Cover Page

Project Name: BDO BINONDO


Project Address: San Fernando St. Binondo Manila City

WEEKLY REPORT

REPORT NO. 10
(Dec 23-29, 2017)

Submitted By:

___________________________
Anthony Albert S. Valdez

Page 1
PROJECT : BDO - BINONDO
LOCATION : San Fernando St. Binondo Manila City
OWNER : BANCO DE ORO
SUBJECT : BAR CHART

WEIGHT OCTOBER ( 2017 ) NOVEMBER ( 2017 ) DECEMBER (2017)


ACTIVITIES AMOUNT FACTOR
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
(target)
1. GENERAL REQUIREMENTS 645,000.00 14.31%
(actual)
2. SITE WORKS 182,350.00 4.04%

3. CONCRETING 156,077.90 3.46%

4. MASONRY 207,898.00 4.61%

5. METAL WORKS 238,569.90 5.29%

6. CARPENTRY & PLASTICS 551,523.80 12.23%

7. THERMAL & MOISTURE 12,953.60 0.29%

8. DOORS & WINDOWS 102,500.00 2.27%

9. FINISHES 1,159,778.78 25.72%

10. SPECIALTIES 37,895.00 0.84%

11. PLUMBING WORKS 0.00%

12. FIRE PROTECTION WORKS 142,000.00 3.15%

13. ELECTRICAL WORKS 1,072,074.72 23.78%

14. VAULT DOOR OTHERS

15. LOW / HIGH COUNTERS OTHERS

16. BACKROOM GLASS STICKERS OTHERS

17. SHELVES / CHAIRS / ATM OTHERS

TOTAL 4,508,621.70 100.00%

11.4900%
PROJECT WEEKLY ACCOMPLISHMENT 5.00% 10.00% 15.00% 10.00% 10.00% 10.00% 10.00% 5.00% 5.00% 5.00%
PROJECT CUMULATIVE ACCOMPLISHMENT 5.00% 15.00% 30.00% 40.00% 50.00% 60.00% 75.00% 80.00% 85.00% 90.00%
ACTUAL WEEKLY ACCOMPLISHMENT 4.64% 5.96% 9.38% 5.84% 11.49% 10.19% 20.61% 7.78% 2.03% 4.35%
ACTUAL CUMULATIVE ACCOMPLISHMENT 4.64% 10.60% 19.98% 25.82% 37.31% 47.50% 68.11% 75.89% 77.92% 82.27%

PREPARED BY:

Anthony Albert S. Valdez


Project Manager
PROJECT : BDO BINONDO
LOCATION : San Fernando St. Binondo Manila City
OWNER : BANCO DE ORO
SUBJECT : S-CURVE

100.00%

90.00% 90.00%
85.00%
80.00% 82.27%
80.00%
77.92%
75.89%
75.00%
70.00%
68.11%
Weighted
60.00% Accomplished 60.00%

50.00% 50.00% PROJECT CUMULATIVE ACCOMPLISHMENT


47.50%
ACTUAL CUMULATIVE ACCOMPLISHMENT
40.00% 40.00%
37.31%
30.00% 30.00%
25.82%
20.00% 19.98%
15.00%
10.60%
10.00%
4.64% 5.00%
0.00%
WEEK WEEK WEEK WEEK WEEK WEEK WEEK Week Week Week
1 2 3 4 5 6 7 8 9 10
MYCROTYX BUILDES CORP
664 Barrio Tabe Guiguinto Bulacan
9178968210

PROJECT NAME : BDO BINONDO


LOCATION : San Fernando St. Binondo Manila City
DATE : Dec 29, 2017

ACTIVITIES AMOUNT WEIGHTED PERCENTAGE PERCENT ACCOMPLISHED WEIGHTED ACCOMPLISHED

GENERAL REQUIREMENTS 622,500.00 16.11% 85% 13.70%


1

SITE WORKS 182,350.00 4.72% 100% 4.72%


2

CONCRETING 183,361.02 4.75% 100% 4.75%


3

MASONRY 115,777.00 3.00% 100% 3.00%


4

METAL WORKS 224,850.00 5.82% 95% 5.53%


5

CARPENTRY & PLASTICS 383,583.60 9.93% 75% 7.45%


6

THERMAL & MOISTURE 20,944.00 0.54% 100% 0.54%


7

DOORS & WINDOWS 136,800.00 3.54% 90% 3.19%


8

FINISHES 747,773.61 19.35% 80% 15.48%


9

SPECIALTIES 60,635.00 1.57% 0% 0.00%


10

PLUMBING WORKS 139,511.80 3.61% 100% 3.61%


11

FIRE PROTECTION WORKS 201,700.00 5.22% 30% 1.57%


12

MECHANICAL WORKS 14,000.00 0.36% 0% 0.00%


13

ELECTRICAL WORKS 823,290.90 21.31% 88% 18.75%


14

OTHER REQUIRED WORKS 6,500.00 0.17% 0% 0.00%


15

TOTAL 3,863,576.93 100.00% 82.27%

Target Completion (to date) 90.00%

Variance (+/-) -7.73%

KEY ACCOMPLISHMENT (for this week)

1 Cladding of Ceiling

2 Tiling Works at Toilet and Slop Sink

3 Construction of Hand Sink

4 Installation of Security Grills

Prepared by:

Anthony Albert S. Valdez


PROJECT MANAGER
MYCROTYX BUILDERS CORP
664 Barrio Tabe Guiguinto, Bulacan
9178968210

PROJECT NAME : BDO BINONDO


LOCATION : San Fernando St. Binondo Manila City
DATE : Dec 29, 2017

EXPECTED SCOPE TO BE ACCOMPLISHED NEXT WEEK REMARKS


1 Start of Melamine Works
2 Cladding of Ceiling Continuation
3 Continuation of Painting Works
4 Construction of Slop Sink including installation of Granite Top
5 Installation of Dry Chem Type Sprinkler (still waiting for the quotation of contractor)
6

MANPOWER

PREVIOUS WEEK 5
WEEK 9 0
TOTAL TO DATE 5

CRITICAL WORKS:

1 Sprinkler - Waiting for Quotation from Dry Chem Type Sprinkler Contractor

2 Just started construction of Hand Sink. Owner just recently relocated the door of EE room

3 Ceiling at Pantry - still can't layout ceiling due to undismantled electrical system at this area

4 Ceiling at Storage/Accounting - still can't layout due to water leak coming from 2nd Floor

5 Existing Electrical System at Pantry still has not been dismantled

ISSUES AND CONCERNS: REMARKS

1 Since Dec 23, Power only resumed on Dec 26.

2
Water leak from 2nd floor is still an issue

OTHERS

Prepared by:

Engr. Anthony Valdez


Project Manager
weekly report 3
MYCROTYX BUILDERS CORP
664 Barrio Tabe Guiguinto, Bulacan
9E+09

PROJECT NAME : BDO Binondo


LOCATION : San Fernando Street Manila C
DATE : Dec 29, 2017

PERMIT STATUS

ITEM PARTICULAR DATE SUBMITTED DATE RELEASED REMARKS


1 Barangay Permit 18-Aug-17 15-Sep-17 Delay due to CARI issue
2 Demolition permit (if applicable)
3 Locational Clearance 20-Sep-17 not yet released
4 Building Permit 20-Sep-17 not yet released
5 Electrical Permit 20-Sep-17 not yet released
6 Mechanical Permit 20-Sep-17 not yet released
7 Sanitary Permit
8 Electronics Permit (If applicable)
9 DENR permit (if applicable)
10 Signage Permit
11 FSIC
12 CEI
13 CUSP
14 PTO (aircon)
15 Occupancy Permit

OSM

PROPOSED ACTUAL
ITEM PARTICULAR REMARKS
DELIVERY DELIVERY
1 Unitized Electrical Panel 4-Dec-17 23-Dec-17
2 Data Cabinet 11-Dec-17
3 Marketing Counters 9-Dec-17
4 Teller’s Counter 9-Dec-17
5 Air-conditioning Units 12-Dec-17
6 Cash Vault Door 24-Nov-17
7 Generator Set 9-Dec-17
8 Glass Panels 7-Dec-17
9 Security Film 9-Dec-17
10 Roller Shades 12-Dec-17
11 Horizontal Sign 14-Dec-17
12 Flag sign 14-Dec-17
13 Door sign sticker 14-Dec-17
14 Intercom 14-Dec-17
15 Corporate Identity Wall 10-Dec-17
16 Dreamline 10-Dec-17
17 Telephone lines 9-Dec-17
18 UPS 9-Dec-17

Page 6
Picture 1 Picture 2

Activity: Cladding of Ceiling Activity: Cladding of Ceiling


Location: Bank Hall Location: Bank Hall

Picture 3 Picture 4

Activity: Ongoing Painting Works Activity: Painting Works


Location: Accounting Location: Cash Vault

Picture 5 Picture 6

Activity: Painting Works Activity: Slop Sink Construction


Location Accounting Area Location Pantry