Professional Documents
Culture Documents
SYNOPSIS
INTRODUCTION
865
') ')
Seventh Panamerican Conference Deere
6 = average inclination of the valley side, types like certain lavas, sandstones and limestones, or
H = static water head at point in question (m), in very blocky and seamy rock."
y
r
= density of the rock mass. Broch (1982a) notes that where abnormal tectonic stresses
are expected, control tests of the in-situ stress are oc-
It is possible alsa to express the equation as follows: easionally made during construction. Also, adversely ori-
ented joints have been tested in boreholes for hydraulic
H splitting to see if sufficient stress exists across them
Z > (2)
2 to resist the full internal water pressure witha factor
'fr ·cos 6 of safety of 1.2. Bergh-Christensen and Kj~lberg (1982)
deseribe the studies for a new 1130-m long 45°-inclined
where Z = vertical rock cover (m). pressure shaft with a static head of 980 m to be built
soon for an aluminum plant in Norway. An unlined shaft is
Actually, the new rule-of-thumb Equation (1) results in eontemplated on the basis of FEM results already obtained.
about the same answer as the original one, except for The first phase of construction will be a pilot adit to
slopes steeper than 50° where it gives a more conserva- the base of the shaft so that in-situ stres s measurements
tive value. and hydraulic fracturing tests can be made. If adverse
results are obtained, time is available in the schedule
Since 1972 the Norwegian unlined pressure shafts have to allow a steel lining to be placed in the lower part of
been sited with the aid of computerized FEM analysis of the shaft.
the in-situ stress conditions. The concept is based on
locating the pressure tunnel or shaft so that at every The Norwegian experience ean be summed up, perhaps, by the
point the in-situ minor principal stress in the surround- following coneluding remarks from Buen and Palmstr~m
ing rock mass exceeds the internal water pressure thus (1982), "The solution with unlined pressure shafts and
avoiding hydraulic splitting (Broch, 1982a). The analy- tunnels is both cost- and time-saving. Unexpected ad-
sis uses a plane strain, two-dimensional model with both verse geological conditions have, however, in the past
gravitational and tectonic stresses. The results, of been the cause of extensive repairs and loss in produc-
course, are dependent on the assumed stress conditions tion in several hydro power schemes. This proves the
and Poissons ratio. In the two cases examined by the neeessity of thorough planning and control during all
writer for slopes of 40° (Broch, 1982a) and 25° (Buen and phases of construction."
Palmstr~m, 1982), factors of safety of 1.2 and 1.4 were
used, respectively. For both cases, the determined posi-
tion corresponded quite closely to Z = (0.60-0.65) H, the
old rule-of-thumb location. HYDROFRACTURING POTENTIAL IN WEATHERED & DE-STRES SED ROCKS
The Norwegian authors in their papers have emphasized The potential for hydrofracturing is increased in areas
that rock conditions must be quite good to apply their of steep, irregular topography where erosion and asso-
criteria--i.e., hard, massive rock with moderate in-situ ciated lateral strain relief have reduced the in-situ
stress; absence of open or partially filled joints paral- horizontal stresses. Joints have been opened and addi-
lel to slope; and general lack of faults and shear zones. tional joints have formed. Weathering has proceeded
High pressure grouting of all potential leakage zones along the joints which results in even further de-
with pressures slightly above the future static pressure stressing. A rock mass is formed which has both a lower
is recommended. A regular, continuous side slope is alsa in-situ rock modulus and a lower horizontal in-situ stress
favored. Selmer-Olsen (1970) pointed out that the effects (or, more correctly, a lower minimum principal stress)
of erratic topography--protruding "noses" between gorges, than deeper within the mountain.
tributary valleys, or irregular curves of the main
3tream--reduce the horizontal stresses. For these condi- Recently, in the U.S.A. hydrofracturing tests were made
tions the pressure tunnel or shaft should be placed at in boreholes at depths of 100-200 m at the site of a l2-m
deeper levels than normal. He alsa notes that all clay- diameter pressure tunnel located in an elongated mesa or
filled weak zones should be sealed with a concrete lining ridge nose. Minimum in-situ stress of only 0.4 to 0.6
and grouted. He further states, "It seems hazardous to times the vertical overburden stress were obtained in
place an unlined pressure shaft in typical porous rock
870 871
) )
Deere
Sevenılı Pan« lcan Conjerence
index of about 0.6 H (steel) and about 1.0 H (reinforced ~ghtly Permeable Linings
concrete transition). The lining that best fits this category is the one of
reinforced concrete. The amount of reinforcing can range
Where the above conditions are met, the leakage from the from about 0.25% of the area of the concrete to 0.75% or
steel lining should be zero and from the reinforced con- more. In the normal design, the reinforcing steel takes
crete lining it should be very small, and insufficient very little of the tensile load. Its purpose is to dis-
both in volume and pressure to cause hydraulic fracturing. tribute the cracks--the higher the steel percentage, the
Problems of leakage could still develop deeper in the greater the number of cracks and the thinner the cracks.
mountain beyond the potential hydrofracturing zone depend- crack widths are limited in the design to 0.3 mm.
ing on the rock permeability and the relative positions
of the internal water head and the existing groundwater The sum of all the cracks equals the total change in cir-
levels. Where a lining is used, an additional factor is cumference. This is a result of compression of the rock
the modulus of the rock mass and the number and size of and is a function of the rock modulus and the difference
any induced cracks in the lining. The following section in internal and external water pressures. Moduli values
presents a brief review of pressure tunnel linings. for design should include the disturbed rock zone sur-
rounding the first 0.5-1.5 m of the opening, plus the
deeper, undisturbed rock zone--both zones with somewhat
improved modulus due to grouting.
TYPES OF TUNNEL LININGS
For practieality in placing the concrete and for assuring
Impermeable Linings sufficient covering of the reinforcing bars, the rein-
The only common impermeable lining is the one of welded foreing is placed about 10-15 em from the formed free-
steel. It is universally used to connect the turbines to face. A single row of reinforcing mat is much preferred
the lower end of the pressure tunnel, part, as a free- to a double row. Concrete placement and vibration is
standing penstock pipe and, part, as the concrete- more difficult with a double row of reinforcement; poor
backfilled steel tunnel lining. The steel liner is concrete with rock pockets or honeycombs can result.
designed for full design internal head (static plus Water seeping from rock joints must be handled in plastic
dynamic) without assuming rock restraint for the outer pipes, appropriately sealed to prevent washing out the
few tens to few hundreds of meters, for instance, to the sand and cement from the fresh concrete. Other important
point where Z = 0.40 H and the horizontal cover equals details include the type of concrete joints. These may
1.2 H (American Iron and Steel Institute and Steel Fabri- be formed vertical joints with the steel passing through
cators Assoc., Ine., 1981). The steel liner for the the joints, or formed vertical joints without the rein-
remainder of its length is designed on the basis of load- foreing steel passing through but with plastic, de form-
sharing with the rock in accordance with its modulus. r able waterstops. Alternatively, the joints may be un-
formed sloping joints with continuous steel.
Steel linings are also used at any place along the tunnel
line where the rock cover is low (e.g., less than 0.5 H) Faulty joints and honeycombed areas will be remedied in
or where absolute water tightness is required. part by the contact and consolidation grouting but
repairs with epoxy mortar are-also advisable. Even
Impermeable linings have occasionally been constructed though these repairs are ma de and the finished conerete
with flexible, multi-pli, plastic-steel mesh membranes lining is made essentially water tight, the first filling
held in place against the rock with poured concrete. with the pressurized water will cause the tunnel to ex-
Also, to a somewhat greater extent, prestressed rein- pand and numerous, thin, distributed cracks will occur,
forced concrete linings have been used, as well as plain oriented in a longitudinal direction. A certain amount
concrete lining post-tensioned by special grouting of water will escape--thus the elassification of
(Swanson, 1981). These latter types have been used "slightly permeable" lining. However, in most cases the
mostly in Austria, in Italy, and in Switzerland. quantity would not be sufficient to cause hydrofracturing
of the rock--and if it did, the quantity of outflow would
still be small.
874 875
) ")
Seventh Panamerican Centerence
Deere
SYNOPSIS
The major geoteehnieal problems eneountered when dealing with perma-
frost and with freezing ground are reviewed and reeent developments
in resolving these problems are summarized. Examples of design eon-
siderations are described that inelude ereep in frozen slopes and
soil-strueture interaetion analyses of ripelines and well easings
subjeeted to thaw subsidenee.
INTRODUCTION
While the Arctic regions of North America are rich in
minerals and hydro-power, the main thrust of development
in recent years has been associated with the exploration
and production of oil and natural gas. On land the
geotechnical engineer must confront the implications of
frozen ground while offshore the need to design
structures against massiye horizontal loads due to ice
forces creates novel problems and solutions. For this
overview of geotechnical contributions to arctic resource
development it is convenient to take 1973 as a starting
point.
At that time, the design of the Alyeska pipeline was
well-advanced and the subsequent years witnessed the
successful construction of this pivotal project with
start-up in early 1977. A discussion of some of the major
design and construction issues is given by Liguori, Maple
~/ and Heuer (1979). From a geotechnical perspective, this
project forced several significant advances. Terrain
<, ;.::~' i .••
:' ~,'\":'
888
889