BILL OF QUANTITY FOR SILO FOUNDATION

Project:- Factory Building of M/s. Gorkha Brewery


Location:- Mukundapur, Nawalparasi
Rate
S.No. Description Quantity Unit Amount
In Figures In Words
1. Earthwork
1.1 Earthwork in Excavation
E/W in excavation inclusive of shoring and dumping, surplus waste along
with trenching, dewatering all necessary as per design, specification &
instruction of Consultant, all complete including the soil dumping outside the
site by transportation. 139.00 Cu.m.
Earthwork in Back Filling Work
E/W in back filling work in necessary proper compaction with water sprinkle
on layer by layer for compaction as per design, specification & instruction of
Consultant, all complete. 37.00 Cu.m.
2. Gravel Sand (60:40) Filling Works
Supplying and filling gravel sand (60:40) filling work with proper compaction
in layer by layer as per design, specification & instruction of Consultant, all
complete. 40.00 Cu.m.
3. Brick Soling Work
One layer flat chimney made brick soling to the line and level as per drawing,
specification and instruction of the Consultant, all complete. 90.00 Sq.m.
4. Concreting for PCC Work
P.C.C. in foundation base or floor surface with cement, sand, stone ballast

38mm & down including mixing, laying finishing to approved line and level all

complete as per drawing, specification and instruction of the Consultant.


4.1 P. C. C. (1 : 3 : 6) on foundation base all complete. 7.00 Cu.m.
5. P. C. C. for R. C. C. Work
Plain cement concrete for R. C. C. shearwall, column, beam, slabs, lintels, wall
footing and all types of R. C. C. works with cement, sand and stone ballast
20mm & down including mixing, laying, finishing & curing as per drawing,
specification and instruction of the Consultant.
5.1 P. C. C. M20 Grade Concreting 63.00 Cu.m.
6. Form Work
BILL OF QUANTITY FOR SILO FOUNDATION
Project:- Factory Building of M/s. Gorkha Brewery
Location:- Mukundapur, Nawalparasi
Rate
S.No. Description Quantity Unit Amount
In Figures In Words
Form work, centering and shuttering with standard quality water proof ply
wood for all kinds of R. C. C. works including all necessary propping,
scaffolding, staging, supporting and necessary hooks, screws clamps, nuts,
bolt, etc. all complete as per instruction of Consultant.
6.1 Normal Formwork 77.00 Sq.m.
BILL OF QUANTITY FOR SILO FOUNDATION
Project:- Factory Building of M/s. Gorkha Brewery
Location:- Mukundapur, Nawalparasi
Rate
S.No. Description Quantity Unit Amount
In Figures In Words
7. Steel Reinforcement
TMTsteel for steel reinforcement bars manufactured by Himal Iron or
equivalent including straightening, cleaning, cutting, bending with 20 SWG
annealed tying wire and fixing in position drawing, specification & instruction
of the Consultant.
7.1 HYSD Fe 500 Grade 7,407.00 Kg
8. 230mm or more thick brick work at substructure
Brick work in cement sand (1:6) mortar in substructure with 1st class chimney
made bricks in perfect line and level including wetting the dry bricks, packing
the joints and curing the work all complete as per specification & instruction of
the Consultant. 7.00 Cu.m.

9. Plaster Work (1:6)


Plaster work (1:6) cement, sand mortar (20mm thick) in accurate line and level

including wetting the surface and curing the work all complete as per drawing

specification and instruction of the Consultant. 66.00 Sq.m.

10. I. P. S. flooring Works


Providing & laying 50mm thick (1:2:4) cement, sand, stone chips-concrete and

finishing the surface with 1:1 cement sand neat finish as per drawing,

specification & instruction of the Consultant, all complete. 87.00 Sq.m.

11. Exterior Weather Coat Paints


Supplying and applying weather coat paints over plaster surface with primer
and paints to give an even and uniform shade all complete as per specification
and instruction of the Consultant. 22.00 Sq.m.

Sub Total Amount of Silo Foundation NRs. :-

VAT 13% :-

Total Amount of Silo Foundation NRs. :-


Remarks
Remarks