Conditions for Participation in the Briefing and Viewing /
Use of Information
• The participants of this briefing agree that, in future if he enters into a
contract with the HKSAR Government to design and/or construct the
Desalination Plant works, he will waive any claim or proceeding against the
HKSAR Government, the consultants or any person/party associated,
employed or retained by either of them, in relation to any information
presented in this briefing and to any difference between the nature and/or
extent of conditions encountered in the execution of any works included in
the contract and that which is disclosed or implied by this briefing.
3
Conditions for Participation in the Briefing and Viewing /
Use of Information
• The HKSAR Government reserves ownership to all intellectual property
rights to the information presented in this briefing. No such information
shall be used without the written permission of Water Supplies Department
(WSD).
• Further participation in this briefing shall represent acceptance of the above
conditions.
• Any one who view or use the information presented in this briefing shall also
be deemed to have accepted the above conditions.
4
Agenda
• Introduction
• Project Overview
• Project Risks and Constraints
• Procurement Method
• Tendering
• Questions & Answers (45 minutes)
5 5
Is
Hong Kong a Water Rationing in the 1960s
WATER-SCARCE
city?
Section 1: Introduction
6
Diversification of Water Sources
7
Section 2: Project Overview
8 8
Roles of TKO Desalination Plant
9
Operating Mode & Plant Output
10 10
Overall Scheme
Existing TKO FW
Primary Service
Reservoir
Legend:
Current
Project
Scope
• Core Technology
• Reverse Osmosis
• Phased Development
• Stage 1: 135MLD (The Project)
• Ultimate: 270MLD Total (in future)
• Both stages to be built within a 8ha site
• Stage 1 tentatively scheduled for
commissioning by end of 2021
12 12
The Site and Surroundings
Landfill
Desalination
Plant Site
Country Park
13
Environmental
Permitting
14 14
Intake & Outfall
Intake Structure
Submarine Outfall
Marine works Pipeline
authorised
under the
Foreshore and
Sea-bed Outfall
(Reclamations) Diffusers
Ordinance
15
Mandatory Requirements
• Boron ≤ 1.0 mg/L
Fresh Water Quality • Bromide ≤ 0.2 mg/L
• TDS < 250mg/L
On-site Generation of • Chlor-alkali process
Chorine Gas for • High-purity grade salt as feedstock
Final Disinfection
Operation &
• Through a structured secondment
Maintenance Skill
programme
Transfer
16
Other Requirements
Use of • Solar
Renewable
Energy • Landfill Gas
17
Section 3: Risks and Constraints
18 18
Seawater Quality
Seawater quality parameters for which the plant must be able to operate to meet
full performance requirements
Parameter Value
Temperature 15 to 30 0C
Total Suspended Solids ≤ 30 mg/L
Total Dissolved Solids ≤ 38,740 mg/L
Bromide ≤ 80 mg/L
Boron ≤ 5.3 mg/L
Red tide events could occur occasionally; plant output may be relaxed during such periods
19
Site Apportionment and Hand Over
Access Road
Stage 1 site
(Handover
within 1st year)
Stage 2 site
(Handover
within 2nd year )
Stage 1 site
(Handover upon
commencement)
20
Construction Access
23 23
Other Risks and Constraints
24 24
Slope mitigation measures
to follow detailed design Other Requirements
provided by the Employer
• Flexible barrier
• Rock dowels • Natural terrain hazards mitigation measures
• Boulder removal approved by GEO
• Building height limitation per Environmental
Permit
• 90-day chemical storage for stage 1 plant
• Sizing of chlorine contact tank(s) per WSD
requirements
• BIM with asset management
25 25
Section 4: Procurement Method
26 26
Proposed Project
Delivery Model
27 27
Proposed Commercial Model
Contract Fixed
Payments Operating Costs
Operations Variable
Phase Operating Costs
Asset
Replacement
28 28
Proposed Hybrid Operations Payment Model
General ($/month)
Fixed Operating Charge
Operations Payment
Readiness ($/month)
Periodic Asset
$ per Asset Item
Replacement Charge
29 29
Section 5: Tendering
30
Tender Process and Tentative Timeline
Pre- Contract
Shortlist Tendering Evaluation
qualification Award
Stage 1 Stage 2
(Screening) (Marking Scheme)
32 32
Screening Criterion 1
(tentative, subject to change)
33 33
Screening Criterion 2
(tentative, subject to change)
34 34
Screening Criterion 3
(tentative, subject to change)
building contract
• Awarded contract sum ≥ HK$500 million
• Completed within the past 10 years from PQ closing date
• No. of past contracts to be discounted
• % financial participation in the referenced contract,
if undertaken as part of a JV
• % financial participation,
if applicant is part of a JV proposed for TKO
35 35
Common Pitfalls
36
Tender Evaluation
Fee Technical
Weighting Weighting • Two-envelope system
• Technical Proposal will be evaluated
and finalised, prior to reviewing the
Fee Proposal
50% 50%
to to • Weighting of Proposals, to be
60% 40% determined
37 37
Typical Tender Marking Scheme
39