You are on page 1of 8

CI/SfB 68.

6
March 1998

dıgest Protecting buildings


against lightning
Digest
428

The average number of days A lightning protection system lightning. It describes the
each year during which (LPS) for any structure must principles of designing LPS
thunderstorms may occur be considered to be a for new and existing
across the UK is between 5 sensible precaution, but its buildings. However, as stated
and 20. This figure can installation is particularly in BS 6651, even where an
double over an 11-year important where there is a LPS is provided, it can never
period due to the sunspot clear risk to life, the structure be completely effective in
cycle. The number of or its contents are eliminating the risk of
lightning strikes to a square irreplaceable, or essential damage to a structure or its
kilometre of land each year in services could be affected. contents.
England and Wales ranges This Digest gives guidance on
from 0.1 to 0.6 depending on calculating the risk of a
geographical location. building being struck by

Courtesy of A N Wallis & Co Ltd


2
Lightning is an electrostatic discharge between for calculating the overall lightning strike risk
one cloud and another or between a cloud and factor for a building or structure. An ‘acceptable’
earth. It is estimated that cloud potential voltages risk factor is given as 10-5 per year, ie 1 in 100
can be as high as 100 MV prior to a discharge and 000 per year. So if the overall risk factor is more,
the peak current stroke can rise in approximately for example 10-4, ie 1 in 10 000, then protection is
10 µs to anything between 2 kA and 200 kA. necessary. Sometimes other issues may override
For this reason, electromagnetically generated a calculated low risk factor and a lightning
mechanical forces between adjacent conductive protection system will be installed, for example,
metalworks are extremely high so that an LPS at an explosives dump or in a small art gallery.
must be of robust design and secured with
substantial fixtures. Furthermore, the shock Calculating the overall risk factor
wave produced by such a current can damage the The overall risk factor is determined by:
structural parts of any building. ● Geographical location of a structure. This
Conversely, because each flash is of extremely determines the number of flashes to the ground
short duration, the thermal effects in conducting per km2 per year, that is, average lightning
materials are usually minimal. Obviously, fusing flash density (Ng). Ng can be assessed for
can occur if the wrong size materials are used and England/Wales and globally by using the maps
fire can result. in BS 6651 (Figures 1 and 3).
● Effective collection area (Ac) of a structure.
Sideflashing This is the plan area of a building opened out
Extremely high potential voltages are generated in all directions. So, for example, the taller the
in the metalwork of a structure when struck by building, the more likely it is to attract a strike.
lightning. These potentials vary throughout the
Ac = LW + 2LH + 2WH + πH2 (m2)
building and should the difference between
where L = length
adjacent metalwork be great, then there is a risk
W = width
of a flashover. This is called ‘sideflashing’ and if
H = height
it occurs, the lightning current can discharge to
service pipes, wiring, information technology The probable number of strikes per annum on the
equipment, communications, and along many structure:
other unintended paths to create extensive P = Ac × Ng × 10-6
damage, including risk of electric shock, fire due
to sparking and havoc to essential services. Weighting factors
Where sideflashing is considered to be a The probability, P, is multiplied by five
possibility, measures should be taken to either weighting factors to obtain the overall risk factor.
isolate the metalwork or to bond the metalwork The weighting factors take account of:
to the LPS (see also Down conductors, page 5). A Use of structure: the number of people using
Both have considerable implications and need the building, for example, a school, hospital,
consideration. office block or church
The design intention is that the lightning B Type of construction: for example, a thatched
current should be confined to the path provided or metal roof, or constructed of stone
by the LPS and so discharge itself safely to earth. C Contents or consequential effects: whether a
building is of historic or cultural importance
The risk to buildings of a lightning (museum, art gallery), or is a building where
essential public services are performed
strike (hospital, school, telephone exchange, power
The average number of days each year during station) or a building containing explosive or
which thunderstorms may occur across the UK is flammable materials
between 5 and 20. This figure can double over an D Degree of isolation: for example, a building on
11-year cycle due to the sunspot cycle. Figure 1 a flat plain or a tall building in a town
in BS 6651 gives the average number of strikes to exceeding at least twice the height of
each km2 of land annually in England and Wales. surrounding buildings
The probability of a strike to a building increases E Type of country: for example, flat or
when an LPS is installed so it is important to mountainous
ensure that the system effectively conducts the Zones of protection
lightning current safely to earth.
The need for protection A lightning conductor provides protection by
attracting lightning to itself. The zone of
Acceptable risk protection is the volume around the conductor
British Standard BS 6651 provides a procedure which is protected against a lightning strike. The
3

A sample calculation of overall risk factor Table 2 Weighting factor B (From BS 6651)
An old stone church in a village in Lincolnshire of Factor B
dimensions: Type of construction value
L = 20 m
W= 15 m Steel framed encased with any roof 0.2
H = 30 m other than metal*
Reinforced concrete with any roof 0.4
From Figure 1 in BS 6651, Ng = 0.6 flashes/km2/year other than metal
Steel framed encased or reinforced 0.8
Ac = (20 × 15) + 2 (20 × 30) + 2 (15 × 30) + 3.14
concrete with metal roof
× 302 m2
Brick, plain concrete or masonry with any 1.0
= 300 + 1200 + 900 + 2826 m2
roof other than metal or thatch
= 5226 m2
Timber framed or clad with any roof other 1.4
Probability of church being struck than metal or thatch
= Ac × Ng × 10-6 Brick, plain concrete, masonry, timber 1.7
= 5226 × 0.6 × 10-6 framed but with metal roofing
= 3.136 × 10-3 Any building with a thatched roof 2.0
* A structure of exposed metal which is continuous down to ground level is
Applying the weighting factors from Tables 1–5: excluded from the table as it requires no lightning protection except adequate
Factor A = 1.3 earthing arrangements.
Factor B = 1.0
Factor C = 1.7 Table 3 Weighting factor C (From BS 6651)
Factor D = 1.0 Contents or Factor C
Factor E = 0.3 consequential effects value

The overall weighting factor Ordinary domestic or office buildings, 0.3


= A×B×C×D×E factories and workshops not containing
= 0.663 valuable or specially susceptible contents
Industrial and agricultural buildings 0.8
The overall risk factor
with specially susceptible* contents
= Probability of being struck × overall weighting
Power stations, gas installations, 1.0
factor
= 3.136 × 10-3 × 0.663 telephone exchanges, radio stations
= 2.08 × 10-3 Key industrial plants, ancient monuments 1.3
and historic buildings, museums,
that is, greater than 10-5 and therefore an LPS is art galleries or other buildings with
recommended. specially valuable contents
Schools, hospitals, children’s and other 1.7
residential homes, places of assembly
* This means specially valuable plant or materials vulnerable to fire or its
results.

Table 1 Weighting factor A (From BS 6651) Table 4 Weighting factor D (From BS 6651)
Factor A Factor D
Use of structure value Degree of isolation value

Houses and other buildings 0.3 Structure located in a large area of 0.4
of comparable size structures or trees of the same or greater
Houses and other buildings of 0.7 height, eg in a large town or forest
comparable size with outside aerial Structure located in an area with few other 1.0
Factories, workshops and 1.0 structures or trees of similar height
laboratories Structure completely isolated or 2.0
Office blocks, hotels, blocks of flats 1.2 exceeding at least twice the height of
and other residential buildings surrounding structures or trees
other than those included below
Places of assembly, eg churches, 1.3
Table 5 Weighting factor E (From BS 6651)
halls, theatres, museums, exhibitions, Factor E
department stores, post offices, stations, Type of country value
airports and stadium structures
Schools, hospitals, children’s and 1.7 Flat country at any level 0.3
other residential homes Hill country 1.0
Mountain country between 300 m and 900 m 1.3
Mountain country above 900 m 1.7
4
volume and shape of the zone will determine the those involved in the design project team from
number and location of lightning conductors the beginning of the project. The lightning
needed to protect a structure. For structures less protection engineer must also ensure that the
than 20 m high and for vertical conductors, the principles are understood by the various
zone is defined as a cone, its apex being the top of contractors during installation.
a conductor and its base the ground. The
protection angle is that made between the side of Components of the LPS
the cone and the vertical at the apex (see Figure The LPS comprises the following networks:
2). To achieve an acceptable degree of ● air terminations network,
protection, the protection angle is recommended ● down conductors network (including joints
by BS 6651 to be 45°. (For horizontal lightning and bonds),
conductors, the zone of protection is the volume ● earth electrodes network (including test
generated by a cone with its apex on the joints),
conductor moved from end to end.) ● earth termination network.
For structures more than 20 m high, the
protection zone should be determined using a Initially, a survey of the building or relevant
rolling sphere where the zone of protection is that drawings should be undertaken to identify the
volume formed between the rolling sphere and metallic components in or on the structure that
the point where it touches the structure (Figure can be integrated into the LPS. For example, a
2). The smaller the radius of the sphere, the metal roof, metal window-cleaning rails, a steel
greater the protection but the greater the cost of frame or concrete reinforcing bars may be
installing the LPS. BS 6651 recommends a incorporated into the LPS design. Making use of
sphere of 60 m radius. the building construction metalwork may incur
Designing a lightning protection design time costs, but the benefits can be
considerable. However, it must be borne in mind
system (LPS) that if parts of the LPS are immediately beneath
General considerations the surface of the structure’s fabric, surface
Having established, by risk analysis, that a damage may result from a lightning strike.
building requires an LPS, it is important for the
lightning protection engineer to liaise with all Air terminations network
Lightning The air terminations network is provided
conductors on roof
primarily to intercept a lightning strike. No part
45 of a roof should be more than 5 m from an air
termination conductor. Typically, this will be
Zone of
protection achieved by a conductor mesh 10 m × 20 m for a
Up to
20 m
flat roof area.
Those metallic projections above the general
profile of a roof, for example, aerials and air-
conditioning units, should be connected to the air
termination network, unless they fall within the
protection zone of a higher protected part of the
structure.
Lightning
conductors on roof
Buildings and structures most likely to be hit
by lightning are those that project above their
surroundings, for example, chimneys, spires,
Additional flagpoles, aerials, towers, water tanks and
protection
needed railings.
Radius
Those parts of a building which project from,
of sphere or form sharp corners of, buildings or structures
100 m
are also likely to be struck, for example, the edge
of a roof.
Zone of Where reinforced concrete is used for down
protection
conductors the air termination network should be
connected to the reinforcing bars.

Down conductors network


The purpose of the down conductors system is to
Figure 2 Zones of protection: buildings 20 m high or provide a low impedance path from the air
less (top); principle of the rolling sphere for buildings termination network to the earth termination
over 20 m high (below) (from W J Furse & Co Ltd
5
network, in order to conduct the lightning strike 8d maximum Exceeding 8d

safely to the earth termination network.


Therefore, the down conductors should take,
where possible, the most direct route to the earth
termination network. Bends in the down
conductors should, if possible, be avoided (the
lightning current pulse will tend to straighten
them out!) as they generate a high self-inductive
voltage that may result in sideflashing. ‘Re-
entrant loops’ where unavoidable should be
designed as shown in Figures 3 and 4 as the high
inductive voltage can cause sideflashing and
structural damage. Down conductors should be d d
symmetrically placed around the periphery of the
structure, no more than 20 m apart, starting from Figure 3 Routing a down conductor to avoid
the corners. Where the building is more than 20 sideflashing: (left) this arrangement is permissible as
m high, the down conductors should be no more the sum of the length of the sides of the loop is less
than 10 m apart. than eight times the distance, d, across the open side
A separate down conductor system is not of the loop; (right) this arrangement presents a hazard
required on structures with steel frame or and is not permissible (from BS 6651)
reinforced concrete construction. All structural
metal, for example, pipes, stanchions, etc. should
be interconnected, that is bonded, so that it
participates in the lightning discharge to the earth
Not permissible
termination.
Permissible
The design of a down conductor system
should, in all instances, take into consideration
the need to minimise the probability of
sideflashing.

Joints and bonds


Joints are subject to failure and therefore should
be kept to a minimum. Dissimilar metals in
contact will promote corrosion and should be
avoided. For example, if aluminium and copper
are connected, a moisture-inhibiting paste should Figure 4 Routing a down conductor to avoid
be applied around the joints. sideflashing: where there are cantilevered upper floors
Any metalwork inside a structure and in the down conductor should be routed down the side of
contact, directly or indirectly, with earth, must be the building and not into the recess (from BS 6651)
either bonded to the LPS or adequately isolated
from it. BS 6651 provides a graphical method to
establish the minimum isolation distance
required to prevent sideflashing, but it should be
noted that this is only applicable to the isolation
distance through air.
Bonding the LPS to the main earthing terminal
is essential and is recommended not only in BS
6651, but also in BS 7671 and BS 7430.

Earth electrodes network


The purpose of the earth electrodes is to provide
a consistent quality connection to the general
mass of earth during all seasonal conditions. The
proper function of the earth electrode is therefore
very dependent on the nature of the soil. Indeed,
it is important to conduct soil resistivity tests, as
described in BS 7430, in order to select the
appropriate earth electrode system.
6
Soil resistivity Ground level

Ideally, the value of soil resistivity should be low. Inspection pit


The conditions which contribute to the soil
resistivity are: Earth rod
● moisture content,
● chemical composition, L
Coupling
● temperature of the soil.

To achieve a low resistance electrode system, a


wet marshy soil would be ideal. In practice, all
Not less than L
that can be done is to attempt to influence the
immediate surroundings of the earth electrode.
Because of its corrosive nature, salt should
never be added to the area immediately around Figure 5 Spacing of rod electrodes in parallel
the electrode. Other added conducting materials (from W J Furse & Co Ltd 1992)
can suffer with migration and leaching from the
soil over a period of time. The installation will A foundation metal structure buried in the
require regular inspection and, if the conducting ground, for example, a reinforced concrete pile,
material is required to be removed and replaced, can form a most effective earthing system
maintenance will be costly. provided there is electrical continuity between
However, where locations demand such the structural metalwork and the foundation pile.
treatment, the area around the electrodes can be Metallic water pipes, perhaps with plastics joints,
replaced with lower resistivity material, for cannot be considered to provide a reliable earth.
example:
● bentonite which retains and absorbs moisture, Test joints
● concrete, A test link should be connected between each
● concrete with a conductive additive. down conductor and its earth electrode. This is
removed to measure the resistance of the
The deeper the installation the better as this has electrode to earth.
the advantage that its electrical resistance will be
less affected by seasonal fluctuations in Earth termination network
temperature and moisture. Moreover, where the Where the installation of earth electrodes does
installation comprises horizontal conductors, not achieve a sufficiently low ohmic value, the
they will be less likely to be affected by various electrodes should be interconnected by a
kinds of ground work in close proximity. conductor installed at least 0.5 m beneath ground
level. The interconnections should follow the
Types of earth electrode periphery of the building and are referred to as
The electrodes can form a combination of metal ‘ring earths’.
rods, tubes, strips, plates or a combination of A ring-earth arrangement is an important part
these, and indigenous earths such as piles or of the earth connection system, offering many
foundations can be most effective. advantages and should be considered for all LPS
Ideally, rod electrodes should be spaced apart installations. One advantage is that the ring earth
at distances greater than their depth (Figure 5). If can be extended and used to reduce the voltage
it is not possible to drive the rod deep into the gradient at the surface of the ground, making the
ground, several shorter rods could be installed, area safer for personnel.
each connected to its adjacent rod by horizontal
conductors. If there is bedrock just below the soil Corrosion protection
and driving electrodes into the ground is not Because of corrosion, particularly in wet
feasible, a horizontal strip electrode can be used conditions, the conductors, connecting the down-
and will have to be laid radially, preferably in all conductors to the earth-electrodes, should be
directions, and about 1 m deep. Alternatively, protected by a PVC sleeve for a distance of 0.3 m
horizontal solid plates or mats can be used but above and below ground.
their installation can be more expensive and For the same reasons, aluminium must not be
time-consuming. buried underground or placed in contact with
cement or mortar mixes.
7

Inspection, testing, maintenance Construction sites


and records From the commencement of the installation of an
Inspection LPS, it must be connected to earth at all times
The LPS should be inspected every 12 months by (see BS 6651).
a competent person. Furthermore, if it is known All large and prominent steel structures, such
that the LPS has been hit by lightning, it should as cranes, scaffolding, etc, should be earthed as
be inspected as soon after the event as possible. they are erected (see BS 7430).
The LPS should be mechanically robust, free
of corrosion and compliant with the Electronic systems protection
recommendations made in BS 6651.
A visual inspection would include: The proliferation of information technology
● signs of damage to the LPS conductors, equipment (ITE) in buildings of all kinds makes
● physical condition of fixtures, clamps and it advisable to consider providing special
system components, protection for ITE against damage from a
● signs of corrosion, particularly at joints, lightning strike. Communications networks
● sample condition of the underground earth- interconnecting buildings are particularly
termination system, susceptible to damage from remote lightning.
● modifications to the LPS since the last check. Running external cables underground,
combined with a well-designed LPS for the
Testing structure, will often provide adequate protection
There are two electrical resistance tests to for electronic systems. Additional protection can
conduct and record. be obtained by fitting surge protection devices
● First, the resistance of each earth electrode (SPDs) to cables at their point of entry to
should be measured in isolation by removing buildings.
the test link and ring-earth interconnecting Appendix C of BS 6651 provides guidance on
conductors. The resistance measurement protecting electronic equipment against
(ohms) should not be more than 10 times the lightning, including risk assessment and the
number of earth electrodes provided, so that criteria for selecting suitable SPDs.
the combined resistance to earth does not
exceed 10 ohms.
● Second, the test link should be restored and the
resistance of the LPS system measured at any
point, but with the bonding to other services
disconnected. The reading should not be more
than 10 ohms.

Safety warning!
Any testing conducted on an earth system must be
undertaken by a competent person as under certain
circumstances the system can become live.

The recommended method of testing for


resistance values is outlined in BS 7430.

Maintenance
Any deficiencies found during any inspection
should be repaired, renewed or redesigned.

Records
It is prudent to keep adequate records, for
example, for safety purposes should an incident
or accident happen or, perhaps, for the purpose of
trend analysis of test data. The records should
include:
● all LPS drawings,
● details of soil tests, if any,
● all test results,
● all details of maintenance undertaken.
8

Acknowledgements List of abbreviations and terms


BRE wishes to thank J P Whiting, MSc, CEng, Ac Effective collection area of a structure (the
FIEE, for his technical assistance with the plan area of a building opened out in all
drafting of this Digest. directions)
Tables and figures from BS 6651: 1992 Code BS British Standard
of practice for protection of structures against H Height
lightning are reproduced with the permission of ITE Information technology equipment
BSI. Complete editions of BS 6651 and all other L Length
Standards can be obtained by post from BSI LPS Lightning protection system
Customer Services, 389 Chiswick High Road, Ng Average lightning flash density
London W4 4AL. P Probability
SPD Surge protection device
W Width
Further reading
Allen N L. The protection of churches against lightning.
SI units
London, Council for the Care of Churches; 1988, 15 pp.
CIBSE. How to strike back. Journal of the Chartered A ampere Electrical current
Institution of Building Services, March 1985, 34–38. m metre Length
Furse & Co. Earthing and lightning protection: s second Time
consultants handbook. Nottingham, W J Furse; 1992,
V volt Electric potential, potential
55 pp.
difference, tension,
Furse & Co. Electronic systems protection handbook: a
guide to protecting electronic equipment from lightning electromotive force
and transient overvoltages. Nottingham, W J Furse;
1995, 108 pp. SI prefixes
Johansson M. Lightning protection of buildings and their
contents—a review of current practice. Technical Note M mega 106 1 000 000
TN 1/94. Bracknell, Berkshire, BSRIA; 1994. k kilo 103 1000
Summers M. Lightning protection the natural way. m milli 10-3 0.001
CIBSE J, July 1994, Vol 16 , No 7, 45–46.
µ micro 10-6 0.000001
Woods P. BS 6651: providing calm before the storm.
CIBSE J, January 1993, Vol 15, No 1, 41–42.

Building Research Establishment


Other BRE Digests
335 Electrical interference in buildings
424 Installing BMS to meet electromagnetic
compatibility requirements

British Standards Institution


BS 6651: 1992 Code of practice for protection of
structures against lightning
BS 7430: 1991 Code of practice for earthing
BS 7671: 1992 Requirements for electrical installations

Technical enquiries to: Digests Construction Research Full details of all recent issues Published by Applications to copy all or any
BRE Advisory Service Good Building Guides Communications Ltd, of BRE publications are given Construction Research part of this publication should
Garston, Watford, Good Repair Guides 151 Rosebery Avenue in BRE News, sent free to Communications Ltd by be made to Construction
WD2 7JR Information Papers London, EC1R 4QX. E-mail: subscribers. permission of Building Research Communications
Telephone 01923 664664 are available on subscription. crc@construct.emap.co.uk Research Establishment Ltd Ltd,
Facsimile 01923 664098 For current prices please Telephone 0171 505 6622 © Copyright BRE 1998 PO Box 202, Watford,
contact: Facsimile 0171 505 6606 ISBN 1 86081 130 2 Herts, WD2 7QG

You might also like