Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site

WEEKLY PROGRESS REPORT


LOT-I WWTP1 Date: 25 November 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No meeting conducted and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Footing Pad Excavation and lean concrete pouring for PTU
-lean concrete pouring and form work fixing for base slab at Aeration Sludge Tank
-Backfilling with suitable material under base slab of Areation sludge
tank and gravity thickners
-Base Slab formwork and water stop fixing at Biological
treatment unit -Top tie beam and roof slab form work
fixing at Control Building
6 E-M Installation Activities: NA
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological
treatment, Aeration Sludge Tank and Control Building, water stop for Chilorination tank,
embeded pipes for gravity thickners
-No sufficient stock of fine and course aggregates at site.

12 Any Other Remarks: NA

Signature Mesfin D.
minium Site

esfin Derbew

b at Aeration Sludge Tank


lab of Areation sludge

ing at Biological
nd roof slab form work

ebar for Biological


Chilorination tank,

urse aggregates at site.


Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 04 December 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: Meeting conducted on 24/11/2017 and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Footing Pad C-30 Concrete pouring and Foundation Column Formwork fixingfor PTU
-Backfilling with suitable material and lean concrete pouring
under base slab at Gravity Thickener
-Base Slab formwork and
water stop fixing at Biological treatment unit -Top tie beam
and roof slab form work fixing at Control Building
6 E-M Installation Activities: NA-X-stop Water stop positioning on chilorination tank
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological treatment,
Aeration Sludge Tank and Control Building, water stop for Chilorination tank, embeded pipes for
gravity thickners
-No sufficient stock of fine and course aggregates at site.
-Most of units are on lean concrete level and are waiting for reinforcement supply.
accordingly we have issued an instruction letter to deliver sufficient quantity of construction
materials which is affecting the quality and progress of works.
12 Any Other Remarks: NA

Signature Mesfin D.
minium Site

Mesfin Derbew

work fixingfor PTU


al and lean concrete pouring

-Base Slab formwork and


-Top tie beam

ebar for Biological treatment,


on tank, embeded pipes for

ting for reinforcement supply.


quantity of construction
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 18 December 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Backfilling under PTU seat and around foundation columns completed -Masonary work under gra
beam -C
Pouring for 1/9th porition of the Biological treatment unit base slab

-Top tie beam and roof slab form work fixing at Control Building
-Water stop and wall form work positioning and fixing on chilorination tan
6 E-M Installation Activities: NA -HCB block work placing for chemical building

7 Testing and Commissioning: NA


8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological treatment, A
Sludge Tank, Gravity thickner and Control Building.
-No sufficient stock of fine and course aggregates at site.
-Most of units are on lean concrete level and are waiting for
reinforcement supply.
12 Any Other Remarks:
-Diameter 20mm bars has supplied on Saturday 16 December 2017 and Contractor requested to
rebar bending and placing for porition of Biological treatment unit paused b/c of 20mm diam
parallel to taking samples for quality tests. The Contractor's representative informed by letter tha
will be failure up on test results, they will take the risk and will remove from site accordingly.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

ed -Masonary work under grade


-Concrete

rol Building
and fixing on chilorination tank
uilding

ebar for Biological treatment, Aeration

rse aggregates at site.


ete level and are waiting for
and Contractor requested to continue
t paused b/c of 20mm diameter bars
entative informed by letter that if there
e from site accordingly.
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 25 December 2017 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Lean Concrete pouring under PTU seat, C-30 Concrete pouring under PTU seat below ground le
Ground Elevation columns of PTU unit are completed
-Concrete Pouring for Chilorination tank wall

-HCB block work


for chemical building
6 E-M Installation Activities: NA
7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as rebar for Biological treatment, A
Sludge Tank, Gravity thickner and Control Building.
-No sufficient stock of fine and course aggregates at site.
-Most of units are on lean concrete level and are waiting for
reinforcement supply.
12 Any Other Remarks: -Supplied Diameter 20mm bars has failed to satisfy the minimum ASTM A615 requirements and h
Contractor didn't started any activity on Biological treatment unit.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

der PTU seat below ground level and

-HCB block work placing

ebar for Biological treatment, Aeration

rse aggregates at site.


ete level and are waiting for

STM A615 requirements and hence the


Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium Site
WEEKLY PROGRESS REPORT
LOT-I WWTP1 Date: 01 January 2018 Prepared By: Mesfin Derbew

1 Weather: Sunny
2 Health and Safety: No Meeting and No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC and EM issues still pending
5 Civil Construction Activities: -Concrete pouring for above ground PTU seat and first intermidiate beam
- second lift wall formwork preparation on
chilorination tank

-Plastering of HCB block wall for chemical building

6 E-M Installation Activities: NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11 Overall Progress: -low progress of works due to shortage of material supply such as reinforcement rebar for Biologic
treatment, Aeration Sludge Tank, Gravity thickner and Control Building.
-No sufficient stock of fine and course aggre
site. -Most of units are on lean concrete level
waiting for reinforcement supply.
12 Any Other Remarks: -We have forwarded EOT Approval to the Employer with Completion date 13 July 2018
Contractor has been requested to submit Master work schedule according to the EOT. He
Contractor has submitted Guant chart Master schedule on Saturday 30 December 2017.

Signature Mesfin D.
minium Site

By: Mesfin Derbew

beam
wall formwork preparation on

einforcement rebar for Biological


ng.
tock of fine and course aggregates at
ts are on lean concrete level and are
mpletion date 13 July 2018 and the
e according to the EOT. Hence, the
30 December 2017.