You are on page 1of 18

Groundwater and drawdown in a large earth excavation1

F. DEBIDIN
AND C. F. LEE
Georecht~icalEt~gitleeritlgDeparrtner~t,Otzrnrio Hydro, Tolwt~ro,Otlr., Cut~aduM5G 1x6
Received October 17, 1978
Accepted December 17, 1979

In deep excavations below the water table, the transient and steady state drawdown condi-
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

tions are often of interest. Particularly in moderately pervious soils, the stability of the slopes,
the excavation methods, and equipment are affected by the groundwater response in the
excavation. The extent of the drawdown in the area beyond the excavation must also be deter-
mined.
For a site under construction by Ontario Hydro, a test excavation to determine the drawdown
response in the irregularly stratified soils is described. Analyses of the data by the finite element
method and by the theory of aquifer tests are presented. The effect of recharge on the steady
state and transient drawdown is discussed.
For the main excavation, approximate methods to determine the rate of drawdown, the
quantity of seepage, and the steady state drawdown position with recharge from infiltration or
deep seepage are outlined.

Dans les excavations sous la nappe phrkatique, la connaissance des conditions transitoires et
perrnanentes de rabattement prCsente un frCquent intCrCt. En particulier, dans les sols faiblement
permCables, la stabilitC des pentes, les mCthodes et les Cquipements d'excavation dCpendent de la
rCaction de la nappe phrCatique dans l'excavation. L'Ctendue du rabattement dans la zone
voisine de l'excavation doit aussi Ctre dCterminCe.
For personal use only.

L'article dCcrit une excavation experimentale rCalisCe sur un site de construction de I'Hydro-
Ontario, pour Ctudier le phCnomkne de rabattement dans des sols irrkgulikrement stratifiCs. Les
analyses des rnesures par la mCthode des ClCments finis et par la thCorie des essais d'aquifkre
sont prCsentCes. L'effet d'une recharge sur les Ctats de rabatternent transitoire et permanent
est discutC.
On prksente les mCthodes approximatives utilisCes pour determiner dans I'excavation reelle,
la vitesse de rabattement, le dCbit d'infiltration et la position permanente de la nappe aprks
rabattement compte tenu d'une recharge par infiltration ou par Ccoulement profond.
Can. Geotech. J., 17, 185-202 (1980)

Introduction Description of the Site and the Proposed Excavation


In a large excavation below the water table, the The site is being developed for a nuclear power
effects of groundwater and seepage are important plant on the north shore of Lake Ontario near
when considering the stability of the slopes, construc- Bowmanville about 70 km east of Toronto. The
tion planning, equipment, and methods. Also, major location is part of the area covered in a detailed
changes in the water table may be caused by the hydrogeological study by Singer (1974). In Fig. 1 is a
drawdown in a deep, wide excavation. The extent of plan of the general layout of the major features of
these changes in the area surrounding the excavation the works-the excavation, the cooling water fore-
must be determined. bay, the powerhouse, and vacuum building.
Following the general description of a site under A cross section generalized from details from bore-
development by Ontario Hydro, the investigation of holes drilled during various stages of investigations
the groundwater response in a test excavation on the of the site is presented in Fig. 2. The overburden can
site is discussed and the application of the data be considered in three main formations: (i) an upper
derived from the test pit to the study of seepage in the stratum, about 3-10 m thick, of lacustrine sand and
main excavation is presented. Transient and steady silts or silty till.; (ii) an interglacial series of fine sand
state conditions analysed by the finite element meth- and layered clayey silt up to about 30 m thick; and
od are compared with the results from the theory of (iii) a lower basal silty till about 3 m thick.
aquifer tests. At the shoreline the upper till or lacustrine soil as
well as the interglacial fine sands and clayey silt are
'Presented at the 31st Canadian Geotechnical Conference, visible in steep bluffs that rise 10-20 m above the
Winnipeg, Man., October 1978. mean lake level, elev. 74.7 m (Canadian geodetic

OOO8-3674/80/020185-18$01.00/0
1980 National Research Council of Canada/Conseil national de recherches du Canada
186 CAN. GEOTECH. J. VOL. 17, 1980
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

I
For personal use only.

FIG. 1. Darlington Generating Station-site layout.

LIMESTONE

ELEVATION I N METRES
SYMBOLS [CG Dl

-1- BEDROCK SURFACE


7/TILL
//
A WATER LEVEL

EXCAVATION LIMIT
FIG.2. Darlington Generating Station-section.

datum). From the shore cliff the ground surface rises The bedrock surface is at around elev. 66 m and is
gradually to the north to about elev. 106 m near the fairly flat. The bedrock consists mainly of Ordovician
excavation limits and to higher values further north. limestone of the Trenton Group. The upper 7-9 m of
DEBIDIN AND LEE
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

-
P

0
0.001 0.01 0.1 1.0 10 100
GRAIN SIZE DIAMETER (mm)

SAND GRAVEL
CLAY TO SILT COBBL E S
FINE IMEDIUM I co FINE I co
FIG. 3. Typical grading curves.
For personal use only.

bedrock consists generally of dark brown to black tesian flow. Also, the water levels measured in the
thin to medium bedded fossiliferous shaly limestone. overburden are about 4 m higher than the water level
U p to about 0.6 m of weathered rock occurs on the in bedrock. The elevation of the water table in the
surface at some locations; the remainder of the rock overburden near the north limits of the site excava-
mass is generally free of any major open joints or tion is at around elev. 90 m. The water table surface
fissures. slopes to the south at a gradient of about 2% and, at
In Fig. 3 are shown typical grain-size curves for the local exit points, the water flows from the face of the
upper till and the fine sand strata. Based on the bluffs from exposed fine sand strata.
exceedingly high standard penetration resistance in The proposed excavation for site grading and
the soils, with N values exceeding 100, the deposits foundations covers an area of about 800 m by 300 m.
are in a very dense or hard state. From laboratory The soil excavation will be taken to bedrock at
and borehole tests, the mean coefficient of per- around elev. 66 m and will remain open for about
meability of the upper and lower tills and interglacial 5 years for construction of the foundations after
clayey silts is in the range of to m/s and which the site will be backfilled to around elev. 78 m.
that of the fine sand is of the order of to The forebay for the cooling water system is located
m/s. Where exposed in natural slopes at the shoreline near the toe of the north slope of the excavation
or in excavations, the soil deposits do not exhibit any about 250 m from the shoreline.
secondary structures or more pervious zones that At the north side of the site excavation, the tem-
may have any influence on the average permeability. porary drawdown of the water table will be about
From the appearance of the fine sand strata, it is 24 m but the permanent changes at the slope location
assumed that the deposit is homogeneous and iso- will be about 12 m. Because of the pervious fine sands
tropic with respect to permeability. Water pressure in the interglacial complex, the control of ground-
tests in the boreholes in the bedrock indicate the rock water and seepage was considered a major problem
mass to be generally watertight with a permeability in the preliminary engineering stage. For example,
coefficient probably less than 10-%/s. Fig. 3 shows the fine sand grading falling in the limits
The groundwater conditions were observed over in which gravity drainage is too slow and special
several years in observation wells with tips in the treatment of well point systems may be required. A
bedrock and also with tips in the overburden. The field drawdown test was considered useful for evalua-
water levels in the overburden are, in some locations, tion of the groundwater response during and after
under excess hydrostatic pressure and produce ar- the excavation for site grading and foundations.
CAN. GEOTECH. 1. VOL. 17, 1980
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

'E- 2 A

SYMBOL 0 6 10 METRES
PIEZOMETER LOCATION mT E - 8
m

FIG. 4. Darlington Generating Station-plan of test excavation.


For personal use only.

The Test Excavation upper 3 m section, which was sealed with a ben-
Based on data from the borehole investigations, tonite-cement grout up to the ground surface. In
preliminary studies of the groundwater control re- addition to the piezometers immediately around the
quirements indicated major problems with installa- test excavation, other boreholes drilled on the site for
tion and testing of deep wells or well points. As an previous investigations were available for water level
alternative a test excavation could provide data for observations.
drawdown evaluation and access for iiz situ loading At the location selected, the ground surface was a t
tests for undisturbed block samples for laboratory around elev. 88 m, gently sloping to the east. The test
work. Direct observation of the slopes and of the per- excavation, as shown in Fig. 4, was about 80 m long
formance of construction equipment particularly for by 36 m wide. The depth ranged between 7 and 9 m.
disposal of the soil could also be made. Side slopes in the upper 3 m and above elev. 84.8 m
A location for the test excavation was selected were at 1 to 1 and, below, in the interglacial strata,
where the surficial soils and upper till were about 3 m they were about 2 to 1. The bottom of the pit was at
thick and minimum stripping was required to reach around elev. 80.3 m and about 3 m wide.
the interglacial deposits. Also, at this location bore- The test excavation was started on 3 August 1976
hole piezometers showed the initial groundwater and was carried out in two main stages (shown in
table to be close to the ground surface with artesian Fig. 5) with a backhoe and dump trucks as follows:
conditions thus providiig a suitable background for (i) stripping of topsoil, surficial material and till, and
data for studying the drawdown during the test the upper level of the interglacial sands to elev.
excavation. 84.8 m; and (ii) the excavation of the interglacial fine
Observations of the water levels in boreholes from sands and clayey silt below elev. 84.8 m to around
earlier site investigations were continued and rainfall elev. 80.3 m.
measurements were started in July 1976. Also, eight After stripping of the topsoil was completed on
boreholes, TEI to TE8, were drilled to confirm the 6 August, ditches for surface runoff control were
stratigraphy and to install additional piezometers. completed on the north, south, and east sides of the
Mende-type piezometer tips were used. The 450 mm area and a sump was excavated at the northeast
long porous plastic cylinder filled with fine gravel corner with the bottom at around elev. 84 m on
was attached to a 38 mm diameter plastic riser pipe 10 August. Several small boils were observed in the
and placed in the borehole. The annular space be- interglacial fine sand in the bottom of the sump. The
tween the riser and the wall of the borehole was filled seepage ranged between 4 and 9 L/min.
with clean medium to coarse sand except for the The excavation of the upper stage from 16 t o
DEBIDIN AND LEE
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

0 v YI
m W
C
C
WL.3 / 8 / 7 6 88.97
=V 87.93 vC V88.67

---
87.48

WL. 2019176 1

-
"

SYMBOLS 0 2 4 6 8 X) METRES

TILL
SILT
FINE SAND
For personal use only.

C G D (metres)

FIG. 5. (a) Section-soil stratigraphy. (b) Groundwater levels.

23 August was carried out working from west to east. Observations of the groundwater levels and pumping
Numerous temporary small boils were observed in were continued to 1 October when pumping was
the bottom and pumping developed under truck stopped.
traffic. The ramp and parts of the bottom were lined
with crushed stone or rockfill about 0.5 m thick to Results and Analysis
provide a trafficable surface. Water levels in the observation wells near the test
Stage 2 excavation was started on 24 August. excavation were observed at least twice each day, and
Working from the east end, the soil, mainly the inter- at other locations daily readings were taken. Typical
glacial fine sand and clayey silt, was excavated to drawdown-time values are plotted in Figs. 6 and 7 in
final width and depth with side slopes of about 2 to 1 which rainfall measurements for the period are also
and to the bottom with a sump at around elev. 80 m. shown.
Boils of moderate size developed in the bottom soon During the first stage of the excavation, August
after completion of the sump. 3-24, a small seepage of about 6 L/min was pumped.
Fine sand and silt from seepage erosion and piping An initial drawdown was noted. The drawdown
caused frequent silting of the pumps, the flow from increased rapidly after the second stage was started
which now ranged between 27 and 36 L/min. and progressed with the excavation generally reach-
Groundwater levels around the excavation continued ing an equilibrium state soon after the excavation
to drop while digging progressed towards the west. was completed. The lag in response in piezometers
Immediately after excavation, the slope appeared TE3 and TE8 shown in Figs. 6 and 7 is probably
generally stable. Within a few hours, a surface of caused by local variations in the soil permeability
seepage developed and erosion of the fine sand and by irregular stratification.
began. A short section of the slope was lined with The drawdown cone, which developed around the
crusher run stone, 50 mm maximum size and 0.3 m excavation, was of a slightly asymmetrical elliptical
thick, to observe the effects of seepage erosion con- section. Extrapolation of the plot of the drawdown
trol by this means. This treatment was successful in against the log of the distance from the excavation
stopping the erosion of the soil while allowing seep- indicated the average radius of influence of the ex-
age from the slope. cavation to be about 200 m.
The excavation was completed on 10 September. During the second stage, August 24 to September
CAN. GEOTECH. 3. VOL. 17, 1980
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

TlME (DAYS)

FIG. 6. Drawdown-time curves.


For personal use only.

TlME (DAYS)

FIG. 7. Drawdown-time curves.

10, the volume of pumping from the bottom of the excavation was carried out. The soil stratigraphy in
excavation increased to between 27 and 36 L/min Fig. 5 was idealized to give a finite element grid as
with an average of 32 L/min. Because of the increase shown in Fig. 9. The finite element formulation and
in drawdown and flow during the second stage of the solution of steady state seepage problems are well
test excavation, the effect of the first stage is consid- documented (e.g., Zienkiewicz 1971; Desai and Abel
ered negligible after the excavation is deepened. The 1972). The approach adopted for simulating transient
zero drawdown for the second stage is thus taken as drawdown around the test excavation was similar to
the water level position on August 24. Drawdown that described in France et al. (1971) and Zienkiewicz
against time values are shown in Fig. 8. (1971). With this approach the drawdown process is
divided into an arbitrary number of stages, the state
Finite Element Approach of flow within each being considered as momentarily
To aid in the interpretation of these field obser- steady. The free surface is still one of zero excess
vations, and to verify the hydromechanical charac- pressure, but is no longer a streamline. The velocity
teristics of the multilayer system, a finite element vectors are thus computed for each element, along
simulation of seepage and drawdown around the test with the nodal heads and quantities of flow (Lee
DEBIDIN A N D LEE
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

(a) TIME- DAYS


For personal use only.

TIME - DAYS
FIG. 8. Stage 2 drawdown.

1976, 1977). At each stage, the normal true velocity The finite element grid is then revised to account for
of the free surface (V,,,), which is the rate of draw- the reduction in the region of flow as a result of draw-
down, can be determined as down. Figure 9 shows the finite element grids used in
simulating the two stages of the test excavation.
[I1 v n t = v,V,,s/sy The following observations and deductions were
where V,,, is the component of Darcy velocity normal made from the results of this finite element analysis.
to the free surface, and Sy is the specific yield or (1) In a multilayer system consisting of alternating
drainable porosity. layers of fine sand and clayey silt or dense till, seepage
Beginning with its pre-excavation position, the occurs primarily in the relatively pervious fine sand
location of the free surface at the end of a predeter- strata. As illustrated in Fig. 10 a and b, the direction
mined time interval can be deduced from [I] above. of flow is predominantly horizontal in the fine sand
CAN. GEOTECH. J. VOL. 17, 1980

0
(( ! -
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

SCALE:
METRES

FIG. 9. Finite element grids for seepage study: (a) stage 1 ; ( b ) stage 2.

Y Y ,
I v

(a) + -
i

-
'J

- t
v
+ t + - , UPPER TILL
.FINE SAND
For personal use only.

.' " V Y ., J Y "3


CLAYEY SlLT
* C t f -C C C t C t-- C f C
FlNE SAND

CLAYEY SlLT

C C + + t C t C C C C C + f C +-
FlNE SAND

5 10 METRES/DAY
TRUE vELocITYPd=
SCALES :

*
,

4 - C C

"
"

I
* "

"
.

" .
, ,

"
,
C - t c
CLAYEY SlLT
FINE SAND

- -
" , , * " " , u
CLAYEY SlLT

C---- C - - - - - C - - - - - - - - FlNE SAND

NOTE: True velocities in impervious layers generally too small to be drawn to


scale. Only directions of flow are indicated
FIG. 10. Distribution of true velocity: (a) stage 1; ( b ) stage 2.

strata and vertically downward in the less pervious (2) A permeability coefficient of the order of
strata around the excavation. These flow directions 2-4 X m/s can be backfigured for the fine sand
indicate the shortest possible routes for water par- strata, based on the quantities of flow pumped out
ticles to reduce their hydraulic potentials in these two of the excavation and earlier stated.
types of materials. As a result, there is a "stepped" (3) Based on the rates of drawdown depicted in
appearance in the equipotential lines obtained (Fig. Figs. 6 and 7, a range of 0.014-0.02 can be back-
11). figured for the specific yield of the fine sand strata,
DEBIDIN AND LEE
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

-
--
v UPPER TILL
lmE3mD
CLAYEY SILT
FINE SAND
CLAYEY SILT
FlNE SAND

FIG. 11. Equipotentials (in metres) at ends of two stages of excavation: (a) stage 1; (b) stage 2.

giving an average of the order of 0.015. The corre- Active Zone


sponding values for the upper till and the clayey silt The active zone (Sheikov and Zel-brandt 1964) is
For personal use only.

deposits are between 0.002 and 0.007. There is a the thickness of soil below the bottom of the excava-
tendency for the specific yield to increase towards the tion through which seepage occurs. This thickness is
excavation surface, reflecting a further reduction in equal to the depth of the bottom below the initial
the confinement effect immediately around the ex- water table or the depth from the bottom to an im-
cavation. pervious boundary, whichever is less.
For the final depth of the test excavation, the inter-
Analytical Approach glacial strata extend to more than 7.5 m below the
Because of the variability of the soil strata and the bottom and thus the active zone, equal to 7.5 m,
detailed input required by the finite element approach extends to around elev. 77 m. Between the ground
for each situation to be studied, approximate analyti- surface and elev. 77 m, the total thickness (M) of the
cal methods by drawdown theory were also used. pervious fine sands is about 5 m as shown in Fig. 5.
Because the test excavation was carried out in one lift
during the second stage for removal of the inter- Quantity of' Seepage: Cotnpleted Test Excavation
glacial soil, the test excavation is envisaged as a large The drawdown-time plots in Figs. 6 and 7 show
diameter well. After completion of the excavation, an equilibrium or steady state position soon after
the three-dimensional effect on the flow becomes completion of the excavation. It is inferred from this
negligible and the steady state seepage may be con- that a recharge by both vertical and horizontal flow
sidered as a two-dimensional system. occurs and causes the drawdown to stabilize. The
The analyses for the quantity of seepage for the equilibrium may also be caused, to some extent, by
completed excavation and for the transient draw- partial penetration effects both in the excavation and
down during the second stage are presented below. in the observation wells (Hantush 1962).
Assuming confined flow conditions, the quantity
Equivalent Well Racli~ls of seepage (Q) may be calculated by (Peterson 1957):
The excavation may be considered as an equivalent
well with a radius given by (Mansur and Kaufman
1962):

The radius of influence (r') from the drawdown-


where L is the length and B is the width of the excava- distance plot is estimated to be 200 m. The thickness
tion. Thus, for average values of L = 64 m and (M) of the pervious strata is 5 m. The drawdown
B = 18 m, r, = 23.5 m. ( H - h,) at the excavation is the depth from the
194 CAN. GEOTECH. J. VOL. 17. 1980

initial water table to the bottom of the excavation, 1. Stage 2: steady state drawdown--estimate of
TABLE r/p
about 7.5 m. The value of n is the proportion of total
discharge replenished by vertical seepage and is equal Observation Max. drawdown
to unity for a fully recharging system or to zero well No. (m) K"(r/a) r/i3
where there is no recharge. Thus for k = 3 X 3.8 0.68 0.68
m/s and r, = 23.5 m, Q is estimated to be 26 L/min, 3 .O 0.53 0.84
which compares well with the measured value of
about 32 L/min.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

Drawdown Rate: Second Stage


In considering the transient drawdown, it is as-
sumed that the effects of partial penetration of the
excavation and of the observation wells into the able porosity or specific yield particularly at later
aquifers are negligible and that vertical recharge from stages of drawdown. In confined or artesian flow, the
precipitation and upward seepage from underlying storage coefficient is a relatively low value.
strata in the active zone are the main cause of the The analysis by the finite element method was used
equilibrium or steady state conditions. The analysis to back-calculate the specific yield for which an aver-
of this stage is then based on the theorv of drawdown age value of 0.015 was obtained. The recharge during
when from leaky artesian aq;ifers (Hantush the stage 2 drawdown suggests a semi-confined or
1956). leaky aquifer situation and the storage coefficient is
At steady state, the maximum drawdown (S,,,) in a therefore assumed equal to the specific yield or 0.015.
fully penetrating well is given by: The theoretical drawdown is then calculated from
[5] with r/j3 values from Table 1 and W(u, r/@)from
tabulated values (Hantush 1956). The observed draw-
For personal use only.

down is divided by the term Q/4nT to give field


where Q is the discharge from the well; T is the trans- values of W(u, r/j3), which are plotted with the
missibility = k M of the pervious deposits of thick- theoretical values in Figs. 12 and 13. There is a fair
ness M and permeability k ; Ko(rlj3) is the modified agreement between the observed and calculated
Bessel function of the second kind and of zero order values if the distortion in observed values caused by
of the value of r/j3 (given in tables by Hantush 1956); about 25 mm of rain during the drawdown period is
r is the distance from the well; and j3 is the leakage taken into account.
factor, which reflects the performance of the less From the foregoing analysis, it is concluded that
pervious or semi-confining strata. the use of the soil parameters developed in the
In Table 1, the maximum drawdown for the various phases of the investigations and the appropri-
second stage is used to determine the value of Ko(r/j3) ate drawdown theory will yield estimates that are
and r/g. reasonable. The flow conditions may be considered
The values of r/j3 are relatively high and indicate as a semi-confined or unconfined system and the
that the steady state drawdown is caused not only by storage coefficient of 0.015 appears to account for the
recharge but also by the effects of partial penetration. leaky effect of the less pervious strata adequately.
The above values of r/j3 are thus used in studying the
transient drawdown conditions. Drawdown and Seepage in the Excavation
The transient drawdown (s) for a leaky aquifer and Analytical methods for determining the steady
fully penetrating conditions is given by: state and transient drawdown in a reservoir or chan-
nel bank and in subsurface drainage systems give
approximate results sufficiently accurate for practical
purposes (Ferris et al. 1962; Moody 1962; Jenab et al.
where ti = r2S/4Tt (for radial flow conditions to a 1969; Streltsova 1975). The boundary conditions
well); S = storage coefficient; T = transmissibility created by an assumed instantaneous large excava-
= kM; t = time elapsed from start of pumping; and tion may be considered similar to those caused by
W(u, r/@) = well function for leaky systems from drawdown in a reservoir or channel bank, solutions
tables (Hantush 1956). for which may thus be adopted. These methods d o
The storage coefficient is an important parameter not usually include the effects of recharge to the
in transient drawdown studies. For unconfined flow water table from infiltration or deep seepage, which
situations, the storage coefficient is equal to the drain- result in an equilibrium condition or steady state.
DEBIDIN AND LEE
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15
For personal use only.

- 40
TIME- MYS

-t
E
E 30
20

10

FIG. 12. Well function - time curves.

An approximate solution is attempted herein to esti- considered equal to the drainable porosity for suffi-
mate the extent of the groundwater changes with ciently large values of t, particularly if the conditions
recharge from precipitation or deep seepage. of flow are unconfined (Streltsova 1975).
Also, the quantity of seepage (Q) from the slope is
Drawdown without Recharge given by :
When there is no recharge, the drawdown (s) at
any time (2) and distance ( x ) from the slope is given
by :
The quantity of seepage thus decreases in time.
161 s = SoD(u) In using this analysis for the site, the effect of strati-
[7] u2 = x2S/4Tt fication or the thickness of the less pervious silt and
clay strata in the site excavation is ignored. It is
(for flow to a line sink such as a channel, drain, or assumed that these less pervious soils allow sufficient
long slope) where Sois the drawdown at the slope leakage or are discontinuous enough to permit drain-
face; D(u) is a function of u (values for which are age into the fine sand strata. This assumption is
tabulated in Ferris et al. 1962); and S and T are the justified by the response of the water levels in the
coefficients of storage and transmissibility of the boreholes around the test excavation.
pervious strata. The coefficient of storage may be The transmissibility T = k M depends on the total
CAN. GEOTECH. J. VOL. 17, 1980

5 AUGUST 3111 SEPTEMBER 8 7 6 301 1


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15
For personal use only.

FIG. 13. Well function - time curves.

thickness ( M ) of the sand strata, which ranges be- time (days) is shown.
tween 3 and 10 m with an average value of about 6 m. From these figures it is seen that the drawdown
The drainable porosity, S , is assumed to be 0.015 for ratio increases with time and with values of M. After
the fine sand deposits as back-calculated from the a period of about 100 days or more, the difference in
test excavation. drawdown ratio for the range of values of M is small.
Near the location of the main excavation slopes, For earlier times the difference in D(zt) is generally
the existing water table ranges between elev. 90 and appreciable. Values of D(u) for intermediate times ( t )
95.4 m. For general site grade at around elev. 78 m, or thickness ( M ) can be obtained by interpolation or
the drawdown ( S O )at the slope is about the same as from other typical curves.
the depth of excavation below the water table, Because no recharge is considered in the above
12-17.4 m. For additional excavation to bedrock at analysis, the drawdown increases indefinitely with
elev. 66 m, SOwill be increased to 24-29 m. time at any distance. However, recharge may occur
In Fig. 14 are shown typical values of the draw- from vertical infiltration from precipitation or from
down ratio D(u) = s / S o plotted against the distance deep seepage and a steady state condition is eventu-
( x ) from the slope on a logarithmic scale for values of ally attained.
t = 32, 128, and 512 days and for M equal to 7.6 m.
In Fig. 15, for various values of M and for a distance Reclzarge Rate and Injiltration
( x ) equal to 15 m, the typical variation in D(u) with In a few locations, the water levels in boreholes on
DEBIDIN AND LEE
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

FIG. 14. Drawdown ratio (D(ri))vs. distance (x) from the slope.
For personal use only.

the site in summer are about 6 m higher than those (iii) For an average radius of influence in the test
observed in winter. Generally, however, the fluctua- excavation of about 200 m and a pumping rate of
tion is much smaller, about 0.6 m. These changes about 46 m3/day, the recharge rate is estimated to
reflect the effect of recharge from precipitation, which be 3.6 X 10-%/day. Erom the above ranges a
is estimated below. value of R = 4.5 X m/day is conservatively
(i) Singer (1974) considers that the flow region assumed for the site.
extends to about 15 m below the bedrock surface. In Effects of Recharge
the analysis discussed herein, the effect of the seepage The effects of recharge are assumed to be negligible
in the bedrock is neglected because of the low per- when the quantity of seepage (Q) from a slope is
meability of the rock mass. Singer estimates from relatively high. The quantity decreases in time and a
base flow analyses that the recharge rate (R) for the steady state position is reached, when, for a unit
Bowmanville Creek area (immediately east of the width of slope :
site) is about 9.55 in./year or 6.7 X m/day. For
an annual precipitation of about 825 rnm, the re- [lo] RL = Q
charge from infiltration is about 30%. A value of where L is the recharge section or the distance from
23% is estimated for the area further east of the site. the slope to the zero drawdown point for the elapsed
(ii) Borehole water levels are plotted in Fig. 16 time.
against the distance (x) from the shoreline on the Both RL/So and Q/So are straight lines when
logarithmic scale. An approximate position for the plotted on log-log paper against time ( t ) and this
water table may be obtained from the drawdown provides a convenient means of estimating the time
form for a subsurface drain or a channel given by to steady state (t,). The procedure is shown in Fig. 17
Maasland (1959) or by Ferris et al. (1962): for M = 7.6 m and Sobetween 6 and 24 m.
For the assumed value of R, the time for steady
state (t,) for values of M between 3 and 10 m are
where h is the water surface height above lake level; shown in Fig. 18. The following points may be noted.
R is the recharge rate; k and M are the permeability 1. The time to steady state is proportional to the
and thickness of the draining strata; and a is the drawdown at the slope.
distance to a position where the water table is as- 2. The time to steady state is maximum for M
sumed horizontal. For a range of a = 300-610, R is equal to about 7.6 m and is slightly lower for smaller
estimated to vary between 1.5 X lo-* and 4.5 X lo-* and larger values of M. No explanation could be
m/day. found for this variation.
CAN. GEOTECH. J. VOL. 17, 1980
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15
For personal use only.

-'?
5 a2

a"
$ OA

B2 "
Q.0

1.0

10 m loo0
(b)
TIME - DAYS
FIG. 15. (a) Drawdown ratio (s/So)for x = 15 m vs. time. (b) Drawdown ratio (s/So)for x = 30 m vs. time.
DEBIDIN AND LEE

ESTIMATED STEADY SEEPAGE


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15
For personal use only.

DISTANCE ( x ) FROM SHORELINE ( m )


FIG. 16. Borehole water levels vs. distance from shoreline.

I
3. The time for steady state for So = 18 m and meability of the soil strata and the associated water
M = 7.6 m is about 120 days. These values of Soand table recession rate is assumed to be rapid enough
M are approximately the average values for the not to have any effect, except locally or after a heavy
existing water table and shoreline conditions and, rainfall, on the drawdown. This assumption is justi-
from [S], the quantity of seepage is estimated at fied by the small general variation in borehole water
164 L per metre width per day. levels over several seasons and the fluctuations
Singer (1974) estimates the range to be 2.11-7.74 around the test excavation.
L/s per kilometre (0.12-0.44 cfs per mile) length of Polubarinova-Kochina (1962) gives an alternative
shoreline or 180-670 L per metre width per day, with approximate solution for drawdown with constant
the higher values in summer and fall. vertical recharge for a horizontal drain. For uncon-
4. Based on the time to steady stqte (2,) of about fined flow:
120 days, the water table position is estimated by
means of [3]and [4] for So = 18 m and M = 7.6 m.
The estimated position shown in Fig. 16 is generally
close to the upper limit of the measured borehole where
water levels.
5. Also shown in Fig. 18 are the data for the test [12] a = 6 R / S H
excavation for which S; = 7.6 m and M = 5 m. The and where R = recharge rate; S = drainable por-
estimated number of days to equilibrium is 42, which osity; L1 = distance from the slope to zero draw-
may be compared with the period of about 38 days down after time t ; and H = the drawdown at the
during which the excavation was in progress. slope.
The transient drawdown rate in the slope given by The length Lt tends to a limit LF for large values of
[6]does not include the effect of recharge from verti- t given by
cal flow. The equivalent average recharge rate of
4.5 X m/da; is smaller than the average per- [I31 LF = H ( ~ / ~ R ) ' / z
CAN. GEOTECH. J. VOL. 17, 1980
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15
For personal use only.

FIG. 17. Determination of steady state time (1,).

For a practical value of Lt of about 90% of LF, it exit cannot be ignored since it will result in an actual
may be shown that the term at in [Ill and [I21 will exit point higher than that given by [14], which, in
give a linear relationship between t and H. This turn, will influence the position of the drawdown
result confirms the linear relationship given in Fig. surface.
18, particularly for a value of Lt = 0.85L~.
Also, for the existing water table, LF calculated by
[13] for H = 18.3 m is about 310 m, which may be Application to Design and Construction
compared. with about 370 m obtained from Fig. 14 The methods described above were used in deter-
for a drawdown period of about 128 days. mining the drawdown and seepage in the main ex-
cavation to establish the background for stability
Exit Conditions analysis, construction planning, slope protection,
At the surface of the slope, the exit point and sur- and drainage requirements.
face of seepage may be determined by [I41 due to In considering the groundwater problems in the
Kashef (1969): main works, the test excavation has shown that the
kD cot B groundwater table may be lowered by deep ditches
[14] - =
in advance of excavation. Erosion of the silts and fine
Q 1-Qsin2B
sand by seepage is a major problem, which will
where D is the height of the exit point above the toe necessitate special attention to the surface protection
of the slope; Q is the quantity of flow at steady state; treatment. The fine sand, even after drainage, still
and B is the slope angle in degrees. retains a large percentage of moisture and the
The presence of an impervious stratum within the trafficability of the material will be generally poor.
DEBIDIN AND LEE
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15
For personal use only.

FIG. 18. Time to steady state vs. drawdown at slope.

The steady state condition attained by the water with the observations. The effect of recharge from
surface is dependent on recharge from infiltration vertical flow must be taken into account in evaluating
and deep seepage. The drawdown caused by the the data and in determining the effects of excavation
excavation is unlikely to extend more than about below the water table. The approximate methods of
400 m from the slope when the excavation below the analyses are outlined to indicate the main parameters
water table is about 22 m deep. to be considered. In transient drawdown studies the
specific yield or drainable porosity is an important
Summary and Conclusions parameter, which should be determined by field tests.
A test excavation has proved useful for determin- In the fine sand strata, a specific yield of 0.015 ap-
ing the drawdown and seepage characteristics in semi- pears to give acceptable results for the conditions at
confined fine sand deposits in conditions in which the site considered.
conventional pumped wells may be of limited use- At the time of writing, the main excavation is in
fulness. progress above the water table. Deep ditches at select
The analyses of the data by the finite element locations are planned as part of the groundwater
method and by the theory of aquifer tests produce control as the excavation continues. It is intended to
approximate results, which are generally compatible observe the groundwater response and to compare
202 CAN. GEOTECH. 3. VOL. 17. 1980

the results with those obtained from the analyses elements, interim report on trial excavation. Ontario Hydro
presented. Research Division, Toronto, Ont., Report No. 76-449-K,
p. 32.
Acknowledgments 1977. Darlington GS-powerhouse and forebay ex-
cavation, seepage study by finite elements. Ontario Hydro
This paper is published with the permission of the Research Division, Toronto, Ont., Report No. 76-508-K,
Director, Design and Development Division, Ontario p. 25.
Hydro. The authors are indebted to several of their MAASLAND, M. 1959. Water table fluctuations induced by
intermittent recharge. Journal of Geophysical Research,
colleagues for assistance and helpful discussion in the 64(5), pp. 549-559.
preparation of the paper and to Mr. J. I. Adams, MANSUR,C. I., and KAUFMAN, R . I. 1962. Dewatering. 112
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Otago on 07/05/15

Manager, Geotechnical Engineering Department, for Foundation engineering. Edited by G . A. Leonards. McGraw-
his encouragement and critical review. Hill Book Company, New York, NY, Chapter 3, p. 303.
MOODY,W. T. 1962. Unsteady flow of groundwater into a
surface reservoir: Discussion.Transactions of the American
DESAI,C. S., and ABEL,J. F. 1972. Introduction to the finite Society of Civil Engineers, 127(Part I), pp. 417-420.
element method. John Wiley & Sons, Inc., New York, NY. PETERSON, D. F. 1957. Hydraulics of wells. Transactions of the
FERRIS,J. G., KNOWLES, D. B., BROWN,R. H., and STALLMAN, American Society of Civil Engineers, 122, pp. 502-512.
R. W. 1962. Geological Water Supply Paper 1536-E. U.S. POLUBARINOVA-KOCHINA, P. Y. 1962. Theory of groundwater
Govt. Printing Office, Washington, DC. movement. Princeton University Press, Princeton, NJ.
FRANCE, P. W., PAREKH, C. J., PETERS,J. C., and TAYLOR, C. (Trc2tlslatedby J. M. R. De Wiest.)
1971. Numerical analysis of free surface seepage problems. SHEIKOV,M. L., and ZEL-BRANDT, V. A. 1964. A practical
ASCE Journal of the Irrigation and Drainage Division, method of calculating the flow of water into a foundation
97(IR1), pp. 165-179. pit through a multilayered soil. Soil Mechanics and Founda-
HANTUSH, M. S. 1956. Analysis of data from pumping tests in tion Engineering (USSR), J(Sept.-Oct.), pp. 319-323.
leaky aquifers. Transactions, American Geophysical Union, (Translated from Russian, Consultants Bureau, New York,
37(6), pp. 702-714. NY.)
1962. Drawdown around a partially penetrating well. SINGER,S. N. 1974. A hydrogeological study along the north
For personal use only.

Transactions of the American Society of Civil Engineers, shore of Lake Ontario in the Bowmanville-Newcastle area.
127(Part I), pp. 268-283. Ministry of Environment, Toronto, Ont., Water Resources
JENAB,S. A., BISHOP,A. A., and PETERSON,D. E. 1969. Report 5d.
Transient functions for land drainage. ASCE Journal of the STRELTSOVA, T. D. 1975. Unsteady unconfined flow into a
Irrigation and Drainage Division, (95)(IR3), pp. 361-373. surface reservoir. Journal of Hydrology, 27(1/2), pp. 95-110.
KASHEF,A. 1. 1969. Seepage towards highway cuts. ASCE ZIENKIEWICZ, 0. C. 1971. The finite element method in
Transportation Engineering Journal, 95(TE4), pp. 667-680. engineering science. McGraw-Hill Book Co., London,
LEE, C. F. 1976. Darlington GS-seepage study by finite England.

You might also like