You are on page 1of 9

Engineering on the precipice: mountain road

rehabilitation in the Philippines


J. Hart, G. Hearn & C. Chant
Scott Wilson Kirkpatrick & Co Ltd, Scott House, Basing View, Basingstoke, Hants, RG21 4JG, UK

Abstract Abra River and Haphap Faults. There is clear evi-


dence of the recent, disturbing forces of earthquake
opography and ground conditions for mountain activity which, according to the Philippine Institute of

T road engineering within the Central Cordillera of


Luzon in the northern Philippines (Fig. 1) are
some of the most extreme and unstable in the
world. The Central Cordillera is a range of mountains that
has been emplaced and shaped by rapid uplift, valley
Volcanology and Seismology (PHIVOLCS), was caused
by movement principally along the Philippine and
Digdig fault lines. Numerous smaller splay faults were
mapped during the project (see below) trending both

incision, slope erosion, and often massive landslides


(Fig. 2). The Halsema Highway is a 180 km-long,
tortuous road that traverses this mountain range and is a
vital economic and strategic lifeline to the intensively
farmed agricultural mountainous regions of northern
Luzon. In 1990 the road suffered extensive loss and
damage as a result of a Richter magnitude 7.8 earth-
quake followed by a succession of typhoons and intense
rainstorms. Given the strategic and socio-economic
importance of the highway, the Philippines Government
sought international aid to rehabilitate this vital link fol-
lowing the devastation, and feasibility and design studies
commenced in late 1996. This paper presents some
of the geotechnical investigation carried out for these
studies, describing the types of instability and ground
conditions affecting the road and the approach adopted
to maximize the interpretation of the ground, and
to provide geotechnical engineering options for road
rehabilitation.

Keywords: earthworks, engineering geology maps, geological


hazards, geomorphology, highways

Regional geology
The Philippine Archipelago is one of the most tec-
tonically active regions in the world, and since 1954 six
earthquakes have been recorded at greater than 7.3 on
the Richter scale. On average, five earthquakes are
recorded each day (NZNSEE Reconnaissance Team
1991). Regular and often very intense seismicity in the
region is principally related to subduction-zone tectonic
activity surrounding the Philippine Islands (Fig. 3).
Lying at the convergence of the Philippine Sea Plate
to the east and the Eurasian Plate to the west the
Philippines are situated above two subducting plate
margins. Subduction occurs at rates of between 10 mm
and 70 mm per year, which is accommodated on land by
predominantly sinistral, strike–slip deformation along
major fault zones associated with the Philippine Fault
(Fig. 3). Within the project area, three major splays
cross the road from the main fault, including the Digdig, Fig. 1. The location of the Halsema Highway, Philippines
Quarterly Journal of Engineering Geology and Hydrogeology, 35, 223–231 1470-9236/02 $15.00  2002 Geological Society of London
224 HART ET AL.

volcanic breccias and coarse-grained conglomerates. In


addition to complex geology, the ground profile is
further complicated by subtropical weathering, with
saprolite thickness often in excess of 40 m.

The Halsema Highway


There are two main tourist destinations in the Central
Cordillera of north Luzon. For cool climate seekers
Baguio (Fig. 1) is regarded as the summer capital of the
Philippines. It is the gateway to the Cordillera and, as
such, has become the principal marketing point for the
vegetable growing hinterland further north. The impres-
sive 2000 years old Banaue rice terraces constitute the
second focal point. Since the end of the 19th century the
road between these two locations has been progressively
upgraded from a horse and cart track to a motorable
road, with two-lane concrete carriageway now con-
structed for about 77 km. This progressive upgrade
has placed increasing demands on the neighbouring
landscape as slopes have been cut, waste rock and soil
have been dumped and natural drainage patterns, them-
selves probably only meta-stable, have been significantly
disturbed.
The highway follows a contour alignment and as a
result is very tortuous. The current motorable speed is a
maximum of 30 km/h but the limited records available
Fig. 2. Massive landslide and erosion scars along the Halsema show a high number of deaths and critical injuries
Highway occurring along the highway. For example, 23 deaths
were reported between 1995 and 1997 alone. Many of
NW–SE and NE–SW (Fig. 4). These are associated with these were due to vehicles being driven over the road
extensive zones of shearing, fracturing and fault gouge edge onto the precipitous slopes below. There are seven-
(clayey gouge up to 2 m thick was observed in some teen bridges along the highway, including Bailey-type
landslide scars and cut slopes). Consequently, both bridges constructed across eroded cols on the ridgeline.
active and relict, small and large-scale discontinuities The road formation itself is supported extensively on
control the Cordillera landscape and traverse the road retaining walls utilizing masonry and reinforced con-
alignment. crete grid designs that, as far as the authors are aware,
The area is dominated by relatively young tectonic are unique to the mountain areas of the Philippines.
arc volcanic rocks interbedded with sedimentary for- The combined effect on the Halsema Highway of the
mations, both of which have been intruded during 1990 earthquake and subsequent typhoons was devas-
numerous magmatic phases by plutonic assemblages tating, and the road has been in decay ever since, under
(Fig. 4). The oldest rocks exposed in the area are the continuing onslaught of 3.5 m of typhoon rainfall
Cretaceous to early Tertiary in age and comprise basal- each year. The Philippines Department of Public Works
tic and andesitic volcanic rocks, which were meta- and Highways (DPWH) has undertaken selective
morphosed by later tectonic uplift and intrusion improvements, but sections of the road are closed for
(Geomatrix-Certeza 1996). These are overlain uncon- significant periods each year (e.g. for up to 6 weeks in
formably by tuffs, volcaniclastics and younger, relatively 1997), and the hazards posed by falling debris from
massive andesitic lava flows together with thick lime- above and failing carriageway from below (Fig. 5)
stone sequences laid down during periods of volcanic combine to make this a particularly treacherous
quiescence. This sequence was subsequently intruded mountain highway. However, the alternatives are not
during the Oligocene and Miocene, by a suite of plutonic good. Early pioneers planned a route close to and along
and hypabyssal intermediate and occasionally basic the major river valley floors to avoid the steep and
rocks including diorite, granodiorite, monzodiorite, dac- unstable terrain above, but their attempts were futile
ite and gabbro (Geomatrix-Certeza 1996). As the area given the flooding and shifting channel patterns of the
was uplifted, explosive volcanic activity produced large river systems found there. The nearest alternative route
volumes of volcaniclastic deposits, including tuffs, between Baguio and Bontoc lies some 30 to 40 km to the
MOUNTAIN ROAD REHABILITATION 225

Fig. 3. Tectonic setting and active fault zone

west, but this route would not serve the intensely farmed and spoiling of waste material, processes that have also
agricultural areas currently accessed via the Halsema tended to contribute to slope degradation.
Highway. Major road realignment would therefore be
unacceptable from the local socio-economic point of
view. Road rehabilitation
In addition to the inherent natural instability within
the road corridor, changing land use patterns, namely Feasibility and design studies for road rehabilitation
from forest cover to intensive farming, have affected commenced in December 1996 and were completed in
drainage patterns and have led to an increase in erosion the summer of 1998. Given the sheer scale of existing
potential. Past road improvement schemes and on-going road damage, the heterogeneity and complexity of
roadside developments have resulted in slope excavation ground conditions, and the dynamism of the landscape,
226 HART ET AL.

Fig. 4. General geology of the Halsema Highway

a pragmatic and low cost geotechnical design approach feasible if rehabilitation within the existing corridor were
was developed, giving full consideration to engineering impracticable or too costly. Usually, one of the first
geology and geomorphology. Field mapping therefore considerations in mountain road construction is the
became a critical tool that provided data upon which identification of a stable rock out-crop in which support
engineering feasibility and design decisions were made. structures can be founded or an excavation can be made
Studies commenced with a rapid reconnaissance survey to create a road bench. In the case of the Halsema
made by a team of highway engineers, geotechnical Highway, neither ‘stable’ nor ‘rock foundation’ could be
engineers, drainage engineers and geologists. Their easily visualized during this preliminary assessment, and
brief was to assess the options available for on-line road this was proven correct during later ground investi-
reconstruction, and whether alternative routes were gations (see below). Nevertheless, it was concluded that
MOUNTAIN ROAD REHABILITATION 227

In the critical areas, road access had been com-


promised by failures from below, leading to loss of
support for the concrete carriageway. In the most
extreme of these, erosion and instability had created
20 m deep voids beneath the carriageway leaving as
much as half the carriageway undercut for several
metres. The options for reinstatement were few. The
simplest was to shift the road into the hillside, thus
creating a bench wide enough to support the road. This
option, however, further oversteepens and destabilizes
the slopes above, and does not necessarily prevent the
instability below from progressing back to the edge of
the realigned road. The alternative was to reconstruct
the road edge on retaining wall. This option was least
tenable where the depth of the void beneath the road
was greatest. As wall heights increase, so too do bearing
pressures, and foundation investigations revealed that
ground conditions were poor and generally did not
increase significantly within surface layers. Calculated
bearing pressures and sliding forces were such that
foundation depths had to be scheduled several metres
beneath existing ground in some cases. The advantages
offered by cantilevered slabs and flying buttresses
(reinforced concrete carriageway decks supported on
piers) were examined at individual sites, but they are
both liable to damage if a significant rock fall hazard
remains on the slopes above the road. They are also
reliant on the remaining bench beneath the carriageway
Fig. 5. Typical section of undermined road along the Halsema for partial support. Nevertheless, at a few selected
Highway (case study 2) locations cantilever slabs were adopted in the design as
appropriate.
a road formation could be satisfactorily reinstated along Trial pitting and drilling investigations were under-
the majority of the alignment, leaving short sections taken in advance of and during detailed design. Trial
with a moderate to high degree of residual risk pits proved useful and cost effective in defining founding
from failure. The relevant authorities were advised conditions for retaining walls and in assessing the
of this accordingly. Engineering alternatives, including
stability and bearing capacity of soil and rock beneath
re-routing and tunnelling, were considered too costly,
existing wall foundations. Throughout the trial pitting
impractical and unrealistic given that similar steep and
investigations, an experienced engineering geologist was
unstable terrain would be encountered elsewhere, and
assigned full time to log 3-dimensionally the trial pit
considerable effort had already been made to keep the
existing corridor open. exposures and to ensure that adequate penetration was
A regional geological map, highlighting the principal achieved. Both machine and hand-dug trial pits were
lithologies and discontinuities, and supplemented with carried out to optimize progress. Rotary core drilling
previous geological information gained from a pre- was used in bridge foundation investigation, stability
feasibility geohazard study (Geomatrix-Certeza 1996), assessment at sites of suspected major slope movement,
was completed at an early stage of the project (Fig. 4). and to identify depths to rock head beneath ground level
The results of the mapping, combined with an inventory when examining the feasibility for road edge retaining
of road and slope instability, indicated that the fractured walls. However, drilling through extremely disturbed
metavolcanic rocks, particularly those located close to and fractured material and in remote locations proved
intrusive and faulted boundaries and affected by hydro- difficult both physically, leading to low recovery rates,
thermal activity in the past, were intimately linked with and logistically. Careful interpretation of the samples
the zones of major slope instability along the road. A was required and in many cases the findings were
programme of aerial photograph interpretation, geologi- inconclusive.
cal and geomorphological mapping, sub-surface investi- Two case studies are described below to illustrate the
gation, and slope analysis was undertaken at critical problems encountered and the approach adopted for
sections of the road. design of road reinstatement and slope remedial works.
228 HART ET AL.

Fig. 6. Combined field mapping for site appraisal at km 314

Case study 1 diorites at the site. Two dominant joint sets, dipping at
45o to 50o controlled plane failure surfaces forming the
Figure 6 illustrates the combined mapping approach slopes close to the ridge top. In addition, major gullies
adopted at a location (shown in Fig. 4) where an appeared to be following similar planes of weakness
unstable hillside above the road, and perennial seepage along the flanks of the failing mass. Three observations
at road level, were responsible for the frequent blockage were critical to the interpretation of ground conditions
(weekly during the wet season) of the carriageway by at this location. First, there were no signs of movement
debris. The geomorphology of the slopes above the road at or beneath road level, implying that failure was
was indicative of deep-seated structure-controlled confined to the slopes above the road. Second, there was
ground movement. Engineering geological mapping juxtaposition of slightly weathered and even fresh rock
highlighted the presence of sheared, variably weathered, with fractured, sheared and highly weathered material in
weak and highly fractured meta-andesites and micro- several locations. Third, there were outcrops of clayey
MOUNTAIN ROAD REHABILITATION 229

Fig. 7. Cross section A–A and detailed design at km 314 (case study 1)

fault gouge in at least two of the main gullies. Given been removed by these processes, and the road bench
these observations, together with the presence of has been realigned by the DPWH into the hillside to
stronger, less weathered rock at road level, the hillside compensate. In some locations the mountainside has
above the road was interpreted as part of a shear zone. regressed back by up to an estimated 50 m since 1990.
Stereographic analyses of discontinuity data indicated Most of this regression took place during and shortly
that movement was kinematically feasible along the line after the earthquake, but progressive erosion has also
of intersection of the two dominant joint sets, which taken place since then. Continuous realignment of the
dipped out of the slope towards the road at about 30o. road into the hillside has deepened and steepened the
Gradual movement towards the road was postulated cuts and natural hillsides above the road, leading to
along multiple failure surfaces defined both by shear slope failures and potentially unstable slope conditions
planes and by the intersection of the two joint sets. in many places. Sections of road over culverts have
Stability analysis assuming failure along a plane inclined failed due to washouts and rapid downcutting on slopes
at 30o (Fig. 7) was used to demonstrate the positive and in stream channels beneath the road, and the
effects on the calculated factor of safety of cutting back disposal of large quantities of spoil material has led to
the slope above the road to a shallower angle. In further disturbance and erosion. In one particular area,
addition, ancillary works scheduled at this location the outside edge of the road bench was observed to have
included the installation of horizontal subsurface drains regressed back by approximately 6 m during the
towards the slope toe to reduce groundwater levels in 18 month feasibility study and design period (Fig. 5).
that area, breast walling and the extensive use of scour Ironically, immediately to the south of this narrowing
protection works using masonry cascades and bio- section of road bench, the carriageway remains relatively
engineering (Chant et al. 1999), to reduce the impact of intact (though severely cracked) across a massive relict
surface erosion and debris transportation. The overall landslide (Fig. 8). The potential for reactivation of this
improvement in factor of safety was calculated to be failure, and thus the stability of the 250 m of road
approximately 20%. located on it, were also of primary concern. Field
mapping identified active tension cracking and localized
Case study 2 slumping above the road. In addition, severe erosion
and localized slumping below the road have led to the
Figure 8 illustrates the combined mapping approach and progressive loss of bench support at the northern
the use of subsurface investigation at the site shown in flank of the relict landslide (Fig. 5). The patterns of
Figure 5, where the most distressed and unstable section erosion, slope failure and road distress suggested that
of the alignment was encountered. For approximately the current movements are relatively shallow and related
2 km, long sections of the original road bench have been to erosional unloading rather than deep-seated, large-
lost due to landsliding and erosion. Whole spurs have scale movement of the landslide mass. Mapping of the
230 HART ET AL.

Fig. 8. Combined field mapping and ground investigation for site appraisal at km 282 (case study 2)

Fig. 9. Cross section A–A and detailed design at km 282 (case study 2)

existing scars and cut slope surfaces, combined with metavolcanic rocks (Fig. 9). However, localized out-
selective subsurface drilling, confirmed the presence of crops of relatively stable rock were encountered on
25 to 30 m of disturbed and extremely weak soil and either side of this mass. The design involved realignment
rock, interpreted as a transported mass of hydrother- of the road into the hillside between these two outcrops,
mally altered and moderately to completely decomposed and battering of steeper sections of the northern flank of
MOUNTAIN ROAD REHABILITATION 231

the landslide with all excavated material being hauled to pitting has proven extremely useful in this process, while
approved stable spoil disposal areas. While this had the drilling investigations have, with one or two exceptions,
disadvantage of removing support to the disturbed mass not contributed significantly to the interpretation.
above the road it allowed the road to be relocated away Nevertheless, while the emphasis on using engineering
from the deteriorating road margin below. Furthermore, geological mapping is vindicated by this review, the
as the required slope excavation was to be undertaken geotechnical engineering problems required to be
towards the head of the relict landslide, it was concluded resolved on the Halsema Highway remain extremely
that there would be a positive influence on the stability severe. In several locations the details of the design can
of the landslide slope as a whole. only be confirmed when excavations for deep cuttings
Elsewhere, overhanging sections of pavement, caused and foundations are opened up during construction.
by washouts and erosion below, were frequently seen to Even so, the decision-making at that time will require
coincide with the locations where fault zones, some of marginal value judgements in many instances. It is here
which contained considerable fault gouge, intersected that the value of continuity between the design and
the alignment. At these locations retaining walls, the construction activities will be of value, assisted by
foundations for which were investigated with trial pits, knowledge of the dynamism of each location over the
were scheduled both above the road to support steep soil 5 year time interval. Engineering on the precipice has
cut slopes, and below the road over failure embayments certainly benefited from the application of engineering
to reinstate the road bench. geology, but the real value of the mapping applications
will not be finally gauged until construction is well
underway and the exposed ground conditions and geo-
Construction morphology of the site become clearer during the forth-
coming typhoon seasons. In this respect the impact of
The 180 km long road was divided into three sub- Typhoon Feria, that struck Baguio on 4 July 2001 and
sections and the construction contract for the first 85 km deposited in excess of 1200 mm in 36 hours, will allow
between Baguio and Mt Data was awarded in June the observations, predictions and recommendations of
2001. This section is the most critical from a geotechni- the engineering geological design to be fully put to the
cal point of view, as it is here that the majority of 1990 test.
earthquake damage took place. Fifty percent of the
calculated reinstatement and road improvement cost is Acknowledgements. The authors would like to thank the
designated for bench reinstatement, slope stabilization, Department of Public Works and Highways, Government of
slope protection, and drainage. At the time of writing, the Republic of the Philippines for permission to publish this
construction works had just commenced. Initial reports paper. The lead consultant for feasibility and design studies
from the construction site confirm the value of the trial was BCEOM of France.
pit information, particularly in areas where heavy veg-
etation now conceals ground conditions of concern at References
the time of the design. The construction supervision
programme allows for further geotechnical assessment C, C., E, S., H, G.J. & I, H. 1999.
and advice during implementation of the works, and it is Bio-engineering as an aid to slope protection and erosion
the authors’ intention to publish findings and outcomes control along the Halsema Highway, Philippines. Proceed-
ings of the 1st Asia-Pacific Conference and Exhibition on
at a later date.
Ground and Water Bioengineering for Erosion Control
and Slope Stabilization, Philippines.
G-C 1996. Baguio-Bontoc-Banaue Road
Conclusions (Halsema Road), Pre-Design Investigation. IBRD-
Assisted Highway Management Projects. Department of
The use of engineering geological mapping, with an Public Works and Highways.
NZNSEE R T 1991. The Philippines
emphasis on geomorphological assessment, has allowed Earthquake of July 16, 1990. Report on Field
both the inherent instability and dynamism of the Visit. Bulletin of the New Zealand National Society for
landscape to be evaluated for design purposes. Trial Earthquake Engineering, 1, 1.

Received 9 October 2000; accepted 15 November 2001.

You might also like