PMP Key Points
PMP 5th Edition
Details
5th Edition
Changes
PM Processes
PMP Qns 1­20
21­40
41­60
61­80
Preparation Worksheet #1
81­100
101­120 Project Integration Management – Processes & activities  required to ensure that the various elements of the project are properly coordinated to meet
121­140 stakeholder expectations.
141­160
Area Process Inputs Tools and Outputs / Deliverables Other Notes
161­180
Techniques Process
181­200
201­220
Group
221­240
241­260 4.1 Develop Project   Contract   Project selection   Project Charter Initiating Sponsor initiates the charter;
PMP Extra Notes Charter which formally methods charter includes 1) requirements
PMI Global Stds authorizes a project   SOW (includes to satisfy needs (“what”) 2)
business need,   Project mgmt business needs that the project
PMP Prep Worksheets scope description, methodology addresses (“why”) 3) justification
PM Processes strategic plan) 4) named project manager 5)
Project Lifecycle   PMIS milestones 6) assumptions 7)
  EEF constraints (“fixed dates”) 8)
Quantitative Marketing   Expert judgment business case 9) summary
Study   OPA (templates, budget
Evaluating a procedures)
Market Positioning
Glossary
https://sites.google.com/site/pmpbank/pmppreparationworksheets 1/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Noteworthy Links Project Integration Management – Processes & activities  required to ensure that the various elements of the project are properly coordinated to meet
stakeholder expectations.

Area Process Inputs Tools and Outputs / Deliverables Other Notes


Techniques Process
Group

4.2 Develop   Project charter   Project mgmt   Preliminary project Initiating Scope includes 1) objectives 2)


Preliminary Project methodology scope statement product requirements 3)
Scope Statement   SOW acceptance criteria 4) project
which provides a high   PMIS deliverables 5) constraints &
level scope description   EEF assumptions 6) project
  Expert judgment organization 7) initial risks 8)
  OPA milestones 9) initial WBS 10)
high level cost estimate 11)
project configuration mgmt
requirements 12) approval
requirements

4.3 Develop Project   Preliminary project   Project mgmt   Project Planning Plan includes 1) processes


Management Plan that scope statement methodology management plan selected 2) level of
documents what is implementation 3) tools to be
needed to define,   Project   PMIS includes used 4) interactions 5) how to
prepare, integrate & management config mgmt system execute work 6) how to control
coordinate all processes to identify changes changes 7) how to do
subsidiary plans to product and configuration mgmt 8) baselines
  EEF control changes use 9) communication needs 10)
project phases 11) key mgmt
  OPA   Expert judgment issues

4.4 Direct & Manage   Project   Project mgmt   Deliverables Executing Actions include 1) perform


Project Execution by management plan methodology activities 2) spend money 3)
executing the work   Requested train staff 4) manage vendors 5)
defined in the project   Approved   PMIS changes implement standards 6) create,
management plan to corrective actions control & validate deliverables 7)
meet requirements   Implemented manage risk & risk response
defined in the scope   Approved change requests activities 8) adapt scope
statement preventive actions changes as needed 9) manage
  Implemented communications 10) collect
  Approved change corrective actions project data including cost &
requests milestones 11) collect &
  Implemented document lessons learned and
  Approved defect preventative actions process improvement actions
repair
  Implemented
  Validated defect defect repair
report
  Work performance
  Administrative information (status,
closure procedure budget, % complete)

https://sites.google.com/site/pmpbank/pmppreparationworksheets 2/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Integration Management – Processes & activities  required to ensure that the various elements of the project are properly coordinated to meet
stakeholder expectations.

Area Process Inputs Tools and Outputs / Deliverables Other Notes


Techniques Process
Group

4.5 Monitor & Control   Project   Project mgmt   Recommended Monitor & Actions include 1) compare


Project Work through management plan methodology corrective actions Control actual vs. plan 2) determine
the processes required corrective actions needed 3)
to initiate, plan,   Work performance   PMIS   Recommended analyze risks & ensure
execute & close a information preventative actions corrective actions taken 4)
project to meet   Earned Value maintain information base 5)
performance objectives   Rejected change technique   Forecasts status reporting 6) forecasting
defined in the project requests
management plan   Expert judgment   Recommended
defect repair

  Requested
changes

4.6 Integrated Change   Project   Project mgmt   Approved change Monitor & Change control is needed


Control by reviewing all management plan methodology requests Control because projects seldom run
change requests, according to plan.  Changes
approving changes &   Requested   PMIS   Rejected change must be managed; also includes
controlling changes to changes requests documenting changes and only
the deliverables &   Expert judgment releasing approved changes. 
organizational process   Work performance   Project Defect repair must be validated
documents information management plan and quality controlled.
(updates)
  Recommended  
preventative actions   Project scope
management Configuration management also
  Recommended (updates) occurs – identify changes,
corrective actions determine if changes have been
  Approved implemented, and verify
  Recommended corrective actions changes after complete.
defect repair
  Approved  
  Deliverables preventative actions
Every documented change must
  Approved defect either be accepted or rejected by
repair some authority.

  Validated defect
repair

  Deliverables

https://sites.google.com/site/pmpbank/pmppreparationworksheets 3/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Integration Management – Processes & activities  required to ensure that the various elements of the project are properly coordinated to meet
stakeholder expectations.

Area Process Inputs Tools and Outputs / Deliverables Other Notes


Techniques Process
Group

4.7 Close Project by   Project   Project mgmt   Administrative Closing Updates after project completion


finalizing all activities management plan methodology closure procedure include 1) formal acceptance
across all of the project documentation (written) 2)
process groups to   Contract   PMIS   Contract closure project files updated 3) project
formally close the documentation procedure closure documents prepared
project   Expert judgment (even for projects halted before
  EEF   Final product, completion) 4) historical
service or result information is used to update the
  OPA “lessons learned” database
  OPA (updates)
  Work performance
information

  Deliverables

  

Preparation Worksheet #2

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group
Project Scope Management – Processes required to ensure that the project includes all the work required, and only the work
required, to complete the project successfully; focus on what is and what is not included in the project

5.1 Scope Planning by   EEF   Expert judgment   Project scope Planning Project scope management plan


creating a project management plan includes 1) process to prepare
scope management   OPA   Templates, forms, detailed scope based on
plan which includes standards preliminary scope 2) process to
how the WBS will be   Project charter create WBS from scope 3)
created & defined   process to specify verification of
  Preliminary project deliverables 4) process to
scope statement control scope changes

  Project
management plan

https://sites.google.com/site/pmpbank/pmppreparationworksheets 4/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

5.2 Scope Definition   OPA   Product analysis   Project scope Planning Preparation of a detailed scope


by developing a statement statement is critical to the
detailed project scope   Project charter   Alternatives project success.  Includes 1)
statement identification   Requested objectives 2) scope description
  Preliminary project changes 3) requirements 4) boundaries
scope statement   Expert judgment (excluded items) 5) deliverables
  Project scope 6) acceptance criteria 7)
  Project scope   Stakeholder management plan constraints 8) assumptions 9)
management plan analysis (updates) organization 10) risks 11)
milestones 12) funding 13) cost
  Approved change estimate 14) configuration
requests management requirements 15)
project specifications 16)
approval requirements

5.3 Create Work   OPA   WBS templates   Project scope Planning Decomposition divides work into


Breakdown Structure statement (updates) smaller elements by 1) identify
(WBS) by subdividing   Project scope   Decomposition deliverables 2) structure and
the deliverables & statement   WBS organize WBS 3) decomposing
work into smaller, upper WBS into lower level
more manageable   Project scope   WBS dictionary detailed components 4) assign
components management plan ID codes to WBS components
  Scope baseline 5) verifying that degree of
  Approved change decomposition is sufficient.
requests   Project scope
management plan  
(updates)
Each component must be
  Requested assigned, and defined in terms
changes of how the project will actually
be executed and controlled.

5.4 Scope Verification   Project scope   Inspection   Accepted Monitor & Scope verification is primarily


through formal statement deliverables Control concerned with acceptance of
acceptance of the the scope by stakeholders
completed project   WBS dictionary   Requested
deliverables changes
  Project scope
management plan   Recommended
corrective actions
  Deliverables

https://sites.google.com/site/pmpbank/pmppreparationworksheets 5/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

5.5 Scope Control by   Project scope   Change control   Project scope Monitor & Uncontrolled changes called


controlling changes to statement system statement (updates) Control “scope creep”.  Change is
the inevitable, thus this process is
  WBS   Variance analysis   WBS (updates) needed
project scope
  WBS dictionary   Replanning   WBS dictionary
(updates)
  Project scope   Configuration
management plan management system   Scope baseline
(updates)
  Performance
reports   Requested
changes
  Approved change
requests   Recommended
corrective action
  Work performance
information   OPA (updates)

  Project
Management Plan
(updates)

 Preparation Worksheet #3
Project Time Management ­ Processes required to ensure timely completion of the project

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

6.1 Activity Definition   EEF   Decomposition   Activity list Planning The activity list does not include


by identifying the any schedule activities that are
specific activities that   OPA   Templates   Activity attributes not required as part of the
must be performed to project scope.  
produce the various   Project scope   Rolling Wave   Milestone list
project deliverables statement planning
  Requested
  WBS   Expert judgment changes

  WBS dictionary   Planning
component (control
  Project account, planning
management plan package)

https://sites.google.com/site/pmpbank/pmppreparationworksheets 6/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Time Management ­ Processes required to ensure timely completion of the project

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

6.2 Activity   Project scope   Precedence   Project schedule Planning PDM (a.k.a  Activity on Node)


Sequencing by statement diagramming method network diagrams uses 4 types of dependencies
identifying and (PDM) (F­S, F­F, S­S, S­F). 
documenting   Activity list   Activity list
dependencies among   Arrow diagramming (updates)  
schedule activities   Activity attributes method (ADM)
  Activity attributes ADM (a.k.a.  Activity on Arrow)
  Milestone list   Schedule network (updates) uses only F­S dependencies. 
templates Allows dummy activities to
  Approved change   Requested show logical relationships. 
requests   Dependency changes (Usually shown as a dashed
determination line.)
 
  Applying leads and  
lags
3 types of dependencies ­
mandatory, discretionary (best
practices) and external.

6.3 Activity Resource   EEF   Expert judgment   Activity resource Planning  


Estimating through requirements
estimating the type &   OPA   Alternatives
quantity of resources analysis   Activity attributes
needed to complete   Activity list (updates)
each activity   Published
  Activity attributes estimating data   Resource
breakdown structure
  Resource   Project
availability management   Resource
software calendars (updates)
  Project
management plan   Bottom­up   Requested
estimating changes

https://sites.google.com/site/pmpbank/pmppreparationworksheets 7/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Time Management ­ Processes required to ensure timely completion of the project

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

6.4 Activity Duration   EEF   Expert judgment   Activity duration Planning  


Estimating by estimates
estimating the number   OPA   Analogous
of work periods which estimating (use   Activity attributes
will be needed to   Project scope actual duration of (updates)
complete individual statement similar activity from
activities past)
  Activity list
  Parametric
  Activity attributes estimating (hours per
meter)
  Activity resource
requirements   Three­point
estimates (average of
  Resource most likely, optimistic
calendars & pessimistic)

  Project   Reserve analysis
management plan
(risk register, activity
cost estimates)

https://sites.google.com/site/pmpbank/pmppreparationworksheets 8/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Time Management ­ Processes required to ensure timely completion of the project

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

6.5 Schedule   OPA   Schedule network   Project schedule Planning Critical Path is the longest path


Development by analysis through a network diagram and
analyzing activity   Project scope   Schedule model shows earliest completion of a
sequences, activity statement   Critical path data project. 
durations, and resource method
requirements to create   Activity list   Schedule baseline  
the project schedule   Schedule
  Activity attributes compression   Resource CPM uses the most likely
requirements estimate to calculate the float to
  Project schedule   What­if scenario (updates) determine project duration and
network diagrams analysis scheduling flexibility.
  Activity attributes
  Activity resource   Resource leveling (updates)  
requirements
  Critical chain   Project calendar Critical chain modifies schedule
  Resource method (updates) to account for limited
calendars resources.  Define critical path,
  Project   Requested then apply resources – often
  Activity duration management changes path changes. 
estimates software
  Project  
  Project   Applying calendars management plan
management plan (updates, including Schedule can be showed as a
(risk register)   Adjusting leads schedule network diagram, bar chart
and lags management plan) (gantt), or milestone chart.

  Schedule model

https://sites.google.com/site/pmpbank/pmppreparationworksheets 9/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Time Management ­ Processes required to ensure timely completion of the project

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

6.6 Schedule Control –   Schedule   Progress reporting   Schedule model Monitor & Key measures include Schedule


controlling changes to management plan data (updates) Control Variance (SV) and Schedule
the project schedule   Schedule change Performance Index (SPI).
including 1) determining   Schedule baseline control system   Schedule baseline
current status of (updates)  
project schedule 2)   Performance   Performance
influencing factors that reports measurement   Performance Progress reporting includes
cause changes 3) measurements actual start and finished dates,
determining that the   Approved change   Project and remaining durations for
schedule has changed requests management   Requested unfinished activities..
4) managing changes software changes
as they occur  
  Variance analysis   Recommended
corrective actions Schedule revisions are a special
  Schedule category of schedule updates –
comparison bar   OPA generally incorporated in
charts response to approved change
  Activity list requests.  The original schedule
(updates) baseline and model are saved to
prevent loss of data.
  Activity attributes
(updates)

  Project
management plan
(updates)

 
Preparation Worksheet #4
Project Cost Management – processes in planning and controlling costs so that the project can be completed within budget

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

https://sites.google.com/site/pmpbank/pmppreparationworksheets 10/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

7.1 Cost Estimating   EEF   Analogous   Activity cost Planning Top down / analogous estimating


through estimating estimates is generally less costly and less
  OPA accurate than other techniques.
approximating the   Determine   Activity cost
costs of the resources   Project scope resource cost rates estimate supporting Bottom­up estimating accuracy
needed to complete statement detail (description, is driven by size of work items
project activities   Bottom­up basis of estimate, being estimated.  Reserve
  WBS estimating assumptions, analysis includes “known
constraints, ROM) unknowns”.
  WBS dictionary   Parametric
estimating   Requested Project in initiation phase as
  Project changes rough order of Magnitude (ROM)
management plan   Project of –50/+100%, later could go to
(schedule & staffing management   Cost management –10%/+15%
mgmt plan, risk software plan (updates)
register)
  Vendor bid
analysis

  Reserve analysis

  Cost of quality

7.2 Cost Budgeting by   Project scope   Cost aggregation   Cost baseline Planning Cost baseline is a time­phased


aggregating estimated statement budget to measure and monitor
costs of individual   Reserve analysis   Project funding cost performance.
activities or work   WBS requirements
packages to establish a   Parametric  
cost baseline   WBS dictionary estimating   Cost management
plan (updates) Reserve are budgeted for
  Activity cost   Funding limit unplanned, but potentially
estimates reconciliation   Requested required, changes to project
changes scope and cost – not part of the
  Activity cost project cost baseline or earned
estimate supporting value.
detail
 
  Project schedule
Project funding requirements are
  Resource derived from the cost baseline.
calendars

  Contract

  Cost management
plan

https://sites.google.com/site/pmpbank/pmppreparationworksheets 11/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

7.3 Cost Control by   Cost baseline   Cost change   Cost estimate Monitor &   PV ­ Planned Value (also


influencing factors that control system (updates) Control Budget at Completion BAC)
create cost variances &   Project funding
controlling changes to requirements   Performance   Cost baseline   EV ­ Earned Value
the project budget measurement (updates)
  Performance analysis   AC ­ Actual Cost
reports   Performance
  Forecasting measurements   ETC – Estimate to
  Approved change Complete
requests   Project   Forecasted
management reviews completion   EAC – Estimate at
  Project Completion
management plan   Project   Requested
management changes Formulas to remember:
software
  Recommended   Schedule Variance = EV­
  Variance corrective actions PV 
management
  Organizational   Cost Variance = EV­AC  
process assets
(updates)   Schedule Performance
Index = EV/PV  
  Project
management plan   Cost Performance Index =
(updates) EV/AC  (<1.0 overrun, 1.0 on
budget, > 1.0 underrun)

  SPI, CPI used to forecast
completion date and project
cost projection

Preparation Worksheet #5
Project Quality Management – processes to ensure that the project will satisfy the needs for which it was undertaken & implements the quality
management system

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

https://sites.google.com/site/pmpbank/pmppreparationworksheets 12/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

8.1 Quality Planning by   EEF   Cost­benefit   Quality Planning Quality is “the degree to which a


analysis management plan set of inherent characteristics
identifying which   OPA fulfill requirements”
quality standards are   Benchmarking   Quality metrics
relevant to the project   Project scope Customer Satisfaction:
and determining how to statement   Design of   Quality checklists Conformance to requirements,
satisfy them experiments specifications, and fitness for
  Project   Process use.
management plan   Cost of quality improvement plan
(COQ) (steps to analyze Quality is planned in, not
processes to identify inspected in.
  Additional quality waste & non­value
planning tools added items Cost of quality is total cost of all
efforts related to quality.  Project
  Quality baseline may not reap benefits since
they are later in product lifecycle
  Project (i.e. lower returns)
management plan
(updates)

8.2 Perform Quality   Quality   Quality planning   Requested Executing Deming: Plan, Do, Check, Act


Assurance by management plan tools and techniques changes
employing activities to Kaizen (Continuous
ensure the project   Quality metrics   Quality audits   Recommended Improvement): Small
employs all processes corrective actions improvements in products or
needed to meet   Process   Process analysis processes to reduce costs and
requirements improvement plan   Process analysis ensure consistency of products
  Quality control or services.
  Work performance tools and techniques   Quality control
information tools and techniques ISO 9000:  An international
standard that describes a
  Approved change recommended quality system. 
requests Does not include quality
procedures or forms.
  Quality control
measurements Heuristic is a rule of thumb (e.g.
Rule of Seven)
  Implemented
change requests

  Implemented
corrective actions

  Implemented
defect repair

  Implemented
preventative actions

https://sites.google.com/site/pmpbank/pmppreparationworksheets 13/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

8.3 Perform Quality   Quality   Cause and effect   Quality control Monitor &   +/­ 1 sigma = 68.26%


Control by monitoring management plan diagram measurements Control
specific project results   +/­ 2 sigma = 95.46%
to determine if they   Quality metrics   Control charts   Validated defect
comply with relevant repair   +/­ 3 sigma = 99.73%
quality standards and   Quality checklists   Flowcharting
identifying ways to   Quality baseline   +/­ 6 sigma = 99.99 %
eliminate causes of   OPA   Histogram (updates)
unsatisfactory Variable:  Characteristic to be
performance   Work performance   Pareto chart   Recommended measured (e.g. size, shape)
information corrective actions
  Run chart Attribute:  The measurement
  Approved change   Recommended (e.g. inches, pounds)
requests   Scatter diagram preventative actions
Statistical Independence:  The
  Deliverables   Statistical   Requested probability of 1 event occurring
sampling changes does not affect the probability of
another event occurring.
  Inspection   Recommended
defect repair
  Defect repair
review   OPA

  Validated
deliverables

  Project
management plan
(updates)

Preparation Worksheet #6
Project Human Resource Management – process the organize & manage the project team

Area Process Inputs Tools and Techniques Outputs / Other Notes


Deliverables Process
Group

https://sites.google.com/site/pmpbank/pmppreparationworksheets 14/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

9.1 Human Resources   EEF   Organization   Roles and Planning Staff management plan includes


Planning by identifying, (organizational, charts and position responsibilities (role, 1) staff acquisition 2) timetable
documenting project technical, descriptions authority, 3) release criteria 4) training
roles, responsibilities & interpersonal, (hierarchical charts, responsibility, needs 5) recognition & rewards
reporting relationships logistical & political) matrix charts, text competencies 6) compliance 7) safety
as well as creating the formats) – required)
staffing management   OPA (templates, responsibility
plan checklists) assignment matrix   Project
(RAM) organization charts
  Project
management plan   Networking   Staffing
(activity resource management plan
requirements)   Organizational
theory

9.2 Acquire Project   EEF   Pre­assignment   Project staff Executing Conflict Resolution Techniques:


Team by getting the assignments
human resources   OPA   Negotiation   Problem Solving (Address
needed to complete the   Resource interests)
project   Roles and   Acquisition availability
responsibilities   Compromising (Middle
  Virtual teams   Staffing ground)
  Project management plan
organization charts   (updates)   Forcing (Impose judgement)

  Staffing   Withdrawal (Avoidance)
management plan
  Smoothing (Peace keeping)

PMI recommends Problem
Solving as best choice followed
by compromising.  Forcing is
last.

https://sites.google.com/site/pmpbank/pmppreparationworksheets 15/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

9.3 Develop Project   Project staff   General   Team performance Executing Maslow’s Hierarchy of Needs (in


Team by improving assignments management skills assessment order):
competencies & includes 1)
interactions to enhance   Staffing   Training improvements in   Physiological (Lowest)
project performance management plan skills for individuals
  Team­building 2) improvements in   Safety
  Resource activities competencies for the
availability group as a whole 3)   Social
  Ground rules reduce staff turnover
rate   Esteem
  Co­location
  Self­Actualization (Highest)
  Recognition and
rewards MacGregor’s Theory X – People
must be constantly watched. 
They are incapable, avoid
responsibility, and avoid work.

MacGregor’s Theory Y – People
are willing to work without
supervision and want to achieve.

Ouchi's Theory Z ­ People work
effectively when secure,
consulted and held collectively
responsible.

9.4 Manage Project   OPA   Observation and   Requested Monitor & Lessons learned documentation


Team by tracking conversation changes Control can include 1) org charts as
member performance,   Project staff templates 2) rules or techniques
providing feedback, assignments   Project   Recommended that were particularly successful
resolving issues and performance corrective actions 3) virtual teams, location items
coordinating changes   Roles and appraisals that were successful 4) special
to enhance project responsibilities   Recommended skills discovered during the
performance   Conflict preventative actions project
  Project management
organizational charts   OPA (updates)
  Issue log
  Staffing   Project
management plan management plan
(updates)
  Team performance
assessment

  Work performance
information

  Performance
reports

 
Preparation Worksheet #7
https://sites.google.com/site/pmpbank/pmppreparationworksheets 16/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Communications Management – Processes required to ensure timely and appropriate generation,
collection, dissemination, storage and ultimate disposition of project information; provide the critical links among
people & information that are needed for successful communications

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

10.1 Communication   EEF   Communications   Communications Planning Communication Methods:


Planning by requirements analysis management plan
determining the   OPA (provides 1)   Formal Written – Project
information and   Communications stakeholder Plans/Charters
communications needs   Project scope technology requirements 2) info
of the stakeholders statement to be communicated   Formal Verbal –
3) responsibility 4) Presentations, Speeches
  Project methods & frequency
management plan 5) escalation 6)   Informal Written – Memos,
(constraints, updating ) e­mail
assumptions)
  Informal Verbal –
Meetings, Conversations

Comm. Channels:  N(N­1)/2
where N is equal to the number
of people.

   

10.2 Information   Communications   Communications   OPA Executing PM should spend 70 ­ 90% of


Distribution through management plan skills their time communicating.
making needed   Requested
Basic elements of
information available to   Information changes
communication:
project stakeholders in gathering and
a timely manner retrieval systems
  Sender (or encoder)
  Information
  Message.
distribution methods
  Receiver (or decoder)
  Lessons learned
process

https://sites.google.com/site/pmpbank/pmppreparationworksheets 17/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Communications Management – Processes required to ensure timely and appropriate generation,
collection, dissemination, storage and ultimate disposition of project information; provide the critical links among
people & information that are needed for successful communications

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

10.3 Performance   Work performance   Information   Performance Monitor & Performance Reporting Tools:


Reporting by collecting information presentation tools reports Control
and disseminating   Status Report
performance   Performance   Performance   Forecasts
information including measurements information gathering   Progress Report
status reporting, and compilation   Requested
progress measurement   Forecasted changes   Trend Report
& forecasting completion   Status review
meetings   Recommended   Forecasting Report
  Quality control corrective actions
measurements   Time reporting   Variance Report
systems   OPA
  Project   Earned Value**
management plan   Cost reporting
(performance systems
measurement
baseline)

  Approved change
requests

  Deliverables

10.4 Manage   Communications   Communications   Resolved issues Monitor &  


Stakeholders by management plan methods Control
managing   Approved change
communications to   OPA   Issue logs requests
satisfy he requirements
of, and resolve issues   Approved
with, project corrective actions
stakeholders
  OPA

  Project
management plans
(updates)

Preparation Worksheet #8
Project Risk Management – processes concerned with planning, identifying, analyzing and responding to project risk; objective is  to increase the
probability & impact of positive events and to decrease the probability and impact of adverse events

https://sites.google.com/site/pmpbank/pmppreparationworksheets 18/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

https://sites.google.com/site/pmpbank/pmppreparationworksheets 19/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

11.1 Risk Management   EEF   Planning Meetings   Risk Management Planning Risk management plan includes


Planning by deciding and analysis Plan methodology, roles,
how to approach, plan   OPA responsibilities, budget, timing,
& execute the risk scoring / interpretation,
management activities   Project scope thresholds, reporting, tracking,
for a project statement etc.

  Project Risk Categories:
management plan
  Technical

  Project management

  Organizational

  External

11.2 Risk Identification   EEF   Documentation   Risk register Planning Risk Components:


by determining which reviews (includes list of
risks might affect the   OPA risks, potential   Risk event
project and   Information responses, root
documenting their   Project scope gathering techniques causes, and updated   Risk event probability
characteristics statement risk categories)
  Checklist analysis   Risk event consequence
  Risk management
plan   Assumptions   Risk event status
analysis
  Project
management plan   Diagramming
techniques

11.3 Qualitative Risk   OPA   Risk probability   Risk register Planning Use of low precision data may


Analysis by prioritizing and impact (updates) lead to faulty analysis.
risks for further   Project scope assessment
analysis or action by statement Risks calculated as high or
assessing & combining   Probability and moderate would be prime
their probability of   Risk management impact matrix candidates for further analysis.
occurrence & impact plan
  Risk data quality
  Risk register assessment

  Risk categorization

  Risk urgency
assessment

https://sites.google.com/site/pmpbank/pmppreparationworksheets 20/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

11.4 Quantitative Risk   OPA   Data gathering and   Risk register Planning Quantitative analysis follows


Analysis through representation (updates) including qualitative analysis. 
numerically analyzing   Project scope techniques 1) probabilistic
the effect on overall statement analysis of the Objectives include:
project objectives of   Quantitative risk project for schedule
identified risks   Risk management analysis and & cost outcomes 2)   Determine probability of
plan modeling techniques prioritized list of reaching project objectives
(sensitivity analysis, quantified risks 3)
  Risk register expected monetary trends in quantitative   Determine size of
value analysis, and risk results) contingency needed
  Project decision tree
management plan analysis, modeling &   Identify risks requiring most
(schedule simulation) attention based on their
management plan, priority
cost management
plan)   Identify realistic cost and
scope targets

11.5 Risk Response   Risk management   Strategies for   Risk register Planning Contingency Plan is a


Planning by developing plan negative risk or (updates) management plan that identifies
options & actions to threats (avoid, alternative strategies to be used
enhance opportunities   Risk register transfer or mitigate)   Project to ensure project success if
& reduce threats to management plan specified risk events occur.
project objectives   Strategies for (updates)
positive risks or Fallback plan is a management
opportunities (exploit,   Risk­related plan that identifies alternative
share or enhance) contractual project approaches if the risk
agreements has high impact, or if the
  Strategy for both strategy might not be fully
risks and effective. 
opportunities
(acceptance) Contingency Reserve accounts
for known risks that have been
  Contingency accepted.
response strategy
Secondary risks arise from
implementing the contingency
plan. 

https://sites.google.com/site/pmpbank/pmppreparationworksheets 21/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

11.6 Risk Monitoring   Risk management   Risk   Risk register Monitor & Purpose of Risk Monitoring is to


and  Control by plan reassessment (updates) Control determine if:
keeping track of
identified risks,   Risk register   Risk audits   Requested   Risk responses
monitoring residual changes implemented as planned
risks and identifying   Approved change   Variance and trend
new risks, executing requests analysis   Recommended   Risk response actions were
risk response plans corrective actions as effective as planned
and evaluating their   Work performance   Technical
effectiveness information performance   Recommended   Project assumptions are
throughout the project measurement preventative actions still valid
life cycle   Performance
reports   Reserve analysis   OPA   Risk trigger has occurred

  Status meetings   Project   Risk exposure has changed


management plan
(updates)  

Preparation Worksheet #9
Project Procurement Management – processes required to acquire goods and services from outside the performing team; administering contractual
obligations placed on the project team by the contract

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

12.1 Plan Purchases   EEF   Make or buy   Procurement Planning Contract Type:


and Acquisitions by analysis management plan
determining what to   OPA   FP – Fixed Price or Lump
purchase or acquire   Expert judgment   Contract sum.  (Simplest form is PO) –
and when to do it   Project scope statement of work – risk on seller
statement   Contract types needs to be clear,
complete and   CR – Cost Reimbursable
  WBS concise (cost plus fee, cost plus fixed
fee or cost plus incentive fee)
  WBS dictionary   Make or buy – place risk on buyer
decisions
  Project   T&M – Time and Materials
management plan   Requested (aspects of FP and CR
(risk register, risk­ changes contracts)  ­ Moderate cost
related contractual risk to buyer.)
agreements,
resource  
requirements, project
schedule, activity
cost estimates, cost
baseline)

https://sites.google.com/site/pmpbank/pmppreparationworksheets 22/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Procurement Management – processes required to acquire goods and services from outside the performing team; administering contractual
obligations placed on the project team by the contract

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

12.2 Plan Contracting   Procurement   Standard forms   Procurement Planning Procurement management plan


by management plan documents can include 1) type of contract 2)
  Expert judgment independent estimates 3)
documenting products,   Contract   Evaluation criteria standardized procurement
services & results statement of work (can include cost, documents 4) constraints &
requirements and technical capability, assumptions 5) lead times for
identifying potential   Make or buy financial capacity, contracting coordination 6)
sellers decisions business type, make­or­buy documentation 7)
references, etc…) scheduled dates in contracts 8)
  Project performance metrics for
management plan   Contract managing contracts
(risk register, risk­ statement of work
related contractual (updates)
agreements,
resource
requirements, project
schedule, activity
cost estimates, cost
baseline)

12.3 Request Seller   OPA   Bidder   Qualified sellers Executing All bidders conference Q&A


Responses by conferences list should be put in writing and
obtaining information,   Procurement issued to all potential sellers as
quotations, bids offers management plan   Advertising   Procurement an addendum to the procurement
or proposals document package docs.
  Procurement   Develop qualified
documents sellers list   Proposals

https://sites.google.com/site/pmpbank/pmppreparationworksheets 23/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Procurement Management – processes required to acquire goods and services from outside the performing team; administering contractual
obligations placed on the project team by the contract

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

12.4 Select Sellers by   OPA   Weighting system   Selected sellers Executing Objectives of Negotiation:


reviewing offers,
choosing among   Procurement   Independent   Contract   Obtain a fair and
potential sellers, and management plan estimates reasonable price
negotiating a written   Contract
contract   Evaluation criteria   Screening system management plan   Develop a good relationship
with the seller (should be a
  Procurement   Contract   Resource win­win situation)
document package negotiation availability
Items to negotiate include:
  Proposals   Seller rating   Procurement Responsibilities, authority,
systems management plan applicable law, technical and
  Qualified sellers (updates) business mgmt approaches,
list   Expert judgment contract financing, and price.
  Requested
  Project   Proposal changes
management plan evaluation
(risk register, risk­ techniques
related contractual
agreements,
resource
requirements, project
schedule, activity
cost estimates, cost
baseline)

https://sites.google.com/site/pmpbank/pmppreparationworksheets 24/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank

Project Procurement Management – processes required to acquire goods and services from outside the performing team; administering contractual
obligations placed on the project team by the contract

Area Process Inputs Tools and Techniques Outputs / Deliverables Other Notes


Process
Group

12.5 Contract   Contract   Contract change   Contract Monitor & Contracts are often managed by


Administration by control system documentation Control a contract department who have
managing contract &   Contract authority and responsibility for
relationship between management plan   Buyer­conducted   Requested contracts.  The PM must work
the buyer & seller; performance review changes closely with this group to ensure
documenting   Selected sellers that project objectives are met.
performance to   Inspections and   Recommended
establish corrective   Performance audits corrective actions
actions, and manage reports
contract change   Performance   OPA
  Approved change reporting
requests   Project
  Payment system management plan
  Work performance (updates)
information   Claims
administration

  Records
management system

  Information
technology

12.6 Contract Closure   Procurement   Procurement   Closed contracts Closing Centralized Contracting – A


through completing and management plan audits separate contracting office
settling each contract,   OPA (update handles contracts for all
including resolution of   Contract   Records contract file, projects.
any open items management plan management system deliverable
acceptance, and Decentralized Contracting – A
  Contract lessons learned contract administrator is
documentation documentation) assigned to each project.

  Contract closure
procedure

Have these advice helped you in preparing for your PMP test? We would like some feedback or testimonial from you. Please kindly email us with your
comments. Thank you very much! To head back to the main page, click here.  

"PMI", "PMP" "PMBOK" are marks of the Project Management Institute (PMI) which are registered in the United States of America and in other nations
PMI has not participated in the creation of this self assessment test and has not reviewed it for correctness.
This test is for self assessment only and no guarantee is given for passing the PMP®.
No content from this site can be reproduced without the permission of the owner.

The owner of this website is not responsible for contents of external pages via hyperlinks.

https://sites.google.com/site/pmpbank/pmppreparationworksheets 25/26
12/25/2017 PMP Prep Worksheets ­ PMP Bank
 

Sign in | Recent Site Activity | Report Abuse | Print Page | Powered By  Google Sites

https://sites.google.com/site/pmpbank/pmppreparationworksheets 26/26

You might also like