Professional Documents
Culture Documents
• Introduction
• Simplified Design Approach
• Determine response factor, R, for floor
• Check against acceptance criteria
• Plan B
Variable Dose Values
µr & µe
W
• Special cases
• Summary
2
Design of Floors for Vibration
Custom and practice
• Design beams to 4 Hz
• Loading = swt, c+s, 10% imposed
• This approach
• probability of adverse comment
• likelihood of resonant excitation
• prevents catastrophe
• gives no indication of performance
3
P354 – Design of Floors for Vibration
What’s inside?
4
P354 – Design of Floors for Vibration
What’s inside?
5
P354 – Design of Floors for Vibration
The BIG picture
• Calculate acceleration
• Compare with acceptance criteria
6
The BIG Picture
Check the frequency
fp/fn=0.67
1
2
1
f0 = = 3.1Hz
1 1
2
+ 2
5 4
1
f0 = = 2.8Hz
1 1 1
2
+ 2
+ 2
20 4 4
8
The BIG Picture
Calculate acceleration
0.1Q
aw,rms = µe µr Wρ
2 2Mζ
F
a=
m
9
• Introduction
• Simplified Design Approach
• Determine response factor, R, for floor
• Check against acceptance criteria
• Plan B
Variable Dose Values
µr & µe
W
• Special cases
• Summary
11
Determine Floor Response Factor, R
Frequency
• Element frequency
• Beams & slab 3Hz
• System/floor frequency
• f0 3Hz
• f0 > fp
• therefore resonance avoided
12
Determine Floor Response Factor, R
Define natural frequency of floor
13
Determine Floor Response Factor, R
Define natural frequency of floor
14
Determine Floor Response Factor, R
Define natural frequency of floor
15
Determine Floor Response Factor, R
Define natural frequency of floor
16
Determine Floor Response Factor, R
Define natural frequency of floor
17
Determine Floor Response Factor, R
Define natural frequency of floor
18
Determine Floor Response Factor, R
Define natural frequency of floor
19
Determine Floor Response Factor, R
Define natural frequency of floor
20
Determine Floor Response Factor, R
21
Determine Floor Response Factor, R
Check against minimum frequency values
• Element frequency
• Beams & slab 3Hz
• System/floor frequency
• f0 3Hz
• f0 > fp
• therefore resonance avoided
22
Determine Floor Response Factor, R
23
Determine Floor Response Factor, R
Determine modal mass
24
Determine Floor Response Factor, R
Determine modal mass
Note:
ny 4 &
nx 4
25
Determine Floor Response Factor, R
Determine modal mass
Note:
ny 4 &
nx 4
26
Determine Floor Response Factor, R
Determine response acceleration
27
Determine Floor Response Factor, R
Determine response acceleration
28
Determine Floor Response Factor, R
Determine response acceleration
29
Determine Floor Response Factor, R
Determine response acceleration
30
Determine Floor Response Factor, R
Determine response acceleration
31
Determine Floor Response Factor, R
Determine response acceleration
32
Determine Floor Response Factor, R
Determine response acceleration
33
Determine Floor Response Factor, R
Determine response acceleration
34
Determine Floor Response Factor, R
Determine response acceleration
35
Determine Floor Response Factor, R
36
Determine Floor Response Factor, R
37
• Introduction
• Simplified Design Approach
• Determine response factor, R, for floor
• Check against acceptance criteria
• Plan B
Variable Dose Values
µr & µe
W
• Special cases
• Summary
38
Check R Against Acceptance Criteria
Table 5.2
39
Check R Against Acceptance Criteria
Table 5.3
40
Theory & practice
Overall
Finishes
Beam depth f0
Bay size slab ζ
Project Sec/Pri R
(m) depth (Hz) (%)
(mm)
(mm)
625/571
Hospital 1 13.2 7.2 300 A 9.0 2.75 0.25
Cellular Beams
700/700
Hospital 2 15 x 7.5 175 A 4.9 0.50 0.58
Cellular Beams
St Richard’s 335+80
5.9 5.5 300ASB153/- E 9.5 1.30 0.29
Hospital screed
Sunderland
6.8 5.7 337 300ASB185/- B 9.6 4.80 0.54
Royal Infirmary
• Special cases
• Summary
42
Variable Dose Values
VDV’s
43
Variable Dose Values
VDV’s
44
Variable Dose Values
VDV’s
45
Variable Dose Values
VDV’s
46
Plan B
µe & µr
47
Plan B
W – Frequency Weighting
48
Plan B
W – Frequency Weighting
49
Plan B
W – Frequency Weighting
50
Determine Floor Response Factor, R
51
• Introduction
• Simplified Design Approach
• Determine response factor, R, for floor
• Check against acceptance criteria
• Plan B
Variable Dose Values
µr & µe
W
• Special cases
• Summary
52
Special Cases
53
Summary
ULS
• Check the Frequency
• Resonance ?
SLS
Check the Acceleration
Calculate Response
Compare to Multipliers
54