Project: Construction of Car Parking Plaza/ Commercial Plaza at Shabuddin Market adjacent to

Empress Market, Saddar-Karachi.


08 August, 2017.

SUMMARY ESCALATION AGAINST IPC # 15

S.NO DESCRIPTION OF ITEMS TOTAL AMOUNT

1 Escalation/De-Escalation for Cement 913,565.98

2 Escalation/De-Escalation for Steel 811,723.69

3 Escalation/De-Escalation for Diesel 342,097.32

TOTAL AMOUNT: 2,067,387.00


Project: Construction of Car Parking Plaza/ Commercial Plaza at Shabuddin Market adjacent to Empress Market,
Saddar-Karachi. 08 AUGUST, 2017

SUMMARY OF ESCALATION FOR DIESEL AGAINST IPC # 15

WORK DONE FOR INCREASE/


PERIOD TOTAL WORK DONE MONTH DIESEL @5% BASIC RATE REVISED PRICE DECREASE

Feb-17 16,551,601.31 16,551,601.31 827,580.07 57.14 80.76 41.34%


Project: Construction of Car Parking Plaza/ Commercial Plaza at Shabuddin Market adjacent to Empress Market,
Saddar-Karachi. 08 AUGUST, 2017

ARY OF ESCALATION FOR DIESEL AGAINST IPC # 15

AMOUNT (PKR)

342,097.32

342,097.32
Project: Construction of Car Parking Plaza/ Commercial Plaza at Shabuddin Market adjacent to Empress Market,
Saddar-Karachi. 08 August, 2017

CONSUMPSION OF CEMENT AGAINST IPC # 15

S.No Description of items Unit Quantity Conv.Factor Bags

1 (1:1½":3) Concrete (3750 psi) Cu.f 17,572.82 0.224 3,936.31

2 (1:1:2) Concrete (5000 psi) Cu.f 1,203.00 0.308 370.52

3 6" Thick Block Masonry (1:6) Sq.f -

4 1" Thick Plaster ratio (1:4) Sq.f -

TOTAL CONSUMTION OF BAGS 4,306.84


Project: Construction of Car Parking Plaza/ Commercial Plaza at Shabuddin Market adjacent to Empress Market,
Saddar-Karachi. 08 August, 2017

SUMMARY OF ESCALATION FOR CEMENT AGAINST IPC # 15

BAGS FOR PRICE DURING INCREASE/


PERIOD IPC BAGS FOR MONTH BASIC RATE PERIOD DECREASE AMOUNT (PKR)

Feb-17 4,306.84 4,306.84 355.00 567.12 212.12 913,565.98

913,565.98
Project: Construction of Car Parking Plaza/ Commercial Plaza at Shabuddin Market adjacent to Empress Market,
Saddar-Karachi.
08 Nov, 2016
SUMMARY OF ESCALATION FOR STEEL AGAINST IPC # 15

PERIOD STEEL FOR IPC # 15 BASIC RATE PRICE DURING PERIOD INCREASE/ DECREASE AMOUNT (PKR)

Feb-17 100.98 65,000.00 73,038.46 8,038.46 811,723.69

811,723.69
`

MEASUREMENT SHEET

STEEL SUMMARY FOR ESCALATION AGAINST IPC # 15


Item no. # DATA FROM IPC #15

ITEM NO. DESCRIPTION/GRID WEIGHTIN TON


SHOPS-CIVIL
4.12 (2) STEEL UPTO GROUND FLOOR 15.53
4.12(3) STEEL GROUND TO MEZZANINE FLOOR 3.92
PARKING-CIVIL
2.01 (1) R/F STEEL 2ND TO 3RD FLOOR 81.53

TOTAL WEIGHT OF STEEL IN TON 100.98


`

MEASUREMENT SHEET

CONCRETE SUMMARY FOR ESCALATION AGAINST IPC # 15

(1:1½":3) Concrete (3750 psi)


ITEM NO. DESCRIPTION/GRID
SHOPS-CIVIL
4.09 ( 2) SLAB UPTO GROUND FLOOR
4.09 (3) WALLS UPTO GROUND FLOOR
PARKING-CIVIL
1.02 (1) BEAMS 2ND FLOOR
1.02 (2) SLAB 2ND FLOOR
ION AGAINST IPC # 15
DATA FROM IPC #15

CFT

2605.68
1178.92

4564.52
9223.7

17572.82
`

MEASUREMENT SHEET

CONCRETE SUMMARY FOR ESCALATION AGAINST IPC # 15


DATA FROM IPC #15
(1:1:2) Concrete (5000 psi)
ITEM NO. DESCRIPTION/GRID CFT
SHOPS-CIVIL
4.05 (1) COLUMN B/W GROUND & MEZZANINE FLOOR 693

PARKING-CIVIL
1.01 (1) COLUMN B/W SECOND & 3RD FLOOR 510

TOTAL CONCRETE 1203