CITYVIEW PLANNERS AND DESIGNERS

SPECIFICATION REPORT TO ACCOMPANY WITH THE ESTIMATE FOR THE WORK

CONSTRUCTION OF A SHOPPING COMPLEX BUILDING AT SF NO.


……………………………………………..…… IN PALLAPALAYAM, COIMBATORE TAMILNADU.

ESTIMATE AMOUNT Rs

The client has requested to prepare an Estimate for his ongoing shopping complex building project located in
Pallapalayam in SF NO: ____ in Pallapalayam vtown panchayat. The proposed plan has been aproved by the
compeitive authority of Coimbatore corporation in its ROC NO.............. dated .......... and the copy of the
plan has also been enclosed herewith.

S.No DESCRIPTION

SUBSTRUCTURE

Earth work open excavation and depositing on bank with in the initial lead of 10m and a lift of 2m in
1 hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed
with small size boulders etc. complete. complying with std. specifications.SS 20 A(SI.no.61)

Plain Cement Concrete 1:5:10 Mix (one part cement, five part fine aggregate and ten part of coarse
aggregate) using 40 mm size ISS HBG metal from approved quarry including cost and conveyance of
2
all materials to site. Loading and unloading charges and labour charges for mixing, Laying and curing
etc. complete. Complying with std. specifications.

Plain Cement Concrete 1:4:8 Mix (one part cement, four part fine aggregate and Eight part of
aggregate) using 40 mm size ISS HBG metal from approved quarry including cost and conveyance of
3
all materials to site. Loading and unloading charges and labour charges for mixing, Laying and curing
etc. complete. Complying with std. specifications.

Reinforced Cement Concrete 1:1½:3 (M20) Mix (One part cement, one and half part of Fine
aggregate and three part of Coarse aggregate) using 20mm size ISS HBG metal machine crushed from
4 approved quarry including cost and conveyance of all materials to site, loading and unloading charges
and labour charges for mixing, laying and curing but excluding cost of reinforcement etc. Complete
with std. Specifications.(Using Vibrator).

a) Upto basement

a) Ground floor ( Base + First Lift)

b) First floor (GF + Additional Lift)

SPECIFICATION CITYVIEW PLANNERS AND DESIGNERS


c) Terrace floor (FF)

Centering for sides and soffits of R.C.C. slab surfaces such as beams, lintels roof slabs and sunshades
5 including cost and conveyance of all materials to site and labour charges for centering and strutting
upto 3.00 m height etc. complete. complying with std. specifications.

a) Upto basement

a) Ground floor ( Base + First Lift)

b) First floor (GF + Additional Lift)

c) Terrace floor (FF)

Providing two legged scaffolding using 15cm dia blue-gum posts of 4.0m overall length (3M HT +
0.5M projection + 0.5m into ground) the distance between two rows being 1.25m and the spacing of
postsbeling 2.0m and the spacing of postsbeling 2.0m in both the rows with two horizontal posts with
6
0.5m overlap on either sideand braces at 2m c/cincluding longitudinal and transverse middle braces to
step up and providing a platform with country woodplanks of 40mm tk & 1.0m width in a complete
form using colr and nalls - 1.0m run -- FOR REJUVENATION WORKS

a) Up to 3m height

b) 3m + every 2.5m height


Supplying fabricating and placing in position of steel rods using M.S. or Ribbed Tor Steel including
7 cost of binding wire, cost of labour charges for fabrication and placing in position etc. Complete.
Complying with std. specifications.

SUPER STRUCTURE

Brick Work in Cement Mortor 1:5 Mix (one cement, five sand) using new best II Class Bricks of size
9 ” x 4 3/8 “x 2 3/4 ” from approved quarry including cost and conveyance of all materials to site.
8
Loading and unloading charges and labour charges for mixing, laying and curing etc. complete.
Complying with std. specifications.

a) Upto basement

b) Ground floor ( Base + First Lift)

c) First floor (GF + Additional Lift)

d) Terrace floor (GF)

FINISHING

Re-filling of Trenches with the excavated earth in layers well rammed and consolidated and
9 depositing the surplus earth in all places with the initial lead and lift including levelling, etc.,
complete. Complying with the standard specification as directed

SPECIFICATION CITYVIEW PLANNERS AND DESIGNERS


Collection, supply and filling of well gravel in approved quarry including cost and Conveyance of all
10
materials to site and all labour charges for filling etc., Complete.

Plastering in Cement Mortor 1:3 Mix (one cement, Three Fine aggregate) 12mm thick including cost
11 and conveyance of all materials to site, loading and unloading charges and labour charges for mixing,
laying and curing etc. complete. complying with std. specifications.

a) Ground floor ( Base + First Lift)

b) First floor (GF + Additional Lift)

c) Terrace floor (FF)

Plastering in Cement Mortor 1:4 Mix (one Cement, four Fine aggregate) 20mm thick including cost
12 and conveyance of all materials to site, loading and unloading charges and labour charges for mixing,
laying and curing etc. complete. Complying with std. specifications.

a) Upto basement

b) Ground floor ( Base + First Lift)

c) First floor (GF + Additional Lift)

d) Terrace floor (FF)

Plastering in Cement Mortor 1:4 Mix (one Cement, four sand) 20mm thick including cost and
13 conveyance of all materials to site, loading and unloading charges and labour charges for mixing,
laying and curing etc. complete. Complying with std. specifications.

Paving hydraulic pressed cement-Mosaic tiles of approved colour and of size 200 mm x 200 mm x 20
14 mm with CM 1:3, 20 mm thick and pointed with the same colour cement including polishing with
power polisher to a high degree of polish so as to be perfectly smooth and gloossy for 10Sqm.

Laying with new C.C. Laminated tiles (Like Dora tiles Eurocon tiles etc),(anti skid) of 20mm thick of
approved spl quality and set in Cement Mortar 1:3 (1 of cement and 3 of sand ) 20mm. Thick using
15 river sand and pointing with colour cement using at the rate of 0.40 kg/M2 and mixing with colour
pigment at the rate of 0.3 Kg/M2 including finishing complete with Standard Specification and as
directed by the Departmental Officers etc.,

Finishing the top of roof with one course of machine pressed tiles 20 C.m x 20 C.m x 2 C.m size
16 using cement mortor 1:3 mix mixed with 2% by weight of Water proofing compound and pointing
with Cement Mortor 1:3 mix Cost of all materials and labour charges and brick jelly concrete.

Colour washing One coats with good quality of Colour pigments including cost of all materials to site
17 and all other labour charges for mixing, applying and proper curring etc., Complete as per Standard
Specifications.

SPECIFICATION CITYVIEW PLANNERS AND DESIGNERS


PLUMBING & SANITATION

Supplying, laying and jointing P.V.C. pipes of approved quality and best variety conformming to
I.S.S. and with I.S.I. mark, of the following sizes including cutting threading and fixing P.V.C.
18 specials but excluding cost of such specials and fixing to wall or drilling holes in roof and making
good the dismantled portions to original condition with necessary brick work and plastering wherever
necessary with necessary scaffolding charges.

For P.V.C. pipes of size :20mm ф

Supplying and fixing in position best Indian make white glazed earthenware WASH HAND BASIN of
550x400mm with a a pair of C.I. Brackets, 15mm dia C.P. Pillar tap, 32mm G.I. Waster water pipe,
32mm dia C.P. Brass waster coupling, plug with chain, 15mm dia PVC connection, 15mm G.M.
19
wheel valve with ISI mark and necessary G.I. union and G.I. Elbow, including fixing wash hand basin
in position with white lead, clamps, teakwood plugs, screws, rubber washer etc., complete without
any leakage complying with standard specifications.

Supplying and fixing in position Indian water closet of size 580x440 mm, white glazed earthen ware
of approved quality with 'P' trap or 'S' trap conforming to IS:2556-part XII with sand cushion and
forming flooring alround the closet using 40mm broken brick jelly in lime concrete 1:2:5 (one part of
lime, two parts of fine aggregate and five parts of brick jelly)100mm thick and finishing the top to
20 required slope and including given necessary connection to cast iron soil pipes by dismantling brick
masonry, reinforced cement concrete roof/floor slab and making good the disturbed portion to orginal
condition without leakage etc., complete complying with standard specificatios and as directed by the
departmental officers. (The water closet should br got approved by the Executive Engineer before use
on works).

Supplying and fixing in position colour glazed European water closet with 'P' or 'S' trap and double
flapped seat cover, 12.50 litres capacity P.V.C. low level flushing tank including all internal fittings
21 fixed on C.I. brackets, 12mm PVC or brass nipple, chromium plated brown headed stopcock, 12mm
nylon connection with necessary teakwood plugs, clamps, screws to the portion coming with walls
and floors, including dismantling masonry and redoing the same to the original condition.

Supplying and fixing of push and pull type Rolling shutter confirming to IS 6248/1979 and as
amended from time to time. With ISI make of approved size and section using 18 gauge G.I.sheet.The
22
shutter shall be painted with one coat of red oxide primer and the rate is inclusive of Hood covers ,
transportation charges etc., and as directed by Engineer incharge.

SPECIFICATION CITYVIEW PLANNERS AND DESIGNERS


Fabricating, supplying and fixing in positon of SOLID PVC DOORS with frames of different sizes as
per the specifications given below: PVC door frames made out of best quality PVC extruded section
of 40mm * 58 mm * 2.50 mm +/- 0.3 mm thick, having multichamber cross section and duly
reinforced with steel to be mitre cut at the corners and welded including providing tie rod at the
bottom and necessary weather seal etc., and PVC door shutters made out of extruded plastic section of
60 mm * 24 mm size in the configruation of an "A" section for shutter frames and multi-chamber
23
hollow plastic section of 200 mm *200 mm*1 mm (average thickness) with tongue and groove
section for panels etc., with necessary holdfasts, rubber beedings, furniture fittings, locking
arrangements etc., complete including dimantling the masnery, making chippings, holes in the RCC
column, beam etc., wherever necessary with power drill to the extent required and redoing the same
to the original condition after fixing etc., complete as per specifications and as directed by the
departmental officers.

a) Solid panel PVC Door with frame

b) Solid panel PVC Door with out frame

M.S. 'N' Type Ventilator.Supply and fabricating and fixing in position of 'N' type ventilators using
M.S. angles of size 25x25x5mm for frame and M.S.Tee of size 25x25x3mm M.S.flat of size 20x3mm
for fixing the weld mesh.Special type for hold fast welded to the frame of 45 degrees inclined towards
centre of wall and fixing the weldmesh 25mm size including 3 mm thick pin headed glass for all
24 panels and glass panels with necessary clips and puttie with required bolts nuts and waste and one
coat of red oxide primer etc., including necessary dismantling , making holes in RCC
columns,beams,masonary wherever necessary with power drill to the extent required and made good
to the original condition after fixing as directed by department officers. All materials should be got
approved by the Executive Engineer befor fixing in position.

ELECTRIFICATION

Wiring with 2x1.5 sqmm (22/0.3) PVC insulated SC unsheathed copper conductor cable of 1100V
grade in suitable heavy gauge MS conduit pipe on wall and ceiling with MS accessories with switch
25 box with 5A F.T. switch inflush with wall and covered with hylum sheet of 3mm thick with painting
of suitable colour with continuous earth wire connection of 14 SWG TC wire for light point / Fan
point (For electronic Regulator) SD 2

OVER HEAD MAINS:Supply and run of 2 of 1.5sqmm (22/0.3) PVC insulated SC unsheathed
26
Cu.Conductor of 1100V grade on 7/20 GI bearer wire for service connection mains.SD 64

Supply and fixing of TNEB meter Board suitable for 32A Three Phase service connection with 3 Nos.
32A Fuse unit (500V) 32A neutral link and earth link (1" x 1/8" Copper flat) on TW plank of size
27 600mm x 450mm x 19mm with supporting TW reepers of 1" thick an either side with painting with
suitable bolt and nuts for fixing the TW plank on wall with earth connection and inter connection with
7/20 PVC insulated copper wire from EB meter to fuse unit. SD 127

SPECIFICATION CITYVIEW PLANNERS AND DESIGNERS


Supply and fixing of 5A 3 pin and 2 pin combined flush type wall socket with 5A flush type switch on
28
suitable TW box. SD 133

This estimate has been prepared by using the current year local rates adopted and ongoing labour charges are
used. The expenditure will be meet out from the whole fund of Client own account.

SPECIFICATION CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 7

BILL OF QUANTITY

NAME OF WORK :

CONSTRUCTION OF A SHOPPING COMPLEX BUILDING AT SF NO.


……………………………………………..…… IN PALLAPALAYAM, COIMBATORE
TAMILNADU.

ESTIMATE AMOUNT Rs

Sl. Measurement
Description of work Nos. Quantity
No Length Breath Depth
SUBSTRUCTURE

Earth work open excavation and depositing on bank with in the initial lead of
10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth,
1
shales, murram, gravel, stoney earth and earth mixed with small size boulders
etc. complete. complying with std. specifications.SS 20 A(SI.no.61)

For Foundation
F1 1 x 18 1.67 1.82 1.83 100.12 m³
F2 1 x 16 1.67 1.67 1.83 81.66
Total 182.00 m³
Plinth beam
North side 1 x 1 24.18 0.38 0.38 3.49 m³
South side 1 x 1 20.95 0.38 0.38 3.03
East side 1 x 1 14.90 0.38 0.38 2.15
West side 1 x 1 11.43 0.38 0.38 1.65
Horizontal beams 1 x 3 20.49 0.38 0.38 8.88
Vertical beams
1 x 10 2.85 0.38 0.38 4.12
1 x 4 1.98 0.38 0.38 1.14
1 x 2 3.50 0.38 0.38 1.01
Total 25.00 m³

Plain Cement Concrete 1:5:10 Mix (one part cement, five part fine aggregate
and ten part of coarse aggregate) using 40 mm size ISS HBG metal from
2 approved quarry including cost and conveyance of all materials to site.
Loading and unloading charges and labour charges for mixing, Laying and
curing etc. complete. Complying with std. specifications.

For Foundation

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 8

F1 1 x 18 1.67 1.82 0.15 8.21 m³


F2 1 x 16 1.67 1.67 0.15 6.69
Total 15.00 m³
Plinth beam
North side 1 x 1 24.18 0.38 - 9.19 m2
South side 1 x 1 20.95 0.38 - 7.96
East side 1 x 1 14.90 0.38 - 5.66
West side 1 x 1 11.43 0.38 - 4.34
Horizontal beams 1 x 3 20.49 0.38 - 23.36
Vertical beams
1 x 10 2.85 0.38 - 10.83
1 x 4 1.98 0.38 - 3.01
1 x 2 3.50 0.38 - 2.66
Total 67.00 m2

Plain Cement Concrete 1:4:8 Mix (one part cement, four part fine aggregate
and Eight part of aggregate) using 40 mm size ISS HBG metal from approved
3 quarry including cost and conveyance of all materials to site. Loading and
unloading charges and labour charges for mixing, Laying and curing etc.
complete. Complying with std. specifications.

Shop 1,2,3,4,5,6 1 x 6 5.64 3.35 - 113.36 m2


Shop 7 1 x 1 6.02 3.35 - 20.17
Staircase 1 x 1 2.44 5.87 - 14.32
Toilet 1 x 2 1.80 1.50 - 5.40
Passage 1 x 1 20.80 1.83 - 38.06
1 x 2 1.22 5.03 - 12.27
1 x 1 12.58 1.22 - 15.35
1 x 1 5.25 1.22 - 6.41
Total 225.00 m2

Reinforced Cement Concrete 1:1½:3 (M20) Mix (One part cement, one and
half part of Fine aggregate and three part of Coarse aggregate) using 20mm
size ISS HBG metal machine crushed from approved quarry including cost
4
and conveyance of all materials to site, loading and unloading charges and
labour charges for mixing, laying and curing but excluding cost of
reinforcement etc. Complete with std. Specifications.(Using Vibrator).

a) Upto basement
For Foundation

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 9

F1 1 x 18 1.37 1.52 0.45 16.87 m³


F2 1 x 16 1.37 1.37 0.45 13.51
Total 30.00 m³
Column
C1 1 x 18 0.23 0.30 1.23 1.53 m³
C2 1 x 16 0.23 0.23 1.23 1.04
Total 3.00 m³
Plinth beam
North side 1 x 1 24.03 0.23 0.38 2.10 m³
South side 1 x 1 20.80 0.23 0.38 1.82
East side 1 x 1 14.75 0.23 0.38 1.29
West side 1 x 1 11.28 0.23 0.38 0.99
Horizontal beams 1 x 2 20.34 0.23 0.38 3.56
Vertical beams
1 x 10 2.70 0.23 0.38 2.36
1 x 1 1.83 0.23 0.38 0.16
1 x 1 3.35 0.23 0.38 0.29
Total 13.00 m³
Tie / Grade beam
North side 1 x 1 20.03 0.23 0.91 4.19 m³
South side 1 x 1 12.58 0.23 0.91 2.63
East side 1 x 1 14.74 0.23 0.91 3.09
West side 1 x 1 11.28 0.23 0.91 2.36
Horizontal walls 1 x 5 3.35 0.23 0.91 3.51
1 x 1 13.69 0.23 0.91 2.87
Vertical walls
1 x 5 5.64 0.23 0.91 5.90
1 x 2 3.35 0.23 0.91 1.40
Total 26.00 m³
a) Ground floor ( Base + First Lift)
Column
C1 1 x 18 0.23 0.30 3.66 4.55 m³
C2 1 x 16 0.23 0.23 3.66 3.10
Total 8.00 m³
Roof beam
Horizontal beams 1 x 4 20.80 0.23 0.38 7.27 m³

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 10

1 x 1 13.87 0.23 0.38 1.21


1 x 1 2.26 0.23 0.38 0.20
Vertical beams
1 x 14 2.71 0.23 0.38 3.32
1 x 7 1.83 0.23 0.38 1.12
1 x 5 4.57 0.23 0.38 2.00
1 x 5 1.22 0.23 0.38 0.53
Total 16.00 m³
Roof slab
1 x 1 20.80 8.16 0.15 25.46 m³
1 x 1 7.39 4.80 0.15 5.32
1 x 1 7.70 4.80 0.15 5.54
Lintel level slab 1 x 1 2.26 3.46 0.15 1.17
Total 37.00 m³
Sill beam
North side 1 x 1 20.80 - - 20.80 m
South side 1 x 1 12.57 - - 12.57
East & West side 1 x 2 9.45 - - 18.90

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 - - 16.75

Shop 1,7 1 x 1 11.66 - - 11.66


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 - - 28.20
Shop 1,7 1 x 2 3.35 - - 6.70
Toilet wall 1 x 2 3.23 - - 6.46
Total 122.00 m
Lintel beam
North side 1 x 1 20.80 0.23 0.15 0.72 m³
South side 1 x 1 12.57 0.23 0.15 0.43
East & West side 1 x 2 9.45 0.23 0.15 0.65

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 0.15 0.58

Shop 1,7 1 x 1 11.66 0.23 0.15 0.40


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 0.15 0.97
Shop 1,7 1 x 2 3.35 0.23 0.15 0.23
Toilet wall 1 x 2 3.23 0.23 0.15 0.22
Total 4.00 m³

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 11

b) First floor (GF + Additional Lift)


Column
C1 1 x 18 0.23 0.30 3.66 4.55 m³
C2 1 x 16 0.23 0.23 3.66 3.10
Total 8.00 m³

Roof beam
Horizontal beams 1 x 4 20.80 0.23 0.38 7.27 m³
1 x 1 13.87 0.23 0.38 1.21
1 x 1 2.26 0.23 0.38 0.20
Vertical beams
1 x 14 2.71 0.23 0.38 3.32
1 x 7 1.83 0.23 0.38 1.12
1 x 5 4.57 0.23 0.38 2.00
1 x 5 1.22 0.23 0.38 0.53
Total 16.00 m³
Roof slab
1 x 1 20.80 8.16 0.15 25.46 m³
1 x 1 7.39 4.80 0.15 5.32
1 x 1 7.70 4.80 0.15 5.54
Lintel level slab 1 x 1 2.26 3.46 0.15 1.17
Total 37.00 m³
Sill beam
North side 1 x 1 20.80 - - 20.80
South side 1 x 1 12.57 - - 12.57
East & West side 1 x 2 9.45 - - 18.90

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 - - 16.75

Shop 1,7 1 x 1 11.66 - - 11.66


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 - - 28.20
Shop 1,7 1 x 2 3.35 - - 6.70
Toilet wall 1 x 2 3.23 - - 6.46
Total 122.00 m
Lintel beam
North side 1 x 1 20.80 0.23 0.15 0.72 m³
South side 1 x 1 12.57 0.23 0.15 0.43

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 12

East & West side 1 x 2 9.45 0.23 0.15 0.65

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 0.15 0.58

Shop 1,7 1 x 1 11.66 0.23 0.15 0.40


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 0.15 0.97
Shop 1,7 1 x 2 3.35 0.23 0.15 0.23
Toilet wall 1 x 2 3.23 0.23 0.15 0.22
Total 4.00 m³
c) Terrace floor (FF)
Headroom slab 1 x 1 2.90 6.10 0.15 2.65
Total 3.00 m³

Centering for sides and soffits of R.C.C. slab surfaces such as beams, lintels
roof slabs and sunshades including cost and conveyance of all materials to
5
site and labour charges for centering and strutting upto 3.00 m height etc.
complete. complying with std. specifications.

a) Upto basement
For Foundation
F1 1 x 18 5.78 - 0.45 46.82 m2
F2 1 x 16 5.48 - 0.45 39.46
Total 86.00 m2
Column
C1 1 x 18 1.06 - 1.23 23.47 m2
C2 1 x 16 0.92 - 1.23 18.11
Total 42.00 m2
Plinth beam
North side 1 x 2 24.03 - 0.38 18.26 m2
South side 1 x 2 20.80 - 0.38 15.81
East side 1 x 2 14.75 - 0.38 11.21
West side 1 x 2 11.28 - 0.38 8.57
Horizontal beams 2 x 2 20.34 - 0.38 30.92
Vertical beams
2 x 10 2.70 - 0.38 20.52
1 x 2 1.83 - 0.38 1.39
1 x 2 3.35 - 0.38 2.55
Total 109.00 m2
a) Ground floor ( Base + First Lift)

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 13

Column
C1 1 x 18 1.06 - 3.66 69.83 m2
C2 1 x 16 0.92 - 3.66 53.88
Total 124.00 m2
Roof beam ( Side sheet )
Horizontal beams 2 x 4 20.80 - 0.38 63.23 m2
1 x 2 13.87 - 0.38 10.54
1 x 2 2.26 - 0.38 1.72
Vertical beams - 0.00
2 x 14 2.71 - 0.38 28.83
2 x 7 1.83 - 0.38 9.74
2 x 5 4.57 - 0.38 17.37
2 x 5 1.22 - 0.38 4.64
Total 136.00 m2
Roof beam ( Bottom sheet )
Horizontal beams 1 x 4 20.80 0.23 - 19.14 m2
1 x 1 13.87 0.23 - 3.19
1 x 1 2.26 0.23 - 0.52
Vertical beams
1 x 14 2.71 0.23 - 8.73
1 x 7 1.83 0.23 - 2.95
1 x 5 4.57 0.23 - 5.26
1 x 5 1.22 0.23 - 1.40
Total 41.00 m2
Roof slab ( Side sheet )
1 x 1 57.92 - 0.15 8.69 m2
1 x 1 24.38 - 0.15 3.66
1 x 1 25.00 - 0.15 3.75
Lintel level slab 1 x 1 11.44 - 0.15 1.72
Total 18.00 m2
Roof slab ( Bottom sheet )
1 x 1 57.92 - - 57.92 m
1 x 1 24.38 - - 24.38
1 x 1 25.00 - - 25.00
Lintel level slab 1 x 1 11.44 - - 11.44
Total 119.00 m

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 14

b) First floor (GF + Additional Lift)


Column
C1 1 x 18 1.06 - 3.66 69.83 m2
C2 1 x 16 0.92 - 3.66 53.88
Total 124.00 m2
Roof beam ( Side sheet )
Horizontal beams 2 x 4 20.80 - 0.38 63.23 m2
1 x 2 13.87 - 0.38 10.54
1 x 2 2.26 - 0.38 1.72
Vertical beams - 0.00
2 x 14 2.71 - 0.38 28.83
2 x 7 1.83 - 0.38 9.74
2 x 5 4.57 - 0.38 17.37
2 x 5 1.22 - 0.38 4.64
Total 136.00 m2
Roof beam ( Bottom sheet )
Horizontal beams 1 x 4 20.80 0.23 - 19.14 m2
1 x 1 13.87 0.23 - 3.19
1 x 1 2.26 0.23 - 0.52
Vertical beams
1 x 14 2.71 0.23 - 8.73
1 x 7 1.83 0.23 - 2.95
1 x 5 4.57 0.23 - 5.26
1 x 5 1.22 0.23 - 1.40
Total 41.00 m2
Roof slab (Side sheet)
1 x 1 57.92 - 0.15 8.69 m2
1 x 1 24.38 - 0.15 3.66
1 x 1 25.00 - 0.15 3.75
Lintel level slab 1 x 1 11.44 - 0.15 1.72
Total 18.00 m2
Roof slab (Bottom sheet)
1 x 1 57.92 - - 57.92 m
1 x 1 24.38 - - 24.38
1 x 1 25.00 - - 25.00
Lintel level slab 1 x 1 11.44 - - 11.44

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 15

Total 119.00 m
c) Terrace floor (FF)
Headroom slab (Side sheet) 1 x 1 18.00 - 0.15 2.70
Total 3.00 m2
Headroom slab (Bottom sheet) 1 x 1 18.00 - - 18.00
Total 18.00 m

Providing two legged scaffolding using 15cm dia blue-gum posts of 4.0m
overall length (3M HT + 0.5M projection + 0.5m into ground) the distance
between two rows being 1.25m and the spacing of postsbeling 2.0m and the
spacing of postsbeling 2.0m in both the rows with two horizontal posts with
6
0.5m overlap on either sideand braces at 2m c/cincluding longitudinal and
transverse middle braces to step up and providing a platform with country
woodplanks of 40mm tk & 1.0m width in a complete form using colr and
nalls - 1.0m run -- FOR REJUVENATION WORKS

a) Up to 3m height
b) 3m + every 2.5m height
Supplying fabricating and placing in position of steel rods using M.S. or
Ribbed Tor Steel including cost of binding wire, cost of labour charges for
7 fabrication and placing in position etc. Complete. Complying with std.
specifications.

16.00 MT

SUPER STRUCTURE

Brick Work in Cement Mortor 1:5 Mix (one cement, five sand) using new
best II Class Bricks of size 9 ” x 4 3/8 “x 2 3/4 ” from approved quarry
8 including cost and conveyance of all materials to site. Loading and unloading
charges and labour charges for mixing, laying and curing etc. complete.
Complying with std. specifications.

a) Upto basement
Brick on edge
North side 1 x 1 24.03 - - 24.03 m
South side 1 x 1 20.80 - - 20.80
East side 1 x 1 14.75 - - 14.75
West side 1 x 1 11.28 - - 11.28
Horizontal walls 1 x 2 20.34 - - 40.68
Vertical walls - - 0.00
1 x 10 2.70 - - 27.00
1 x 1 1.83 - - 1.83

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 16

1 x 1 3.35 - - 3.35
Total 144.00 m
For basement
North side 1 x 1 20.03 0.23 0.91 4.19 m³
South side 1 x 1 12.58 0.23 0.91 2.63
East side 1 x 1 14.74 0.23 0.91 3.09
West side 1 x 1 11.28 0.23 0.91 2.36
Horizontal walls 1 x 5 3.35 0.23 0.91 3.51
1 x 1 13.69 0.23 0.91 2.87
Vertical walls
1 x 5 5.64 0.23 0.91 5.90
1 x 2 3.35 0.23 0.91 1.40
Total 26.00 m³
b) Ground floor ( Base + First Lift)
North side 1 x 1 20.80 0.23 3.66 17.51 m³
South side 1 x 1 12.57 0.23 3.66 10.58
East & West side 1 x 2 9.45 0.23 3.66 15.91

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 3.66 14.10

Shop 1,7 1 x 1 11.66 0.23 3.66 9.82


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 3.66 23.74
Shop 1,7 1 x 2 3.35 0.23 3.66 5.64
Toilet wall 1 x 2 3.23 0.23 2.44 3.63
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 60.00 m³
d) Terrace floor (GF)
North side 1 x 1 20.80 0.23 3.66 17.51 m³
South side 1 x 1 12.57 0.23 3.66 10.58
East & West side 1 x 2 9.45 0.23 3.66 15.91

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 3.66 14.10

Shop 1,7 1 x 1 11.66 0.23 3.66 9.82

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 17

Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 3.66 23.74


Shop 1,7 1 x 2 3.35 0.23 3.66 5.64
Toilet wall 1 x 2 3.23 0.23 2.44 3.63
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 60.00 m³
d) Second floor (FF + Additional Lift)
Parapet wall
North side 1 x 1 20.80 0.23 0.76 3.64 m³
South side 1 x 1 15.02 0.23 0.76 2.63
East side & West side 1 x 2 12.50 0.23 0.76 4.37
Headroom 1 x 1 14.18 0.23 2.44 7.96
Deduction
Door 1 -1 x 1 0.91 - 2.14 -1.95
Total 17.00 m³
FINISHING

Re-filling of Trenches with the excavated earth in layers well rammed and
consolidated and depositing the surplus earth in all places with the initial lead
9
and lift including levelling, etc., complete. Complying with the standard
specification as directed

F1 1 x 18 1.37 1.52 0.60 22.49 m³


F2 1 x 16 1.37 1.37 0.60 18.02
Dedution
C1 -1 x 18 0.23 0.30 1.23 -1.53
C2 -1 x 16 0.23 0.23 1.23 -1.04
Total 38.00 m³

Collection, supply and filling of well gravel in approved quarry including cost
10 and Conveyance of all materials to site and all labour charges for filling etc.,
Complete.

Earthwork for Foundation 1 x 1 182.00 m³


Earthwork for Plinth beam 1 x 1 25.00
Footing PCC -1 x 1 -15.00

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 18

Footing concrete -1 x 1 -30.00


Plinth beam PCC -1 x 1 -67.00
Plinth beam concrete -1 x 1 -13.00
Column upto basement -1 x 1 -3.00
79.00
Consolidation 30% 23.70
Total 182.00 m³

Plastering in Cement Mortor 1:3 Mix (one cement, Three Fine aggregate)
12mm thick including cost and conveyance of all materials to site, loading
11
and unloading charges and labour charges for mixing, laying and curing etc.
complete. complying with std. specifications.

a) Ground floor ( Base + First Lift)


For ceiling
Shop 1,2,3,4,5,6 1 x 6 5.64 3.35 - 113.36 m2
Shop 7 1 x 1 6.02 3.35 - 20.17
Toilet 1 x 2 1.80 1.50 - 5.40
Passage area 1 x 1 20.80 1.83 - 38.06
1 x 2 1.22 5.03 - 12.27
1 x 1 15.02 1.22 - 18.32
Toilet (Mezaline) 1 x 1 5.26 1.22 - 6.42
Total 214.00 m2
b) First floor (GF + Additional Lift)
For ceiling
Shop 1,2,3,4,5,6 1 x 6 5.64 3.35 - 113.36 m2
Shop 7 1 x 1 6.02 3.35 - 20.17
Toilet 1 x 2 1.80 1.50 - 5.40
Passage area 1 x 1 20.80 1.83 - 38.06
1 x 2 1.22 5.03 - 12.27
1 x 1 15.02 1.22 - 18.32
Toilet (Mezaline) 1 x 1 5.26 1.22 - 6.42
Total 214.00 m2
d) Terrace floor (FF)
Headroom plastering 1 x 1 2.44 5.64 - 13.76
Total 14.00 m2

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 19

Plastering in Cement Mortor 1:4 Mix (one Cement, four Fine aggregate)
20mm thick including cost and conveyance of all materials to site, loading
12
and unloading charges and labour charges for mixing, laying and curing etc.
complete. Complying with std. specifications.

a) Upto basement
Shop 1,2,3,4,5,6 1 x 1 17.98 - 0.91 16.36 m2
Staircase 1 x 1 16.16 - 0.91 14.71
Toilet 1 x 2 6.60 - 0.91 12.01
Total 43.00 m2

b) Ground floor ( Base + First Lift)


For Internal
Shop 1,2,3,4,5,6 1 x 6 17.98 - 3.66 394.84
Shop 7 1 x 1 18.74 - 3.66 68.59
Toilet 1 x 1 6.60 - 2.44 16.10
Passage area 1 x 1 18.36 - 3.66 67.20
1 x 1 12.58 - 3.66 46.04
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 552.00 m2
c) First floor (GF + Additional Lift)
For Internal
Shop 1,2,3,4,5,6 1 x 6 17.98 - 3.66 394.84
Shop 7 1 x 1 18.74 - 3.66 68.59
Toilet 1 x 1 6.60 - 2.44 16.10
Passage area 1 x 1 18.36 - 3.66 67.20
1 x 1 12.58 - 3.66 46.04
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 552.00 m2

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 20

d) Terrace floor (FF)


Parapet wall 1 x 1 17.98 - 0.76 13.66
Total 14.00 m2

Plastering in Cement Mortor 1:4 Mix (one Cement, four sand) 20mm thick
including cost and conveyance of all materials to site, loading and unloading
13
charges and labour charges for mixing, laying and curing etc. complete.
Complying with std. specifications.

External
North side 1 x 1 18.54 - 8.38 155.37
South side 1 x 1 12.58 - 8.38 105.42
East & West side 1 x 2 9.91 - 8.38 166.09
Toilet 1 x 1 9.18 - 4.88 44.80
Head room 1 x 1 14.67 - 2.44 35.79
Total 507.00 m2

Paving hydraulic pressed cement-Mosaic tiles of approved colour and of size


200 mm x 200 mm x 20 mm with CM 1:3, 20 mm thick and pointed with the
14
same colour cement including polishing with power polisher to a high degree
of polish so as to be perfectly smooth and gloossy for 10Sqm.

Ground floor
Shop 1,2,3,4,5,6 1 x 6 3.35 - 5.64 113.36 m2
Shop 7 1 x 1 6.02 - 3.35 20.17
Staircase 1 x 1 1.29 - 2.66 3.43
Passage
1 x 1 20.80 - 1.83 38.06
1 x 2 1.22 - 5.03 12.27
1 x 1 12.58 - 1.22 15.35
Total 203.00 m2
First floor
Shop 1,2,3,4,5,6 1 x 6 3.35 - 5.64 113.36 m2
Shop 7 1 x 1 6.02 - 3.35 20.17
Staircase 1 x 1 1.29 - 2.66 3.43
Passage
1 x 1 20.80 - 1.83 38.06
1 x 2 1.22 - 5.03 12.27
1 x 1 12.58 - 1.22 15.35
Total 203.00 m2

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 21

Laying with new C.C. Laminated tiles (Like Dora tiles Eurocon tiles etc),(anti
skid) of 20mm thick of approved spl quality and set in Cement Mortar 1:3 (1
of cement and 3 of sand ) 20mm. Thick using river sand and pointing with
15
colour cement using at the rate of 0.40 kg/M2 and mixing with colour
pigment at the rate of 0.3 Kg/M2 including finishing complete with Standard
Specification and as directed by the Departmental Officers etc.,

Ground & First floor (Toilet) 2 x 2 1.80 - 1.50 10.80


Total 11.00 m2

Finishing the top of roof with one course of machine pressed tiles 20 C.m x
20 C.m x 2 C.m size using cement mortor 1:3 mix mixed with 2% by weight
16
of Water proofing compound and pointing with Cement Mortor 1:3 mix Cost
of all materials and labour charges and brick jelly concrete.

1 x 1 20.34 - 12.50 254.25 m2


Dedution for Head room -1 x 1 2.90 - 5.87 -17.02
Dedution for Open area -1 x 1 5.87 - 5.03 -29.53
Total 208.00 m2

Colour washing One coats with good quality of Colour pigments including
17 cost of all materials to site and all other labour charges for mixing, applying
and proper curring etc., Complete as per Standard Specifications.

Plastering area 1625.00


Total 1625.00 m2

PLUMBING & SANITATION

Supplying, laying and jointing P.V.C. pipes of approved quality and best
variety conformming to I.S.S. and with I.S.I. mark, of the following sizes
including cutting threading and fixing P.V.C. specials but excluding cost of
18
such specials and fixing to wall or drilling holes in roof and making good the
dismantled portions to original condition with necessary brick work and
plastering wherever necessary with necessary scaffolding charges.

For P.V.C. pipes of size :20mm ф 10.00 m

Supplying and fixing in position best Indian make white glazed earthenware
WASH HAND BASIN of 550x400mm with a a pair of C.I. Brackets, 15mm
dia C.P. Pillar tap, 32mm G.I. Waster water pipe, 32mm dia C.P. Brass waster
coupling, plug with chain, 15mm dia PVC connection, 15mm G.M. wheel
19 2.00 No
valve with ISI mark and necessary G.I. union and G.I. Elbow, including fixing
wash hand basin in position with white lead, clamps, teakwood plugs, screws,
rubber washer etc., complete without any leakage complying with standard
specifications.

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 22

Supplying and fixing in position Indian water closet of size 580x440 mm,
white glazed earthen ware of approved quality with 'P' trap or 'S' trap
conforming to IS:2556-part XII with sand cushion and forming flooring
alround the closet using 40mm broken brick jelly in lime concrete 1:2:5 (one
part of lime, two parts of fine aggregate and five parts of brick jelly)100mm
20 thick and finishing the top to required slope and including given necessary 2.00 No
connection to cast iron soil pipes by dismantling brick masonry, reinforced
cement concrete roof/floor slab and making good the disturbed portion to
orginal condition without leakage etc., complete complying with standard
specificatios and as directed by the departmental officers. (The water closet
should br got approved by the Executive Engineer before use on works).

Supplying and fixing in position colour glazed European water closet with 'P'
or 'S' trap and double flapped seat cover, 12.50 litres capacity P.V.C. low level
flushing tank including all internal fittings fixed on C.I. brackets, 12mm PVC
21 or brass nipple, chromium plated brown headed stopcock, 12mm nylon 2.00 No
connection with necessary teakwood plugs, clamps, screws to the portion
coming with walls and floors, including dismantling masonry and redoing the
same to the original condition.

Supplying and fixing of push and pull type Rolling shutter confirming to IS
6248/1979 and as amended from time to time. With ISI make of approved size
22 and section using 18 gauge G.I.sheet.The shutter shall be painted with one 18.00 No
coat of red oxide primer and the rate is inclusive of Hood covers ,
transportation charges etc., and as directed by Engineer incharge.

Fabricating, supplying and fixing in positon of SOLID PVC DOORS with


frames of different sizes as per the specifications given below: PVC door
frames made out of best quality PVC extruded section of 40mm * 58 mm *
2.50 mm +/- 0.3 mm thick, having multichamber cross section and duly
reinforced with steel to be mitre cut at the corners and welded including
providing tie rod at the bottom and necessary weather seal etc., and PVC door
shutters made out of extruded plastic section of 60 mm * 24 mm size in the
23 configruation of an "A" section for shutter frames and multi-chamber hollow
plastic section of 200 mm *200 mm*1 mm (average thickness) with tongue
and groove section for panels etc., with necessary holdfasts, rubber beedings,
furniture fittings, locking arrangements etc., complete including dimantling
the masnery, making chippings, holes in the RCC column, beam etc.,
wherever necessary with power drill to the extent required and redoing the
same to the original condition after fixing etc., complete as per specifications
and as directed by the departmental officers.

a) Solid panel PVC Door with frame 3.00 No


b) Solid panel PVC Door with out frame 4.00 No

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 23

M.S. 'N' Type Ventilator.Supply and fabricating and fixing in position of 'N'
type ventilators using M.S. angles of size 25x25x5mm for frame and M.S.Tee
of size 25x25x3mm M.S.flat of size 20x3mm for fixing the weld
mesh.Special type for hold fast welded to the frame of 45 degrees inclined
towards centre of wall and fixing the weldmesh 25mm size including 3 mm
thick pin headed glass for all panels and glass panels with necessary clips and
24 4.00 No
puttie with required bolts nuts and waste and one coat of red oxide primer
etc., including necessary dismantling , making holes in RCC
columns,beams,masonary wherever necessary with power drill to the extent
required and made good to the original condition after fixing as directed by
department officers. All materials should be got approved by the Executive
Engineer befor fixing in position.

ELECTRIFICATION

Wiring with 2x1.5 sqmm (22/0.3) PVC insulated SC unsheathed copper


conductor cable of 1100V grade in suitable heavy gauge MS conduit pipe on
wall and ceiling with MS accessories with switch box with 5A F.T. switch
25 50.00 m
inflush with wall and covered with hylum sheet of 3mm thick with painting of
suitable colour with continuous earth wire connection of 14 SWG TC wire for
light point / Fan point (For electronic Regulator) SD 2

OVER HEAD MAINS:Supply and run of 2 of 1.5sqmm (22/0.3) PVC


26 insulated SC unsheathed Cu.Conductor of 1100V grade on 7/20 GI bearer 14.00 No
wire for service connection mains.SD 64

Supply and fixing of TNEB meter Board suitable for 32A Three Phase service
connection with 3 Nos. 32A Fuse unit (500V) 32A neutral link and earth link
(1" x 1/8" Copper flat) on TW plank of size 600mm x 450mm x 19mm with
27 supporting TW reepers of 1" thick an either side with painting with suitable 1.00 No
bolt and nuts for fixing the TW plank on wall with earth connection and inter
connection with 7/20 PVC insulated copper wire from EB meter to fuse unit.
SD 127

Supply and fixing of 5A 3 pin and 2 pin combined flush type wall socket with
28 30.00 No
5A flush type switch on suitable TW box. SD 133

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 24

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 25

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 26

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


BOQ Page 27

MT

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 29

BILL OF QUANTITY

NAME OF WORK :

CONSTRUCTION OF A SHOPPING COMPLEX BUILDING AT SF NO.


……………………………………………..…… IN PALLAPALAYAM, COIMBATORE
TAMILNADU.

ESTIMATE AMOUNT Rs

Sl. Measurement
Description of work Nos. Quantity
No Length Breath Depth
SUBSTRUCTURE

Earth work open excavation and depositing on bank with in the initial lead of
10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth,
1
shales, murram, gravel, stoney earth and earth mixed with small size boulders
etc. complete. complying with std. specifications.SS 20 A(SI.no.61)

For Foundation
F1 1 x 18 1.67 1.82 1.83 100.12 m³
F2 1 x 16 1.67 1.67 1.83 81.66
Total 182.00 m³
Plinth beam
North side 1 x 1 24.18 0.38 0.38 3.49 m³
South side 1 x 1 20.95 0.38 0.38 3.03
East side 1 x 1 14.90 0.38 0.38 2.15
West side 1 x 1 11.43 0.38 0.38 1.65
Horizontal beams 1 x 3 20.49 0.38 0.38 8.88
Vertical beams
1 x 10 2.85 0.38 0.38 4.12
1 x 4 1.98 0.38 0.38 1.14
1 x 2 3.50 0.38 0.38 1.01
Total 25.00 m³

Plain Cement Concrete 1:5:10 Mix (one part cement, five part fine aggregate
and ten part of coarse aggregate) using 40 mm size ISS HBG metal from
2 approved quarry including cost and conveyance of all materials to site.
Loading and unloading charges and labour charges for mixing, Laying and
curing etc. complete. Complying with std. specifications.

For Foundation

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 30

F1 1 x 18 1.67 1.82 0.15 8.21 m³


F2 1 x 16 1.67 1.67 0.15 6.69
Total 15.00 m³
Plinth beam
North side 1 x 1 24.18 0.38 - 9.19 m2
South side 1 x 1 20.95 0.38 - 7.96
East side 1 x 1 14.90 0.38 - 5.66
West side 1 x 1 11.43 0.38 - 4.34
Horizontal beams 1 x 3 20.49 0.38 - 23.36
Vertical beams
1 x 10 2.85 0.38 - 10.83
1 x 4 1.98 0.38 - 3.01
1 x 2 3.50 0.38 - 2.66
Total 67.00 m2

Plain Cement Concrete 1:4:8 Mix (one part cement, four part fine aggregate
and Eight part of aggregate) using 40 mm size ISS HBG metal from approved
3 quarry including cost and conveyance of all materials to site. Loading and
unloading charges and labour charges for mixing, Laying and curing etc.
complete. Complying with std. specifications.

Shop 1,2,3,4,5,6 1 x 6 5.64 3.35 - 113.36 m2


Shop 7 1 x 1 6.02 3.35 - 20.17
Staircase 1 x 1 2.44 5.87 - 14.32
Toilet 1 x 2 1.80 1.50 - 5.40
Passage 1 x 1 20.80 1.83 - 38.06
1 x 2 1.22 5.03 - 12.27
1 x 1 12.58 1.22 - 15.35
1 x 1 5.25 1.22 - 6.41
Total 225.00 m2

Reinforced Cement Concrete 1:1½:3 (M20) Mix (One part cement, one and
half part of Fine aggregate and three part of Coarse aggregate) using 20mm
size ISS HBG metal machine crushed from approved quarry including cost
4
and conveyance of all materials to site, loading and unloading charges and
labour charges for mixing, laying and curing but excluding cost of
reinforcement etc. Complete with std. Specifications.(Using Vibrator).

a) Upto basement
For Foundation

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 31

F1 1 x 18 1.37 1.52 0.45 16.87 m³


F2 1 x 16 1.37 1.37 0.45 13.51
Total 30.00 m³
Column
C1 1 x 18 0.23 0.30 1.23 1.53 m³
C2 1 x 16 0.23 0.23 1.23 1.04
Total 3.00 m³
Plinth beam
North side 1 x 1 24.03 0.23 0.38 2.10 m³
South side 1 x 1 20.80 0.23 0.38 1.82
East side 1 x 1 14.75 0.23 0.38 1.29
West side 1 x 1 11.28 0.23 0.38 0.99
Horizontal beams 1 x 2 20.34 0.23 0.38 3.56
Vertical beams
1 x 10 2.70 0.23 0.38 2.36
1 x 1 1.83 0.23 0.38 0.16
1 x 1 3.35 0.23 0.38 0.29
Total 13.00 m³
Tie / Grade beam
North side 1 x 1 20.03 0.23 0.91 4.19 m³
South side 1 x 1 12.58 0.23 0.91 2.63
East side 1 x 1 14.74 0.23 0.91 3.09
West side 1 x 1 11.28 0.23 0.91 2.36
Horizontal walls 1 x 5 3.35 0.23 0.91 3.51
1 x 1 13.69 0.23 0.91 2.87
Vertical walls
1 x 5 5.64 0.23 0.91 5.90
1 x 2 3.35 0.23 0.91 1.40
Total 26.00 m³
a) Ground floor ( Base + First Lift)
Column
C1 1 x 18 0.23 0.30 3.66 4.55 m³
C2 1 x 16 0.23 0.23 3.66 3.10
Total 8.00 m³
Roof beam
Horizontal beams 1 x 4 20.80 0.23 0.38 7.27 m³

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 32

1 x 1 13.87 0.23 0.38 1.21


1 x 1 2.26 0.23 0.38 0.20
Vertical beams
1 x 14 2.71 0.23 0.38 3.32
1 x 7 1.83 0.23 0.38 1.12
1 x 5 4.57 0.23 0.38 2.00
1 x 5 1.22 0.23 0.38 0.53
Total 16.00 m³
Roof slab
1 x 1 20.80 8.16 0.15 25.46 m³
1 x 1 7.39 4.80 0.15 5.32
1 x 1 7.70 4.80 0.15 5.54
Lintel level slab 1 x 1 2.26 3.46 0.15 1.17
Total 37.00 m³
Sill beam
North side 1 x 1 20.80 - - 20.80 m
South side 1 x 1 12.57 - - 12.57
East & West side 1 x 2 9.45 - - 18.90

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 - - 16.75

Shop 1,7 1 x 1 11.66 - - 11.66


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 - - 28.20
Shop 1,7 1 x 2 3.35 - - 6.70
Toilet wall 1 x 2 3.23 - - 6.46
Total 122.00 m
Lintel beam
North side 1 x 1 20.80 0.23 0.15 0.72 m³
South side 1 x 1 12.57 0.23 0.15 0.43
East & West side 1 x 2 9.45 0.23 0.15 0.65

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 0.15 0.58

Shop 1,7 1 x 1 11.66 0.23 0.15 0.40


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 0.15 0.97
Shop 1,7 1 x 2 3.35 0.23 0.15 0.23
Toilet wall 1 x 2 3.23 0.23 0.15 0.22
Total 4.00 m³

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 33

b) First floor (GF + Additional Lift)


Column
C1 1 x 18 0.23 0.30 3.66 4.55 m³
C2 1 x 16 0.23 0.23 3.66 3.10
Total 8.00 m³

Roof beam
Horizontal beams 1 x 4 20.80 0.23 0.38 7.27 m³
1 x 1 13.87 0.23 0.38 1.21
1 x 1 2.26 0.23 0.38 0.20
Vertical beams
1 x 14 2.71 0.23 0.38 3.32
1 x 7 1.83 0.23 0.38 1.12
1 x 5 4.57 0.23 0.38 2.00
1 x 5 1.22 0.23 0.38 0.53
Total 16.00 m³
Roof slab
1 x 1 20.80 8.16 0.15 25.46 m³
1 x 1 7.39 4.80 0.15 5.32
1 x 1 7.70 4.80 0.15 5.54
Lintel level slab 1 x 1 2.26 3.46 0.15 1.17
Total 37.00 m³
Sill beam
North side 1 x 1 20.80 - - 20.80
South side 1 x 1 12.57 - - 12.57
East & West side 1 x 2 9.45 - - 18.90

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 - - 16.75

Shop 1,7 1 x 1 11.66 - - 11.66


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 - - 28.20
Shop 1,7 1 x 2 3.35 - - 6.70
Toilet wall 1 x 2 3.23 - - 6.46
Total 122.00 m
Lintel beam
North side 1 x 1 20.80 0.23 0.15 0.72 m³
South side 1 x 1 12.57 0.23 0.15 0.43

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 34

East & West side 1 x 2 9.45 0.23 0.15 0.65

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 0.15 0.58

Shop 1,7 1 x 1 11.66 0.23 0.15 0.40


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 0.15 0.97
Shop 1,7 1 x 2 3.35 0.23 0.15 0.23
Toilet wall 1 x 2 3.23 0.23 0.15 0.22
Total 4.00 m³
c) Terrace floor (FF)
Headroom slab 1 x 1 2.90 6.10 0.15 2.65
Total 3.00 m³

Centering for sides and soffits of R.C.C. slab surfaces such as beams, lintels
roof slabs and sunshades including cost and conveyance of all materials to
5
site and labour charges for centering and strutting upto 3.00 m height etc.
complete. complying with std. specifications.

a) Upto basement
For Foundation
F1 1 x 18 5.78 - 0.45 46.82 m2
F2 1 x 16 5.48 - 0.45 39.46
Total 86.00 m2
Column
C1 1 x 18 1.06 - 1.23 23.47 m2
C2 1 x 16 0.92 - 1.23 18.11
Total 42.00 m2
Plinth beam
North side 1 x 2 24.03 - 0.38 18.26 m2
South side 1 x 2 20.80 - 0.38 15.81
East side 1 x 2 14.75 - 0.38 11.21
West side 1 x 2 11.28 - 0.38 8.57
Horizontal beams 2 x 2 20.34 - 0.38 30.92
Vertical beams
2 x 10 2.70 - 0.38 20.52
1 x 2 1.83 - 0.38 1.39
1 x 2 3.35 - 0.38 2.55
Total 109.00 m2
a) Ground floor ( Base + First Lift)

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 35

Column
C1 1 x 18 1.06 - 3.66 69.83 m2
C2 1 x 16 0.92 - 3.66 53.88
Total 124.00 m2
Roof beam ( Side sheet )
Horizontal beams 2 x 4 20.80 - 0.38 63.23 m2
1 x 2 13.87 - 0.38 10.54
1 x 2 2.26 - 0.38 1.72
Vertical beams - 0.00
2 x 14 2.71 - 0.38 28.83
2 x 7 1.83 - 0.38 9.74
2 x 5 4.57 - 0.38 17.37
2 x 5 1.22 - 0.38 4.64
Total 136.00 m2
Roof beam ( Bottom sheet )
Horizontal beams 1 x 4 20.80 0.23 - 19.14 m2
1 x 1 13.87 0.23 - 3.19
1 x 1 2.26 0.23 - 0.52
Vertical beams
1 x 14 2.71 0.23 - 8.73
1 x 7 1.83 0.23 - 2.95
1 x 5 4.57 0.23 - 5.26
1 x 5 1.22 0.23 - 1.40
Total 41.00 m2
Roof slab ( Side sheet )
1 x 1 57.92 - 0.15 8.69 m2
1 x 1 24.38 - 0.15 3.66
1 x 1 25.00 - 0.15 3.75
Lintel level slab 1 x 1 11.44 - 0.15 1.72
Total 18.00 m2
Roof slab ( Bottom sheet )
1 x 1 57.92 - - 57.92 m
1 x 1 24.38 - - 24.38
1 x 1 25.00 - - 25.00
Lintel level slab 1 x 1 11.44 - - 11.44
Total 119.00 m

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 36

b) First floor (GF + Additional Lift)


Column
C1 1 x 18 1.06 - 3.66 69.83 m2
C2 1 x 16 0.92 - 3.66 53.88
Total 124.00 m2
Roof beam ( Side sheet )
Horizontal beams 2 x 4 20.80 - 0.38 63.23 m2
1 x 2 13.87 - 0.38 10.54
1 x 2 2.26 - 0.38 1.72
Vertical beams - 0.00
2 x 14 2.71 - 0.38 28.83
2 x 7 1.83 - 0.38 9.74
2 x 5 4.57 - 0.38 17.37
2 x 5 1.22 - 0.38 4.64
Total 136.00 m2
Roof beam ( Bottom sheet )
Horizontal beams 1 x 4 20.80 0.23 - 19.14 m2
1 x 1 13.87 0.23 - 3.19
1 x 1 2.26 0.23 - 0.52
Vertical beams
1 x 14 2.71 0.23 - 8.73
1 x 7 1.83 0.23 - 2.95
1 x 5 4.57 0.23 - 5.26
1 x 5 1.22 0.23 - 1.40
Total 41.00 m2
Roof slab (Side sheet)
1 x 1 57.92 - 0.15 8.69 m2
1 x 1 24.38 - 0.15 3.66
1 x 1 25.00 - 0.15 3.75
Lintel level slab 1 x 1 11.44 - 0.15 1.72
Total 18.00 m2
Roof slab (Bottom sheet)
1 x 1 57.92 - - 57.92 m
1 x 1 24.38 - - 24.38
1 x 1 25.00 - - 25.00
Lintel level slab 1 x 1 11.44 - - 11.44

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 37

Total 119.00 m
c) Terrace floor (FF)
Headroom slab (Side sheet) 1 x 1 18.00 - 0.15 2.70
Total 3.00 m2
Headroom slab (Bottom sheet) 1 x 1 18.00 - - 18.00
Total 18.00 m

Providing two legged scaffolding using 15cm dia blue-gum posts of 4.0m
overall length (3M HT + 0.5M projection + 0.5m into ground) the distance
between two rows being 1.25m and the spacing of postsbeling 2.0m and the
spacing of postsbeling 2.0m in both the rows with two horizontal posts with
6
0.5m overlap on either sideand braces at 2m c/cincluding longitudinal and
transverse middle braces to step up and providing a platform with country
woodplanks of 40mm tk & 1.0m width in a complete form using colr and
nalls - 1.0m run -- FOR REJUVENATION WORKS

a) Up to 3m height
b) 3m + every 2.5m height
Supplying fabricating and placing in position of steel rods using M.S. or
Ribbed Tor Steel including cost of binding wire, cost of labour charges for
7 fabrication and placing in position etc. Complete. Complying with std.
specifications.

16.00 MT

SUPER STRUCTURE

Brick Work in Cement Mortor 1:5 Mix (one cement, five sand) using new
best II Class Bricks of size 9 ” x 4 3/8 “x 2 3/4 ” from approved quarry
8 including cost and conveyance of all materials to site. Loading and unloading
charges and labour charges for mixing, laying and curing etc. complete.
Complying with std. specifications.

a) Upto basement
Brick on edge
North side 1 x 1 24.03 - - 24.03 m
South side 1 x 1 20.80 - - 20.80
East side 1 x 1 14.75 - - 14.75
West side 1 x 1 11.28 - - 11.28
Horizontal walls 1 x 2 20.34 - - 40.68
Vertical walls - - 0.00
1 x 10 2.70 - - 27.00
1 x 1 1.83 - - 1.83

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 38

1 x 1 3.35 - - 3.35
Total 144.00 m
For basement
North side 1 x 1 20.03 0.23 0.91 4.19 m³
South side 1 x 1 12.58 0.23 0.91 2.63
East side 1 x 1 14.74 0.23 0.91 3.09
West side 1 x 1 11.28 0.23 0.91 2.36
Horizontal walls 1 x 5 3.35 0.23 0.91 3.51
1 x 1 13.69 0.23 0.91 2.87
Vertical walls
1 x 5 5.64 0.23 0.91 5.90
1 x 2 3.35 0.23 0.91 1.40
Total 26.00 m³
b) Ground floor ( Base + First Lift)
North side 1 x 1 20.80 0.23 3.66 17.51 m³
South side 1 x 1 12.57 0.23 3.66 10.58
East & West side 1 x 2 9.45 0.23 3.66 15.91

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 3.66 14.10

Shop 1,7 1 x 1 11.66 0.23 3.66 9.82


Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 3.66 23.74
Shop 1,7 1 x 2 3.35 0.23 3.66 5.64
Toilet wall 1 x 2 3.23 0.23 2.44 3.63
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 60.00 m³
d) Terrace floor (GF)
North side 1 x 1 20.80 0.23 3.66 17.51 m³
South side 1 x 1 12.57 0.23 3.66 10.58
East & West side 1 x 2 9.45 0.23 3.66 15.91

Horizontal wall ( Shop 2,3,4,5,6) 1 x 5 3.35 0.23 3.66 14.10

Shop 1,7 1 x 1 11.66 0.23 3.66 9.82

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 39

Vertical wall (Shop 2,3,4,5,6) 1 x 5 5.64 0.23 3.66 23.74


Shop 1,7 1 x 2 3.35 0.23 3.66 5.64
Toilet wall 1 x 2 3.23 0.23 2.44 3.63
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 60.00 m³
d) Second floor (FF + Additional Lift)
Parapet wall
North side 1 x 1 20.80 0.23 0.76 3.64 m³
South side 1 x 1 15.02 0.23 0.76 2.63
East side & West side 1 x 2 12.50 0.23 0.76 4.37
Headroom 1 x 1 14.18 0.23 2.44 7.96
Deduction
Door 1 -1 x 1 0.91 - 2.14 -1.95
Total 17.00 m³
FINISHING

Re-filling of Trenches with the excavated earth in layers well rammed and
consolidated and depositing the surplus earth in all places with the initial lead
9
and lift including levelling, etc., complete. Complying with the standard
specification as directed

F1 1 x 18 1.37 1.52 0.60 22.49 m³


F2 1 x 16 1.37 1.37 0.60 18.02
Dedution
C1 -1 x 18 0.23 0.30 1.23 -1.53
C2 -1 x 16 0.23 0.23 1.23 -1.04
Total 38.00 m³

Collection, supply and filling of well gravel in approved quarry including cost
10 and Conveyance of all materials to site and all labour charges for filling etc.,
Complete.

Earthwork for Foundation 1 x 1 182.00 m³


Earthwork for Plinth beam 1 x 1 25.00
Footing PCC -1 x 1 -15.00

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 40

Footing concrete -1 x 1 -30.00


Plinth beam PCC -1 x 1 -67.00
Plinth beam concrete -1 x 1 -13.00
Column upto basement -1 x 1 -3.00
79.00
Consolidation 30% 23.70
Total 182.00 m³

Plastering in Cement Mortor 1:3 Mix (one cement, Three Fine aggregate)
12mm thick including cost and conveyance of all materials to site, loading
11
and unloading charges and labour charges for mixing, laying and curing etc.
complete. complying with std. specifications.

a) Ground floor ( Base + First Lift)


For ceiling
Shop 1,2,3,4,5,6 1 x 6 5.64 3.35 - 113.36 m2
Shop 7 1 x 1 6.02 3.35 - 20.17
Toilet 1 x 2 1.80 1.50 - 5.40
Passage area 1 x 1 20.80 1.83 - 38.06
1 x 2 1.22 5.03 - 12.27
1 x 1 15.02 1.22 - 18.32
Toilet (Mezaline) 1 x 1 5.26 1.22 - 6.42
Total 214.00 m2
b) First floor (GF + Additional Lift)
For ceiling
Shop 1,2,3,4,5,6 1 x 6 5.64 3.35 - 113.36 m2
Shop 7 1 x 1 6.02 3.35 - 20.17
Toilet 1 x 2 1.80 1.50 - 5.40
Passage area 1 x 1 20.80 1.83 - 38.06
1 x 2 1.22 5.03 - 12.27
1 x 1 15.02 1.22 - 18.32
Toilet (Mezaline) 1 x 1 5.26 1.22 - 6.42
Total 214.00 m2
d) Terrace floor (FF)
Headroom plastering 1 x 1 2.44 5.64 - 13.76
Total 14.00 m2

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 41

Plastering in Cement Mortor 1:4 Mix (one Cement, four Fine aggregate)
20mm thick including cost and conveyance of all materials to site, loading
12
and unloading charges and labour charges for mixing, laying and curing etc.
complete. Complying with std. specifications.

a) Upto basement
Shop 1,2,3,4,5,6 1 x 1 17.98 - 0.91 16.36 m2
Staircase 1 x 1 16.16 - 0.91 14.71
Toilet 1 x 2 6.60 - 0.91 12.01
Total 43.00 m2

b) Ground floor ( Base + First Lift)


For Internal
Shop 1,2,3,4,5,6 1 x 6 17.98 - 3.66 394.84
Shop 7 1 x 1 18.74 - 3.66 68.59
Toilet 1 x 1 6.60 - 2.44 16.10
Passage area 1 x 1 18.36 - 3.66 67.20
1 x 1 12.58 - 3.66 46.04
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 552.00 m2
c) First floor (GF + Additional Lift)
For Internal
Shop 1,2,3,4,5,6 1 x 6 17.98 - 3.66 394.84
Shop 7 1 x 1 18.74 - 3.66 68.59
Toilet 1 x 1 6.60 - 2.44 16.10
Passage area 1 x 1 18.36 - 3.66 67.20
1 x 1 12.58 - 3.66 46.04
Deduction
Rolling shutter -1 x 9 1.80 - 2.14 -34.67
Door 1 -1 x 1 0.91 - 2.14 -1.95
Door 2 -1 x 2 0.76 - 2.14 -3.25
Ventilator -1 x 2 0.76 - 0.61 -0.93
Total 552.00 m2

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 42

d) Terrace floor (FF)


Parapet wall 1 x 1 17.98 - 0.76 13.66
Total 14.00 m2

Plastering in Cement Mortor 1:4 Mix (one Cement, four sand) 20mm thick
including cost and conveyance of all materials to site, loading and unloading
13
charges and labour charges for mixing, laying and curing etc. complete.
Complying with std. specifications.

External
North side 1 x 1 18.54 - 8.38 155.37
South side 1 x 1 12.58 - 8.38 105.42
East & West side 1 x 2 9.91 - 8.38 166.09
Toilet 1 x 1 9.18 - 4.88 44.80
Head room 1 x 1 14.67 - 2.44 35.79
Total 507.00 m2

Paving hydraulic pressed cement-Mosaic tiles of approved colour and of size


200 mm x 200 mm x 20 mm with CM 1:3, 20 mm thick and pointed with the
14
same colour cement including polishing with power polisher to a high degree
of polish so as to be perfectly smooth and gloossy for 10Sqm.

Ground floor
Shop 1,2,3,4,5,6 1 x 6 3.35 - 5.64 113.36 m2
Shop 7 1 x 1 6.02 - 3.35 20.17
Staircase 1 x 1 1.29 - 2.66 3.43
Passage
1 x 1 20.80 - 1.83 38.06
1 x 2 1.22 - 5.03 12.27
1 x 1 12.58 - 1.22 15.35
Total 203.00 m2
First floor
Shop 1,2,3,4,5,6 1 x 6 3.35 - 5.64 113.36 m2
Shop 7 1 x 1 6.02 - 3.35 20.17
Staircase 1 x 1 1.29 - 2.66 3.43
Passage
1 x 1 20.80 - 1.83 38.06
1 x 2 1.22 - 5.03 12.27
1 x 1 12.58 - 1.22 15.35
Total 203.00 m2

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 43

Laying with new C.C. Laminated tiles (Like Dora tiles Eurocon tiles etc),(anti
skid) of 20mm thick of approved spl quality and set in Cement Mortar 1:3 (1
of cement and 3 of sand ) 20mm. Thick using river sand and pointing with
15
colour cement using at the rate of 0.40 kg/M2 and mixing with colour
pigment at the rate of 0.3 Kg/M2 including finishing complete with Standard
Specification and as directed by the Departmental Officers etc.,

Ground & First floor (Toilet) 2 x 2 1.80 - 1.50 10.80


Total 11.00 m2

Finishing the top of roof with one course of machine pressed tiles 20 C.m x
20 C.m x 2 C.m size using cement mortor 1:3 mix mixed with 2% by weight
16
of Water proofing compound and pointing with Cement Mortor 1:3 mix Cost
of all materials and labour charges and brick jelly concrete.

1 x 1 20.34 - 12.50 254.25 m2


Dedution for Head room -1 x 1 2.90 - 5.87 -17.02
Dedution for Open area -1 x 1 5.87 - 5.03 -29.53
Total 208.00 m2

Colour washing One coats with good quality of Colour pigments including
17 cost of all materials to site and all other labour charges for mixing, applying
and proper curring etc., Complete as per Standard Specifications.

Plastering area 1625.00


Total 1625.00 m2

PLUMBING & SANITATION

Supplying, laying and jointing P.V.C. pipes of approved quality and best
variety conformming to I.S.S. and with I.S.I. mark, of the following sizes
including cutting threading and fixing P.V.C. specials but excluding cost of
18
such specials and fixing to wall or drilling holes in roof and making good the
dismantled portions to original condition with necessary brick work and
plastering wherever necessary with necessary scaffolding charges.

For P.V.C. pipes of size :20mm ф 10.00 m

Supplying and fixing in position best Indian make white glazed earthenware
WASH HAND BASIN of 550x400mm with a a pair of C.I. Brackets, 15mm
dia C.P. Pillar tap, 32mm G.I. Waster water pipe, 32mm dia C.P. Brass waster
coupling, plug with chain, 15mm dia PVC connection, 15mm G.M. wheel
19 2.00 No
valve with ISI mark and necessary G.I. union and G.I. Elbow, including fixing
wash hand basin in position with white lead, clamps, teakwood plugs, screws,
rubber washer etc., complete without any leakage complying with standard
specifications.

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 44

Supplying and fixing in position Indian water closet of size 580x440 mm,
white glazed earthen ware of approved quality with 'P' trap or 'S' trap
conforming to IS:2556-part XII with sand cushion and forming flooring
alround the closet using 40mm broken brick jelly in lime concrete 1:2:5 (one
part of lime, two parts of fine aggregate and five parts of brick jelly)100mm
20 thick and finishing the top to required slope and including given necessary 2.00 No
connection to cast iron soil pipes by dismantling brick masonry, reinforced
cement concrete roof/floor slab and making good the disturbed portion to
orginal condition without leakage etc., complete complying with standard
specificatios and as directed by the departmental officers. (The water closet
should br got approved by the Executive Engineer before use on works).

Supplying and fixing in position colour glazed European water closet with 'P'
or 'S' trap and double flapped seat cover, 12.50 litres capacity P.V.C. low level
flushing tank including all internal fittings fixed on C.I. brackets, 12mm PVC
21 or brass nipple, chromium plated brown headed stopcock, 12mm nylon 2.00 No
connection with necessary teakwood plugs, clamps, screws to the portion
coming with walls and floors, including dismantling masonry and redoing the
same to the original condition.

Supplying and fixing of push and pull type Rolling shutter confirming to IS
6248/1979 and as amended from time to time. With ISI make of approved size
22 and section using 18 gauge G.I.sheet.The shutter shall be painted with one 18.00 No
coat of red oxide primer and the rate is inclusive of Hood covers ,
transportation charges etc., and as directed by Engineer incharge.

Fabricating, supplying and fixing in positon of SOLID PVC DOORS with


frames of different sizes as per the specifications given below: PVC door
frames made out of best quality PVC extruded section of 40mm * 58 mm *
2.50 mm +/- 0.3 mm thick, having multichamber cross section and duly
reinforced with steel to be mitre cut at the corners and welded including
providing tie rod at the bottom and necessary weather seal etc., and PVC door
shutters made out of extruded plastic section of 60 mm * 24 mm size in the
23 configruation of an "A" section for shutter frames and multi-chamber hollow
plastic section of 200 mm *200 mm*1 mm (average thickness) with tongue
and groove section for panels etc., with necessary holdfasts, rubber beedings,
furniture fittings, locking arrangements etc., complete including dimantling
the masnery, making chippings, holes in the RCC column, beam etc.,
wherever necessary with power drill to the extent required and redoing the
same to the original condition after fixing etc., complete as per specifications
and as directed by the departmental officers.

a) Solid panel PVC Door with frame 3.00 No


b) Solid panel PVC Door with out frame 4.00 No

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 45

M.S. 'N' Type Ventilator.Supply and fabricating and fixing in position of 'N'
type ventilators using M.S. angles of size 25x25x5mm for frame and M.S.Tee
of size 25x25x3mm M.S.flat of size 20x3mm for fixing the weld
mesh.Special type for hold fast welded to the frame of 45 degrees inclined
towards centre of wall and fixing the weldmesh 25mm size including 3 mm
thick pin headed glass for all panels and glass panels with necessary clips and
24 4.00 No
puttie with required bolts nuts and waste and one coat of red oxide primer
etc., including necessary dismantling , making holes in RCC
columns,beams,masonary wherever necessary with power drill to the extent
required and made good to the original condition after fixing as directed by
department officers. All materials should be got approved by the Executive
Engineer befor fixing in position.

ELECTRIFICATION

Wiring with 2x1.5 sqmm (22/0.3) PVC insulated SC unsheathed copper


conductor cable of 1100V grade in suitable heavy gauge MS conduit pipe on
wall and ceiling with MS accessories with switch box with 5A F.T. switch
25 50.00 m
inflush with wall and covered with hylum sheet of 3mm thick with painting of
suitable colour with continuous earth wire connection of 14 SWG TC wire for
light point / Fan point (For electronic Regulator) SD 2

OVER HEAD MAINS:Supply and run of 2 of 1.5sqmm (22/0.3) PVC


26 insulated SC unsheathed Cu.Conductor of 1100V grade on 7/20 GI bearer 14.00 No
wire for service connection mains.SD 64

Supply and fixing of TNEB meter Board suitable for 32A Three Phase service
connection with 3 Nos. 32A Fuse unit (500V) 32A neutral link and earth link
(1" x 1/8" Copper flat) on TW plank of size 600mm x 450mm x 19mm with
27 supporting TW reepers of 1" thick an either side with painting with suitable 1.00 No
bolt and nuts for fixing the TW plank on wall with earth connection and inter
connection with 7/20 PVC insulated copper wire from EB meter to fuse unit.
SD 127

Supply and fixing of 5A 3 pin and 2 pin combined flush type wall socket with
28 30.00 No
5A flush type switch on suitable TW box. SD 133

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 46

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 47

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 48

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


Detailed Cost Estimate Page 49

MT

DETAILED ESTIMATE CITYVIEW PLANNERS AND DESIGNERS


ABSTRACT ESTIMATE

NAME OF WORK :

CONSTRUCTION OF A SHOPPING COMPLEX BUILDING AT SF NO.


……………………………………………..…… IN PALLAPALAYAM, COIMBATORE
TAMILNADU.

ESTIMATE AMOUNT Rs

Sl.
Description of work Qty Rate Amount
No.

SUBSTRUCTURE

Earth work open excavation and depositing on


bank with in the initial lead of 10m and a lift of
2m in hard stiff clay, stiff block cotton, hard red
1 earth, shales, murram, gravel, stoney earth and
earth mixed with small size boulders etc.
complete. complying with std. specifications.SS
20 A(SI.no.61)

For Foundation 182.00 m³ 320.00 58240.00

Plinth beam 25.00 m³ 320.00 8000.00

Plain Cement Concrete 1:5:10 Mix (one part


cement, five part fine aggregate and ten part of
coarse aggregate) using 40 mm size ISS HBG
metal from approved quarry including cost and
2
conveyance of all materials to site. Loading and
unloading charges and labour charges for mixing,
Laying and curing etc. complete. Complying with
std. specifications.

For Foundation 15.00 m³ 3330.30 49954.50

Plinth beam 67.00 m2 3330.30 223130.10


Plain Cement Concrete 1:4:8 Mix (one part
cement, four part fine aggregate and Eight part of
aggregate) using 40 mm size ISS HBG metal from
approved quarry including cost and conveyance of
3 225.00 m2 3589.50 807637.50
all materials to site. Loading and unloading
charges and labour charges for mixing, Laying
and curing etc. complete. Complying with std.
specifications.

Reinforced Cement Concrete 1:1½:3 (M20) Mix


(One part cement, one and half part of Fine
aggregate and three part of Coarse aggregate)
using 20mm size ISS HBG metal machine crushed
from approved quarry including cost and
4 0.00
conveyance of all materials to site, loading and
unloading charges and labour charges for mixing,
laying and curing but excluding cost of
reinforcement etc. Complete with std.
Specifications.(Using Vibrator).

a) Upto basement

For Foundation 30.00 m³ 6981.31 209439.30

Column 3.00 m³ 6981.31 20943.93

Plinth beam 13.00 m³ 6981.31 90757.03

Tie / Grade beam 26.00 m³ 6981.31 181514.06

a) Ground floor ( Base + First Lift)

Column 8.00 m³ 6981.31 55850.48

Roof beam 16.00 m³ 6981.31 111700.96

Roof slab 37.00 m³ 6981.31 258308.47

Sill beam 122.00 m 6981.31 851719.82

Lintel beam 4.00 m³ 6981.31 27925.24


b) First floor (GF + Additional Lift)

Column 8.00 m³ 6981.31 55850.48

Roof beam 16.00 m³ 6981.31 111700.96

Roof slab 37.00 m³ 6981.31 258308.47

Sill beam 122.00 m 6981.31 851719.82

Lintel beam 4.00 m³ 6981.31 27925.24

c) Terrace floor (FF)

Headroom slab 3.00 m³ 6981.31 20943.93

Centering for sides and soffits of R.C.C. slab


surfaces such as beams, lintels roof slabs and
sunshades including cost and conveyance of all
5 0.00
materials to site and labour charges for centering
and strutting upto 3.00 m height etc. complete.
complying with std. specifications.

a) Upto basement

For Foundation 86.00 m2 690.61 59392.46

Column 42.00 m2 828.74 34807.08

Plinth beam 109.00 m2 608.59 66336.31

a) Ground floor ( Base + First Lift)

Column 124.00 m2 828.74 102763.76

Roof beam ( Side sheet ) 136.00 m2 690.61 93922.96

Roof beam ( Bottom sheet ) 41.00 m2 690.61 28315.01

Roof slab ( Side sheet ) 18.00 m2 690.61 12430.98

Roof slab ( Bottom sheet ) 119.00 m 0.00

b) First floor (GF + Additional Lift)

Column 124.00 m2 828.74 102763.76

Roof beam ( Side sheet ) 136.00 m2 690.61 93922.96

Roof beam ( Bottom sheet ) 41.00 m2 690.61 28315.01


Roof slab (Side sheet) 18.00 m2 690.61 12430.98

Roof slab (Bottom sheet) 119.00 m 0.00

c) Terrace floor (FF)

Headroom slab (Side sheet) 3.00 m2 690.61 2071.83

Headroom slab (Bottom sheet) 18.00 m 0.00

Providing two legged scaffolding using 15cm dia


blue-gum posts of 4.0m overall length (3M HT +
0.5M projection + 0.5m into ground) the distance
between two rows being 1.25m and the spacing of
postsbeling 2.0m and the spacing of postsbeling
2.0m in both the rows with two horizontal posts
6
with 0.5m overlap on either sideand braces at 2m
c/cincluding longitudinal and transverse middle
braces to step up and providing a platform with
country woodplanks of 40mm tk & 1.0m width in
a complete form using colr and nalls - 1.0m run --
FOR REJUVENATION WORKS

a) Up to 3m height 0.00

b) 3m + every 2.5m height 0.00

Supplying fabricating and placing in position of


steel rods using M.S. or Ribbed Tor Steel
including cost of binding wire, cost of labour
7 16.00 MT 41500.00 664000.00
charges for fabrication and placing in position
etc. Complete. Complying with std. specifications.
SUPER STRUCTURE

Brick Work in Cement Mortor 1:5 Mix (one


cement, five sand) using new best II Class Bricks
of size 9 ” x 4 3/8 “x 2 3/4 ” from approved
8 quarry including cost and conveyance of all
materials to site. Loading and unloading charges
and labour charges for mixing, laying and curing
etc. complete. Complying with std. specifications.

a) Upto basement

Brick on edge 144.00 m 5825.66 838895.04

For basement 26.00 m³ 5825.66 151467.16

b) Ground floor ( Base + First Lift) 60.00 m³ 5825.66 349539.60

d) Terrace floor (GF) 60.00 m³ 5825.66 349539.60

d) Second floor (FF + Additional Lift)

Parapet wall 17.00 m³ 5825.66 99036.22

FINISHING

Re-filling of Trenches with the excavated earth in


layers well rammed and consolidated and
depositing the surplus earth in all places with the
9 38.00 m³ 0.00
initial lead and lift including levelling, etc.,
complete. Complying with the standard
specification as directed

Collection, supply and filling of well gravel in


approved quarry including cost and Conveyance
10 182.00 m³ 165.85 30184.70
of all materials to site and all labour charges for
filling etc., Complete.

Plastering in Cement Mortor 1:3 Mix (one


cement, Three Fine aggregate) 12mm thick
including cost and conveyance of all materials to
11
site, loading and unloading charges and labour
charges for mixing, laying and curing etc.
complete. complying with std. specifications.
a) Ground floor ( Base + First Lift)

For ceiling 214.00 m2 192.02 41092.28

b) First floor (GF + Additional Lift)

For ceiling 214.00 m2 192.02 41092.28

d) Terrace floor (FF)

Headroom plastering 14.00 m2 192.02 2688.28

Plastering in Cement Mortor 1:4 Mix (one


Cement, four Fine aggregate) 20mm thick
including cost and conveyance of all materials to
12
site, loading and unloading charges and labour
charges for mixing, laying and curing etc.
complete. Complying with std. specifications.

a) Upto basement 43.00 m2 330.81 14224.83

b) Ground floor ( Base + First Lift) 552.00 m2 330.81 182607.12

c) First floor (GF + Additional Lift)

For Internal 552.00 m2 330.81 182607.12

d) Terrace floor (FF)

Parapet wall 14.00 m2 330.81 4631.34

Plastering in Cement Mortor 1:4 Mix (one


Cement, four sand) 20mm thick including cost
and conveyance of all materials to site, loading
13
and unloading charges and labour charges for
mixing, laying and curing etc. complete.
Complying with std. specifications.

External 507.00 m2 330.81 167720.67

Paving hydraulic pressed cement-Mosaic tiles of


approved colour and of size 200 mm x 200 mm x
20 mm with CM 1:3, 20 mm thick and pointed
14
with the same colour cement including polishing
with power polisher to a high degree of polish so
as to be perfectly smooth and gloossy for 10Sqm.

Ground floor 203.00 m2 0.00


First floor 203.00 m2 0.00

Laying with new C.C. Laminated tiles (Like Dora


tiles Eurocon tiles etc),(anti skid) of 20mm thick
of approved spl quality and set in Cement Mortar
1:3 (1 of cement and 3 of sand ) 20mm. Thick
15 using river sand and pointing with colour cement 11.00 m2 1002.13 11023.43
using at the rate of 0.40 kg/M2 and mixing with
colour pigment at the rate of 0.3 Kg/M2 including
finishing complete with Standard Specification
and as directed by the Departmental Officers etc.,

Finishing the top of roof with one course of


machine pressed tiles 20 C.m x 20 C.m x 2 C.m
size using cement mortor 1:3 mix mixed with 2%
16 by weight of Water proofing compound and 208.00 m2 727.42 151303.36
pointing with Cement Mortor 1:3 mix Cost of all
materials and labour charges and brick jelly
concrete.

Colour washing One coats with good quality of


Colour pigments including cost of all materials to
17 site and all other labour charges for mixing, 1625.00 m2 0.00
applying and proper curring etc., Complete as per
Standard Specifications.

PLUMBING & SANITATION

Supplying, laying and jointing P.V.C. pipes of


approved quality and best variety conformming to
I.S.S. and with I.S.I. mark, of the following sizes
including cutting threading and fixing P.V.C.
specials but excluding cost of such specials and
18
fixing to wall or drilling holes in roof and making
good the dismantled portions to original condition
with necessary brick work and plastering
wherever necessary with necessary scaffolding
charges.

For P.V.C. pipes of size :20mm ф 10.00 m 0.00


Supplying and fixing in position best Indian make
white glazed earthenware WASH HAND BASIN
of 550x400mm with a a pair of C.I. Brackets,
15mm dia C.P. Pillar tap, 32mm G.I. Waster water
pipe, 32mm dia C.P. Brass waster coupling, plug
with chain, 15mm dia PVC connection, 15mm
19 2.00 No 2200.00 4400.00
G.M. wheel valve with ISI mark and necessary
G.I. union and G.I. Elbow, including fixing wash
hand basin in position with white lead, clamps,
teakwood plugs, screws, rubber washer etc.,
complete without any leakage complying with
standard specifications.

Supplying and fixing in position Indian water


closet of size 580x440 mm, white glazed earthen
ware of approved quality with 'P' trap or 'S' trap
conforming to IS:2556-part XII with sand cushion
and forming flooring alround the closet using
40mm broken brick jelly in lime concrete 1:2:5
(one part of lime, two parts of fine aggregate and
five parts of brick jelly)100mm thick and
20 finishing the top to required slope and including 2.00 No 2353.53 4707.06
given necessary connection to cast iron soil pipes
by dismantling brick masonry, reinforced cement
concrete roof/floor slab and making good the
disturbed portion to orginal condition without
leakage etc., complete complying with standard
specificatios and as directed by the departmental
officers. (The water closet should br got approved
by the Executive Engineer before use on works).
Supplying and fixing in position colour glazed
European water closet with 'P' or 'S' trap and
double flapped seat cover, 12.50 litres capacity
P.V.C. low level flushing tank including all
internal fittings fixed on C.I. brackets, 12mm PVC
21 or brass nipple, chromium plated brown headed 2.00 No 0.00
stopcock, 12mm nylon connection with necessary
teakwood plugs, clamps, screws to the portion
coming with walls and floors, including
dismantling masonry and redoing the same to the
original condition.

Supplying and fixing of push and pull type


Rolling shutter confirming to IS 6248/1979 and as
amended from time to time. With ISI make of
approved size and section using 18 gauge
22 18.00 No 0.00
G.I.sheet.The shutter shall be painted with one
coat of red oxide primer and the rate is inclusive
of Hood covers , transportation charges etc., and
as directed by Engineer incharge.
Fabricating, supplying and fixing in positon of
SOLID PVC DOORS with frames of different
sizes as per the specifications given below: PVC
door frames made out of best quality PVC
extruded section of 40mm * 58 mm * 2.50 mm +/-
0.3 mm thick, having multichamber cross section
and duly reinforced with steel to be mitre cut at
the corners and welded including providing tie rod
at the bottom and necessary weather seal etc., and
PVC door shutters made out of extruded plastic
section of 60 mm * 24 mm size in the
configruation of an "A" section for shutter frames
23
and multi-chamber hollow plastic section of 200
mm *200 mm*1 mm (average thickness) with
tongue and groove section for panels etc., with
necessary holdfasts, rubber beedings, furniture
fittings, locking arrangements etc., complete
including dimantling the masnery, making
chippings, holes in the RCC column, beam etc.,
wherever necessary with power drill to the extent
required and redoing the same to the original
condition after fixing etc., complete as per
specifications and as directed by the departmental
officers.

a) Solid panel PVC Door with frame 3.00 No 0.00

b) Solid panel PVC Door with out frame 4.00 No 0.00


M.S. 'N' Type Ventilator.Supply and fabricating
and fixing in position of 'N' type ventilators using
M.S. angles of size 25x25x5mm for frame and
M.S.Tee of size 25x25x3mm M.S.flat of size
20x3mm for fixing the weld mesh.Special type for
hold fast welded to the frame of 45 degrees
inclined towards centre of wall and fixing the
weldmesh 25mm size including 3 mm thick pin
headed glass for all panels and glass panels with
24 4.00 No 0.00
necessary clips and puttie with required bolts nuts
and waste and one coat of red oxide primer etc.,
including necessary dismantling , making holes in
RCC columns,beams,masonary wherever
necessary with power drill to the extent required
and made good to the original condition after
fixing as directed by department officers. All
materials should be got approved by the Executive
Engineer befor fixing in position.

ELECTRIFICATION

Wiring with 2x1.5 sqmm (22/0.3) PVC insulated


SC unsheathed copper conductor cable of 1100V
grade in suitable heavy gauge MS conduit pipe on
wall and ceiling with MS accessories with switch
25 box with 5A F.T. switch inflush with wall and 50.00 m 0.00
covered with hylum sheet of 3mm thick with
painting of suitable colour with continuous earth
wire connection of 14 SWG TC wire for light
point / Fan point (For electronic Regulator) SD 2

OVER HEAD MAINS:Supply and run of 2 of


1.5sqmm (22/0.3) PVC insulated SC unsheathed
26 14.00 No 0.00
Cu.Conductor of 1100V grade on 7/20 GI bearer
wire for service connection mains.SD 64
Supply and fixing of TNEB meter Board suitable
for 32A Three Phase service connection with 3
Nos. 32A Fuse unit (500V) 32A neutral link and
earth link (1" x 1/8" Copper flat) on TW plank of
size 600mm x 450mm x 19mm with supporting
27 1.00 No 0.00
TW reepers of 1" thick an either side with
painting with suitable bolt and nuts for fixing the
TW plank on wall with earth connection and inter
connection with 7/20 PVC insulated copper wire
from EB meter to fuse unit. SD 127

Supply and fixing of 5A 3 pin and 2 pin combined


28 flush type wall socket with 5A flush type switch 30.00 No 0.00
on suitable TW box. SD 133

8209803.48
###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###

###
###

###

###

###

###

###

###

###

###

###

###

###

###