Professional Documents
Culture Documents
Regional geology
The Philippine Archipelago is one of the most tec-
tonically active regions in the world, and since 1954 six
earthquakes have been recorded at greater than 7.3 on
the Richter scale. On average, five earthquakes are
recorded each day (NZNSEE Reconnaissance Team
1991). Regular and often very intense seismicity in the
region is principally related to subduction-zone tectonic
activity surrounding the Philippine Islands (Fig. 3).
Lying at the convergence of the Philippine Sea Plate
to the east and the Eurasian Plate to the west the
Philippines are situated above two subducting plate
margins. Subduction occurs at rates of between 10 mm
and 70 mm per year, which is accommodated on land by
predominantly sinistral, strike–slip deformation along
major fault zones associated with the Philippine Fault
(Fig. 3). Within the project area, three major splays
cross the road from the main fault, including the Digdig, Fig. 1. The location of the Halsema Highway, Philippines
Quarterly Journal of Engineering Geology and Hydrogeology, 35, 223–231 1470-9236/02 $15.00 2002 Geological Society of London
224 HART ET AL.
west, but this route would not serve the intensely farmed and spoiling of waste material, processes that have also
agricultural areas currently accessed via the Halsema tended to contribute to slope degradation.
Highway. Major road realignment would therefore be
unacceptable from the local socio-economic point of
view. Road rehabilitation
In addition to the inherent natural instability within
the road corridor, changing land use patterns, namely Feasibility and design studies for road rehabilitation
from forest cover to intensive farming, have affected commenced in December 1996 and were completed in
drainage patterns and have led to an increase in erosion the summer of 1998. Given the sheer scale of existing
potential. Past road improvement schemes and on-going road damage, the heterogeneity and complexity of
roadside developments have resulted in slope excavation ground conditions, and the dynamism of the landscape,
226 HART ET AL.
a pragmatic and low cost geotechnical design approach feasible if rehabilitation within the existing corridor were
was developed, giving full consideration to engineering impracticable or too costly. Usually, one of the first
geology and geomorphology. Field mapping therefore considerations in mountain road construction is the
became a critical tool that provided data upon which identification of a stable rock out-crop in which support
engineering feasibility and design decisions were made. structures can be founded or an excavation can be made
Studies commenced with a rapid reconnaissance survey to create a road bench. In the case of the Halsema
made by a team of highway engineers, geotechnical Highway, neither ‘stable’ nor ‘rock foundation’ could be
engineers, drainage engineers and geologists. Their easily visualized during this preliminary assessment, and
brief was to assess the options available for on-line road this was proven correct during later ground investi-
reconstruction, and whether alternative routes were gations (see below). Nevertheless, it was concluded that
MOUNTAIN ROAD REHABILITATION 227
Case study 1 diorites at the site. Two dominant joint sets, dipping at
45o to 50o controlled plane failure surfaces forming the
Figure 6 illustrates the combined mapping approach slopes close to the ridge top. In addition, major gullies
adopted at a location (shown in Fig. 4) where an appeared to be following similar planes of weakness
unstable hillside above the road, and perennial seepage along the flanks of the failing mass. Three observations
at road level, were responsible for the frequent blockage were critical to the interpretation of ground conditions
(weekly during the wet season) of the carriageway by at this location. First, there were no signs of movement
debris. The geomorphology of the slopes above the road at or beneath road level, implying that failure was
was indicative of deep-seated structure-controlled confined to the slopes above the road. Second, there was
ground movement. Engineering geological mapping juxtaposition of slightly weathered and even fresh rock
highlighted the presence of sheared, variably weathered, with fractured, sheared and highly weathered material in
weak and highly fractured meta-andesites and micro- several locations. Third, there were outcrops of clayey
MOUNTAIN ROAD REHABILITATION 229
Fig. 7. Cross section A–A and detailed design at km 314 (case study 1)
fault gouge in at least two of the main gullies. Given been removed by these processes, and the road bench
these observations, together with the presence of has been realigned by the DPWH into the hillside to
stronger, less weathered rock at road level, the hillside compensate. In some locations the mountainside has
above the road was interpreted as part of a shear zone. regressed back by up to an estimated 50 m since 1990.
Stereographic analyses of discontinuity data indicated Most of this regression took place during and shortly
that movement was kinematically feasible along the line after the earthquake, but progressive erosion has also
of intersection of the two dominant joint sets, which taken place since then. Continuous realignment of the
dipped out of the slope towards the road at about 30o. road into the hillside has deepened and steepened the
Gradual movement towards the road was postulated cuts and natural hillsides above the road, leading to
along multiple failure surfaces defined both by shear slope failures and potentially unstable slope conditions
planes and by the intersection of the two joint sets. in many places. Sections of road over culverts have
Stability analysis assuming failure along a plane inclined failed due to washouts and rapid downcutting on slopes
at 30o (Fig. 7) was used to demonstrate the positive and in stream channels beneath the road, and the
effects on the calculated factor of safety of cutting back disposal of large quantities of spoil material has led to
the slope above the road to a shallower angle. In further disturbance and erosion. In one particular area,
addition, ancillary works scheduled at this location the outside edge of the road bench was observed to have
included the installation of horizontal subsurface drains regressed back by approximately 6 m during the
towards the slope toe to reduce groundwater levels in 18 month feasibility study and design period (Fig. 5).
that area, breast walling and the extensive use of scour Ironically, immediately to the south of this narrowing
protection works using masonry cascades and bio- section of road bench, the carriageway remains relatively
engineering (Chant et al. 1999), to reduce the impact of intact (though severely cracked) across a massive relict
surface erosion and debris transportation. The overall landslide (Fig. 8). The potential for reactivation of this
improvement in factor of safety was calculated to be failure, and thus the stability of the 250 m of road
approximately 20%. located on it, were also of primary concern. Field
mapping identified active tension cracking and localized
Case study 2 slumping above the road. In addition, severe erosion
and localized slumping below the road have led to the
Figure 8 illustrates the combined mapping approach and progressive loss of bench support at the northern
the use of subsurface investigation at the site shown in flank of the relict landslide (Fig. 5). The patterns of
Figure 5, where the most distressed and unstable section erosion, slope failure and road distress suggested that
of the alignment was encountered. For approximately the current movements are relatively shallow and related
2 km, long sections of the original road bench have been to erosional unloading rather than deep-seated, large-
lost due to landsliding and erosion. Whole spurs have scale movement of the landslide mass. Mapping of the
230 HART ET AL.
Fig. 8. Combined field mapping and ground investigation for site appraisal at km 282 (case study 2)
Fig. 9. Cross section A–A and detailed design at km 282 (case study 2)
existing scars and cut slope surfaces, combined with metavolcanic rocks (Fig. 9). However, localized out-
selective subsurface drilling, confirmed the presence of crops of relatively stable rock were encountered on
25 to 30 m of disturbed and extremely weak soil and either side of this mass. The design involved realignment
rock, interpreted as a transported mass of hydrother- of the road into the hillside between these two outcrops,
mally altered and moderately to completely decomposed and battering of steeper sections of the northern flank of
MOUNTAIN ROAD REHABILITATION 231
the landslide with all excavated material being hauled to pitting has proven extremely useful in this process, while
approved stable spoil disposal areas. While this had the drilling investigations have, with one or two exceptions,
disadvantage of removing support to the disturbed mass not contributed significantly to the interpretation.
above the road it allowed the road to be relocated away Nevertheless, while the emphasis on using engineering
from the deteriorating road margin below. Furthermore, geological mapping is vindicated by this review, the
as the required slope excavation was to be undertaken geotechnical engineering problems required to be
towards the head of the relict landslide, it was concluded resolved on the Halsema Highway remain extremely
that there would be a positive influence on the stability severe. In several locations the details of the design can
of the landslide slope as a whole. only be confirmed when excavations for deep cuttings
Elsewhere, overhanging sections of pavement, caused and foundations are opened up during construction.
by washouts and erosion below, were frequently seen to Even so, the decision-making at that time will require
coincide with the locations where fault zones, some of marginal value judgements in many instances. It is here
which contained considerable fault gouge, intersected that the value of continuity between the design and
the alignment. At these locations retaining walls, the construction activities will be of value, assisted by
foundations for which were investigated with trial pits, knowledge of the dynamism of each location over the
were scheduled both above the road to support steep soil 5 year time interval. Engineering on the precipice has
cut slopes, and below the road over failure embayments certainly benefited from the application of engineering
to reinstate the road bench. geology, but the real value of the mapping applications
will not be finally gauged until construction is well
underway and the exposed ground conditions and geo-
Construction morphology of the site become clearer during the forth-
coming typhoon seasons. In this respect the impact of
The 180 km long road was divided into three sub- Typhoon Feria, that struck Baguio on 4 July 2001 and
sections and the construction contract for the first 85 km deposited in excess of 1200 mm in 36 hours, will allow
between Baguio and Mt Data was awarded in June the observations, predictions and recommendations of
2001. This section is the most critical from a geotechni- the engineering geological design to be fully put to the
cal point of view, as it is here that the majority of 1990 test.
earthquake damage took place. Fifty percent of the
calculated reinstatement and road improvement cost is Acknowledgements. The authors would like to thank the
designated for bench reinstatement, slope stabilization, Department of Public Works and Highways, Government of
slope protection, and drainage. At the time of writing, the Republic of the Philippines for permission to publish this
construction works had just commenced. Initial reports paper. The lead consultant for feasibility and design studies
from the construction site confirm the value of the trial was BCEOM of France.
pit information, particularly in areas where heavy veg-
etation now conceals ground conditions of concern at References
the time of the design. The construction supervision
programme allows for further geotechnical assessment C, C., E, S., H, G.J. & I, H. 1999.
and advice during implementation of the works, and it is Bio-engineering as an aid to slope protection and erosion
the authors’ intention to publish findings and outcomes control along the Halsema Highway, Philippines. Proceed-
ings of the 1st Asia-Pacific Conference and Exhibition on
at a later date.
Ground and Water Bioengineering for Erosion Control
and Slope Stabilization, Philippines.
G-C 1996. Baguio-Bontoc-Banaue Road
Conclusions (Halsema Road), Pre-Design Investigation. IBRD-
Assisted Highway Management Projects. Department of
The use of engineering geological mapping, with an Public Works and Highways.
NZNSEE R T 1991. The Philippines
emphasis on geomorphological assessment, has allowed Earthquake of July 16, 1990. Report on Field
both the inherent instability and dynamism of the Visit. Bulletin of the New Zealand National Society for
landscape to be evaluated for design purposes. Trial Earthquake Engineering, 1, 1.