You are on page 1of 7

)

Unique Geotechnical Problems at Some


Hydroelectric Projects
Donald U. Deere!

SYNOPSIS

The experiences so well reported by the Norwegian authors


of both good and bad performances ·of unlined pressure
tunnels, and the recent failures reported here in of
several pressure tunnels in soft rock lined with plain
concrete, all point to the difficulty of the problem.
Conventional rules-of-thumb have been found wanting. A
conservative approach in design is warranted; the cost
in time and money of repairing a failed pressure tunnel
is much greater than the cost of providing initially at
the downstream end additional lengths of reinforced con-
crete transition section and steel lining. A modified
rule-of-thumb is given for the preliminary layout of
these sections. The lengths should be checked later for
appropriatenes~ by hydraulic splitting tests across rock
joints, conducted either in test adits or in the excava-
ted pressure tunnel. The filling of a pressure tunnel
should be slow and by steps, preferably over a period of
15 to 20 days, so that external water levels can build
up. Periodic measurements should be made of water losses
and of changes in the piezometric levels in borings along
the tunnel line.

INTRODUCTION

Hydroelectric projects contain several elements which


impose severe requirements of performance on the founda-
tion medium. These may include high dams, underground
powerhouses, and pressure tunnels. Where geological

(ll Consultant, Engineering Geology and Applied Rock


Mechanics, Gainesville, Florida; Adjunct Professor,
Department of C~vil Engineering, Univ. of Florida.

865
') ')
Seventh Panamerican Conference Deere

6 = average inclination of the valley side, types like certain lavas, sandstones and limestones, or
H = static water head at point in question (m), in very blocky and seamy rock."

y
r
= density of the rock mass. Broch (1982a) notes that where abnormal tectonic stresses
are expected, control tests of the in-situ stress are oc-
It is possible alsa to express the equation as follows: easionally made during construction. Also, adversely ori-
ented joints have been tested in boreholes for hydraulic
H splitting to see if sufficient stress exists across them
Z > (2)
2 to resist the full internal water pressure witha factor
'fr ·cos 6 of safety of 1.2. Bergh-Christensen and Kj~lberg (1982)
deseribe the studies for a new 1130-m long 45°-inclined
where Z = vertical rock cover (m). pressure shaft with a static head of 980 m to be built
soon for an aluminum plant in Norway. An unlined shaft is
Actually, the new rule-of-thumb Equation (1) results in eontemplated on the basis of FEM results already obtained.
about the same answer as the original one, except for The first phase of construction will be a pilot adit to
slopes steeper than 50° where it gives a more conserva- the base of the shaft so that in-situ stres s measurements
tive value. and hydraulic fracturing tests can be made. If adverse
results are obtained, time is available in the schedule
Since 1972 the Norwegian unlined pressure shafts have to allow a steel lining to be placed in the lower part of
been sited with the aid of computerized FEM analysis of the shaft.
the in-situ stress conditions. The concept is based on
locating the pressure tunnel or shaft so that at every The Norwegian experience ean be summed up, perhaps, by the
point the in-situ minor principal stress in the surround- following coneluding remarks from Buen and Palmstr~m
ing rock mass exceeds the internal water pressure thus (1982), "The solution with unlined pressure shafts and
avoiding hydraulic splitting (Broch, 1982a). The analy- tunnels is both cost- and time-saving. Unexpected ad-
sis uses a plane strain, two-dimensional model with both verse geological conditions have, however, in the past
gravitational and tectonic stresses. The results, of been the cause of extensive repairs and loss in produc-
course, are dependent on the assumed stress conditions tion in several hydro power schemes. This proves the
and Poissons ratio. In the two cases examined by the neeessity of thorough planning and control during all
writer for slopes of 40° (Broch, 1982a) and 25° (Buen and phases of construction."
Palmstr~m, 1982), factors of safety of 1.2 and 1.4 were
used, respectively. For both cases, the determined posi-
tion corresponded quite closely to Z = (0.60-0.65) H, the
old rule-of-thumb location. HYDROFRACTURING POTENTIAL IN WEATHERED & DE-STRES SED ROCKS

The Norwegian authors in their papers have emphasized The potential for hydrofracturing is increased in areas
that rock conditions must be quite good to apply their of steep, irregular topography where erosion and asso-
criteria--i.e., hard, massive rock with moderate in-situ ciated lateral strain relief have reduced the in-situ
stress; absence of open or partially filled joints paral- horizontal stresses. Joints have been opened and addi-
lel to slope; and general lack of faults and shear zones. tional joints have formed. Weathering has proceeded
High pressure grouting of all potential leakage zones along the joints which results in even further de-
with pressures slightly above the future static pressure stressing. A rock mass is formed which has both a lower
is recommended. A regular, continuous side slope is alsa in-situ rock modulus and a lower horizontal in-situ stress
favored. Selmer-Olsen (1970) pointed out that the effects (or, more correctly, a lower minimum principal stress)
of erratic topography--protruding "noses" between gorges, than deeper within the mountain.
tributary valleys, or irregular curves of the main
3tream--reduce the horizontal stresses. For these condi- Recently, in the U.S.A. hydrofracturing tests were made
tions the pressure tunnel or shaft should be placed at in boreholes at depths of 100-200 m at the site of a l2-m
deeper levels than normal. He alsa notes that all clay- diameter pressure tunnel located in an elongated mesa or
filled weak zones should be sealed with a concrete lining ridge nose. Minimum in-situ stress of only 0.4 to 0.6
and grouted. He further states, "It seems hazardous to times the vertical overburden stress were obtained in
place an unlined pressure shaft in typical porous rock
870 871
) )
Deere
Sevenılı Pan« lcan Conjerence

index of about 0.6 H (steel) and about 1.0 H (reinforced ~ghtly Permeable Linings
concrete transition). The lining that best fits this category is the one of
reinforced concrete. The amount of reinforcing can range
Where the above conditions are met, the leakage from the from about 0.25% of the area of the concrete to 0.75% or
steel lining should be zero and from the reinforced con- more. In the normal design, the reinforcing steel takes
crete lining it should be very small, and insufficient very little of the tensile load. Its purpose is to dis-
both in volume and pressure to cause hydraulic fracturing. tribute the cracks--the higher the steel percentage, the
Problems of leakage could still develop deeper in the greater the number of cracks and the thinner the cracks.
mountain beyond the potential hydrofracturing zone depend- crack widths are limited in the design to 0.3 mm.
ing on the rock permeability and the relative positions
of the internal water head and the existing groundwater The sum of all the cracks equals the total change in cir-
levels. Where a lining is used, an additional factor is cumference. This is a result of compression of the rock
the modulus of the rock mass and the number and size of and is a function of the rock modulus and the difference
any induced cracks in the lining. The following section in internal and external water pressures. Moduli values
presents a brief review of pressure tunnel linings. for design should include the disturbed rock zone sur-
rounding the first 0.5-1.5 m of the opening, plus the
deeper, undisturbed rock zone--both zones with somewhat
improved modulus due to grouting.
TYPES OF TUNNEL LININGS
For practieality in placing the concrete and for assuring
Impermeable Linings sufficient covering of the reinforcing bars, the rein-
The only common impermeable lining is the one of welded foreing is placed about 10-15 em from the formed free-
steel. It is universally used to connect the turbines to face. A single row of reinforcing mat is much preferred
the lower end of the pressure tunnel, part, as a free- to a double row. Concrete placement and vibration is
standing penstock pipe and, part, as the concrete- more difficult with a double row of reinforcement; poor
backfilled steel tunnel lining. The steel liner is concrete with rock pockets or honeycombs can result.
designed for full design internal head (static plus Water seeping from rock joints must be handled in plastic
dynamic) without assuming rock restraint for the outer pipes, appropriately sealed to prevent washing out the
few tens to few hundreds of meters, for instance, to the sand and cement from the fresh concrete. Other important
point where Z = 0.40 H and the horizontal cover equals details include the type of concrete joints. These may
1.2 H (American Iron and Steel Institute and Steel Fabri- be formed vertical joints with the steel passing through
cators Assoc., Ine., 1981). The steel liner for the the joints, or formed vertical joints without the rein-
remainder of its length is designed on the basis of load- foreing steel passing through but with plastic, de form-
sharing with the rock in accordance with its modulus. r able waterstops. Alternatively, the joints may be un-
formed sloping joints with continuous steel.
Steel linings are also used at any place along the tunnel
line where the rock cover is low (e.g., less than 0.5 H) Faulty joints and honeycombed areas will be remedied in
or where absolute water tightness is required. part by the contact and consolidation grouting but
repairs with epoxy mortar are-also advisable. Even
Impermeable linings have occasionally been constructed though these repairs are ma de and the finished conerete
with flexible, multi-pli, plastic-steel mesh membranes lining is made essentially water tight, the first filling
held in place against the rock with poured concrete. with the pressurized water will cause the tunnel to ex-
Also, to a somewhat greater extent, prestressed rein- pand and numerous, thin, distributed cracks will occur,
forced concrete linings have been used, as well as plain oriented in a longitudinal direction. A certain amount
concrete lining post-tensioned by special grouting of water will escape--thus the elassification of
(Swanson, 1981). These latter types have been used "slightly permeable" lining. However, in most cases the
mostly in Austria, in Italy, and in Switzerland. quantity would not be sufficient to cause hydrofracturing
of the rock--and if it did, the quantity of outflow would
still be small.

874 875
) ")
Seventh Panamerican Centerence
Deere

rock permeability. However, even low permeability rocks


case History 1
can sustain high leakage rates if the in-situ stress con-
ditions allow hydrofracturing or hydraulic splitting. partial filling of the tunnel was done by pumping over a
period of 3 day s which achieved a hydraulic head of 17 m
In the following section some case histories are examined. at the lower end of the tunnel. The intake shaft gate
was then opened and full reservoir pressure was achieved
in a matter of 2 hours. This increased the head at the
lower end to 58 m which was maintained for the next 10
CASE HISTORY EXPERIENCES dayS. Soon af ter the rapid pressure increase, numerous
surface springs were noted near the penstock slope.
In the past 5 years there have been several failures in Their number and their flow increased over the next few
Latin America of pressure tunnels during first filling. days from 10 to 80 liters/see (1270 gpm). The ground
The writer had the opportunity of studying the causes of saturation caused a landslide which blocked the access
the failures and of helping in planning the remedial road to the powerhouse; a decision was made 2 days later
measures together with other consultants. In several to unwater the tunnel for inspection and possible repairs.
instances he entered the tunnels within 24 hours of the
failure. The pressure tunnel is 6.7 km long and is lined with plain
concrete of SO-cm minimum thickness to a circular section
The majority of the failures took place in weak volcanic of S-m diameter. The last 170 m of the tunnel, connecting
rocks, notably low density tuff, tuffaceous breccia, and the surge tank to the surface penstock, is steel lined.
altered, blocky lava. On8 case involved sedimentary ASO-m long transition section of reinforced concrete
rocks, shale and sandstone, with numerous, weathered i
extends upstream of the surge tank. The remainder of the
shear zones. The projects were designed by experienced tunnel is of unreinforced concrete except 100 m at the
international design firms using their normal procedures. 1: intake end and 315 m near the center where the tunnel
There were no connections among the projects and each passes beneath a depression.
project was in a different country, designed by a sep-
arate firm. The inspection revealed noticeable cracking of the SO-m
long reinforced concrete section upstream of the surge
The first two cases involve volcanic rocks and failures tank. A total of 13 distributed cracks were noted, a
of the plain concrete linings by severe cracking of the little more than hairline in width but probably less
water under pressure. Af ter the tunnels were unwatered, than 0.5 mm. By contrast, the adjacent plain concrete
some of the cracks were seen to contain leaves and smaIl section had two enormous cracks--one at the top and one
pieces of wood branches that were tightly held, indicating at the bottom with widths ranging from 10 mm to 20 mm but
that the cracks had closed somewhat as the tunnel was occasionally as wide as 50 mm. They ran continuously
unwatered. down the tunnel for 600 m and then discontinuously for
.another 200 m. The next kilometer of lining had cracking
The other two cases involve horizontal displacements of but much less serious and with intermediate and horizon-
20 to 30 mm where enlarged portions of the tunnel were tal orientations.
reduced to the smaller-diameter steel penstock portion.
The displacement was caused by excessive horizontal de- The studyand repairs took nearly 8 months and consisted
formation of the weak rock because of its low modulus and of sinking a 71-m deep construction shaft of ll-m diam-
the very large horizontal thrust associated with the diam- eter and installing a steel liner through the worst
eter difference and the nearly 100 m of water head. The section for a length of 1 km. Only minor repairs and
horizontal displacement caused cracking of the reinforced additional grouting were carried out in adjacent areas.
concrete linings with failure of the longitudinal steel The tunnel was placed back in service and its performance
in tension, followed by escape of high-pressure water to is satisfaetory.
the surface and subsequent landsliding.
The rocks involved were voleanie, mostly blocky lava
with altered, soil-like joints, some interbedded tuff and
tuffaceous breccia; and a few layers of hard, more com-
pact lava. Seismic velocity values are estimated as less
than 2000 m/see in the blocky; altered lava and tuff
878
879
')
Deere
Seventh Panamerican Conference
original head. It was apparent that considerable water
poor, low modulus rock. This interesting phenomenon waS leaking out of the tunnel.
appears to be a result of the lesser restraint of the
low quality rock to the longitudinal shrinking. The 9-m A substantial part of the leakage was from a tuff area
spaced cracks were about twice as wide as the more near the downstream end, adjacent to the 680-m long sec-
closely spaced ones. Two areas of longitudinal cracks tion of steel liner. Following the unwatering, 70% of
up to 200 m long were alsa noted in the concrete fol- the back-flow water was from the last 3 km of the 12-km
ıowing construction and before filling. These were alsa tunnel; probably a similar percentage of the leakage also
caused by the thermal shrinkage, an unusual occurrence. occurred here.
Much of the lining was probably under tension with local
zones of incipient cracking. The studies and repairs took over 1 year. An additional
4.4 km of steel lining were added at the downstream sec-
As noted, the inspection revealed hundreds of new cracks tion; 760 m of heavily reinforced shotcrete were added
located throughout the tunnel, in the form of only ~ or over a cracked concrete section; and several kilometers
2 cracks located at the roof and along the floor where were_treated by cutting a groove along the cracks with a
the tunnel was closest to the surface. At greater diamond saw and filling with an ingenuous combination
depths, the cracks were at or near springline and occa- design of Waterplug, an elastic polysulphide Thorospan,
sionally diagonally (some following concrete weaknesses and sikadur. This made a flexible, watertight craek-
of sloping construction joints). These cracks were all filler which could endure the anticipated radial expan-
caused by the concrete displacement and compression of sions upon refillingo The repaired tunnel has been in
the low-modulus tunnel rock. Crack widths ranged from service for about a year with excellent results; leakage
0.2 mm to about 3 mm, much smaIler than in Case 1. is estimated as less than 20 liters/sec (300 gpm).
The rock s again were volcanic rocks--mostly tuff and tuff- The problem resulted from the presence of a low-density
breccia but some hard ignimbrites and lava. The cracks volcanic rock that had a lower than expected modulus,
in the lining in the hard rock zones were notably lesser further reduced by creep. The thermally-cracked concrete
and finer. Seismic velocities of the tuffs and tuff- contributed to the problem. Hydrofracturing probably
breccias were found in the comprehensive studies follow- contributed to the flow through the otherwise, moderately
ing the failure to be from 1800 to 2200 m/see, with occa- impermeable tuff and tuff-breccia. The problems could
sional low values of 1100-1400 m/see. Large-scale plate have been avoided by having a longer section of steel
jacking tests of 1 m2 bearing area, and with extensometer lining and reinforced concrete throughout. Also, a very
points at several depths, were carried out following the slow first filling would have helped reduce the leakage
failure. These were done both on the inplace lining, by allowing a recharge of the groundwater table before
with relieved sections, and on virgin ground. Values as high internal pressures were achieved.
low as 1,000-4,000 kg/cm2 were found for the first 1/2 m
of disturbed rock and values of 5,000-25,000 kg/cm2 for At the end of the original steel lining the Z/H ratio
the deeper rock. One interesting phenomenon was the ex- was 1.0, which is even better than the recommended 0.8.
tensive creep of the soft, tuff rock under sustained However, the recommended transition section of reinforced
load as shown in one test carried out over a 28-day concrete to the point of Z/H of 1.3 (about a 100-m length
period--a 40% decrease in the modulus in one week. in this case) was not provided; only plain concrete lin-
ing was placed. But in this case, because of the occur-
The original groundwater level was measured in 9 piezo- rence of very low-modulus tuff and tuff-breccia in long
me ters placed from the surface along the tunnel route. stretches of the tunnel, a reinforced concrete lining
Except at the downstream end the waterlevel was from 50 m for much of the tunnel would have been beneficial.
to 100 m above the tunnel, about equal or higher than the
future hydraulic pressure. However, the readings showed Case History 3
that the water levels dropped to tunnel grade during the
construction period. With the placement of the concrete Both Case Histories 3 and 4 involve low modulus rocks and
lining and the extensive grouting (contact and consolida- large hydraulic thrusts which caused horizontal displace-
tion) several of the piezometers showed rises of a few ments and rupture of the reinforced concrete linings near
meters to 20 m. During filling, the piezometers reacted, their junctures with the steel linings.
rising slowly but erratically but not achieving the
883
882
'\
")
Oeere
Seıienth Pa, .erican Conference
The first filling of the pressure tunnel should be done
They work well where rock conditions and in-situ stress sıowly, in steps, in a controlled manner over a period of
conditions are favorable; where the contrary is true, 15 to 20 days. The water level at each step should be
the performance of the pressure tunnel can be unsatis- hel constant for 1 to 2 days while leakage measurements
factory. d
and piezometer reading s are made. A slow build-up of
external pressure during the early stages will help
The problem is related both to the in-situ stres s condi-
reduce the losses at the later stages.
tions and to low modulus values of the rock mass.
Greater emphasis will have to be given in the design in conclusion, to design, build, and opera te successfully
studies to investigating both these aspects. Hydro- pressure tunnels and shafts in what are of ten hostile
fracturing (hydro-splitting) tests should be made in the
environments, a greater amount of effort and cost in
exploratory borings from the surface and in exploratory exploration, design, and probably in construction will
adits. Proof tests of the hydraulic splitting pressure have to be expended. This is the challenge to the geo-
across joints should be made along the excavated tunnel. technical and hydro engineers both of this generation and
In-situ modulus tests of large scale should be carried
out in critical areas including 2-week creep tests, the following.
together with more numerous indexing tests along the tun-
nel walls for correlating with the modulus by means of
dilatometers, ultrasonic velocity determinations, and
closely spaced seismic refraction studies. REFERENCES
American Iron & Steel Inst. & steel Plate FabricatorsAsso.
The writer believes that these tests, when done in criti- Ine. (1981). Steel penstocks and tunnel liners.
cal areas of rock cover or of poor quality rock, will
steel plate Engineering Data, Vol. 4.
lead to more conservative and more realistic lengths of
steel lining and reinforced concrete. A modified rule- Bergh-Christensen, J. and Dannevig, N.T. (1971).
of-thumb for preliminary layout has been suggested which ıngeni~rgeologiske vurderinger vedr~rende ufôret
consists of taking the downstream steel lining into the trykksjakt ved mauranger kraftverk. Unpubl. rept.
hillside to the point of Z = 0.8 H and the transition
zone of reinforced concrete to Z = 1.3 H. Proof-testing Geoteam AlS, Oslo.
by hydraulic splitting tests should be done during con- Bergh-Christensen, J. and Kj~lberg, R. (1982). Investi-
struction to check the appropriateness of these posi- gation for Norway's longest unlined pressure shaft.
tions. Plain concrete lining, shotcrete lining, or an Water Power & Dam construction, April 1982, 31-32.
unlined tunnel would still be appropriate under many
conditions of deep burial and high groundwater. However, Broch, E. (1982a). The development of unlined pressure
the writer feels that reinforced concrete should be used shafts and tunnels in Norway. Proc. ISRM symposium
rather than plain concrete for questionable areas. on Rock Mechanics: Caverns and Pressure Shafts,
The problem of horizontal thrust and potential horizontal 545-554, Aachen.
displacement with associated vertical cracking should be
Broch, E. (1982b). Designing and excavating underground
realized at enlarged areas and near opening intersections.
powerplants. Water Power & Dam Construction, April
Such intersections should be minimized, and should be
widely separated. Concrete plugs in connecting adits 1982, 19-25.
should be flush with the main tunnel wall. The plug
should extend a good distance down the adit and should be Buen, B. and Palmstr~m, A. (1982). Design and super-
vision of unlined hydro power shafts and tunnels
followed some length by a reinforced concrete section.
with head up to 590 meters. Proc. ISRM Symposium
on Rock Mech.: Caverns and Pressure Shafts, 567-574,
Numerous piezometers should be placed in the exploratory
borings along the tunnel line. Readings should be taken Aachen.
for at least one year before construction to establish
Selmer-Olsen, R. (1970). Experience with unlined pres-
the seasonal groundwater levels. Readings should be con-
sure shafts in Norway. Proc. Intl. Symp. on Large
tinued during excavation and following concreting and
grouting. Permanent Underground Openings, 327-332, Oslo.
887
886
j
Seventh Panamerican Conlerence

Swanson, D.T. (1981). Prestressed concrete pressure t1


tunnels. Proc. 1981 Rapid Excavation and Tunneling
Conf., San Francisco. Vol. 1, 519-531, Soc. Min. ~
Eng., A.I.M.E., N.Y. ~,.

Geotechnical Contributions to Aretic


Resource Development
Norbert R. Morgenstern-

SYNOPSIS
The major geoteehnieal problems eneountered when dealing with perma-
frost and with freezing ground are reviewed and reeent developments
in resolving these problems are summarized. Examples of design eon-
siderations are described that inelude ereep in frozen slopes and
soil-strueture interaetion analyses of ripelines and well easings
subjeeted to thaw subsidenee.

INTRODUCTION
While the Arctic regions of North America are rich in
minerals and hydro-power, the main thrust of development
in recent years has been associated with the exploration
and production of oil and natural gas. On land the
geotechnical engineer must confront the implications of
frozen ground while offshore the need to design
structures against massiye horizontal loads due to ice
forces creates novel problems and solutions. For this
overview of geotechnical contributions to arctic resource
development it is convenient to take 1973 as a starting
point.
At that time, the design of the Alyeska pipeline was
well-advanced and the subsequent years witnessed the
successful construction of this pivotal project with
start-up in early 1977. A discussion of some of the major
design and construction issues is given by Liguori, Maple
~/ and Heuer (1979). From a geotechnical perspective, this
project forced several significant advances. Terrain
<, ;.::~' i .••
:' ~,'\":'

analysis for route location was relied on to a greater


Donald U. Deere degree than in any previous northern project. The
techniques for site investiqation in arctic terrain

(1) Professor of Civil Engineering, University of Alberta, Edmonton,


Alberta, Canada, T6G 2G7

888
889

You might also like