main breakers and tie load on both sides of all the secondary with any of the previous systems
breaker should one of the sources buses it is serving under secondary discussed, which involve two primary
become unavailable. emergency transfer If the loss of sources. Although not recommended, ii
voltage was due to a failure of one of if allowed by the utility, momentary
The primary selective-secondary radial the transformers in the double-ended re-transfer of loads to the restored
system, however, may be less costly unit substation, then the associated source may be made closed transition 1
or more costly than a primary loop— primary fuses would open taking only (anti-parallel interlock schemes would
secondary radial system of Figure 1.3-6 the failed transformer out of service, have to be defeated) for either the
depending on the physical location and then only the secondary loads primary or secondary systems. Under 2
of the transformers. It also offers normally served by the faulted this condition, all equipment interrupt-
comparable downtime and reliability. transformer would have to be ing and momentary ratings should be
The cost of conductors for the types of transferred to the opposite transformer. suitable for the fault current available 3
systems may vary depending on the from both sources.
location of the transformers and loads In either of the above emergency
within the facility. The cost differences conditions, the in-service transformer For double-ended unit substations 4
of the conductors may offset cost of of a double-ended unit substation equipped with ground fault systems
the primary switching equipment. would have to have the capability of special consideration to transformer
serving the loads on both sides of the neutral grounding and equipment 5
4. Two-Source Primary— tie breaker. For this reason, transform- operation should be made—see
Secondary Selective System ers used in this application must have “Grounding” and “Ground Fault
This system uses the same principle
equal kVA ratings on each side of the Protection” in Section 1.6. Where 6
double-ended unit substation. The two single-ended unit substations
of duplicate sources from the power transformers are sized so the normal are connected together by busway
supply point using two primary main
breakers and a primary tie breaker.
operating maximum load on each or external tie conductors, it is 7
transformer is typically about 2/3 base recommended that a tie breaker
The two primary main breakers and nameplate kVA rating. be furnished at each end of the tie
primary tie breaker being either
Typically these transformers are
conductors. The second tie breaker 8
manually or electrically interlocked provides a means to isolate the
to prevent closing all three at the same furnished with fan-cooling and/or interconnection between the two
time and paralleling the sources. Upon lower than normal temperature rise single-ended substations for 9
loss of voltage on one source, a manual such that under emergency conditions maintenance or servicing purposes.
or automatic transfer to the alternate they can continuously carry the
source line may be used to restore maximum load on both sides of the 10
power to all primary loads. secondary tie breaker. Because of this
spare transformer capacity, the voltage
Each transformer secondary is regulation provided by the double-
arranged in a typical double-ended ended unit substation system under
11
unit substation arrangement as shown normal conditions is better than that
in Figure 1.3-14. The two secondary
main breakers and secondary tie
of the systems previously discussed.
.
12
breaker of each unit substation are
again either mechanically or electrically
interlocked to prevent parallel operation.
13
Upon loss of secondary source voltage 52 52 Primary Main Breakers
on one side, manual or automatic
transfer may be used to transfer the
52 14
loads to the other side, thus restoring 52 52 52 52 Primary Feeder Breakers
power to all secondary loads.
15
This arrangement permits quick To Other Substations To Other Substations
restoration of service to all loads when
a primary feeder or transformer fault Typical 16
Double-Ended
occurs by opening the associated Unit
secondary main and closing the Substation
secondary tie breaker. If the loss 17
of secondary voltage has occurred
because of a primary feeder fault with
the associated primary feeder breaker 18
opening, then all secondary loads
normally served by the faulted feeder
would have to be transferred to the 19
opposite primary feeder.
Primary Fused Switch Transformer Tie Breaker Secondary Main Breaker
20
Figure 1.3-14. Two-Source Primary—Secondary Selective System
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-8 Power Distribution Systems
Types of Systems August 2017
Sheet 01 036

5. Sparing Transformer System The sparing transformer system In facilities without qualified electrical
i The sparing transformer system concept
operates as follows: power operators, an open transition
with key interlocking is often a
came into use as an alternative to the ■ All main breakers, including prudent design.
ii capital cost intensive double-ended
secondary unit substation distribution
the sparing main breaker, are
normally closed; the tie breakers Note: Each pair of “main breaker/tie breaker”
system (see Two-Source Primary— are normally open key cylinders should be uniquely keyed to
prevent any paralleled source operations.
1 Secondary Selective System). It essen- ■ Once a transformer (or primary
tially replaces double-ended substations cable or primary switch/fuse) fails,
with single-ended substations and one Careful sizing of these transformers
the associated secondary main
as well as careful specification of the
2 or more “sparing” transformer substa- breaker is opened. The associated
transformers is required for reliability.
tions all interconnected on a common tie breaker is then closed, which
secondary bus—see Figure 1.3-15. Low temperature rise specified with
restores power to the single-ended
continuous overload capacity or
3 Generally no more than three to five
substation bus
upgraded types of transformers
single-ended substations are on a ■ Schemes that require the main to should be considered.
sparing loop. be opened before the tie is closed
4 (“open transition”), and that allow One disadvantage to this system is
The essence of this design philosophy any tie to be closed before the the external secondary tie system,
is that conservatively designed and substation main is opened, see Figure 1.3-15. As shown, all single-
5 loaded transformers are highly reliable (“closed transition”) are possible ended substations are tied together
electrical devices and rarely fail. There- on the secondary with a tie busway or
fore, this design provides a single com- With a closed transition scheme, it is cable system. Location of substations
6 mon backup transformer for a group of common to add a timer function that is therefore limited because of voltage
transformers in lieu of a backup trans- opens the tie breaker unless either drop and cost considerations.
former for each and every transformer. main breaker is opened within a
7 This system design still maintains a time interval. Routing of busway, if used, must be
carefully layed out. It should also be
high degree of continuity of service. This closed transition allows power noted, that a tie busway or cable fault
to be transferred to the sparing
8 Referring to Figure 1.3-15, it is apparent
transformer without interruption, such
will essentially prevent the use of the
that the sparing concept backs up sparing transformer until it is repaired.
primary switch and primary cable as for routine maintenance, and then Commonly, the single-ended substa-
back to the substation. This closed
9 failure as well. Restoration of lost or
transition transfer has an advantage in
tions and the sparing transformer
failed utility power is accomplished must be clustered. This can also be
similarly to primary selective scheme some facilities; however, appropriate an advantage, as more kVA can be
interrupting capacities and bus bracing
10 previously discussed. It is therefore
must be specified suitable for the
supported from a more compact
important to use an automatic throw- space layout.
over system in a two source lineup momentary parallel operation.
11 of primary switchgear to restore utility
power as discussed in the “Two-Source
Primary” scheme—see Figure 1.3-14.
12 A major advantage of the sparing
transformer system is the typically
lower total base kVA of transformation. K K K
13 In a double-ended substation design,
each transformer must be rated to
carry the sum of the loads of two
14 busses and usually requires the
addition of cooling fans to accomplish Sparing Transformer
this rating. In the “sparing” concept,
15 each transformer carries only its own
load, which is typically not a fan-cooled
K K
rating. In addition to first cost savings,
16 there is a side benefit of reduced
equipment space.
17 Typical Secondary Busway Loop

18
K K
19 Typical Single-Ended Substation

20
Figure 1.3-15. Sparing Transformer System

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-9
August 2017 Types of Systems
Sheet 01 037

6. Simple Spot Network Systems The purpose of the network protector system design with similar spare
The ac secondary network system
is to protect the integrity of the capacity. This occurs in many radial i
network bus voltage and the loads systems because more and smaller
is the system that has been used for served from it against transformer feeders are often used in order to
many years to distribute electric power and primary feeder faults by quickly minimize the extent of any outage ii
in the high-density, downtown areas disconnecting the defective feeder- when a primary fault event occurs.
of cities, usually in the form of utility transformer pair from the network
grids. Modifications of this type of when backfeed occurs. In spot networks, when a fault occurs 1
system make it applicable to serve on a primary feeder or in a transformer,
loads within buildings. The simple spot network system the fault is isolated from the system
The major advantage of the secondary
resembles the secondary-selective through the automatic tripping of the 2
radial system in that each load area primary feeder circuit breaker and all
network system is continuity of is supplied over two or more primary of the network protectors associated
service. No single fault anywhere
on the primary system will interrupt
feeders through two or more trans- with that feeder circuit. This operation 3
formers. In network systems, the does not interrupt service to any loads.
service to any of the system’s loads. transformers are connected through After the necessary repairs have been
Most faults will be cleared without
interrupting service to any load.
network protectors to a common made, the system can be restored to 4
bus, as shown in Figure 1.3-16, from normal operating conditions by closing
Another outstanding advantage that which loads are served. Because the the primary feeder breaker. All network
the network system offers is its flexibil-
ity to meet changing and growing load
transformers are connected in parallel, protectors associated with that feeder 5
a primary feeder or transformer fault will close automatically.
conditions at minimum cost and does not cause any service interrup-
minimum interruption in service to The chief purpose of the network bus
other loads on the network. In addition
tion to the loads.
normally closed ties is to provide for
6
to flexibility and service reliability, the The paralleled transformers supplying the sharing of loads and a balancing
secondary network system provides each load bus will normally carry equal of load currents for each primary
exceptionally uniform and good load currents, whereas equal loading service and transformer regardless of
7
voltage regulation, and its high of the two separate transformers the condition of the primary services.
efficiency materially reduces the supplying a substation in the
costs of system losses. secondary-selective radial system is Also, the ties provide a means for 8
difficult to obtain. The interrupting isolating and sectionalizing ground
Three major differences between the duty imposed on the outgoing feeder fault events within the switchgear
network system and the simple radial breakers in the network will be greater network bus, thereby saving a portion 9
system account for the outstanding with the spot network system. of the loads from service interruptions,
advantages of the network. First, yet isolating the faulted portion for
a network protector is connected in The optimum size and number of corrective action. 10
the secondary leads of each network primary feeders can be used in the
transformer in place of, or in addition spot network system because the The use of spot network systems
to, the secondary main breaker, as loss of any primary feeder and its provides users with several important 11
shown in Figure 1.3-16. Also, the associated transformers does not advantages. First, they save trans-
secondaries of each transformer in result in the loss of any load even former capacity. Spot networks permit
a given location (spot) are connected for an instant. In spite of the spare equal loading of transformers under 12
together by a switchgear or ring bus capacity usually supplied in network all conditions. Also, networks yield
from which the loads are served over systems, savings in primary switch- lower system losses and greatly
short radial feeder circuits. Finally, the gear and secondary switchgear costs improve voltage conditions. 13
primary supply has sufficient capacity often result when compared to a radial
to carry the entire building load with-
out overloading when any one primary 14
feeder is out of service.
Typical Feeder
A network protector is a specially Primary Circuit 15
designed heavy-duty air power breaker, To Other
spring close with electrical motor-charged Networks
Network Transformer
mechanism, with a network relay to 16
control the status of the protector Network Protector
(tripped or closed). Fuses

The network relay is usually a solid- Optional Main, 50/51


17
Relaying and/or
state microprocessor-based component Network Disconnect Tie Tie
integrated into the protector enclosure Drawout 18
that functions to automatically close Low-Voltage
LV Feeder NC NC Switchgear
the protector only when the voltage
conditions are such that its associated
transformer will supply power to the
19
Customer Customer Customer
secondary network loads. It also serves Loads Loads Loads
to automatically open the protector 20
when power flows from the secondary Figure 1.3-16. Three-Source Spot Network
to the network transformer.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-10 Power Distribution Systems
Types of Systems August 2017
Sheet 01 038

The voltage regulation on a network 7. Medium-Voltage Distribution Retransfer to the “Normal” can be
i system is such that both lights and
System Design closed transition subject to the approval
power can be fed from the same load of the utility. Closed transition momen-
bus. Much larger motors can be started A. Single Bus, Figure 1.3-17 tarily (5–10 cycles) parallels both
ii across-the-line than on a simple radial utility sources. Caution: when both
system. This can result in simplified The sources (utility and/or generator(s)) sources are paralleled, the fault current
motor control and permits the use of are connected to a single bus. All feeders available on the load side of the main
1 relatively large low voltage motors with are connected to the same bus. device is the sum of the available fault
their less expensive control. This configuration is the simplest current from each source plus the motor
system; however, outage of the utility fault contribution. It is recommended
2 Finally, network systems provide a
results in total outage. that the short-circuit ratings of the
greater degree of flexibility in adding bus, feeder breakers and all load side
future loads; they can be connected to Normally the generator does not have equipment are rated for the increased
3 the closest spot network bus. adequate capacity for the entire load. available fault current.
Spot network systems are economical A properly relayed system equipped
with load shedding, automatic voltage/ If the utility requires open transfer, the
for buildings that have heavy concen-
4 trations of loads covering small areas, frequency control may be able to disconnection of motors from the bus
maintain partial system operation. must be ensured by means of suitable
with considerable distance between time delay on reclosing as well as
areas, and light loads within the
5 distances separating the concentrated
Any future addition of breaker sections supervision of the bus voltage and its
to the bus will require a shutdown of phase with respect to the incoming
loads. They are commonly used in the bus, because there is no tie breaker. source voltage
hospitals, high rise office buildings,
6 institutional buildings or laboratories This busing scheme does not preclude
where a high degree of service reliabil- the use of cogeneration, but requires
Utility
ity is required from the utility sources. the use of sophisticated automatic syn-
7 Spot network systems are especially chronizing and synchronism checking
G
economical where three or more controls, in addition to the previously
8 primary feeders are available. mentioned load shedding, automatic
frequency and voltage controls.
Principally, this is due to supplying
each load bus through three or This configuration is more expensive
9 more transformers and the reduction than the scheme shown in Figure 1.3-17,
in spare cable and transformer 52 52 but service restoration is quicker. Again,
capacity required. a utility outage results in total outage to
10 Main Bus the load until transfer occurs. Extension
They are also economical when of the bus or adding breakers requires
compared to two transformer double- a shutdown of the bus.
11 ended substations with normally
opened tie breakers. If paralleling sources, reverse current,
52 reverse power and other appropriate
12 Emergency power should be connected relaying protection should be added
to network loads downstream from as requested by the utility.
One of Several Feeders
the network, or upstream at primary
13 voltage, not at the network bus itself.
Figure 1.3-17. Single Bus
Utility #1 Utility #2
B. Single Bus with Two Sources from
14 the Utility, Figure 1.3-18
Same as the single bus, except that Normal Standby

15 two utility sources are available.


This system is operated normally with
the main breaker to one source open.
16 Upon loss of the normal service, the
transfer to the standby normally
open (NO) breaker can be automatic 52 NC 52 NO
17 or manual. Automatic transfer is
preferred for rapid service restoration
especially in unattended stations.
18 Loads

Figure 1.3-18. Single Bus with Two-Sources


19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.3-11
August 2017 Types of Systems
Sheet 01 039

C. Multiple Sources with Tie Breaker, In Figure 1.3-20, closing of the tie Summary
Figure 1.3-19 and Figure 1.3-20 breaker following the opening of a The medium-voltage system configu- i
This configuration is similar to the main breaker can be manual or auto- rations shown are based on using
configuration shown in Figure 1.3-18. It matic. However, because a bus can metal-clad drawout switchgear. The
differs significantly in that both utility be fed through two tie breakers, the service continuity required from ii
sources normally carry the loads and control scheme should be designed electrical systems makes the use of
also by the incorporation of a normally to make the selection. single-source systems impractical.
open tie breaker. The outage to the 1
The third tie breaker allows any bus In the design of a modern medium-
system load for a utility outage is to be fed from any utility source.
limited to half of the system. Again, voltage system, the engineer should:
the closing of the tie breaker can be 1. Design a system as simple as
2
Caution for Figures 1.3-18, 1.3-19 and
manual or automatic. The statements 1.3-20: If continuous paralleling of possible.
made for the retransfer of the configu-
ration shown in Figure 1.3-18 apply to
sources is planned, reverse current,
2. Limit an outage to as small a 3
reverse power and other appropriate
this scheme also. portion of the system as possible.
relaying protection should be added.
When both sources are paralleled for 3. Provide means for expanding the 4
any amount of time, the fault current system without major shutdowns.
Utility #1 Utility #2
available on the load side of the main
device is the sum of the available 4. Design a protective relaying 5
fault current from each source plus system so that only the faulted
the motor fault contribution. It is part is removed from service,
required that bus bracing, feeder and damage to it is minimized
consistent with selectivity.
6
breakers and all load side equipment
is rated for the increased available 5. Specify and apply all equipment
52 NC 52 NC
fault current. within its published ratings and 7
NO national standards pertaining to
Bus #1 Bus #2 the equipment and its installation.
52 8
Utility #1 Utility #2 Utility #3
52 52 9

Load Load
10

Figure 1.3-19. Two-Source Utility with 52 NC 52 NC 52 NC 11


Tie Breaker
NO NO
If looped or primary selective Bus #1 Bus #2 Bus #3 12
distribution system for the loads 52 52
is used, the buses can be extended
without a shutdown by closing the tie 13
breaker and transferring the loads to 52 NO 52 Typical Feeder 52 52 52 NO
the other bus.
This configuration is more expensive Tie Busway 14
than the configuration shown in
Figure 1.3-18. The system is not limited Figure 1.3-20. Triple-Ended Arrangement
to two buses only. Another advantage 15
is that the design may incorporate
momentary paralleling of buses on
retransfer after the failed line has been 16
restored to prevent another outage.
See the Caution for Figures 1.3-18,
1.3-19 and 1.3-20. 17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.3-12 Power Distribution Systems
August 2017
Sheet 01 040

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-1
August 2017 Power System Analysis
Sheet 01 041

Systems Analysis ■ Circuit breaker duty—identify The following additional studies


asymmetrical fault current based should be considered depending i
A major consideration in the design on X/R ratio upon the type and complexity of the
of a distribution system is to ensure ■ Protective device coordination— distribution system, the type of facility
that it provides the required quality determine characteristics and set- and the type of loads to be connected ii
of service to the various loads. This tings of medium voltage protective to the system:
includes: serving each load under relays and fuses, and entire low
normal conditions, under abnormal voltage circuit breaker and fuse
■ Harmonic analysis 1
conditions and providing the desired ■ Transient stability
coordination
protection to service and system ■ Insulation coordination
■ Load flow—simulate normal and
apparatus so that interruptions of abnormal load conditions of system ■ Grounding study
2
service are minimized. voltages, power factor, line and ■ Switching transient
Under normal conditions, the transformer loadings 3
The Power Systems Engineering Team
important technical factors include ■ Motor starting—identify system
within Eaton’s Electrical Services &
voltage profile, losses, load flow, voltages, motor terminal voltage,
Systems division can provide any
effects of motor starting, service motor accelerating torque, and
of the system studies discussed in 4
continuity and reliability. The prime motor accelerating time when
this section.
considerations under faulted starting large motors
conditions are apparatus protection,
Short-circuit calculations define
5
fault isolation service continuity and
momentary and steady-state fault
Short-Circuit Currents—
of course personnel safety. General
currents for specific points in the
During the system preliminary electrical system. This information is
6
planning stage, before selection of used to select protective devices and The amount of current available in
the distribution apparatus, several to determine required equipment bus a short-circuit fault is determined by
distribution systems should be bracing and withstand levels. These the capacity of the system voltage 7
analyzed and evaluated, including calculations are generated for both sources and the impedances of the
normal, emergency and alternative system, including the fault. Voltage
both economic and technical factors.
During this stage, if system size system configurations. sources include the power supply 8
or complexity warrant, it may be (utility or on-site generation) plus all
Computer software programs can rotating machines connected to the
appropriate to provide a thorough
identify the fault current at any bus system at the time of the fault, and 9
review of each system under both
in the distribution system under any are not connected through power
normal and abnormal conditions.
number of scenarios of source and load conversion equipment such as
This type of dynamic analysis is combinations. It is often necessary to variable frequency drives. 10
typically done using Computer evaluate the distribution system in all
Simulation Software. Selection of the possible operating states of sources A fault may be either an arcing or
components such as circuit breakers, and loads to understand available fault bolted fault. In an arcing fault, part of 11
cables, transformers, equipment currents in all possible states. The the circuit voltage is consumed across
motors and generators are entered results of these calculations permit the arc and the total fault current is
into a power flow one-line of the optimizing service to the loads while somewhat smaller than for a bolted 12
system. Changes to these variables, properly applying distribution appara- fault. The bolted fault condition results
including the type of breaker as well as tus within their intended limits. in the highest fault magnitude fault
its trip unit settings, the size and length currents, and therefore is the value 13
Articles 110.21(B) and 110.24 of 2014 sought in the fault calculations.
of conductors, the hp of motors and
National Electrical Code (NEC) have
kVA of transformers and generators, Basically, the short-circuit current is
can be adjusted to reflect the impact
increased the field-applied available
determined by applying Ohm’s Law
14
fault current marking requirements for
this will have on the short-circuit to an equivalent circuit consisting
electrical equipment. Article 110.24(A)
energy available at various points in
the power distribution system.
states: “Service equipment in other of a constant voltage source and a
time- varying impedance. A time-
15
than dwelling units shall be legibly
The principal types of computer marked in the field with the maximum varying impedance is used in order
programs used to provide system available fault current. The field mark- to account for the changes in the 16
studies include: ing(s) shall include the date the fault- effective voltages of the rotating
current calculation was performed and machines during the fault.
■ Short circuit—identify three-phase be of sufficient durability to withstand In an AC system, the resulting short- 17
and line-to-ground fault currents the environment involved.” Article
and system impedances circuit current starts out higher in
110.24(B) then takes this a step further magnitude than the final steady-state
■ Arc flash—calculates arc flash stating: “When modifications to the value and asymmetrical (due to the 18
energy levels, which leads to electrical installation occur that affect DC offset) about the X-axis. The
the proper selection of personal the maximum available fault current at current then decays toward a lower
protective equipment (PPE) the service, the maximum available symmetrical steady-state value. 19
fault current shall be verified or recal-
culated as necessary. The required
field marking(s) in 110.24(A) shall be 20
adjusted to reflect the new level of
maximum available fault current.”
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-2 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 042

The time-varying characteristic of Synchronous reactance (Xd ), which The electric network that determines
i the impedance accounts for the determines fault current after steady- the short-circuit current consists of an
symmetrical decay in current. The state condition is reached. It has no AC driving voltage equal to the pre-fault
ratio of the reactive and resistive effect as far as short-circuit calculations system voltage and an impedance
ii components (X/R ratio) accounts are concerned, but is useful in the corresponding to that observed when
for the DC decay, see Figure 1.4-1. determination of relay settings. looking back into the system from the
The fault current consists of an fault location.
1 exponentially decreasing direct- Transformer impedance, in percent, is
current component superimposed defined as that percent of rated primary In industrial medium- and high-voltage
upon a decaying alternating-current. voltage that must be applied to the work, it is generally satisfactory to
2 transformer to produce rated current regard reactance as the entire imped-
The rate of decay of both the DC and flowing in the secondary, with the ance; resistance may be neglected.
AC components depends upon the secondary shorted through zero However, this is normally permissible
3 ratio of reactance to resistance (X/R) resistance. It is important to note that only if the X/R ratio of the medium
of the circuit. The greater this ratio, the transformer percent impedance is voltage system is equal to or more
the longer the current remains higher a per-unit value typically expressed on than 25.
4 than the steady-state value that it the base kVA rating of the transformer.
In low-voltage (1000 V and below)
would eventually reach. Therefore, it is not necessary to calcu-
late maximum fault current produced calculations, it is usually worthwhile to
The total fault current is not symmetrical attempt greater accuracy by including
5 with respect to the time-axis because
at the fan-cooled rating or the higher
resistance with reactance in dealing
temperature rise kVA ratings because
of the direct-current component, hence the per-unit impedance at those kVA with impedance. It is for this reason,
it is called asymmetrical current. The plus ease of manipulating the various
6 DC component depends on the point
ratings increases by the same ratio,
impedances of cables and buses and
making the fault current calculation
on the voltage wave at which results the same.Therefore, assuming transformers of the low-voltage
the fault is initiated. circuits, that computer studies are
7 the primary voltage can be sustained
recommended before final selection of
See Figure 1.4-2 for multiplying factors (generally referred to as an infinite
or unlimited supply), the maximum apparatus and system arrangements.
that relate the rms asymmetrical value
8 of total current to the rms symmetrical current a transformer can deliver to When evaluating the adequacy
value, and the peak asymmetrical a fault condition is the quantity of of short-circuit ratings of medium
value of total current to the rms (100 divided by percent impedance) voltage circuit breakers and fuses,
9 symmetrical value. times the transformer rated secondary both the rms symmetrical value and
current. Limiting the power source asymmetrical value of the short-circuit
The AC component is not constant fault capacity to the transformer current should be determined.
10 if rotating machines are connected primary will thereby reduce the
to the system because the impedance maximum fault current from the For low-voltage circuit breakers and
of this apparatus is not constant. The transformer secondary. fuses, the rms symmetrical value
11 rapid variation of motor and generator should be determined along with
impedance is due to these factors: either: the X/R ratio of the fault
at the device or the asymmetrical
12 Subtransient reactance (Xd ), deter- short-circuit current.
mines fault current during the first
cycle, and after about 6 cycles this
13 value increases to the transient
Total Current—A Wholly Offset
reactance. It is used for the calculation Asymmetrical Alternating Wave
of the momentary interrupting and/or 3.0
14 momentary withstand duties of rms Value of Total Current
equipment and/or system. 2.5 Alternating Component -
Symmetrical Wave
Transient reactance (Xd ), which
15 determines fault current after about
2.0 rms Value of
Alternating Component
6 cycles and this value in 1/2 to
1.5
Scale of Curent Values

2 seconds increases to the value of


16 the synchronous reactance. It is used 1.0
in the setting of the phase overcurrent
relays of generators and medium- 0.5
17 voltage circuit breakers. 1 2 3 4
0

18 0.5

–1.0
19
Direct Component—The Axis
–1.5 of Symmetrical Wave Time in Cycles of
a 60 Hz Wave
20 –2.0

Figure 1.4-1. Structure of an Asymmetrical Current Wave


21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-3
August 2017 Power System Analysis
Sheet 01 043

Fault Current Waveform Relationships i


The following Figure 1.4-2 describes Based on a 60 Hz system and t = 1/2 cycle
the relationship between fault (ANSI/IEEE C37.13.2015)
current peak values, rms symmetrical – 260
-----------------
ii
values and rms asymmetrical values 120 - –
Ip  ----------------  -----------
depending on the calculated X/R ratio. Peak multiplication factor = ----- = 2 1 + e X  R  = 2 1 + e X  R 
I     1
The table is based on the following  
general formulas:
 – 2   260 

– t
-------------
---------------------------------
120 – 2
2
1. Ip = I 2  1 + e X  R I rms asym
---------------------------------
XR
-------------
XR
  rms multiplication factor = ------------------------------ = 1 + 2e = 1 + 2e
  I 3
– 2t
---------------
Example for X/R =15
XR
2. I rms asym = I 1 + 2e – 4
 ------- 
Peak mf = 2  1 + e 15  = 2.5612
Where:  
  5
I = Symmetrical rms current
– 2
Ip = Peak current -----------
rms mf = 1 + 2e
15
= 1.5217 6
e = 2.718
=2f 7
f = Frequency in Hz
t = Time in seconds 8

2.8
9
2.7 10
PEAK MAXIMUM ASYMMETRICAL

RMS MAXIMUM ASYMMETRICAL


Based Upon: rms Asym = DC 2 + rms Sym2
2.6 with DC Value
RMS SYMMETRICAL

Taken at Current Peak 11

RMS SYMMETRICAL
2.5

2.4 12
2.3
13
2.2 1.8
R
TO

14
C
FA

2.1 1.7
N
PEAK MULTIPLICATION FACTOR =

O
TI

RMS MULTIPLICATION FACTOR =


CA

2.0 1.6
15
LI
IP
LT

1.9 1.5
U
M

OR
AK

CT 16
PE

1.8 FA 1.4
TION
1.7 LICA 1.3
UL
TIP 17
M
1.6 RMS 1.2

1.5 1.1
18
1.4
1 1.5 2 2.5 3 4 5 6 7 8 9 10 15 20 25 30 40 50 60 70 80 90 100 19
CIRCUIT X/R RATIO (TAN PHASE)
20
Figure 1.4-2. Relation of X/R Ratio to Multiplication Factor
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-4 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 044

i Fault Current Calculations To determine the motor contribution Medium-Voltage Motors


during the first half-cycle fault current,
when individual motor horsepower If known, use actual values otherwise
The calculation of asymmetrical
load is known, the subtransient use the values indicated for the same
currents is a laborious procedure since
ii the degree of asymmetry is not the reactances found in the IEEE Red Book type of motor.
same on all three phases. It is common should be used in the calculations.
practice for medium voltage systems,
Calculation Methods
1 to calculate the rms symmetrical fault
For motors fed through adjustable The following pages describe various
frequency drives or solid-state soft methods of calculating short-circuit
current, with the assumption being
starters, there is no contribution to currents for both medium- and low-
made that the DC component has
2 decayed to zero, and then apply a multi-
fault current, unless 1) they have an voltage systems. A summary of
internal run contactor or 2) they have the types of methods and types of
plying factor to obtain the first half-
a bypass contactor. calculations is as follows:
cycle rms asymmetrical current, which
3 is called the “momentary current.” When the motor load is not known, ■ Medium-voltage
the following assumptions generally switchgear—exact
For medium-voltage systems (defined
are made. The following percentage
4 by IEEE as greater than 1000 V up to
estimates are based on design load or
method . . . . . . . . . . . . . . Page 1.4-5
69,000 V) the multiplying factor is ■ Medium-voltage
transformer nameplate rating, when
established by NEMA® and ANSI switchgear—quick
known.
5 standards depending upon the check table . . . . . . . . . . . Page 1.4-8
operating speed of the breaker. 208Y/120 V Systems ■ Medium-voltage
For low-voltage systems, short-circuit ■ Assume 50% lighting and 50% switchgear
6 study software usually calculates the motor load Example 1—verify
symmetrical fault current and the ratings of breakers . . . . Page 1.4-9
or
faulted system X/R ratio using UL ■ Medium-voltage
7 and ANSI guidelines. If the X/R ratio ■ Assume motor feedback contribu- switchgear
is within the standard (lower than the tion of twice full load current of Example 2—verify
ratings of breakers
8 breaker test X/R ratio), and the breaker
interrupting current is under the
transformer
with rotating
symmetrical fault value, the breaker or loads . . . . . . . . . . . . . . . . Page 1.4-10
9 is properly rated. 240/480/600 V Three-Phase, Three-Wire or ■ Medium-voltage
Four-Wire Systems switchgear Example 3
If the X/R ratio is higher than UL or
—verify ratings of
ANSI standards, the study applies a ■ Assume 100% motor load
10 multiplying factor to the symmetrical
breakers with
or generators . . . . . . . . . . . Page 1.4-11
calculated value (based on the
X/R value of the system fault) and ■ Medium-voltage
■ Assume motors 25% synchronous
11 compares that value to the breaker and 75% induction
fuses—exact method . . Page 1.4-11
symmetrical value to assess if it is ■ Power breakers—
properly rated. or asymmetry
12 derating factors . . . . . . . Page 1.4-12
In the past, especially using manual ■ Assume motor feedback contribu-
■ Molded-case
calculations, a multiplying factor of tion of four times full load current
breakers—asymmetry
13 1.35 (based on the use of an X/R ratio of transformer
derating factors . . . . . . . Page 1.4-13
of 6.6 representing a source short-
circuit power factor of 15%) was used 480Y/277 V Systems in Commercial Buildings ■ Short-circuit
14 to calculate the asymmetrical current. ■ Assume 50% induction motor load calculations—
These values take into account that short cut method
or for a system . . . . . . . . . . Page 1.4-14
medium voltage breakers are rated
15 on maximum asymmetry and low ■ Assume motor feedback contribu- ■ Short-circuit
voltage breakers are rated average tion of two times full load current calculations—short
asymmetry. of transformer or source cut method for
16 end of cable . . . . . . . . . . Page 1.4-16
■ Short-circuit currents—
chart of transformers
17 300–3750 kVA. . . . . . . . . Page 1.11-9

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-5
August 2017 Power System Analysis
Sheet 01 045

Fault Current Calculations Ultimately, as vacuum circuit breakers For example, consider the following case:
i
became more and more prevalent in
for Specific Equipment— the industry, the IEEE C37.06-2000 Assume a 12.47 kV system with
20,000 A symmetrical available. In
Exact Method standard was published to recognize
order to determine if an Eaton Type ii
both MVA and K = 1 rated breakers.
150 VCP-W 500 vacuum breaker is
The purpose of the fault current calcu-
The following is a review of the suitable for this application, check
lations is to determine the fault current
meaning of the ratings. (See Tab 5, the following: 1
at the location of a circuit breaker, fuse
or other fault interrupting device in Section 5.4.)
From Table 5.4-1B in Tab 5, Section 5.4
order to select a device adequate for the The Rated Maximum Voltage under column “Rated Maximum
calculated fault current or to check the
This designates the upper limit of Voltage” V = 15 kV, under column 2
thermal and momentary ratings of non- “Rated short-circuit Current” I = 18 kA,
interrupting devices. When the devices design and operation of a circuit
breaker. For example, a circuit breaker “Rated Voltage Range Factor” K = 1.3.
to be used are ANSI-rated devices, the
with a 4.76 kV rated maximum voltage
3
fault current must be calculated and the Test 1 for V/Vo x I or 15 kV/12.47 kV x 18
device selected as per ANSI standards. cannot be used in a 4.8 kV system. kA = 21.65; also check K x I (which
The calculation of available fault current K-Rated Voltage Factor is shown in the column headed 4
“Maximum Symmetrical Interrupting
and system X/R rating is also used to The rated voltage divided by this factor Capability”) or 1.3 x 18 kA = 23.4 kA.
verify adequate busbar bracing and determines the system kV a breaker can
momentary withstand ratings of be applied up to the short-circuit kVA
Because both of these numbers are 5
greater than the available system fault
devices such as contactors. rating calculated by the formula current of 20,000 A, the breaker is
Medium-Voltage VCP-W 3  Rated SC Current  Rated Max. Voltage
acceptable (assumes the breaker’s 6
momentary and fault close rating is
Metal-Clad Switchgear Note: Interrupting capabilities of some of
also acceptable).
MVA breaker ratings first originated today’s vacuum breakers may have K=1, Note: If the system available fault current 7
many years ago to describe the whereby the interrupting current is constant were 22,000 A symmetrical, this breaker
across its entire operating range. could not be used even though the
preferred ratings of air-magnetic circuit
breakers that had published short- “Maximum Symmetrical Interrupting 8
Rated Short-Circuit Current Capability” is greater than 22,000 because
circuit current interruption ratings
For K = 1 breakers, this is the symmetri- Test 1 calculation is not satisfied.
based on their rated maximum
voltage. These breakers, however, cal current that a breaker can interrupt
For approximate calculations, Table 1.4-1
9
could achieve higher interruption across it's operational range. With
MVA rated breakers (K >1), this is provides typical values of % reactance
ratings at lower operating voltages (X) and X/R values for various rotating
until the maximum interruption the symmetrical rms value of current
equipment and transformers. For sim-
10
rating was exceeded. that the breaker can interrupt at rated
maximum voltage. For example, with plification purposes, the transformer
The ratio of these two interruption an Eaton 50 VCP-W 250 circuit breaker, impedance (Z) has been assumed to be 11
ratings is called rated voltage range it should be noted that the product primarily reactance (X). In addition, the
indicator (K). The rated voltage range 3 x 4.76 x 29,000 = 239,092 kVA is less resistance (R) for these simplified cal-
indicator, K, is greater than 1 for MVA than the nominal 250,000 kVA listed. culations has been ignored. For detailed 12
rated breakers. For example, an Eaton This rating (29,000 A) is also the base calculations, the values from the IEEE
quantity that all the “related” capabili- Red Book Standard 141, for rotating
150 VCP-W 500, (15 kV – 500 MVA rated
machines, and ANSI C57 and/or C37
breaker with a K=1.30 rating has a ties are referred to.
for transformers should be used.
13
published interruption rating of 18 kA Maximum Symmetrical Interrupting
at 15 kV, but has a maximum interrup- Capability
tion rating of 23 kA (18 kA x 1.30) at
With K=1 breakers, the short-time
14
11.5 kV (15 kV divided by 1.30).
withstand current and the maximum
As new vacuum interrupting symmetrical interrupting current 15
technologies were developed, are equal to the rated symmetrical
scientists discovered that reducing interrupting current. For MVA rated
breakers (K >1), this is expressed
the operating voltage did not increase
in rms symmetrical amperes or
16
the short-circuit current interrupting
capability of new interrupters. In fact, kiloamperes and is K x I rated;
1.24 x 29,000 = 35,960 rounded
as the operating voltage is reduced,
to 36 kA. 17
the short-circuit current interrupting
capability changes only little. There- This is the rms symmetrical current
fore the MVA (K >1.0) basis of rating that the breaker can interrupt down to 18
no longer accurately reflected the true a voltage equal to maximum rated
interrupting characteristics of the voltage divided by K (for example,
newer circuit breaker designs. 4.76/1.24 = 3.85). If this breaker is 19
applied in a system rated at 2.4 kV, the
calculated fault current must be less
than 36 kA. 20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-6 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 046

Table 1.4-1. Reactance X The Close and Latch Capability


i System Reactance X Used for Typical Values and Range K = 1 and K >1 breakers also differ in
Component Short-Circuit Close and Latch on Component Base the calculations for the breaker's close
Duty (Momentary) % Reactance X/R Ratio and latch rating. With K = 1 breakers,
ii this is a calculated peak value using
Two-pole turbo generator X X 9 (7–14) 80 (40–120)
Four-pole turbo generator X X 15 (12–17) 80 (40–120) 2.6 x the breaker’s symmetrical
interrupting rating. For MVA rated
1 Hydro generator with damper wedges
and synchronous condensers
X X 20 (13–32) 30 (10–60)
breakers (K >1), this is also a related
quantity expressed in rms asymmetri-
Hydro generator without damper windings 0.75X 0.75X 16 (16–50) 30 (10–60)
cal amperes by 1.6 x maximum
2 All synchronous motors 1.5X 1.0X 20 (13–35) 30 (10–60)
symmetrical interrupting capability.
Induction motors above 1000 hp, 1800 rpm 1.5X 1.0X 17 (15–25) 30 (15–40) For example, 1.6 x 36 = 57.6 or 58 kA,
and above 250 hp, 3600 rpm
or 1.6 K x rated short-circuit current.
3 All other induction motors 50 hp and above 3.0X 1.2X 17 (15–25) 15 (2–40)
Induction motors below 50 hp and Neglect Neglect — — Another way of expressing the close
all single-phase motors and latch rating is in terms of the peak
4 Distribution system from remote X X As specified 15 (5–15) current, which is the instantaneous
transformers or calculated value of the current at the crest. ANSI
Current limiting reactors X X As specified 80 (40–120) Standard C37.09 indicates that the ratio
5 or calculated of the peak to rms asymmetrical value
Transformers for any asymmetry of 100% to 20%
ONAN to 10 MVA, 69 kV X X 8.0 18 (7–24)
(percent asymmetry is defined as the
6 ONAN to 10 MVA, above 69 kV X X 8.0 to 10.5 18 (7–24)
ratio of DC component of the fault in
Depends on per unit to 2 ) varies not more than
OFAF 12–30 MVA X X 20 (7–30) ±2% from a ratio of 1.69. Therefore, the
primary
7 OFAF 40–100 MVA X X windings BIL 38 (32–44) close and latch current expressed in
rating terms of the peak amperes is = 1.6 x
1.69 x K x rated short-circuit current.
8 Table 1.4-2. Typical System X/R Ratio Range (for Estimating Purposes)
Type of Circuit X/R Range In the calculation of faults for the
purposes of breaker selection, the
9 Remote generation through other types of circuits such as transformers rated 10 MVA
or smaller for each three-phase bank, transmission lines, distribution feeders, etc.
15 or less rotating machine impedances specified
in ANSI Standard C37.010 Article 5.4.1
Remote generation connected through transformer rated 10 MVA to 100 MVA 15–40 should be used. The value of the
for each three-phase bank, where the transformers provide 90% or more
10 of the total equivalent impedance to the fault point
impedances and their X/R ratios
should be obtained from the equipment
Remote generation connected through transformers rated 100 MVA or larger 30–50
for each three-phase bank where the transformers provide 90% or more manufacturer. At initial short-circuit
11 of the total equivalent impedance to the fault point studies, data from manufacturers is
Synchronous machines connected through transformers rated 25–100 MVA 30–50 not available. Typical values of imped-
for each three-phase bank ances and their X/R ratios are given
12 Synchronous machines connected through transformers rated 100 MVA and larger 40–60 in Table 1.4-1.
Synchronous machines connected directly to the bus or through reactors 40–120 The ANSI Standard C37.010 allows the
13 use of the X values only in determin-
ing the E/X value of a fault current.
The R values are used to determine the
14 X/R ratio, in order to apply the proper
multiplying factor, to account for the
total fault clearing time, asymmetry,
15 and decrement of the fault current.

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-7
August 2017 Power System Analysis
Sheet 01 047

The steps in the calculation of fault Step 5: Reduce the resistance network reactance external to the generation
currents and breaker selection are to an equivalent resistance. Call this is 1.5 times or more than the subtran- i
described hereinafter: resistance RI. The above calculations sient reactance of the generation on
of XI and RI may be calculated by a common base. Also use Figure 1.4-5
Step 1: Collect the X and R data of the several computer programs. where the fault is supplied by a ii
circuit elements. Convert to a common utility only.
kVA and voltage base. If the reactances Step 6: Calculate the E/XI value, where
and resistances are given either in E is the prefault value of the voltage at Step 9: Interrupting duty short-circuit 1
ohms or per unit on a different voltage the point of fault nominally assumed current = E/XI x MFx = E/X2.
or kVA base, all should be changed 1.0 pu.
Step 10: Construct the sequence
to the same kVA and voltage base. This X
Step 7: Determine X/R = ------I as (positive, negative and zero) networks 2
caution does not apply where RI
the base voltages are the same as previously calculated. properly connected for the type of fault
under consideration. Use the
the transformation ratio. Step 8: Go to the proper curve for X values required by ANSI Standard 3
Step 2: Construct the sequence the type of fault under consideration C37.010 for the “Close and Latch”
networks and connect properly for (three-phase, phase-to-phase, phase- duty value of the short-circuit current.
the type of fault under consideration. to-ground), type of breaker at the loca- 4
Use the X values required by ANSI tion (2, 3, 5 or 8 cycles), and contact Step 11: Reduce the network to an
Standard C37.010 for the “interrupting” parting time to determine the multi- equivalent reactance. Call the reac-
duty value of the short-circuit current. plier to the calculated E/XI. tance X. Calculate E/X x 1.6 if the 5
breaker close and latch capability is
Step 3: Reduce the reactance network See Figures 1.4-3, 1.4-4 and 1.4-5 for given in rms amperes or E/X x 2.7 if
to an equivalent reactance. Call this 5-cycle breaker multiplying factors. 6
the breaker close and latch capability
reactance XI. Use Figure 1.4-5 if the short circuit is is given in peak or crest amperes.
fed predominantly from generators
Step 4: Set up the same network for
resistance values.
removed from the fault by two or 7
more transformations or the per unit

130 130 130 8


120 120 120
9
8

7
5

110 110 110


4
6

12
10
10
5

8
6
100 100 100
4

4
3

90
90 90
11

3
80 80 80

12

TIME
Ratio X/R

Ratio X/R
Ratio X/R

TIME

70 70 70

ING
13
RT
IN G

60 60 60
PA
ART

T
AC

50 50 50
T P

14
NT
AC

CO

40
NT

40 40
CO

30 30
5-CYCLE
30 15
5-CYCLE 5-CYCLE
BREAKER BREAKER BREAKER
20 20 20
16
10 10 10

17
1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4 1.0 1.1 1.2 1.3 1.4
Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes Multiplying Factors for E / X Amperes
18
Figure 1.4-3. Three-phase Fault Multiplying Figure 1.4-4. Line-to-Ground Fault Multiplying Figure 1.4-5. Three-phase and Line-to-Ground
Factors that Include Effects of AC and Factors that Include Effects of AC and Fault Multiplying Factors that Include Effects
DC Decrement DC Decrement of DC Decrement Only 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-8 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 048

i
Step 12: Select a breaker whose: Application Quick Check Table Application Above 3,300 ft (1,000 m)
a. Maximum voltage rating exceeds The rated one-minute power frequency
For application of circuit breakers in a withstand voltage, the impulse with-
the operating voltage of the system:
radial system supplied from a single stand voltage, the continuous current
ii E V max source transformer, short-circuit duty rating, and the maximum voltage rating
b. --------  I  -----------------  KI was determined using E/X amperes must be multiplied by the appropriate
X2 Vo
and 1.0 multiplying factor for X/R ratio correction factors below to obtain
1 of 15 or less and 1.25 multiplying modified ratings that must equal or
See Table 6.0-1, Tab 6. factor for X/R ratios in the range of exceed the application requirements.
15 to 40. Refer to Table 1.4-4 below.
2 Where: Note: For assemblies containing vacuum
I = Rated short-circuit current breakers at high altitudes, system voltage is
not derated.
Vmax = Rated maximum voltage
3 of the breaker Note: Intermediate values may be obtained
by interpolation.
Vo = Actual system voltage
4 Table 1.4-3. Altitude Derating
KI = Maximum symmetrical
interrupting capacity Altitude in Correction Factor
5 c. E/X x 1.6 m rms closing and
Feet (Meters) Current Voltage

latching capability of the breaker 3300 (1006) (and below) 1.00 1.00
5000 (1524) 0.99 0.95
6 and/or 10,000 (3048) 0.96 0.80

E/X x 2.7 m Crest closing and Table 1.4-4. Application Quick Check Table
7 latching capability of the breaker.
Source Operating Voltage
The ANSI standards do not require the Transformer kV
inclusion of resistances in the calcula- MVA Rating
8 tion of the required interrupting and Motor Load 2.4 4.16 6.6 12 13.8
close and latch capabilities. Thus the 100% 0%
calculated values are conservative.
9 However, when the capabilities of 1 1.5
1.5 2 50VCP-W250
existing switchgear are investigated, 2 2.5 12 kA 50VCP-W250 150VCP-W500 150VCP-W500 150VCP-W500
the resistances should be included.
10 2.5 3 10.1 kA 23 kA 22.5 kA 19.6 kA
3 3.75
For single line-to-ground faults, the
symmetrical interrupting capability 3.75 5 50VCP-W250
11 is 1.15 x the symmetrical interrupting 5 7.5 36 kA 50VCP-W250
33.2 kA
capability at any operating voltage, 7.5 10 50VCP-W350
10 1 10 49 kA
but not to exceed the maximum
12 symmetrical capability of the breaker. 10 12 1
12 15 50VCP-W350 75VCP-W500
ANSI C37 provides further guidance for 46.9 kA 41.3 kA
13 medium voltage breaker application. 15 20
Reclosing Duty 20 1 20 Breaker Type and 150VCP-W750 150VCP-W750
25 symmetrical interrupting capacity 35 kA 30.4 kA
14 ANSI Standard C37.010 indicates the
30 at the operating voltage
reduction factors to use when circuit
breakers are used as reclosers. Eaton 50 1 150VCP-W1000 150VCP-W1000
46.3 kA 40.2 kA
15 VCP-W breakers are listed at 100%
1 Transformer impedance 6.5% or more, all other transformer impedances are 5.5% or more.
rating factor for reclosing.

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-9
August 2017 Power System Analysis
Sheet 01 049

Application of K >1 Breakers on a Symmetrical Current Rating Basis For Three-Phase Fault
E i
Example 1—Fault Calculations I 3-Phase  -----
X
Given a circuit breaker interrupting and momentary rating in the table below,
verify the adequacy of the ratings for a system without motor loads, as shown.
where X is ohms per phase and E is ii
the highest typical line-to-neutral
Table 1.4-5. Short-Circuit Duty operating voltage or
Type V Max. Three-Phase Symmetrical Interrupting Capability Close and Latch or IB
1
Breaker at V Max. Max. KI at 4.16 kV Oper. Voltage Momentary I 3-Phase  ------
X
50VCP–W250 4.76 kV 29 kA 36 kA 4.76
----------- (29) = 33.2 kA I1
58 kA I3
where X is per unit reactance
2
4.16
LG symmetrical interrupting capability IB is base current
— 36 kA 1.15 (33.2) = 38.2 kA I2 3
Base current I B = 3.75 MVA
 = 0.52kA
Note: Interrupting capabilities I1 and I2 at operating voltage must not exceed maximum 3  4.16 kV 
symmetrical interrupting capability Kl. 4
0.52 I1
Check capabilities I1, I2 and I3 on the following utility system where there is no I 3-Phase    8.6 kA Sym.
----- ----------------------
X 0.0604
motor contribution to short circuit. 5
On 13.8 kV System, 3.75 MVA Base   9 (is less than 15)
System X
R
13.8 kV
would use 1.0 multiplying factor for
6
3.75 MVA- = 0.01 pu or 1%
Z = --------------------------------
375 MVA short-circuit duty, therefore, short-
X circuit duty is 8.6 kA sym. for three-
R
= 15
phase fault I1 and momentary duty is
7
2X 
2
2 2 2
Z = X +R = R  --------
+ 1 8.6 x 1.6 = 13.7 kA I3.
375 MVA  R
2  8
Available For Line-to-Ground Fault
Z 1 1
R  -----------------------  ----------------  ------------------  0.066% 3E 3I B
2 266 15.03 I LG  ----------------------------  ---------------------------- 9
X
-------- + 1 2X 1 + X 0 2X 1 + X 0
2
13.8 kV
R
For this system, X0 is the zero sequence
reactance of the transformer, which
10
3750 kVA X = X
-----  R  = 15 (0.066) = .99% is equal to the transformer positive
R sequence reactance and X1 is the posi-
tive sequence reactance of the system.
11
Transformer Standard 5.5% Impedance
has a ±7.5% Manufacturing Tolerance Therefore,
4.16 kV
5.50 Standard Impedance
12
3(0.52)
–0.41 (–7.5% Tolerance) I LG    9.1 kA Sym.
Transformer Z = 2(0.0604) + 0.0505
50VPC-W250 5.09%
Using 1.0 multiplying factor (see
13
Table 1.4-6), short-circuit duty = 9.1 kA
Sym. LG (I2) 14
Answer
Figure 1.4-6. Example 1—One-Line Diagram The 50VCP-W250 breaker capabilities 15
exceed the duty requirements and
From transformer losses per unit or may be applied.
percent R is calculated 16
With this application, shortcuts could
31,000 Watts Full Load 24.2 kW have been taken for a quicker check of
– 6,800 Watts No Load R  --------------------------------  0.0065 pu or 0.65% the application. If we assume unlimited 17
3750 kVA
24,200 Watts Load Losses short circuit available at 13.8 kV and
that Trans. Z = X
Transformer X = Z –R
2 2 2
(5.09) – (0.65) =
2
25.91 – 0.42 = 25.48 IB
18
0.52
Then I 3-Phase  ------  ------------------  9.5 kA Sym.
X = 5.05% X 0.055
19
X/R ratio 15 or less multiplying factor
X R X/R is 1.0 for short-circuit duty.
13.8 kV System 0.99%
Transformer 5.05%
0.066% 15
0.65% 8 The short-circuit duty is then 9.5 kA 20
System Total 6.04% 0.716% 9 Sym. (I1, I2) and momentary duty is
9.5 x 1.6 kA = 15.2 kA (I3).
or 0.0604 pu 0.00716 pu 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-10 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 050

Example 2—Fault Calculations


i Given the system shown with motor 13.8 kV System
loads, calculate the fault currents X = 15
and determine proper circuit breaker 21 kA Sym. Available
ii selection.
13.8 kV R

X = 5.5% X
All calculations on per unit basis. 7500 kVA Z = 5.53% = 10
R = 0.55% R
1 7.5 MVA base
7.5 MVA- = 0.628 kA
Base Current IB = ------------------------------ 6.9 kV
2 3 6.9 kV 1

X R X/R
3 13.8 kV System

X = 0.628 (6.9) = 0.015 0.015 0.001 15 X X


21 (13.8) = 25 = 35
4 Transformer 0.055 0.0055 10 2 R 3
R
197A FL 173A FL
Total Source Transformer 0.070 pu 0.0065 pu 11 X''d = 20% X''d = 25%
5 3000 hp Synchronous Motor

X = 0.20 (0.628) = 0.638 pu at 7.5 MVA Base 3000 hp


6 0.197 1.0 PF 2500 hp
Ind.
Syn.
2500 hp Ind. Motor
7
X = 0.25 (0.628) = 0.908 pu at 7.5 MVA Base Figure 1.4-7. Example 2—One-Line Diagram
0.173
8 E I B- Source of Interrupting Momentary X X (1) 1
I 3-Ph  -----  ----- where X on per unit base Short-Circuit Current E/X Amperes E/X Amperes R R (X) R
X X
I1 Source Transformer 0.628 0.628 11 11 = 157
= 8.971 = 8.971
9 Table 1.4-6. Multiplying Factor for E/X 0.070 0.070 0.070
Amperes (ANSI C37) I2 3000 hp Syn. Motor 0.628 0.628 25 = 39
= 0.656 = 0.984 25
(1.5) 0.638 0.638 0.638
System Type VCP-W Vacuum
10 X/R Circuit Breaker I3 2500 hp Ind. Motor 0.628
= 0.461
0.628
= 0.691 35 35 = 39
Rated Interrupting Time, 5-Cycle (1.5) 0.908 0.908 0.908
Type of Fault I3F = 10.088 10.647 Total 1/R = 235
11 Ratio Three- LG Three-Phase
or 10.1 kA x 1.6
17.0 kA Momentary Duty
Phase and LG
Source of Short Circuit
12 Local Remote
I B = 0.628 = 0.062
Total X = -------- ------------------
I 3F 10.1
1 1.00 1.00 1.00
13 15 1 1.00 1.00 1.00 X
System ----- = 0.062 (235) = 14.5 is a Multiplying Factor of 1.0 from Table 1.4-6
20 1.00 1.02 1.05 R
25 1.00 1.06 1.10
14 30 1.04 1.10 1.13
Table 1.4-7. Short-Circuit Duty = 10.1 kA
36 1.06 1.14 1.17
40 1.08 1.16 1.22 Breaker V Three-Phase Symmetrical Interrupting Capability Close and Latch
45 1.12 1.19 1.25 Type Max. or Momentary
15 50 1.13 1.22 1.27
at V Max. Max. KI at 6.9 kV Oper. Voltage

55 1.14 1.25 1.30 75VCP-W500 8.25 kV 33 kA 41 kA 8.25 (33) = 39.5 kA 66 kA


60 1.16 1.26 1.32 6.9
16 65 1.17 1.28 1.33 150VCP-W500 15 kV 18 kA 23 kA 15 (18) (39.1) = 23 kA 37 kA
70 1.19 1.29 1.35 6.9
75 1.20 1.30 1.36 (But not to exceed KI)
17 80 1.21 1.31 1.37
85 — — 1.38 Answer
90 1.22 1.32 1.39
Either breaker could be properly
18 95
100

1.23

1.33
1.40
1.41 applied, but price will make the type
100 1.24 1.34 1.42 150VCP-W500 the more economical
selection.
19 120
130
1.24
1.24
1.35
1.35
1.43
1.43
1 Where system X/R ratio is 15 or less, the
multiplying factor is 1.0.
20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-11
August 2017 Power System Analysis
Sheet 01 051

Example 3—Fault Calculations Medium-Voltage Fuses— i


Check breaker application or generator bus for the system of generators shown.
Fault Calculations
Each generator is 7.5 MVA, 4.16 kV 1040 A full load, IB = 1.04 kA
There are two basic types of medium ii
Sub transient reactance Xd” = 11% or, X = 0.11 pu voltage fuses. The following definitions
are taken from ANSI Standard C37.40.
Gen X
----- ratio is 30 1
R Expulsion Fuse (Unit)
A vented fuse (unit) in which the
1 1 1 1 3 1 1 1 1 3 expulsion effect of the gases produced 2
         and         
XS X X X X RS R R R R by internal arcing, either alone or aided
by other mechanisms, results in current
interruption. 3
XS X-
or XS  X
----- and R S  ---- Therefore, System ---------  ----
R  Gen X
-----  30 Current-Limiting Fuse (Unit)
3 3 RS R R
A fuse unit that, when its current-
responsive element is melted by a
4
Since generator neutral grounding reactors are used to limit the ILG to I3-phase or
below, we need only check the I3 short-circuit duty. current within the fuse’s specified
current-limiting range, abruptly 5
introduces a high resistance to
I B I B I B 31B 3(1.04)
IB Phase  -----
- + ------ + ------ + ------------  -----------------------  28.4 kA Symmetrical E/X amperes reduce current magnitude and
X X X X 0.11 duration, resulting in subsequent
current interruption.
6
X
System ----- of 30 is a Multiplying Factor of 1.04 from Table 1.4-6. There are two classes of fuses;
R 7
power and distribution. They are
Short-circuit duty is 28.4 (1.04) = 29.5 kA Symmetrical distinguished from each other by
the current ratings and minimum
Three-Phase Symmetrical Interrupting Capability melting type characteristics. 8
Breaker Type V Max. at V Max. Max. KI at 4.16 kV Oper. Voltage
The current-limiting ability of a
50VCP-W250 4.76 kV 29 kA 36 kA 4.76
4.16
(29) = 33.2 kA current-limiting fuse is specified by 9
its threshold ratio, peak let-through
Answer current and I2t characteristics.
Interrupting Ratings of Fuses
10
The 50VCP-W250 breaker could be applied. The use of a specific generator circuit
breaker such as the Eaton VCP-WG should also be investigated. Modern fuses are rated in amperes
rms symmetrical. They also have a 11
listed asymmetrical rms rating that
is 1.6 x the symmetrical rating.
Refer to ANSI/IEEE C37.48 for fuse
12
interrupting duty guidelines.
Calculation of the Fuse Required 13
Interrupting Rating:
Step 1—Convert the fault from
G1 G2 G3 the utility to percent or per unit on
14
a convenient voltage and kVA base.
Step 2—Collect the X and R data of all 15
the other circuit elements and convert
to a percent or per unit on a conve-
nient kVA and voltage base same as 16
4.16 kV that used in Step 1. Use the substran-
sient X and R for all generators and
motors. 17
Step 3—Construct the sequence
networks using reactances and connect 18
properly for the type of fault under
consideration and reduce to a single
Figure 1.4-8. Example 3—One-Line Diagram equivalent reactance. 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-12 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 052

i
Step 4—Construct the sequence Low-Voltage Power Circuit The multiplying factor MF can be
calculated by the formula:
networks using resistances and
connect properly for the type of Breakers—Fault Calculations
–      X/R 
fault under consideration and reduce 2  1  2.718 
ii to a single equivalent resistance. The steps for calculating the fault MF  
current for the selection of a low 2.29
Step 5—Calculate the E/XI value, voltage power circuit breaker are If the X/R of system feeding the
1 where E is the prefault value of the the same as those used for medium breaker is not known, use X/R = 15.
voltage at the point of fault normally voltage circuit breakers except that
assumed 1.0 in pu. For three-phase where the connected loads to the low For fused breakers by the formula:
2 faults E/XI is the fault current to be voltage bus includes induction and
synchronous motor loads. –  2    X/R 
used in determining the required 1  2   2.718 
interrupting capability of the fuse. MF  
The assumption is made that in 1.25
3 Note: It is not necessary to calculate a 208Y/120 V systems the contribution If the X/R of the system feeding the
single phase-to-phase fault current. This from motors is two times the full load breaker is not known, use X/R = 20.
current is very nearly 3 /2 x three-phase current of the step-down transformer.
4 fault. The line-to-ground fault may exceed This corresponds to an assumed 50% Refer to Table 1.4-8 for the standard
the three-phase fault for fuses located in motor aggregate impedance on a kVA ranges of X/R and power factors used in
generating stations with solidly grounded base equal to the transformer kVA testing and rating low voltage breakers.
5 neutral generators, or in delta-wye trans-
formers with the wye solidly grounded,
rating or 50% motor load. Refer to Table 1.4-9 for the circuit
where the sum of the positive and negative breaker interrupting rating derating
For 480 V, 480Y/277 V and 600 V sys- factors to be used when the calculated
sequence impedances on the high voltage
6 side (delta) is smaller than the impedance of
tems, the assumption is made that the X/R ratio or power factor at the point
the transformer. contribution from the motors is four the breaker is to be applied in the
times the full load current of the step- power distribution system falls outside
7 For single line-to-ground fault: down transformer, which corresponds of the X/R or power factors used in test-
to an assumed 25% aggregate motor
X I  XI (+) + X I (–) + X I (0) impedance on a kVA base equal to
ing and rating the circuit breakers. The
derating factors shown in Table 1.4-9
8 the transformer kVA rating or 100% are the inverse of the MF (multiplying
E motor load. factors) calculated above. These derat-
If  -------  3
XI In low voltage systems that contain ing factors are applied to the nameplate
9 generators, the subtransient reactance interrupting rating of the breaker to
Step 6—Select a fuse whose should be used. indicate the device’s interrupting
published interrupting rating capacity at the elevated X/R ratio.
10 exceeds the calculated fault current. The X/R ratio is calculated in the same
manner as that for medium-voltage
Figure 1.4-2 should be used where circuit breakers. If the X/R at the point
11 older fuses asymmetrically rated are of fault is greater than 6.6, a multiply-
involved. ing factor (MF) must be applied.

12 The voltage rating of power fuses used The calculated symmetrical amperes
should be multiplied by the multiply-
on three-phase systems should equal
or exceed the maximum line-to-line ing factor (MF) and compared to the
13 voltage rating of the system. Current nameplate rating to ensure the breaker
is applied within its rating.
limiting fuses for three-phase systems
should be so applied that the fuse
14 voltage rating is equal to or less than
1.41 x nominal system voltage.

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-13
August 2017 Power System Analysis
Sheet 01 053

Molded-Case Breakers and Low-Voltage Circuit Breaker i


Insulated Case Circuit Interrupting Derating Factors
Breakers—Fault Calculations Refer to Table 1.4-8 for the standard Established standard values include ii
ranges of X/R and power factors the following:
The method of fault calculation is the
used in testing and rating low voltage
same as that for low voltage power Table 1.4-8. Standard Test Power Factors
circuit breakers. The calculated fault
breakers. Refer to Table 1.4-9 for 1
the circuit breaker interrupting rating Interrupting Power Factor X/R Test
current times the MF must be less than Rating in kA Test Range Range
de-rating factors to be used when the
the breaker interrupting capacity.
Because molded case breakers are
calculated X/R ratio or power factor Molded-Case Circuit Breaker 2
at the point the breaker is to be applied 10 or Less 0.45–0.50 1.98–1.73
tested at lower X/R ratios, the MFs are
in the power distribution system falls Over 10 to 20 0.25–0.030 3.87–3.18
different than those for low voltage Over 20 0.15–0.20 6.6–4.9
power circuit breakers.
outside of the Table 1.4-8 X/R or power 3
factors used in testing and rating the Low-Voltage Power Circuit Breaker
X circuit breakers.
–    2
All 0.15 Maximum 6.6 Minimum
1 + 2.718  R 2 Normally the short-circuit power factor 4
MF  ----------------------------------------------------- For distribution systems where the
X1 or X/R ratio of a distribution system
–     calculated short-circuit current X/R
 R 1 need not be considered in applying
1 + 2.718
low voltage circuit breakers. This is
ratio differs from the standard values 5
given in the above table, circuit breaker
X1 / R1 = test X/R value because the ratings established in
interrupting rating derating factors from
the applicable standard are based
on power factor values that amply
Table 1.4-9 table should be applied. 6
X2 / R2 = X/R at point where breaker
is applied cover most applications.
7
Table 1.4-9. Circuit Breaker Interrupting Rating Derating Factors
% P.F. X/R Interrupting Rating
Molded Case or Insulated Case Power Circuit Breaker 8
>10 kA
m/ = 10 kA m/ = 20 kA L20 kA Unfused Fused
9
50 1.73 1.000 1.000 1.000 1.000 1.000
30 3.18 0.847 1.000 1.000 1.000 1.000
25 3.87 0.805 0.950 1.000 1.000 1.000
10
20 4.90 0.762 0.899 1.000 1.000 1.000
15 6.59 0.718 0.847 0.942 1.000 0.939
12 8.27 0.691 0.815 0.907 0.962 0.898
10 9.95 0.673 0.794 0.883 0.937 0.870
11
8.5 11.72 0.659 0.778 0.865 0.918 0.849
7 14.25 0.645 0.761 0.847 0.899 0.827
5 19.97 0.627 0.740 0.823 0.874 0.797
12
Note: These are derating factors applied to the breaker and are the inverse of MF.
13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-14 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 054

i Short-Circuit Calculations
Determination of Short-Circuit Current
ii Note 1: Transformer impedance generally relates to self-ventilated rating (e.g., with ONAN/ONAF/OFAF transformer use OA base).
Note 2: kV refers to line-to-line voltage in kilovolts.
Note 3: Z refers to line-to-neutral impedance of system to fault where R + jX = Z.
1 Note 4: When totaling the components of system Z, arithmetic combining of impedances as “ohms Z”. “per unit Z”. etc., is considered a
shortcut or approximate method; proper combining of impedances (e.g., source, cables transformers, conductors, etc.). should use
individual R and X components. This Total Z = Total R + j Total X (see IEEE “Red Book” Standard No. 141).
2 1. Select convenient kVA base for system to
be studied.
kVA base 2
(a) Per unit = pu impedance kVA base 2 =   (pu impedance on kVA base 1)
3 2. Change per unit, or percent, impedance from
one kVA base to another:
kVA base 1
kVA base 2
(b) Percent = % impedance kVA base 2 =   (% impedance on kVA base 1)
kVA base 1
4 percent impedance = (ohms impedance) (kVA base)
3. Change ohms, or percent or per unit, etc.: (a) Per unit impedance = pu Z =   kV
2 
  1000 
100
5 (ohms impedance) (kVA base)
(b) % impedance = % Z = 
 kV 2
 
 10 
(% impedance)  kV 2 (10)
(c) Ohms impedance = 
6 kVA base

4. Change power-source impedance to per unit (a) —if utility fault capacity given in kVA
7 or percent impedance on kVA base as selected
for this study: kVA base in study
Per-unit impedance = pu Z = ------------------------------------------------------------------------------------------
-
power-source kVA fault capacity
8 (b) —if utility fault capacity given in rms symmetrical short circuit amperes

kVA base in study


Per-unit impedance = pu Z = ---------------------------------------------------------------------------------------------------------------
-
9 (short-circuit current)  3 (kV of source)

5. Change motor rating to kVA: (a) —motor kVA —  3  (kV) (I) where I = motor nameplate full-load amperes

10 (b) —if 1.0 power factor synchronous motorkVA = (0.8) (hp)


(c) —if 0.8 power factor synchronous motorkVA = (1.0) (hp)
(d) —if induction motor kVA = (1.0) (hp)
11 Three-phase kVA Single-phase kVA
6. Determine symmetrical short-circuit current: (a) Base current = I Base =  or 
 3   kV  kV line-to-neutral

12 (b) Per unit I SC = 1.0



pu Z

(c) rms Symmetrical current = ISC = (pu ISC) (IBase Amperes)


13
Three-phase KVA base Single-phase kVA base
(d) rms Symmetrical current = Amperes = ---------------------------------------------------------------- or -----------------------------------------------------------------
 pu Z   3   kV   pu Z   kV 
14 (Three-phase kVA base) (100) Single-phase kVA base (100)
(e) = ----------------------------------------------------------------------------------- or --------------------------------------------------------------------------------
(%Z)  3   kV  (%Z)  kV 

15 (g)
(kV) (1000)
= -----------------------------------
3 (ohms Z)

(a) Symmetrical short-circuit kVA = kVA (kVA base) (100)- =  kV 2  1000 


base- = ---------------------------------------------
16 7. Determine symmetrical short-circuit kVA: -------------------------
 pu Z  %Z
----------------------------------
ohms Z
2
3(line-to-neutral kV)  1000 
(b) = ------------------------------------------------------------------------------
(ohms Z)
17
8. Determine line-to-line short-circuit current: (a) —from three-phase transformer—approx. 86% of three-phase current
(b) —three single-phase transformers (e.g., 75 kVA, Z = 2%) calculate same as one three-phase
18 unit (i.e., 3 x 75 kVA = 225 kVA, Z = 2%).
(c) —from single-phase transformer—see Page 1.4-16.

19 (a) —synchronous motor—5 times motor full load current (impedance 20%)
9. Determine motor contribution (or feedback) as
source of fault current: (b) —induction motor—4 times motor full-load current (impedance 25%) j
See IEEE
Standard No. 141
(c) —motor loads not individually identified, use contribution from group of motors as follows:
20 —on 208Y/120 V systems—2.0 times transformer full-load current
—on 240-480-600 V three-phase, three-wire systems—4.0 times transformer full-load current
—on 480Y/277 V three-phase, four-wire systems
21 —In commercial buildings, 2.0 times transformers full-load current (50% motor load)
—In industrial plants, 4.0 times transformer full-load current (100% motor load)

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-15
August 2017 Power System Analysis
Sheet 01 055

Example Number 1
i
How to Calculate Short-Circuit Currents at Ends of Conductors

A. System Diagram B. Impedance Diagram (Using “Short Cut” Method for Combining Impedances
ii
and Sources).
1
A B C
Utility Source 500 MVA
Utility
Major Contribution
2
Cables
Transformer
Switchboard Fault
3
1000 kV A
5.75%
480V Cables 4
Cable Fault
Switchboard Fault

F1 Zm 5
Zu 0.002 pu Zm 1.00 pu Zm 1.00 pu 1.00 pu
100 ft (30m)
3–350 kcmil Cable
in Steel Conduit Zc Zc
Zc 6
A B C 0.0575 pu 0.027 pu 0.027 pu 0.027 pu
Switchboard Fault Zequiv
Mixed Load—Motors and Lighting
Each Feeder—100 ft (30m) of 3–350 kcmil
F1
7
Cable in Steel Conduit Feeding Lighting and Zc 0.027 pu
250 kVA of Motors
Cable Fault
F2
Cable Fault
F2 8
Combining Series Impedances: ZTOTAL = Z1 + Z2 + ... +Zn
C. Conductor impedance from Table 1.11-6.
Conductors: 3–350 kcmil copper, single Combining Parallel Impedances:
1 =
ZTOTAL
1 + 1 + ... 1
Z1 Z2 Zn
9
conductors Circuit length: 100 ft
(30 m), in steel (magnetic) conduit
Impedance 10
0.0777 pu
Z = 0.0617 ohms/ 1,000 ft (304.8 m). 0.0595 pu 0.342 pu 0.0507 pu
ZTOT = 0.00617 ohms (100 circuit feet) Es
F1 F1
11
D. Fault current calculations (combining 0.027 pu 0.027 pu
impedances arithmetically, using approxi-
mate “Short Cut” method—see Note 4, F2 12
Page 1.4-14)

Equation 13
Step (See) Calculation
1 – Select 1000 kVA as most convenient base, since all data except utility source is on
secondary of 1000 kVA transformer.
14
2 4(a) Zu kVA base - = --------------------
Utility per unit impedance = Z = ------------------------------------------ 1000 - = 0.002 pu
pu
utility fault kVA 500.000

%Z- = 5.75
15
3 3(a) ZT Transformer per unit impedance = Z = --------- ----------- = 0.0575 pu
pu
100 100

4 4(a) and Zm kVA base - = -------------------


Motor contribution per unit impedance = Z pu = --------------------------------------- 1000 - = 1.00 pu 16
9(c) 4 x motor kVA 4 x 250

5 3(a) Zc Cable impedance in ohms (see above) = 0.00619 ohms 17


Cable impedance per unit = Z (ohms)(kVA base) = (0.00619)(1000) = 0.027 pu
= -------------------------------------------------
pu - -------------------------------------------
2 2
(kV) (1000) (0.480) (1000) 18
6 6(d) F1 Total impedance to switchboard fault = 0.0507 pu (see diagram above)

Symmetrical short circuit current at switchboard fault = 3-phase kVA base 1000
 =  = 23,720 amperes rms 19
 Z   3   kV   0.0507   3   0.480 
pu
7 6(d) F2 Total impedance to cable fault = 0.0777 pu (see diagram above)
20
Symmetrical short circuit current at cable fault = 3-phase kVA base 1000
 =  = 15, 480 amperes rms
 Z   3   kV   0.0777   3   0.480 
pu
21
Figure 1.4-9. Example Number 1

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-16 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 056

Example Number 2
i
Fault Calculation—Secondary Side of Single-Phase Transformer
ii A. System Diagram Deriving Transformer R and X:
480 V Three-Phase Switchboard Bus at 50,000 A Symmetrical, X/R = 6.6 { R = 0.1498 Z
X = 0.9887 Z
X
  6.6 X = 6.6 R
1 R

2 2 2 2 2 2 2
Z= X +R =  6.6R  + R = 43.56R + R = 44.56R = 6.6753R
100 Ft. Two #2/0 Copper Conductors, Magnetic Conduit R = 0.0104 Ohms
{
2 X = 0.0051 Ohms
Z
R=  R = 0.1498Z
6.6753
75 kVA Single-Phase 480–120/240 V; Z = 2.8%, R = 1.64%, X = 2.27%
3 X = 6.6R X = 0.9887Z

120 V
4 F2
Half-winding of Transformer
{ Multiply % R by 1.5
Multiply % X by 1.2 } Reference: IEEE Standard No. 141
240 V
F1 Full-winding of Transformer

5 B. Impedance Diagram—Fault F1 C. Impedance Diagram—Fault F2

6 RSyst = 0.00054 XSyst = 0.00356 RSyst = 0.00054 XSyst = 0.00356

RCond = 0.00677 XCond = 0.00332 RCond = 0.00677 XCond = 0.00332

7 RTfmr = 0.0164 XTfmr = 0.0227 RTfmr = 0.0246 XTfmr = 0.0272

RTotal = 0.02371 XTotal = 0.02958 RTotal = 0.03191 XTotal = 0.03408


F1 F1 F2 F2
8
D. Impedance and Fault Current Calculations—75 kVA Base
Note: To account for the outgoing and return paths of single-phase circuits (conductors,
9 systems, etc.) use twice the three-phase values of R and X.
75
ZSyst    0.0018 pu (From Page 1.4-14 RSyst = 2 (0.1498 x ZSYST) = 0.00054 pu
3  0.480  50,000
10 Formula 4(b) )
XSyst = 2 (0.9887 x ZSYST) = 0.00356 pu

ZCond =
ohms  kVA Base
 (From Page 1.4-14 RCond = 2  0.0104  75 
 = 0.00677 pu
2
 kV   1000
 0.48 2  1000
11 Formula 3(a) )
0.0051  75
XCond = 2    = 0.00332 pu
  0.48  2  1000
12 Full-winding of Transformer (75 kVA Base)
1.64
RTfmr =  = 0.0164 pu
100
2.27
XTfmr =  = 0.0277 pu
13 100
1.64
Half-winding of Transformer (75 kVA Base) RTfmr = 1.5    = 0.0246 pu
100
14 2.27
XTfmr = 1.2    = 0.0272 pu
100

15 Impedance to Fault F1—Full Winding Z= 2


 0.02371  +  0.02958 
2 = 0.03791 pu
Impedance to Fault F2—Half Winding
Z= 2 2 = 0.04669 pu
Short circuit current F1 = 75 ÷ (0.03791 x 0.240 kV) = 8,243 A Symmetrical  0.03191  +  0.03408 
16 Short circuit current F2 = 75 ÷ (0.04669 x 0.120 kV) = 13,386 A Symmetrical

Figure 1.4-10. Example Number 2


17
Shortcut Method—End of Cable 277 V/30,000 A = 0.00923 ohms Next, 277 V/0.01196 ohms = 23,160 A
(source impedance) rms at load side of conductors
This method uses the approximation
18 of adding Zs instead of the accurate Conductor ohms for 500 kcmil
method of Rs and Xs. X 30,000 A available
conductor from Table 1.11-6 in
magnetic conduit is 0.00551 ohms 100 ft (30 m)
19 For Example: For a 480/277 V system per 100 ft (30 m). For 100 ft (30 m) and 2–500 kcmil per phase
with 30,000 A symmetrical available two conductors per phase we have:
at the line side of a conductor run of X If = 23,160 A
20 100 ft (30 m) of 2–500 kcmil per phase 0.00551/2 = 0.00273 ohms (conductor
and neutral, the approximate fault current impedance) Figure 1.4-11. Short-Circuit Diagram

21 at the load side end of the conductors Add source and conductor impedance or
can be calculated as follows. 0.00923 + 0.00273 = 0.01196 total ohms

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-17
August 2017 Power System Analysis
Sheet 01 057

Determining X and R Values Voltage Drop Considerations Voltage variation in such areas should
i
be held to 2 or 3% under motor-starting
from Transformer Loss Data The first consideration for voltage or other transient conditions.
drop is that under the steady-state
Method 1: conditions of normal load, the voltage Computer Equipment: With the ii
Given a 500 kVA, 5.5% Z transformer at the utilization equipment must be proliferation of data-processing and
with 9000W total loss; 1700W no-load adequate. Fine-print notes in the NEC computer- or microprocessor-controlled
loss; 7300W load loss and primary recommend sizing feeders and branch manufacturing, the sensitivity of 1
voltage of 480 V. circuits so that the maximum voltage computers to voltage has become an
drop in either does not exceed 3%, important consideration. Severe dips of
Watts Load Loss = 3 x (I2 x R) with the total voltage drop for feeders short duration can cause a computer 2
and branch circuits not to exceed 5%, to “crash”—shut down completely,
2
3     R = 7300 W
500 for efficiency of operation. (Fine print and other voltage transients caused
 3  0.480 notes in the NEC are not mandatory.) by starting and stopping motors can 3
cause data-processing errors. While
R = 0.0067 ohms Local energy codes as well as the voltage drops must be held to a mini-
standards for high performance
0.0067  500 green buildings should be referenced
mum, in many cases computers will 4
%R =  = 1.46% require special power-conditioning
10  0.48
2 to determine any additional project equipment to operate properly.
related voltage drop requirements.
2 2 Industrial Plants: Where large motors
5
%X = 5.5 – 1.46 = 5.30% In addition to steady-state conditions, exist, and unit substation transformers
voltage drop under transient condi- are relatively limited in capacity,
Method 2: 6
tions, with sudden high-current, short- voltage dips of as much as 20% may
Using same values above. time loads, must be considered. The be permissible if they do not occur too
2 most common loads of this type are frequently. Lighting is often supplied
I R Losses 7
%R =  motor inrush currents during starting.
10  kVA from separate transformers, and is
These loads cause a voltage dip on minimally affected by voltage dips in
7300 the system as a result of the voltage the power systems. However, it is
 = 1.46 drop in conductors, transformers and 8
10  500 usually best to limit dips to between
generators under the high current. 5 and 10% at most.
2 2 This voltage dip can have numerous
%X = 5.5 – 1.46 = 5.30%
adverse effects on equipment in the One critical consideration is that 9
system, and equipment and conduc- a large voltage dip can cause a
How to Estimate Short-Circuit tors must be designed and sized to dropout (opening) of magnetic
Currents at Transformer Secondaries: minimize these problems. In many motor contactors and control relays. 10
cases, reduced-voltage starting of The actual dropout voltage varies
Method 1: motors to reduce inrush current considerably among starters of
To obtain three-phase rms symmetrical will be necessary. different manufacturers. 11
short-circuit current available at
transformer secondary terminals, Recommended Limits of The only standard that exists is that of
use the formula: Voltage Variation
NEMA, which states that a starter must 12
not drop out at 85% of its nominal coil
100
ISC = I FLC  ------------ General Illumination: Flicker in voltage, allowing only a 15% dip.
%Z While most starters will tolerate con- 13
incandescent lighting from voltage
where %Z is the transformer impedance dip can be severe; lumen output drops siderably more voltage dip before
in percent, from Tables 1.11-6 through about three times as much as the dropping out, limiting dip to 15% is the
1.11-11, Page 1.11-11. voltage dips. That is, a 10% drop in only way to ensure continuity of oper- 14
voltage will result in a 30% drop in ation in all cases.
This is the maximum three-phase sym- light output. While the lumen output
metrical bolted-fault current, assuming X-Ray Equipment: Medical x-ray and 15
drop in fluorescent lamps is roughly
sustained primary voltage during fault, similar diagnostic equipment, such as
proportional to voltage drop, if the
i.e., an infinite or unlimited primary CAT-scanners, are extremely sensitive
voltage dips about 25%, the lamp will
power source (zero source impedance). go out momentarily and then restrike.
to low voltage. They present a small,
steady load to the system until the
16
Because the power source must
always have some impedance, this For high-intensity discharge (HID) instant the x-ray tube is “fired.” This
is a conservative value; actual fault lamps such as mercury vapor, high- presents a brief but extremely high 17
current will be somewhat less. pressure sodium or metal halide, if the instantaneous momentary load.
lamp goes out because of an excessive
In some modern x-ray equipment,
Note: This will not include motor short-
circuit contribution.
voltage dip, it will not restrike until it
the firing is repeated rapidly to 18
has cooled. This will require several
create multiple images. The voltage
minutes. These lighting flicker effects
Method 2: regulation must be maintained within
can be annoying, and in the case of
the manufacturer’s limits, usually 2 to 19
Refer to Table 1.7-7 in the Reference HID lamps, sometimes serious.
section, and use appropriate row of 3%, under these momentary loads,
In areas where close work is being to ensure proper x-ray exposure.
data based on transformer kVA and
done, such as drafting rooms, precision
20
primary short-circuit current available.
This will yield more accurate results assembly plants, and the like, even
a slight variation, if repeated, can be
and allow for including motor short-
very annoying, and reduce efficiency.
21
circuit contribution.

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-18 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 058

Motor Starting Engine Generator Systems In other words, a NEMA design C motor
i Motor inrush on starting must be limited With an engine generator as the with an autotransformer would have a
source of power, the type of starter starting torque of approximately full-
to minimize voltage dips. Table 1.4-10 load (see Table 1.4-10) whereas the
that will limit the inrush depends on
ii on the next page will help select the
proper type of motor starter for various the characteristics of the generator. NEMA design D motor under the same
Although automatic voltage regulators conditions would have a starting torque
motors, and to select generators of of approximately 1-1/2 times full-load.
are usually used with all AC engine-
1 adequate size to limit voltage dip.
generators, the initial dip in voltage is
See Tab 29 for additional data on Note: If a resistance starter were used for
reduced voltage motor starting. caused by the inherent regulation of the same motor terminal voltage, the
the generator and occurs too rapidly starting torque would be the same as that
2 Utility Systems for the voltage regulator to respond. obtained with autotransformer type, but the
Where the power is supplied by a utility It will occur whether or not a regulator starting current would be higher, as shown.
network, the motor inrush can be is installed.
3 assumed to be small compared to the Shortcut Method
Consequently, the percent of initial
system capacity, and voltage at the voltage drop depends on the ratio of The last column in Table 1.4-10 has
4 source can be assumed to be constant the starting kVA taken by the motor to been worked out to simplify checking.
during motor starting. Voltage dips the generator capacity, the inherent The figures were obtained by using
resulting from motor starting can be regulation of the generator, the the formula above and assuming
5 calculated on the basis of the voltage power-factor of the load thrown on 1 kVA generator capacity and 1%
drop in the conductors between the the generator, and the percentage voltage drop.
power source and the motor resulting load carried by the generator.
6 from the inrush current. Example:
A standard 80% power-factor engine- Assuming a project having a
Where the utility system is limited, the type generator (which would be 1000 kVA generator, where the
utility will often specify the maximum
7 permissible inrush current or the
used where power is to be supplied voltage variation must not exceed
to motor loads) has an inherent 10%. Can a 75 hp, 1750 rpm, 220 V,
maximum hp motor they will permit regulation of approximately 40% three-phase, squirrel-cage motor be
to be started across-the-line.
8 from no-load to full-load. This means started without objectionable lamp
Transformer Considerations that a 50% variation in load would flicker (or 10% voltage drop)?
cause approximately 20% variation
If the power source is a transformer, From tables in the circuit protective
9 and the inrush kVA or current of the
in voltage (50% x 40% = 20%).
devices reference section, the full-load
motor being started is a small portion Assume that a 100 kVA, 80% PF amperes of this size and type of motor
of the full-rated kVA or current of the engine-type generator is supplying is 158 A. To convert to same basis as
10 transformer, the transformer voltage dip the power and that the voltage drop the last column, 158 A must be divided
will be small and may be ignored. As should not exceed 10%. Can a 7-1/2 hp, by the generator capacity and %
the motor inrush becomes a significant 220 V, 1750 rpm, three-phase, squirrel- voltage drop, or:
11 percentage of the transformer full-load cage motor be started without
rating, an estimate of the transformer exceeding this voltage drop? 158 = 0.0158 A per kVA
voltage drop must be added to the 1000 x 10 per 1% voltage drop
12 conductor voltage drop to obtain the Starting current (%F.L.) =
Checking against the table, 0.0158 falls
total voltage drop to the motor.
Percent voltage drop  gen. kVA  1000 within the 0.0170–0.0146 range for a

13 Accurate voltage drop calculation F.L. amperes  volts  3  reg. of gen. NEMA A with an autotransformer
would be complex and depend upon starter. This indicates that a general-
transformer and conductor resistance, From the nameplate data on the motor, purpose motor with autotransformer
14 reactance and impedance, as well as the full-load amperes of a 7-1/2 hp. starting can be used.
motor inrush current and power factor. 220 V, 1750 rpm, three-phase, squirrel- Note: Designers may obtain calculated
However, an approximation can be cage motor is 19.0 A. Therefore: information from engine generator
15 made on the basis of the low power- manufacturers.
factor motor inrush current (30–40%) Starting current (%F.L.) =
and impedance of the transformer. 10  100  1000 The calculation results in conservative
16   3.45 or 345%. results. The engineer should provide
19.0  220  3  0.40
to the engine-generator vendor the
For example, if a 480 V transformer starting kVA of all motors connected
From Table 1.4-10, a NEMA design C or
17 has an impedance of 5%, and the NEMA design B motor with an autotrans- to the generator and their starting
motor inrush current is 25% of the former starter gives approximately this sequence. The engineer should also
transformer full-load current (FLC), starting ratio. It could also be obtained specify the maximum allowable drop.
18 then the worst case voltage drop will from a properly set solid-state adjust- The engineer should request that the
be 0.25 x 5%, or 1.25%. able reduced voltage starter. engine-generator vendor consider the
proper generator size when closed-
19 The allowable motor inrush current is The choice will depend upon the transition autotransformer reduced
determined by the total permissible torque requirements of the load voltage starters, and soft-start solid-
voltage drop in transformer and since the use of an autotransformer state starter are used; so the most
20 conductors. starter reduces the starting torque in economical method of installation
direct proportion to the reduction in is obtained.
starting current.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-19
August 2017 Power System Analysis
Sheet 01 059

Table 1.4-10. Factors Governing Voltage Drop


Type of Starting Starting How Starting Starting Torque per Unit of Full-Load Amperes i
Motor 1 Torque Current 2 Started Current Full Load Torque per kVA Generator
% Full-Load 3 Motor Rpm Capacity for Each

1750 1150 3 850


1% Voltage Drop ii
Design A Normal Normal Across-the-line 600–700 1.5 1.35 1.25 0.0109–.00936
resistance 480–560 ➁ 0.96 0.87 0.80 0.0136–.0117 1
autotransformer 375–450 ➁ 0.96 0.87 0.80 0.0170–.0146
Design B Normal Low Across-the-line 500–600 1.5 1.35 1.25 0.0131–.0109
resistance
autotransformer
400–480 ➁
320–400 ➁
0.96
0.96
0.87
0.87
0.80
0.80
0.0164–.01365
0.0205–.0170
2
Design C High Low Across-the-line 500–600 — 0.2 to 2.5 — 0.0131–.0109
resistance 400–480 ➁ — 1.28 to 1.6 — 0.0164–.01365 3
autotransformer 320–400 ➁ — 1.28 to 1.6 — 0.0205–.0170
Wound Rotor High Low Secondary controller 100% current — — — —
for 100%
torque







0.0655
4
Synchronous (for compressors) Low — Across-the-line 300 40% Starting, 40% Pull-In 0.0218
Synchronous (for centrifugal pumps) Low — Across-the-line 450–550 60% Starting, 110% Pull-In 0.0145–.0118
Autotransformer 288–350 4 38% Starting, 110% Pull-In 0.0228–.0197 5
1 Consult NEMA MG-1 sections 1 and 12 for the exact definition of the design letter.
2 In each case, a solid-state reduced voltage starter can be adjusted and controlled to provide the required inrush current and torque characteristics.
3 Where accuracy is important, request the code letter of the the motor and starting and breakdown torques from the motor vendor. 6
4 Using 80% taps.

Voltage Drop Formulas If the receiving end voltage, load current and power factor 7
(PF) are known.
Approximate Method
Voltage Drop
2
E VD =  E R cos + I R  +  E R sin + IX  – E R
2 8
E VD = IR cos + IX sin
ER is the receiving end voltage. 9
where abbreviations are same as below “Exact Method.” Exact Method 2—If receiving or sending mVA and its power
factor are known at a known sending or receiving voltage.
Exact Methods 10
Voltage drop 2
2 2  ZMVA R 
- + 2ZMVA R cos   –  R 
E S = E R + ---------------------------------
Exact Method 1—If sending end voltage and load PF
ER
2 11
are known.
or
2
E VD = E S + IR cos + IX sin – E S –  IX cos – IR sin 
2
12
2
2 2  ZMVA R 
ER = - – 2ZMVA S cos   –  S 
E S + ---------------------------------
where: 2
ES 13
EVD = Voltage drop, line-to-neutral, volts
where:
ES = Source voltage, line-to-neutral, volts
ER = Receiving line-line voltage in kV
14
I = Line (Load) current, amperes
ES = Sending line-line voltage in kV
R = Circuit (branch, feeder) resistance, ohms 15
MVAR = Receiving three-phase mVA
X = Circuit (branch, feeder) reactance, ohms
MVAS = Sending three-phase mVA
cos = Power factor of load, decimal 16
Z = Impedance between and receiving ends
sin = Reactive factor of load, decimal
 = The angle of impedance Z 17
R = Receiving end PF
S = Sending end PF, positive when lagging 18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-20 Power Distribution Systems
Power System Analysis August 2017
Sheet 01 060

i Voltage Drop Table 1.4-11. Temperature Correction Factors


for Voltage Drop
To select minimum conductor size:
1. Determine maximum desired
Voltage Drop Tables Conductor Percent Correction voltage drop, in volts.
Size Power Factors %
ii Note: Busway voltage drop tables are
100 90 80 70 60
2. Divide voltage drop by
shown in Tab 24 of this catalog. (amperes x circuit feet).
No. 14 to No. 4 5.0 4.7 4.7 4.6 4.6
1 Tables for calculating voltage drop for No. 2 to 3/0 5.0 4.2 3.7 3.5 3.2
3. Multiply by 100.
copper and aluminum conductors, in 4/0 to 500 kcmil 5.0 3.1 2.6 2.3 1.9 4. Find nearest lower voltage drop
either magnetic (steel) or nonmagnetic 600 to 1000 kcmil 5.0 2.6 2.1 1.5 1.3
value in tables, in correct column
2 (aluminum or non-metallic) conduit,
for type of conductor, conduit and
appear on Page 1.4-13. These tables Calculations power factor. Read conductor size
give voltage drop per ampere per
for that value.
3 100 ft (30 m) of circuit length. The To calculate voltage drop:
circuit length is from the beginning 1. Multiply current in amperes by 5. Where this results in an oversized
point to the end point of the circuit the length of the circuit in feet to cable, verify cable lug sizes for
4 regardless of the number of conductors. get ampere-feet. Circuit length is molded case breakers and fusible
the distance from the point of switches. Where lug size available
Tables are based on the following
origin to the load end of the circuit. is exceeded, go to next higher
5 conditions: rating.
1. Three or four single conductors in 2. Divide by 100.
a conduit, random lay. For three- Example:
3. Multiply by proper voltage drop
6 conductor cable, actual voltage
value in tables. Result is voltage A three-phase, four-wire lighting
drop will be approximately the feeder on a 208 V circuit is 250 ft
drop.
same for small conductor sizes (76.2 m) long. The load is 175 A at
7 and high power factors. Actual Example: 90% PF. It is desired to use aluminum
voltage drop will be from 10 to A 460 V, 100 hp motor, running at 80% conductors in aluminum conduit. What
15% lower for larger conductor PF, draws 124 A full-load current. It is size conductor is required to limit the
8 sizes and lower power factors. fed by three 2/0 copper conductors in voltage drop to 2% phase-to-phase?
2
2.Voltage drops are phase-to-phase, steel conduit. The feeder length is 1. VD =   208 = 4.16 V
for three-phase, three-wire or 150 ft (46 m). What is the voltage drop 100
9 three-phase, four-wire 60 Hz in the feeder? What is the percentage
circuits. For other circuits, multiply voltage drop? 2. 4.16
 = 0.0000951
175  250
voltage drop given in the tables by
10 the following correction factors:
1. 124 A x 150 ft (46 m) = 18,600 A-ft
3. 0.0000951  100 = 0.00951
2. Divided by 100 = 186
Three-phase, four-wire, 4. In table, under aluminum conduc-
11 phase-to-neutral x 0.577 3. Table: 2/0 copper, magnetic conduit, tors, nonmagnetic conduit, 90%
Single-phase, two-wire x 1.155 80% PF = 0.0187 PF, the nearest lower value is
Single-phase, three-wire, 186 x 0.0187 = 3.48 V drop 0.0091. Conductor required is
12 phase-to-phase x 1.155 3.48 x 100 = 0.76% drop 500 kcmil. (Size 4/0 THW would
Single-phase, three-wire, 460 have adequate ampacity, but the
phase-to-neutral x 0.577 voltage drop would be excessive.)
13 4. Conclusion: 0.76% voltage drop
3. Voltage drops are for a conductor is very acceptable. (See NEC 2005
temperature of 75 °C. They may be Article 215, which suggests that a
14 used for conductor temperatures voltage drop of 3% or less on a
between 60 °C and 90 °C with feeder is acceptable.)
reasonable accuracy (within ±5%).
15 However, correction factors in
Table 1.4-11 can be applied if
desired. The values in the table are
16 in percent of total voltage drop.
For conductor temperature of 60 °C–
17 SUBTRACT the percentage from
Table 1.4-11.
For conductor temperature of 90 °C–
18 ADD the percentage from Table 1.4-11.

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.4-21
August 2017 Power System Analysis
Sheet 01 061

Table 1.4-12. Voltage Drop—Volts per Ampere per 100 Feet (30 m); Three-Phase, Phase-to-Phase
Conductor Size Magnetic Conduit (Steel) Nonmagnetic Conduit (Aluminum or Nonmetallic) i
AWG Load Power Factor, % Load Power Factor, %
or kcmil
60 70 80 90 100 60 70 80 90 100 ii
Copper Conductors
14 0.3390 0.3910 0.4430 0.4940 0.5410 0.3370 0.3900 0.4410 0.4930 0.5410
12 0.2170 0.2490 0.2810 0.3130 0.3410 0.2150 0.2480 0.2800 0.3120 0.3410 1
10 0.1390 0.1590 0.1790 0.1980 0.2150 0.1370 0.1580 0.1780 0.1970 0.2150
8 0.0905 0.1030 0.1150 0.1260 0.1350 0.0888 0.1010 0.1140 0.1250 0.1350
6
4
0.0595
0.0399
0.0670
0.0443
0.0742
0.0485
0.0809
0.0522
0.0850
0.0534
0.0579
0.0384
0.0656
0.0430
0.0730
0.0473
0.0800
0.0513
0.0849
0.0533
2
2 0.0275 0.0300 0.0323 0.0342 0.0336 0.0260 0.0287 0.0312 0.0333 0.0335
1 0.0233 0.0251 0.0267 0.0279 0.0267 0.0218 0.0238 0.0256 0.0270 0.0266
1/0 0.0198 0.0211 0.0222 0.0229 0.0213 0.0183 0.0198 0.0211 0.0220 0.0211
3
2/0 0.0171 0.0180 0.0187 0.0190 0.0170 0.0156 0.0167 0.0176 0.0181 0.0169
3/0 0.0148 0.0154 0.0158 0.0158 0.0136 0.0134 0.0141 0.0147 0.0149 0.0134
4/0 0.0130 0.0134 0.0136 0.0133 0.0109 0.0116 0.0121 0.0124 0.0124 0.0107 4
250 0.0122 0.0124 0.0124 0.0120 0.0094 0.0107 0.0111 0.0112 0.0110 0.0091
300 0.0111 0.0112 0.0111 0.0106 0.0080 0.0097 0.0099 0.0099 0.0096 0.0077
350 0.0104 0.0104 0.0102 0.0096 0.0069 0.0090 0.0091 0.0091 0.0087 0.0066 5
500 0.0100 0.0091 0.0087 0.0080 0.0053 0.0078 0.0077 0.0075 0.0070 0.0049
600 0.0088 0.0086 0.0082 0.0074 0.0046 0.0074 0.0072 0.0070 0.0064 0.0042
750
1000
0.0084
0.0080
0.0081
0.0077
0.0077
0.0072
0.0069
0.0063
0.0040
0.0035
0.0069
0.0064
0.0067
0.0062
0.0064
0.0058
0.0058
0.0052
0.0035
0.0029
6
Aluminum Conductors
12 0.3296 0.3811 0.4349 0.4848 0.5330 0.3312 0.3802 0.4328 0.4848 0.5331 7
10 0.2133 0.2429 0.2741 0.3180 0.3363 0.2090 0.2410 0.2740 0.3052 0.3363
8 0.1305 0.1552 0.1758 0.1951 0.2106 0.1286 0.1534 0.1745 0.1933 0.2115
6 0.0898 0.1018 0.1142 0.1254 0.1349 0.0887 0.1011 0.1127 0.1249 0.1361 8
4 0.0595 0.0660 0.0747 0.0809 0.0862 0.0583 0.0654 0.0719 0.0800 0.0849
2 0.0403 0.0443 0.0483 0.0523 0.0535 0.0389 0.0435 0.0473 0.0514 0.0544
1 0.0332 0.0357 0.0396 0.0423 0.0428 0.0318 0.0349 0.0391 0.0411 0.0428
1/0 0.0286 0.0305 0.0334 0.0350 0.0341 0.0263 0.0287 0.0322 0.0337 0.0339
9
2/0 0.0234 0.0246 0.0275 0.0284 0.0274 0.0227 0.0244 0.0264 0.0274 0.0273
3/0 0.0209 0.0220 0.0231 0.0241 0.0217 0.0160 0.0171 0.0218 0.0233 0.0222
4/0 0.0172 0.0174 0.0179 0.0177 0.0170 0.0152 0.0159 0.0171 0.0179 0.0172 10
250 0.0158 0.0163 0.0162 0.0159 0.0145 0.0138 0.0144 0.0147 0.0155 0.0138
300 0.0137 0.0139 0.0143 0.0144 0.0122 0.0126 0.0128 0.0133 0.0132 0.0125
350 0.0130 0.0133 0.0128 0.0131 0.0100 0.0122 0.0123 0.0119 0.0120 0.0101 11
500 0.0112 0.0111 0.0114 0.0099 0.0076 0.0093 0.0094 0.0094 0.0091 0.0072
600 0.0101 0.0106 0.0097 0.0090 0.0063 0.0084 0.0085 0.0085 0.0081 0.0060
750 0.0095 0.0094 0.0090 0.0084 0.0056 0.0081 0.0080 0.0078 0.0072 0.0051 12
1000 0.0085 0.0082 0.0078 0.0071 0.0043 0.0069 0.0068 0.0065 0.0058 0.0038

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.4-22 Power Distribution Systems
August 2017
Sheet 01 062

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-1
August 2017 System Protection Considerations
Sheet 01 063

Overcurrent Protection To study and accomplish ■ Understanding of operating charac-


coordination requires: teristics and available adjustments i
and Coordination of each protective device
■ A one-line diagram, the roadmap
■ Any special overcurrent protection
Overcurrents in a power distribution of the power distribution system, ii
system can occur as a result of both showing all protective devices and requirements including utility
normal (motor starting, transformer the major or important distribution limitations; refer to Figure 1.5-1
inrush, etc.) and abnormal (overloads, and utilization apparatus To ensure complete coordination, the 1
ground fault, line-to-line fault, etc.) ■ Identification of desired degrees time-trip characteristics of all devices
conditions. In either case, the funda- of power continuity or criticality of in series should be plotted on a single
mental purposes of current-sensing loads throughout system sheet of standard log-log paper. 2
protective devices are to detect the Devices of different-voltage systems
■ Definition of operating-current
abnormal overcurrent and with proper can be plotted on the same sheet by
characteristics (normal, peak,
coordination, to operate selectively
starting) of each utilization circuit converting their current scales, using 3
to protect equipment, property the voltage ratios, to the same voltage-
and personnel while minimizing the ■ Equipment damage or withstand
characteristics basis. Such a coordination plot is
outage of the remainder of the system.
■ Calculation of maximum short-
shown in Figure 1.5-1. 4
With the increase in electric power circuit currents (and ground fault
consumption over the past few decades,
dependence on the continued supply of
currents if ground fault protection 5
is included) available at each
this power has also increased so that the protective device location
direct costs of power outages have risen
significantly. Power outages can create
6
dangerous and unsafe conditions as a SCALE X 100 = CURRENT IN AMPERES AT 480V
result of failure of lighting, elevators,

10,000
7

1000

2000

3000

4000
5000
6000
7000
8000
9000
100

200

300

400
500
600
700
800
900
70
80
90
.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60
ventilation, fire pumps, security 1000
900
800 4.16 kV 250 MVA
1000
900
800
systems, communications systems, 700
600
700
600

and the like. In addition, economic loss


from outages can be extremely high
500
400
500
400 8
300 B 300
as a result of computer downtime, or, A D
200 200
especially in industrial process plants,
interruption of production.
C
9
D
100
90
250A 100
90
Protective equipment must be 80 1000 80

adjusted and maintained in order


70
60
50
kVA
5.75%
4,160V Δ
480/277V
70
60
50
10
to function properly when an over- 40
ANSI Three-Phase 19,600A 40

current occurs. Coordination, however, 30 Thru Fault 30

begins during power system design 20


Protection Curve
(More Than 10 in C 1,600A 20
11
Lifetime)
with the knowledgeable analysis and
selection and application of each over- B 24,400A

current protective device in the series


10
9
8
7
600A
10
9
8
7
12
M
circuit from the power source(s) to

TIME IN SECONDS
TIME IN SECONDS

6 6
5 5
each load apparatus. 20,000A
13
4 4

3 3

The objective of coordination is to A 175A


2 B C 2
localize the overcurrent disturbance
so that the protective device closest 14
to the fault on the power-source side 1
.9
.8 100 hp –
1
.9
.8
has the first chance to operate. Each .7
.6
M 124A FLC .7
.6

preceding protective device upstream .5


.4 X = Available fault current
.5
.4
15
toward the power source should be .3
including motor
contribution. .3
capable, within its designed settings Ground
of current and time, to provide backup .2 Fault Trip
C
.2
16
and de-energize the circuit if the fault
persists. Sensitivity of coordination is .1
.09
.1
.09

the degree to which the protective


.08
.07
.06
B
Transformer
.08
.07
.06
17
devices can minimize the damage .05 Inrush .05
Max. Three-Phase

.04 .04
to the faulted equipment.
18
4.16 kV Fault

.03 .03

A
480V Fault

.02 .02
Max.

.01 .01 19
70
80
90
100

200

300

400
500
600
700
800
900
1000

2000

3000

4000
5000
6000
7000
8000
9000
10,000

.5 .6 .7 .8 .9 1 2 3 4 5 6 7 8 9 10 20 30 40 50 60

SCALE X 100 = CURRENT IN AMPERES AT 480V

Figure 1.5-1. Time-Current Characteristic Curves for Typical Power Distribution System 20
Protective Devices Coordination Analysis

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-2 Power Distribution Systems
System Protection Considerations August 2017
Sheet 01 064
Protection and Coordination

In this manner, primary fuses and However, the primary (high voltage) If perfect coordination is not feasible,
i circuit breaker relays on the primary side fault is the same as if the secondary then lack of coordination should be
side of a substation transformer can fault was a three-phase fault. limited to the smallest part of the system.
be coordinated with the low voltage
ii breakers. Transformer damage points, Therefore in coordination studies, the Application data is available for all
based on ANSI standards, and low knee of the short-time pickup setting protective equipment to permit systems
voltage cable heating limits can also on the secondary breaker should be to be designed for adequate overcurrent
1 be plotted on this set of curves to multiplied by protection and coordination.
ensure that apparatus limitations are ■ For circuit breakers of all types, time-
not exceeded. 1 or 1.1547
0.866 current curves permit selection of
2 instantaneous and inverse-time trips
Ground-fault curves may also be before it is compared to the minimum
included in the coordination study ■ For more complex circuit breakers,
melting time of the upstream primary
3 if ground-fault protection is provided, with solid-state trip units, trip curves
fuse curve. In the example shown,
but care must be used in interpreting include long- and short-time delays,
the knee is at 4000 A 30 sec., and the
their meaning. as well as ground-fault tripping,
30-sec. trip time should be compared to
4 with a wide range of settings and
Standard definitions have been the MMT (minimum melt time) of the
features to provide selectivity and
established for overcurrent protective fuse curve at 4000 x 1.1547 = 4619 A.
coordination
devices covering ratings, operation In this case, there is adequate clearance
5 and application systems. Referring to the fuse curve. ■ For current-limiting circuit breakers,
fuses, and circuit breakers with
to Figure 1.5-1, the Single Line In the example shown, the ANSI integral fuses, not only are time-
Diagram references the below
6 defined equipment.
three-phase through fault transformer current characteristic curves
protection curve must be multiplied available, but also data on current-
M—Motor (100 hp). Dashed line shows by 0.577 and replotted in order to limiting performance and protection
7 initial inrush current, starting current determine the protection given by for downstream devices
during 9-sec. acceleration, and drop to the primary for a single line to ground
fault in the secondary. In a fully rated system, all circuit
124 A normal running current, all well breakers must have an interrupting
8 below CBA trip curve. Maximum 480 V three-phase fault capacity adequate for the maximum
A—CB (175 A) coordinates selectively indicated on the horizontal current axis. available fault current at their point of
9 with motor M on starting and running application. All breakers are equipped
Maximum 4160 V three-phase fault with long-time-delay (and possibly
and with all upstream devices, except indicated, converted to 480 V basis.
that CB B will trip first on low level short delay) and instantaneous over-
10 ground faults. 4160 current trip devices. A main breaker
I 480V  I 4160V   may have short time-delay tripping to
480
B—CB (600 A) coordinates selectively allow a feeder breaker to isolate the
with all upstream and downstream
11 devices, except will trip before A on
The ANSI protection curves are fault while power is maintained to all
specified in ANSI C57.109 for liquid- the remaining feeders.
limited ground faults, since A has no filled transformers and C57.12.59 for
ground fault trips. A selective or fully coordinated system
12 dry-type transformers.
permits maximum service continuity.
C—Main CB (1600 A) coordinates Illustrative examples such as shown The tripping characteristics of each
selectively with all downstream here start the coordination study from overcurrent device in the system must
13 devices and with primary fuse D, the lowest rated device proceeding be selected and set so that the breaker
for all faults on load side of CB. upstream. In practice, the setting or nearest the fault opens to isolate the
rating of the utility’s protective device faulted circuit, while all other breakers
14 D—Primary fuse (250 A, 4160 V) coor-
sets the upper limit. Even in cases remain closed, continuing power to
dinates selectively with all secondary
where the customer owns the medium the entire unfaulted part of the system.
protective devices. Curve converted to
voltage or higher distribution system,
15 480 V basis. Clears transformer inrush
the setting or rating of the lowest set The 2014 edition of the National
point (12 x FLC for 0.1 sec.), indicating Electrical Code contains specific
that fuse will not blow on inrush. protective device at the source deter-
mines the settings of the downstream requirements for designing certain
16 Fuse is underneath right-half of ANSI
devices and the coordination. circuits with selective coordination.
three-phase withstand curve, indicating Article 100 defines selective coordina-
fuse will protect transformer for high- Therefore the coordination study tion: Coordination (Selective), the
17 magnitude faults up to ANSI rating. should start at the present setting following definition: “Localization of
or rating of the upstream device and an overcurrent condition to restrict
Delta-wye transformer secondary
work toward the lowest rated device. If outages to the circuit or equipment
18 side short circuit is not reflected to
this procedure results in unacceptable affected, accomplished by the selec-
the primary by the following relation
settings, the setting or rating of the tion and installation of overcurrent
for L-L and L-G faults.
upstream device should be reviewed. protective devices and their ratings or
19 VS Where the utility is the sole source, settings for the full range of available
I P    I S they should be consulted. Where the overcurrents, from overload to the
VP
owner has its own medium or higher maximum available fault current,
20 voltage distribution, the settings or and for the full range of overcurrent
For line-to-line fault, the secondary protective device opening times
ratings of all upstream devices should
(low voltage) side fault current is associated with those overcurrents.”
be checked.
21 0.866 x I three-phase fault current.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-3
August 2017 System Protection Considerations
Sheet 01 065
Protection and Coordination

Article 620.62 (elevators, dumbwaiters, In general for systems such as shown B. Devices Rated 800 A or Less. The
escalators, moving walks, wheelchair in Figure 1.5-1: next higher standard overcurrent i
lifts, and stairway chair lifts) requires device rating (above the ampacity
“Where more than one driving machine 1. The settings or ratings of the of the conductors being protected)
disconnecting means is supplied by a transformer primary side fuse shall be permitted to be used, ii
single feeder, the overcurrent protective and main breaker must not provided all of the following
devices in each disconnecting means exceed the settings allowed by conditions are met.
shall be selectively coordinated with NEC Article 450. 1
any other supply side overcurrent 1. The conductors being protected
2. At 12 x IFL the minimum melting are not part of a branch circuit
protective device.” A similar require- time characteristic of the fuse
ment under Article 700.28 is as follows; should be higher than 0.1 second.
supplying more than one receptacle 2
“Emergency system(s) overcurrent for cord-and-plug-connected
devices shall be selectively coordinated 3. The primary fuse should be to the portable loads.
with all supply side overcurrent left of the transformer damage 2. The ampacity of the conductors 3
protective devices.” Article 701.27 curve as much as possible. The does not correspond with the
states that “Legally required standby correction factor for a single line- standard ampere rating of a fuse or
system(s) overcurrent devices shall be to-ground factor must be applied a circuit breaker without overload 4
selectively coordinated with all supply to the damage curve. trip adjustments above its rating
side overcurrent devices.” (but that shall be permitted to have
4. The setting of the short-time delay
other trip or rating adjustments).
5
Exception: Selective coordination element must be checked against
shall not be required between two the fuse Minimum Melt Time 3. The next higher standard rating
overcurrent devices located in series (MMT) after it is corrected for selected does not exceed 800 A. 6
if no loads are connected in parallel line-to-line faults.
with the downstream device. C. Overcurrent Devices Rated Over
5. The maximum fault current must
In addition, for healthcare facilities, be indicated at the load side of
800 A. Where the overcurrent 7
device is rated over 800 A, the
Article 517.26, Application of Other each protective device. ampacity of the conductors it
Articles requires that “The life safety
branch of the essential electrical
6. The setting of a feeder protective protects shall be equal to or 8
device must comply with Article greater than the rating of the
system shall meet the requirements overcurrent device as defined in
240 and Article 430 of the NEC.
of Article 700, except as amended by Section 240.6. 9
It also must allow the starting
Article 517.“
and acceleration of the largest D. Small Conductors. Unless
All Overcurrent Protective Devices motor on the feeder while carrying specifically permitted in 240.4(E)
must have an interrupting capacity all the other loads on the feeder. or 240.4(G), the overcurrent
10
not less than the maximum available protection shall not exceed 15 A
short-circuit current at their point Protection of Conductors (Excerpts for 14 AWG, 20 A for 12 AWG, and
of application. A selective system from NFPA 70-2014, Article 240.4) 30 A for 10 AWG copper; or 15 A
11
is a fully rated system with tripping for 12 AWG and 25 A for 10 AWG
devices chosen and adjusted to Conductors, other than flexible cords
and fixture wires, shall be protected aluminum and copper-clad 12
provide the desired selectivity. aluminum after any correction
against overcurrent in accordance with
The tripping characteristics of each their ampacities as specified in Section factors for ambient temperature
overcurrent device should not over- 310.15, unless otherwise permitted or and number of conductors have 13
lap, but should maintain a minimum required in 240.4 (A) through (G). been applied.
time interval for devices in series (to E. Tap Conductors. Tap conductors
allow for normal operating tolerances) A. Power Loss Hazard. Conductor 14
overload protection shall not be shall be permitted to be protected
at all current values. Generally, a against overcurrent in accordance
maximum of four low voltage circuit required where the interruption of
with the following:
breakers can be operated selectively the circuit would create a hazard,
such as in a material handling
15
in series, with the feeder or branch 1. 210.19(A)(3) and (A)(4) Household
breaker downstream furthest from magnet circuit or fire pump circuit. Ranges and Cooking Appliances
the source. Short-circuit protection shall be and Other Loads. 16
provided.
Specify true rms sensing devices in 2. 240.5(B)(2) Fixture Wire.
Note: FPN See NFPA 20-2013, standard
order to avoid false trips due to rapid
for the Installation of Stationary Pumps 3. 240.21 Location in Circuit. 17
currents or spikes. Specify tripping for Fire Protection.
elements with I2t or I4t feature for 4. 368.17(B) Reduction in Ampacity
improved coordination with other Size of Busway. 18
devices having I2t or I4t characteristics
and fuses. 5. 368.17(C) Feeder or Branch Circuits
(busway taps).
19
6. 430.53(D) Single Motor Taps.

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-4 Power Distribution Systems
System Protection Considerations August 2017
Sheet 01 066
Protection and Coordination

Circuit Breaker Cable The maximum allowable settings are: For low-voltage systems with high-
i Temperature Ratings 1200 A pickup, 1 second or less trip magnitude available short-circuit
delay at currents of 3000 A or greater. currents, common in urban areas and
UL listed circuit breakers rated 125 A or large industrial installations, several
ii less shall be marked as being suitable The characteristics of the ground-fault solutions are available:
for 60 ºC (140 ºF), 75 ºC (167 ºF) only or trip elements create coordination
60/75 ºC (140/167 ºF) wire. All Eaton problems with downstream devices ■ High interrupting molded-case
1 breakers rated 125 A or less are marked not equipped with ground fault breakers
60/75 ºC (140/167 ºF). All UL listed circuit protection. The National Electrical ■ Current-limiting circuit breakers
breakers rated over 125 A are suitable Code exempts fire pumps and or current-limiting fuses
2 for 75 ºC conductors. continuous industrial processes ■ Limiters integral with molded-case
from this requirement. circuit breakers (TRI-PAC®)
Conductors rated for higher tempera-
The NEC has addressed the concern ■ MDS-L power circuit breakers
3 tures may be used, but must not be
that the impedance added by a with integral current-limiting
loaded to carry more current than the
75 ºC ampacity of that size conductor step-up, step-down or isolation fuses or MDS-X without current-
transformer causes the primary limiting fuses
4 for equipment marked or rated 75 ºC
side ground fault protection to be
or the 60 ºC ampacity of that size To provide current limiting, these
conductor for equipment marked or desensitized to faults on its secondary
side. Consequently, Article 215.10 devices must clear the fault completely
5 rated 60 ºC. However, when applying
clarifies the need for equipment within the first half-cycle, limiting the
derated factors, so long as the actual peak current (Ip) and heat energy (I2t)
load does not exceed the lower of the ground fault protection on 1000 A
and above 480 Vac feeder circuit let-through to considerably less than
6 derated ampacity or the 75 ºC or 60 ºC
disconnects on the secondary of what would have occurred without
ampacity that applies. the device.
these transformers. Article 210.13 has
been added to the 2014 NEC, which
7 Zone Selective Interlocking
recognized the same need for branch
For a fully fusible system, rule-of-
thumb fuse ratios or more accurate
Trip elements equipped with zone circuits being fed by transformers, I2t curves can be used to provide
selective interlocking, trip without as for feeder circuits outlined in
8 intentional time delay unless a Article 215.10.
selectivity and coordination. For fuse-
breaker combinations, the fuse should
restraint signal is received from
It is recommended that in solidly be selected (coordinated) so as to
a protective device downstream.
9 Breakers equipped with this feature grounded 480/277 V systems where permit the breaker to handle those
main breakers are specified to be overloads and faults within its capacity;
reduce the damage at the point of
equipped with ground fault trip elements the fuse should operate before or
fault if the fault occurs at a location
10 within the zone of protection. that the feeder breakers be specified with the current breaker only on large
to be equipped with ground fault trip faults, approaching the current
The upstream breaker upon receipt elements as well. interrupting capacity of the breaker,
11 of the restraint signal will not trip until to minimize fuse blowing.
its time-delay setting times out. If the Suggested Ground Fault Settings The three-pole FDCE breakers include
breaker immediately downstream of the
a Digitrip 310+ electronic trip unit
12 fault does not open, then after timing For the main devices:
and are available in three models
out, the upstream breaker will trip. A ground fault pickup setting equal
covering loads from 15 A through
to 20–30% of the main breaker rating
13 Breakers equipped with ground fault 225 A. Optional equipment ground
but not to exceed 1200 A, and a time
trip elements should also be specified fault allows the designer to extend
delay equal to the delay of the short-
to include zone interlocking for the protection to smaller loads that are
time element, but not to exceed
14 ground fault trip element. more likely to cause a ground fault
1 second.
trip, such as motors or lighting. Zone
Ground Fault Protection For the feeder ground fault setting: Selective Interlocking is also available
15 A setting equal to 20–30% of the feeder to ensure coordinated tripping with
Article 230.95 of NEC requires ground-
ampacity and a time delay to coordinate upstream breakers.
fault protection of equipment shall be
provided for solidly grounded wye with the setting of the main (at least
The Series G high performance,
16 electrical services of more than 150 V 6 cycles below the main).
current-limiting circuit breaker series
to ground, but not exceeding 600 V If the desire to selectively coordinate offers interrupting ratings to 200 kA.
phase-to-phase for each service ground fault devices results in settings Frames are EGC, JGC and LGU.
17 disconnect rated 1000 A or more. that do not offer adequate damage
The rating of the service disconnect protection against arcing single line-
ground faults, the design engineer
18 shall be considered to be the rating
should decide between coordination
of the largest fuse that can be installed
or the highest continuous current trip and damage limitation.
19 setting for which the actual overcurrent
device installed in a circuit breaker is
rated or can be adjusted.
20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.5-5
August 2017 System Protection Considerations
Sheet 01 067
Protection and Coordination

Any of these current-limiting devices— The 2014 National Electrical Code Arc Flash Considerations
fuses, fused breakers or current-limit- (NEC) included new marking require-
The Arcflash Reduction Maintenance
i
ing breakers—cannot only clear these ments for electrical equipment.
large faults safely, but also will limit Article 110.24 applies to service System™ is available on power circuit
the Ip and I2t let-through significantly equipment in other than dwelling breakers, insulated-case circuit breakers ii
to prevent damage to apparatus units and mandates that they “shall and molded-case circuit breakers. The
downstream, extending their zone be legibly marked in the field with the trip units have maintenance settings of
of protection. Without the current maximum available fault current. 2.5 to 4 times the current setting. These 1
limitation of the upstream device, The field marking(s) shall include the breakers deliver faster clearing times
the fault current could exceed the date the fault-current calculation than standard instantaneous trip
withstand capability of the down- was performed and be of sufficient by eliminating the microprocessor 2
stream equipment. durability to withstand the environ- processing latencies. This system
ment involved.” Article 110.24 (B) is superior to simply reducing the
Underwriters Laboratories tests requires that: “When modifications instantaneous setting and results in 3
and lists these series combinations. to the electrical installation occur arc energy reduction that can allow
Application information is available for that affect the maximum available for reduced PPE, improving worker
combinations that have been tested fault current at the service, the dexterity and mobility. The system can 4
and UL®-listed for safe operation. maximum available fault current also include a remote activation switch
shall be verified or recalculated as with status indicator.
Protective devices in electrical
distribution systems may be properly necessary. The required field NEC 2014 240.87 requires Arc Energy 5
coordinated when the systems are marking(s) in 110.24 (A) shall be Reduction “Where the highest continu-
designed and built, but that is no adjusted to reflect the new level of ous current trip setting for which the
guarantee that they will remain maximum available fault current.” actual overcurrent device installed
6
coordinated. System changes and Consequently, periodic study of in a circuit breaker is rated or can be
additions, plus power source changes, adjusted is 1200 A or higher, 240.87(A)
frequently modify the protection
protective-device settings and
and (B) shall apply.
7
ratings is as important for safety
requirements, sometimes causing loss and preventing power outages
of coordination and even increasing A. Documentation shall be available
fault currents beyond the ratings of
as is periodic maintenance of the to those authorized to design, 8
distribution system. install, operate or inspect the
some devices.
In addition, NFPA 70E 130.3 requires installation as to the location
the study be reviewed periodically, of the circuit breaker(s). 9
but not less than every 5 years, to B. Method to Reduce Clearing
account for changes in the electrical Time. One of the following or 10
distribution system that could affect approved equivalent means
the original arc-flash analysis. shall be provided:
1. Zone-selective interlocking
11
2. Differential relaying
12
3. Energy-reducing maintenance
switching with local status
indicator 13
4. Energy-reducing active arc flash
mitigation system
14
5. An approved equivalent
means”
15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.5-6 Power Distribution Systems
August 2017
Sheet 01 068

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.6-1
August 2017 Grounding/Ground Fault Protection
Sheet 01 069

Grounding such an object while grounded could The equipment grounding system
i
be seriously injured or killed. In addi- must be bonded to the grounding
Grounding encompasses several tion, current flow from the accidental electrode at the source or service;
different but interrelated aspects of grounding of an energized part of the however, it may be also connected
electrical distribution system design system could generate sufficient heat to ground at many other points. ii
and construction, all of which are (often with arcing) to start a fire. This will not cause problems with
essential to the safety and proper the safe operation of the electrical
operation of the system and equip-
To prevent the establishment of distribution system. 1
such unsafe potential difference
ment supplied by it. Among these
requires that: Where computers, data processing,
are: equipment grounding, system
grounding, static and lightning ■ The equipment grounding
or microprocessor-based industrial 2
process control systems are installed,
protection, and connection to earth conductor provide a return path the equipment grounding system must
as a reference (zero) potential. for ground fault currents of
sufficiently low impedance to
be designed to minimize interference 3
with their proper operation. Often,
1. Equipment Grounding prevent unsafe voltage drop isolated grounding of this equipment,
Equipment grounding is essential ■ The equipment grounding or isolated electrical supply systems are 4
to safety of personnel. Its function is conductor be large enough to required to protect microprocessors
to ensure that all exposed noncurrent- carry the maximum ground fault from power system “noise” that does
carrying metallic parts of all structures current, without burning off, for not in any way affect motors or other 5
and equipment in or near the electrical sufficient time to permit protective electrical equipment.
distribution system are at the same devices (ground fault relays, circuit
Such systems must use single-point
potential, and that this is the zero breakers, fuses) to clear the fault
ground concept to minimize “noise”
6
reference potential of the earth.
The grounded conductor of the system and still meet the NEC requirements.
Equipment grounding is required (usually the neutral conductor), although Any separate isolated ground mat must
by both the National Electrical Code grounded at the source, must not be be tied to the rest of the facility ground
7
(Article 250) and the National Electrical used for equipment grounding. mat system for NEC compliance.
Safety Code regardless of how the
power system is grounded. Equipment The equipment grounding conductor
2. System Grounding 8
grounding also provides a return path may be the metallic conduit or raceway
of the wiring system, or a separate System grounding connects the
for ground fault currents, permitting
protective devices to operate. equipment grounding conductor, electrical supply, from the utility, from 9
run with the circuit conductors, as transformer secondary windings, or
Accidental contact of an energized permitted by NEC. If a separate from a generator, to ground. A system
conductor of the system with an equipment grounding conductor is can be solidly grounded (no intentional 10
improperly grounded noncurrent- used, it may be bare or insulated; if impedance to ground), impedance
carrying metallic part of the system insulated, the insulation must be green, grounded (through a resistance or
(such as a motor frame or panelboard green with yellow stripe or green tape. reactance), or ungrounded (with no 11
enclosure) would raise the potential of Conductors with green insulation may intentional connection to ground.
the metal object above ground poten- not be used for any purpose other than
tial. Any person coming in contact with for equipment grounding. 12
3. Medium-Voltage System: Grounding
Table 1.6-1. Features of Ungrounded and Grounded Systems (from ANSI C62.92)
13
Description A B C D E
Ungrounded Solidly Grounded Reactance Grounded Resistance Grounded Resonant Grounded 14
(1) Apparatus Fully insulated Lowest Partially graded Partially graded Partially graded
insulation
(2) Fault to Usually low Maximum value rarely Cannot satisfactorily be Low Negligible except when 15
ground current higher than three-phase reduced below one-half Petersen coil is short
short circuit current or one-third of values circuited for relay purposes
for solid grounding when it may compare with
solidly grounded systems
16
(3) Stability Usually unimportant Lower than with other Improved over solid Improved over solid Is eliminated from
methods but can be grounding particularly grounding particularly consideration during
made satisfactory by use if used at receiving end if used at receiving end single line-to-ground faults 17
of high-speed breakers of system of system unless neutralizer is short
circuited to isolate fault
by relays 18
(4) Relaying Difficult Satisfactory Satisfactory Satisfactory Requires special
provisions but can be

(5) Arcing Likely Unlikely Possible if reactance Unlikely


made satisfactory
Unlikely
19
grounds is excessive
(6) Localizing Effect of fault transmitted Effect of faults localized to Effect of faults localized to Effect of faults transmitted Effect of faults transmitted
faults as excess voltage on system or part of system system or part of system as excess voltage on as excess voltage on sound 20
sound phases to all where they occur where they occur unless sound phases to all phases to all parts of
parts of conductively reactance is quite high parts of conductively conductively connected
connected network connected network network 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.6-2 Power Distribution Systems
Grounding/Ground Fault Protection August 2017
Sheet 01 070

Table 1.6-1. Features of Ungrounded and Grounded Systems (Continued)


i Description A B C D E
Ungrounded Solidly Grounded Reactance Grounded Resistance Grounded Resonant Grounded
(7) Double faults Likely Likely Unlikely unless reactance Unlikely unless resistance Seem to be more likely but
ii is quite high and insulation is quite high and insulation conclusive information
weak weak not available
(8) Lightning Ungrounded neutral Highest efficiency and If reactance is very high Arresters for ungrounded, Ungrounded neutral
1 protection service arresters must be lowest cost arresters for ungrounded neutral service usually service arresters must
applied at sacrifice in cost neutral service must be must be applied at sacrifice be applied at sacrifice in
and efficiency applied at sacrifice in cost in cost and efficiency cost and efficiency
and efficiency
2 (9) Telephone Will usually be low except Will be greatest in Will be reduced from Will be reduced from Will be low in magnitude
interference in cases of double faults magnitude due to higher solidly grounded values solidly grounded values except in cases of double
or electrostatic induction fault currents but can be faults or series resonance
3 with neutral displaced but quickly cleared particularly at harmonic frequencies,
duration may be great with high speed breakers but duration may be great
(10) Radio May be quite high during Minimum Greater than for Greater than for solidly May be high during faults
4 interference faults or when neutral
is displayed
solidly grounded,
when faults occur
grounded, when faults
occur
(11) Line Will inherently clear Must be isolated for Must be isolated for Must be isolated for Need not be isolated but
availability themselves if total length each fault each fault each fault will inherently clear itself
5 of interconnected line is in about 60 to 80 percent
low and require isolation of faults
from system in increasing
6 percentages as length
becomes greater
(12) Adaptability to Cannot be interconnected Satisfactory indefinitely Satisfactory indefinitely Satisfactory with solidly-
Cannot be interconnected
7 interconnection unless interconnecting
system is ungrounded or
with reactance-grounded
systems
with solidly-grounded
systems
or reactance-grounded
systems with proper
unless interconnected
system is resonant
isolating transformers attention to relayinggrounded or isolating
are used transformers are used.
8 Requires coordination
between interconnected
systems in neutralizer
9 (13) Circuit Interrupting capacity Same interrupting Interrupting capacity Interrupting capacity
settings
Interrupting capacity
breakers determined by three-phase capacity as required for determined by three-phase determined by three-phase determined by three-phase
conditions three-phase short circuit fault conditions fault conditions fault conditions
10 will practically always be
satisfactory
(14) Operating Ordinarily simple but Simple Simple Simple Taps on neutralizers must
11 procedure possibility of double faults be changed when major
introduces complication system switching is
in times of trouble performed and difficulty
may arise in intercon-
12 nected systems. Difficult
to tell where faults are
located
13 (15) Total cost High, unless conditions Lowest Intermediate Intermediate Highest unless the arc
are such that arc tends to suppressing characteristic
extinguish itself, when is relied on to eliminate
14 transmission circuits may
be eliminated, reducing
transmission circuits when
it may be lowest for the
total cost particular types of service

15 Because the method of grounding The aforementioned definition is With selective ground fault isolation
affects the voltage rise of the unfaulted of significance in medium-voltage the fault current should be at least 60%
phases above ground, ANSI C62.92 distribution systems with long lines of the three-phase current at the point
16 classifies systems from the point of and with grounded sources removed of fault. Damage to cable shields must
view of grounding in terms of a during light load periods so that in be checked. Although this fact is not
coefficient of grounding some locations in the system the a problem except in small cables, it is a
17 Highest Power Frequency X0 /X1, R0 /X1 may exceed the defining good idea to supplement the cable
rms Line – Ground Voltage limits. Other standards (cable and shields returns of ground fault current
COG = ---------------------------------------------------------------------------------------------
lightning arrester) allow the use of to prevent damage, by installing an
18 rms Line – Line Voltage at Fault
Location with the Fault Removed 100% rated cables and arresters equipment grounding conductor.
selected on the basis of an effectively
This same standard also defines grounded system only where the The burdens on the current transformers
19 systems as effectively grounded when criteria in the above are met. In must be checked also (for saturation
COG is less than or equal to 0.8. Such effectively grounded system the line- considerations), where residually
a system would have X0 /X1 less than connected ground relays are used
to-ground fault current is high and
20 or equal to 3.0 and R0 /X1 less than
there is no significant voltage rise in and the current transformers supply
or equal to 1.0. Any other grounding current to phase relays and meters.
the unfaulted phases.
means that does not satisfy these
21 conditions at any point in a system
is not effectively grounded.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.6-3
August 2017 Grounding/Ground Fault Protection
Sheet 01 071

If ground sensor current transformers should not be limited to less than the Grounding Point
(zero sequence type) are used they current transformers rating of the The most commonly used grounding i
must be of high burden capacity. source. This rule will provide sensitive point is the neutral of the system.
differential protection for wye-connected This may be a neutral point created
Table 1.6-2 taken from ANSI-C62.92 generators and transformers against by means of a zigzag or a wye-broken ii
indicates the characteristics of the line-to-ground faults near the neutral.
various methods of grounding. delta grounding transformer in a
system that was operating as an
Reactance Grounding
Of course, if the installation of ground
ungrounded delta system. 1
fault differential protection is feasible,
It is generally used in the grounding or ground sensor current transformers In general, it is a good practice that all
of the neutrals of generators directly are used, sensitive differential relaying source neutrals be grounded with the 2
connected to the distribution system in resistance grounded system with same grounding impedance magnitude.
bus, in order to limit the line-to-ground greater fault limitation is feasible. However, neutrals should not be tied
fault to somewhat less than the
three-phase fault at the generator
In general, ground sensor current together to a single resistor. Where 3
transformers (zero sequence) do not one of the medium-voltage sources is
terminals. If the reactor is so sized, have high burden capacity. the utility, their consent for impedance
in all probability the system will
Resistance grounded systems limit grounding must be obtained. 4
remain effectively grounded.
the circulating currents of triplen The neutral impedance must have a
Resistance Grounded harmonics and limit the damage at
Medium-voltage systems in general the point of fault. This method of
voltage rating at least equal to the rated 5
line-to-neutral voltage class of the
should be low resistance grounded. grounding is not suitable for line-to- system. It must have at least a 10-second
The ground fault is typically limited to neutral connection of loads.
about 200–400 A but less than 1000 A
rating equal to the maximum future line- 6
On medium-voltage systems, 100% to-ground fault current and a continuous
(a cable shield consideration). With a rating to accommodate the triplen
cable insulation is rated for phase-to-
properly sized resistor and relaying
application, selective fault isolation
neutral voltage. If continued operation harmonics that may be present. 7
with one phase faulted to ground is
is feasible. The fault limit provided
desired, increased insulation thickness 4. Low-Voltage System: Grounding
has a bearing on whether residually
is required. For 100% insulation, fault Solidly grounded three-phase 8
connected relays are used or ground
clearance is recommended within systems (Figure 1.6-1) are usually
sensor current transformers are used
one minute; for 133% insulation, one wye-connected, with the neutral point
for ground fault relaying.
hour is acceptable; for indefinite grounded. Less common is the 9
In general, where residually connected operation, as long as necessary, “red-leg” or high-leg delta, a 240 V
ground relays are used (51N), the 173% insulation is required. system supplied by some utilities with
fault current at each grounded source one winding center-tapped to provide 10
120 V to ground for lighting. This
Table 1.6-2. Characteristics of Grounding 240 V, three-phase, four-wire system
Grounding Classes Ratios of Symmetrical Percent Fault Per Unit Transient is used where 120 V lighting load is 11
and Means Component Parameters 1 Current LG Voltage small compared to 240 V power load,
because the installation is low in cost
X0/X1 R0/X1 R0/X0 2 3
to the utility. 12
A. Effectively ➃
1. Effective 0-3 0-1 — >60 m2
2. Very effective 0-1 0-0.1 — >95 <1.5
Phase A
13
B. Noneffectively
1. Inductance • • • Phase B
N
a. Low inductance 3-10 0-1 — >25 <2.3
b. High inductance >10 — <2 <25 m2.73 8 • Phase C 14
2. Resistance • Neutral
a. Low resistance 0-10 — Š2 <25 <2.5
b. High resistance — >100 m(-1) <1 m2.73 Grounded Wye 15
3. Inductance and resistance >10 — >2 <10 m2.73
4. Resonant
5. Ungrounded/capacitance
5 — — <1 m2.73 • Phase B

a. Range A y to -40 6 — — <8 m3 9 16


b. Range B -40 to 0 — — >8 >3 79
• • • Phase C
Phase A
1 Values of the coefficient of grounding (expressed as a percentage of maximum phase-to-phase • Neutral
17
voltage) corresponding to various combinations of these ratios are shown in the ANSI C62.92
Appendix figures. Coefficient of grounding affects the selection of arrester ratings. Center-Tapped (High-Leg) Delta
2 Ground-fault current in percentage of the three-phase short-circuit value.
3 Transient line-to-ground voltage, following the sudden initiation of a fault in per unit of the crest
• Phase A 18
of the prefault line-to-ground operating voltage for a simple, linear circuit.
In linear circuits, Class A1 limits the fundamental line-to-ground voltage on an unfaulted phase to
4
• • Phase B
5
138% of the prefault voltage; Class A2 to less than 110%.
See ANSI 62.92 para. 7.3 and precautions given in application sections.
• Phase C 19
6 Usual isolated neutral (ungrounded) system for which the zero-sequence reactance is capacitive
(negative). Corner-Grounded Delta
7 Same as NOTE (6) and refer to ANSI 62.92 para. 7.4. Each case should be treated on its own merit. 20
8 Under restriking arcing ground fault conditions (e.g., vacuum breaker interrupter operation), Figure 1.6-1. Solidly Grounded Systems
this value can approach 500%.
9 Under arcing ground fault conditions, this value can easily reach 700%, but is essentially unlimited. 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.6-4 Power Distribution Systems
Grounding/Ground Fault Protection August 2017
Sheet 01 072

A corner-grounded three-phase delta Most transformer-supplied systems These faults are usually arcing and
i system is sometimes found, with are either solidly grounded or resis- can cause severe damage if at least
one phase grounded to stabilize all tance grounded. Generator neutrals one of the grounds is not cleared
voltages to ground. Better solutions are often grounded through a reactor, immediately. If the second circuit is
ii are available for new installations. to limit ground fault (zero sequence) remote, enough current may not
currents to values the generator can flow to cause protection to operate.
Ungrounded systems (Figure 1.6-2) withstand. This can leave high voltages and
1 can be either wye or delta, although stray currents on structures and
the ungrounded delta system is far Selecting the Low-Voltage System jeopardize personnel.
more common. Grounding Method
2 There is no one “best” distribution In general, where loads will be
system for all applications. In choosing connected line-to-neutral, solidly
• Phase A
among solidly grounded, resistance grounded systems are used. High
3 • • Phase B grounded, or ungrounded power resistance grounded systems are
Phase C distribution, the characteristics of the used as substitutes for ungrounded
system must be weighed against the systems where high system
Ungrounded Delta
4 requirements of power loads, lighting availability is required.
Phase A loads, continuity of service, safety With one phase grounded, the voltage
• • • Phase B and cost. to ground of the other two phases
5 N
rises 73%, to full phase-to-phase
• Phase C Under ground fault conditions, each
voltage. In low-voltage systems this
Ungrounded Wye system behaves very differently:
is not important, since conductors
6 ■ A solidly grounded system produces are insulated for 600 V.
Figure 1.6-2. Ungrounded Systems high fault currents, usually with
arcing, and the faulted circuit must A low-voltage resistance grounded
7 Resistance-grounded systems
be cleared on the first fault within system is normally grounded so that
(Figure 1.6-3) are simplest with a the single line-to-ground fault current
wye connection, grounding the neutral a fraction of a second to minimize
damage exceeds the capacitive charging
8 point directly through the resistor. current of the system. If data for the
Delta systems can be grounded by ■ An ungrounded system will pass
charging current is not available, use
means of a zig-zag or other grounding limited current into the first ground
40–50 ohm resistor in the neutral
9 transformer. Wye broken delta fault—only the charging current
of the transformer.
transformer banks may also be used. of the system, caused by the
distributed capacitance to ground In commercial and institutional
10 of the system wiring and equip- installations, such as office buildings,
Phase A ment. In low-voltage systems, shopping centers, schools and hospitals,
• • • Phase B this is rarely more than 1 or 2 A lighting loads are often 50% or more
N
11 R • Phase C Therefore, on first ground fault, an
of the total load. In addition, a feeder
outage on first ground fault is seldom
ungrounded system can continue in
crucial—even in hospitals, that have
service, making it desirable where
12 Resistance-Grounded Wye power outages cannot be tolerated.
emergency power in critical areas. For
these reasons, a solidly grounded wye
However, if the ground fault is
distribution, with the neutral used for
13 • • Phase A intermittent, sputtering or arcing, a
lighting circuits, is usually the most
high voltage—as much as 6 to 8 times
• • • Phase B economical, effective and convenient
phase voltage—can be built up across
• Phase C
the system capacitance, from the
design. In some instances, it is an
14 • NEC requirement.
• phase conductors to ground.
N
R • Similar high voltages can occur as a
In industrial installations, the effect
15 of a shutdown caused by a single
result of resonance between system
ground fault could be disastrous. An
capacitance and the inductances of
Delta With Derived Neutral Resistance- interrupted process could cause the
transformers and motors in the
16 Grounded Using Zig-Zag Transformer loss of all the materials involved, often
system. However, the phase-to-phase
ruin the process equipment itself, and
voltage is not affected. This high
Figure 1.6-3. Resistance-Grounded Systems sometimes create extremely danger-
transient phase-to-ground voltage
17 These arrangements create a derived can puncture insulation at weak
ous situations for operating personnel.
neutral point, which can be either points, such as motor windings, and On the other hand, lighting is usually
solidly or impedance-grounded. If the is a frequent cause of multiple motor only a small fraction of the total
18 grounding transformer has sufficient failures on ungrounded systems. industrial electrical load. Conse-
capacity, the neutral created can be quently, a solidly grounded neutral
Locating a first fault on an ungrounded
solidly grounded and used as part of circuit conductor is not imperative.
19 a three-phase, four-wire system.
system can be difficult. If, before the
When required, a neutral to feed the
first fault is cleared, a second ground
lighting loads can be obtained from
fault occurs on a different phase, even
inexpensive lighting transformers.
20 on a different, remote feeder, it is a
high-current phase-to-ground-to-
phase fault.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.6-5
August 2017 Grounding/Ground Fault Protection
Sheet 01 073

Because of the ability to continue in system, the voltage drop across Overcurrent protection is designed
operation with one ground fault on the arc can be from 70 to 140 V. The to protect conductors and equipment i
the system, many existing industrial resulting ground fault current is against currents that exceed their
plants use ungrounded delta distribu- rarely enough to cause the phase ampacity or rating under prescribed
tion. Today, new installations can have overcurrent protection device to open time values. An overcurrent can result ii
all the advantages of service continuity instantaneously and prevent damage. from an overload, short circuit or (high
of the ungrounded delta, yet minimize level) ground fault condition.
the problems of the system, such Sometimes, the ground fault is below 1
as the difficulty of locating the first the trip setting of the protective device When currents flow outside the normal
ground fault, risk of damage from a and it does not trip at all until the fault current path to ground, supplementary
second ground fault, and damage escalates and extensive damage is ground fault protection equipment will 2
transient overvoltages. done. For these reasons, low level be required to sense low-level ground
ground protection devices with mini- fault currents and initiate the protection
A high-resistance grounded wye mum time delay settings are required required. Normal phase overcurrent 3
distribution can continue in operation to rapidly clear ground faults. This is protection devices provide no protection
with a ground fault on the system emphasized by the NEC requirement against low-level ground faults.
and will not develop transient that a ground fault relay on a service
There are three basic means of sensing
4
overvoltages. shall have a maximum delay of one
second for faults of 3000 A or more. ground faults. The most simple and
And, because the ground point is direct method is the ground return
established, locating a ground fault is The NEC (Sec. 230.95) requires that method as illustrated in Figure 1.6-4.
5
less difficult than on an ungrounded ground fault protection, set at no more This sensing method is based on the fact
system especially when a “pulsing than 1200 A, be provided for each that all currents supplied by a trans-
contactor” design is applied. When service disconnecting means rated former must return to that transformer.
6
combined with sensitive ground-fault 1000 A or more on solidly grounded
protection, damage from a second wye services of more than 150 V to
ground fault can be nearly eliminated. ground, but not exceeding 600 V
Main 7
phase-to-phase. Practically, this makes
Ungrounded delta systems can be ground fault protection mandatory
Neutral
converted to high-resistance grounded on 480Y/277 V services, but not on
Service
Transformer
8
GFR
systems, using a zig-zag or other 208Y/120 V services.
Sensor
Typical
grounding transformer to derive a Ground Bus Feeder

neutral, with similar benefits, see On a 208 V system, the voltage to 9


Tab 36. While the majority of ground is 120 V. If a ground fault Main Bonding
Jumper
manufacturing plants use solidly occurs, the arc goes out at current zero, Typical

grounded systems, in many instances, and the voltage to ground is often too
Grounding
Electrode
Equipment
Grounding
4W Load 10
Conductor Conductor
the high-resistance grounded distribu- low to cause it to restrike. Therefore,
tion will be the most advantageous. arcing ground faults on 208 V systems
tend to be self-extinguishing. Figure 1.6-4. Ground Return Sensing Method 11
Ground Fault Protection When an energized conductor faults
On a 480 V system, with 277 V to
A ground fault normally occurs in one ground, restrike usually takes place to grounded metal, the fault current 12
of two ways: by accidental contact of after current zero, and the arc tends to returns along the ground return path to
an energized conductor with normally be self-sustaining, causing severe and the neutral of the source transformer.
grounded metal, or as a result of increasing damage, until the fault is This path includes the main bonding 13
an insulation failure of an energized cleared by a protective device. jumper as shown in Figure 1.6-4.
conductor. When an insulation failure
The NEC requires ground fault service A current sensor on this conductor
occurs, the energized conductor
disconnecting means rated 1000 A or (which can be a conventional bar-type
14
contacts normally noncurrent-carrying
grounded metal, which is bonded to higher. This protection works so fast or window type CT) will respond to
that for ground faults on feeders, or ground fault currents only. Normal
or part of the equipment grounding
even branch circuits, it will often open neutral currents resulting from
15
conductor.
the service disconnect before the feeder unbalanced loads will return along
In a solidly grounded system, the fault the neutral conductor and will not be
current returns to the source primarily
or branch circuit overcurrent device can
operate. This is highly undesirable, and detected by the ground return sensor.
16
along the equipment grounding in the NEC (230.95), an informational
conductors, with a small part using This is an inexpensive method of sensing
parallel paths such as building steel or
note states that “additional ground fault
ground faults where protection per 17
protective equipment may be needed
piping. If the ground return impedance NEC (230.95) is desired. For it to
on feeders and branch circuits where
was as low as that of the circuit operate properly, the neutral must be
conductors, ground fault currents
maximum continuity of electric service
grounded in only one place as indicated 18
is necessary.”
would be high, and the normal phase in Figure 1.6-4. In many installations,
overcurrent protection would clear Unless it is acceptable to disconnect the servicing utility grounds the neutral
them with little damage. the entire service on a ground fault at the transformer and additional 19
almost anywhere in the system, such grounding is required in the service
Unfortunately, the impedance of the additional stages of ground fault equipment per NEC (250.24(A)(2)).
ground return path is usually higher, protection must be provided. At 20
the fault itself is usually arcing and the least two stages of protection are
impedance of the arc further reduces mandatory in healthcare facilities
the fault current. In a 480Y/277 V (NEC Sec. 517.17). 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.6-6 Power Distribution Systems
Grounding/Ground Fault Protection August 2017
Sheet 01 074

In such cases, and others including This method of sensing ground faults As with the zero sequence sensing
i multiple source with multiple, inter- can be employed on the main discon- method, the resultant residual sensor
connected neutral ground points, nect where protection per NEC (230.95) output to the ground fault relay or
residual or zero sequence ground is desired. It can also be easily employed integral ground fault tripping circuit
ii sensing methods should be employed. in multi-tier systems where additional will be zero if all currents flow only
levels of ground fault protection are in the circuit conductors. Should a
A second method of detecting ground desired for added service continuity. ground fault occur, the current from
1 faults involves the use of a zero Additional grounding points may be
employed upstream of the sensor,
the faulted conductor will return along
sequence sensing method, as illus- the ground path, rather than on the
trated in Figure 1.6-5. This sensing but not on the load side.
other circuit conductors, and the resid-
2 method requires a single specially
Ground fault protection employing ual sum of the sensor outputs will not
designed sensor, either of a toroidal ground return or zero sequence be zero. When the level of ground fault
or rectangular shaped configuration. sensing methods can be accomplished current exceeds the pre-set current
3 This core balance current transformer by the use of separate ground fault and time delay settings, a ground
surrounds all the phase and neutral relays (GFRs) and disconnects fault tripping action will be initiated.
conductors in a typical three-phase, equipped with standard shunt trip
4 four-wire distribution system. devices. Alternately, it can be done This method of sensing ground faults
by circuit breakers using electronic can be economically applied on main
This sensing method is based on the trip units with integral ground fault service disconnects where circuit break-
fact that the vectorial sum of the phase
5 and neutral currents in any distribution
protection using external connections ers with integral ground fault protection
from sensors arranged for this mode are provided. It can be used in protec-
circuit will equal zero unless a ground of sensing. In some cases, a reliable tion schemes per NEC (230.95) or in
fault condition exists downstream from
6 the sensor. All currents that flow only
source of control power is needed. multi-tier schemes where additional
The third basic method of detecting levels of ground fault protection are
in the circuit conductors, including desired for added service continuity.
balanced or unbalanced phase-to-phase ground faults involves the use of
7 and phase-to-neutral normal or fault multiple current sensors connected Additional grounding points may be
in a residual sensing method as illus- employed upstream of the residual
currents, and harmonic currents, will sensors, but not on the load side.
result in zero sensor output. trated in Figure 1.6-6. This is a very
8 common sensing method used with Both the zero sequence and
However, should any conductor circuit breakers equipped with elec- residual sensing methods have
become grounded, the fault current tronic trip units, current sensors and been commonly referred to as
9 will return along the ground path— integral ground fault protection. The “vectorial summation” methods.
not the normal circuit conductors. three-phase sensors are required for
Consequently, the sensor will have an normal phase overcurrent protection. Most distribution systems can use
10 unbalanced magnetic flux condition. Ground fault sensing is obtained with either of the three sensing methods
The ground fault relay will sense the the addition of an identically rated exclusively or a combination of the
unbalance and provide a trip signal to sensor mounted on the neutral. sensing methods depending upon
11 the breaker. the complexity of the system and
In a residual sensing scheme, the the degree of service continuity and
relationship of the polarity markings selective coordination desired.
12 Zero
Sequence
Alternate
Sensor —as noted by the “X” on each sensor— Different methods will be required
Sensor Location
Main
is critical. Because the vectorial sum of depending upon the number of supply
the currents in all the conductors will sources, and the number and location
13 total zero under normal, non-ground of system grounding points.
faulted conditions, it is imperative
Neutral
that proper polarity connections are As an example, one of the more
14 employed to reflect this condition. frequently used systems where
GFR Typical
Feeder
continuity of service to critical loads
is a factor is the dual source system
15 Sensor
Polarity
Residual
illustrated in Figure 1.6-7. This system
Typical
4W Load Marks
Sensors uses tie-point grounding as permitted
Main under NEC Sec. 250.24(A)(3). The use
16 Figure 1.6-5. Zero Sequence Sensing Method of this grounding method is limited
to services that are dual fed (double-
Zero sequence sensors are available Neutral ended) in a common enclosure or
17 with various window openings for grouped together in separate enclo-
circuits with small or large conductors, Typical sures, employing a secondary tie.
GFR
and even with large rectangular win- Feeder

18 dows to fit over bus bars or multiple


large size conductors in parallel. Some Typical
4W Load
sensors have split cores for installation
19 over existing conductors without
Figure 1.6-6. Residual Sensing Method
disturbing the connections.

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.6-7
August 2017 Grounding/Ground Fault Protection
Sheet 01 075

This scheme uses individual sensors


connected in ground return fashion. Power Power i
Transformer Transformer
Under tie breaker closed operating
conditions, either the M1 sensor or
M2 sensor could see neutral unbalance Neutral Sensor Neutral Sensor Main
ii
Main
currents and possibly initiate an Bkr. Main Bkr. 52-1 Tie Bkr. Main Bkr. 52-2 Bkr.
improper tripping operation. However, 52-1 52-T 52-2
with the polarity arrangements of ØA, ØB, ØC ØA, ØB, ØC 1
these two sensors along with the tie Neutral Neutral
Neutral Sensor
breaker auxiliary switch (T/a) and Tie Bkr. 52-T ( )B5
interconnections as shown, this Typical
4-Wire
( )B5 Typical
( )B4
2
( )B4 52-T 52-T 4-Wire

M2N
possibility is eliminated.

M1G

M2G
M1N
Feeder

TN
TG
a a Feeder
Selective ground fault tripping 33-
52-T
3
coordination between the tie breaker 4-Wire
B5 B4 B4 B5 B4 B5
4-Wire
Load Load
and the two main circuit breakers is Digitrip Digitrip Digitrip
B4 B5
achieved by pre-set current pickup and
Digitrip
Main Bkr.
52-1
Main Bkr.
52-T
Main Bkr.
52-2
B4
Digitrip
B5
4
time delay settings between devices
GFR/1, GFR/2 and GFR/T.
The advantages of increased service
Figure 1.6-7. Dual Source System—Single Point Grounding 5
Note: This GF scheme requires trip units to be set to source ground sensing.
continuity offered by this system can
only be effectively used if additional
levels of ground fault protection are
6
added on each downstream feeder. Power Power
Some users prefer individual grounding Transformer Transformer
of the transformer neutrals. In such
7
cases, a partial differential ground fault
scheme should be used for the mains X X
8
X X
and tie breaker. Neutral Neutral
Sensor Main Sensor Main
An example of a residual partial differ- Main Breaker 52-1 Breaker 52-2 Main
ential scheme is shown in Figure 1.6-8.
Breaker
52-1
Breaker
52-2
9
The scheme typically relies upon the
vector sum of at least two neutral Phase A, Tie Breaker Phase A,
sensors in combination with each Phase B, 52-T Phase B, 10
breakers’ three-phase sensors. To Phase C Phase C
reduce the complexity of the drawing, Neutral Neutral
each of the breakers’ three-phase Neutral Sensor X
X
11
Tie Breaker 52-T
sensors have not been shown. It is

Trip Unit
Trip Unit

Typical X
Typical X

absolutely critical that the sensors’ X X

polarities are supplied as shown, the


Four-Wire
Feeder 52-1 52-T 52-2
Four-Wire
Feeder
12
neutral sensor ratings of the mains and a a a
tie are the same, and that there are
no other grounds on the neutral bus Four-Wire Load Four-Wire Load 13
made downstream of points shown. Trip Unit Trip Unit Trip Unit
Main Breaker Tie Breaker Main Breaker
An infinite number of ground fault 52-1 52-T 52-2 14
protection schemes can be developed
depending upon the number of alternate Figure 1.6-8. Dual Source System—Multiple Point Grounding
sources, the number of grounding points To maintain maximum service continu- The use of GFRs (or circuit breakers 15
and system interconnections involved. ity, more than two levels (zones) of with integral ground fault protection)
Depending upon the individual system ground fault protection will be that incorporate Zone Selective
configuration, either mode of sensing required, so that ground fault outages Interlocking, allows a coordinated 16
or a combination of all types may be can be localized and service interrup- response in a system by operating in
employed to accomplish the desired tion minimized. To obtain selectivity a time delayed mode for ground faults
end results. between different levels of ground occurring most remote from the
17
The NEC (230.95) limits the maximum fault relays, time delay settings should source. This time delayed mode is
be employed with the GFR furthest only actuated when the GFR protecting
setting of the ground fault protection
downstream having the minimum the zone containing the fault sends a
18
used on service equipment to 1200 A
(and timed tripping at 3000 A for one time delay. This will allow the GFR restraining signal to the upstream
nearest the fault to operate first. GFRs. The absence of a restraining
second). In order to prevent tripping
signal from a downstream GFR is an
19
of the main service disconnect on a With several levels of protection, this
downstream feeder ground fault, indication to the next upstream GFR
will reduce the level of protection for that a ground fault is within its zone
ground fault protection must be faults within the upstream GFR zones. of protection and it will operate
20
provided on all the feeders. Zone interlocking was developed for instantaneously to clear the fault with
GFRs to overcome this problem. minimum damage and maximum
service continuity.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.6-8 Power Distribution Systems
Grounding/Ground Fault Protection August 2017
Sheet 01 076

This operating mode permits all GFRs Further Information These supplemental grounding
i to operate instantaneously for a fault ■ PRSC-4E—System Neutral Ground- electrodes include: the effectively
within their zone and still provide ing and Ground Fault Protection grounded metal frame of the building,
complete selectivity between zones. (ABB Publication) a concrete-encased electrode, a copper
ii ■ PB 2.2—NEMA Application Guide
conductor ground ring encircling the
The National Electrical Manufacturers building, or a made electrode such as
Association (NEMA) states, in their for Ground Fault Protective Devices
one or more driven ground rods or
1 application guide for ground fault for Equipment
a buried plate. Where any of these
protection, that zone interlocking is ■ IEEE Standard 142—Grounding of electrodes are present, they must be
necessary to minimize damage from Industrial and Commercial Power bonded together into one grounding
2 ground faults. A two-wire connection Systems (Green Book) electrode system.
is required to carry the restraining ■ IEEE Emerald Book (Standard 1100)
signal from the GFRs in one zone to One of the most effective grounding
■ UL 96A, Installation Requirements
3 the GFRs in the next zone.
for Lightning Protection Systems
electrodes is the concrete-encased
electrode, sometimes called the Ufer
Circuit breakers with integral ground ground, named after the man who
fault protection and standard circuit Lightning and Surge Protection
4 breakers with shunt trips activated
developed it. It consists of at least
Physical protection of buildings 20 ft (6 m) of steel reinforcing bars or
by the ground fault relay are ideal for from direct damage from lightning rods not less than 1/2 inches (12.7 mm)
ground fault protection. Eaton’s
5 Pringle Bolted Pressure Type fused
is beyond the scope of this section. in diameter, or at least 20 ft (6 m) of
Requirements will vary with geographic bare copper conductor, size No. 4 AWG
switches have an optional integral location, building type and environ- or larger, encased in at least 2 inches
ground fault protection relay and meet
6 UL Class 1 requirements to open safely
ment, and many other factors (see (50.8 mm) of concrete. It must be
IEEE/ANSI Standard 142, Grounding located within and near the bottom of
on faults up to 12 times their rating. of Industrial and Commercial Power a concrete foundation or footing that
Eaton’s Shunt Trip Safety Switches
7 have passed Class 1 ground fault
Systems). Any lightning protection is in direct contact with the earth. Tests
system must be grounded, and the have shown this electrode to provide a
testing and include an integral shunt lightning protection ground must be low-resistance earth ground even in
8 trip mechanism that can be field wired bonded to the electrical equipment poor soil conditions.
to an external ground fault relay. grounding system.
The electrical distribution system and
Power distribution systems differ equipment ground must be connected
9 widely from each other, depending Grounding Electrodes
to this grounding electrode system by
upon the requirements of each end At some point, the equipment and a grounding electrode conductor. All
user’s facility type and application. A system grounds must be connected other grounding electrodes, such
10 power system design professional to the earth by means of a grounding as those for the lightning protection
needs to carefully evaluate total system electrode system. system, the telephone system,
overcurrent protection, including television antenna and cable TV
11 ground fault currents, to meet these Outdoor substations usually use a
system grounds, and computer
needs. Experienced and knowledgeable ground grid, consisting of a number
of ground rods driven into the earth systems, must be bonded to this
engineers have to consider the impact
12 on all power sources (utility and on-site and bonded together by buried copper grounding electrode system.
generation), the effects of outages and conductors. The required grounding There are many books written
the cost impact of downtime, as well as electrode system for a building is about the design and application of
13 safety for people and equipment from spelled out in NEC Article 250. grounding systems. For those diligent
arc flash hazards, when balancing The preferred grounding electrode engineers seeking more information,
enhanced protection schemes against is a metal underground water pipe the following publications are
14 initial equipment cost. They must apply in direct contact with the earth for at recommended reading:
protective devices, analyzing the least 10 ft (3 m). However, because ■ Soares Book on Grounding and
time-current characteristics and fault
15 interrupting capacity, as well as
underground water piping is often
plastic outside the building, or may
Bonding, 2014 NEC. IAEI 12th
selectivity and coordination methods Edition by International Association
later be replaced by plastic piping, of Electrical Inspectors
to provide the most safe and cost-
16 effective distribution system.
the NEC requires this electrode to be
■ McGraw Hill’s National Electrical
supplemented by and bonded to at
Code 2014 Grounding & Earthing
least one other grounding electrode.
Handbook
17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.6-9
August 2017 Grounding/Ground Fault Protection
Sheet 01 077

Medium-Voltage Equipment Surge Recognizing that distribution system Surge Protection Recommendations
Protection Considerations can be subject to voltage transients 1. For circuits exposed to lightning, i
caused by lighting or switching, the surge arresters should be applied
Transformers industry has developed standards to in line with Industry standard
provide guidelines for surge protection practices. ii
If the voltage withstand/BIL rating of of electrical equipment. Those guide-
the transformer is less than that of the lines should be used in design and 2. Transformers—Because each
switchgear feeding the transformer, protection of electrical distribution installation is unique, a variety 1
surge protection is recommended at systems independent of the circuit of different factors can impact
the transformer terminals, in line with breaker interrupting medium. The how the various electrical
established practices. In addition, industry standards are: components interact as a system 2
consideration should be given to using (i.e.,: transformer type and MVA
surge arresters and/or surge capacitors ANSI C62 rating, system impedances,
for transformers having equal or Guides and Standards for Surge the Manufacturer’s Vacuum 3
greater withstand/BIL ratings than Protection Interrupter Current Chop Rating,
that of the switchgear feeding the etc.). Consequently, there is no
IEEE 242—Buff Book
transformer for distribution systems
IEEE Recommended Practice for singular answer for all situations. 4
where reflected voltage waves and/or The optimum application of
resonant conditions may occur. Protection and Coordination of
Industrial and Commercial Power snubbers may require
Typically incoming voltage surges are Systems recommendations from a 5
reflected at the transformer primary switching transient study.
terminals, resulting in voltages at the IEEE 141—Red Book
ends of the transformer primary Recommended Practice for Typical rules of thumb are: 6
terminals/windings of up to two times Electric Power Distribution for a. Close-coupled to medium-
the incoming voltage wave. System Industrial Plants voltage primary breaker:
capacitance and inductance values Provide transients surge 7
IEEE C37.20.2
combined with the transformer Standards for Metal-Clad Switchgear protection, such as Surge
impedance values can cause resonant Arrester in parallel with RC
conditions resulting in amplified Eaton’s medium-voltage metal-clad Snubber. The surge protection
8
reflected waves. Surge arresters/ and metal-enclosed switchgear that device selected should be
capacitors when required, should uses vacuum circuit breakers is applied located and connected at the
be located as close to the transformer over a broad range of circuits. It is one transformer primary terminals
9
primary terminals as practical. of the many types of equipment in the or it can be located inside the
total distribution system. Whenever a switchgear and connected on
Where concerns exist for transformer switching device is opened or closed, the transformer side of the
10
failures or life reduction due to certain interactions of the power primary breaker.
switching transients, Eaton’s system elements with the switching
Cooper Transformer Group offers device can cause high frequency voltage
b. Cable-connected to medium- 11
an environmentally friendly oil-filled voltage primary breaker:
transients in the system. Provide transient surge
hardened transformer solution. See
White Paper WP202001 and Brochure Due to the wide range of applications protection, such as surge 12
B210-10035 on Eaton/Cooper website and variety of ratings used for different arrester in parallel with RC
for details. elements in the power systems, a Snubber for transformers
given circuit may or may not require connected by cables with 13
Motors surge protection. Therefore, Eaton lengths up to 150 feet. The
Surge capacitors and, where does not include surge protection as surge protection device should
appropriate, surge arresters should standard with its metal-clad or metal- be located and connected at the 14
be applied at the motor terminals. enclosed medium-voltage switchgear. transformer terminals. Surge
protection is generally not
Generators The system designer must specify needed for transformers with 15
Surge capacitors and station class the optional type and extent of surge lightning impulse withstand
surge arresters should be properly protection necessary, depending on ratings equal to that of the
applied at the machine terminals. the individual circuit characteristics switchgear and connected to 16
and cost considerations. Because the switchgear by cables at
Surge Protection transformers have both high initial least 150 feet or longer. For
Eaton’s VacClad-W metal-clad switch-
installation and replacement costs, transformers with lower BIL, 17
the specifying engineer should provide surge arrester in parallel
gear is applied over a broad range of consider commissioning an optional with RC Snubber.
circuits, and is one of the many types study. These switching transient 18
of equipment in the total system. The c. When special transient resis-
studies and their associated tant transformer designs are
distribution system can be subject to recommendations can be provided used, RC snubbers may not be
voltage transients caused by lighting
or switching surges.
by Eaton’s Engineering Services & required for power transformer 19
Systems group (EESS). protection. However, they
may be needed for instrument
The following are Eaton’s recommenda-
tions for surge protection of medium- transformer protection. 20
voltage equipment. Please note these
recommendations are valid when using 21
Eaton’s vacuum breakers only.

CA08104001E For more information, visit: www.eaton.com/consultants


1.6-10 Power Distribution Systems
Grounding/Ground Fault Protection August 2017
Sheet 01 078

RC Snubber to dampen internal Types of Surge Protection Devices B. Low Resistance Grounded Sys-
i transformer resonance:
Generally surge protective devices
tems (systems grounded through
resistor rated for 10 seconds):
The natural frequency of transformer should be located as closely as possible Arrester 10-second MCOV capability
ii windings can under some circumstances to the circuit component(s) that require
protection from the transients, and
at 60 ºC, which is obtained from
be excited to resonate. Transformer manufacturer’s data, should be
windings in resonance can produce connected directly to the terminals of equal to 1.05 x VLL, where VLL is
1 elevated internal voltages that produce the component with conductors that nominal line-to-line service voltage,
insulation damage or failure. An RC are as short and flat as possible to and 1.05 factor allows for +5%
Snubber applied at the transformer minimize the inductance. It is also voltage variation above the
2 terminals as indicated above can important that surge protection devices nominal voltage.
dampen internal winding resonance should be properly grounded for
and prevent the production of damag- effectively shunting high frequency C. Ungrounded or Systems
3 ing elevated internal voltages. This is transients to ground. Grounded through impedance
typically required where rectifiers, UPS other than a 10-second resistor:
or similar electronic equipment is on Surge Arresters Arrester MCOV rating should be
4 the transformer secondary. Modern metal-oxide surge arresters equal to 1.05 x VLL/T, where VLL
are recommended as this design and T are as defined above.
3. Arc-Furnace Transformers— ensures better performance and high
Provide Surge Arrester in parallel Refer to Table 1.6-3 for recommended
5 with RC Snubber at the trans-
reliability of surge protection schemes.
ratings for metal-oxide surge arresters
Manufacturer’s technical data must be
former terminals. consulted for correct application of a that are sized in accordance with the
above guidelines, when located in
6 4. Motors—Provide Surge Arrester given type of surge arrester.
Eaton’s switchgear.
in parallel with RC Snubber at the Many manufacturer’s published
motor terminals. For those motors arrester MCOV (maximum continuous Surge Capacitors
7 using VFDs, surge protection operating voltage) ratings are based Metal-oxide surge arresters limit the
should be applied and precede on 40 ºC or 45 ºC ambient temperature. magnitude of prospective surge over-
the VFD devices as well. In general, the following guidelines are voltage, but are ineffective in control-
8 recommended for arrester selections, ling its rate of rise. Specially designed
5. Generators—Provide station class
Surge Arrester in parallel with RC when installed inside Eaton’s medium- surge capacitors with low internal
voltage switchgear: inductance are used to limit the rate of
9 Snubber at the generator terminals.
rise of this surge overvoltage to protect
6. Capacitor Switching—No surge A. Solidly Grounded Systems: turn-to-turn insulation. Recommended
protection is required. Make sure Arrester MCOV rating should be values for surge capacitors are: 0.5 µf
10 that the capacitor’s lightning equal to 1.05 x VLL/(1.732 x T), on 5 and 7.5 kV, 0.25 µf on 15 kV, and
impulse withstand rating is equal where VLL is nominal line-to-line 0.13 µf on systems operating at 24 kV
to that of the switchgear. service voltage, 1.05 factor allows and higher.
11 for +5% voltage variation above
7. Shunt Reactor Switching— the nominal voltage according
Provide Surge Arrester in parallel to ANSI C84.1, and T is derating
12 with RC Snubber at the reactor factor to allow for operation at
terminals. 55 ºC switchgear ambient, which
should be obtained from the
13 8. Motor Starting Reactors or Reduced arrester manufacturer for the type
Voltage Auto-Transformers— of arrester under consideration.
Provide Surge Arrester in parallel Typical values of T are: 0.946 to 1.0.
14 with RC Snubber at the reactor or
RVAT terminals.
9. Switching Underground Cables—
15 Surge protection should be
properly applied as determined
by a switching transient study.
16

17

18

19 Figure 1.6-9. Surge Protection Devices

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.6-11
August 2017 Grounding/Ground Fault Protection
Sheet 01 079

RC Snubber Under high frequency transient Better protection: An RC Snubber


A RC Snubber device consists of a conditions, the capacitor offers in parallel with Surge Arrester for i
non-inductive resistor R sized to match very low impedance, thus effectively protection from high frequency
surge impedance of the load cables, “inserting” the resistor R and ZnO transients and voltage peaks.
typically 20 to 30 ohms, and connected in the power system as a cable ii
terminating network, thus minimizing Best protection: RC Snubber with
in series with a Surge Capacitor C. The surge suppressor, plus proper surge
Surge Capacitor is typically sized to be reflection of the steep wave-fronts of
0.15 to 0.25 microfarad. Under normal the voltage transients and prevents arrester preceding it where needed 1
voltage doubling of the traveling for protection against lightning. The
operating conditions, impedance of RC Snubber with surge suppressor
the capacitor is very high, effectively wave. The ZnO element limits the
“isolating” the resistor R from the peak voltage magnitudes. provides protection from high 2
frequency voltage transients and
system at normal power frequencies, The combined effects of R, ZnO, limits peak magnitude of the transient
and minimizing heat dissipation during
normal operation.
and capacitor of this device provides to 1 to 2 PU. A surge arrester provides 3
optimum protection against high protection from higher voltage peaks
Under high frequency transient frequency transients by absorbing, resulting from lightning surges.
conditions, the capacitor offers very damping, and by limiting the peak Note that special design liquid-filled 4
low impedance, thus effectively amplitude of the voltage wave-fronts. and dry-type transformers are avail-
“inserting” the resistor R in the power Please note that this suppressor is able that do not require the addition
system as a cable terminating resistor, not a lightning protection device. If of RC Snubbers to mitigate switching 5
thus minimizing reflection of the steep lightning can occur or be induced in the transients.
wave-fronts of the voltage transients electrical system, a properly rated and
and prevents voltage doubling of the applied surge arrester must precede Further Information 6
traveling wave. The RC Snubber this device. ■ IEEE/ANSI Standard 142—Grounding
provides protection against high Industrial and Commercial Power
frequency transients by absorbing Surge Protection Summary Systems (Green Book) 7
and damping the transients. Minimum protection: Surge Arrester ■ IEEE Standard 241—Electric Power
for protection from high overvoltage Systems in Commercial Buildings
An RC Snubber is most effective in
peaks, or Surge Capacitor for (Gray Book) 8
mitigating fast-rising transient volt-
protection from fast-rising transient. ■ IEEE Standard 141—Electric Power
ages, and in attenuating reflections
Please note that the surge arresters Distribution for Industrial Plants
and resonances before they have a
or surge capacitor alone may not (Red Book)
9
chance to build up, but does not limit
provide adequate surge protection
the peak magnitude of the transient.
from escalating voltages caused by
Therefore, the RC Snubber alone may
circuit resonance. Note that when 10
not provide adequate protection. To
applying surge capacitors on both
limit peak magnitude of the transient,
sides of a circuit breaker, the surge
application of a surge arrester should
capacitor on one side of the breaker 11
also be considered.
must be an RC Snubber or RC Snubber
RC Snubber with Surge Suppressor with surge suppressor, to mitigate
possible virtual current chopping.
12
This type of device consists of parallel
combination of Resistor (R) and Zinc Good protection: Surge arrester in
Oxide Voltage Suppressor (ZnO), parallel with surge capacitor for 13
connected in series with a Surge protection from high overvoltage peaks
Capacitor. The resistor R is sized to and fast rising transient. This option
match the surge impedance of the load may not provide adequate surge 14
cables, typically 20 to 30 ohms. The protection from escalating voltages
ZnO is a gapless metal-oxide nonlinear caused by circuit resonance. When
arrester, set to trigger at 1 to 2 PU applying surge capacitors on both 15
voltage, where 1 PU = 1.412*(VL-L/1.732). sides of a circuit breaker, the surge
The Surge Capacitor is typically sized to capacitor on one side of the breaker
be 0.15 to 0.25 microfarad. As with RC must be an RC Snubber or RC Snubber 16
Snubber, under normal operating with surge suppressor, to mitigate
conditions, impedance of the capacitor possible virtual current chopping.
is very high, effectively “isolating” the 17
resistor R and ZnO from the system
at normal power frequencies, and
minimizing heat dissipation during 18
normal operation.

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.6-12 Power Distribution Systems
Grounding/Ground Fault Protection August 2017
Sheet 01 080

Table 1.6-3. Surge Arrester Selections—Recommended Ratings


i Service Distribution Class Arresters Station Class Arresters
Voltage Solidly Low Resistance High Resistance or Solidly Low Resistance High Resistance or
Line-to-Line Grounded System Grounded System Ungrounded System Grounded System Grounded System Ungrounded System
ii kV
Arrester Ratings kV Arrester Ratings kV
Nominal MCOV Nominal MCOV Nominal MCOV Nominal MCOV Nominal MCOV Nominal MCOV

1 2.30 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55 3 2.55


2.40 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10
3.30 3 2.55 3 2.55 6 5.10 3 2.55 3 2.55 6 5.10
2 4.00
4.16
3
6
2.55
5.10
6
6
5.10
5.10
6
6
5.10
5.10
3
6
2.55
5.10
6
6
5.10
5.10
6
6
5.10
5.10
4.76 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
4.80 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
3 6.60 6 5.10 6 5.10 9 7.65 6 5.10 6 5.10 9 7.65
6.90 6 5.10 6 5.10 9 7.65 6 5.10 9 7.65 9 7.65
7.20 6 5.10 6 5.10 10 8.40 6 5.10 9 7.65 10 8.40
4 8.32 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20
8.40 9 7.65 9 7.65 12 10.20 9 7.65 9 7.65 12 10.20
11.00 9 7.65 9 7.65 15 12.70 9 7.65 10 8.40 15 12.70
5 11.50
12.00
9
10
7.65
8.40
10
10
8.40
8.40
18
18
15.30
15.30
9
10
7.65
8.40
12
12
10.20
10.20
18
18
15.30
15.30
12.47 10 8.40 12 10.20 18 15.30 10 8.40 12 10.20 18 15.30
13.20 12 10.20 12 10.20 18 15.30 12 10.20 12 10.20 18 15.30
6 13.80 12 10.20 12 10.20 18 15.30 12 10.20 15 12.70 18 15.30
14.40 12 10.20 12 10.20 21 17.00 12 10.20 15 12.70 21 17.00
18.00 15 12.70 15 12.70 27 22.00 15 12.70 18 15.30 27 22.00
7 20.78 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40
22.00 18 15.30 18 15.30 30 24.40 18 15.30 21 17.00 30 24.40
22.86 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
8 23.00 18 15.30 21 17.00 — — 18 15.30 24 19.50 36 29.00
24.94 21 17.00 24 19.50 — — 21 17.00 24 19.50 36 29.00
25.80 21 17.00 24 19.50 — — 21 17.00 24 19.50 36 29.00
26.40 21 17.00 24 19.50 — — 21 17.00 27 22.00 39 31.50
9 33.00 27 22.00 30 24.40 — — 27 22.00 36 29.00 45 36.50
34.50 30 24.40 30 24.40 — — 30 24.40 36 29.00 48 39.00
38.00 30 24.40 — — — — 30 24.40 36 29.00 — —
10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-1
August 2017 Typical Components of a Power System
Sheet 01 081

Typical Power System Because the majority of medium- and Power Equipment Losses
i
low-voltage switchgear is mounted
Components indoors, they are typically provided Table 1.7-1. Power Equipment Losses
in NEMA 1A enclosures. In these Equipment Watts
The System One-line on Page 1.2-4, applications, ventilation openings are Loss ii
illustrates schematically the various normally provided to allow heat to Medium-Voltage Switchgear (Indoor, 5 and 15 kV)
types of power distribution equipment escape from the enclosures. Where 1200 A breaker 600
that an engineer will encounter during required, optional dust screens and 2000 A breaker 1400 1
the design of a power system. It is gasketing can be provided. 3000 A breaker 2100
important to consider the various 4000 A breaker 3700
physical attributes of the various pieces Many indoor applications are in base- Medium-Voltage Switchgear (Indoor, 5 and 15 kV) 2
of electrical equipment that will be ments or areas where condensation 600 A unfused switch 500
utilized as well as the constraints that on the ceiling may leak on top of the 1200 A unfused switch 750
will be encountered in their application. switchgear. Additional concerns may 100 A CL fuses 840 3
arise where sprinklers are provided Medium-Voltage Starters (Indoor, 5 kV)
Electrical equipment that distributes above the switchgear or alternately,
power has a heat loss due to the 400 A starter FVNR 600
impedance and/or resistance of its
on the floor above. Eaton can provide 800 A starter FVNR 1000 4
“sprinkler resistant” low-voltage 600 A fused switch 500
conductors. This heat is radiated into switchgear or low- and medium- 1200 A fused switch 800
the electrical room where the equip-
ment is placed and must be removed
voltage switchgear with a drip hood. Low-Voltage Switchgear (Indoor, 480 V) 5
to ensure excess heat does not cause For outdoor environments, this equip- 800 A breaker 400
1600 A breaker 1000
failures. Table 1.7-1 provides heat loss ment may be mounted in a NEMA 3R
in watts for typical power distribution drip-proof enclosure. Where equipment
2000 A breaker 1500 6
3200 A breaker 2400
equipment that may be used in the is located outdoors, the humidity in the 4000 A breaker 3000
sizing of HVAC equipment. air may condense during evening
hours, resulting in water droplets fall-
5000 A breaker 4700 7
As indicated on the one-line, a Fuse limiters—800 A CB 200
ing on the bus bars in the equipment. Fuse limiters—1600 A CB 500
number of distribution components, Under these circumstances, an optional
are provided with a description of the space heater may be provided and
Fuse limiters—2000 A CB 750
8
Fuse truck—3200 A CB 3600
physical structure in which they are to wired to a thermostat or humidistat Fuse truck—4000 A CB 4500
be enclosed. The National Electrical for control.
Manufacturers Association (NEMA) Structures—3200 A
Structures—4000 A
4000
5000
9
has developed a set of standards to Because many countries around Structures—5000 A 7000
ensure the consistent application the world refer to International
performance of enclosures. Electrotechnical Commission
High resistance grounding 1200 10
Panelboards (Indoor, 480 V)
standards (IEC), designers should
As an example, the panelboard shown reference Table 1.7-5 to determine the 225 A, 42 circuit 300
in Figure 1.2-2 is called out as being appropriate alternate enclosure rating. Low-Voltage Busway (Indoor, Copper, 480 V) 11
NEMA 4X. Table 1.7-2 and Table 1.7-3,
800 A 44 per foot
show the various performance data 1200 A 60 per foot
for these enclosures in indoor and 1350 A 66 per foot 12
outdoor applications respectively. 1600 A 72 per foot
Table 1.7-4 covers enclosures to be 2000 A 91 per foot
installed in explosive or hazardous 2500 A 103 per foot 13
environments. 3200 A 144 per foot
4000 A 182 per foot
5000 A 203 per foot 14
Motor Control Centers (Indoor, 480 V)
NEMA Size 1 starter 39
NEMA Size 2 starter 56 15
NEMA Size 3 starter 92
NEMA Size 4 starter 124
NEMA Size 5 starter 244 16
Structures 200
Adjustable Frequency Drives (Indoor, 480 V)
Adjustable frequency drives > 96% 17
efficiency

Note: The information provided on power 18


equipment losses is generic data intended
to be used for sizing of HVAC equipment.
19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-2 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 082

Enclosures
i The following are reproduced from NEMA 250.
Table 1.7-2. Comparison of Specific Applications of Enclosures for Indoor Nonhazardous Locations
ii Provides a Degree of Protection Against the Enclosure Type
Following Environmental Conditions 11 21 4 4X 5 6 6P 12 12K 13
1 Incidental contact with the enclosed equipment ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Falling dirt ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Falling liquids and light splashing ■ ■ ■ ■ ■ ■ ■ ■ ■
2 Circulating dust, lint, fibers and flyings 2 ■ ■ ■ ■ ■ ■ ■
Settling airborne dust, lint, fibers and flyings 2 ■ ■ ■ ■ ■ ■ ■ ■
Hosedown and splashing water ■ ■ ■ ■
■ ■ ■
3 Oil and coolant seepage
Oil or coolant spraying and splashing ■
Corrosive agents ■ ■
Occasional temporary submersion ■ ■
4 Occasional prolonged submersion ■
1 These enclosures may be ventilated.
2 These fibers and flying are nonhazardous materials and are not considered the Class III type ignitable fibers or combustible flyings. For Class III type
5 ignitable fibers or combustible flyings, see the National Electrical Code, Article 500.

Table 1.7-3. Comparison of Specific Applications of Enclosures for Outdoor Nonhazardous Locations
6 Provides a Degree of Protection Against the Enclosure Type
Following Environmental Conditions 3 3R 3 3S 4 4X 6 6P

7 Incidental contact with the enclosed equipment


Rain, snow and sleet 4














Sleet 5 ■
■ ■ ■ ■ ■ ■
8 Windblown dust
Hosedown ■ ■ ■ ■
Corrosive agents ■ ■
Occasional temporary submersion ■ ■
9 Occasional prolonged submersion ■
3 These enclosures may be ventilated.
4 External operating mechanisms are not required to be operable when the enclosure is ice covered.
10 5 External operating mechanisms are operable when the enclosure is ice covered.

Table 1.7-4. Comparison of Specific Applications of Enclosures for Indoor Hazardous Locations
11 Provides a Degree of Protection Against Class Enclosure Types Enclosure Type
Atmospheres Typically Containing 7 and 8, Class I Groups 6 9, Class II Groups 6
(For Complete Listing, See NFPA 497M) A B C D E F G 10
12
Acetylene I ■
Hydrogen, manufactured gas I ■
diethyl ether, ethylene, cyclopropane I ■
13 Gasoline, hexane, butane, naphtha, propane,
acetone, toluene, isoprene I ■
Metal dust II ■
14 Carbon black, coal dust, coke dust II ■
Flour, starch, grain dust II ■
Fibers, flyings 7 III ■

15 Methane with or without coal dust MSHA
6 For Class III type ignitable fibers or combustible flyings, see the National Electrical Code, Article 500.
7 Due to the characteristics of the gas, vapor or dust, a product suitable for one class or group may not be suitable for another class or group unless so
16 marked on the product.
Note: If the installation is outdoors and/or additional protection is required by Tables 1.7-2 and 1.7-3, a combination-type enclosure is required.

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-3
August 2017 Typical Components of a Power System
Sheet 01 083

Table 1.7-5. Conversion of NEMA Enclosure Type Ratings to IEC 60529 Enclosure Classification Designations (IP) (From NEMA Publication 250)
(Cannot be Used to Convert IEC Classification Designations to NEMA Type Ratings) i

IP NEMA Enclosure Type IP


ii
First 1 2 3 3R 3S 4 4X 5 6 6P 12 12K 13 Second
Character Character
IP0– IP–0 1
IP1– IP–1
IP2– IP–2
IP3– IP–3 2
IP4– IP–4
IP5– IP–5
IP6– IP–6
IP–7 3
IP–8
A B A B A B A B A B A B A B A B A B A B A B A B A B
A = A shaded block in the “A” column indicates that the NEMA Enclosure Type exceeds the requirements for the respective IEC 60529 4
IP First Character Designation. The IP First Character Designation is the protection against access to hazardous parts and solid
foreign objects.
B = A shaded block in the “B” column indicates that the NEMA Enclosure Type exceeds the requirements for the respective IEC 60529 5
IP Second Character Designation. The IP Second Character Designation is the protection against the ingress of water.

EXAMPLE OF TABLE USE 6


An IEC IP45 Enclosure Rating is specified. What NEMA Type Enclosures meet and exceed the IP45 rating?

Referencing the first character, 4, in the IP rating and the row designated “IP4–” in the leftmost column in the 7
table; the blocks in Column “A” for NEMA Types 3, 3S, 4, 4X, 5, 6, 6P, 12, 12K and 13 are shaded. These NEMA
ratings meet and exceed the IEC protection requirements against access to hazardous parts and solid foreign
objects. Referencing the second character, 5, in the IP rating and the row designated “IP–5” in the rightmost 8
column in the table; the blocks in Column “B” for NEMA Types 3, 3S, 4, 4X, 6 and 6P are shaded. These NEMA
ratings meet and exceed the IEC requirements for protection against the ingress of water. The absence of shading
in Column “B” beneath the “NEMA Enclosure Type 5” indicates that Type 5 does not meet the IP45 protection 9
requirements against the ingress of water. Likewise, the absence of shading in Column “B” for NEMA Type 12,
12K and 13 enclosures indicates that these enclosures do not meet the IP45 requirements for protection against
the ingressof water. Only Types 3, 3S, 4, 4X, 6 and 6P have both Column “A” in the “IP4–” row and Column “B”
in the “IP–5” row shaded and could be used in an IP45 application.
10
The NEMA Enclosure Type 3 not only meets the IP45 Enclosure Rating, but also exceeds the IEC requirements 11
because the NEMA Type requires an outdoor corrosion test; a gasket aging test; a dust test; an external icing
test; and no water penetration in the rain test. Slight differences exist between the IEC and NEMA test methods,
but the IEC rating permits the penetration of water if “it does not deposit on insulation parts, or reach live parts.” 12
The IEC rating does not require a corrosion test; gasket aging test; dust test or external icing test. Because the
NEMA ratings include additional test requirements, this table cannot be used to select IP Designations for NEMA
rated enclosure specifications. 13
IEC 60529 specifies that an enclosure shall only be designated with a stated degree of protection indicated by
the first characteristic numeral if it also complies with all lower degrees of protection. Furthermore, IEC 60529 14
states that an enclosure shall only be designated with a degreeof protection indicated by the second characteristic
numeral if it also complies with all lower degrees of protection up to and including the secondcharacteristic
numeral 6. An enclosure designated with a second characteristic numeral 7 or 8 only is considered unsuitable 15
for exposure to water jets (designated by second characteristic numeral 5 or 6) and need not comply with
requirements for numeral 5 or 6 unless it is dual coded. Because the IEC protection requirements become more
stringent with increasing IP character value up through 6, once a NEMA Type rating meets the requirements for 16
an IP designation up through 6, it will also meet the requirements for all lower IP designations. This is apparent
from the shaded areas shown in the table.
17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-4 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 084

i Transformers Transformers were the key component For example, a 300 kVA three-phase
in the growth of alternating current power transformer has 5% impedance
The work of early electrical pioneer (AC) distribution systems over whereas higher kVA transformers have
Michael Faraday, in documenting the the direct current (DC) alternative 5.75%. See Table 1.7-7 for information
ii principal of electro-magnetic induction, promoted by Thomas Edison. on transformer secondary FLA ratings
led to a discovery that voltage flowing and short-circuit current available.
NEMA has worked through the years
through a coil wrapped around a donut
1 shaped piece of iron could induce a
to standardize transformer primary Because there are a number of
and secondary full load amperes categories with the ANSI C57 family,
voltage in a second coil of wire also
(FLA). Table 1.7-6 is a compilation of the design engineer needs to pinpoint
wrapped around the iron. This
2 discovery was key to Faraday’s work
various transformers kVA and primary the transformer design type. When
voltages along with their primary FLA. designing systems involving different
in 1831 and became the basis for
types of transformers such as larger
others in the development of Transformers are designed with a
3 transformer technology. specific number of primary versus
fluid-filled units like the 7500 kVA
(7.5 MVA) unit “T1” shown in
secondary winding turns. These are Figure 1.2-2 on Page 1.2-4, the
While Sebastian Ferranti and others
a ratio of the primary voltage to the
4 continued to develop and patent
secondary voltage. Each winding
impedance can be 6.5% or greater.
transformer technology, it was a
has a specific amount of resistance, Table 1.7-8 through Table 1.7-12
demonstration of a power transformer
however, when first energized, acts provide further information on the
5 during 1884 in Turin, Italy that caught
like a short circuit drawing a high impedances and electrical characteris-
the attention of George Westinghouse.
inrush current that falls off as the tics of various styles of transformers.
In 1885, Westinghouse purchased the
core material magnetizes. This Note that smaller dry-type distribution
6 American rights to manufacture the
combination of electrical properties transformers may not have uniform
transformer developed by Lucien
is termed impedance. impedances across various manufac-
Gaulard and John Gibbs.
turers due to design characteristics
7 In subsequent years, William
Dry-type power transformers that meet and construction tolerances.
the ANSI C57 standard follow a specific
Stanley, Jr., Westinghouse’s chief
requirement for impedance based on Eaton markets dry-type distribution
8 engineer, would alter the Gaulard and
Gibbs design by changing the series
their kVA rating and type. Lower transformers (see Section 19),
impedances allow more secondary secondary substation transformers
coil arrangement to a parallel coil
short-circuit current to flow versus in liquid and dry configurations
9 design. Stanley also developed the
higher impedance versions. (see Section 14), liquid and dry net-
“E” coil using laminated stamped steel
work transformers (see Section 18),
core pieces. Both of these innovations
tamper-proof pad-mounted, liquid
10 improved the transformer by stabiliz-
filled transformers (see Section 17),
ing its regulation as well as improving
and liquid-filled and dry-type primary
its manufacturability and efficiency.
substation transformers (see Section
11 13). The features of each type of
transformer are explained with the
individual sections of this guide.
12
Table 1.7-6. Transformer Full-Load Current, Three-Phase, Self-Cooled Ratings
Voltage, Line-to-Line
13 kVA 208 240 480 600 2400 4160 7200 12,000 12,470 13,200 13,800 22,900 34,400

30 83.3 72.2 36.1 28.9 7.22 4.16 2.41 1.44 1.39 1.31 1.26 0.75 0.50
14 45
75
125
208
108
180
54.1
90.2
43.3
72.2
10.8
18.0
6.25
10.4
3.61
6.01
2.17
3.61
2.08
3.47
1.97
3.28
1.88
3.14
1.13
1.89
0.76
1.26
112-1/2 312 271 135 108 27.1 15.6 9.02 5.41 5.21 4.92 4.71 2.84 1.89
150 416 361 180 144 36.1 20.8 12.0 7.22 6.94 6.56 6.28 3.78 2.52
15 225 625 541 271 217 54.1 31.2 18.0 10.8 10.4 9.84 9.41 5.67 3.78
300 833 722 361 289 72.2 41.6 24.1 14.4 13.9 13.1 12.6 7.56 5.04
500 1388 1203 601 481 120 69.4 40.1 24.1 23.1 21.9 20.9 12.6 8.39
16 750 2082 1804 902 722 180 104 60.1 36.1 34.7 32.8 31.4 18.9 12.6
1000 2776 2406 1203 962 241 139 80.2 48.1 46.3 43.7 41.8 25.2 16.8
1500 4164 3608 1804 1443 361 208 120 72.2 69.4 65.6 62.8 37.8 25.2
17 2000 — 4811 2406 1925 481 278 160 96.2 92.6 87.5 83.7 50.4 33.6
2500 — — 3007 2406 601 347 200 120 116 109 105 63.0 42.0
3000 — — 3609 2887 722 416 241 144 139 131 126 75.6 50.4
3750 — — 4511 3608 902 520 301 180 174 164 157 94.5 62.9
18 5000 — — — 4811 1203 694 401 241 231 219 209 126 83.9
7500 — — — — 1804 1041 601 361 347 328 314 189 126
10,000 — — — — 2406 1388 802 481 463 437 418 252 168
19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-5
August 2017 Typical Components of a Power System
Sheet 01 085

Table 1.7-7. Secondary Short-Circuit Current of Typical Power Transformers


Trans- Maximum 208 V, Three-Phase 240 V, Three-Phase 480 V, Three-Phase 600 V, Three-Phase i
former Short- Rated Short-Circuit Current Rated Short-Circuit Current Rated Short-Circuit Current Rated Short-Circuit Current
Rating Circuit Load rms Symmetrical Amps Load rms Symmetrical Amps Load rms Symmetrical Amps Load rms Symmetrical Amps
Three-
Phase
kVA
Available
Contin- Trans- 50% Com- Contin- Trans- 100% Com- Contin- Trans- 100% Com- Contin- Trans- 100% Com-
ii
uous former Motor bined uous former Motor bined uous former Motor bined uous former Motor bined
kVA and from Current, Current, Current, Current,
Impedance Primary Alone 1 Load 2 Alone 1 Load 2 Alone 1 Load 2 Alone 1 Load 2
Amps Amps Amps Amps
Percent System 1
300 50,000 834 14,900 1700 16,600 722 12,900 2900 15,800 361 6400 1400 7800 289 5200 1200 6400
5% 100,000 834 15,700 1700 17,400 722 13,600 2900 16,500 361 6800 1400 8200 289 5500 1200 6700
150,000 834 16,000 1700 17,700 722 13,900 2900 16,800 361 6900 1400 8300 289 5600 1200 6800 2
250,000 834 16,300 1700 18,000 722 14,100 2900 17,000 361 7000 1400 8400 289 5600 1200 6800
500,000 834 16,500 1700 18,200 722 14,300 2900 17,200 361 7100 1400 8500 289 5700 1200 6900
Unlimited 834 16,700 1700 18,400 722 14,400 2900 17,300 361 7200 1400 8600 289 5800 1200 7000 3
500 50,000 1388 21,300 2800 25,900 1203 20,000 4800 24,800 601 10,000 2400 12,400 481 8000 1900 9900
5% 100,000 1388 25,200 2800 28,000 1203 21,900 4800 26,700 601 10,900 2400 13,300 481 8700 1900 10,600
150,000 1388 26,000 2800 28,800 1203 22,500 4800 27,300 601 11,300 2400 13,700 481 9000 1900 10,900
250,000 1388 26,700 2800 29,500 1203 23,100 4800 27,900 601 11,600 2400 14,000 481 9300 1900 11,200
4
500,000 1388 27,200 2800 30,000 1203 23,600 4800 28,400 601 11,800 2400 14,200 481 9400 1900 11,300
Unlimited 1388 27,800 2800 30,600 1203 24,100 4800 28,900 601 12,000 2400 14,400 481 9600 1900 11,500
750 50,000 2080 28,700 4200 32,900 1804 24,900 7200 32,100 902 12,400 3600 16,000 722 10,000 2900 12,900 5
5.75% 100,000 2080 32,000 4200 36,200 1804 27,800 7200 35,000 902 13,900 3600 17,500 722 11,100 2900 14,000
150,000 2080 33,300 4200 37,500 1804 28,900 7200 36,100 902 14,400 3600 18,000 722 11,600 2900 14,500
250,000 2080 34,400 4200 38,600 1804 29,800 7200 37,000 902 14,900 3600 18,500 722 11,900 2900 14,800 6
500,000 2080 35,200 4200 39,400 1804 30,600 7200 37,800 902 15,300 3600 18,900 722 12,200 2900 15,100
Unlimited 2080 36,200 4200 40,400 1804 31,400 7200 38,600 902 15,700 3600 19,300 722 12,600 2900 15,500
1000
5.75%
50,000
100,000
2776
2776
35,900
41,200
5600
5600
41,500 2406
46,800 2406
31,000
35,600
9800
9800
40,600 1203
45,200 1203
15,500
17,800
4800
4800
20,300
22,600
962
962
12,400
14,300
3900
3900
16,300
18,200
7
150,000 2776 43,300 5600 48,900 2406 37,500 9800 47,100 1203 18,700 4800 23,500 962 15,000 3900 18,900
250,000 2776 45,200 5600 50,800 2406 39,100 9800 48,700 1203 19,600 4800 24,400 962 15,600 3900 19,500
500,000 2776 46,700 5600 52,300 2406 40,400 9800 50,000 1203 20,200 4800 25,000 962 16,200 3900 20,100 8
Unlimited 2776 48,300 5600 53,900 2406 41,800 9800 51,400 1203 20,900 4800 25,700 962 16,700 3900 20,600
1500 50,000 4164 47,600 8300 55,900 3609 41,200 14,400 55,600 1804 20,600 7200 27,800 1444 16,500 5800 22,300
5.75% 100,000
150,000
4164
4164
57,500
61,800
8300
8300
65,800 3609
70,100 3609
49,800
53,500
14,400
14,400
64,200 1804
57,900 1804
24,900 7200 32,100 1444 20,000 5800 25,800 9
26,700 7200 33,900 1444 21,400 5800 27,200
250,000 4164 65,600 8300 73,900 3609 56,800 14,400 71,200 1804 28,400 7200 35,600 1444 22,700 5800 28,500
500,000 4164
Unlimited 4164
68,800
72,500
8300
8300
77,100 3609
80,800 3609
59,600
62,800
14,400
14,400
74,000 1804
77,200 1804
29,800
31,400
7200
7200
37,000 1444
38,600 1444
23,900
25,100
5800
5800
29,700
30,900
10
2000 50,000 — — — — — — — — 2406 24,700 9600 34,300 1924 19,700 7800 27,500
5.75% 100,000 — — — — — — — — 2406 31,000 9600 40,600 1924 24,800 7800 32,600
150,000 — — — — — — — — 2406 34,000 9600 43,600 1924 27,200 7800 35,000 11
250,000 — — — — — — — — 2406 36,700 9600 46,300 1924 29,400 7800 37,200
500,000 — — — — — — — — 2406 39,100 9600 48,700 1924 31,300 7800 39,100
Unlimited — — — — — — — — 2406 41,800 9600 51,400 1924 33,500 7800 41,300 12
2500 50,000 — — — — — — — — 3008 28,000 12,000 40,000 2405 22,400 9600 32,000
5.75% 100,000 — — — — — — — — 3008 36,500 12,000 48,500 2405 29,200 9600 38,800
150,000
250,000 —
— —













3008
3008
40,500
44,600
12,000
12,000
52,500 2405
56,600 2405
32,400
35,600
9600
9600
42,000
45,200
13
500,000 — — — — — — — — 3008 48,100 12,000 60,100 2405 38,500 9600 48,100
Unlimited — — — — — — — — 3008 52,300 12,000 64,300 2405 41,800 9600 51,400
3000 50,000 — — — — — — — — 3609 30,700 14,000 44,700 2886 24,600 11,500 36,100
14
5.75% 100,000 — — — — — — — — 3609 41,200 14,000 55,200 2886 33,000 11,500 44,500
150,000 — — — — — — — — 3609 46,600 14,000 60,600 2886 37,300 11,500 48,800
250,000 — — — — — — — — 3609 51,900 14,000 65,900 2886 41,500 11,500 53,000 15
500,000 — — — — — — — — 3609 56,800 14,000 70,800 2886 45,500 11,500 57,000
Unlimited — — — — — — — — 3609 62,800 14,000 76,800 2886 50,200 11,500 61,700
3750
5.75%
50,000
100,000
















4511
4511
34,000
47,500
18,000
18,000
52,000 3608
65,500 3608
27,200
38,000
14,400
14,400
41,600
52,400
16
150,000 — — — — — — — — 4511 54,700 18,000 72,700 3608 43,700 14,400 58,100
250,000 — — — — — — — — 4511 62,200 18,000 80,200 3608 49,800 14,400 64,200
500,000 — — — — — — — — 4511 69,400 18,000 87,400 3608 55,500 14,400 69,900 17
Unlimited — — — — — — — — 4511 78,500 18,000 96,500 3608 62,800 14,400 77,200
1 Short-circuit capacity values shown correspond to kVA and impedances shown in this table. For impedances other than these, short-circuit currents
are inversely proportional to impedance. 18
2 The motor’s short-circuit current contributions are computed on the basis of motor characteristics that will give four times normal current.
For 208 V, 50% motor load is assumed while for other voltages 100% motor load is assumed. For other percentages, the motor short-circuit
current will be in direct proportion. 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-6 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 086

Approximate Impedance Data Table 1.7-11. 15 kV Class Primary— Table 1.7-13. 600V Primary Class Three-Phase
i Table 1.7-8. Typical Impedances—
Dry-Type Substation Transformers DOE 2016 Energy-Efficient Dry-Type
kVA %Z %R %X X/R
Distribution Transformers, Copper Wound
Three-Phase Transformers Liquid-Filled 1
150 °C Rise kVA %Z %X %R X/R
ii kVA Liquid-Filled
150 °C Rise Copper
300 4.50 2.87 3.47 1.21
Network Padmount
500 5.75 2.66 5.10 1.92 15 3.10 1.59 2.66 0.60
750 5.75 2.47 5.19 2.11 30 2.52 0.79 2.39 0.33
1 37.5
45



— 1000 5.75 2.16 5.33 2.47 45 3.80 2.60 2.77 0.94
50 — — 1500 5.75 1.87 5.44 2.90 75 2.84 1.94 2.08 0.93
75 — 3.4 2000 5.75 1.93 5.42 2.81 112.5 3.63 3.11 1.88 1.66
2 112.5 — 3.4 2500 5.75 1.74 5.48 3.15 150 3.02 2.64 1.46 1.81
150 — 3.4
80 °C Rise 225 4.34 3.98 1.73 2.31
225 — 3.4 300 3.48 3.19 1.38 2.31
3 300 5.00 3.4
300
500
4.50
5.75
1.93
1.44
4.06
5.57
2.10
3.87 115 °C Rise Copper
500 5.00 4.6
750 5.75 1.28 5.61 4.38
750 5.00 5.75 15 2.90 1.59 2.43 0.66
1000 5.75 0.93 5.67 6.10 30 2.35 0.97 2.14 0.45
4 1000
1500
5.00
7.00
5.75
5.75
1500 5.75 0.87 5.68 6.51 45 3.85 2.87 2.57 1.12
2000 5.75 0.66 5.71 8.72
2000 7.00 5.75 75 2.86 2.12 1.92 1.10
2500 5.75 0.56 5.72 10.22 112.5 4.02 3.59 1.82 1.97
2500 7.00 5.75
5 3000 — 5.75 150 3.34 3.05 1.37 2.23
3750 — 6.00
Table 1.7-12. 600 V Primary Class Three- 225 5.03 4.78 1.58 3.02
5000 — 6.50 Phase DOE 2016 Energy-Efficient Dry-Type 300 4.14 3.94 1.29 3.06
6 1 Values are typical. For guaranteed values,
Distribution Transformers, Aluminum Wound 80 °C Rise Copper
refer to transformer manufacturer. kVA %Z %X %R X/R 15 3.09 2.04 2.32 0.88
150 °C Rise Aluminum 30 2.53 1.73 1.85 0.94
7 Table 1.7-9. 15 kV Class Primary— 45 1.70 1.16 1.25 0.93
15 4.04 2.08 3.46 0.60
Oil Liquid-Filled Substation Transformers 30 2.52 1.13 2.25 0.50 75 2.42 2.07 1.25 1.66
45 3.75 2.64 2.67 0.99 112.5 2.27 1.98 1.09 1.81
8 kVA %Z %R %X X/R
75 4.05 3.34 2.29 1.46
150 2.89 2.65 1.15 2.31
65 °C Rise 225 3.11 2.95 0.96 3.06
112.5 4.66 4.22 1.99 2.12
112.5 5.00 1.71 4.70 2.75
150 3.48 3.09 1.61 1.92
9 150
225
5.00
5.00
1.88
1.84
4.63
4.65
2.47
2.52 225 4.20 3.96 1.39 2.85
300 5.00 1.35 4.81 3.57 300 4.46 4.26 1.32 3.23
500 5.00 1.50 4.77 3.18 115 °C Rise Aluminum
10 750 5.75 1.41 5.57 3.96
15 3.77 2.08 3.14 0.66
1000 5.75 1.33 5.59 4.21 30 2.34 1.37 1.90 0.72
1500 5.75 1.12 5.64 5.04 45 4.26 3.44 2.52 1.37
11 2000 5.75 0.93 5.67 6.10
75 4.45 3.90 2.14 1.83
2500 5.75 0.86 5.69 6.61 112.5 5.17 4.81 1.89 2.54
150 3.89 3.59 1.49 2.41
12 Table 1.7-10. DOE 2016 Transformer 225 4.90 4.73 1.28 3.69
Efficiencies—Medium-Voltage Three-Phase 300 4.80 4.65 1.21 3.85
Distribution Transformers 1 80 °C Rise Aluminum
13 kVA % Efficiency 15 4.19 2.94 2.98 0.99
Liquid- Dry Transformers 30 2.50 1.76 1.78 0.99
Filled 45 2.43 2.01 1.37 1.46
14 All 25–45 46–95 M96 kV 75 3.11 2.81 1.32 2.12
BILs kV BIL kV BIL BIL 112.5 2.61 2.31 1.21 1.92
150 2.80 2.64 0.93 2.85
15 15 98.65 97.5 97.18 — 225 3.35 3.20 0.99 3.23
30 98.83 97.9 97.63 —
45 98.92 98.1 97.86 —
16 75 99.03 98.33 98.13 —
112.5 99.11 98.52 98.36 —
150 99.16 98.65 98.51 —
17 225
300
99.23
99.27
98.82
98.93
98.69
98.81
98.57
98.69
500 99.35 99.09 98.99 98.89

18 750
1000
99.40
99.43
99.21
99.28
99.12
99.2
99.02
99.11
1500 99.48 99.37 99.3 99.21
2000 99.51 99.43 99.36 99.28
19 2500 99.53 99.47 99.41 99.33
1 Based on transformer operating at 50% of
nameplate base kVA.
20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-7
August 2017 Typical Components of a Power System
Sheet 01 087

Transformer Loss Data Transformer losses for various At 0% load:


Data for the following calculations can
loading can be estimated in the 1800 watts i
following manner. The no load watt
be found in Section 14—Secondary losses of the transformer are due to At 50% load:
Unit Substations. magnetization and are present ii
1800 watts + (13,300)(0.5)2 =
Transformer Losses at Reduced Loads whenever the transformer is 1800 watts + 3325 watts = 5125 watts
energized. The load watt losses are
Information on losses based on actual At 100% load: 1
the difference between the no load
transformer test data can be obtained 1800 watts + 13,300 watts = 15,100 watts
watt losses and the full load watt
from the manufacturer. Transformer
losses. The load watt losses are
manufacturers provide no load watt At 110% load: 2
proportional to I2R and can be
losses and total watt losses in accor- 1800 watts + (13,300)(1.1)2 =
estimated to vary with the transformer
dance with ANSI standards. The 1800 watts + 16,093 watts = 17,893 watts
load by the square of the load current.
calculated difference between the 3
no load losses and the total losses For example, the approximate watts Because transformer losses vary
are typically described as the load loss data for a 1000 kVA oil-filled between designs and manufacturers,
losses. Although transformer coils additional losses such as from
are manufactured with either aluminum
substation transformer is shown in
cooling fans can be ignored for
4
the table as having 1800 watts no
or copper conductors, the industry load losses and 15,100 watts full load these approximations.
has sometimes referred to these load losses, so the load losses are approxi- Note: 1 watthour = 3.413 Btu. 5
losses as the “copper losses.” mately 13,300 watts (15,100–1800). The
transformer losses can be calculated
for various loads as follows. 6

10

11

12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-8 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 088

Table 1.7-7. Three-Phase Transformer Winding Connections


i Phasor Notes
Diagram

ii DELTA-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire service with a mid-tap ground.
Phasor H2 X2
Diagram:
1

2 H1 H3 X1 X3

Angular Displacement (Degrees): 0


3 DELTA-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire grounded service with
Phasor H2 X2 XO grounded.
4 Diagram:
3. With XO grounded, the transformer acts as a ground source for the
secondary system.
X1 X0
4. Fundamental and harmonic frequency zero-sequence currents in the secondary
5 H1 H3
lines supplied by the transformer do not flow in the primary lines. Instead the
X3 zero sequence currents circulate in the closed delta primary windings.
Angular Displacement (Degrees): 30 5. When supplied from an effectively grounded primary system does not see load
6 unbalances and ground faults in the secondary system.
WYE-DELTA Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire delta service with a mid-tap ground.
7 Phasor
Diagram:
H2 X2 3. Grounding the primary neutral of this connection would create a ground source
for the primary system. This could subject the transformer to severe overloading
during a primary system disturbance or load unbalance.
X1
8 4. Frequently installed with mid-tap ground on one leg when supplying
combination three-phase and single-phase load where the three-phase
H1 H3 load is much larger than single-phase load.
X3
9 Angular Displacement (Degrees): 30 5. When used in 25 kV and 35 kV three-phase four-wire primary systems,
ferroresonance can occur when energizing or de-energizing the transformer
using single-pole switches located at the primary terminals. With smaller kVA
transformers the probability of ferroresonance is higher.
10 WYE-WYE Connection 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service only, even if XO is grounded.
Phasor H2 X2 3. This connection is incapable of furnishing a stabilized neutral and its use may
11 Diagram:
result in phase-to-neutral overvoltage (neutral shift) as a result of unbalanced
phase-to-neutral load.
X0
4. If a three-phase unit is built on a three-legged core, the neutral point of the
12 H1 H3 X1 X3
primary windings is practically locked at ground potential.

Angular Displacement (Degrees): 0


13
GROUNDED WYE-WYE Connection 1. Suitable for four-wire effectively grounded source only.
2. Suitable for a three-wire service or for four-wire grounded service with
14 Phasor
Diagram:
H2 X2 XO grounded.
3. Three-phase transformers with this connection may experience stray flux tank
heating during certain external system unbalances unless the core configuration
H0 X0
15 (four or five legged) used provides a return path for the flux.
4. Fundamental and harmonic frequency zero-sequence currents in the secondary
H1 H3 X1 X3
lines supplied by the transformer also flow in the primary lines (and primary
neutral conductor).
16 Angular Displacement (Degrees): 0
5. Ground relay for the primary system may see load unbalances and ground
faults in the secondary system. This must be considered when coordinating
overcurrent protective devices.
17 6. Three-phase transformers with the neutral points of the high-voltage and low-
voltage windings connected together internally and brought out through an
HOXO bushing should not be operated with the HOXO bushing ungrounded
18 (floating). To do so can result in very high voltages in the secondary systems.
DELTA-DELTA Connection with Tap 1. Suitable for both ungrounded and effectively grounded sources.
2. Suitable for a three-wire service or a four-wire service with a mid-tap ground.
19 Phasor
Diagram:
H2 X2 3. When using the tap for single-phase circuits, the single-phase load kVA should
X4 not exceed 5% of the three-phase kVA rating of the transformer. The three-phase
rating of the transformer is also substantially reduced.
20
H1 H3 X1 X3

21 Angular Displacement (Degrees): 0

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-9
August 2017 Typical Components of a Power System
Sheet 01 089

Sound Levels Area Consideration Because values given in Table 1.7-9


In determining permissible sound lev- are in general higher than those given i
Sound Levels of Electrical Equipment els within a building, it is necessary to in Table 1.7-8, the difference must be
for Offices, Hospitals, Schools and consider how the rooms are to be used attenuated by distance and by proper
Similar Buildings and what levels may be objectionable use of materials in the design of ii
Insurance underwriters and building to occupants of the building. The the building. It may appear that a
owners require that the electrical ambient sound level values given in transformer is noisy because the level
apparatus be installed for maximum Table 1.7-8 are representative average in the room where it is located is high. 1
safety and minimum impact on normal values and may be used as a guide in Two transformers of the same sound
functioning of the property. Architects determining suitable building levels. output in the same room increase the
should take particular care with the sound level in the room approximately 2
The decrease in sound level varies at 3 dB, and three transformers by about
designs for hospitals, schools and
an approximate rate of 6 dB for each 5 dB, etc. A good engineer needs to
similar buildings to keep the sound
perception of such equipment as
doubling of the distance from the consider these factors while designing 3
source of sound to the listener. For the electrical rooms and allocating
motors, blowers and transformers
example, if the level 6 ft (1.8 m) from locations for the transformers.
to a minimum.
a transformer is 50 dB, the level at a 4
Even though transformers are distance of 12 ft (3.7 m) would be 44 dB In many buildings, floors between
relatively quiet, resonant conditions and at 24 ft (7.3 m) the level decreases different levels can act like the sound
may exist near the equipment, which to 38 dB, etc. However, this rule applies board in a piano. In these cases, 5
will amplify their normal 120 Hz hum. only to equipment in large areas sounds due to structure-transmitted
Therefore, it is important that consid- equivalent to an out-of-door installation, vibrations originating from the trans-
eration be given to the reduction of with no nearby reflecting surfaces. former are lowered by mounting the 6
amplitude and to the absorption of transformers on vibration dampeners
Table 1.7-8. Typical Sound Levels or isolators. There are a number of
energy at this frequency. This problem
begins in the designing stages of Description Average different sound vibration isolating 7
the equipment and the building. Decibel materials that may be used with
Level (dB) good results.
There are two points worthy of Radio, recording and TV studios 25–30 Dry-type power transformers are often
8
consideration: Theatres and music rooms 30–35
built with an isolator mounted between
Hospitals, auditoriums and churches 35–40
■ What sound levels are desired in the the transformer support and case
normally occupied rooms of this Classrooms and lecture rooms 35–40
members. The natural period of the
9
Apartments and hotels 35–45
building? Private offices and conference rooms 40–45 core and coil structure when mounted
■ To effect this, what sound level in on vibration dampeners is about 10% 10
Stores 45–55
the equipment room and what type Residence (radio, TV off) of the fundamental frequency. The
of associated acoustical treatment and small offices 53 reduction in the transmitted vibration
will give the most economical Medium office (3 to 10 desks) 58 is approximately 98%. 11
installation overall? Residence (radio, TV on) 60
If the floor or beams beneath the
Large store (5 or more clerks) 61
A relatively high sound level in the Factory office 61 transformer are light and flexible,
equipment room does not indicate Large office 64 the isolator must be softer or have 12
an abnormal condition within the Average factory 70 improved characteristics in order to
apparatus. However, absorption may Average street 80 keep the transmitted vibrations to
be necessary if sound originating in a minimum. (Enclosure covers 13
an unoccupied equipment room is Transformer Sound Levels and ventilating louvers are often
objectionable outside the room. Transformers emit a continuous improperly tightened or gasketed
Furthermore, added absorption 120 Hz hum with harmonics when and their vibration can produce 14
material usually is desirable if sound connected to 60 Hz circuits. The unnecessary noise.)
is magnified due to reflections. fundamental frequency is the “hum” The building structure will assist the 15
that annoys people primarily because dampeners if the transformer is
While some sound reduction or of its continuous nature. For purposes
attenuation takes place as the sound mounted above heavy floor members
of reference, sound measuring or if mounted on a heavy floor slab. 16
waves travel through building walls, instruments convert the different
the remainder may be reflected in Positioning of the transformer in
frequencies to 1000 Hz and a 40 dB relation to walls and other reflecting
various directions, resulting in a
build-up or apparent higher levels.
level. Transformer sound levels based
on NEMA publication TR-1 are listed
surfaces has a great effect on reflected 17
This is especially true if resonance noise and resonances. Often, placing
in Table 1.7-9. the transformer at an angle to the
occurs because of room dimensions
or material characteristics. wall, rather than parallel to it, will 18
reduce noise.
Electrical connections to a substation 19
transformer should be made with
flexible braid or conductors;
connections to an individually 20
mounted transformer should be
in flexible conduit.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-10 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 090

Table 1.7-9. Maximum Average Sound Levels


i for Medium-Voltage Transformers—Decibels
kVA Liquid-Filled Transformers Dry-Type Transformers
Self-Cooled Forced-Air Self-Cooled Forced-Air
ii Rating (OA) Cooled Rating (FA) Rating (AA) Cooled Rating (FA)

300 55 — 58 67
1 500
750
56
57

67
60
64
67
67
1000 58 67 64 67
2 1500
2000
60
61
67
67
65
66
68
69
2500 62 67 68 71
3000 63 67 68 71
3 3750 64 67 70 73
5000 65 67 71 73
6000 66 68 72 74
4 7500 67 69 73 75
10,000 68 70 — 76

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-11
August 2017 Typical Components of a Power System
Sheet 01 091

Motor Protection Table 1.7-10. Motor Circuit Protector (MCP), Circuit Breaker and Fusible Switch Selection Guide
Consistent with the 2014 NEC Horsepower Full Load Fuse Size NEC 430.52 Recommended Eaton i
Amperes Maximum Circuit Motor Circuit
430.6(A)(1) circuit breaker, HMCP and (NEC) FLA Amperes
fuse rating selections are based on Breaker Protector Type HMCP
full load currents for induction motors Time Delay Non-Time Delay Amperes Amperes Adj. Range
ii
running at speeds normal for belted 230 V, Three-Phase
motors and motors with normal 1 3.6 10 15 15 7 21–70 1
torque characteristics using data taken 1-1/2 5.2 10 20 15 15 45–150
from NEC Table 430.250 (three-phase). 2 6.8 15 25 15 15 45–150
3 9.6 20 30 20 30 90–300
Actual motor nameplate ratings shall 2
be used for selecting motor running 5 15.2 30 50 30 30 90–300
overload protection. Motors built 7-1/2 22 40 70 50 50 150–500
10 28 50 90 60 50 150–500
special for low speeds, high torque 15 42 80 150 90 70 210–700 3
characteristics, special starting
20 54 100 175 100 100 300–1000
conditions and applications will 25 68 125 225 125 150 450–1500
require other considerations as 30 80 150 250 150 150 450–1500 4
defined in the application section 40 104 200 350 150 150 750–2500
of the NEC. 50 130 250 400 200 150 750–2500
These additional considerations may
60 154 300 500 225 250 1250–2500 5
75 192 350 600 300 400 2000–4000
require the use of a higher rated HMCP, 100 248 450 800 400 400 2000–4000
or at least one with higher magnetic
pickup settings.
125
150
312
360
600
700
1000
1200
500
600
600
600
1800–6000
1800–6000
6
200 480 1000 1600 700 600 1800–6000
Circuit breaker, HMCP and fuse
ampere rating selections are in
460 V, Three-Phase 7
line with maximum rules given in 1 1.8 6 6 15 7 21–70
1-1/2 2.6 6 10 15 7 21–70
NEC 430.52 and Table 430.250. Based
on known characteristics of Eaton type
2
3
3.4
4.8
6
10
15
15
15
15
7
15
21–70
45–150
8
breakers, specific units are recom- 5 7.6 15 25 15 15 45–150
mended. The current ratings are no 7-1/2 11 20 35 25 30 90–300
more than the maximum limits set by 10 14 25 45 35 30 90–300 9
the NEC rules for motors with code 15 21 40 70 45 50 150–500
letters F to V or without code letters. 20 27 50 90 50 50 150–500
Motors with lower code letters will 25 34 60 110 70 70 210–700 10
require further considerations. 30 40 70 125 70 100 300–1000
40 52 100 175 100 100 300–1000
In general, these selections were 50 65 125 200 110 150 450–1500 11
based on: 60 77 150 150 125 150 750–2500
75 96 175 300 150 150 750–2500
1. Ambient—outside enclosure not
more than 40 °C (104 °F).
100 124 225 400 175 150 750–2500
12
125 156 300 500 225 250 1250–2500
150 180 350 600 250 400 2000–4000
2. Motor starting—infrequent 200 240 450 800 350 400 2000–4000
starting, stopping or reversing. 575 V, Three-Phase
13
3. Motor accelerating time— 1 1.4 3 6 15 3 9–30
10 seconds or less. 1-1/2
2
2.1
2.7
6
6
10
10
15
15
7
7
21–70
21–70
14
4. Locked rotor—maximum 6 times 3 3.9 10 15 15 7 21–70
motor FLA. 5 6.1 15 20 15 15 45–150
7-1/2 9 20 30 20 15 45–150 15
Type HMCP motor circuit protector 10 11 20 35 25 30 90–300
may not set at more than 1300% of 15 17 30 60 40 30 90–300
the motor full-load current to comply 20 22 40 70 50 50 150–500 16
with NEC 430.52. (Except for NEMA 25 27 50 90 60 50 150–500
Design B energy high-efficiency 30 32 60 100 60 50 150–500
motors that can be set up to 1700%.) 40 41 80 125 80 100 300–1000 17
50 52 100 175 100 100 300–1000
Circuit breaker selections are based 60 62 110 200 125 150 750–2500
on types with standard interrupting 75
100
77
99
150
175
250
300
150
175
150
150
750–2500
750–2500
18
ratings. Higher interrupting rating types
may be required to satisfy specific 125 125 225 400 200 250 1250–2500
150 144 300 450 225 250 1250–2500
system application requirements.
200 192 350 600 300 400 2000–4000
19
For motor full load currents of
208 V and 200 V, increase the
corresponding 230 V motor values
20
by 10 and 15% respectively.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-12 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 092

Table 1.7-11. 60 Hz, Recommended Protective Setting for Induction Motors


i hp Full Load Minimum Wire Size Minimum Conduit Size, Fuse Size NEC 430.52 Recommended Eaton:
Amperes 75 °C Copper Ampacity Inches (mm) Maximum Amperes 1 Circuit Motor Circuit
(NEC) FLA at 125% FLA THW THWN Time Non-Time Breaker 2 Protector
ii Size Amperes XHHN Delay Delay Amperes Amperes Adjustable Range
115 V, Single-Phase
1 3/4 13.8 14 20 0.50 (12.7) 0.50 (12.7) 25 45 30 Two-pole device
1 16 14 20 0.50 (12.7) 0.50 (12.7) 30 50 35 not available
1-1/2 20 12 30 0.50 (12.7) 0.50 (12.7) 35 60 40
2 2
3
24
34
10
8
30
50
0.50 (12.7)
0.75 (19.1)
0.50 (12.7)
0.50 (12.7)
45
60
80
110
50
70
5 56 4 85 1.00 (25.4) 0.75 (19.1) 100 175 100
7-1/2 80 3 100 1.00 (25.4) 1.00 (25.4) 150 250 150
3 230 V, Single-Phase
3/4 6.9 14 20 0.50 (12.7) 0.50 (12.7) 15 25 15 Two-pole device
4 1
1-1/2
8
10
14
14
20
20
0.50 (12.7)
0.50 (12.7)
0.50 (12.7)
0.50 (12.7)
15
20
25
30
20
25
not available

2 12 14 20 0.50 (12.7) 0.50 (12.7) 25 40 30


3 17 12 30 0.50 (12.7) 0.50 (12.7) 30 60 40
5 5 28 10 50 0.50 (12.7) 0.50 (12.7) 50 90 60
7-1/2 40 8 50 0.75 (19.1) 0.50 (12.7) 70 125 80
1 Consult fuse manufacturer’s catalog for smaller fuse ratings.
6 2 Types are for minimum interrupting capacity breakers. Ensure that the fault duty does not exceed breaker’s I.C.

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-13
August 2017 Typical Components of a Power System
Sheet 01 093

Generators and The other requirements for grounded Types of Generators


i
systems were renumbered to accom-
Generator Systems modate the 250.30(A)(2) change. Generators can be either synchronous
250.30(B)(3)—Ungrounded Systems— or asynchronous. Asynchronous
was added and this language requires generators are also referred to as ii
a supply-side bonding jumper to be induction generators. The construction
installed from the source of a sepa- is essentially the same as an induction
rately derived system to the first dis- motor. It has a squirrel-cage rotor and 1
connecting means in accordance with wound stator. An induction generator
250.30(A)(2). Another new require- is a motor driven above its designed
ment, 250.30(C)—Outdoor Source— synchronous speed thus generating 2
was added that requires a grounding power. It will operate as a motor if it
electrode connection at the source is running below synchronous speed.
Typical Diesel Genset—Caterpillar location when the separately derived The induction generator does not have 3
system is located outside of the build- an exciter and must operate in parallel
Introduction ing or the structure being supplied. with the utility or another source. The
The selection and application induction generator requires VARs from 4
of generators into the electrical Article 445.19—Generators Supplying
Multiple Loads—was also revised an external source for it to generate
distribution system will depend on power. The induction generator
the particular application. There are to require that the generator have
operates at a slip frequency so its 5
many factors to consider, including overcurrent protection per 240.15(A)
when using individual enclosures output frequency is automatically
code requirements, environmental locked in with the utility's frequency.
constraints, fuel sources, control tapped from a single feeder. 6
complexity, utility requirements and Article 517.17(B)—Feeder Ground Fault An induction generator is a popular
load requirements. The healthcare Protection (Healthcare Facilities)—now choice for use when designing
requirements for legally required allows, but does not require, multiple cogeneration systems, where it will 7
emergency standby generation levels of Ground Fault Protection operate in parallel with the utility.
systems are described starting Equipment (GFPE) upstream of the This type of generator offers certain
on Page 1.8-1. transfer switch when the choice is advantages over a synchronous 8
made to provide GFPE on the alternate generator. For example, voltage and
Systems described in this section are frequency are controlled by the utility;
applicable to healthcare requirements, power source (i.e., generator). 9
thus voltage and frequency regulators
as well as other facilities that may Article 701.6(D)—Signals (Legally are not required. In addition, the
require a high degree of reliability. Required Standby Systems)—now generator construction offers high
The electrical supply for data centers, requires ground fault indication for reliability and little maintenance. 10
financial institutions, telecommunica- legally required standby systems of Also, a minimum of protective relays
tions, government and public more than 150 V to ground and OCPDs and controls are required. Its major
utilities also require high reliability. rated 1000 A or more. disadvantages are that it requires 11
Threats of disaster or terror attacks VARs from the system and it normally
have prompted many facilities to Types of Engines cannot operate as a standby/
require complete self-sufficiency for emergency generator. 12
continuous operation. Many generator sets are relatively
small in size, typically ranging from Synchronous generators, however,
NEC Changes Related to several kilowatts to several megawatts. are the most common. Their output is 13
These units are often required to come determined by their field and governor
Generator Systems online and operate quickly. They need controls. Varying the current in the
Article 250.30—Grounding Separately to have the capacity to run for an DC field windings controls the voltage 14
Derived AC Systems—was completely extended period of time. output. The frequency is controlled
rewritten for clarity and for usability in by the speed of rotation. The torque
The internal combustion engine is an
the 2011 NEC. Most notably, the term
excellent choice as the prime mover
applied to the generator shaft by 15
equipment bonding jumper was the driving engine controls the power
for the majority of these applications.
changed to supply-side bonding jumper output. In this manner, the synchro-
Diesel-fueled engines are the most
(see 250.30(A)(2)). This was necessary
common, but other fuels used include
nous generator offers precise control 16
to ensure proper identification and over the power it can generate. In
natural gas, digester gas, landfill gas,
installation of bonding conductors cogeneration applications, it can be
propane, biodiesel, crude oil, steam
within or on the supply side of service
and others.
used to improve the power factor of 17
equipment and between the source of a the system.
separately derived system and the first Some campuses and industrial facilities
disconnecting means. use and produce steam for heating and 18
other processes. These facilities may
find it economically feasible to produce
electricity as a byproduct of the steam 19
production. These installations would
typically be classified as a cogeneration
facility producing a fairly constant 20
power output and operating in parallel
with the electric utility system.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-14 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 094

Generator Systems Multiple Isolated Standby Generators Multiple generator systems have a
i The second type of generator system more complex control and protection
Emergency Standby Generator System is a multiple isolated set of standby requirement as the units have to be
There are primarily three types of generators. Figure 1.7-2 shows synchronized and paralleled together.
ii generator systems. The first and multiple generators connected to The generators are required to share
simplest type is a single generator a paralleling bus feeding multiple the load proportionally without swings
that operates independently from transfer switches. The utility is the or prolonged hunting in voltage or
1 the electric utility power grid. normal source for the transfer frequency for load sharing. They may
This is typically referred to as an switches. The generators and the also require multiple levels of load
emergency standby generator utility are never continuously shedding and/or load restoration
2 system. Figure 1.7-1 shows a single connected together in this scheme. schemes to match generation capacity.
standby generator, utility source Multiple Generators Operating in
and a transfer switch. Multiple generators may be required
3 to meet the load requirements Parallel with Utility System
In this case, the load is either supplied (N system). Generators may be The third type of system is either one
from the utility or the generator. The applied in an N+1 or a 2N system with a single or multiple generators
4 generator and the utility are never for improved system reliability. that operate in parallel with the utility
continuously connected together. This system. Figure 1.7-3 shows two
simple radial system has few require- generators and a utility source feeding
5 ments for protection and control. It also Utility a switchgear lineup feeding multiple
has the least impact on the complete G1 G2 loads. This system typically requires
electric power distribution system. generator capacity sufficient to carry
6 It should be noted that this type of the entire load or sophisticated load
Switchgear
generator system improves overall shedding schemes. This system will
electrical reliability but does not require a complete and complex
7 provide the redundancy that some protection and control scheme. The
ATS-1 ATS-2
facilities require if the generator fails electric utility may have very stringent
to start or is out for maintenance. and costly protection requirements
8 for the system. IEEE standard 1547
Load 1 Load 2 describes the interconnection require-
ments for paralleling to the utility.
9 Utility
G1 Figure 1.7-2. Multiple Isolated Set of
Standby Generators Utility
10 In an N system, where N is the number
G1 G2

of generators required to carry the


Switchgear
11 load; if a generator fails or is out for
maintenance, then the load may be
dropped. This is unacceptable for most
ATS
12 critical 24/7 operations. In an N + 1
system, N is the number of generators
needed to carry the load and 1 is an
13 extra generator for redundancy. If one Load 1 Load 2 Load 3
Load generator fails to start or is out for
maintenance, it will not affect the load.
14 In a 2N system, there is complete 100%
Figure 1.7-3. Multiple Generators Operating
in Parallel with Utility System
Figure 1.7-1. Emergency Standby
Generator System redundancy in the standby generation
system such that the failure of one
15 complete set of generators will not
affect the load.
16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-15
August 2017 Typical Components of a Power System
Sheet 01 095

Generator Fundamentals The application of generators adds An IEEE working group has studied the
A generator consists of two primary
special protection requirements to practice of low resistance grounding i
the system. The size, voltage class, of medium-voltage generators within
components, a prime mover and an importance and dollar investment the general industry. This “working
alternator. The prime mover is the will influence the protection scheme ii
group” found that, for internal generator
energy source used to turn the rotor associated with the generator(s). The ground faults, the vast majority of the
of the alternator. It is typically a mode of operation will influence the damage is done after the generator
diesel combustion engine for most utility company’s interface protection 1
breaker is tripped offline, and the field
emergency or standby systems. requirements. Paralleling with the and turbine are tripped. This is due to
In cogeneration applications, the electric utility is the most complicated the stored energy in the generator flux
prime mover may come from a steam of the utility inter-tie requirements. 2
driven turbine or other source. On that takes several seconds to dissipate
IEEE ANSI 1547 provides recom- after the generator is tripped offline.
diesel units, a governor and voltage mended practices.
regulator are used to control the speed
and power output.
It is during this time that the low 3
Generator Grounding and Bonding resistance ground allows significant
amounts of fault current to flow into
The alternator is typically a synchro- (Ref. NEC 2014, Article 250.30(A)(1)
nous machine driven by the prime the ground fault. Because the large 4
mover. A voltage regulator controls its and (2)) fault currents can damage the
voltage output by adjusting the field. Generator grounding methods need generator’s winding, application of
The output of a single generator or to be considered and may affect the an alternate protection method is 5
multiple paralleled generator sets is distribution equipment and ratings. desirable during this time period.
controlled by these two inputs. The Generators may be connected in delta One of the solutions set forth by this
alternator is designed to operate at a or wye, with wye being the most “working group” is a hybrid high 6
specified speed for the required output typical connection. A wye-connected resistance grounding (HHRG) scheme
frequency, typically 60 or 50 Hz. The generator can be solidly grounded, as shown in Figure 1.7-4.
voltage regulator and engine governor low impedance grounded, high In the HHRG scheme, the low
7
along with other systems define the impedance grounded or ungrounded.
resistance ground (LRG) is quickly
generator’s response to dynamic Section 1.4 discusses general ground-
tripped offline when the generator 8
load changes and motor starting ing schemes, benefits of each and
protection senses the ground fault.
characteristics. protection considerations.
The LRG is cleared at the same time
A solidly grounded generator may have that the generator breaker clears,
Generators are rated in power and
a lower zero sequence impedance than leaving the high resistance ground
9
voltage output. Most generators are
designed to operate at a 0.8 power its positive sequence impedance. In this portion connected to control the
case, the equipment will need to be rated transient overvoltages during the
factor. For example, a 2000 kW
generator at 277/480 V would have a for the larger available ground fault coast-down phase of the generator,
10
kVA rating of 2500 kVA (2000 kW/ current. The generator’s neutral may thereby all but eliminating generator
be connected to the system-neutral; if damage.
08 pf) and a continuous
··· current rating
of 3007A  2500 kVA  480V 3 . it is, the generator is not a separately 11
derived system and a three-pole transfer
Typical synchronous generators switch is used.
for industrial and commercial 12
power systems range in size from If the generator’s neutral is bonded to
100–3000 kVA and from 208 V–13,800 V. ground separate from the system-
Other ratings are available and these neutral, it is a separately derived 13
discussions are applicable to those system and a four-pole transfer switch
ratings as well. is required or ground fault relays could
misoperate and unbalanced neutral 14
Generators must be considered in the current may be carried on ground
short-circuit and coordination study conductors.
as they may greatly impact the rating 15
of the electrical distribution system.
This is especially common on large
installations with multiple generators HRG 16
and systems that parallel with the
utility source. Short-circuit current 51G
Gen R 59G
contribution from a generator 86
R LRG
17
typically ranges from 8 to 12 times Phase
full load amperes. 87GN
Relays
18

19

20
Figure 1.7-4. Hybrid High Resistance Grounding Scheme
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-16 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 096

i
Generator Controls During this time, the breakers for Generator Short-Circuit
the other generators are held open
The engine generator set has controls and not permitted to close until Characteristics
to maintain the output frequency certain conditions are met. Once
ii (speed) and voltage. These controls
consist of a governor and voltage
the paralleling bus is energized, If a short circuit is applied directly to
the output terminals of a synchronous
the remaining generators must
regulator. As loads change on the be synchronized to it before the generator, it will produce an extremely
1 system, the frequency and voltage generators can be paralleled. high current initially, gradually decaying
to a steady-state value. This change
will change. The speed control will
then adjust the governor to correct Synchronization compares the voltage is represented by a varying reactive
2 for the load (kW) change. The phasor’s angle and magnitude. Both impedance. Three specific reactances
voltage regulator will change the generators must be operating at the are used for short-circuit fault currents.
field current to adjust the voltage same frequency and phase-matched They are:
3 to the desired voltage value. These within typically 5 to 10 degrees with
■ Subtransient reactance Xd”, which is
are the basic controls found on all each other. The voltage magnitude
synchronous generators. typically must be within 20 to 24%. used to determine the fault
current during the first 1 to 5 cycles
4 Multiple generator systems require A synch-scope is typically supplied ■ Transient reactance Xd’, which is
more sophisticated controls. Generators on paralleling gear. The synch-scope used to determine the fault current
are paralleled in a multi-generator displays the relative relationship during the next 5 to 200 cycles
5 system and they must share the load. between voltage phasors on the ■ Synchronous reactance Xd”, which is
These systems often have a load shed generator to be paralleled and used to determine the steady- state
scheme, which adds to the complexity. the bus.
6 fault current
Multiple generator schemes need a If the generator is running slower than The subtransient reactance Xd” will
master controller to prevent units from the bus (less than 60 Hz) then the range from a minimum of approxi-
7 being connected out-of-phase. The needle on the scope will spin in the mately 9% for a two-pole, wound-rotor
sequence of operation is to send a counterclockwise direction. If it is machine to approximately 32% for a
start signal to all generators simulta- running faster, then it will rotate in low-speed, salient-pole, hydro-generator.
8 neously. The first unit up to frequency the clockwise direction. The greater The initial symmetrical fault current
and voltage will be permitted to close the frequency difference, the faster can be as much as 12 times full
its respective breaker and energize the is the rotation. It is important that the load current.
9 paralleling bus. generators are in phase before they
are paralleled. Severe damage will Depending on the generator type,
occur if generators are paralleled the zero sequence impedance may be
10 out-of-phase. less than the subtransient reactance
and the ground fault current substan-
tially higher than the three-phase
11 short-circuit current. For example, a
2500 kVA, 480/277 V, four-pole, 2/3
pitch standby generator has a 0.1411
12 per unit subtransient reactance Xd”
and a 0.033 per unit zero sequence Xo
reactance. The ground current is
13 approximately a third larger than the
three-phase fault current. The ground
fault current can be reduced to the
14 three-phase level by simply adding a
small reactance between the generator
neutral and ground while still being
15 considered solidly grounded.
An electric power system analysis
16 must be performed based on the worst-
case operating conditions. Typically
this is when all sources are paralleled.
17 If the system can operate with both
the utility supply and generators in
parallel, then the equipment must be
18 rated for the combined fault current
plus motor contribution. If the generator
and utility will not be paralleled, then
19 both cases will need to be looked at
independently and the worst case used
for selecting the equipment ratings.
20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-17
August 2017 Typical Components of a Power System
Sheet 01 097

Generator Protection
Generator protection will vary and
Generator Protection ANSI/IEEE i
Std 242-1986
depend on the size of the generator,
type of system and importance of the ii
generator. Generator sizes are defined 1 1 1
1
as: small—1000 kVA maximum up
51 Alternate 32 40
to 600 V (500 kVA maximum when Location
51V
1
above 600 V); medium over 1000 kVA
to 12,500 kVA maximum regardless
of voltage; large—from 12,500– 2
50,000 kVA.
1 3
The simplest is a single generator
system used to feed emergency Gen 51G 87 3
and/or standby loads. In this case,
1
the generator is the only source
available when it is operating in the 51 Preferred 4
Location Gen
emergency mode and must keep
operating until the normal source 1
returns. 51G
5
Figure 1.7-5 Part (A) shows minimum
recommended protection for a single (A) (A) Single Isolated Generator on Low-Voltage System (B) 6
(B) Multiple Isolated Generator on Medium-Voltage System
generator used as an emergency or
standby system. Phase and ground
time overcurrent protection (Device Figure 1.7-5. Typical Protective Relaying Scheme for Small Generators 7
51 and 51G) will provide protection for
external faults. For medium-voltage
generators, a voltage controlled time 8
overcurrent relay (Device 51V) is R
recommended for the phase protec-
tion as it can be set more sensitive 9
than standard overcurrent relays
and is less likely to false operate on 50/5A 87-1
normal overloads. 10
This scheme may not provide 50/5A 87-2
adequate protection for internal 11
generator faults when no other
power source exists. Local generator 50/5A 87-3
controllers may offer additional 12
protection for voltage and frequency
conditions outside the generator’s
capabilities. 13
Figure 1.7-5 Part (B) shows the
recommended protection for multiple, 14
Gen
isolated, medium-voltage, small
generators. Additional protection
may be desired and could include 15
generator differential, reverse power,
and loss of field protection. Differential
protection (Device 87) can be accom- 16
plished with either a self-balancing
set of CTs as in Figure 1.7-6 or with Figure 1.7-6. Self-Balancing Generator
a percentage differential scheme as Differential Relay Scheme 17
in Figure 1.7-7 on Page 1.7-18.
The percentage differential scheme
offers the advantage of reducing the 18
possibility for false tripping due to
CT saturation. The self-balancing
scheme offers the advantages of 19
increased sensitivity, needing three
current transformers in lieu of six, and
the elimination of current transformer 20
external wiring from the generator
location to the generator switchgear
location. 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-18 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 098

Reverse power protection (Device 32)


i is used to prevent the generator
from being motored. Motoring could Grounding
Resistor
damage (with other hazards) the prime
ii mover. A steam turbine could overheat 51G

and fail. A diesel or gas engine could


either catch fire or explode. A steam
1 turbine can typically withstand approx-
imately 3% reverse power where a
diesel engine can withstand up to 25%
2 reverse power.
Loss of field protection (Device 40) is 87

3 needed when generators are operating


01
in parallel with one another or the R1
PC
power grid. When a synchronous R1

4 generator loses its field, it will continue 02 R2


to generate power as an induction Gen
generator obtaining its excitation from OC
R2

5 the other machines on the system. 03 R3


87G
During this condition, the rotor will R3

quickly overheat due to the slip


6 frequency currents induced in it. Loss
of excitation in one machine could
jeopardize the operation of the other
7 machines beyond their capability and
52

the entire system.


8

9
To Main Bus
OC = Operating coil
PC = Permissive coil
10
Figure 1.7-7. Generator Percentage Differential Relay (Phase Scheme)
and Ground Differential Scheme Using a Directional Relay
11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-19
August 2017 Typical Components of a Power System
Sheet 01 099

Typical protection for larger generators


is shown in Figure 1.7-8. It adds i
phase unbalance and field ground
fault protection. Phase unbalance 3
(Device 46) or negative sequence
87B
ii
overcurrent protection prevents the 81U/O
generator’s rotor from overheating
damage. 1
Unbalanced loads, fault conditions 27/59
or open phasing will produce a 2
negative sequence current to flow. The
unbalanced currents induce double
system frequency currents in the 3 1 1 1 3
rotor, which quickly causes rotor 51V 40 32 46
overheating. Serious damage will
occur to the generator if the unbalance 3 1 4
is allowed to persist. 87G
87
60
Other protection functions such as
under/overvoltage (Device 27/59) could Voltage Regulator and 5
Metering Circuits
be applied to any size generator. The 1
voltage regulator typically maintains
the output voltage within its desired
1 64 6
49
output range. This protection can
provide backup protection in case the
voltage regulator fails. Under/over
7
Gen
frequency protection (Device 81U/81O) E
could be used for backup protection 8
for the speed control. Sync check
relays (Device 25) are typically applied
as a breaker permissive close function 9
where generators are paralleled. 51G

Many modern protective relays are


microprocessor-based and provide a 10
full complement of generator protection
functions in a single package. The cost
per protection function has been 11
drastically reduced such that it is Figure 1.7-8. Typical Protective Relaying Scheme for Large Generator
feasible to provide more complete
protection even to smaller generators. 12
IEEE ANSI 1547 provides recommended
practices for utility inter-tie protection. 13
If the system has closed- transition or
paralleling capability, additional pro-
tection may be required by the utility. 14
Typically, no additional protection is
required if the generator is paralleled
to the utility for a maximum of 15
100 msec or less.
Systems that offer soft transfer, peak
shaving or co-generation will require
16
additional utility inter-tie protection.
The protection could include directional 17
overcurrent and power relays and
even transfer trip schemes. Please
consult your local utility for specific 18
requirements.

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-20 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 100

i Generator Set Sizing Typical rating definitions for diesel Electrical rating definitions for natural
gensets are: standby, prime plus 10, gas powered gensets are typically
and Ratings continuous and load management defined as standby or continuous with
(paralleled with or isolated from definitions similar to those mentioned
ii Many factors must be considered
when determining the proper size or
utility). Any diesel genset can have above for diesels. Natural gas gensets
several electrical ratings depending recover more slowly than diesel gensets
electrical rating of an electrical power on the number of hours of operation when subjected to block loads. Diesel
1 generator set. The engine or prime per year and the ratio of electrical engines have a much more direct path
mover is sized to provide the actual load/genset rating when in operation. from the engine governor and fuel
or real power in kW, as well as speed The same diesel genset can have a delivery system to the combustion
2 (frequency) control through the use standby rating of 2000 kW at 0.8 power chamber, resulting in a very responsive
of an engine governor. factor (pf) and a continuous rating of engine-generator.
The generator is sized to supply the 1825 kW at 0.8 pf.
3 kVA needed at startup and during
A natural gas engine is challenged with
The lower continuous rating is due to air-fuel flow dynamics and a much
normal running operation. It also the additional hours of operation and more indirect path from the engine
provides voltage control through the
4 use of a brushless exciter and voltage
higher load that the continuous genset governor (throttle actuator) and fuel
must carry. These additional require- delivery system (natural gas pressure
regulator. Together the engine and ments put more stress on the engine regulator, fuel valve and actuator,
generator provide the energy
5 necessary to supply electrical loads
and generator and therefore the rating carburetor mixer, aftercooler, intake
is decreased to maintain longevity of manifold) to the combustion chamber.
in many different applications the equipment. This results in a less responsive
encountered in today’s society.
6 Different generator set manufacturers
engine-generator. Diesel gensets
The generator set must be able to recover about twice as fast as natural
use basically the same diesel genset gas gensets.
supply the starting and running electrical rating definitions. These are
7 electrical load. It must be able to based on International Diesel Fuel For the actual calculations involved
pick up and start all motor loads and Stop Power standards from organiza- for sizing a genset, there are readily
low power factor loads, and recover tions like ISO, DIN and others. accessible computer software programs
8 without excessive voltage dip or that are available on the genset manu-
extended recovery time. ■ Standby diesel genset rating— facturer’s Internet sites or from the
Typically defined as supplying manufacturer’s dealers or distributors.
9 Nonlinear loads like variable frequency varying electrical loads for the These programs are used to quickly
drives, uninterruptible power supply duration of a power outage with the
(UPS) systems and switching power and accurately size generator sets for
load normally connected to utility, their application. The programs take
10 supplies also require attention because genset operating <100 hours per into consideration the many different
the SCR switching causes voltage year and no overload capability
and current waveform distortion and parameters discussed above, including
■ Prime plus 10 rating—Typically the size and type of the electrical loads
11 harmonics. The harmonics generate
defined as supplying varying (resistive, inductive, SCR, etc.), reduced
additional heat in the generator wind-
ings, and the generator may need to electrical loads for the duration voltage soft starting devices (RVSS),
of a power outage with the load motor types, voltage, fuel type, site
12 be upsized to accommodate this.
normally connected to utility, genset conditions, ambient conditions and
The type of fuel (diesel, natural gas, operating <500 hours per year and other variables.
propane, etc.) used is important as it is overload capability of 10% above its
13 a factor in determining generator set rating for 1 hour out of 12 The software will optimize the starting
response to transient overloads. It is ■ Continuous rating—Typically
sequences of the motors for the least
also necessary to determine the load amount of voltage dip and determine
14 factor or average power consumption
defined as supplying unvarying
the starting kVA needed from the
electrical loads (i.e., base loaded)
of the generator set. This is typically for an unlimited time genset. It also provides transient
defined as the load (kW) x time response data, including voltage
15 (hrs. while under that particular load) /
■ Load management ratings—Apply
dip magnitude and recovery duration.
to gensets in parallel operation with If the transient response is unaccept-
total running time. When this load the utility or isolated/islanded from
factor or average power is taken into able, then design changes can be
16 consideration with peak demand
utility and these ratings vary in considered, including oversizing the
usability from <200 hours per generator to handle the additional kvar
requirements and the other operating year to unlimited usage
parameters mentioned above, the load, adding RVSS devices to reduce
17 overall electrical rating of the genset Refer to generator set manufacturers the inrush current, improving system
can be determined. for further definitions on load manage- power factor and other methods.
18 Other items to consider include the
ment ratings, load factor or average The computer software programs are
power consumption, peak demand quite flexible in that they allow changes
unique installation, ambient, and site and how these ratings are typically
requirements of the project. These to the many different variables and
19 will help to determine the physical
applied. Even though there is some parameters to achieve an optimum
standardization of these ratings across design. The software calculates how
configuration of the overall system. the manufacturers, there also exists to minimize voltage dips and can
20 some uniqueness with regard to recommend using paralleled gensets
how each manufacturer applies their vs. a single genset.
generator sets.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-21
August 2017 Typical Components of a Power System
Sheet 01 101

Genset Sizing Guidelines Generator Set Installation ■ Hazardous waste considerations


for fuel, antifreeze, engine oil i
Some conservative rules of thumb and Site Considerations ■ Meeting local building and
for genset sizing include:
There are many different installation electrical codes
1. Oversize genset 20–25% parameters and site conditions ■ Genset exposure (coastal
ii
for reserve capacity and for that must be considered to have a conditions, dust, chemicals, etc.)
across the line motor starting. successful generator set installation. ■ Properly sized starting systems 1
2. Oversize gensets for unbalanced The following is a partial list of areas (compressed air, batteries
loading or low power factor to consider when conducting this and charger)
running loads. design. Some of these installation ■ Allowing adequate space for 2
parameters include: installation of the genset and for
3. Use 1/2 hp per kW for motor loads. maintenance (i.e., air filter removal,
■ Foundation type (crushed rock,
4. For variable frequency drives, concrete, dirt, wood, separate oil changing, general genset 3
oversize the genset by at least 40% concrete inertia pad, etc.) inspection, etc…)
for six-pulse technology drives. ■ Flex connections on all systems that
■ Foundation to genset vibration
dampening (spring type, cork are attached to the genset and a 4
5. For UPS systems, oversize the rigid structure (fuel piping, founda-
genset by 40% for 6 pulse and and rubber, etc.)
tion vibration isolators, exhaust, air
15% for 6 pulse with input filters or ■ Noise attenuation (radiator fan intake, control wiring, power cables, 5
12 pulse. mechanical noise, exhaust noise, radiator flanges/duct work, etc.)
air intake noise)
6. Always start the largest motor ■ Diesel fuel day tank systems
first when stepping loads.
■ Combustion and cooling air (pumps, return piping)
6
requirements
■ Fuel storage tank (double walled,
For basic sizing of a generator system, ■ Exhaust backpressure requirements
the following example could be used: ■ Emissions permitting
fire codes) and other parameters 7
■ Delivery and rigging requirements Please see the generator set manufac-
Step 1: Calculate Running Amperes turer’s application and installation
■ Motor loads: ■ Genset derating due to high guidelines for proper application 8
❑ 200 hp motor. . . . . . . . . . . . .156 A
altitudes or excessive ambient and operation of their equipment.
temperatures
❑ 100 hp motor . . . . . . . . . . . . . .78 A 9
❑ 60 hp motor . . . . . . . . . . . . . . .48 A
■ Lighting load . . . . . . . . . . . . . . . .68 A
■ Miscellaneous loads . . . . . . . . . .95 A
10
■ Running amperes . . . . . . . . . . .445 A

Step 2: Calculating Starting Amperes


11
Using 1.25 Multiplier
■ Motor loads: 12
❑ 200 hp motor. . . . . . . . . . . . .195 A
❑ 100 hp motor . . . . . . . . . . . . . .98 A
❑ 60 hp motor . . . . . . . . . . . . . . .60 A
13
■ Lighting load . . . . . . . . . . . . . . . .68 A
■ Miscellaneous loads . . . . . . . . . .95 A 14
■ Starting amperes . . . . . . . . . . .516 A

Step 3: Selecting kVA of Generator 15


■ Running kVA =
(445 A x 480 V x 1.732)/
1000 = 370 kVA 16
■ Starting kVA =
(516 A x 480 V x 1.732)/ 17
1000 = 428 kVA
Solution
Generator must have a minimum
18
starting capability of 428 kVA and Figure 1.7-9. Typical Genset Installation
minimum running capability of 370 kVA. 19
Note: Courtesy of Caterpillar, Inc.
Also, please see section “Factors
Governing Voltage Drop” on
Page 1.4-19 for further discussion 20
on generator loading and reduced
voltage starting techniques for motors.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-22 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 102

i Capacitors and Power Factor ANSI Standard C37.06 (indoor oilless Low-Voltage Capacitor Switching
circuit breakers) indicates the preferred
ratings of Eaton’s Type VCP-W vacuum Circuit breakers and switches for use
Capacitor General Application breaker. For capacitor switching, with a capacitor must have a current
ii Considerations careful attention should be paid to rating in excess of rated capacitor
current to provide for overcurrent from
Additional application information the notes accompanying the table.
The definition of the terms are in ANSI overvoltages at fundamental frequency
is available in Tab 35 regarding
1 capacitors and harmonic filters Standard C37.04 Article 5.13 (for the and harmonic currents. The following
latest edition). The application guide percent of the capacitor-rated current
as follows: should be used as a general guideline:
ANSI/IEEE Standard C37.012 covers the
2 ■ Capacitor selection method of calculation of the Fused and unfused switches . . . .165%
■ Where to install capacitors in a plant quantities covered by C37.06 Standard.
distribution system Molded-case breaker or
3 ■ Locating capacitors on reduced
Note that the definitions in C37.04 equivalent . . . . . . . . . . . . . . . . . .150%
make the switching of two capacitors
voltage and multi-speed starters banks in close proximity to the switch- Insulated-case breakers . . . . . . . .135%
4 ■ Harmonic considerations gear bus a back-to-back mode of
Magnum DS power
■ Eliminating harmonic problems switching. This classification requires
circuit breaker . . . . . . . . . . . . . . .135%
■ National Electrical Code a definite purpose circuit breaker
5 requirements (breakers specifically designed for Contactors:
capacitance switching). Open type. . . . . . . . . . . . . . . . . . . .135%
Medium-Voltage We recommend that such application
6 Capacitor Switching be referred to Eaton.
Enclosed type . . . . . . . . . . . . . . . .150%

Capacitance switching constitutes The NEC, Section 460.8(C), requires


A breaker specified for capacitor the disconnecting means to be rated not
7 severe operating duty for a circuit switching should include as applicable: less than 135% of the rated capacitor
breaker. At the time the breaker opens
at near current zero, the capacitor is 1. Rated maximum voltage. current (for 600 V and below).
8 fully charged. After interruption, when 2. Rated frequency. See Tab 35 for switching device
the alternating voltage on the source ampere ratings. They are based on
side of the breaker reaches its opposite 3. Rated open wire line charging percentage of capacitor-rated current
9 maximum, the voltage that appears switching current. as indicated (above). The interrupting
across the contacts of the open breaker rating of the switch must be selected
is at least twice the normal peak line- 4. Rated isolated cable charging and
to match the system fault current
10 to-neutral voltage of the circuit. If a shunt capacitor switching current.
available at the point of capacitor
breakdown occurs across the open 5. Rated back-to-back cable application. Whenever a capacitor
contact, the arc is re-established. Due charging and back-to-back bank is purchased with less than the
11 to the circuit constants on the supply capacitor switching current. ultimate kvar capacity of the rack or
side of the breaker, the voltage across enclosure, the switch rating should
the open contact can reach three times 6. Rated transient overvoltage factor. be selected based on the ultimate
12 the normal line-to-neutral voltage. kvar capacity—not the initial installed
After it is interrupted and with 7. Rated transient inrush current and
its frequency. capacity.
subsequent alternation of the supply
13 side voltage, the voltage across the 8. Rated interrupting time. Refer to Tab 35 for recommended
open contact is even higher. selection of capacitor switching
9. Rated capacitive current devices; recommended maximum
14 switching life. capacitor ratings for various motor
types and voltages; and for required
10. Grounding of system and multipliers to determine capacitor kvar
15 capacitor bank. required for power factor correction.
Load break interrupter switches
are permitted by ANSI/IEEE Standard
16 C37.30 to switch capacitance, but they
must have tested ratings for the purpose.
Refer to Tab 8 Eaton Type MVS ratings.
17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.7-23
August 2017 Typical Components of a Power System
Sheet 01 103

Motor Power Factor % AR (amp reduction) is the percent To derate a capacitor used on a system
i
reduction in line current due to the voltage lower than the capacitor
Correction capacitor. A capacitor located on the voltage rating, such as a 240 V
motor side of the overload relay capacitor used on a 208 V system,
See Tab 35 containing suggested reduces line current through the relay. use the following formula: ii
maximum capacitor ratings for Therefore, a different overload relay
induction motors switched with the Actual kvar =
and/or setting may be necessary.
capacitor. The data is general in nature The reduction in line current may be  Applied Voltage 
2
Nameplate kvar  ----------------------------------------------------------------------
1
and representative of general purpose determined by measuring line current 2
induction motors of standard design.  Nameplate Voltage 
with and without the capacitor or by
The preferable means to select capacitor calculation as follows: 2
ratings is based on the “maximum For the kVAC required to correct the
recommended kvar” information (Original PF) power factor from a given value of
% AR  100 – 100   COS 1 to COS 2, the formula is:
available from the motor manufacturer. (Improved PF) 3
If this is not possible or feasible, the
tables can be used. kVAC = kW (tan phase1–tan phase2)
If a capacitor is used with a lower kvar
An important point to remember
rating than listed in tables, the % AR Capacitors cause a voltage rise. 4
can be calculated as follows: At light load periods the capacitive
is that if the capacitor used with the
motor is too large, self-excitation Actual kvar voltage rise can raise the voltage at
may cause a motor-damaging over-
% AR  Listed % AR  
kvar in Table
the location of the capacitors to an 5
voltage when the motor and capacitor unacceptable level. This voltage rise
combination is disconnected from the The tables can also be used for other can be calculated approximately by the
line. In addition, high transient torques motor ratings as follows: formula: 6
capable of damaging the motor shaft A. For standard 60 Hz motors MVA r
or coupling can occur if the motor is % VR  
reconnected to the line while rotating
operating at 50 Hz: MVA SC 7
kvar = 1.7–1.4 of kvar listed
and still generating a voltage of self- % AR = 1.8–1.35 of % AR listed
excitation. Low-speed pump motors, MVAR is the capacitor rating and MVASC
or motors with more than four poles, B. For standard 50 Hz motors is the system short-circuit capacity. 8
will typically exhibit low power factor operating at 50 Hz: With the introduction of variable speed
and high FLA. kvar = 1.4–1.1 of kvar listed
% AR = 1.4–1.05 of % AR listed
drives and other harmonic current 9
Definitions generating loads, the capacitor
C. For standard 60 Hz wound-rotor impedance value determined must
kvar—rating of the capacitor in
reactive kilovolt-amperes. This value motors: not be resonant with the inductive 10
kvar = 1.1 of kvar listed reactances of the system.
is approximately equal to the motor
no-load magnetizing kilovars. % AR= 1.05 of % AR listed
11
Note: For A, B, C, the larger multipliers
apply for motors of higher speeds; i.e.,
3600 rpm = 1.7 mult., 1800 rpm = 1.65
mult., etc.
12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.7-24 Power Distribution Systems
Typical Components of a Power System August 2017
Sheet 01 104

BIL—Basic Impulse Levels Table 1.7-12. Metal-Clad Switchgear Table 1.7-15. Liquid-Immersed
i ANSI standards define recommended
Voltage and Insulation Levels Transformers Voltage and Basic
(From IEEE Std. C37.20.2-2015) Lightning Impulse Insulation Levels (BIL)
and required BIL levels for: (From ANSI/IEEE C57.12.00)
Rated Maximum Impulse
ii ■ Metal-clad switchgear Voltage (kV rms) Withstand (kV) Applica- Nominal BIL
(typically vacuum breakers) tion System (kV Crest) 1
4.76 60 Voltage
■ Metal-enclosed switchgear 8.25 95
1 (typically load interrupters, 15.0 95
(kV rms)

switches) 27.0 125 Distribu- 1.2 30 — — —


38.0 150 tion 2.5 45 — — —
2 ■ Pad-mounted and overhead 5.0 60 — — —
distribution switchgear 8.7 75 — — —
Table 1.7-13. Metal-Enclosed Switchgear
■ Liquid immersed transformers Voltage and Insulation Levels 15.0 95 — — —
3 ■ Dry-type transformers (From IEEE Std. C37.20.3-2013) 25.0 150 125 — —
34.5 200 150 125 —
Table 1.7-12 through Table 1.7-16 Rated Maximum Impulse
46.0 250 200 — —
Voltage (kV rms) Withstand (kV)
4 contain those values. 69.0 350 250 — —
4.76 60 Power 1.2 45 30 — —
8.25 95 2.5 60 45 — —
5 15.0 95 5.0 75 60 — —
27.0 125 8.7 95 75 — —
38.0 150 15.0 110 95 — —
25.0 150 — — —
6 Table 1.7-14. Pad Mounted and Overhead 34.5 200 — — —
Distribution Switchgear, Voltage and 46.0 250 200 — —
Insulation Levels 69.0 350 250 — —
7 115.0 550 450 350 —
Rated Maximum Impulse
Voltage Level (kV rms) Withstand (kV) 138.0 650 550 450 —
161.0 750 650 550 —
8 Pad Mount Switchgear (per IEEE C37.74-2014)
230.0 900 825 750 650
15.5 95 345.0 1175 1050 900 —
27 125 500.0 1675 1550 1425 1300
9 38 150 765.0 2050 1925 1800 —
Overhead Switchgear (per IEEE C37.60-2012) 1 BIL values in bold typeface are listed as
15 95 standard. Others listed are in common use.
10 15.5 110
27 125 Table 1.7-16. Dry-Type Transformers Voltage
38 150 and Basic Lightning Impulse Insulation
11 38 170 Levels (BIL)—From ANSI/IEEE C57.12.01-1998)
Nominal BIL (kV Crest) 2
System
12 Voltage
(kV rms)

1.2 — 10 20 30
13 2.5 — 20 30 45
5.0 — 30 45 60
8.7 — 45 60 95
14 15.0 — 60 95 110
25.0 95 3 110 125 150
34.5 — 125 3 150 200
15 2 BIL values in bold typeface are listed as
standard. Others listed are in common use.
Optional higher levels used where exposure
to overvoltage occurs and higher protection
16 margins are required.
3 Lower levels where surge arrester
protective devices can be applied with
17 lower spark-over levels.

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.8-1
August 2017 Typical Application by Facility Type
Sheet 01 105

Healthcare Facilities In addition to NFPA guidelines, there All electrical power in a healthcare
i
are additional standards documents facility is important, though some
Healthcare facilities are defined by important in the design of healthcare loads are not critical to the safe opera-
NFPA (National Fire Protection Agency) power distribution systems and tion of the facility. These “non-essential”
as “Buildings or portions of buildings accreditation of those facilities or “normal” loads include things such ii
in which medical, dental, psychiatric, including: as general lighting, general lab equip-
nursing, obstetrical, or surgical care ment, non-critical service equipment,
are provided.” Due to the critical nature
■ Joint Commission—Environment patient care areas, etc. These loads are 1
of Care 2016 not required to be fed from an alternate
of the care being provided at these
facilities and their increasing depen- ■ Facility Guidelines Institute (FGI)— source of power.
dence on electrical equipment for Guidelines for Design and 2
Construction of Hospitals and The electrical system requirements for
preservation of life, healthcare facilities
Outpatient Facilities—2014 the essential electrical system (EES)
have special requirements for the
design of their electrical distribution These codes, standards and guidelines
vary according to the associated risk to 3
the patients, visitors and staff that
systems. These requirements are represent the most industry recognized might occupy that space. NFPA 99
typically much more stringent than requirements for healthcare electrical
commercial or industrial facilities. design. However, the electrical design
assigns a risk category to each space 4
within the healthcare facility based on
The following section summarizes engineer should consult with the the risk associated with a failure of the
some of the unique requirements
of healthcare facility design.
authorities having jurisdiction over power distribution system serving 5
the local region for specific electrical that space. These risk categories are
There are several agencies and organi- distribution requirements. summarized in Table 1.8-1.
zations that develop requirements
The risk category of the space within
6
for healthcare electrical distribution Healthcare Electrical System
the healthcare facility determines
system design. The following is a Requirements whether or not that space is required
listing of some of the specific NFPA
Healthcare electrical systems usually to be served by an Essential Electrical
7
(National Fire Protection Agency)
consist of two parts: System (EES). If an EES is required
standards that affect healthcare facility
to serve the space, the risk category 8
design and implementation: 1. Non-essential or normal also dictates whether the EES must
electrical system. meet Type 1 or Type 2 requirements.
■ NFPA 37-2015—Standard for
Stationary Combustion Engines 2. Essential electrical system. Table 1.8-2 lists the associated 9
and Gas Turbines EES Type requirements for each
■ NFPA 70-2014—National risk category.
Electrical Code 10
■ NFPA 99-2015—Healthcare Facilities
Table 1.8-1. Essential Electrical System (EES) Risk Categories
■ NFPA 101-2015—Life Safety Code
■ NFPA 110-2016—Standard for Risk Category Failure of Such Equipment or System is Likely to Cause: 11
Emergency and Standby Category 1 ...major injury or death of patients or caregivers…
Power Systems Category 2 ...minor injury to patients or caregivers… 12
■ NFPA 111-2016—Standard on Stored Category 3 ...patient discomfort…
Electrical Energy Emergency and Category 4 ...no impact on patient care…
Standby Power Systems 13
Table 1.8-2. Essential Electrical System (EES) Risk Category by Type
Risk Category Essential Electrical System (EES) Type Example
14
Category 1 Type 1 Critical Care Space
Category 2 Type 2 General Care Space
Category 3 EES not required Basic Examination Space
15
Category 4 EES not required Waiting Room
16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.8-2 Power Distribution Systems
Typical Application by Facility Type August 2017
Sheet 01 106

i Normal Source Normal Source Normal Source Emergency Power Supply

ii G

4 Non-Essential Loads Non-Essential Loads

5
Manual Transfer Switch
6 Equipment Life Safety Critical
Delayed Automatic Transfer Switch Branch Branch Branch

7 Automatic (Non-Delaying)
Essential Electrical System
Transfer Switch

8
Figure 1.8-1. Typical Large Hospital Electrical System—Type 1 Essential Electrical System

9 Type 1 Essential Electrical The transfer switches can be non- Table 1.8-3. Type 1 EES Applicable Codes
delayed automatic, delayed automatic
Systems (EES) or manual transfer depending on the
Description Standard Section

10 Type 1 essential electrical systems requirements of the specific branch Sources NFPA 99 6.4.1
(EES) have the most stringent require- of the EES that they are feeding. It is Uses NFPA 99 6.4.1.1.8
ments for providing continuity of permissible to feed multiple branches Emergency NFPA 110 4.1
11 electrical service and will, therefore, or systems of the EES from a single Power Supply
be the focus of this section. Type 1 automatic transfer switch provided Classification
EES requirements meet or exceed that the maximum demand on the Distribution NFPA 99 6.4.2
12 the requirements for Type 2 facilities. EES does not exceed 150 kVA. This NEC 517.30
configuration is typically seen in General NFPA 99 6.4.2.2.1
Sources: Type 1 systems are required smaller healthcare facilities that NEC 517.25 thru 517.31
to have a minimum of two independent
13 sources of electrical power—a normal
must meet Type 1 EES requirements Life Safety
Branch
NFPA 99
NEC
6.4.2.2.3
517.32
(see Figure 1.8-3).
source that generally supplies the Critical NFPA 99 6.4.2.2.4
entire facility and one or more alter-
14 nate sources that supply power when
Branch NEC 517.33
Normal Source Equipment NFPA 99 6.4.2.2.5
the normal source is interrupted. The Branch NEC 517.34
alternate source(s) must be an on-site
15 generator driven by a prime mover Alternate
Wiring NFPA 99 6.4.2.2.6
NEC 517.30.(C)
unless a generator(s) exists as the Source
normal power source. In the case
16 where a generator(s) is used as the G
normal source, it is permissible for the
alternate source to be a utility feed.
17
Alternate source generators must be
classified as Type 10, Class X, Level 1
18 gensets per NFPA 110 Tables 4.1(a) and
4.2(b) that are capable of providing
power to the load in a maximum of Non-Essential
19 10 seconds. Typically, the alternate
Loads

sources of power are supplied to the Entire Essential


loads through a series of automatic Electric System
20 and/or manual transfer switches (150 kVA or Less)
(see Tab 25).
Figure 1.8-2. Small Healthcare Facility
21 Electrical System—Single EES Transfer Switch

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.8-3
August 2017 Typical Application by Facility Type
Sheet 01 107

Essential Electrical System Branches: 3. Task illumination and selected The following equipment must be
The Type 1 EES consists of three receptacles in the following arranged for delayed automatic or i
separate branches capable of supply- patient care areas: infant manual transfer to the emergency
ing power considered essential for life nurseries, medication prep power supply:
safety and effective facility operation areas, pharmacy, selected ii
during an interruption of the normal acute nursing areas, psychiatric 1. Select heating equipment.
power source. They are the life safety bed areas, ward treatment 2. Select elevators.
branch, critical branch and equipment rooms, nurses’ stations. 3. Supply, return and exhaust 1
branch. 4. Specialized patient care task ventilating systems for surgical,
illumination, where needed. obstetrical, intensive care,
A. Life Safety Branch—supplies
coronary care, nurseries and 2
power for lighting, receptacles 5. Nurse call systems.
and equipment to perform the emergency treatment areas.
6. Blood, bone and tissue banks.
following functions:
7. Telephone equipment rooms
4. Supply, return and exhaust 3
ventilating systems for airborne
1. Illumination of means of egress. and closets. infectious/isolation rooms, labs and
2. Exit signs and exit direction signs. 8. Task illumination, selected medical areas where hazardous 4
3. Alarms and alerting systems. receptacles and selected power materials are used.
circuits for the following: general 5. Hyperbaric facilities.
4. Emergency communications
systems.
care beds (at least one duplex
6. Hypobaric facilities. 5
receptacle), angiographic labs,
5. Task illumination, battery cardiac catheterization labs, 7. Autoclaving equipment.
chargers for battery powered coronary care units, hemodialysis 8. Controls for equipment listed above. 6
lighting, and select receptacles rooms, selected emergency
at the generator. room treatment areas, human 9. Other selected equipment in
kitchens, laundries, radiology
6. Elevator lighting control, physiology labs, intensive care
rooms and central refrigeration 7
communication and signal units, selected postoperative
recovery rooms. as selected.
systems.
7. Automatic doors used for egress. 9. Additional circuits and single- Any loads served by the generator that 8
phase fraction motors as needed are not approved as outlined above as
These are the only functions for effective facility operation. part of the essential electrical system
permitted to be on the life safety must be connected through a separate 9
branch. Life safety branch equip- C. Equipment Branch—consists transfer switch. These transfer switches
ment and wiring must be entirely of major electrical equipment must be configured such that the loads
independent of all other loads necessary for patient care and will not cause the generator to overload 10
and branches of service. This Type 1 operation. and must be shed in the event the
includes separation of raceways, generator enters an overload condition.
boxes or cabinets. Power must be The equipment branch of the EES 11
supplied to the life safety branch that consists of large electrical Ground fault protection—per NFPA 70
from a non-delayed automatic equipment loads needed for NEC Article 230.95, ground fault
transfer switch. patient care and basic healthcare protection is required on any feeder or 12
facility operation. Loads on the service disconnect 1000 A or larger on
B. Critical Branch—supplies power for equipment system that are systems with line to ground voltages
task illumination, fixed equipment, essential to generator operation of 150 V or greater and phase-to-phase 13
selected receptacles and selected are required to be fed by a non- voltages of 600 V or less. For healthcare
power circuits for areas related to delayed automatic transfer switch. facilities (of any type), a second level
patient care. The purpose of the of ground fault protection is required 14
critical branch is to provide power The following equipment must be to be on the next level of feeder
to a limited number of receptacles arranged for delayed automatic downstream.
and locations to reduce load transfer to the emergency power
This second level of ground fault is
15
and minimize the chances of supply:
fault conditions. only required for feeders that serve
1. Central suction systems for patient care areas and equipment
medical and surgical functions. intended to support life. 100%
16
The transfer switch(es) feeding the
critical branch must be automatic 2. Sump pumps and other selective coordination of the two
type. They are permitted to have equipment required for the safe levels of ground fault protection 17
appropriate time delays that will operation of a major apparatus. must be achieved with a minimum
follow the restoration of the life six-cycle separation between the
3. Compressed air systems for upstream and downstream device.
safety branch, but should have medical and surgical functions. 18
power restored within 10 seconds As of the 2011 NEC, ground fault
of normal source power loss. 4. Smoke control and stair
protection is allowed between the
The critical branch provides power pressurization systems.
generator(s) and the EES transfer 19
to circuits serving the following 5. Kitchen hood supply and switch(es). However, NEC 517.17(B)
areas and functions: exhaust systems, if required prohibits the installation of ground
1. Critical care areas.
to operate during a fire. fault protection on the load side of a 20
transfer switch feeding EES circuits
2. Isolated power systems in (see Figure 1.8-3—additional level of
special environments. ground fault). 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.8-4 Power Distribution Systems
Typical Application by Facility Type August 2017
Sheet 01 108

i Normal Source Normal Source(s)


G
Generator Breakers are
ii 480/277 V  480/277 V  480/277 V 
Typically Supplied with
Ground Fault Alarm
1000 A Service 1000 A Service 1000 A Service Only. (NEC 700.27)
GF GF GF
or Larger Entrance or Larger Entrance or Larger Entrance
1
Ground Fault
is Permitted
Additional Level Between Generator
2 GF GF GF GF GF of Ground Fault GF GF GF GF GF GF and EES Transfer
Protection Switches.
(NEC 517.17 (B))
3 Non-Essential Loads
Non-Essential Loads

4
GF = Ground Fault Protection Required Additional Level of Ground Fault is
5 Essential Electrical System
not Permitted on Load Side of EES
Transfer Switches. (NEC 517.17(B)

Figure 1.8-3. Additional Level of Ground Fault Protection


6 1 Ground fault protection is required for service disconnects 1000 A and larger or systems with less than 600 V phase-to-phase and greater than
150 V to ground per NEC 230.95.

7 Careful consideration should be used Wet procedure locations—A wet Electronic line isolation monitors (LIM)
in applying ground fault protection procedure location in a healthcare are used to monitor and display leakage
on the essential electrical system to facility is any patient care area that currents to ground. When leakage
8 prevent a ground fault that causes a is normally subject to wet conditions current thresholds are exceeded, visible
trip of the normal source to also cause while patients are present. By default, and/or audible alarms are initiated to
a trip on the emergency source. Such operating rooms are considered alert occupants of a possible hazardous
9 an event could result in complete power wet procedure locations unless a condition. This alarm occurs without
loss of both normal and emergency risk assessment is performed to interrupting power to allow for the
power sources and could not be show otherwise. Other examples of safe conclusion of critical procedures.
10 recovered until the source of the wet procedure locations might include
ground fault was located and isolated anesthetizing locations, dialysis Table 1.8-5. Wet Procedure Location
from the system. To prevent this locations, etc. (patient beds, toilets Applicable Codes
11 condition, NEC 700.27 removes the and sinks are not considered wet Description Standard Section
ground fault protection requirement locations). These wet procedure General NFPA 99 6.3.2.2.8
for the emergency system source. locations require special protection NEC 517.20
12 Typically, the emergency system to guard against electric shock. The GFCI Protection NFPA 99 6.3.2.2.8.8
generator(s) are equipped with ground fault current in these areas
Isolated Power NFPA 99 6.3.2.2.9, 6.3.2.6
ground fault alarms that do not must be limited to not exceed 5 mA.
13 automatically disconnect power
Systems NE 517.160

during a ground fault. Protection to patient and staff in wet


procedure locations can be provided
14 Table 1.8-4. Ground Fault Protection through the use of GFCI outlets, GFCI
Applicable Codes breakers or isolated power systems.
Description Standard Section If GFCI protection is utilized, each
15 circuit must have a dedicated GFCI
Services NEC 230.95 outlet or GFCI breaker. It is not
Branch-Circuits NEC (see Article 210.13
permissible to use a single GFCI
100 Definition
16 for Applicability) device to protect multiple outlets.
Feeders NEC 215.10 This limits interruption resulting
Additional NFPA 99 6.3.2.5 from a ground fault to a single outlet.
17 Level NEC 517.17
Isolated power systems provide power
Alternate NEC 700.27 to an area that is isolated from ground
Source NEC 701.26
18 (or ungrounded). This type of system
limits the amount of current that
flows to ground in the event of a single
19 line-to-ground fault and maintains
circuit continuity.

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.8-5
August 2017 Typical Application by Facility Type
Sheet 01 109

Maintenance and Testing Routine maintenance should be Paralleling Emergency Generators


Regular maintenance and testing of performed on circuit breakers, transfer i
the electrical distribution system in switches, switchgear, generator equip- Without Utility Paralleling
a healthcare facility is necessary ment, etc. by trained professionals In many healthcare facilities (and other
to ensure proper operation in an to ensure the most reliable electrical large facilities with critical loads), the ii
emergency and, in some cases, to system possible. See Tab 41 for Eaton’s demand for standby emergency power
maintain government accreditation. Electrical Services & Systems (EESS), is large enough to require multiple
Any healthcare facility receiving which provides engineers, trained generator sets to power all of the 1
Medicare or Medicaid reimbursement in development and execution of required essential electrical system
from the government must be annual preventative maintenance (EES) loads. In these cases, it becomes
accredited by the Joint Commission. procedures of healthcare facility more flexible and easier to operate the 2
electrical distribution systems. required multiple generators from a
The Joint Commission has established single location using generator paral-
a group of standards called the Table 1.8-6. Maintenance and Testing
leling switchgear. Figure 1.8-4 shows 3
Environment of Care, which must be Applicable Codes
an example of a typical one-line for a
met for healthcare facility accredita- Description Standard Section
paralleling switchgear lineup feeding
tion. Included in these standards is
Grounding NFPA 99 6.3.3.1 the EES. 4
the regular testing of the emergency
(alternate) power system(s). Diesel- Essential NFPA 99 6.4.4.1 A typical abbreviated sequence of
powered EPS installations must be
Electrical
System
Joint Commission
Environment
EC.2.1.4(d)
operation for a multiple emergency 5
tested monthly in accordance with of Care generator and ATS system follows.
NFPA 110 Standard for Emergency and Generator NFPA 110 8.4 Note that other modes of operation
Standby Power Systems. Generators
Transfer NFPA 110 8.3.5, 8.4.6
such as generator demand priority 6
must be tested for a minimum of Switches
and automated testing modes are
30 minutes under the criteria defined available but are not included below.
in NFPA 110.
Breakers NFPA 99
NFPA 110
6.4.4.1.2.1
8.4.7 (Reference Tab 40 for complete 7
detailed sequences of operation.)

8
Utility
9
Transformer Generators X = Number of Units

Utility G1 G2 Gx 10
Metering

Typical
11
Generator
Breaker
Service Main 12
Emergency Bus
Normal Bus
13
Optional Optional Electrically
Electrically Operated Stored
Operated Energy Breakers 14
Stored EF1 EF2 EFx
F1 F2 Fx
Energy
Breakers 15

16
Equipment Life Safety Critical Load Shed/Load
ATS # 1 ATS # 2 ATS # X Add ATS Units
Non-Essential
Loads 17
Optional Closed
EP1 EP2 Typical EPX Transition
Panelboards Paralleling of 18
Generators and
Utility
19
Figure 1.8-4. Typical One-Line for a Paralleling Switchgear Lineup Feeding the Essential Electrical System (EES)

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.8-6 Power Distribution Systems
Typical Application by Facility Type August 2017
Sheet 01 110

1. Entering emergency mode b. As each automatic transfer Healthcare facilities are ideally suited
i switch transfers back to utility to take advantage of these programs
a. Upon loss of normal source, power, it removes its run request because they already have significant
automatic transfer switches from the generator plant. on-site generation capabilities due to
ii send generator control system
c. When the last automatic trans- the code requirements described.
a run request. Many healthcare facilities are taking
fer switch has retransferred to
b. All available generators are the utility and all run requests advantage of these utility incentives
1 started. The first generator up have been removed from the by adding generator capacity over
to voltage and frequency is generator plant, all generator and above the NFPA requirements.
closed to the bus. circuit breakers are opened. Figure 1.8-5 shows an example
2 c. Unsheddable loads and load one-line of a healthcare facility with
d. The generators are allowed complete generator backup and
shed Priority 1 loads are pow- to run for their programmed
ered in less than 10 seconds. utility interconnect.
3 cool-down period.
d. The remaining generators are e. The system is now back in NFPA 110 requirements state that the
synchronized and paralleled automatic/standby mode. normal and emergency sources must
4 to the bus as they come up to be separated by a fire-rated wall.
voltage and frequency. With Utility Paralleling
The intent of this requirement is so that
e. As additional generators are Today, many utilities are offering their a fire in one location cannot take out
5 paralleled to the emergency customers excellent financial incen- both sources of power. To meet this
bus, load shed priority levels tives to use their on-site generation requirement, the paralleling switchgear
are added, powering their capacity to remove load from the utility must be split into separate sections
6 associated loads. grid. These incentives are sometimes with a tie bus through a fire-rated wall.
f. The system is now in referred to as limited interruptible For more information on generator
emergency mode. rates (LIP). Under these incentives, paralleling switchgear, see Tab 40.
7 utilities will greatly reduce or eliminate
2. Exit from emergency mode kWhr or kW demand charges to their
a. Automatic transfer switches customers with on-site generation
8 sense the utility source is within capabilities. In exchange, during times
acceptable operational toler- of peak loading of the utility grid, the
ances for a time duration set at utility can ask their LIP rate customers
9 the automatic transfer switch. to drop load from the grid by using
their on-site generation capabilities.

10
Utility Fire-Rated Wall
or Separation Barrier
11 Transformer
Generators X = Number of Units

12 Utility G1 G2 Gx
Metering
Utility
13 Protective
Closed
Transition Typical
Relay Generator
Paralleling of
Generators and Breaker
14 Service Main Utility, Plus
Soft Loading/
Unloading
15 Normal Bus Emergency Bus
TIE Optional TIE
Optional Electrically Operated
16 Electrically
Field Installed
Stored Energy
Breakers
Operated
Cable or Busway
Stored F1 F2 Fx EF1 EF2 EFx
17 Energy
Breakers

18
Equipment Life Safety Critical Load Shed/
ATS # 1 ATS # 2 ATS # X Load Add
19 Non-Essential
Loads
ATS Units

20 EP1 EP2 EPX Typical


Panelboards

21 Figure 1.8-5. Typical One-Line Healthcare Facility with Complete Generator Backup and Utility Interconnect

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.8-7
August 2017 Typical Application by Facility Type
Sheet 01 111

Quick Connect Generator and i


Load Bank Capabilities
ii

6
Quick-Connect Double-Throw
7
Many facilities are increasing their
resiliency by including quick connect
capabilities for temporary roll-up Cam-Type Receptacle Sub-Assembly 8
generators. Quick-connect sections can
be added to generator switchboards to Typical (1200 A) Generator Quick Connect Switchboard
allow for the use of temporary roll-up 9
generators when permanent genera-
tors are out-of-service for maintenance
and repair. The same quick-connect 10
device can also be used for convenient
connection of a load bank for periodic
testing of the permanent generators. 11
Another common application for
generator quick-connect structures 12
is on the normal service. Having a
quick-connect infrastructure in place
provides the ability to restore some or 13
all normal system loads such as HVAC,
chillers, etc. that can become crucial
if there were a long-term utility outage. 14
The flexibility to quickly and safely
connect a temporary generator to
these normal system loads can help 15
resume more normal facility opera-
tion during an extended utility
outage. See Tab 21.7 or additional 16
information on quick-connect switch-
boards up to 4000 A and Tab 28
for quick-connect safety switches 17
up to 800 A.

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.8-8 Power Distribution Systems
August 2017
Sheet 01 112

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.9-1
August 2017 Power Quality
Sheet 01 113
Power Quality

Power Quality Terms Defining the Problem Power Quality Terms


i
Power quality problems can be Power disturbance: Any deviation
Technical Overview resolved in three ways: by reducing from the nominal value (or from some
the variations in the power supply selected thresholds based on load
Introduction (power disturbances), by improving tolerance) of the input ac power ii
Sensitive electronic loads deployed the load equipment’s tolerance to those characteristics.
today by users require strict require- variations, or by inserting some
ments for the quality of power delivered interface equipment (known as power Total harmonic distortion or distortion 1
conditioning equipment) between factor: The ratio of the root-mean-
to loads.
the electrical supply and the sensitive square of the harmonic content to the
For electronic equipment, power load(s) to improve the compatibility of root-mean-square of the fundamental 2
disturbances are defined in terms of the two. Practicality and cost usually quantity, expressed as a percentage
amplitude and duration by the elec- determine the extent to which each of the fundamental.
tronic equipment operating envelope. option is used. 3
Crest factor: Ratio between the
Electronic loads may be damaged
Many methods are used to define peak value (crest) and rms value of
and disrupted, with shortened life
expectancy, by these disturbances. power quality problems. For example, a periodic waveform. 4
one option is a thorough on-site Apparent (total) power factor: The
The proliferation of computers, variable investigation, which includes inspecting ratio of the total power input in watts
frequency motor drives, UPS systems wiring and grounding for errors, to the total volt-ampere input. 5
and other electronically controlled monitoring the power supply for
equipment is placing a greater demand power disturbances, investigating Sag: An rms reduction in the ac
on power producers for a disturbance- equipment sensitivity to power voltage, at the power frequency, for 6
free source of power. Not only do these disturbances, and determining the the duration from a half-cycle to a few
types of equipment require quality load disruption and consequential seconds. An undervoltage would have
power for proper operation; many effects (costs), if any. In this way, the a duration greater than several seconds. 7
times, these types of equipment are power quality problem can be defined,
also the sources of power disturbances Interruption: The complete loss of
alternative solutions developed,
that corrupt the quality of power in a and optimal solution chosen.
voltage for a time period. 8
given facility. Transient: A sub-cycle disturbance
Before applying power-conditioning
Power quality is defined according to in the ac waveform that is evidenced
IEEE Standard 1100 (Recommended
equipment to solve power quality
by a sharp brief discontinuity of the 9
problems, the site should be checked
Practice for Powering and Grounding waveform. May be of either polarity
for wiring and grounding problems.
Electronic Equipment) as the concept and may be additive to or subtractive
of powering and grounding electronic
Often, correcting a relatively inexpen-
from the nominal waveform. 10
sive wiring error, such as a loose
equipment in a manner that is suitable connection or a reversed neutral Surge or impulse: See transient.
to the operation of that equipment. and ground wire, can avoid a more 11
IEEE Standard 1159 (Recommended expensive power conditioning solution. Noise: Unwanted electrical signals
Practice for Monitoring Electric Power that produce undesirable effects
Quality) notes that “within the industry, Sometimes the investigative approach in the circuits of control systems 12
alternate definitions or interpretations is not viable, as the exact sensitivities in which they occur.
of power quality have been used, of the load equipment may be
unknown and difficult to determine. Common-mode noise: The noise
reflecting different points of view.”
In other cases, monitoring for power voltage that appears equally and in 13
In addressing power quality problems anomolies may be needed over an phase from each current-carrying
at an existing site, or in the design extended period of time to capture conductor to ground.
stages of a new building, engineers infrequent disturbances. This added
14
need to specify different services or Normal-mode noise: Noise signals
time and expense can be impractical measurable between or among active
mitigating technologies. The lowest in smaller installations.
cost and highest value solution is circuit conductors feeding the subject 15
to selectively apply a combination It is important to remember that while load, but not between the equipment
of different products and services the thorough on-site investigation grounding conductor or associated
as follows: can identify and help solve observed signal reference structure and the active 16
problems on existing installations, for circuit conductors.
■ Power quality surveys, analysis a power systems engineer designing a
and studies new facility, there is no site or equip- 17
■ Power monitoring ment to investigate. Consequently, as
■ Grounding products and services in the prior instances cited, it is often
practical to implement power quality 18
■ Surge protection
solutions to address common issues
■ Voltage regulation as a preemptive measure. Using well-
■ Harmonic solutions accepted practices, such as tiered levels 19
■ Lightning protection (ground rods, of surge protection or UPS systems,
hardware, etc.) an engineer can avoid or alleviate the
■ Uninterruptible power supply (UPS) potential problems that poor power 20
or motor-generator (M-G) set quality can cause on a power system.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.9-2 Power Distribution Systems
Power Quality August 2017
Sheet 01 114
Power Quality

Methodology for Ensuring Effective The proliferation of communication The benefit of implementing cascaded
i Power Quality to Electronic Loads and computer network systems network protection is shown in
The power quality pyramid is an has increased the need for proper Figure 1.9-2. Combined, the two stages
effective guide for addressing power grounding and wiring of ac and data/ of protection at the service entrance
ii quality problems at an existing facility. communication lines. In addition to and branch panel locations reduce the
The framework is also useful for reviewing ac grounding and bonding IEEE 62.41 recommended test wave
specifying engineers who are practices, it is necessary to prevent (C3–20 kV, 10 kA) to less than 200 V
1 designing a new facility. ground loops from affecting the signal voltage, a harmless disturbance level
reference point. for 120 V rated sensitive loads.
Power quality starts with grounding
2 (the base of the pyramid) and then 2. Surge Protection If surge protection is only provided for
moves upward to address the potential the building entrance feeder, the let-
Surge protection devices (SPDs) are through voltage will be approximately
issues. This simple, yet proven
3 recommended as the next stage power 950 V in a 277/480 V system exposed
methodology, will provide the most
quality solutions. NFPA, UL 96A, to induced lightning surges. This
cost-effective approach. As we move
IEEE Emerald Book and equipment level of let-through voltage can cause
higher up the pyramid, the cost per
4 manufacturers recommend the use degradation or physical damage of
kVA of mitigating potential problems
of surge protectors. The SPDs are used most electronic loads.
increase and the quality of the power
to shunt short duration voltage
increases (refer to Figure 1.9-1). Wherever possible, consultants,
5 disturbances to ground, thereby
preventing the surge from affecting specifiers and application engineers
electronic loads. When installed as should ensure similar loads are fed
from the same source. In this way,
6 part of the facility-wide design, SPDs
are cost-effective compared to all disturbance-generating loads are
other solutions (on a $/kVA basis). separated from electronic circuits
Cost Per kVA

affected by power disturbances. For


7 The IEEE Emerald Book recommends example, motor loads, HVAC systems
the use of a two-stage protection and other linear loads should be
concept. For large surge currents, separated from the sensitive process
8 diversion is best accomplished in control and computer systems.
two stages: the first diversion should
be performed at the service entrance The most effective and economic
9 to the building. Then, any residual solution for protecting a large number
5. Uninterruptible Power Supply voltage resulting from the action of loads is to install parallel style SPDs
(UPS, Gen. Sets, etc.) can be dealt with by a second at the building service entrance feeder
10 4. Harmonic Distortion protective device at the power and panelboard locations. These SPDs
3. Voltage Regulation panel of the computer room are either placed in parallel with the
(or other critical loads). loads directly on the equipment
11 2. Surge Protection
bus bars or externally by means of a
1. Grounding short cable. This reduces the cost of
protection for multiple sensitive loads.
12 Figure 1.9-1. Power Quality Pyramid

13 1. Grounding Input—high energy


SPD
transient disturbance; IEEE Category
Grounding represents the foundation CP
SPD C3 Impulse 20,000V; 10,000A
20,000V
of a reliable power distribution 480V 120/208V
PEAK VOLTAGE

14 system. Grounding and wiring


Computer or Best achievable
problems can be the cause of up to Sensitive
performance with single SPD
80% of all power quality problems. Stage 1 Protection Loads
at main panel (950V, at Stage 1)
15 All other forms of power quality (Service Entrance) Stage 2 Protection
(Branch Location)
solutions are dependent upon good 800V
System Test Parameters:
grounding procedures. 400V
IEEE C62.41[10] and C62.45 [10]
16 test procedures using category; 0
480V main entrance panels; 25 uS 50 uS
TIME (MICROSECONDS)
100 ft (30m) of three-phase wire;
17 480/208V distribution transformer; Two stage (cascade
and 208V branch panel. approach) achieves best
possible protection (less
= SPD than 200V at Stage 2)
18
Figure 1.9-2. Cascaded System Protection
19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.9-3
August 2017 Power Quality
Sheet 01 115
Power Quality

The recommended system approach Advantages of the system approach are: By twisting the installation wires, the
for installing SPDs is summarized in
■ The lowest possible investment
area between wires is reduced and the i
Figure 1.9-3. mutual inductance affect minimized.
in mitigating equipment to protect
a facility Increasing the diameter of the ii
1. ■ Building entrance SPDs protect installation wires is of negligible
Identify Critical Loads the facility against large external benefit. Inductance is a “skin effect”
transients, including lightning phenomenon and a function of wire 1
2. ■ SPDs are bi-directional and prevent circumference. Because only a
Identify Non-Critical Loads transient and noise disturbances marginal reduction in inductance is
from feeding back within a system achieved when the diameter of the 2
3. when installed at distribution or installation conductors is increased,
Identify Noise and branch panels the use of large diameter wire results
Disturbance Generating Loads ■ Two levels of protection safeguard
in only minimal improvement 3
sensitive loads from physical (see Figure 1.9-5).
4. damage or operational upset Further benefits provided by integrated
Review Internal Power Distribution Layout
surge suppression designs are the
4
Side-Mounted SPD vs. Integral SPD
elimination of field installation costs and
5. Directly connecting the surge the amount of expensive “outboard”
Identify Facility Exposure to suppresser to the bus bar of electrical wall space taken up by side-mounted
5
Expected Levels of Disturbance distribution equipment results in SPD devices.
the best possible level of protection.
6. Compared to side-mounted devices, Building Entrance Feeder Installation 6
Apply Mitigating Equipment to: connecting the SPD unit to the bus bar Considerations
a) Service Entrance Main Panels eliminates the need for lead wires Installing an SPD device immediately
b) Key Sub-Panels and reduces the let-through voltage after the switchgear or switchboard
7
c) Critical Loads
up to 50% (see Figure 1.9-4). main breaker is the optimal location
d) Data and Communication Lines
for protecting against external distur-
Given that surges are high frequency
bances such as lightning. When placed
8
Figure 1.9-3. System Approach for Installing SPDs disturbances, the inductance of the
installation wiring increases the in this location, the disturbance is
There may be specific single-phase “intercepted” by the SPD and reduced
critical loads within a facility that
let-through voltage of the protective
to a minimum before reaching the
9
device. Figure 1.9-5 shows that
require a higher level of protection. distribution and/or branch panel(s).
for every inch of lead length, the
In these instances, a series style SPD
is best suited for protecting such loads. let-through voltage is increased by The use of a disconnect breaker 10
Application of the series style SPD an additional 15–25 V above the eliminates the need to de-energize
involves wiring it in series with the manufacturers stated suppression the building entrance feeder equip-
load it is feeding. performance. ment should the SPD fail or require 11
Lead length has the greatest effect on isolation for Megger testing.
the actual level of protection realized. 12
Twisting of the installation wires is
the second most important installation
consideration. 13
208Y/120 Panelboard
(integrated versus side mounted SPD)
14
1000 Side-Mounted SPD Device
Side-Mounted SPD SPD Integrated 15
Let-Through Voltage at Bus Bar

(assuming 14-inch (355.6 mm) lead length to bus)


used for Retrofit into Panelboards,
Applications Switchboards, MCCs 800

600
16

SPD
N 400 17
Integrated SPD
SPD (direct bus bar connection)
200
18
GRO UND G RO UND
0
Surge
–200
Event 19
G
G –2.00 0.00 2.00 4.00 6.00 8.00 10.00
\ N
Microseconds 20
Figure 1.9-4. Performance Comparison of Side-Mounted vs. Integrated SPD
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.9-4 Power Distribution Systems
Power Quality August 2017
Sheet 01 116
Power Quality

Reference Tab 34 for detailed


i Additional Let-Through Voltage Using IEEE C1(6000V, 3000A)[3] information on SPDs.
Additional Let-Through Voltage ¿

Waveform (UL 1449 Test Wave)[12]


900 14 AWG
800 209V (23%) 3. Voltage Regulation
ii 700
10 AWG
4 AWG Voltage regulation (i.e., sags or over-
600
673V (75%) voltage) disturbances are generally
500
site- or load-dependent. A variety of
1 400
300 mitigating solutions are available
200
depending upon the load sensitivity,
100
fault duration/magnitude and the
2 0
3 ft (914.4 mm) 1 ft (304.8 mm) specific problems encountered. It is
Lead Length Lead Length, recommended to install monitoring
Loose Wiring Twisted Wires Twisted Wires equipment on the ac power lines to
3 assess the degree and frequency of
Figure 1.9-5. The Effect of Installation Lead Length on Let-Through Voltage occurrences of voltage regulation
1 Additional to UL 1449 ratings.
4 problems. The captured data will allow
The size or capacity of a suppressor is This increase in disturbance voltage for the proper solution selection.
measured in surge current per phase. can result in process disruption
5 Larger suppressers rated at approxi- and downtime. 4. Harmonics Distortion
mately 250 kA per phase should be
Installing Dataline Surge Protection Harmonics and Nonlinear Loads
installed at the service entrance to
6 survive high-energy surges associated Most facilities also have communica- In the past, most loads were primarily
with lightning. tion lines that are potential sources linear in nature. Linear loads draw the
for external surges. As identified by full sine wave of electric current at its
7 A 250 kA per phase surge rating allows the power quality pyramid, proper 60 cycle (Hz) fundamental frequency—
for over a 25-year life expectancy grounding of communication lines is Figure 1.9-6 shows balance single-
assuming an IEEE defined high essential for dependable operation. phase, linear loads. As the figure
8 exposure environment. Lower surge
rating devices may be used; however,
NEC Article 800 states that all data, shows, little or no current flows in
power and cable lines be grounded the neutral conductor when the loads
device reliability and long-term and bonded. are linear and balanced.
9 performance may be compromised.
Power disturbances such as lightning The advent of nonlinear electronic
For aerial structures, the 99.8 percentile can elevate the ground potential loads, where the ac voltage is
recorded lightning stroke current is between two communicating pieces converted to a dc voltage, altered the
10 less than 220 kA. The magnitude of of electronic equipment with different way power was traditionally drawn
surges conducted or induced into a ground references. The result is current from a normal ac sine wave. During
facility electrical distribution system is flowing through the data cable, causing the ac to dc conversion, power
11 considerably lower given the presence component failure, terminal lock-up, electronic devices are switched on
of multiple paths for the surge to travel data corruption and interference. during a fraction of each 1/2 cycle
along. It is for this reason that IEEE causing voltage and current to be
12 C62.41 recommends the C3 (20 kV, NFPA 780 D—4.8 warns that “surge drawn in pulses to obtain the required
10 kA) test wave for testing SPDs suppression devices should be installed dc output. This deviation of voltage
installed at building entrance feeders. on all wiring entering or leaving elec- and current from the normal sine wave
13 tronic equipment, usually power, data results in harmonics.
SPDs with surge ratings greater than or communication wiring.”
250 kA are not required, however, It is important to note that the current
14 higher ratings are available and may Surge suppressers should be installed distortion caused by loads such as
provide longer life. at both ends of a data or communica- rectifiers or switch mode power
tion cable. In those situations where supplies causes the voltage distortion.
15 Installing Panelboard Surge one end of the cable is not connected That voltage distortion is caused by
Protection Devices into an electronic circuit (e.g., contactor distorted currents flowing through an
Smaller surge capacity SPDs (120 kA coil), protection on the electronic end impedance. The amount of voltage
16 per phase) are installed at branch only is required. distortion depends on:
panelboards where power disturbances
are of lower energy, but occur much To prevent the coupling or inducing of ■ System impedance
17 more frequently. This level of surge power disturbances into communication
lines, the following should be avoided:
■ Amount of distorted current
current rating should result in a greater
than 25-year life expectancy. Devices that can cause harmonic
■ Data cables should not be run over
18 fluorescent lighting fixtures
disturbances include rectifiers,
When isolated ground systems are thrusters and switching power
used, the SPD should be installed such ■ Data cables should not be in the supplies, all of which are nonlinear.
19 that any common mode surges are vicinity of electric motors Further, the proliferation of electronic
shunted to the safety ground. ■ The right category cable should equipment such as computers, UPS
be used to ensure transmission systems, variable speed drives,
The use of a disconnect breaker is
20 optional. The additional let-through
performance programmable logic controllers, and
■ Data cables must be grounded at the like: nonlinear loads have become
voltage resulting from the increased a significant part of many installations.
inductance caused by the disconnect both ends when communicating
21 switch is about 50–60 V. between buildings

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.9-5
August 2017 Power Quality
Sheet 01 117
Power Quality

Other types of harmonic-producing and C-phase are in sequence with each Harmonic Issues
loads include arcing devices (such as other. Meaning, the triplen harmonics
Harmonic currents may cause system
i
arc furnaces, welders and fluorescent present on the three phases add
lighting). losses that over burden the distribution
together in the neutral, as shown in
system. This electrical overloading may ii
Figure 1.9-7, rather than cancel each
Nonlinear load currents vary widely contribute to preventing an existing
other out, as shown in Figure 1.9-6.
from a sinusoidal wave shape; often electrical distribution system from
Odd non-triplen harmonics are
they are discontinuous pulses. This serving additional future loads. 1
classified as “positive sequence”
means that nonlinear loads are or “negative sequence” and are the In general, harmonics present on
extremely high in harmonic content. 1st, 5th, 7th, 11th, 13th, etc. a distribution system can have the
Triplen harmonics are the 3rd, 9th, following detrimental effects: 2
In general, as the order of a harmonic
15th,...harmonics. Further, triplen gets higher, its amplitude becomes 1. Overheating of transformers and
harmonics are the most damaging
to an electrical system because these
smaller as a percentage of the funda- rotating equipment. 3
mental frequency.
harmonics on the A-phase, B-phase 2. Increased hysteresis losses.
3. Decreased kVA capacity. 4
60 Hz Fundamental 4. Overloading of neutral.
5. Unacceptable neutral-to-ground 5
A Phase voltages.
6. Distorted voltage and current
waveforms.
6
7. Failed capacitor banks.
120º
Lagging 7
B Phase 8. Breakers and fuses tripping.
9. Double sized neutrals to defy
the negative effects of triplen 8
harmonics.
120º
Lagging
In transformers, generators and 9
C Phase uninterruptible power supplies (UPS)
systems, harmonics cause overheating
and failure at loads below their ratings 10
because the harmonic currents cause
Balance greater heating than standard 60 Hz
Neutral
Current current. This results from increased 11
eddy current losses, hysteresis losses
in the iron cores, and conductor skin
Figure 1.9-6. Balanced Neutral Current Equals Zero effects of the windings. In addition, 12
the harmonic currents acting on the
impedance of the source cause
60 Hz Fundamental harmonics in the source voltage, which 13
3rd Harmonic is then applied to other loads such as
motors, causing them to overheat.
A Phase
The harmonics also complicate the
14
application of capacitors for power
factor correction. If, at a given harmonic 15
120º frequency, the capacitive impedance
B Phase
Lagging equals the system reactive impedance,
the harmonic voltage and current can 16
reach dangerous magnitudes. At the
same time, the harmonics create
120º C Phase
problems in the application of power 17
Lagging factor correction capacitors, they
lower the actual power factor. The
rotating meters used by the utilities for 18
watthour and various measurements
do not detect the distortion component
Neutral
Triplen
caused by the harmonics. Rectifiers 19
Current with diode front ends and large dc side
capacitor banks have displacement

Phase Triplen Harmonics power factor of 90% to 95%. More 20


Added in the Neutral recent electronic meters are capable
of metering the true kVA hours taken
Figure 1.9-7. Single-Phase Loads with Triplen Harmonics
by the circuit. 21

CA08104001E For more information, visit: www.eaton.com/consultants


1.9-6 Power Distribution Systems
Power Quality August 2017
Sheet 01 118
Power Quality

Single-phase power supplies for Table 1.9-2. Low-Voltage System Classification When evaluating current distortion,
i computer and fixture ballasts are and Distortion Limits for 480 V Systems it is important to understand the
rich in third harmonics and their Class C AN DF difference between THD (Total
odd multiples. Harmonic Distortion) and TDD (Total
ii Special application 2 10 16,400 3% Demand Distortion). THD is the
Even with the phase currents perfectly General system 5 22,800 5% measured distortion on the actual
balanced, the harmonic currents in Dedicated system 2 36,500 10%
magnitude of current flowing at a
1 the neutral can total 173% of the 2 Special systems are those where the rate given instant. This could be referred
phase current. This has resulted in of change of voltage of the notch might
to as a “sine wave quality factor”
overheated neutrals. The Information mistrigger an event. AN is a measurement
of notch characteristics measured in as it is a measure of the amount of
2 Technology Industry Council (ITIC)
volt-microseconds, C is the impedance distortion at that given time, for that
formerly known as CBEMA, recom- ratio of total impedance to impedance given magnitude of current. It can
mends that neutrals in the supply to at common point in system. DF is be measured with a simple harmonic
3 electronic equipment be oversized distortion factor. current metering device. Current
to at least 173% of the ampacity of THD is not utilized anywhere in the
the phase conductors to prevent Table 1.9-3. Utility or Cogenerator Supply IEEE 519 standard. Instead, the IEEE
4 problems. ITIC also recommends Voltage Harmonic Limits
519 standard sets limits based on TDD,
derating transformers, loading them Voltage 2.3–69 kV 69–138 kV >138 kV or Total Demand Distortion. TDD is a
to no more than 50% to 70% of their Range
calculated value based on the amount
5 nameplate kVA, based on a rule-of-
Maximum 3.0% 1.5% 1.0% of harmonic distortion related to the
thumb calculation, to compensate individual full load capacity of the electrical
for harmonic heating effects. harmonic system. The formula for calculating
6 In spite of all the concerns they cause, Total 5.0% 2.5% 1.5% TDD is as follows:
harmonic
nonlinear loads will continue to
distortion
increase. Therefore, the systems that
7 supply them will have to be designed
so that their adverse effects are greatly
reduced. Table 1.9-1 shows the typical
Vh
Percentages are  x 100 for each
( IL
)
TDD =  I22 + I32 + I24 + I52 + … x 100

8 harmonic orders from a variety of


harmonic V1
The numerator of the formula is the
harmonic generating sources. and square root of the sum of the current
9 harmonics squared. This value is
Table 1.9-1. Source and Typical Harmonics
Source Typical
Harmonics 1
(
VTHD % =  V22 + V32 + V42 + V25 + … x 100
V1 rms
) divided by IL, which is the full load
capacity of the system. From this, you
10 can see that even heavily distorted
6-pulse rectifier 5, 7, 11, 13, 17, 19… currents (i.e., high current THD) that are
12-pulse rectifier 11, 13, 23, 25… It is important for the system designer only a small fraction of the capacity of
11 18-pulse rectifier 17, 19, 35, 37… to know the harmonic content of the the system will result in a low TDD.
Switch-mode power utility’s supply voltage because it will
supply 3, 5, 7, 9, 11, 13…
Fluorescent lights 3, 5, 7, 9, 11, 13…
affect the harmonic distortion of Harmonic Solutions
12 Arcing devices 2, 3, 4, 5, 7…
the system.
In spite of all the concerns nonlinear
Transformer energization 2, 3, 4 Table 1.9-4. Current Distortion Limits for loads cause, these loads will continue
1 Generally, magnitude decreases as harmonic General Distribution Systems (120– 69,000 V) to increase. Therefore, the application
13 order increases. of nonlinear loads such as variable
Maximum Harmonic Current Distortion in
Percent of IL frequency drives (VFDs) and the
Total Harmonic Distortion systems that supply them will require
14 Revised standard IEEE 519-2014
Individual Harmonic Order (Odd Harmonics)
further scrutiny by the design profes-
ISC /IL <11 11 17 23 35 TDD
indicates the limits of current distortion <h <h <h <h sional. The use of “Clean Power” multi-
pulse VFDs has become a common
15 allowed at the PCC (Point of Common
Coupling) point on the system where
<17 <23 <35
approach so adverse harmonic effects
<20 3 4.0 2.0 1.5 0.6 0.3 5.0 are greatly reduced. Table 1.9-5 and
the current distortion is calculated. 20<50 7.0 3.5 2.5 1.0 0.5 8.0
depicts many harmonic solutions along
16 The 2014 revision is more focused on 50<100 10.0 4.5 4.0 1.5 0.7 12.0
with their advantages and disadvantages.
harmonic limits on the system over 100<1000 12.0 5.5 5.0 2.0 1.0 15.0
time. It now clearly indicates that the >1000 15.0 7.0 6.0 2.5 1.4 20.0
Eaton’s Engineering Services &
17 PCC is the point of connection to 3 All power generation equipment is limited Systems Group (EESS) can perform
the utility. to these values of current distortion,
regardless of actual ISC/IL where: harmonic studies and recommend
The standard now primarily addresses ISC = Maximum short-circuit current at PCC. solutions for harmonic problems.
18 the harmonic limits of the supply volt- IL = Maximum demand load current
age from the utility or cogenerators. (fundamental frequency component) at PCC.
TDD = Total Demand Distortion. Even
19 harmonics are limited to 25% of the odd
harmonic limits above. Current distortions
that result in a dc offset, e.g., half-wave
20 converters, are not allowed.

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.9-7
August 2017 Power Quality
Sheet 01 119
Power Quality

Table 1.9-5. Harmonic Solutions for Given Loads


Load Solutions Advantages Disadvantages i
Type

Drives and rectifiers— Line reactors ■ Inexpensive ■ May require additional compensation ii
includes three-phase ■ For 6-pulse standard drive/rectifier, can
UPS loads reduce harmonic current distortion from
80% down to about 35–40%
K-rated/drive isolation ■ Offers series reactance (similar to line ■ No advantage over reactors for
1
transformer reactors) and provides isolation for reducing harmonics unless in pairs
some transients for shifting phases
dc choke ■ Slightly better than ac line reactors ■ Not always an option for drives
2
for 5th and 7th harmonics ■ Less protection for input semiconductors
■ 85% reduction versus standard ■ Cost difference approaches 18-pulse drive
12-pulse convertor
6-pulse drives and blocking filters, which guarantee
3
IEEE 519 compliance
Harmonic mitigating ■ Substantial (50–80%) reduction in harmonics ■ Harmonic cancellation highly dependent
transformers/phase shifting when used in tandem on load balance 4
■ Must have even multiples of matched loads
Tuned filters ■ Bus connected—accommodates ■ Requires allocation analysis
load diversity ■ Sized only to the requirements of that system;
5
■ Provides PF correction must be resized if system changes
Broadband filters ■ Makes 6-pulse into the equivalent ■ Higher cost
of 18-pulse ■ Requires one filter per drive 6
18-pulse converter ■ Excellent harmonic control for drives ■ High cost
above 100 hp
■ IEEE 519 compliant 7
■ No issues when run from generator sources
Active filters ■ Handles load/harmonic diversity ■ High cost
■ Complete solution up to 50th harmonic
8
Active front end ■ Excellent harmonic control ■ High cost
■ Four quadrant (regen) capability ■ High complexity
■ Can have system stability issues when run
9
from generator source
Computers/ Neutral blocking filter ■ Eliminates the 3rd harmonic from load ■ High cost
switch-mode ■ Relieves system capacity ■ May increase voltage distortion
10
power supplies ■ Possible energy savings
■ 3rd harmonic recalculated back to the load ■ Requires fully rated circuits and
Harmonic mitigating
transformers ■ When used as phase-shifted transformers, oversized neutrals to the loads
11
reduces other harmonics
■ Reduces voltage “flat-topping”
Oversized neutral/derated ■ Tolerate harmonics rather than correct ■ Upstream and downstream equipment
12
transformer ■ Typically least expensive fully rated for harmonics
■ Tolerate harmonics rather than correct ■ Does not reduce system harmonics
K-rated transformer
13
Fluorescent Harmonic mitigating ■ 3rd harmonic recalculated back to the load ■ Requires fully rated circuits and
lighting transformers ■ When used as phase-shifted transformers, oversized neutrals to the loads
reduces other harmonics
■ Reduces voltage “flat-topping”
14
K-rated transformer ■ Tolerate harmonics rather than correct them ■ Does not reduce system harmonics
Low distortion ballasts ■ Reduce harmonics at the source ■ Additional cost and typically more 15
expensive than “system” solutions
Welding/arcing Active filters ■ Fast response and broadband ■ High cost
loads harmonic correction 16
■ Reduces voltage flicker
Tuned filters ■ SCR controlled tuned filters simulates ■ SCR controlled units are high cost
an active filter response but fixed filters are reasonable 17
System Tuned filters ■ Provides PF correction ■ System analysis required to verify application.
solutions ■ Lower cost compared to other systems Must be resized if system changes
Harmonic mitigating ■ Excellent choice for new design or upgrade ■ No PF correction benefit 18
transformers
Active filters ■ Ideal solution and handles system diversity ■ Highest cost
19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.9-8 Power Distribution Systems
Power Quality August 2017
Sheet 01 120

5. Uninterruptible Power Uninterruptible power supply (UPS) Rotary UPS Systems


i Systems (UPS) systems have evolved to serve the
needs of sensitive equipment and Typical Ratings
The advent and evolution of solid-state can supply a stable source of electrical 300–3 MW maximum.
ii semiconductors has resulted in a pro- power, or switch to backup to allow
liferation of electronic computational for an orderly shutdown of the loads Typical Rotary Configurations
devices that we come in contact with without appreciable loss of data or Rotary UPS systems are among the
1 on a daily basis. These machines all process. In the early days of main- oldest working systems developed
rely on a narrow range of nominal frame computers, motor-generator to protect sensitive loads. Many of
ac power in order to work properly. sets provide isolation and clean power these systems are complicated engine-
2 Indeed, many other types of equip- to the computers. They did not have generator sets coupled with high
ment also require that the ac electrical deep reserves, but provided extensive inertial flywheels operated at relatively
power source be at or close to nominal ride-through capability while other low rotational speeds. These legacy
3 voltage and frequency. Disturbances sources of power (usually standby types of hybrid UPS systems are not
of the power translate into failed emergency engine generator sets) the focus of this discussion, because
processes, lost data, decreased were brought online while the normal only one or two vendors continue to
4 efficiency and lost revenue. source of power was unstable or offer them.
unavailable.
The normal power source supplied by See Figure 1.9-8 for the modern high
5 the local utility or provider is typically UPS systems have evolved along the speed Rotary UPS systems discussed
not stable enough over time to lines of rotary types and static types in this section of the guide. These
continuously serve these loads with- of systems, and they come in many types of modern rotary UPS systems
6 out interruption. It is possible that a configurations, including hybrid are advanced, integrated designs
facility outside a major metropolitan designs having characteristics of using scalable configurations of high-
area served by the utility grid will both types. The discussion that speed flywheel, motor and generator in
7 experience outages of some nature follows attempts to compare and one compact UPS package. The new
15–20 times in one year. Certain contrast the two types of UPS rotary technologies have the potential
outages are caused by the weather, systems, and give basic guidance to replace battery backup systems, or
8 and others by the failure of the utility on selection criteria. This discussion at least reduce the battery content
supply system due to equipment will focus on the medium, large and for certain applications. The appeal
failures or construction interruptions. very large UPS systems required by of rotary systems is the avoidance of
9 Some outages are only several cycles users who need more than 10 kVA of the purchase, maintenance and facility
in duration, while others may be for clean reliable power. space required by dc battery based
hours at a time. backup systems.
10 In a broader sense, other problems
Power Ratings of UPS Systems
exist in the area of power quality, and ■ Small UPS: Typically 300 VA to 10 kVA, High-Speed Rotary
11 many of those issues also contribute and sometimes as high as 18 kVA Concept of Operation
to the failure of the supply to provide ■ Medium UPS: 10–60 kVA The modern rotary type of UPS
that narrow range of power to these ■ Large UPS: 100–200 kVA units, and operation is understood by reviewing
12 sensitive loads. higher when units are paralleled the four topics below: startup mode,
Power quality problems take the form ■ Very Large UPS: 200–2 MW normal operation mode, discharge
of any of the following: power failure, units, and higher when units mode and recharge mode.
13 power sag, power surge, undervoltage, are paralleled
Startup Mode
overvoltage, line noise, frequency
Each of these categories is arbitrary The UPS output is energized on
variations, switching transients and
14 harmonic distortion. Regardless of the
because manufacturers have many bypass as soon as power is applied
different UPS offerings for the same from the source to the system input.
reason for outages and power quality
application. The choice of UPS type The UPS continues the startup
problems, the sensitive loads can not
15 function normally without a backup
and the configuration of UPS modules procedure automatically when the
for a given application depends upon front panel controls are placed into
power source. Additionally, in many
many factors, including: the “Online” position. Internal UPS
cases, the loads must be isolated from
16 the instabilities of the utility supply ■ How many power quality problems
system checks are performed then
and power quality problems and given the input contactor is closed. The static
the UPS is expected to solve
clean reliable power on a continuous disconnect switch is turned on and the
17 ■ How much future capacity is to be conduction angle is rapidly increased
basis, or be able to switch over to purchased now for future loads
reliable clean electrical power quickly. from zero to an angle that causes the
■ The nature of the sensitive loads dc bus voltage between the utility con-
18 and load wiring verter and the flywheel converter to
■ Which type of UPS system is reach approximately 650 V through the
favored, rotary or static rectifying action of the freewheeling
19 ■ Choices of battery or dc storage diodes in the utility converter. As soon
technology considered as this level of dc voltage is reached,
the static disconnect turns on fully.
■ A host of other application issues
20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.9-9
August 2017 Power Quality
Sheet 01 121

Static Bypass Option i


It = Input Current
Ir = Real Load Current
Ic = Charging Current
ii
Ig = Voltage Regulation Current
Bypass Contactor
1
It = Ir + Ic + Ig Id = Ih + Ix + Ir
Input Static Disconnect
Output
Contactor Switch Line Inductor
Contactor 2
Source Load

Flywheel Converter Utility Converter Ic Inverter


Fuse Output Transformer
3
Ix
Field Coil ac dc Filter Inductor Ig Id = Output Current 4
Ih = Harmonic Current
Driver dc ac Ix = Reactive Load Current
Ir = Real Load Current
5
Ih
Integrated Motor/Flywheel/
and Generator
6
Figure 1.9-8. Typical-High Speed Modern Rotary UPS
The next step involves the utility Once the flywheel reaches 60 rpm, The second component is charging 7
converter IGBTs to start firing, the flywheel inverter controls the current required by the flywheel to
which allows the converter to act as a acceleration to keep currents below the keep the rotating mass fully charged at
rectifier, a regulating voltage source maximum charging and the maximum rated rpm, or to recharge the rotating 8
and an active harmonic filter. As the input settings. The point that the fly- mass after a discharge. The power to
IGBTs begin to operate, the dc bus wheel reaches 4000 rpm, the UPS is maintain full charge is low at 2 kW and
is increased to a normal operating fully functional and capable of support- is accomplished by the IGBTs of the 9
voltage of approximately 800 V, and ing the load during a power quality flywheel converter gating to provide
the output bus is transferred from event. flywheel acceleration continues small pulses of motoring current to
bypass to the output of the power until the Flywheel reaches “full charge” he flywheel. This current can be 10
electronics module. The transfer from at 7700 rpm. The total time to complete much higher if fast recharge times
bypass is completed when the output startup is less than 5 minutes. are selected.
contactor is closed and the bypass 11
contactor opened in a make-before- Normal Operation Mode The final component of input current
break manner. Once the UPS is started and the is the voltage regulation current, which
flywheel is operating at greater than is usually a reactive current that 12
The firing of the SCRs in the static 4000 rpm, the UPS is in the normal circulates between the input and the
disconnect switch is now changed so operating mode where it is regulating utility converter to regulate the output
that each SCR in each phase is only output voltage and supplying reactive voltage. Leading reactive current 13
turned on during the half-cycle, which and harmonic currents required by the causes a voltage boost across the line
permits real power to flow from the load. At the same time it cancels the inductor, and a lagging current causes
utility supply to the UPS. This firing effect of load current harmonics on the a bucking voltage. By controlling the 14
pattern at the static disconnect switch UPS output voltage. utility converter to maintain nominal
prevents power from the flywheel output voltage, just enough reactive
from feeding backward into the Input current consists of three current flows through the line inductor 15
utility supply and ensures that all of components: real load current, to make up the difference between the
the flywheel energy is available to charging current, and voltage input voltage and the output voltage.
support the load. regulation current. Real current is
The load current consists of three
16
current that is in phase with the supply
Immediately after the output is voltage and supplies real power to components: the harmonic current
transferred from bypass to the power the load. Real current flowing through required by the load, the reactive load 17
electronic module, the flywheel field is the line inductor causes a slight phase current, and the real current, which
excited, which also provides magnetic shift of the current lagging the voltage does the work. The utility converter
lift to unload the flywheel bearings. by 10 degrees and ensures that the supplies both the harmonic and 18
The flywheel inverter is turned on UPS can quickly transfer to bypass reactive currents. Because these
and gradually increases frequency without causing unacceptable currents supply no net power to the
at a constant rate to accelerate the switching transients. load, the flywheel supplies no energy 19
flywheel to approximately 60 rpm. for these currents. They circulate
between the utility converter and
the load. 20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.9-10 Power Distribution Systems
Power Quality August 2017
Sheet 01 122

The power stage controls analyze the Recharge Mode High-Speed Rotary Advantages
i harmonic current requirements of When input power is restored to ■ Addresses all power quality
the load and set the firing angle of acceptable limits, the UPS synchronizes problems
the inverter IGBTs to make the utility the output and input voltages, closes ■ Battery systems are not required
ii converter a very low impedance source the input contactor and turns on the or used
to any harmonic currents. Thus, static disconnect switch. The utility
nonlinear load currents are supplied ■ No battery maintenance required
converter then transfers power from
1 almost entirely from the utility the flywheel to the input source by ■ Unlimited discharge cycles
converter with little effect on the linearly increasing the real input ■ 150-second recharge time available
quality of the UPS output voltage current. The transfer time is program- ■ Wide range of operating tempera-
2 waveform and with almost no mable from 1 to 15 seconds. As soon tures can be accommodated
transmission of load harmonics as the load power is completely (–20 ° to 40 °C)
currents to the input of the UPS. transferred to the input source, the
3 ■ Small compact size and less floor
Discharge Mode utility converter and flywheel converter space required (500 kW systems
start to recharge the flywheel and takes 20 sq ft)
The UPS senses the deviation of return to normal operation mode.
4 the voltage or frequency beyond The flywheel recharge power is
■ N+1 reliability available up to
programmed tolerances and quickly 900 kVA maximum
programmable between a slow and
disconnects the supply source by fast rate. Using the fast rate results ■ No disposal issues
5 turning off the static disconnect switch in an increase of UPS input current
and opening the input contactor. The High-Speed Rotary Disadvantages
over nominal levels.
disconnect occurs in less than one-half ■ Flywheel does not have deep
6 cycle. Then the utility converter starts Recharging the flywheel is accom- reserve capacity—rides through
delivering power from the dc bus to plished by controlling the utility and for up to 13 seconds at 100% load
the load, and the flywheel converter flywheel converter in a similar manner ■ Some enhanced flywheel systems
7 changes the firing point of its IGBTs as is used to maintain full charge in the may extend the ride through to
to deliver power to the dc bus. The normal operation mode, however the 30 seconds at 100% load
UPS maintains a clean output voltage IGBT gating points are changed to ■ Mechanical flywheel maintenance
8 within 3% or nominal voltage to the increase current into the flywheel. required every 2–3 years, and oil
load when input power is lost. changes required every year
9 ■ Recharge fast rates require the
input to be sized for 125% of
nominal current
10 ■ Flywheels failures in field not
understood
■ Requires vacuum pumps for
11 high-speed flywheels
■ Limited number of vendors
and experience
12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.9-11
August 2017 Uninterruptible Power Systems (UPS)
Sheet 01 123

Static UPS Systems Double Conversion Concept of Operation 5. The bypass circuit provides a
The basic operation of the Double path for unregulated normal i
Typical Ratings Conversion UPS is: power to be routed around the
20 kW to 1 MVA / 1 MW, and higher major electronic sub-assemblies
when multiple units are paralleled. 1. Normal power is connected to of the UPS to the load so that ii
the UPS input through the facility the load can continue to operate
Typical Static UPS Configurations electrical distribution system. during maintenance, or if the UPS
Static UPS systems modules are This usually involves two input electronics fails. The bypass static 1
available in three basic types of circuits that can either come from switch can switch to conducting
configurations known as standby, line the same source or from separate mode in <1 millisecond. When the
interactive and double conversion. sources such as utility and site UPS recognizes a requirement to 2
See Tab 33 in this guide for details on generation. transfer to the bypass mode, it
all the UPS configurations available simultaneously turns the static
from Eaton. The lower power ratings
2. The Rectifier/Charger function
switch ON, the output breaker to 3
converts the normal ac power
are likely to be one of the first two OPEN, and the bypass breaker to
to dc power to charge the battery
types of configurations, e.g., standby CLOSE. The output breaker opens
or line interactive. Most medium or
and power the inverter. The
and the bypass breaker closes 4
load is isolated from the normal
large static UPS installations use the in about 50 milliseconds. The
input source.
double conversion technology in one restoration of normal conditions at
or multiple module configurations, 3. The battery stores dc energy the UPS results in the automatic 5
i.e., or multiple UPS units in parallel. for use when input power to the restoration of the UPS module
UPS fails. The amount of power powering the load through the
Special UPS high-efficiency operating available from the dc battery rectifier/charger and inverter with 6
modes like Eco mode or ESS can system and time to discharge load isolation from power quality
provide efficiency improvements to voltage is a function of the type of problems, and the opening of the
over 99%, equating to less than 1% battery selected and the ampere- bypass circuit. 7
losses through the UPS. These modes hour sized used. Battery systems
depend on the system operating with Static Double Conversion Advantages
should be sized for no less than
the static switch closed and power 5 minutes of clean power usage ■ Addresses all power quality 8
conversion sections suspended from a fully charged state, and, in problems
(not off). Modern UPSs can instantly many cases, are sized to provide ■ Suitable for applications from
revert to traditional double conversion more time on battery power. 5 kVA to over 2500 kVA 9
operation within 2 ms on detection of
■ Simple battery systems are
any power anomaly. 4. The dc link connects the output
sized for application 10
of the rectifier/charger to the input
Figure 1.9-9 illustrates the one-line of the inverter and to the battery. ■ Long battery backup times and
diagram of a simple single Double Typically the rectifier/charger is long life batteries are available
Conversion UPS module. Brief sized slightly higher than 100% of ■ Higher reliability is available 11
explanations appear for the standby UPS output because it must power using redundant UPS modules
and line interactive UPS systems the inverter and supply charger
after the text explaining the Double power to the battery. 12
Conversion static UPS type of system.

13
Bypass Breaker (Optional) UPS Module
14
Bypass Static Switch
15
Source Load
Normal Rectifier/Charger Output
Breaker
Inverter
Breaker 16
ac dc
dc ac
17
Battery Breaker

Battery
18

19
Figure 1.9-9. Typical Static UPS, Double Conversion Type with Battery Backup

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.9-12 Power Distribution Systems
Power Quality August 2017
Sheet 01 124

Static Double Conversion Disadvantages 3. The battery stores dc energy for Static Line Interactive UPS
i ■ Battery systems, battery maintenance use by the inverter when input Concept of Operation
and battery replacement are required power to the UPS fails. The The basic operation of the Line
amount of power available from Interactive UPS is:
■ Large space requirement for
ii battery systems (higher life takes
the dc battery system and time to
discharge voltage is a function of 1. The Line Interactive type of UPS
more space, e.g., 500 kW takes
the type of battery selected and has a different topology than
1 80–200 sq ft depending upon the
the ampere-hour sized used. the static double conversion and
type of battery used, VRLA 10 year,
Battery systems should be sized standby systems. The normal
VRLA 20 year or flooded)
for the anticipated outage. input power is connected to the
2 ■ Limited discharge cycles of load in parallel with a battery
battery system 4. The dc link connects the output of and bi-directional inverter/charger
■ Narrow temperature range the rectifier/charger to the input of assembly. The input source
3 for application the inverter and to the battery. usually terminates at a line
Typically the rectifier/charger inductor and the output of the
■ Efficiencies are in the 90–97%
is sized only to supply charger inductor is connected to the load
■ Bypass mode places load at risk
4 unless bypass has UPS backup
power to the battery, and is in parallel with the battery and
rated far lower than in the inverter/charger circuit. See
■ Redundancy of UPS modules double conversion UPS. Figure 1.9-11 for more details.
5 results in higher costs
5. The bypass circuit provides a
■ Output faults are cleared by the 2. The traditional rectifier circuit
direct connection of bypass source is eliminated and this results
bypass circuit
to the load. The load operates
6 ■ Output rating of the UPS is 150% from unregulated power. The
in a smaller footprint and
weight reduction. However, line
■ Battery disposal and safety bypass static switch can switch conditioning is compromised.
issues exist to non-conducting mode in
7 <8 milliseconds. When the UPS 3. When the input power fails, the
Standby UPS Concept of Operation recognizes the loss of normal battery/inverter charger circuit
The basic operation of the Standby input power, it transfers to battery/ reverses power and supplies the
8 UPS is: inverter mode by simultaneously load with regulated power.
1. The Standby UPS topology is turning the Inverter ON and the
static switch OFF. Static Line Interactive UPS Advantages
9 similar to the double conversion ■ Slight improvement of power
type, but the operation of the UPS Static Standby UPS Advantages conditioning over standby
is different in significant ways.
■ Lower costs than double conversion UPS systems
10 Normal power is connected to
■ Small footprints and weights
the UPS input through the facility ■ Rectifier and charger are
electrical distribution system. economically sized ■ Efficient design
11 This usually involves two input ■ Efficient design ■ Batteries are sized for the
circuits that can come from one or ■ Batteries are sized for the application
two sources such as utility and site application
12 generation. See Figure 1.9-10 Static Line Interactive UPS Disadvantages
for details. Static Standby UPS Disadvantages ■ Impractical over 10 kVA
■ Impractical over 2 kVA ■ Not as good conditioning as
13 2. The rectifier/charger function
■ Little to no isolation of load from double conversion
converts the normal ac power to
dc power to charge the battery power quality disturbances ■ Standby power is from battery alone
■ Standby power is from battery alone ■
14 only, and does not simultaneously Battery systems, battery maintenance
power the inverter. The load is ■ Battery systems, battery mainte- and battery replacement are required
connected to the bypass source nance and battery replacement ■ Limited discharge cycles for the
15 through the bypass static switch. are required battery system
The inverter is in the standby ■ Limited discharge cycles of ■ Narrow temperature range for
mode ready to serve the load battery system application
16 from battery power if the input ■ Narrow temperature range for ■ Battery disposal and safety
power source fails. application issues exist
■ Output faults are cleared by the
17 bypass circuit
■ Battery disposal and safety
18 issues exist

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.9-13
August 2017 Power Quality
Sheet 01 125

UPS Module i

Bypass Static Switch ii

Source Load
2
Rectifier/
Normal Output
Breaker
Charger Inverter
Breaker 3
ac dc

dc ac
4
Battery
Breaker
5
Battery
6

Figure 1.9-10. Typical Static UPS, Standby Type with Battery Backup
7

UPS Module
8

9
Source Load
10
Inductor

11
Bidirectional
Inverter/Charger 12
dc

ac
13

14
Battery 15

16
Figure 1.9-11. Typical Static UPS, Line Interactive Type with Battery Backup

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.9-14 Power Distribution Systems
August 2017
Sheet 01 126

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.10-1
August 2017 Other Application Considerations
Sheet 01 127
Seismic Requirements

Seismic Requirements i

ii

1
General
In the 1980s, Eaton embarked on a 2
comprehensive program centered
around designing and building
electrical distribution and control 3
equipment capable of meeting and
exceeding the seismic load require-
ments of the Uniform Building Code 4
(UBC) and California Building Code
(CBC). These codes emphasize build-
ing design requirements. Electrical 5
equipment and distribution system
components are considered attach-
ments to the building. The entire 6
program has been updated to show
compliance with the 2015 International
Building Code (IBC) and the 2016 CBC 7
seismic requirements. Figure 1.10-1. Typical Earthquake Ground Motion Map for the United States

A cooperative effort with the equip- International Building Code (IBC) California Building Code 8
ment user, the building designer and
On December 9, 1994, the International The 2001 CBC was based upon the
the equipment installer ensures that
Code Council (ICC) was established 1997 UBC. In August of 2006, it was
the equipment is correctly anchored 9
as a nonprofit organization dedicated repealed by the California Building
such that it can withstand the effects
to developing a single set of compre- Standards Commission (CBSC) and
of an earthquake. Eaton’s electrical
hensive and coordinated codes. The replaced by the 2007 CBC, California
distribution and control equipment has 10
ICC founders—the Building Officials Code of Regulations (CCR),Title 24,
been tested and seismically proven for
and Code Administrators (BOCA), the Part 2 and used the 2006 IBC as the
requirements in compliance with the
International Conference of Building basis for the code. The 2016 CBC
IBC and CBC. Over 100 different
Officials (ICBO), and the Southern is based upon the 2015 IBC, with 11
assemblies representing essentially all
Building Code Congress International amendments as deemed appropriate
product lines have been successfully
(SBCCI)—created the ICC in response by the CBSC. Eaton’s seismic
tested and verified to seismic require-
to technical disparities among the qualification program fully envelopes 12
ments specified in the IBC and CBC.
three nationally recognized model the requirements of the 2016 CBC with
The equipment maintained structural
codes now in use in the U.S. The many of the distribution and control
integrity and demonstrated the ability
ICC offers a single, complete set of products having Seismic Certification 13
to function immediately after the
construction codes without regional Pre-approval with the California Office
seismic tests. A technical paper,
limitations—the International of Statewide Health Planning and
Earthquake Requirements and Eaton
Building Code. Development (OSHPD). 14
Distribution and Control Equipment
Seismic Capabilities (SA12501SE),
Uniform Building Code (UBC) Process
provides a detailed explanation 15
of the applicable seismic codes 1997 was the final year in which the According to Chapter 16 of the 2015
and Eaton’s equipment qualification UBC was published. It has since been IBC, structure design, the seismic
program. The paper may be found replaced by the IBC. requirements of electrical equipment 16
at www.eaton.com/seismic. Type in buildings may be computed in two
in SA12501SE in the document steps. The first step is to determine
search field. the maximum ground motion to be 17
considered at the site. The second step
is to evaluate the equipment mounting
and attachments inside the building 18
or structure. These are then evaluated
to determine appropriate seismic test
requirements. The ground motion, 19
seismic requirements of the equipment,
and the seismic response spectrum
requirements are discussed on 20
Page 1.10-3, see Figure 1.10-3.

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.10-2 Power Distribution Systems
Other Application Considerations August 2017
Sheet 01 128
Seismic Requirements

Ground Motion As a result, the adjusted maximum According to the IBC and ASCE 7, the
i The first step in the process is to
considered earthquake spectral spectral acceleration (Sa) at periods
response for 0.2 second short period less than 1.45 seconds may be com-
determine the maximum considered (SMS) and at 1.0 second (SM1), adjusted puted by using the following formula:
ii earthquake spectral response accelera-
tion at short periods of 0.2 seconds
for site class effects, are determined
Sa = SDS (0.6 T/T0 + 0.4)
from the following equations:
(SS) and at a period of 1.0 second (S1).
Where T is the period where Sa is
1 These values are determined from a
set of spectral acceleration maps
SMS = Fa SS = 1.0 x 3.73 g = 3.73 g
being calculated:
(Figure 1.10-1) and include numerous SM1 = Fv S1 = 1.5 x 1.389 g = 2.08 g
Therefore, the acceleration at
2 contour lines indicating the severity ASCE 7 (American Society of Civil 0.0417 seconds (24 Hz), for example,
of the earthquake requirements at a Engineers) provides a plot of the is equal to:
particular location in the country. final shape of the design response
3 Sa = 2.49 (0.6 ((0.0417/0.112) + 0.4) = 1.55 g
The spectral acceleration maps spectra of the seismic ground motion.
indicate low to moderate seismic The plot is shown in Figure 1.10-2. The acceleration at 0.03 seconds
requirements for the entire country, ASCE 7 is referenced throughout (33 Hz) is equal to:
4 with the exception of two particular the IBC as the source for numerous
structural design criteria. Sa = 2.49 (0.6 (0.3/0.112) + 0.4) = 1.40 g
areas; the West Coast and the Midwest
(the New Madrid area). The maps At zero period (infinite frequency),
5 indicate that the high seismic require-
The design spectral acceleration curve
T = 0.0, the acceleration (ZPA) is
can now be computed. The peak spec-
ments in both regions, West Coast tral acceleration (SDS) and the spectral equal to:
and Midwest, quickly decrease as one
6 moves away from the fault area.
acceleration at 1.0 second (SD1) may Sa = 2.49 (0.6 (0.0/0.112) + 0.4) =
now be computed from the following 0.996 g (ZPA)
Therefore, the high requirements formulas in the code:
are only limited to a relatively narrow
7 strip along the fault lines. Just a few SDS = 2/3 x SMS = 2/3 x 3.73 g = 2.49 g
The acceleration to frequency
relationship in the frequency range
miles away from this strip, only a of 1.0 Hz to TS is stated equal to:
SD1 = 2/3 x SM1 = 2/3 x 2.08 g = 1.39 g
small percentage of the maximum
8 requirements are indicated. SDS, the peak spectral acceleration, Sa = SD1/T
extends between the values of T0 and
Assuming the worse condition, which Where Sa is the acceleration at the
9 TS. T0 and TS are defined in the codes
is a site directly located near a fault, T period.
as follows:
the maximum considered earthquake
spectral response acceleration at short At 1.0 Hz (T=1.0) this equation yields
T0 = 0.2 SD1/SDS = 0.2 x 1.39/2.49 =
10 periods of 0.2 seconds (SS) is equal to 0.112 seconds (8.96 Hz)
the following acceleration:
285% gravity and at 1.0 second period Sa = 1.39/1 = 1.39 g
(S1) is 124% gravity. These numbers TS = SD1/SDS = 1.39/2.49 =
11 are the maximum numbers for the 5.585 seconds (1.79 Hz)
entire country.
12
Spectural Response Acceleration Sa(g)

To help understand the 2015 IBC (and


2016 CBC) seismic parameters for a
SDS
specific building location, the link to
13 the US Geological Society is extremely Sa =
SD1
T
helpful: http://earthquake.usgs.gov/
research/hazmaps/design/
14 The program will allow one to enter the SD1 SD1 TL
Sa =
latitude and longitude of a location. The T2

15 IBC (CBC) seismic parameters for that


location will then be displayed.
To determine the maximum considered
16 earthquake ground motion for most T0 TS 1.0 TL
site classes (A through D), the code Period T (sec)
introduces site coefficients, which
17 when applied against the location- Figure 1.10-2. Design Response Spectrum
specific site class, produces the
adjusted maximum considered
18 earthquake spectral response
acceleration for the required site.
The site coefficients are defined as
19 Fa at 0.2 seconds short period and
FV at 1.0 second period. From the
tables in the code, the highest adjust-
20 ing factor for SS is equal to 1.0 and the
highest adjusting factor for S1 is 1.50.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.10-3
August 2017 Other Application Considerations
Sheet 01 129
Seismic Requirements

Testing has demonstrated that the It can be seen that Eaton has elected to This completes the ground motion
lowest dominant natural frequency of develop generic seismic requirements design response spectrum. The i
Eaton’s electrical equipment is above that envelop two criteria: spectral accelerations are equal to
3.2 Hz. This indicates that testing at 0.76 g at ZPA, or 33 Hz, and increases
■ The highest possible spectral peak ii
1.39 g at 1 Hz is not necessary. In linearly to a peak acceleration of 1.90 g
addition, having the low end of the accelerations and ZPA at 0.09 seconds (or 11.49 Hz) and stays
spectra higher than realistically ■ The maximum frequency range constant to 0.653 seconds (1.53 Hz),
required forces the shake table to required for many different sites then gradually decreases to 1.24 g at 1
move at extremely high displacements 1 second (or 1.0 Hz). This curve is
to meet the spectral acceleration at shown in Figure 1.10-3.
the low frequencies. 2
Testing to accommodate the low end
10
of the spectra using this acceleration 9
8
3
component can result in testing to a 7 Test Response Spectrum Zero Period

Acceleration (g peak)
factor 2 to 3 times greater than that 6 (TRS) Acceleration = Maximum
realistically required. 5

4
Table Test Motion 4
Through testing experience and data 3
analysis, the seismic acceleration at
1.0 Hz is taken equal to 0.7 g, which 2 Spectrum Dip – Not Important
5
will ensure that the seismic levels are Because Frequency is Not an
Equipment Natural Frequency
achieved well below 3.2 Hz. This yields
a more vigorous test over a wider 1.0
6
.9
range of seismic intensities. .8
.7

In developing the seismic requirements .6 Required Response Spectrum


(RRS)
Zero Period
Acceleration = Maximum
7
.5
above, it is important to recognize Floor Motion
.4
the following:
.3 8
T0 and TS are dependent on SMS and
SD1. If SD1 is small relative to SMS then .2

T0 and TS will be smaller and the 9


associated frequencies will shift
.1
higher. The opposite is also true. 1 2 3 4 5 6 78 9 10 20 30 40 60 80 100
This must be realized in developing Frequency Hz 10
the complete required response
spectrum (RRS). Therefore, it is not Figure 1.10-3. Design Response Spectrum
adequate to stop the peak spectral 11
acceleration at 8.96 Hz. There are other ASCE 7—Seismic Demands on Rp = Component response modifica-
contour line combinations that will tion factor that for electrical equipment
produce higher T0. To account for this Non-Structural Components varies from 2.5 to 6.0. 12
variation it is almost impossible to ASCE 7 provides a formula for
consider all combinations. However, computing the seismic requirements Ip = Component importance factor that
a study of the spectral acceleration of electrical and mechanical equipment is either 1.0 or 1.5. 13
maps indicates that all variations with inside a building or a structure. The Z = Highest point of equipment in a
high magnitude of contour lines could formula is designed for evaluating the building relative to grade elevation.
very well be enveloped by a factor equipment attachment to the equip- 14
of 1.25. Therefore, T0 is recomputed ment foundations. The seismic loads h = Average roof height of building
as follows: are defined as: relative to grade elevation.
T0 = 0.2 SD1/(SDS x 1.25) = 0.2 x 1.39/ Fp = 0.4 ap SDS Wp (1 + 2 Z/h)/(Rp/Ip) The following parameters produce the
15
(2.49 x 1.25) = 0.089 seconds (11.20 Hz) maximum required force:
Where:
Eaton ensures maximum certification ■ Z is taken equal to h (equipment 16
by requiring peak acceleration during Fp = Seismic design force imposed on roof)
testing to extend to 12 Hz. at the component’s center of gravity
■ Ip is taken equal to 1.5
(C.G.) and distributed relative to
■ ap is taken equal to 2.5
17
component mass distribution.
■ Rp is taken equal to 2.5
ap = Component amplification factor 18
■ SDS is equal to 2.49 g as indicated
that varies from 1.00 to 2.50.
in the previous section
SDS = Ground level spectral
acceleration, short period.
The acceleration (Fp/Wp) at the C.G. 19
of the equipment is then computed
Wp = Component operating weight. equal to:
Acceleration = Fp/Wp = 0.4 x 2.5 x 20
2.49 g (1 + 2) / (2.5/1.5) = 4.482 g
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.10-4 Power Distribution Systems
Other Application Considerations August 2017
Sheet 01 130
Seismic Requirements

For equipment on (or below) grade,


i the acceleration at the equipment C.G.
Required Response Spectrum
is then computed equal to:
10
ii Acceleration = Fp/Wp = 0.4 x 2.5 x
2.49 g (1 + 0) / (2.5 /1.5) = 1.49 g
It is impractical to attempt to measure

Acceleration (g)
1 the actual acceleration of the C.G. of a
piece of equipment under seismic test.
1
The seismic response at the middle of
2 base mounted equipment close to its
C.G. is at least 50% higher than the
floor input at the equipment natural
3 frequency. The base accelerations
associated with the accelerations of
0.1
FP/WP at the C.G. of the equipment
4 could then be computed as 4.48 /1.5 1 10 100
= 2.99 g. It is the equipment base input Frequency (Hz)
acceleration that is measured and
5 documented during seismic testing
Eaton Seismic IBC 2015/CBC 2016

and is the acceleration value shown


on Eaton’s seismic certificates.
6 Figure 1.10-4. Required Response Spectrum Curve
Final Combined Requirements
7 To better compare all seismic levels
and determine the final envelope 100% vs. 120%
seismic requirements, the 2016 CBC 10
8 and 2015 IBC for California are plotted
in Figure 1.10-4. All curves are plotted
at 5% damping. An envelopment of the
9 seismic levels in the frequency range
Acceleration (g)

of 3.2 Hz to 100 Hz is also shown.


This level is taken as Eaton’s generic
10 seismic test requirements for all
1

certifications. Eaton performed


additional seismic test runs on the
11 equipment at approximately 120%
of the generic enveloping seismic
requirements (see Figure 1.10-5). Eaton
12 has established this methodology 0.1
to provide additional margin to 1 10 100
accommodate potential changes Frequency (Hz)
13 with the spectral maps, thus eliminat-
Eaton 100% Seismic Envelope Eation 120% Seismic Envelope
ing the need for additional testing.

14 Figure 1.10-5. Eaton Test Required Response Spectrum Curve

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.10-5
August 2017 Other Application Considerations
Sheet 01 131
Seismic Requirements

Product Specific Test Summaries


Table 1.10-6. Distribution Equipment
i
Tested and Seismically Proven Against
Requirements within IBC 2015
Note: For most current information,
ii
see www.eaton.com/seismic.
Eaton Equipment 1
MV Metal-Clad Switchgear, VacClad-W
MV Metal-Enclosed Switchgear:
MEF Front Access
2
MV Metal-Enclosed Switchgear; MVS, MEB
MV Motor Starters: Ampgard 3
MV Variable Frequency Drives (VFD)
MV Busway: Non-Segregated
Unitized Power Centers
4
Spot Network Equipment
LV Metal-Enclosed Drawout Switchgear:
Magnum
5
LV Busway
LV Motor Control Centers (MCC) 6
Switchboards
Panelboards
Dry-Type Distribution Transformers (DTDT)
7
Transfer Switch Equipment
Enclosed Molded-Case Circuit Breakers 8
Safety Switches
Elevator Control
Enclosed Motor Starters & Contactors 9
Variable Frequency Drives (VFD)
Uninterruptible Power Supplies (UPS)
10
CAT Generator Paralleling Switchgear
Resistance Grounding Systems
IEC Equipment 11
Solar Systems Interconnect Equipment
Fire Pump Controllers
Residential/Light Commercial Metering
12
& Distribution

Note: See www.eaton.com/seismic for


13
current seismic certificates.

14
Figure 1.10-6. Sample Seismic Certificate
15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.10-6 Power Distribution Systems
Other Application Considerations August 2017
Sheet 01 132
Seismic Requirements

Additional Design and Note: Eaton recommends that designers Energy Conservation
i Installation Considerations
confirm with the manufacturer if the
Because of the greatly increased cost
seismic certification supplied with the
When installing electrical distribution equipment is based on: of electrical power, designers must
ii and control equipment, consideration
1. ACTUAL shaker table test as
consider the efficiency of electrical
distribution systems, and design for
must be given as to how the methods
employed will affect seismic forces required by the IBC and CBC. energy conservation. In the past,
1 imposed on the equipment, equipment 2. The seismic certificate and test
especially in commercial buildings,
mounting surface, and conduits design was for lowest first cost,
data clearly state if the equipment because energy was inexpensive.
entering the equipment. was tested as free-standing—
2 anchored at the bottom of the
Today, even in the speculative office
Eaton recommends that when specify- building, operating costs are so high
ing a brand of electrical distribution equipment to the shaker table. that energy-conserving designs can
3 and control equipment, the designer 3. Structure attached, that is, justify their higher initial cost with a
references the installation manuals of anchored at the center of gravity rapid payback and continuing savings.
that manufacturer to ascertain that the (C.G.) or at the TOP of the equip- The leading standard for energy
4 requirements can be met through the ment to a simulated wall on the conservation is ASHRAE 90.1 (latest
design and construction process. shaker table. is 2016) and International Energy
Conservation Code (IECC) as adopted
For Eaton electrical distribution and Stand-Alone or Free-Standing Equipment
5 control products, the seismic installa-
by the International Building Code (IBC).
If stand-alone or free-standing, then
tion guides for essentially all product There are four major sources of
this may require that additional width
lines can be found at our Web site: electrical energy conservation in
6 http://www.eaton.com/seismic.
space be allowed at each end of the
a commercial building: 1) Lighting
equipment for additional seismic
Systems, 2) Motors and controls,
Electrical designers must work closely bracing supplied by the manufacturer.
3) Transformers, 4) HVAC system.
7 with the structural or civil engineers
Additional thought must be given to
for a seismic qualified installation. The lighting system must take
the clearances around the equipment
advantage of the newest equipment
8 Consideration must be given to the to rigid structural edifices. Space must
and techniques. New light sources,
type of material providing anchorage be allowed for the differing motions of
familiar light sources with higher
for the electrical equipment. the equipment and the structure, so
efficiencies, solid-state ballasts with
9 that they do not collide during a seis-
If steel, factors such as thickness or dimming controls, use of daylight,
mic event and damage one another.
gauge, attachment via bolts or welding, environmental design, efficient
and the size and type of hardware Note: If the equipment is installed as stand- luminaires, computerized or
10 must be considered. alone or free-standing, with additional programmed control, and the like,
seismic bracing at each end and not are some of the methods that can
If concrete, the depth, the PSI, the type attached to the structure as tested, and yet, increase the efficiency of lighting
11 of re-enforcing bars used, as well as it is fitted tightly against a structural wall,
systems. They add up to providing
then this would be an incorrect installation
the diameter and embedment of the necessary amount of light, with the
for the application of the seismic certificate.
anchorage all must be considered. desired color rendition, from the most
12 Furthermore, if conduits are to be efficient sources, where and when it is
The designer must also give consider-
installed overhead into the equipment, needed, and not providing light where
ation if the equipment will be secured
does the design call for flexible conduits or when it is not necessary.
13 to the wall, versus stand-alone or
of sufficient length to allow for the
free-standing, which requires the The installation of energy-efficient
equipment to withstand the highest conflicting motion of the equipment lighting provides the best payback
14 level of seismic forces. Top cable and the structure during a seismic event for the lowest initial investment and
entry should be avoided for large so as to not damage the conductors should be considered the first step in
enclosures, as accommodation for contained therein, and the terminations a facility energy reduction program.
15 cable/conduit flexibility will need to points within the equipment.
be designed into the system. Motors and controls are another cause
Structure Attached Equipment of wasted energy that can be reduced.
For a manufacturer to simply state The designer must work closely New, energy-efficient motor designs
16 “Seismic Certified” or “Seismic with the structural engineer if the are available using more and better
Qualified” does not tell the designer equipment is to be attached to the core steel, and larger windings.
if the equipment is appropriate for structure to ascertain that the internal
17 the intended installation. wall re-enforcement of the structure,
type of anchor, and depth of embed-
18 ment is sufficient to secure the
equipment so that the equipment,
conduits and structure move at or
19 near the same frequency.

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.10-7
August 2017 Other Application Considerations
Sheet 01 133
Seismic Requirements

For any motor operating 10 or The U.S. Department of Energy (DOE) HVAC systems have traditionally been
more hours per day, the use of has established energy efficiency very wasteful of energy, often being i
energy-efficient types is strongly standards that manufacturers of designed for lowest first cost. This,
recommended. These motors have a distribution transformers must too, is changing. For example, reheat
premium cost of about 20% more comply with since 2007. As of systems are being replaced by variable ii
than standard motors. Depending on January 1, 2016, the DOE standard air volume systems, resulting in equal
loading, hours of use and the cost of CFR Title 10 Chapter II Part 431 comfort with substantial increases in
energy, the additional initial cost could (in Appendix A of Subpart K 2016) efficiency. While the electrical engineer 1
be repaid in energy saved within a few requires increased minimum operat- has little influence on the design of the
months, and it rarely takes more than ing efficiencies for each distribution HVAC system, he/she can specify that
two years. Because, over the life of a transformer size at a loading equal to all motors with continuous or long duty 2
motor, the cost of energy to operate it is 35% of the transformer full load kVA. cycles are specified as energy-efficient
many times the cost of the motor itself, The 35% loading value in the NEMA types, and that the variable-air-volume
any motor with many hours of use standard reflects field studies fans do not use inlet vanes or outlet 3
should be of the energy-efficient type. conducted by the U.S. Department dampers, but are driven by variable-
of Energy, which showed that dry-type speed drives.
Where a motor drives a load with transformers installed in commercial 4
variable output requirements such facilities are typically loaded at an Variable speed drives can often be
as a centrifugal pump or a large fan, average of 35% of their full load desirable on centrifugal compressor
customary practice has been to run the capacity over a 24-hour time period. units as well. Because some of these 5
motor at constant speed, and to throttle Figure 1.10-7 compares losses for requirements will be in HVAC
the pump output or use inlet vanes or both low temperature rise TP-1 specifications, it is important for
outlet dampers on the fan. This is highly and DOE 2016 transformers using the energy-conscious electrical 6
inefficient and wasteful of energy. In a 75 kVA design. engineer to work closely with the
order to achieve maximum energy HVAC engineer at the design stage
efficiency in these applications, solid- to ensure that these systems are as 7
state variable frequency, variable speed energy efficient as possible.
drives for AC induction motors are
available as a reliable and relatively 8
inexpensive option. Using a variable- Former TP-1 Versus NEW DOE 2016 Transformer Loss Comparison
speed drive, the throttling valves, for 75 kVA Copper Wound
80C, 115C and 150C Temperature Rated Designs
inlet vanes or output dampers can be 3500 9
eliminated, saving their initial cost and
energy over the life of the system. An 3000 2903
additional benefit of both energy- 10
efficient motors and variable speed 2557

drives used to control the speed of 2500 2346

variable torque loads, such as centrifu- 2146


2075 11
gal fans and pumps, is that the motors
Watts Losses

2000 1848 1837


1753
operate at reduced temperatures, 1640
resulting in increased motor life.
1500
1612
1519
1407 1426
1615
12
1333
1238 1202 1508
Transformers have inherent losses. 1104 1334
1040
Transformers, like motors, are designed 1000 911 1127 13
for lower losses by using more and 976
857 838
better core materials, larger conductors, 666
759
500
etc., and this results in increased initial 360
300
545 598
14
cost. Because the 480 V to 208Y/120 V 256
193
stepdown transformers in an office 0
building are usually energized 24 hours 0% 25% 35%

Percentage of Load
50% 75% 100%
15
a day, savings from lower losses can
be substantial, and should be consid- DOE 2016 Efficient 150C TP-1 Efficient 150C DOE 2016 Efficient 115C
ered in all transformer specifications. TP-1 Efficient 115C DOE 2016 Efficient 80C TP-1 Efficient 80C 16
One method of obtaining reduced
losses is to specify Premium Efficiency
Figure 1.10-7. Former TP-1 NEW DOE 2016 Transformer Loss Comparison for 75 kVA Copper Wound
transformers with no more than 80 °C 17
(or sometimes 115 °C) average winding
temperature rise at full load. These
transformers generate less heat than 18
standard 150 °C rise transformers,
resulting in lower HVAC operating
costs to remove the heat in areas 19
where they are located.

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.10-8 Power Distribution Systems
Application Considerations August 2017
Sheet 01 134

Building Control Systems Increasingly, advanced signaling is Prime Power


i In order to obtain the maximum
being implemented utilizing sensors DER can be used for generating prime
that communicate wirelessly to power or for cogeneration. Prime power
benefit from these energy-saving gateways that connect them back to concerns a system that is electrically
ii lighting, power and HVAC systems,
they must be controlled to perform
the master control system. The newest separated from the electrical grid.
systems are using fiber optic cables Prime power is generated at remote
their functions most efficiently. as the Ethernet backbone to carry sites where commercial electrical
1 Constant monitoring would be tremendous quantities of data, free power is not available.
required for manual operation but from electromagnetic interference
is impractical and not cost-effective back to the master control system and Cogeneration
2 given the skilled labor rates of facilities auxiliary building systems. While the
engineering personnel. In order to actual method used will depend on Cogeneration is another outgrowth of
ensure optimum energy performance, the type, number and complexity the high cost of energy. Cogeneration
3 some form of automatic control of functions to be performed, the is the production of electric power con-
is required. commonality of exchanging data at the currently with the production of steam,
Ethernet level is a prime consideration hot water and similar energy uses. The
The simplest of these energy-saving
4 controls is a time clock to turn various in the selection of equipment that will electric power can be the main prod-
need to be integrated into the overall uct, and steam or hot water the
systems on and off. Where flexible
system. Eaton offers a variety of byproduct, as in most commercial
control is required, programmable
5 controllers may be used. These metering, protection and control installations, or the steam or hot water
devices that can be used as local Web can be the most required product,
range from simple devices, similar
servers as well as to communicate and electric power a byproduct, as
to multi-function time clocks, to fully
6 programmable, microprocessor-based over Ethernet LANs by BACnet/IP in many industrial installations. In
or Modbus TCP to other master some industries, cogeneration has
devices that run dedicated software to
control systems. been common practice for many
control specific loads or processes.
7 years, but until recently it has not
For complete control of all building Because building design and control been economically feasible for most
systems, building management for maximum energy saving is commercial installations.
8 systems (BMS) with specialized important and complex, and
This has been changed by the high
software can be used. Computers can frequently involves many functions
and several systems, it is necessary cost of purchased energy, plus federal
not only control lighting and HVAC
9 for the design engineer to make a and state policies incentivizing public
systems, and provide peak demand
thorough building and environmental utilities to purchase any excess power
control to minimize the cost of energy,
study, and to weigh the costs and generated by the cogeneration plant.
but they can perform many other
10 advantages of many systems. The In many cases, practical commercial
functions. Fire detection and alarm
result of good design and planning cogeneration systems have been built
systems that generally have their own
can be economical, efficient operation. that provide some or all of the electric
dedicated control system can report
11 back information to the BMS System. Poor design can be wasteful and power required, plus hot water, steam,
extremely costly. and sometimes steam absorption-type
Other auxiliary systems, such as
air conditioning. Such cogeneration
elevator control and various aspects
12 of access and intrusion control, often Distributed Energy Resources systems are now operating success-
fully in hospitals, shopping centers,
have the capability to be integrated Distributed energy resources (DER) high-rise apartment buildings and
to share information with the BMS. are increasingly becoming prominent
13 Other building systems, such as sources of electric power. Distributed
even commercial office buildings.
closed-circuit television monitoring, energy resources are usually small-to- Where a cogeneration system is being
are increasingly sharing data and medium sources of electric generation, considered, the electrical distribution
14 bandwidth over the same Ethernet either from renewable or non-renew- system becomes more complex.
backbone with the building manage- able sources. Sources include: The interface with the utility company
ment computer system. is critical, requiring careful relaying
15 ■ Photovoltaic (PV) systems to protect both the utility and the
The time clocks, programmable (solar systems) cogeneration system. Many utilities
controllers and computers can ■ Energy storage systems (battery) have stringent requirements that
16 obtain data from external sensors
■ Wind must be incorporated into the
and control the lighting, motors and
■ Fossil-fueled (diesel, natural gas, system. Proper generator control
other equipment by means of hard
and protection is necessary, as well.
17 wiring-separate wires to and from landfill gas, coal-bed methane)
An on-site electrical generating plant
each piece of equipment. In the more generators (reciprocating engines)
tied to an electrical utility requires a
complex systems, this would result ■ Gas-fired turbines (natural gas, sophisticated engineering design,
18 in a tremendous number of control landfill gas, coal-bed methane) interconnection application and
wires, so other methods are frequently ■ Water-powered (hydro) system impact studies.
used. A single pair of wires, with
■ Fuel cells
19 electronic digital multiplexing, can
control or obtain data from many ■ Microturbines
different points. ■ Wave power
20 ■ Coal-fired boilers
Distributed energy resources may also
21 be termed alternative energy resources.

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.10-9
August 2017 Application Considerations
Sheet 01 135

Utilities require that when the For installation in/on/for existing Seek the solar module data sheet for
protective device at their substation structures and sites, it is advised a list of standard test condition (STC) i
opens that the device connecting a that, at the minimum, pre-design data, temperature coefficients, and any
cogenerator to the utility open also. and construction tests be performed special module-related information to
This is often accomplished by Transfer for existing power-quality issues, determine the low-temperature open ii
Trip Systems utilizing dedicated fiber water drainage and the utility circuit voltage. The prevailing industry
optic connectivity and local multiplex- feeder/transformer. practice, requires the use of the site’s
ing equipment. Extreme Annual Mean Minimum 1
Additionally, electrical distribution Design Dry Bulb Temperature data,
This can add considerable cost and panel ratings ampacity and short- available in the ASHRAE Handbook.
complexity to the design as well as circuit ratings must be sufficient for Code requires that the resulting 2
reoccuring monthly charges to pay the planned solar system, and the maximum voltage (Voc) when added
for the use of the dedicated fiber. necessary arc flash studies be in the “string of modules” be under
One reason for these complex
performed. Connection to the utility maximum system voltage. Record low 3
is always preceded by a utility inter- temperatures provide an indication of
Transfer Trip arrangements is that connect agreement (application)
most cogenerators are connected to system performance when tempera-
process. Successful approval is tures drop to these levels. Power 4
feeders serving other customers. typically required for the available
Utilities desire to reclose the feeder Xpert Solar inverters are designed to
solar incentives and programs offered 1000 Vdc and 1500 Vdc standards.
after a transient fault is cleared.
Reclosing in most cases will damage
by the utility, municipality, state, and 5
various federal agencies and depart- High Temperature Equation
the cogenerator if it had remained ments. State, and IRS tax incentives
connected to their system. Once the maximum number of
require well-documented records. modules per string is established, 6
Islanding is another reason why the Solar systems, while low maintenance, the minimum number of modules per
utility insists on the disconnection of do require periodic service. The solar string needs to be calculated. Here,
the cogenerator. Islanding is the event modules need to be washed-clean on more site-related aspects come into 7
that after a fault in the utility’s system a regular basis and electrical termina- play, as the voltage of solar modules
is cleared by the operation of the tions require initial and annual checks. decreases with increasing tempera-
protective devices, a part of the Cooling system filters are periodic ture. The modules’ (photovoltaic cell) 8
system may continue to be supplied maintenance items, with the re-fresh temperature is influenced by the
by cogeneration. Such a condition is rate dependent upon typical and ambient temperature, reflected
dangerous to the utility’s operation unusual circumstances. sun-loads from nearby structures, 9
during restoration work. parapet walls, roof-coatings, etc.
Solar systems installed near other new
Major cogenerators are connected to construction where dust is generated Air-flow above and behind the solar 10
the subtransmission or the transmission (e.g., grading, paving) or agricultural modules affect the cell temperature.
system of a utility. Major cogenerators environments may require additional The accepted industry standards to
have buy-sell agreements. In such solar-system checks and services. add to the module heating are listed 11
cases, utilities will use a trip transfer Planning for such contingencies is below. Unusual mounting systems
scheme to trip the cogenerator breaker. the business of solar-system design, may adjust these figures, and it is best
Guidelines that are given in IEEE 1547 construction and on-going operation. to seek assistance in establishing and 12
Performance-based incentives planning such installations.
and IEEE P2030 are starting points,
but the entire design should be require verifiable metering, often ■ 15–20 °C for ground or pole
coordinated with the utility. by registered/approved independent mounted solar systems
13
third parties. Such monitoring periods
■ 20–25 °C for roof-top solar systems
PV System Design Considerations are typically for 60 or more months.
mounted at inclined angles 14
Successful photovoltaic (PV) design It is generally wise to involve engineer- (offers improved air-flow behind
and construction is a complex multi- ing design firms that specialize in the modules)
discipline endeavor. Proper planning complete solar systems “turn-key” ■ 25–30 °C for roof-top solar systems 15
includes site survey and solar site calculations, drawings, construction mounted flat, yet at least 6.00 inches
assessment for maximizing the sun’s management and procurement. (152.4 mm) above the roof surface
energy harvesting for solar module
The following equations are the basis
16
selection, and for updating the Vmp_min = Vmp + (temp-differential x
electrical/mechanical design and of all solar system layout and design. temp-coefficient-of-Vmp)
construction to the latest code and Low Temperature Equation The temp-differential in this case 17
local constraints, including fire includes the above temperature
Voc_max = Voc + (temp-differential x
marshal and seismic regulations. “adders.” The Vmp and related
temp-coefficient-of-Voc) 18
Professionally prepared bid, permit, temperature coefficients are listed
construction and as-built drawings The temp-differential is the difference on the solar module’s data sheets.
must be required and maintained. between the standard module rating
at 25 °C and the low temperature. 19
The voltage (Voc) will rise with
temperatures under 25 °C.
20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.10-10 Power Distribution Systems
Application Considerations August 2017
Sheet 01 136

While the code doesn’t indicate the All wiring from emergency source to Where the emergency or standby
i high temperature to use (i.e., because emergency loads must be kept separate source, such as an engine generator
it is an equipment application issue), from all other wiring and equipment, or separate service, has capacity to
the industry standard is to evaluate the in its own distribution and raceway supply the entire system, the transfer
ii ASHRAE 2% high temperature figures, system, except in transfer equipment scheme can be either a full-capacity
coupled to known location differences. enclosures and similar locations. automatic transfer switch, or, less
Record high temperatures provide costly but equally effective, normal
1 an indication of system performance The most common power source for and emergency main circuit breakers,
when climatic condition reaches large emergency loads is an engine- electrically interlocked such that on
these levels. generator set, but the NEC also permits failure of the normal supply the
2 the emergency supply (subject to emergency supply is connected to the
Beyond the damaging temperature local code requirements) to be storage load. However, if the emergency or
affects on photovoltaic module Vmp batteries, uninterruptible power standby source does not have capacity
3 voltage levels, voltage drop in PV supplies, a separate emergency for the full load, as is usually the
conductors under such conditions also service, or a connection to the service case, such a scheme would require
need to be calculated and evaluated, ahead of the normal service discon- automatic disconnection of the
4 beyond normal temperatures. The necting means. Unit equipment for nonessential loads before transfer.
inverter only uses (knows) the Vmp emergency illumination, with a
voltage at the inverter, not at the rechargeable battery, a charger to A simpler and more economical
5 PV modules. keep it at full capacity when normal approach is a separate emergency
power is on, one or more lamps, and bus, supplied through an automatic
Increasing grid voltages also puts a a relay to connect the battery to the transfer switch, to feed all critical
constraint on the minimum Vmp
6 voltage at the DC input stage.
lamps on loss of normal power, is loads. The transfer switch connects
also permitted. this bus to the normal supply, in
To ensure the full MPPT range without normal operation. On failure of the
Because of the critical nature of
7 power-clipping (reduced power output), emergency power, ground fault
normal supply, the engine-generator
prudent PV system designs shall con- is started, and when it is up to speed
protection is not required. It is the automatic switch transfers the
sider the PV array’s Vmp voltage drop considered preferable to risk arcing
8 to the point of the inverter connection, damage, rather than to disconnect
emergency loads to this source. On
ambient temperatures and the PV return of the normal source, manual or
the emergency supply completely. For automatic retransfer of the emergency
system installation type’s effects on emergency power, ground fault alarm
9 Vmp, solar module miss-match and is required by NEC 700.5(D) to indicate
loads can take place.
tolerance variations, degradation of a ground fault in solidly grounded
solar modules over time (solar system Peak Shaving
10 wye emergency systems of more than
life), etc. Typical Vmp design values, 150 V to ground and circuit-protective Many installations now have
based upon known and expected devices rated 1000 A or more. emergency or standby generators.
conditions are 5–10% over the In the past, they were required for
11 minimum MPPT tracking voltage. Legally required standby systems, as hospitals and similar locations, but
Reference NEC 2017 Section 690 and required by the governmental agency not common in office buildings or
691, Solar Photovoltaic Systems. having jurisdiction, are intended to shopping centers. However, many
12 supply power to selected loads, other costly and unfortunate experiences
Emergency Power than those classed as emergency during utility blackouts in recent years
systems, on loss of normal power. have led to the more frequent installa-
13 Most areas have requirements
These are usually loads not essential tion of engine generators in commer-
for emergency and standby power
systems. The National Electrical Code to human safety, but loss of which cial and institutional systems for safety
could create hazards or hamper and for supplying important loads.
14 does not specifically call for any
rescue or fire-fighting operations.
emergency or standby power, but Industrial plants, especially in process
does have requirements for those NEC requirements are similar to those industries, usually have some form
15 systems when they are legally for emergency systems, except that of alternate power source to prevent
mandated and classed as emergency wiring may occupy the same distribu- extremely costly shutdowns. These
(Article 700), legally required standby tion and raceway system as the standby generating systems are
16 (Article 701) by municipal, state, normal wiring if desired. Optional critical when needed, but they are
federal or other codes, or by any standby systems are those not legally needed only infrequently. They
governmental agency having jurisdic- required, and are intended to protect represent a large capital investment.
17 tion. Optional standby systems, not private business or property where To be sure that their power will be
legally required, are also covered in life safety does not depend on available when required, they should
the NEC (Article 702). performance of the system. Optional be tested periodically under load.
18 Emergency systems are intended to systems can be treated as part of the
supply power and illumination essen- normal building wiring system. Both
tial for safety to human life, when the legally required and optional standby
19 normal supply fails. NEC requirements systems should be installed in such
are stringent, requiring periodic testing a manner that they will be fully avail-
under load and automatic transfer to able on loss of normal power. It is
20 emergency power supply on loss of preferable to isolate these systems
normal supply. See Figure 1.10-8. as much as possible, even though
not required by code.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.10-11
August 2017 Application Considerations
Sheet 01 137

Utility i
Source
Typical Application: Three engine generator sets serve the load, plus one additional engine
generator set for redundancy to achieve N+1 level of performance. Open or Closed transition is available.
ii
G1 G2 G3 G4
Paralleling Switchgear

Revenue
with Distribution 1
Metering
HMI
Touchscreen 2
52G1 52G2 52G3 52G4

Main
Service
D1 D2 D3 D4 3

6
ATS1 N E ATS2 N E ATS3 N E ATS4 N E
To Normal To Emergency
Distribution Circuits
Circuits
7
EDP1 EDP2 EDP3 EDP4
8
Optional Remote PC
with Software 9
LP1 BP1 LP2 BP2 LP3 BP3 LP4 BP4

10
Figure 1.10-8. Typical Emergency Power System

The cost of electric energy has risen The engine-generator must be It is important that the electrical sys- 11
to new high levels in recent years, and selected to withstand the required tem designer providing a substantial
utilities bill on the basis not only of duty cycle. The simplest of these source of emergency and standby
power consumed, but also on the schemes transfer specific loads to the power investigate the possibility of 12
basis of peak demand over a small generator. More complex schemes using it for peak shaving, and even
interval. As a result, a new use for operate the generator in parallel with of partial utility company financing.
in-house generating capacity has the normal utility supply. The savings Frequently, substantial savings in 13
developed. Utilities measure demand in demand charges can reduce the cost power costs can be realized for a
charges on the basis of the maximum of owning the emergency generator small additional outlay in distribution
demand for electricity in any given equipment. and control equipment.
14
specific period (typically 15 or 30
minutes) during the month. Some In some instances, utilities with little Peak shaving equipment operating in
utilities have a demand “ratchet clause” reserve capacity have helped finance parallel with the utility are subject to the 15
that will continue demand charges on the cost of some larger customer- comments made under cogeneration
a given peak demand for a full year, owned generating equipment. In as to separation from the utility under
unless a higher peak results in even return, the customer agrees to take fault conditions. 16
higher charges. One large load, coming some or all of his load off the utility
on at a peak time, can create higher system and on to his own generator at
electric demand charges for a year. the request of the utility (with varying 17
limitations) when the utility load
Obviously, reducing the peak demand approaches capacity.
can result in considerable savings in 18
the cost of electrical energy. For those In some cases, the customer’s
installations with engine generators generator is paralleled with the utility
for emergency use, modern control to help supply the peak utility loads, 19
systems (computers or programmable with the utility buying the supplied
controllers) can monitor the peak power. Some utilities have been able
demand, and start the engine-generator to delay large capital expenditures for 20
to supply part of the demand as it additional generating capacity by such
approaches a preset peak value. arrangements.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.10-12 Power Distribution Systems
August 2017
Sheet 01 138

This page intentionally left blank.


i

ii

10

11

12

13

14

15

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.11-1
August 2017 Reference Data
Sheet 01 139

Codes and Standards a number of other testing laboratories A design engineer should conform
i
have been recognized and accepted. to all applicable codes, and require
The National Electrical Code (NEC), The Institute of Electrical and Electronic equipment to be listed by UL or
NFPA Standard No. 70, is the most Engineers (IEEE) publishes a number another recognized testing laboratory
prevalent electrical code in the United of books (the “color book” series) on wherever possible, and to meet ii
States. The NEC, which is revised every recommended practices for the design ANSI or NEMA standards. ANSI/IEEE
three years, has no legal standing of of industrial buildings, commercial recommended practices should
its own, until it is adopted as law by buildings, emergency power systems, be followed to a great extent. In 1
a jurisdiction, which may be a city, grounding, and the like. Most of these many cases, standards should be
county or state. Most jurisdictions IEEE standards have been adopted as exceeded to get a system of the
adopt the NEC in its entirety; some ANSI standards. They are excellent quality required. The design goal 2
adopt it with variations, usually more guides, although they are not in any should be a safe, efficient, long-
rigid, to suit local conditions and way mandatory. lasting, flexible and economical
requirements. A few large cities, such electrical distribution system. 3
as New York and Chicago, have their
own electrical codes, basically similar Professional Organizations
to the NEC. The designer must deter- American National Standards Institute National Electrical Manufacturers
4
mine which code applies in the area (ANSI) Association (NEMA)
of a specific project.
Headquarters: 1300 North 17th Street 5
The Occupational Safety and Health Suite 900
Act (OSHA) of 1970 sets uniform 1899 L Street, NW Arlington, VA 22209
11th Floor
national requirements for safety in the
Washington, DC 20036
703-841-3200 6
workplace—anywhere that people are
202-293-8020 www.nema.org
employed. Originally OSHA adopted
the 1971 NEC as rules for electrical Operations: National Fire Protection Association 7
safety. As the NEC was amended every (NFPA)
25 West 43rd Street
three years, the involved process for
4th Floor 1 Batterymarch Park
modifying a federal law such as OSHA
New York, NY 10036 Quincy, MA 02169-7471
8
made it impossible for the act to adopt
212-642-4900 617-770-3000
each new code revision. To avoid this
problem, the OSHA administration www.ansi.org www.nfpa.org 9
in 1981 adopted its own code, a con-
densed version of the NEC containing Institute of Electrical and Electronic Underwriters Laboratories (UL)
only those provisions considered Engineers (IEEE) 333 Pfingsten Road 10
related to occupational safety. OSHA Northbrook, IL 60062-2096
Headquarters:
was amended to adopt this code, 847-272-8800
based on NFPA Standard 70E, Part 1, 3 Park Avenue 11
which is now federal law. 17th Floor www.ul.com
New York, NY 10016-5997
International Code Council (ICC)
The NEC is a minimum safety 212-419-7900
500 New Jersey Avenue, NW
12
standard. Efficient and adequate
design usually requires not just Operations: 6th Floor
meeting, but often exceeding NEC 445 and 501 Hoes Lane Washington, DC 20001
1-888-422-7233
13
requirements to provide an effective, Piscataway, NJ 08854-4141
reliable, economical electrical system. 732-981-0060
www.iccsafe.org
Many equipment standards have been www.ieee.org 14
established by the National Electrical
The American Institute of Architects (AIA)
Manufacturers’ Association (NEMA) International Association of Electrical 1735 New York Avenue, NW
and the American National Standards Inspectors (IAEI) Washington, DC 20006-5292 15
Institute (ANSI). Underwriters 901 Waterfall Way 1-800 242-3837
Laboratories (UL) has standards that Suite 602
equipment must meet before UL will Richardson, TX 75080-7702
www.aia.org 16
list or label it. Most jurisdictions and 972-235-1455
OSHA require that where equipment
listed as safe by a recognized labora- www.iaei.org 17
tory is available, unlisted equipment
may not be used. UL is by far the most 18
widely accepted national laboratory,
although Factory Mutual Insurance
Company lists some equipment, and 19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.11-2 Power Distribution Systems
Reference Data August 2017
Sheet 01 140

Table 1.11-1. Selected IEEE Device Numbers for Switchgear Apparatus


i Device Function Definition Typical
Number Uses

ii 2 Time-delay starting or closing relay A device that functions to give a desired amount
of time delay before or after any point of operation
Used for providing a time-delay for
re-transfer back to the normal source
in a switching sequence or protective relay system, in an automatic transfer scheme.
except as specifically provided by device functions
1 48, 62 and 79 described later.
6 Starting circuit breaker A device whose principal function is to connect —
a machine to its source of starting voltage.
2 19 Starting to running transition timer A device that operates to initiate or cause the Used to transfer a reduced voltage
automatic transfer of a machine from the starting starter from starting to running.
to the running power connection.
3 21 Distance relay A device that functions when the circuit —
admittance, impedance or reactance increases or
decreases beyond predetermined limits.
4 23 Temperature control device A device that functions to raise or to lower the Used as a thermostat to control
temperature of a machine or other apparatus, or space heaters in outdoor equipment.
of any medium, when its temperature falls below
5 or rises above, a predetermined level.
24 Volts per hertz relay A device that operates when the ratio of voltage ETR-5000 transformer protective relays,
to frequency is above a preset value or is below EGR-5000 generator protective relay.
6 a different preset value. The relay may have any
combination of instantaneous or time delayed
characteristics.
25 Synchronizing or synchronism check device A device that operates when two AC circuits are In a closed transition breaker
7 within the desired limits of frequency, phase angle transfer, a 25 relay is used to ensure
or voltage, to permit or cause the paralleling of two-sources are synchronized before
these two circuits. paralleling. Eaton EDR-5000 feeder
8 protective relays, EGR-5000 generator
protective relay.
27 Undervoltage relay A device which functions on a given value of Used to protect a motor or other devices
9 undervoltage. from a sustained under-voltage and/or
initiate an automatic transfer when a
primary source of power is lost. Eaton
EDR feeder protective relay, EMR-4000/
10 EMR-5000 motor protective relays,
ETR-5000 transformer protective relay,
EGR-5000 generator protective relay.
11 30 Annunciator relay A non-automatically reset device that gives a Used to remotely indicate that a
number of separate visual indications upon the protective relay has functioned, or
functioning of protective devices, and which may that a circuit breaker has tripped.
also be arranged to perform a lockout function. Typically, a mechanical “drop” type
12 annunciator panel is used.
32 Directional power relay A relay that functions on a desired value of power Used to prevent reverse power from
flow in a given direction, or upon reverse power feeding an upstream fault. Often
13 resulting from arc back in the anode or cathode used when primary backup generation
circuits of a power rectifier. is used in a facility. Eaton EDR-5000
feeder protective relay, EMR-4000/
14 EMR-5000 motor protective relays,
ETR-5000 transformer protective relay,
EGR-5000 generator protective relay.

15 33 Position switch A device that makes or breaks contact when the


main device or piece of apparatus, which has no
Used to indicate the position of a
drawout circuit breaker (TOC switch).
device function number, reaches a given point.
34 Master sequence device A device such as a motor-operated multi-contact —
16 switch, or the equivalent, or a programmable
device, that establishes or determines the operating
sequence of the major devices in equipment
17 during starting and stopping, or during sequential
switching operations.
37 Undercurrent or underpower relay A relay that functions when the current or power Eaton EMR-3000, EMR-4000, EMR-5000
18 flow decreases below a predetermined value. motor protective relays.
38 Bearing protective device A device that functions on excessive bearing —
temperature, or on other abnormal mechanical
19 conditions, such as undue wear, which may
eventually result in excessive bearing temperature.
40 Field relay A device that functions on a given or abnormally EGR-5000 generator protective relay.
high or low value or failure of machine field current,
20 or on an excessive value of the reactive component
of armature current in an AC machine indicating
abnormally high or low field excitation.
21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.11-3
August 2017 Reference Data
Sheet 01 141

Table 1.11-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
Device Function Definition Typical i
Number Uses

41 Field circuit breaker A device that functions to apply, or to remove,


the field excitation of a machine.
— ii
42 Running circuit breaker A device whose function is to connect a machine —
to its source of running or operating voltage.
This function may also be used for a device, such
1
as a contactor, that is used in series with a circuit
breaker or other fault-protecting means, primarily
for frequent opening and closing of the circuit. 2
43 Manual transfer or selector device A manually operated device that transfers control —
or potential circuits in order to modify the plan of
operation of the associated equipment or of some 3
of the associated devices.
44 Unit sequence starting relay A device that functions to start the next available —
unit in multiple-unit equipment upon the failure or
non-availability of the normally preceding unit.
4
46 Reverse-phase, or phase balance, A relay that functions when the polyphase Eaton EDR-3000/EDR-5000 feeder
current relay currents are of reverse-phase sequence, or when
the polyphase currents are unbalanced or contain
protective relay, EMR-3000/EMR-4000/
EMR-5000 motor protective relays,
5
the negative phase-sequence components above ETR-5000 transformer protective relay,
a given amount. EGR-5000 generator protective relay.
47 Phase-sequence voltage relay A relay that functions upon a predetermined Eaton EDR-5000 feeder protective 6
value of polyphase voltage in the desired phase relay, EMR-4000/EMR-5000 motor
sequence. protective relays, ETR-5000
transformer protective relay, 7
EGR-5000 generator protective relay.
48 Incomplete sequence relay A relay that generally returns the equipment to the EMR-3000/EMR-4000/EMR-5000
normal, or off, position and locks it out of the
normal starting, or operating or stopping sequence
motor protective relays. 8
is not properly completed within a predetermined
amount of time. If the device is used for alarm
purposes only, it should preferably be designated 9
as 48 A (alarm).
49 Machine, or transformer, thermal relay A relay that functions when the temperature of a Eaton EMR-3000/EMR-4000/EMR-5000
machine armature, or other load carrying winding motor protective relays, ETR-4000/ 10
or element of a machine, or the temperature ETR-5000 transformer protective relay,
of a power rectifier or power transformer EGR-5000 generator protective relay.
(including a power rectifier transformer) exceeds
a predetermined value.
(Note: When used with external RTD
module.)
11
50 Instantaneous overcurrent, A relay that functions instantaneously on an Used for tripping a circuit breaker
or rate-of-rise relay excessive value of current, or an excessive rate of instantaneously during a high-level
current rise, thus indicating a fault in the apparatus short circuit. Can trip on phase-phase 12
of the circuit being protected. (50), phase-neutral (50N), phase-ground
(50G) faults. Eaton EDR-3000/EDR-5000
protective relays, MP-3000/MP-4000/ 13
EMR-3000/EMR-4000/EMR-5000
motor protective relays, ETR-4000/
ETR-5000 transformer protective relay,
EGR-5000 generator protective relay. 14
51 AC time overcurrent relay A relay with either a definite or inverse time Used for tripping a circuit breaker after
characteristic that functions when the current in an a time delay during a sustained
AC circuit exceeds a predetermined value. overcurrent. Used for tripping a circuit 15
breaker instantaneously during a
high-level short circuit. Can trip on
phase (51), neutral (51N) or ground
(51G) overcurrents. Eaton EDR-3000/
16
EDR-5000 protective relays, MP-3000/
MP-4000/EMR-3000/EMR-4000/
EMR-5000 motor protective relays, 17
ETR-4000/ETR-5000 transformer
protective relay, EGR-5000 generator
protective relay.
18
52 AC circuit breaker A device that is used to close and interrupt an A term applied typically to medium
AC power circuit under normal conditions or to voltage circuit breakers, or low voltage
interrupt this circuit under fault or emergency power circuit breakers. Eaton VCP
conditions. vacuum circuit breaker, magnum DS 19
low voltage power circuit breaker
53 Exciter or DC generator relay A device that forces the DC machine field excitation —
to build up during starting or that functions when 20
the machine voltage has built up to a given value.

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.11-4 Power Distribution Systems
Reference Data August 2017
Sheet 01 142

Table 1.11-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
i Device Function Definition Typical
Number Uses

ii 55 Power factor relay A relay that operates when the power factor
in an AC circuit rises above or below a
Eaton EDR-5000 feeder protective
relay and EMR-4000/EMR-5000
predetermined value. motor protective relays, ETR-5000
transformer protective relay,
1 EGR-5000 generator protective relay.
56 Field application relay A device that automatically controls the application —
of the field excitation to an AC motor at some
2 predetermined point in the slip cycle.
59 Overvoltage relay A relay that functions on a given value of Used to trip a circuit breaker,
overvoltage. protecting downstream equipment
3 from sustained overvoltages.
Eaton EDR-5000 feeder protective
relay and EMR-4000/EMR-5000 motor
protective relays, ETR-5000
4 transformer protective relay,
EGR-5000 generator protective relay.
60 Voltage or current balance relay A relay that operates on a given difference in —
5 voltage, or current input or output of two circuits.
62 Time-delay stopping or opening relay A time-delay relay that serves in conjunction with Used in conjunction with a 27 device
the device that initiates the shutdown, stopping to delay tripping of a circuit breaker
6 or opening operation in an automatic sequence. during a brief loss of primary voltage,
to prevent nuisance tripping.
63 Pressure switch A switch that operates on given values or on a Used to protect a transformer during
7 given rate of change of pressure. a rapid pressure rise during a short
circuit. This device will typically act
to open the protective devices above
and below the transformer. Typically
8 used with a 63-X auxiliary relay to
trip the circuit breaker.
64 Ground protective relay A relay that functions on a failure of the insulation Used to detect and act on a ground-
9 of a machine, transformer or of other apparatus to fault condition. In a pulsing high
ground, or on flashover of a DC machine to ground. resistance grounding system, a 64
device will initiate the alarm.
10 65 Governor A device consisting of an assembly of fluid, —
electrical or mechanical control equipment used for
regulating the flow of water, steam or other media
11 to the prime mover for such purposes as starting,
holding speed or load, or stopping.
66 Notching or jogging device A device that functions to allow only a specified Eaton EMR-3000/EMR-4000/EMR-5000
number of operations of a given device, or motor protective relays.
12 equipment, or a specified number of successive
operations within a given time of each other. It also
functions to energize a circuit periodically or for
13 fractions of specified time intervals, or that is used
to permit intermittent acceleration or jogging of a
machine at low speeds for mechanical positioning.
14 67 AC directional overcurrent relay A relay that functions on a desired value of AC
overcurrent flowing in a predetermined direction.
Eaton EDR-5000 feeder protective
relay, EMR-4000/EMR-5000 motor
protective relays, ETR-5000 transformer
protective relay, EGR-5000 generator
15 protective relay.
69 Permissive control device A device that is generally a two-position manually Used as a remote-local switch for
operated switch that in one position permits the circuit breaker control.
16 closing of a circuit breaker, or the placing of
equipment into operation, and in the other position
prevents the circuit breaker to the equipment from
being operated.
17 71 Level switch A switch that operates on given values, or on a Used to indicate a low liquid level within
given rate of change of level. a transformer tank in order to save
transformers from loss-of-insulation
18 failure. An alarm contact is available
as a standard option on a liquid level
gauge. It is set to close before an unsafe
19 condition actually occurs.
72 DC circuit breaker A device that is used to close and interrupt a —
DC power circuit under normal conditions or to
20 interrupt this circuit under fault or emergency
conditions.

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.11-5
August 2017 Reference Data
Sheet 01 143

Table 1.11-1. Selected IEEE Device Numbers for Switchgear Apparatus (Continued)
Device Function Definition Typical i
Number Uses

73 Load-resistor contactor A device that is used to shunt or insert a step of


load limiting, shifting or indicating resistance in
— ii
a power circuit; to switch a space heater in circuit; or
to switch a light or regenerative load resistor
of a power rectifier or other machine in and out 1
of circuit.
74 Alarm relay A device other than an annunciator, as covered —
under device number 30, which is used to operate, 2
or to operate in connection with, a visible or
audible alarm.
78 Phase-angle measuring relay A device that functions at a predetermined phase EDR-5000 feeder protective relay, 3
angle between two voltages, between two currents, EMR-4000/EMR-5000 motor
or between voltage and current. protective relays, ETR-5000
transformer protective relay,
EGR-5000 generator protective relay. 4
(Note: For Voltage Only—78 V.)
79 AC reclosing relay A relay that controls the automatic closing and Used to automatically reclose a
locking out of an AC circuit interrupter. circuit breaker after a trip, assuming 5
the fault has been cleared after the
power was removed from the circuit.
The recloser will lock-out after a
predetermined amount of failed
6
attempts to reclose. EDR-5000 feeder
protective relay, ETR-5000 transformer
protective relay, EGR-5000 generator 7
protective relay.
81 Frequency relay A relay that functions on a predetermined value of Used to trip a generator circuit
frequency—either under or over, or on normal breaker in the event the frequency 8
system frequency—or rate of change frequency. drifts above or below a given value.
Eaton EDR-5000 feeder protective
relay and EMR-4000/EMR-5000
motor protective relays, ETR-5000 9
transformer protective relay, EGR-5000
generator protective relay.
83 Automatic selective control or transfer relay A relay that operates to select automatically Used to transfer control power 10
between certain sources or conditions in sources in a double-ended
equipment, or performs a transfer operation switchgear lineup.
automatically. 11
85 Carrier or pilot-wire relay A device that is operated or restrained by a signal —
transmitted or received via any communications
media used for relaying. 12
86 Locking-out relay An electrically operated hand, or electrically, reset Used in conjunction with protective
relay that functions to shut down and hold an relays to lock-out a circuit breaker
equipment out of service on the occurrence of (or multiple circuit breakers) after
abnormal conditions. a trip. Typically required to be
13
manually reset by an operator before
the breaker can be reclosed.
87 Differential protective relay A protective relay that functions on a percentage or Used to protect static equipment, 14
phase angle or other quantitative difference of two such as cable, bus or transformers,
currents or of some other electrical quantities. by measuring the current differential
between two points. Typically the
upstream and/or downstream circuit
15
breaker will be incorporated into the
“zone of protection.” Eaton EBR-3000
bus differential relay, ETR-4000/ 16
ETR-5000 transformer protective relays,
EMR-5000 motor protective relay,
EGR-5000 generator protective relay. 17
90 Regulating device A device that functions to regulate a quantity or —
quantities, such as voltage, current, power, speed,
frequency, temperature and load, at a certain value
or between certain (generally close) limits for
18
machines, tie lines or other apparatus.
91 Voltage directional relay A device that operates when the voltage across an —
open circuit breaker or contactor exceeds a given 19
value in a given direction.
94 Tripping or trip-free relay A relay that functions to trip a circuit breaker, —
contactor or equipment, or to permit immediate 20
tripping by other devices, or to prevent immediate
reclosure of a circuit interrupter, in case it should
open automatically even though its closing circuit
is maintained closed.
21

CA08104001E For more information, visit: www.eaton.com/consultants


1.11-6 Power Distribution Systems
Reference Data August 2017
Sheet 01 144

i Suggested IEEE Designations Main Device Other Suffix Letters


for Suffix Letters The following letters denote the main The following letters cover all other
device to which the numbered device distinguishing features, characteristics
ii Auxiliary Devices is applied or is related: or conditions not specifically described
in Auxiliary Devices through Main
These letters denote separate auxiliary A Alarm/auxiliary power Device Parts, which serve to describe
devices, such as the following:
1 AC Alternating current the use of the device in the equipment,
C Closing relay/contactor such as:
BP Bypass
A Automatic
2 CL Auxiliary relay, closed
BT Bus tie
(energized when main device BF Breaker failure
is in closed position) C Capacitor
3 C Close
CS Control switch DC Direct current
D Decelerating/down
D “Down” position switch relay E Exciter
4 E Emergency
L Lowering relay F Feeder/field
F Failure/forward
O Opening relay/contactor G Generator/ground
5 HS High speed
OP Auxiliary relay, open M Motor/metering
(energized when main device L Local/lower
6 is in open position) MOC Mechanism operated contact
M Manual
PB Push button S Synchronizing/secondary
O Open
7 R Raising relay T Transformer
OFF Off
U “UP” position switch relay TOC Truck-operated contacts
ON On
8 X Auxiliary relay Main Device Parts R Raise/reclosing/remote/reverse
Y Auxiliary relay These letters denote parts of the
9 main device, except auxiliary con- T Test/trip
Z Auxiliary relay tacts, position switches, limit switches TDC Time-delay closing contact
and torque limit switches:
10 Actuating Quantities TDDO Time delayed relay coil
C Coil/condenser/capacitor drop-out
These letters indicate the condition or
electrical quantity to which the device CC Closing coil/closing contactor
11 responds, or the medium in which it is
TDO Time-delay opening contact
located, such as the following: HC Holding coil TDPU Time delayed relay coil pickup
12 A Amperes/alternating M Operating motor THD Total harmonic distortion
C Current OC Opening contactor
13 F Frequency/fault S Solenoid

I0 Zero sequence current SI Seal-in


14 I-, I2 Negative sequence current T Target

I+, I1 Positive sequence current TC Trip coil


15
P Power/pressure
PF Power factor
16
S Speed

17 T Temperature
V Voltage/volts/vacuum
18 VAR Reactive power
VB Vibration
19 W Watts

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.11-7
August 2017 Reference Data
Sheet 01 145

Enclosures
The following are reproduced from NEMA 250.
i
Table 1.11-2. Comparison of Specific Applications of Enclosures for Indoor Nonhazardous Locations
Provides a Degree of Protection Against the Enclosure Type
ii
Following Environmental Conditions 11 21 4 4X 5 6 6P 12 12K 13

Incidental contact with the enclosed equipment ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ 1


Falling dirt ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Falling liquids and light splashing ■ ■ ■ ■ ■ ■ ■ ■ ■
Circulating dust, lint, fibers and flyings 2 ■ ■ ■ ■ ■ ■ ■ 2
Settling airborne dust, lint, fibers and flyings 2 ■ ■ ■ ■ ■ ■ ■ ■
Hosedown and splashing water ■ ■ ■ ■
■ ■ ■
Oil and coolant seepage
Oil or coolant spraying and splashing ■
3
Corrosive agents ■ ■
Occasional temporary submersion ■ ■
Occasional prolonged submersion ■ 4
1 These enclosures may be ventilated.
2 These fibers and flying are nonhazardous materials and are not considered the Class III type
ignitable fibers or combustible flyings. For Class III type ignitable fibers or combustible flyings, 5
see the National Electrical Code, Article 500.

Table 1.11-3. Comparison of Specific Applications of Enclosures for Outdoor Nonhazardous Locations 6
Provides a Degree of Protection Against the Enclosure Type
Following Environmental Conditions 3 3R 3 3S 4 4X 6 6P
7
Incidental contact with the enclosed equipment ■ ■ ■ ■ ■ ■ ■
Rain, snow and sleet 4 ■ ■ ■ ■ ■ ■ ■
Sleet 5 ■
Windblown dust ■ ■ ■ ■ ■ ■
8
Hosedown ■ ■ ■ ■
Corrosive agents ■ ■
Occasional temporary submersion ■ ■ 9
Occasional prolonged submersion ■
3 These enclosures may be ventilated.
4 External operating mechanisms are not required to be operable when the enclosure is ice covered. 10
5 External operating mechanisms are operable when the enclosure is ice covered.

Table 1.11-4. Comparison of Specific Applications of Enclosures for Indoor Hazardous Locations 11
Provides a Degree of Protection Against Class Enclosure Types Enclosure Type
Atmospheres Typically Containing 7 and 8, Class I Groups 6 9, Class II Groups 6
(For Complete Listing, See NFPA 497M) A B C D E F G 10 12
Acetylene I ■
Hydrogen, manufactured gas I ■
diethyl ether, ethylene, cyclopropane I ■ 13
Gasoline, hexane, butane, naphtha, propane,
acetone, toluene, isoprene I ■
Metal dust II ■ 14
Carbon black, coal dust, coke dust II ■
Flour, starch, grain dust II ■

Fibers, flyings 7
Methane with or without coal dust
III
MSHA ■
15
6 For Class III type ignitable fibers or combustible flyings, see the National Electrical Code, Article 500.
7 Due to the characteristics of the gas, vapor or dust, a product suitable for one class or group may
not be suitable for another class or group unless so marked on the product.
16
Note: If the installation is outdoors and/or additional protection is required by Tables 1.11-2 and
1.11-3, a combination-type enclosure is required.
17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.11-8 Power Distribution Systems
Reference Data August 2017
Sheet 01 146

Table 1.11-5. Conversion of NEMA Enclosure Type Ratings to IEC 60529 Enclosure Classification Designations (IP)
i (Cannot be Used to Convert IEC Classification Designations to NEMA Type Ratings)

IP NEMA Enclosure Type IP


ii First 1 2 3 3R 3S 4 4X 5 6 6P 12 12K 13 Second
Character Character
IP0– IP–0
1 IP1– IP–1
IP2– IP–2
IP3– IP–3
2 IP4–
IP5–
IP–4
IP–5
IP6– IP–6
IP–7
3 IP–8
A B A B A B A B A B A B A B A B A B A B A B A B A B
A = A shaded block in the “A” column indicates that the NEMA Enclosure Type exceeds the requirements for the respective IEC 60529
4 IP First Character Designation. The IP First Character Designation is the protection against access to hazardous parts and solid
foreign objects.
B = A shaded block in the “B” column indicates that the NEMA Enclosure Type exceeds the requirements for the respective IEC 60529
5 IP Second Character Designation. The IP Second Character Designation is the protection against the ingress of water.

EXAMPLE OF TABLE USE


6 An IEC IP45 Enclosure Rating is specified. What NEMA Type Enclosures meet and exceed the IP45 rating?

Referencing the first character, 4, in the IP rating and the row designated “IP4–” in the leftmost column in the
7 table; the blocks in Column “A” for NEMA Types 3, 3S, 4, 4X, 5, 6, 6P, 12, 12K and 13 are shaded. These NEMA
ratings meet and exceed the IEC protection requirements against access to hazardous parts and solid foreign
objects. Referencing the second character, 5, in the IP rating and the row designated “IP–5” in the rightmost
8 column in the table; the blocks in Column “B” for NEMA Types 3, 3S, 4, 4X, 6 and 6P are shaded. These NEMA
ratings meet and exceed the IEC requirements for protection against the ingress of water. The absence of shading
in Column “B” beneath the “NEMA Enclosure Type 5” indicates that Type 5 does not meet the IP45 protection
9 requirements against the ingress of water. Likewise, the absence of shading in Column “B” for NEMA Type 12,
12K and 13 enclosures indicates that these enclosures do not meet the IP45 requirements for protection against
the ingressof water. Only Types 3, 3S, 4, 4X, 6 and 6P have both Column “A” in the “IP4–” row and Column “B”
10 in the “IP–5” row shaded and could be used in an IP45 application.

The NEMA Enclosure Type 3 not only meets the IP45 Enclosure Rating, but also exceeds the IEC requirements
11 because the NEMA Type requires an outdoor corrosion test; a gasket aging test; a dust test; an external icing
test; and no water penetration in the rain test. Slight differences exist between the IEC and NEMA test methods,
but the IEC rating permits the penetration of water if “it does not deposit on insulation parts, or reach live parts.”
12 The IEC rating does not require a corrosion test; gasket aging test; dust test or external icing test. Because the
NEMA ratings include additional test requirements, this table cannot be used to select IP Designations for NEMA
rated enclosure specifications.
13
IEC 60529 specifies that an enclosure shall only be designated with a stated degree of protection indicated by
the first characteristic numeral if it also complies with all lower degrees of protection. Furthermore, IEC 60529
14 states that an enclosure shall only be designated with a degreeof protection indicated by the second characteristic
numeral if it also complies with all lower degrees of protection up to and including the secondcharacteristic
numeral 6. An enclosure designated with a second characteristic numeral 7 or 8 only is considered unsuitable
15 for exposure to water jets (designated by second characteristic numeral 5 or 6) and need not comply with
requirements for numeral 5 or 6 unless it is dual coded. Because the IEC protection requirements become more
stringent with increasing IP character value up through 6, once a NEMA Type rating meets the requirements for
16 an IP designation up through 6, it will also meet the requirements for all lower IP designations. This is apparent
from the shaded areas shown in the table.

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.11-9
August 2017 Reference Data
Sheet 01 147

2 2
Average Characteristics of Application Notes ■ Z  X R
600 V Conductors— ■ Resistance and reactance are ■ For busway impedance data, see
i
phase-to-neutral values, based on Tab 21 of this catalog
Ohms per 1000 ft (305 m)
60 Hz AC, three-phase, four-wire ■ For PF (power factor) values less ii
The tables below are average charac- distribution, in ohms per 100 ft than 1.0, the effective impedance Ze
teristics based on data from IEEE (30 m) of circuit length (not total is calculated from
Standard 141-1993. Values from
different sources vary because of
conductor lengths) Z e  R  PF  X sin (arc cos PF) 1
■ Based upon conductivity of 100% for
operating temperatures, wire ■ For copper cable data, resistance
copper, 61% for aluminum
stranding, insulation materials based on tinned copper at 60 Hz;
and thicknesses, overall diameters, ■ Based on conductor temperatures
600 V and 5 kV nonshielded cable
2
random lay of multiple conductors of 75 °C. Reactance values will
based on varnished cambric insula-
in conduit, conductor spacing, and have negligible variation with
tion; 5 kV shielded and 15 kV cable 3
other divergences in materials, test temperature. Resistance of both
based on neoprene insulation
conditions and calculation methods. copper and aluminum conductors
will be approximately 5% lower ■ For aluminum cable data, cable is
These tables are for 600 V 5 kV and
15 kV conductors, at an average at 60 °C or 5% higher at 90 °C. cross-linked polyethylene insulated 4
temperature of 75 °C. Other parame- Data shown in tables may be
ters are listed in the notes. For used without significant error
medium voltage cables, differences between 60 ° and 90 °C 5
among manufacturers are consider- ■ For interlocked armored cable,
ably greater because of the wider vari- use magnetic conduit data for
ations in insulation materials and steel armor and non-magnetic
6
thicknesses, shielding, jacketing, over- conduit data for aluminum armor
all diameters, and the like. Therefore, 7
data for medium voltage cables should
be obtained from the manufacturer
of the cable to be used. 8
Table 1.11-6. 60 Hz Impedance Data for Three-Phase Copper Cable Circuits, in Approximate Ohms per 1000 ft (305 m) at 75 °C (a) Three Single Conductors
Wire Size, In Magnetic Duct In Non-Magnetic Duct
9
AWG or 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
R X Z R X Z R X Z R X Z
10
8 0.811 0.0754 0.814 0.811 0.0860 0.816 0.811 0.0603 0.813 0.811 0.0688 0.814
8 (solid) 0.786 0.0754 0.790 0.786 0.0860 0.791 0.786 0.0603 0.788 0.786 0.0688 0.789
6 0.510 0.0685 0.515 0.510 0.0796 0.516 0.510 0.0548 0.513 0.510 0.0636 0.514 11
6 (solid) 0.496 0.0685 0.501 0.496 0.0796 0.502 0.496 0.0548 0.499 0.496 0.0636 0.500
4 0.321 0.0632 0.327 0.321 0.0742 0.329 0.321 0.0506 0.325 0.321 0.0594 0.326
4 (solid)
2
0.312
0.202
0.0632
0.0585
0.318
0.210
0.312
0.202
0.0742
0.0685
0.321
0.214
0.312
0.202
0.0506
0.0467
0.316
0.207
0.312
0.202
0.0594
0.0547
0.318
0.209
12
1 0.160 0.0570 0.170 0.160 0.0675 0.174 0.160 0.0456 0.166 0.160 0.0540 0.169
1/0 0.128 0.0540 0.139 0.128 0.0635 0.143 0.127
2/0 0.102 0.0533 0.115 0.103 0.0630 0.121 0.101
0.0432
0.0426
0.134
0.110
0.128
0.102
0.0507
0.0504
0.138
0.114
13
3/0 0.0805 0.0519 0.0958 0.0814 0.0605 0.101 0.0766 0.0415 0.0871 0.0805 0.0484 0.0939
4/0 0.0640 0.0497 0.0810 0.0650 0.0583 0.0929 0.0633 0.0398 0.0748 0.0640 0.0466 0.0792
250 0.0552 0.0495 0.0742 0.0557 0.0570 0.0797 0.0541 0.0396 0.0670 0.0547 0.0456 0.0712 14
300 0.0464 0.0493 0.0677 0.0473 0.0564 0.0736 0.0451 0.0394 0.0599 0.0460 0.0451 0.0644
350 0.0378 0.0491 0.0617 0.0386 0.0562 0.0681 0.0368 0.0393 0.0536 0.0375 0.0450 0.0586
400 0.0356 0.0490 0.0606 0.0362 0.0548 0.0657 0.0342 0.0392 0.0520 0.0348 0.0438 0.0559 15
450 0.0322 0.0480 0.0578 0.0328 0.0538 0.0630 0.0304 0.0384 0.0490 0.0312 0.0430 0.0531
500 0.0294 0.0466 0.0551 0.0300 0.0526 0.0505 0.0276 0.0373 0.0464 0.0284 0.0421 0.0508
600
750
0.0257
0.0216
0.0463
0.0495
0.0530
0.0495
0.0264
0.0223
0.0516
0.0497
0.0580
0.0545
0.0237
0.0194
0.0371
0.0356
0.0440
0.0405
0.0246
0.0203
0.0412
0.0396
0.0479
0.0445
16
Note: More tables on Page 1.11-10.
17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.11-10 Power Distribution Systems
Reference Data August 2017
Sheet 01 148

Table 1.11-7. 60 Hz Impedance Data for Three-Phase Copper Cable Circuits, in Approximate Ohms per 1000 ft (305 m) at 75 °C (b) Three Conductor Cable
i Wire Size, In Magnetic Duct and Steel Interlocked Armor In Non-Magnetic Duct and Aluminum Interlocked Armor
AWG or 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
ii R X Z R X Z R X Z R X Z

8 0.811 0.0577 0.813 0.811 0.0658 0.814 0.811 0.0503 0.812 0.811 0.0574 0.813
8 (solid) 0.786 0.0577 0.788 0.786 0.0658 0.789 0.786 0.0503 0.787 0.786 0.0574 0.788
1 6
6 (solid)
0.510
0.496
0.0525
0.0525
0.513
0.499
0.510
0.496
0.0610
0.0610
0.514
0.500
0.510
0.496
0.0457
0.0457
0.512
0.498
0.510
0.496
0.0531
0.0531
0.513
0.499
4 0.321 0.0483 0.325 0.321 0.0568 0.326 0.321 0.0422 0.324 0.321 0.0495 0.325
2 4 (solid)
2
0.312
0.202
0.0483
0.0448
0.316
0.207
0.312
0.202
0.0508
0.0524
0.317
0.209
0.312
0.202
0.0422
0.0390
0.315
0.206
0.312
0.202
0.0495
0.0457
0.316
0.207
1 0.160 0.0436 0.166 0.160 0.0516 0.168 0.160 0.0380 0.164 0.160 0.0450 0.166
1/0 0.128 0.0414 0.135 0.128 0.0486 0.137 0.127 0.0360 0.132 0.128 0.0423 0.135
3 2/0 0.102 0.0407 0.110 0.103 0.0482 0.114 0.101 0.0355 0.107 0.102 0.0420 0.110
3/0 0.0805 0.0397 0.0898 0.0814 0.0463 0.0936 0.0766 0.0346 0.0841 0.0805 0.0403 0.090
4/0 0.0640 0.0381 0.0745 0.0650 0.0446 0.0788 0.0633 0.0332 0.0715 0.0640 0.0389 0.0749
4 250 0.0552 0.0379 0.0670 0.0557 0.0436 0.0707 0.0541 0.0330 0.0634 0.0547 0.0380 0.0666
300 0.0464 0.0377 0.0598 0.0473 0.0431 0.0640 0.0451 0.0329 0.0559 0.0460 0.0376 0.0596
350 0.0378 0.0373 0.0539 0.0386 0.0427 0.0576 0.0368 0.0328 0.0492 0.0375 0.0375 0.0530
5 400 0.0356 0.0371 0.0514 0.0362 0.0415 0.0551 0.0342 0.0327 0.0475 0.0348 0.0366 0.0505
450 0.0322 0.0361 0.0484 0.0328 0.0404 0.0520 0.0304 0.0320 0.0441 0.0312 0.0359 0.0476
500 0.0294 0.0349 0.0456 0.0300 0.0394 0.0495 0.0276 0.0311 0.0416 0.0284 0.0351 0.0453
600 0.0257 0.0343 0.0429 0.0264 0.0382 0.0464 0.0237 0.0309 0.0389 0.0246 0.0344 0.0422
6 750 0.0216 0.0326 0.0391 0.0223 0.0364 0.0427 0.0197 0.0297 0.0355 0.0203 0.0332 0.0389

Table 1.11-8. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 Ft (305 m) at 90 °C (a) Three Single Conductors
7 Wire Size, In Magnetic Duct In Non-Magnetic Duct
AWG or 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
kcmil
8 R X Z R X Z R X Z R X Z

6 0.847 0.053 0.849 — — — 0.847 0.042 0.848 — — —


4 0.532 0.050 0.534 0.532 0.068 0.536 0.532 0.040 0.534 0.532 0.054 0.535
9 2 0.335 0.046 0.338 0.335 0.063 0.341 0.335 0.037 0.337 0.335 0.050 0.339
1 0.265 0.048 0.269 0.265 0.059 0.271 0.265 0.035 0.267 0.265 0.047 0.269
1/0 0.210 0.043 0.214 0.210 0.056 0.217 0.210 0.034 0.213 0.210 0.045 0.215
10 2/0
3/0
0.167
0.133
0.041
0.040
0.172
0.139
0.167
0.132
0.055
0.053
0.176
0.142
0.167
0.133
0.033
0.037
0.170
0.137
0.167
0.132
0.044
0.042
0.173
0.139
4/0 0.106 0.039 0.113 0.105 0.051 0.117 0.105 0.031 0.109 0.105 0.041 0.113

11 250
300
0.0896
0.0750
0.0384
0.0375
0.0975
0.0839
0.0892
0.0746
0.0495
0.0479
0.102
0.0887
0.0894
0.0746
0.0307
0.0300
0.0945
0.0804
0.0891
0.0744
0.0396
0.0383
0.0975
0.0837
350 0.0644 0.0369 0.0742 0.0640 0.0468 0.0793 0.0640 0.0245 0.0705 0.0638 0.0374 0.0740
400 0.0568 0.0364 0.0675 0.0563 0.0459 0.0726 0.0563 0.0291 0.0634 0.0560 0.0367 0.0700
12 500 0.0459 0.0355 0.0580 0.0453 0.0444 0.0634 0.0453 0.0284 0.0535 0.0450 0.0355 0.0573
600 0.0388 0.0359 0.0529 0.0381 0.0431 0.0575 0.0381 0.0287 0.0477 0.0377 0.0345 0.0511
700 0.0338 0.0350 0.0487 0.0332 0.0423 0.0538 0.0330 0.0280 0.0433 0.0326 0.0338 0.0470
13 750 0.0318 0.0341 0.0466 0.0310 0.0419 0.0521 0.0309 0.0273 0.0412 0.0304 0.0335 0.0452
1000 0.0252 0.0341 0.0424 0.0243 0.0414 0.0480 0.0239 0.0273 0.0363 0.0234 0.0331 0.0405

14 Table 1.11-9. 60 Hz Impedance Data for Three-Phase Aluminum Cable Circuits, in Approximate Ohms per 1000 ft (30 m) at 90 °C (b) Three Conductor Cable
Wire Size, In Magnetic Duct and Steel Interlocked Armor In Non-Magnetic Duct and Aluminum Interlocked Armor
AWG or 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV 600 V and 5 kV Non-Shielded 5 kV Shielded and 15 kV
15 kcmil
R X Z R X Z R X Z R X Z

6 0.847 0.053 0.849 — — — 0.847 0.042 0.848 — — —



16 4
2
0.532
0.335
0.050
0.046
0.534
0.338

0.335 0.056

0.340
0.532
0.335
0.040
0.037
0.534
0.337

0.335

0.045

0.338
1 0.265 0.048 0.269 0.265 0.053 0.270 0.265 0.035 0.267 0.265 0.042 0.268
1/0 0.210 0.043 0.214 0.210 0.050 0.216 0.210 0.034 0.213 0.210 0.040 0.214
17 2/0 0.167 0.041 0.172 0.167 0.049 0.174 0.167 0.033 0.170 0.167 0.039 0.171
3/0 0.133 0.040 0.139 0.133 0.048 0.141 0.133 0.037 0.137 0.132 0.038 0.138
4/0 0.106 0.039 0.113 0.105 0.045 0.114 0.105 0.031 0.109 0.105 0.036 0.111
18 250 0.0896 0.0384 0.0975 0.0895 0.0436 0.100 0.0894 0.0307 0.0945 0.0893 0.0349 0.0959
300 0.0750 0.0375 0.0839 0.0748 0.0424 0.0860 0.0746 0.0300 0.0804 0.0745 0.0340 0.0819
350 0.0644 0.0369 0.0742 0.0643 0.0418 0.0767 0.0640 0.0245 0.0705 0.0640 0.0334 0.0722
19 400
500
0.0568
0.0459
0.0364
0.0355
0.0675
0.0580
0.0564
0.0457
0.0411 0.0700 0.0563 0.0291 0.0634 0.0561 0.0329 0.0650
0.0399 0.0607 0.0453 0.0284 0.0535 0.0452 0.0319 0.0553
600 0.0388 0.0359 0.0529 0.0386 0.0390 0.0549 0.0381 0.0287 0.0477 0.0380 0.0312 0.0492
700 0.0338 0.0350 0.0487 0.0335 0.0381 0.0507 0.0330 0.0280 0.0433 0.0328 0.0305 0.0448
20 750 0.0318 0.0341 0.0466 0.0315 0.0379 0.0493 0.0309 0.0273 0.0412 0.0307 0.0303 0.0431
1000 0.0252 0.0341 0.0424 0.0248 0.0368 0.0444 0.0239 0.0273 0.0363 0.0237 0.0294 0.0378

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.11-11
August 2017 Reference Data
Sheet 01 149

Current Carrying Capacities of Copper and Aluminum and Copper-Clad Aluminum Conductors
From National Electrical Code (NEC), 2014 Edition (NFPA 70-2014)
i
Table 1.11-10. Allowable Ampacities of Insulated Conductors Rated 0–2000 V, 60 ° to 90 °C (140° to 194 °F).
Not more than three current-carrying conductors in raceway, cable or earth (directly buried), based on ambient temperature of 30 °C (86 °F). ii
Size Temperature Rating of Conductor (See Table 310.15 [B][16]) Size
AWG or 60 °C (140 °F) 75 °C (167 °F) 90 °C (194 °F) 60 °C (140 °F) 75 °C (167 °F) 90 °C (194 °F) AWG or
kcmil Types Types kcmil 1
TW, UF RHW, THHW, TBS, SA, SIS, FEP, TW, UF RHW, THHW, TBS, SA, SIS,
THW, THWN,
XHHW, USE, ZW
FEPB, MI,
RHH, RHW-2,
THW, THWN,
XHHW, USE
THHN, THHW,
THW-2, THWN-2,
2
THHN, THHW, RHH, RHW-2,
THW-2, THWN-2, USE-2, XHH,
USE-2, XHH, XHHW, XHHW-2, 3
XHHW, XHHW-2, ZW-2
ZW-2
Copper Aluminum or Copper-Clad Aluminum 4
18 — — 14 — — — —
16 — — 18 — — — —
14 1 15 20 25 — — — — 5
12 1 20 25 30 20 20 25 12 1
10 1 30 35 40 25 30 35 10 1
8 40 50 55 30 40 45 8 6
6 55 65 75 40 50 60 6
4 70 85 95 55 65 75 4
3 85 100 110 65 75 85 3 7
2 95 115 130 75 90 100 2
1 110 130 150 85 100 115 1
1/0 125 150 170 100 120 135 1/0 8
2/0 145 175 195 115 135 150 2/0
3/0 165 200 225 130 155 175 3/0
4/0 195 230 260 150 180 205 4/0 9
250 215 255 290 170 205 230 250
300 240 285 320 190 230 255 300
350 260 310 350 210 250 280 350
10
400 280 335 380 225 270 305 400
500 320 380 430 260 310 350 500
600 355 420 475 285 340 385 600
700 385 460 520 310 375 420 700
11
750 400 475 535 320 385 435 750
800 410 490 555 330 395 450 800
900 435 520 585 355 425 480 900
12
1000 455 545 615 375 445 500 1000
1250 495 590 665 405 485 545 1250
1500 520 625 705 435 520 585 1500 13
1750 545 650 735 455 545 615 1750
2000 560 665 750 470 560 630 2000
1 See NEC Section 240.4 (D). 14
Note: For complete details of using Table 1.11-10, see NEC Article 310 in its entirety.

Table 1.11-11. Correction Factors From NFPA 70-2014 (See Table 310.15 [B][2][a]) 15
Ambient For ambient temperatures other than 30 °C (86 °F), multiply the allowable ampacities shown Ambient
Temperature °C above by the appropriate factor shown below. Temperature °F
16
21–25 1.08 1.05 1.04 1.08 1.05 1.04 070–77
26–30 1.00 1.00 1.00 1.00 1.00 1.00 078–86
31–35 0.91 0.94 0.96 0.91 0.94 0.96 087–95 17
36–40 0.82 0.88 0.91 0.82 0.88 0.91 096–104
41–45 0.71 0.82 0.87 0.71 0.82 0.87 105–113
46–50 0.58 0.75 0.82 0.58 0.75 0.82 114–122
18
51–55 0.41 0.67 0.76 0.41 0.67 0.76 123–131
56–60 — 0.58 0.71 — 0.58 0.71 132–140
61–70 — 0.33 0.58 — 0.33 0.58 141–158
71–80 — — 0.41 — — 0.41 159–176
19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.11-12 Power Distribution Systems
Reference Data August 2017
Sheet 01 150

i Ampacities for Conductors (B) Tables. Ampacities for conductors (3) Adjustment Factors.
rated 0–2000 V shall be as specified
Rated 0–2000 V (Excerpted in the Allowable Ampacity (a) More Than Three Current-
Carrying Conductors in a Raceway
ii from NFPA 70-2014, 310.15) Table 310.15(B)(16) through
or Cable. Where the number of
Table 310.15(B)(19), and
Note: Fine Print Note (FPN) was changed Ampacity Table 310.15(B)(20) and current-carrying conductors in a
to Informational Note in the 2011 NEC. Table 310.15(B)(21) as modified raceway or cable exceeds three, or
1 (A) General.
by 310.15(B)(1) through (B)(7). where single conductors or multi-
conductor cables are installed
(1) Tables or Engineering Supervision. Note: Table 310.15(B)(16) through without maintaining spacing for
2 Ampacities for conductors shall Table 310.15(B)(19) are application tables
for use in determining conductor sizes
a continuous length longer than
be permitted to be determined by 24.00-inch (600 mm) and are not
on loads calculated in accordance with
tables as provided in 310.15(B) or installed in raceways, the allowable
Article 220. Allowable ampacities result
3 under engineering supervision, from consideration of one or more of ampacity of each conductor shall be
as provided in 310.15(C). the following: reduced as shown in Table
310.15(B)(3)(a). Each current-carry-
Note: Informational Note No. 1: Ampacities
4 provided by this section do not take voltage (1) Temperature compatibility with ing conductor of a paralleled set of
drop into consideration. See 210.19(A), connected equipment, especially conductors shall be counted as a
Informational Note No. 4, for branch circuits the connection points. current-carrying conductor.
5 and 215.2(A), Informational No. 2, for feeders. Note: Informational Note No. 1: See Annex
(2) Coordination with circuit and
Note: Informational Note No. 2: For the system overcurrent protection. B, Table B.310.15(B)(2)(11), for adjustment
allowable ampacities of Type MTW wire, factors for more than three current-carrying
6 see Table 13.5.1 in NFPA 79-2007, Electrical (3) Compliance with the requirements conductors in a raceway or cable with
Standard for Industrial Machinery. of product listings or certifications. load diversity.
See 110.3(B).
7 (2) Selection of Ampacity. Where Note: Informational Note No. 2: See 366.23(A)
more than one ampacity applies (4) Preservation of the safety benefits for adjustment factors for conductors in
for a given circuit length, the of established industry practices sheet metal auxiliary gutters and 376.22(B)
8 lowest value shall be used. and standardized procedures. for adjustment factors for conductors in
metal wireways.
Exception: Where two different
ampacities apply to adjacent (1) General. For explanation of type let-
(1) Where conductors are installed in
9 portions of a circuit, the higher ters used in tables and for
recognized sizes of conductors for cable trays, the provisions of
ampacity shall be permitted to 392.80 shall apply.
be used beyond the point of the various conductor insulations,
10 transition, a distance equal to see Table 310.104(A) and Table (2) Adjustment factors shall not apply
10 ft (3.0 m) or 10 percent of the 310.104(B). For installation to conductors in raceways having
circuit length figured at the higher requirements, see 310.1 through a length not exceeding 24.00-inch
11 ampacity, whichever is less. 310.15(A)(3) and the various (600 mm).
articles of this Code. For flexible
Note: See 110.14(C) for conductor cords, see Table 400.4, Table (3) Adjustment factors shall not apply
temperature limitations due to
12 termination provisions.
400.5(A)(1) and Table 400.5(A)(2). to underground conductors enter-
ing or leaving an outdoor trench
if those conductors have physical
13 protection in the form of rigid
metal conduit, intermediate metal
conduit, rigid polyvinyl chloride
14 conduit (PVC), or reinforced
thermosetting resin conduit (RTRC)
having a length not exceeding
15 10 ft (3.05 m), and if the number of
conductors does not exceed four.

16

17

18

19

20

21

For more information, visit: www.eaton.com/consultants CA08104001E


Power Distribution Systems 1.11-13
August 2017 Reference Data
Sheet 01 151

(4) Adjustment factors shall not Where conductors or cables are (5) Neutral Conductor.
apply to Type AC cable or to installed in circular raceways exposed i
Type MC cable under the following to direct sunlight on or above rooftops, (a) A neutral conductor that carries
conditions: the adjustments shown in Table 1.11-12 only the unbalanced current from
shall be added to the outdoor other conductors of the same ii
a. The cables do not have an overall temperature to determine the circuit shall not be required to
outer jacket. applicable ambient temperature be counted when applying the
b. Each cable has not more than three for application of the correction provisions of 310.15(B)(3)(a). 1
current-carrying conductors. factors in Table 310.15(B)(2)(a) or (b) In a three-wire circuit consisting
Table 310.15(B)(2)(b). of two phase conductors and the
c. The conductors are 12 AWG copper. neutral conductor of a four-wire, 2
Note: Informational Note: One source for
d. Not more than 20 current-carrying the average ambient temperatures in various three-phase, wye-connected
locations is the ASHRAE Handbook system, a common conductor
conductors are installed without
—Fundamentals. carries approximately the same 3
maintaining spacing, are stacked,
or are supported on”bridle rings.” current as the line-to-neutral load
Table 1.11-12. NEC (2014) Table 310.15(B)(3)(c) currents of the other conductors
(5) An adjustment factor of 60 percent Ambient Temperature Adjustment for Circular and shall be counted when applying
4
shall be applied to Type AC cable or Raceways or Cables Exposed to Sunlight On the provisions of 310.15(B)(3)(a).
Type MC cable under the following or Above Rooftops
conditions: Distance Above Roof to Temperature
(c) On a four-wire, three-phase wye 5
Bottom of Conduit Adder ºF (ºC) circuit where the major portion of
a. The cables do not have an overall the load consists of nonlinear loads,
outer jacket. 0–0.51-inch (0–13.0 mm) 60 (33) harmonic currents are present in 6
Above 0.51-inch (13.0 mm)– 40 (22) the neutral conductor; the neutral
b. The number of current carrying 3.54-inch (90.0 mm) conductor shall therefore be con-
conductors exceeds 20.
Above 3.54-inch (90.0 mm)– 30 (17) sidered a current-carrying conductor. 7
c. The cables are stacked or bundled 11.81-inch (300.0 mm)
Above 12.00-inch (300.0 mm)– 25 (14) (6) Grounding or Bonding Conductor.
longer that 24.00-inch (600 mm)
without spacing being maintained. 36.00-inch (900.0 mm) A grounding or bonding conductor 8
shall not be counted when applying
(b) More Than One Conduit, Tube, (4) Bare or Covered Conductors. the provisions of 310.15(B)(3)(a).
or Raceway. Spacing between Where bare or covered conductors 9
conduits, tubing, or raceways are installed with insulated
shall be maintained. conductors, the temperature
(c) Circular Raceways Exposed to
rating of the bare or covered 10
conductor shall be equal to the
Sunlight on Rooftops. lowest temperature rating of the
insulated conductors for the 11
purpose of determining ampacity.

12

13

14

15

16

17

18

19

20

21

CA08104001E For more information, visit: www.eaton.com/consultants


1.11-14 Power Distribution Systems
Reference Data August 2017
Sheet 01 152

Table 1.11-13. Formulas for Determining Amperes, hp, kW and kVA


i To Direct Alternating Current
Find Current Single-Phase Two-Phase—Four-Wire 1 Three-Phase
ii Amperes (l) when hp  746
 hp  746

hp  746

hp  746

horsepower is known E  % eff E  % eff  pf 2  E  % eff  pf 3  E  % eff  pf
Amperes (l) when kW  1000 kW  1000 kW  1000 kW  1000
   
1 kilowatts is known E E  pf 2  E  pf 3  E  % pf
kVA  1000 kVA  1000 kVA  1000
Amperes (l) when —
  
kva is known E 2E 3E
2 Kilowatts IE

l  E  pf

l  E  2  pf

l  E  3  pf

1000 1000 1000 1000
kVA — IE IE2 IE 3
  
3 1000 1000 1000
Horsepower (output) I  E  % eff I  E  % eff  pf I  E  2  % eff  pf I  E  3  % eff  pf
   
746 746 746 746
4 1 For two-phase, three-wire circuits, the current in the common conductor is 2 times that in either of the two other conductors.
Note: Units of measurement and definitions for E (volts), I (amperes), and other abbreviations are given below under Common Electrical Terms.

5 Common Electrical Terms How to Compute Power Factor


Ampere (l) = unit of current or rate of flow of electricity
Watts
Determining Watts pf = ----------------------------------------------
6 Volt (E) = unit of electromotive force Volts  Amperes

Ohm (R) = unit of resistance 1. 1. From watthour meter.


Watts = rpm of disc x 60 x Kh
7 E
Ohms law: I =  (DC or 100% pf)
R
Where Kh is meter constant
Megohm = 1,000,000 ohms
printed on face or nameplate
8 Volt Amperes (VA) = unit of apparent power of meter.
= E  l (single-phase)
If metering transformers are used,
9 = El 3 above must be multiplied by the
Kilovolt Amperes (kVA) = 1000 volt-amperes transformer ratios.
10 Watt (W) = unit of true power 2. Directly from wattmeter reading.
Where:
= VA  pf
11 = 0.00134 hp Volts = line-to-line voltage as
measured by voltmeter.
Kilowatt (kW) = 1000 watts
12 Power Factor (pf) = ratio of true to apparent power Amperes = current measured in
W kW line wire (not neutral) by ammeter.
= -------- ----------
-
13 VA kVA Table 1.11-14. Temperature Conversion
Watthour (Wh) = unit of electrical work (F° to C°) C° = 5/9 (F°–32°)
= 1 watt for 1 hour (C° to F°) F° = 9/5(C°)+32°
14 = 3.413 Btu C° –15 –10 –5 0 5 10 15 20
= 2655 ft-lbs F° 5 14 23 32 41 50 59 68

15 Kilowatt-hour (kWh) = 1000 watthours


Cº 25
F° 77
30
86
35 40 45
95 104 113
50 55
122 131
60
140
C° 65 70 75 80 85 90 95 100
Horsepower (hp) = measure of time rate of doing work
F° 149 158 167 176 185 194 203 212
16 = equivalent of raising 33,000 lbs 1 ft in 1 minute
= 746 watts 1 Inch = 2.54 centimeters
17 Demand Factor = ratio of maximum demand to the total connected load
1 Kilogram = 2.20 lb
1 Square Inch = 1,273,200 circular mills
Diversity Factor = ratio of the sum of individual maximum demands of 1 Circular Mill = 0.785 square mil
18 the various subdivisions of a system to the maximum
1 Btu = 778 ft lb
demand of the whole system
= 252 calories
19 Load Factor = ratio of the average load over a designated period 1 Year = 8760 hours
of time to the peak load occurring in that period

20

21

For more information, visit: www.eaton.com/consultants CA08104001E

You might also like