Name of Work :Construction of Bridge across Cauvery River in the v

Taluk, Mysore Dis


Providing and constructing one span service road to reach isl
length 35mtr , width of service road 9mtr depth of water 5.5 m
ERL-05 transporting the material by tipper. Placing sand bags for pr
labour, lead, lift , loading , unloading, transporting hire charge
in-charge of work, and in accordance with MoSRT&H Technical
Non Sr
Unit = 1796.5 cum
a) Material
Earth Granular material Sl no 57 code 0751

Mate (0.24/1.25)*6.0 Page no LII

Mazdoor for filling sand bags, stitching and


placing (6/1.25)* 6.0Page no LII
c) Machinery
Front end Loader 1 cum capacity
(27/1.25)*5.0 Sl.no 15 code no 1012
Tipper 5.0 cum capacity (28/1.25)*6.0 sl.no
78 code no 1096
D Over head Charges @0.1 on (a+b+c)
E contractor Profit @0.1 on (a+b+c+d)
F Cost for 1 span (a+b+c+d)
G Rate per cu.m (a+b+c+d+e)/1767.5

T
Cauvery River in the vicinity of Holesalu near Kaveripura Village in T.Narsip
Taluk, Mysore District."
ervice road to reach island location from one pier to another pier location of s
r depth of water 5.5 mtr and ht of road 6.0 mtr in 1:2 slope using front end loa
acing sand bags for protection of earthern slopes , including cost of all mat
ransporting hire charges of machineries etc; complete as per the directions of
th MoSRT&H Technical Specification Clause 1200

UNIT QUANTITY RATE AMOUNT


cum 1796.50 170 305,406
day 1.15 249.55
287

day 28.80 244.55 7,043

hour 129.60 700


90,720

hour 134.40 240


32,256
43,571
47,928
527,212
293
Tender premium 24%(H) 70.43

Total Rate per cum(G+H) 363.90


llage in T.Narsipura

pier location of span


sing front end loader,
g cost of all material
the directions of eng-

Rate per
cum