CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
01 OBRAS PROVICIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA 7.20x3.60 m und 1.00 350.00 350.00 350.00 1.00 100%
01.02 ALQUILER DE LOCAL PARA ALMACEN DE OBRA mes 3.00 300.00 900.00 150.00 0.50 17% 300.00 1.00 33%
01.03 FLETE TERRESTRE GLB 1.00 136,796.89 136,796.89 20519.53 0.15 15% 61558.60
01.04 FLETE RURAL GLB 1.00 65,584.72 65,584.72 65584.72 1.00 100%
01.05 ACARREO DE AGREGADO DESDE EL ALMACEN Dprom=0.50km m3 2,011.40 34.48 69,353.07 18048.85 523.46 26% 35245.00 1022.19 51%
01.06 TRANSPORTE DE EQUIPO Y MAQUINARIA A OBRA GLB 1.00 1,000.00 1,000.00 1000.00 1.00 100% 0.00 0%
01.07 PARANTES DE H=1.00 M. PROV. P/SEALIZACION Y PROTECCION und 10.00 73.67 736.70 632.67 8.59 86% 71.47 0.97 10%
01.08 CONO DE VIDRIO FOSFORESCENTE und 2.00 45.00 90.00 90.00 2.00 100% 0.00 0%
01.09 CINTA PLASTICA SEALIZADORA P/LIMITE DE SEGURIDAD DE OBRA m 100.00 5.65 565.00 556.75 98.54 99% 8.25 1.46 1%
01.10 PUENTE DE MADERA PROVISIONAL, PASE VEHICULAR Y PEATONAL SOBRE ZANJAS und 13.00 125.75 1,634.75 1634.75 13.00 100% 0.00 0%
01.11 SEGURIDAD Y SALUD EN OBRA GLB 0.30 59,083.58 17,725.07 17725.07 0.30 100% 0.00 0%
02 CAPTACION TIPO BARRAGE
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 9.00 2.40 21.60 21.60 9.00 100% 0.00 0%
02.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 9.00 5.04 45.36 45.36 9.00 100% 0.00 0%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 2.29 42.02 96.23 96.23 2.29 100% 0.00 0%
02.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.96 8.01 31.72 31.72 3.96 100% 0.00 0%
02.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.68 24.01 16.33 16.33 0.68 100% 0.00 0%
02.03 OBRAS DE CONCRETO SIMPLE
02.03.01 CONCRETO f'c=140 KG/CM2 m3 1.10 389.79 428.77 428.77 1.10 100% 0.00 0%
02.03.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 14.55 62.74 912.87 912.87 14.55 100% 0.00 0%
02.04 OBRAS DE CONCRETO ARMADO
02.04.01 CONCRETO f'c=175 KG/CM2, EN CAPTACION m3 1.07 425.25 455.02 455.02 1.07 100% 0.00 0%
02.04.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 11.76 62.74 737.82 737.82 11.76 100% 0.00 0%
02.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 430.89 6.18 2,662.90 2662.90 430.89 100% 0.00 0%
02.05 TARRAJEO EN CAPTACIONES
02.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 2.52 28.46 71.72 71.72 2.52 100% 0.00 0%
02.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 19.66 22.64 445.10 445.10 19.66 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
01 OBRAS PROVICIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA 7.20x3.60 m und 1.00 350.00 350.00
01.02 ALQUILER DE LOCAL PARA ALMACEN DE OBRA mes 3.00 300.00 900.00 300 1.00 33% 150.00 0.50 17%
01.03 FLETE TERRESTRE GLB 1.00 136,796.89 136,796.89 54718.756 0.40 40%
01.04 FLETE RURAL GLB 1.00 65,584.72 65,584.72
01.05 ACARREO DE AGREGADO DESDE EL ALMACEN Dprom=0.50km m3 2,011.40 34.48 69,353.07 16059.22 465.75 23%
01.06 TRANSPORTE DE EQUIPO Y MAQUINARIA A OBRA GLB 1.00 1,000.00 1,000.00 0.00 0%
01.07 PARANTES DE H=1.00 M. PROV. P/SEALIZACION Y PROTECCION und 10.00 73.67 736.70 32.56 0.44 4%
01.08 CONO DE VIDRIO FOSFORESCENTE und 2.00 45.00 90.00 0.00 0%
01.09 CINTA PLASTICA SEALIZADORA P/LIMITE DE SEGURIDAD DE OBRA m 100.00 5.65 565.00 0.00 0%
01.10 PUENTE DE MADERA PROVISIONAL, PASE VEHICULAR Y PEATONAL SOBRE ZANJAS und 13.00 125.75 1,634.75 0.00 0%
01.11 SEGURIDAD Y SALUD EN OBRA GLB 0.30 59,083.58 17,725.07 0.00 0%
02 CAPTACION TIPO BARRAGE
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 9.00 2.40 21.60 0.00 0%
02.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 9.00 5.04 45.36 0.00 0%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 2.29 42.02 96.23 0.00 0%
02.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.96 8.01 31.72 0.00 0%
02.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.68 24.01 16.33 0.00 0%
02.03 OBRAS DE CONCRETO SIMPLE
02.03.01 CONCRETO f'c=140 KG/CM2 m3 1.10 389.79 428.77 0.00 0%
02.03.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 14.55 62.74 912.87 0.00 0%
02.04 OBRAS DE CONCRETO ARMADO
02.04.01 CONCRETO f'c=175 KG/CM2, EN CAPTACION m3 1.07 425.25 455.02 0.00 0%
02.04.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 11.76 62.74 737.82 0.00 0%
02.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 430.89 6.18 2,662.90 0.00 0%
02.05 TARRAJEO EN CAPTACIONES
02.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 2.52 28.46 71.72 0.00 0%
02.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 19.66 22.64 445.10 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
02.05.03 CURADO DE CONCRETO m2 22.18 3.61 80.07 80.07 22.18 100% 0.00 0%
02.06 VALVULAS Y ACCESORIOS EN CAPTACION
02.06.01 SUMINISTRO E INSTALACION DE VALVULAS Y ACCESORIOS EN CAPTACION und 1.00 1,026.40 1,026.40 1026.40 1.00 100% 0.00 0%
02.06.02 PINTURA EN MUROS EXTERIORES m2 19.66 15.21 299.03 299.03 19.66 100% 0.00 0%
02.07 VARIOS
02.07.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 2.00 216.77 433.54 433.54 2.00 100% 0.00 0%
02.07.02 TAPA SANITARIA METALICA DE 0.40x0.40 M und 1.00 216.77 216.77 216.77 1.00 100% 0.00 0%
02.07.03 CERCO DE PROTECCION DE ESTRUCTURAS m 30.00 11.95 358.50 358.50 30.00 100% 0.00 0%
02.07.04 PIEDRA ASENTADA CON MORTERO 1:8 CEMENTO HORMIGON m2 0.72 322.29 232.05 232.05 0.72 100% 0.00 0%
02.07.05 FILTRO DE GRAVAS m3 1.35 72.44 97.79 97.79 1.35 100% 0.00 0%
03 PASE AEREO L=40 M
03.01 TRABAJOS PRELIMINARES
03.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 400.00 2.40 960.00 960.00 400.00 100% 0.00 0%
03.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 400.00 5.04 2,016.00 2016.00 400.00 100% 0.00 0%
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 77.50 42.02 3,256.55 3256.55 77.50 100% 0.00 0%
03.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 12.50 8.01 100.13 100.13 12.50 100% 0.00 0%
03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 32.81 24.01 787.77 787.77 32.81 100% 0.00 0%
03.03 OBRAS DE CONCRETO SIMPLE
03.03.01 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. PARA DADOS DE APOYO m3 5.00 1,503.07 7,515.35 7515.35 5.00 100% 0.00 0%
03.04 OBRAS DE CONCRETO ARMADO
03.04.01 CONCRETO f'c=140 KG/CM2 PARA ZAPATAS m3 15.00 446.83 6,702.45 6702.45 15.00 100% 0.00 0%
03.04.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 190.46 6.18 1,177.04 1177.04 190.46 100% 0.00 0%
03.04.03 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 3.08 469.08 1,444.77 0.00 0% 1444.77 3.08 100%
03.04.04 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 27.72 52.90 1,466.39 1230.00 23.25 84% 236.39 4.47 16%
03.04.05 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 415.87 6.33 2,632.46 2632.46 415.87 100% 0.00 0%
03.05 MONTAJE EN PENDOLAS Y CABLES
03.05.01 PENDOLA DE ACERO D=1/4" INC. INS. m 67.87 9.53 646.80 0.00 0% 646.80 67.87 100%
03.05.02 TABLERO DE CABLE VIGA H INC. VIGAS H L=1.30 M und 2.00 575.60 1,151.20 0.00 0% 1151.20 2.00 100%
03.05.03 SUMINISTRO E INSTALACION DE ABRAZADERA und 20.00 40.42 808.40 0.00 0% 808.40 20.00 100%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
02.05.03 CURADO DE CONCRETO m2 22.18 3.61 80.07 0.00 0%
02.06 VALVULAS Y ACCESORIOS EN CAPTACION
02.06.01 SUMINISTRO E INSTALACION DE VALVULAS Y ACCESORIOS EN CAPTACION und 1.00 1,026.40 1,026.40 0.00 0%
02.06.02 PINTURA EN MUROS EXTERIORES m2 19.66 15.21 299.03 0.00 0%
02.07 VARIOS
02.07.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 2.00 216.77 433.54 0.00 0%
02.07.02 TAPA SANITARIA METALICA DE 0.40x0.40 M und 1.00 216.77 216.77 0.00 0%
02.07.03 CERCO DE PROTECCION DE ESTRUCTURAS m 30.00 11.95 358.50 0.00 0%
02.07.04 PIEDRA ASENTADA CON MORTERO 1:8 CEMENTO HORMIGON m2 0.72 322.29 232.05 0.00 0%
02.07.05 FILTRO DE GRAVAS m3 1.35 72.44 97.79 0.00 0%
03 PASE AEREO L=40 M
03.01 TRABAJOS PRELIMINARES
03.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 400.00 2.40 960.00 0.00 0%
03.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 400.00 5.04 2,016.00 0.00 0%
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 77.50 42.02 3,256.55 0.00 0%
03.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 12.50 8.01 100.13 0.00 0%
03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 32.81 24.01 787.77 0.00 0%
03.03 OBRAS DE CONCRETO SIMPLE
03.03.01 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. PARA DADOS DE APOYO m3 5.00 1,503.07 7,515.35 0.00 0%
03.04 OBRAS DE CONCRETO ARMADO
03.04.01 CONCRETO f'c=140 KG/CM2 PARA ZAPATAS m3 15.00 446.83 6,702.45 0.00 0%
03.04.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 190.46 6.18 1,177.04 0.00 0%
03.04.03 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 3.08 469.08 1,444.77 0.00 0%
03.04.04 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 27.72 52.90 1,466.39 0.00 0%
03.04.05 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 415.87 6.33 2,632.46 0.00 0%
03.05 MONTAJE EN PENDOLAS Y CABLES
03.05.01 PENDOLA DE ACERO D=1/4" INC. INS. m 67.87 9.53 646.80 0.00 0%
03.05.02 TABLERO DE CABLE VIGA H INC. VIGAS H L=1.30 M und 2.00 575.60 1,151.20 0.00 0%
03.05.03 SUMINISTRO E INSTALACION DE ABRAZADERA und 20.00 40.42 808.40 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
03.05.04 CABLE DE ACERO TIPO BOA D=5/8" INC. INSTALACION m 43.87 28.62 1,255.56 0.00 0% 1255.56 43.87 100%
03.06 REVOQUES Y ENLUCIDOS
03.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 27.72 22.64 627.58 0.00 0% 627.58 27.72 100%
03.07 PINTURA
03.07.01 PINTURA ANTICORROSIVA EN PENDOLAS Y CABLES m2 111.74 11.73 1,310.71 0.00 0% 1310.71 111.74 100%
04 CAMARA ROMPE PRESION
04.01 TRABAJOS PRELIMINARES
04.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 14.67 1.50 22.01 22.01 14.67 100% 0.00 0%
04.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 14.67 5.04 73.94 65.12 12.92 88% 8.82 1.75 12%
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.97 42.02 671.06 0.00 0% 671.06 15.97 100%
04.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 16.83 8.01 134.81 0.00 0% 134.81 16.83 100%
04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 19.96 24.01 479.24 0.00 0% 479.24 19.96 100%
04.03 OBRAS DE CONCRETO SIMPLE
04.03.01 SOLADO E=2" MEZCLA 1:12 C:H m2 12.15 40.80 495.72 0.00 0% 495.72 12.15 100%
04.04 OBRAS DE CONCRETO ARMADO
04.04.01 CONCRETO f'c=210 KG/CM2 EN CAMARA ROMPE PRESION m3 8.26 433.46 3,580.38 0.00 0% 3,580.38 8.26 100%
04.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA ROMPE PRESION m2 61.38 51.55 3,164.14 0.00 0% 3,164.14 61.38 100%
04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 372.97 6.05 2,256.47 0.00 0% 2256.47 372.97 100%
04.05 REVOQUES Y ENLUCIDOS
04.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 17.64 28.46 502.03 0.00 0% 502.03 17.64 100%
04.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 49.14 22.64 1,112.53 0.00 0% 1,112.53 49.14 100%
04.05.03 CURADO DE CONCRETO m2 66.78 3.61 241.08 0.00 0% 241.08 66.78 100%
04.06 OTROS
04.06.01 ACCESORIOS CRP-6, TUB. INGRESO, SALIDA Y REBOSE, Lc=3 1/2" und 4.00 315.55 1,262.20 0.00 0% 1,262.20 4.00 100%
04.06.02 ACCESORIOS INGRESO CRP-7, LD=3 1/2" und 3.00 1,063.34 3,190.02 0.00 0% 3,190.02 3.00 100%
04.06.03 ACCESORIOS INGRESO CRP-7, LD=2 1/2" und 2.00 676.00 1,352.00 0.00 0% 1352 2.00 100%
04.06.04 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=3 1/2" und 3.00 155.66 466.98 0.00 0% 466.98 3.00 100%
04.06.05 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=2 1/2" und 2.00 126.85 253.70 0.00 0% 253.7 2.00 100%
04.06.06 SISTEMA DE VENTILACION - CRP und 9.00 20.94 188.46 0.00 0% 188.46 9.00 100%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
03.05.04 CABLE DE ACERO TIPO BOA D=5/8" INC. INSTALACION m 43.87 28.62 1,255.56 0.00 0%
03.06 REVOQUES Y ENLUCIDOS
03.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 27.72 22.64 627.58 0.00 0%
03.07 PINTURA
03.07.01 PINTURA ANTICORROSIVA EN PENDOLAS Y CABLES m2 111.74 11.73 1,310.71 0.00 0%
04 CAMARA ROMPE PRESION
04.01 TRABAJOS PRELIMINARES
04.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 14.67 1.50 22.01 0.00 0%
04.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 14.67 5.04 73.94 0.00 0%
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.97 42.02 671.06 0.00 0%
04.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 16.83 8.01 134.81 0.00 0%
04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 19.96 24.01 479.24 0.00 0%
04.03 OBRAS DE CONCRETO SIMPLE
04.03.01 SOLADO E=2" MEZCLA 1:12 C:H m2 12.15 40.80 495.72 0.00 0%
04.04 OBRAS DE CONCRETO ARMADO
04.04.01 CONCRETO f'c=210 KG/CM2 EN CAMARA ROMPE PRESION m3 8.26 433.46 3,580.38 0.00 0%
04.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA ROMPE PRESION m2 61.38 51.55 3,164.14 0.00 0%
04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 372.97 6.05 2,256.47 0.00 0%
04.05 REVOQUES Y ENLUCIDOS
04.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 17.64 28.46 502.03 0.00 0%
04.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 49.14 22.64 1,112.53 0.00 0%
04.05.03 CURADO DE CONCRETO m2 66.78 3.61 241.08 0.00 0%
04.06 OTROS
04.06.01 ACCESORIOS CRP-6, TUB. INGRESO, SALIDA Y REBOSE, Lc=3 1/2" und 4.00 315.55 1,262.20 0.00 0%
04.06.02 ACCESORIOS INGRESO CRP-7, LD=3 1/2" und 3.00 1,063.34 3,190.02 0.00 0%
04.06.03 ACCESORIOS INGRESO CRP-7, LD=2 1/2" und 2.00 676.00 1,352.00 0.00 0%
04.06.04 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=3 1/2" und 3.00 155.66 466.98 0.00 0%
04.06.05 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=2 1/2" und 2.00 126.85 253.70 0.00 0%
04.06.06 SISTEMA DE VENTILACION - CRP und 9.00 20.94 188.46 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
05 POZA DE FILTRACION
05.01 TRABAJOS PRELIMINARES
05.01.01 TRAZO, NIVELACION Y REPLANTEO m2 88.40 2.77 244.87 0.00 0% 244.87 88.40 100%
05.01.02 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 88.40 2.40 212.16 0.00 0% 212.16 88.40 100%
05.02 MOVIMIENTO DE TIERRAS
05.02.01 EXCAVACION DE ZANJAS PARA ESTRUCTURA EN TERRENO SEMI-ROCOSO m3 282.54 14.67 4,144.86 0.00 0% 4144.86 282.54 100%
05.02.02 REFINE Y NIVELACION EN TERRENO SEMI ROCOSO m2 87.75 4.01 351.88 0.00 0% 351.88 87.75 100%
05.02.03 FILTRO DE GRAVA DE 3/4" A 1 1/2" m3 72.00 167.10 12,031.20 0.00 0% 0.00 0%
05.02.04 ELIMINACION DE MATERIAL EXCEDENTE HASTA D=30 MTS. MANUAL C/CARRETILLA m3 353.18 11.43 4,036.85 0.00 0% 4036.85 353.18 100%
05.03 OBRAS DE CONCRETO SIMPLE
05.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 88.40 36.01 3,183.28 0.00 0% 3183.28 88.40 100%
05.03.02 DADOS DE CONCRETO SIMPLE DE 0.40x0.40x0.60, INCLUYE COLOCACION DE MADERA 4"x8" m 4.00 20.32 81.28 0.00 0% 81.28 4.00 100%
05.04 OBRAS DE CONCRETO ARMADO
05.04.01 LOSA DE FONDO
05.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 19.52 486.26 9,491.80 0.00 0% 9491.80 19.52 100%
05.04.01.02 ENCOFRADO Y DESENCOFRADO PARA LOSA DE FONDO m2 24.48 48.23 1,180.67 0.00 0% 1180.67 24.48 100%
05.04.01.03 ACERO ESTRUCTURAL TRABAJADO PARA LOSA DE FONDO kg 972.16 6.33 6,153.77 0.00 0% 6153.77 972.16 100%
05.04.02 MUROS REFORZADOS
05.04.02.01 ENCOFRADO Y DESENCOFRADO PARA MUROS m2 321.23 47.68 15,316.25 0.00 0% 15316.25 321.23 100%
05.04.02.02 CONCRETO f'c= 210 KG/CM2 PARA MUROS REFORZADOS m3 39.13 475.06 18,589.10 0.00 0% 18589.10 39.13 100%
05.04.02.03 ACERO ESTRUCTURAL TRABAJADO PARA MUROS REFORZADOS kg 521.56 6.24 3,254.53 0.00 0% 3254.53 521.56 100%
05.04.03 COLUMNAS
05.04.03.01 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 4.29 424.28 1,820.16 0.00 0% 1820.16 4.29 100%
05.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 42.88 49.81 2,135.85 0.00 0% 2135.85 42.88 100%
05.04.03.03 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 383.95 6.33 2,430.40 0.00 0% 2430.40 383.95 100%
05.04.04 VIGAS
05.04.04.01 CONCRETO f'c=175 KG/CM2 PARA VIGAS m3 3.58 424.28 1,518.92 0.00 0% 1518.92 3.58 100%
05.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS m2 71.68 49.81 3,570.38 0.00 0% 3570.38 71.68 100%
05.04.04.03 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg 265.73 6.33 1,682.07 0.00 0% 1682.07 265.73 100%
05.05 MURO DE ALBAILERIA
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
05 POZA DE FILTRACION
05.01 TRABAJOS PRELIMINARES
05.01.01 TRAZO, NIVELACION Y REPLANTEO m2 88.40 2.77 244.87 0.00 0%
05.01.02 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 88.40 2.40 212.16 0.00 0%
05.02 MOVIMIENTO DE TIERRAS
05.02.01 EXCAVACION DE ZANJAS PARA ESTRUCTURA EN TERRENO SEMI-ROCOSO m3 282.54 14.67 4,144.86 0.00 0%
05.02.02 REFINE Y NIVELACION EN TERRENO SEMI ROCOSO m2 87.75 4.01 351.88 0.00 0%
05.02.03 FILTRO DE GRAVA DE 3/4" A 1 1/2" m3 72.00 167.10 12,031.20 12031.2 72.00 100%
05.02.04 ELIMINACION DE MATERIAL EXCEDENTE HASTA D=30 MTS. MANUAL C/CARRETILLA m3 353.18 11.43 4,036.85 0.00 0%
05.03 OBRAS DE CONCRETO SIMPLE
05.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 88.40 36.01 3,183.28 0.00 0%
05.03.02 DADOS DE CONCRETO SIMPLE DE 0.40x0.40x0.60, INCLUYE COLOCACION DE MADERA 4"x8" m 4.00 20.32 81.28 0.00 0%
05.04 OBRAS DE CONCRETO ARMADO
05.04.01 LOSA DE FONDO
05.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 19.52 486.26 9,491.80 0.00 0%
05.04.01.02 ENCOFRADO Y DESENCOFRADO PARA LOSA DE FONDO m2 24.48 48.23 1,180.67 0.00 0%
05.04.01.03 ACERO ESTRUCTURAL TRABAJADO PARA LOSA DE FONDO kg 972.16 6.33 6,153.77 0.00 0%
05.04.02 MUROS REFORZADOS
05.04.02.01 ENCOFRADO Y DESENCOFRADO PARA MUROS m2 321.23 47.68 15,316.25 0.00 0%
05.04.02.02 CONCRETO f'c= 210 KG/CM2 PARA MUROS REFORZADOS m3 39.13 475.06 18,589.10 0.00 0%
05.04.02.03 ACERO ESTRUCTURAL TRABAJADO PARA MUROS REFORZADOS kg 521.56 6.24 3,254.53 0.00 0%
05.04.03 COLUMNAS
05.04.03.01 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 4.29 424.28 1,820.16 0.00 0%
05.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 42.88 49.81 2,135.85 0.00 0%
05.04.03.03 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 383.95 6.33 2,430.40 0.00 0%
05.04.04 VIGAS
05.04.04.01 CONCRETO f'c=175 KG/CM2 PARA VIGAS m3 3.58 424.28 1,518.92 0.00 0%
05.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS m2 71.68 49.81 3,570.38 0.00 0%
05.04.04.03 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg 265.73 6.33 1,682.07 0.00 0%
05.05 MURO DE ALBAILERIA
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
05.05.01 MURO DE CABEZA LADRILLO KING KONG DE ARCILLA CON CEMENTO-ARENA m2 33.60 96.96 3,257.86 0.00 0% 3257.86 33.60 100%
05.06 REVOQUES Y ENLUCIDOS
05.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 212.40 28.46 6,044.90 0.00 0% 4604.01 161.77 76%
05.06.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 109.00 22.64 2,467.76 0.00 0% 2344.56 103.56 95%
05.07 TUBERIAS Y ACCESORIOS
05.07.01 COMPUERTA MANUAL DE MADERA 0.30x0.60 M und 2.00 823.71 1,647.42 0.00 0% 0.00 0%
05.07.02 EQUIPO CON TUBOS Y VALVULA GLB 1.00 3,634.70 3,634.70 0.00 0% 0.00 0%
06 RESERVORIO CIRCULAR APOYADO V=55 m3
06.01 TRABAJOS PRELIMINARES
06.01.01 TRAZO, NIVELACION Y REPLANTEO m2 19.64 2.77 54.40 0.00 0% 54.40 19.64 100%
06.01.02 LIMPIEZA DEL TERRENO MANUAL m2 19.64 2.40 47.14 0.00 0% 41.25 17.19 88%
06.02 MOVIMIENTO DE TIERRAS
06.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 13.99 42.02 587.86 0.00 0% 0.00 0%
06.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 18.85 8.01 150.99 0.00 0% 0.00 0%
06.02.03 CONFORMACION DE SUB RASANTE PARA PISOS Y VEREDAS m3 19.64 5.14 100.95 0.00 0% 0.00 0%
06.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 17.48 24.01 419.69 0.00 0% 0.00 0%
06.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 17.48 23.55 411.65 0.00 0% 0.00 0%
06.03 OBRAS DE CONCRETO SIMPLE
06.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 3.93 36.01 141.52 0.00 0% 0.00 0%
06.04 OBRAS DE CONCRETO ARMADO
06.04.01 VIGA CIRCULAR INFERIOR
06.04.01.01 CONCRETO f'c=245 KG/CM2 m3 5.66 471.42 2,668.24 0.00 0% 0.00 0%
06.04.01.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 371.44 6.05 2,247.21 0.00 0% 0.00 0%
06.04.01.03 CURADO DE CONCRETO m2 9.43 3.61 34.04 0.00 0% 0.00 0%
06.04.02 LOSA DE FONDO
06.04.02.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 3.93 472.06 1,855.20 0.00 0% 0.00 0%
06.04.02.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 373.96 6.05 2,262.46 0.00 0% 0.00 0%
06.04.02.03 CURADO DE CONCRETO m2 95.03 3.61 343.06 0.00 0% 0.00 0%
06.04.03 MURO CILINDRICO
06.04.03.01 CONCRETO f'c=245 KG/CM2 m3 7.25 471.42 3,417.80 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
05.05.01 MURO DE CABEZA LADRILLO KING KONG DE ARCILLA CON CEMENTO-ARENA m2 33.60 96.96 3,257.86 0.00 0%
05.06 REVOQUES Y ENLUCIDOS
05.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 212.40 28.46 6,044.90 1,440.89 50.63 24%
05.06.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 109.00 22.64 2,467.76 123.2 5.44 5%
05.07 TUBERIAS Y ACCESORIOS
05.07.01 COMPUERTA MANUAL DE MADERA 0.30x0.60 M und 2.00 823.71 1,647.42 1,647.42 2.00 100%
05.07.02 EQUIPO CON TUBOS Y VALVULA GLB 1.00 3,634.70 3,634.70 3,634.70 1.00 100%
06 RESERVORIO CIRCULAR APOYADO V=55 m3
06.01 TRABAJOS PRELIMINARES
06.01.01 TRAZO, NIVELACION Y REPLANTEO m2 19.64 2.77 54.40 0.00 0%
06.01.02 LIMPIEZA DEL TERRENO MANUAL m2 19.64 2.40 47.14 5.89 2.45 12%
06.02 MOVIMIENTO DE TIERRAS
06.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 13.99 42.02 587.86 587.86 13.99 100%
06.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 18.85 8.01 150.99 150.99 18.85 100%
06.02.03 CONFORMACION DE SUB RASANTE PARA PISOS Y VEREDAS m3 19.64 5.14 100.95 100.95 19.64 100%
06.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 17.48 24.01 419.69 419.69 17.48 100%
06.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 17.48 23.55 411.65 411.65 17.48 100%
06.03 OBRAS DE CONCRETO SIMPLE
06.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 3.93 36.01 141.52 141.52 3.93 100%
06.04 OBRAS DE CONCRETO ARMADO
06.04.01 VIGA CIRCULAR INFERIOR
06.04.01.01 CONCRETO f'c=245 KG/CM2 m3 5.66 471.42 2,668.24 2,668.24 5.66 100%
06.04.01.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 371.44 6.05 2,247.21 2,247.21 371.44 100%
06.04.01.03 CURADO DE CONCRETO m2 9.43 3.61 34.04 34.04 9.43 100% 0.00 0%
06.04.02 LOSA DE FONDO
06.04.02.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 3.93 472.06 1,855.20 1,855.20 3.93 100% 0.00 0%
06.04.02.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 373.96 6.05 2,262.46 2262.46 373.96 100% 0.00 0%
06.04.02.03 CURADO DE CONCRETO m2 95.03 3.61 343.06 343.06 95.03 100% 0.00 0%
06.04.03 MURO CILINDRICO
06.04.03.01 CONCRETO f'c=245 KG/CM2 m3 7.25 471.42 3,417.80 3417.8 7.25 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
06.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE MURO CILINDRICO m2 111.54 69.07 7,704.07 0.00 0% 0.00 0%
06.04.03.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 1,368.79 6.05 8,281.18 0.00 0% 0.00 0%
06.04.03.04 CURADO DE CONCRETO m2 111.54 3.61 402.66 0.00 0% 0.00 0%
06.04.04 VIGA CIRCULAR SUPERIOR
06.04.04.01 CONCRETO f'c=245 KG/CM2 m3 3.73 471.42 1,758.40 0.00 0% 0.00 0%
06.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGA CIRCULAR SUPERIOR m2 12.57 69.07 868.21 0.00 0% 0.00 0%
06.04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 214.51 6.05 1,297.79 0.00 0% 0.00 0%
06.04.04.04 CURADO DE CONCRETO m2 12.57 3.61 45.38 0.00 0% 0.00 0%
06.04.05 CUPULA
06.04.05.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 2.36 472.06 1,114.06 0.00 0% 0.00 0%
06.04.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE CUPULA m2 23.62 69.07 1,631.43 0.00 0% 0.00 0%
06.04.05.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 461.93 6.05 2,794.68 0.00 0% 0.00 0%
06.04.05.04 CURADO DE CONCRETO m2 23.62 3.61 85.27 0.00 0% 0.00 0%
06.04.06 VERTEDERO
06.04.06.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 0.18 472.06 84.97 0.00 0% 0.00 0%
06.04.06.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VERTEDERO m2 2.60 69.07 179.58 0.00 0% 0.00 0%
06.04.06.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 17.17 6.05 103.88 0.00 0% 0.00 0%
06.04.06.04 CURADO DE CONCRETO m2 2.60 3.61 9.39 0.00 0% 0.00 0%
06.05 REVOQUES Y ENLUCIDOS
06.05.01 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 20.79 28.10 584.20 0.00 0% 0.00 0%
06.05.02 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 110.52 28.10 3,105.61 0.00 0% 0.00 0%
06.05.03 MORTERO 1:3 + IMPERMEABILIZANTE P/JUNTA DE CONSTRUCCION m3 151.52 29.80 4,515.30 0.00 0% 0.00 0%
06.06 PINTURA
06.06.01 PINTADO DE MUROS DE CUBA CON SIKATOP 144 O SIMILAR m2 221.04 15.04 3,324.44 0.00 0% 0.00 0%
06.07 DOBLE PRUEBA HIDRAULICA
06.07.01 PRUEBA HIDRAULICA C/EMPLEO DE LA LINEA DE INGRESO(CAPTACION) m 55.00 11.25 618.75 0.00 0% 0.00 0%
06.07.02 EVACUACION AGUA DE PRUEBA C/EMPLEO DE LINEA DE SALIDA m 55.00 1.01 55.55 0.00 0% 0.00 0%
06.07.03 LIMPIEZA Y DESINFECCION DE RESERVORIOS APOYADOS und 229.81 1.38 317.14 0.00 0% 0.00 0%
06.08 CARPINTERIA METALICA
06.08.01 ESCALERA TUB. F. GVZDO. C/PARANTES DE 2" X PELDAOS DE 3/4" und 10.00 172.34 1,723.40 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
06.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE MURO CILINDRICO m2 111.54 69.07 7,704.07 7704.07 111.54 100% 0.00 0%
06.04.03.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 1,368.79 6.05 8,281.18 8281.18 1368.79 100% 0.00 0%
06.04.03.04 CURADO DE CONCRETO m2 111.54 3.61 402.66 402.66 111.54 100% 0.00 0%
06.04.04 VIGA CIRCULAR SUPERIOR
06.04.04.01 CONCRETO f'c=245 KG/CM2 m3 3.73 471.42 1,758.40 1758.4 3.73 100% 0.00 0%
06.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGA CIRCULAR SUPERIOR m2 12.57 69.07 868.21 868.21 12.57 100% 0.00 0%
06.04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 214.51 6.05 1,297.79 1297.79 214.51 100% 0.00 0%
06.04.04.04 CURADO DE CONCRETO m2 12.57 3.61 45.38 45.38 12.57 100% 0.00 0%
06.04.05 CUPULA
06.04.05.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 2.36 472.06 1,114.06 1114.06 2.36 100% 0.00 0%
06.04.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE CUPULA m2 23.62 69.07 1,631.43 1631.43 23.62 100% 0.00 0%
06.04.05.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 461.93 6.05 2,794.68 2794.68 461.93 100% 0.00 0%
06.04.05.04 CURADO DE CONCRETO m2 23.62 3.61 85.27 85.27 23.62 100% 0.00 0%
06.04.06 VERTEDERO
06.04.06.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 0.18 472.06 84.97 84.97 0.18 100% 0.00 0%
06.04.06.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VERTEDERO m2 2.60 69.07 179.58 179.58 2.60 100% 0.00 0%
06.04.06.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 17.17 6.05 103.88 103.88 17.17 100% 0.00 0%
06.04.06.04 CURADO DE CONCRETO m2 2.60 3.61 9.39 9.39 2.60 100% 0.00 0%
06.05 REVOQUES Y ENLUCIDOS
06.05.01 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 20.79 28.10 584.20 584.2 20.79 100% 0.00 0%
06.05.02 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 110.52 28.10 3,105.61 3105.61 110.52 100% 0.00 0%
06.05.03 MORTERO 1:3 + IMPERMEABILIZANTE P/JUNTA DE CONSTRUCCION m3 151.52 29.80 4,515.30 4515.3 151.52 100% 0.00 0%
06.06 PINTURA
06.06.01 PINTADO DE MUROS DE CUBA CON SIKATOP 144 O SIMILAR m2 221.04 15.04 3,324.44 3,324.44 221.04 100% 0.00 0%
06.07 DOBLE PRUEBA HIDRAULICA
06.07.01 PRUEBA HIDRAULICA C/EMPLEO DE LA LINEA DE INGRESO(CAPTACION) m 55.00 11.25 618.75 618.75 55.00 100% 0.00 0%
06.07.02 EVACUACION AGUA DE PRUEBA C/EMPLEO DE LINEA DE SALIDA m 55.00 1.01 55.55 55.55 55.00 100% 0.00 0%
06.07.03 LIMPIEZA Y DESINFECCION DE RESERVORIOS APOYADOS und 229.81 1.38 317.14 317.14 229.81 100% 0.00 0%
06.08 CARPINTERIA METALICA
06.08.01 ESCALERA TUB. F. GVZDO. C/PARANTES DE 2" X PELDAOS DE 3/4" und 10.00 172.34 1,723.40 1,723.40 10.00 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
06.08.02 MARCO Y TAPA PLANCHA LAC 1/4" C/MECANISM. DE SEG. S/DISEO und 1.00 286.40 286.40 0.00 0% 0.00 0%
06.08.03 VENTILACION C/TUBERIA DE ACERO S/DISEO DE 4" und 4.00 55.72 222.88 0.00 0% 0.00 0%
06.08.04 SOPORTE METALICO T/ABRAZADERA P/TUB. DE DIAMETRO 8"-10" und 4.00 44.91 179.64 0.00 0% 0.00 0%
06.08.05 CANDADO INCLUYE ALDABAS und 3.00 65.14 195.42 0.00 0% 0.00 0%
06.09 VEREDAS
06.09.01 VEREDA DE CONCRETO f'c=140 KG/CM2 E=10 CM m2 25.00 64.13 1,603.25 0.00 0% 0.00 0%
06.09.02 CURADO DE CONCRETO PARA VEREDAS m2 40.00 2.31 92.40 0.00 0% 0.00 0%
06.09.03 JUNTAS ASFALTICAS EN VEREDAS m 18.00 10.47 188.46 0.00 0% 0.00 0%
06.10 JUNTAS DE DILATACION
06.10.01 WATER STOP DE PVC DE 6". PROVISION Y COLOCADO DE JUNTA m 35.13 20.44 718.06 0.00 0% 0.00 0%
06.10.02 PROVISION Y COLOCADO DE SELLO IGAS NEGRO gln 35.13 72.66 2,552.55 0.00 0% 0.00 0%
07 CASETA DE VALVULAS
07.01 TRABAJOS PRELIMINARES
07.01.01 TRAZO, NIVELACION Y REPLANTEO m2 3.06 2.77 8.48 0.00 0% 8.48 3.06 100%
07.01.02 LIMPIEZA DEL TERRENO MANUAL m2 3.06 2.40 7.34 0.00 0% 6.42 2.68 87%
07.02 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.32 33.62 582.30 0.00 0% 0.00 0%
07.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.06 8.01 24.51 0.00 0% 0.00 0%
07.02.03 RELLENO Y COMPACTACION CON MATERIAL AFIRMADO E=10 CM m2 3.06 4.81 14.72 0.00 0% 0.00 0%
07.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 1.20 24.01 28.81 0.00 0% 0.00 0%
07.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1.20 23.55 28.26 0.00 0% 0.00 0%
07.03 OBRAS DE CONCRETO SIMPLE
07.03.01 CIMIENTO CORRIDO 1:10 CEMENTO-HORMIGON 30% PIEDRA GRANDE m3 4.26 255.59 1,088.81 0.00 0% 0.00 0%
07.03.02 SOBRECIMIENTO MEZCLA 1:8 CEMENTO-HORMIGON 25% PIEDRA MEDIANA m3 1.58 263.16 415.79 0.00 0% 0.00 0%
07.03.03 FALSO PISO MEZCLA 1:10 CEMENTO-HORMIGON e=4" m2 5.00 36.07 180.35 0.00 0% 0.00 0%
07.03.04 PISO DE CONCRETO DE 2" SIN COLOREAR m2 5.00 32.15 160.75 0.00 0% 0.00 0%
07.04 OBRAS DE CONCRETO ARMADO
07.04.01 CONCRETO f'c=175 KG/CM2 m3 5.01 198.96 996.79 0.00 0% 0.00 0%
07.04.02 ENCOFRADO Y DESENCOFRADO EN CASETA DE VALVULAS m2 57.70 70.67 4,077.66 0.00 0% 0.00 0%
07.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 769.02 6.05 4,652.57 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
06.08.02 MARCO Y TAPA PLANCHA LAC 1/4" C/MECANISM. DE SEG. S/DISEO und 1.00 286.40 286.40 286.40 1.00 100% 0.00 0%
06.08.03 VENTILACION C/TUBERIA DE ACERO S/DISEO DE 4" und 4.00 55.72 222.88 222.88 4.00 100% 0.00 0%
06.08.04 SOPORTE METALICO T/ABRAZADERA P/TUB. DE DIAMETRO 8"-10" und 4.00 44.91 179.64 179.64 4.00 100% 0.00 0%
06.08.05 CANDADO INCLUYE ALDABAS und 3.00 65.14 195.42 195.42 3.00 100% 0.00 0%
06.09 VEREDAS
06.09.01 VEREDA DE CONCRETO f'c=140 KG/CM2 E=10 CM m2 25.00 64.13 1,603.25 1,603.25 25.00 100% 0.00 0%
06.09.02 CURADO DE CONCRETO PARA VEREDAS m2 40.00 2.31 92.40 92.4 40.00 100% 0.00 0%
06.09.03 JUNTAS ASFALTICAS EN VEREDAS m 18.00 10.47 188.46 188.46 18.00 100% 0.00 0%
06.10 JUNTAS DE DILATACION
06.10.01 WATER STOP DE PVC DE 6". PROVISION Y COLOCADO DE JUNTA m 35.13 20.44 718.06 718.06 35.13 100% 0.00 0%
06.10.02 PROVISION Y COLOCADO DE SELLO IGAS NEGRO gln 35.13 72.66 2,552.55 2,552.55 35.13 100% 0.00 0%
07 CASETA DE VALVULAS
07.01 TRABAJOS PRELIMINARES
07.01.01 TRAZO, NIVELACION Y REPLANTEO m2 3.06 2.77 8.48 0.00 0% 0.00 0%
07.01.02 LIMPIEZA DEL TERRENO MANUAL m2 3.06 2.40 7.34 0.92 0.38 13% 0.00 0%
07.02 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.32 33.62 582.30 582.3 17.32 100% 0.00 0%
07.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.06 8.01 24.51 24.51 3.06 100% 0.00 0%
07.02.03 RELLENO Y COMPACTACION CON MATERIAL AFIRMADO E=10 CM m2 3.06 4.81 14.72 14.72 3.06 100% 0.00 0%
07.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 1.20 24.01 28.81 28.81 1.20 100% 0.00 0%
07.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1.20 23.55 28.26 28.26 1.20 100% 0.00 0%
07.03 OBRAS DE CONCRETO SIMPLE
07.03.01 CIMIENTO CORRIDO 1:10 CEMENTO-HORMIGON 30% PIEDRA GRANDE m3 4.26 255.59 1,088.81 1088.81 4.26 100% 0.00 0%
07.03.02 SOBRECIMIENTO MEZCLA 1:8 CEMENTO-HORMIGON 25% PIEDRA MEDIANA m3 1.58 263.16 415.79 415.79 1.58 100% 0.00 0%
07.03.03 FALSO PISO MEZCLA 1:10 CEMENTO-HORMIGON e=4" m2 5.00 36.07 180.35 180.35 5.00 100% 0.00 0%
07.03.04 PISO DE CONCRETO DE 2" SIN COLOREAR m2 5.00 32.15 160.75 160.75 5.00 100% 0.00 0%
07.04 OBRAS DE CONCRETO ARMADO
07.04.01 CONCRETO f'c=175 KG/CM2 m3 5.01 198.96 996.79 996.79 5.01 100% 0.00 0%
07.04.02 ENCOFRADO Y DESENCOFRADO EN CASETA DE VALVULAS m2 57.70 70.67 4,077.66 4,077.66 57.70 100% 0.00 0%
07.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 769.02 6.05 4,652.57 4652.57 769.02 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
07.04.04 CURADO DE CONCRETO m2 57.70 3.61 208.30 0.00 0% 0.00 0%
07.05 MUROS Y TABIQUES DE ALBAILERIA
07.05.01 MURO DE LADRILLO K.K. 9x14x24, CEMENTO-ARENA 1:5, JUNTA 1.50cm m2 24.94 125.12 3,120.49 0.00 0% 0.00 0%
07.06 REVOQUES, ENLUCIDOS Y PINTURA EN CASETA DE VALVULAS
07.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 106.54 22.64 2,412.07 0.00 0% 0.00 0%
07.06.02 PINTURA ESMALTE EN EXTERIOR DE ESTRUCTURAS m2 106.54 11.35 1,209.23 0.00 0% 0.00 0%
07.07 VALVULAS Y ACCESORIOS EN CASETA DE VALVULAS
07.07.01 SUMINISTRO E INSTALACION DE VALVULA EN CASETA DE VALVULAS und 1.00 3,150.33 3,150.33 0.00 0% 0.00 0%
07.08 TUBERIAS EN CASETA DE VALVULAS
07.08.01 SUMINISTRO E INSTALACION DE TUBERIAS 4" EN CASETA DE VALVULAS m 6.00 103.23 619.38 0.00 0% 0.00 0%
07.08.02 SUMINISTRO E INSTALACION DE TUBERIAS 3 1/2" EN CASETA DE VALVULAS m 18.00 72.26 1,300.68 0.00 0% 0.00 0%
07.09 VARIOS
07.09.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 1.00 216.77 216.77 0.00 0% 0.00 0%
08 LINEA DE CONDUCCION
08.01 TRABAJOS PRELIMINARES
08.01.01 LIMPIEZA DEL TERRENO MANUAL m2 746.59 0.96 716.73 716.73 746.59 100% 0.00 0%
08.01.02 TRAZO Y REPLANTEO LINEA DE CONDUCCION m 933.24 1.01 942.57 942.57 933.24 100% 0.00 0%
08.02 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 933.24 19.21 17,927.54 14192.64 738.82 79% 3734.9 194.42 21%
08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 933.24 1.50 1,399.86 670.77 447.18 48% 729.09 486.06 52%
08.02.03 CAMA DE APOYO PARA TUBERIA m 933.24 11.00 10,265.64 8,603.31 782.12 84% 1,662.33 151.12 16%
08.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 933.24 31.75 29,630.37 0.00 0% 29,630.37 933.24 100%
08.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS
08.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 933.24 31.25 29,163.75 0.00 0% 29,163.75 933.24 100%
08.03.02 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 933.24 2.93 2,734.39 0.00 0% 2,734.39 933.24 100%
09 RED DE DISTRIBUCION DE AGUA POTABLE
09.01 TRABAJOS PRELIMINARES
09.01.01 LIMPIEZA DEL TERRENO MANUAL m2 461.74 0.96 443.27 443.27 461.74 100% 0.00 0%
09.01.02 TRAZO Y REPLANTEO RED DE DISTRIBUCION DE AGUA POTABLE m 1,577.17 1.01 1,592.94 1592.94 1577.17 100% 0.00 0%
09.02 MOVIMIENTO DE TIERRAS
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
07.04.04 CURADO DE CONCRETO m2 57.70 3.61 208.30 208.30 57.70 100% 0.00 0%
07.05 MUROS Y TABIQUES DE ALBAILERIA
07.05.01 MURO DE LADRILLO K.K. 9x14x24, CEMENTO-ARENA 1:5, JUNTA 1.50cm m2 24.94 125.12 3,120.49 3120.49 24.94 100% 0.00 0%
07.06 REVOQUES, ENLUCIDOS Y PINTURA EN CASETA DE VALVULAS
07.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 106.54 22.64 2,412.07 2,412.07 106.54 100% 0.00 0%
07.06.02 PINTURA ESMALTE EN EXTERIOR DE ESTRUCTURAS m2 106.54 11.35 1,209.23 1209.23 106.54 100% 0.00 0%
07.07 VALVULAS Y ACCESORIOS EN CASETA DE VALVULAS
07.07.01 SUMINISTRO E INSTALACION DE VALVULA EN CASETA DE VALVULAS und 1.00 3,150.33 3,150.33 3150.33 1.00 100% 0.00 0%
07.08 TUBERIAS EN CASETA DE VALVULAS
07.08.01 SUMINISTRO E INSTALACION DE TUBERIAS 4" EN CASETA DE VALVULAS m 6.00 103.23 619.38 619.38 6.00 100% 0.00 0%
07.08.02 SUMINISTRO E INSTALACION DE TUBERIAS 3 1/2" EN CASETA DE VALVULAS m 18.00 72.26 1,300.68 1300.68 18.00 100% 0.00 0%
07.09 VARIOS
07.09.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 1.00 216.77 216.77 216.77 1.00 100% 0.00 0%
08 LINEA DE CONDUCCION
08.01 TRABAJOS PRELIMINARES
08.01.01 LIMPIEZA DEL TERRENO MANUAL m2 746.59 0.96 716.73 0.00 0% 0.00 0%
08.01.02 TRAZO Y REPLANTEO LINEA DE CONDUCCION m 933.24 1.01 942.57 0.00 0% 0.00 0%
08.02 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 933.24 19.21 17,927.54 0.00 0% 0.00 0%
08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 933.24 1.50 1,399.86 0.00 0% 0.00 0%
08.02.03 CAMA DE APOYO PARA TUBERIA m 933.24 11.00 10,265.64 0.00 0% 0.00 0%
08.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 933.24 31.75 29,630.37 0.00 0% 0.00 0%
08.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS
08.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 933.24 31.25 29,163.75 0.00 0% 0.00 0%
08.03.02 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 933.24 2.93 2,734.39 0.00 0% 0.00 0%
09 RED DE DISTRIBUCION DE AGUA POTABLE
09.01 TRABAJOS PRELIMINARES
09.01.01 LIMPIEZA DEL TERRENO MANUAL m2 461.74 0.96 443.27 0.00 0% 0.00 0%
09.01.02 TRAZO Y REPLANTEO RED DE DISTRIBUCION DE AGUA POTABLE m 1,577.17 1.01 1,592.94 0.00 0% 0.00 0%
09.02 MOVIMIENTO DE TIERRAS
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
09.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 1,763.26 19.21 33,872.22 13870.09 722.02 41% 20,002.13 1041.24 59%
09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 1,763.26 2.27 4,002.60 0.00 0% 4002.6 1763.26 100%
09.02.03 CAMA DE APOYO PARA TUBERIA m 1,763.26 46.52 82,026.86 0.00 0% 82026.86 1763.26 100%
09.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 1,763.26 31.75 55,983.51 0.00 0% 55983.51 1763.26 100%
09.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.13 24.01 2,620.21 0.00 0% 286.59 11.94 11%
09.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.28 23.55 2,573.54 0.00 0% 0.00 0%
09.03 SUMINISTRO DE INSTALACION DE TUBERIA
09.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 405.88 31.25 12,683.75 0.00 0% 12683.75 405.88 100%
09.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC D=2" m 55.30 11.17 617.70 0.00 0% 617.7 55.30 100%
09.03.03 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1 1/2" m 563.97 9.71 5,476.15 0.00 0% 5476.15 563.97 100%
09.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1" m 738.11 6.81 5,026.53 0.00 0% 5026.53 738.11 100%
09.03.05 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 1,763.26 2.93 5,166.35 0.00 0% 5166.35 1763.26 100%
09.04 SUMINISTRO DE INSTALACION DE ACCESORIOS
09.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED DE DISTRIBUCION GLB 0.50 7,547.31 3,773.66 0.00 0% 3773.66 0.50 100%
09.05 ROTURA Y REPOSICION DE PAVIMENTO
09.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 365.49 96.59 35,302.68 0.00 0% 30244.19 313.12 86%
09.05.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 45.69 24.01 1,097.02 0.00 0% 0.00 0%
09.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55 1,076.00 0.00 0% 0.00 0%
10 CONEXIONES DOMICILIARIAS DE AGUA POTABLE
10.01 TRABAJOS PRELIMINARES
10.01.01 TRAZO, NIVELACION Y REPLANTEO EN ZANJAS m 2,088.00 1.33 2,777.04 2777.04 2088.00 100% 0.00 0%
10.02 MOVIMIENTO DE TIERRAS
10.02.01 EXCAVACION MANUAL EN TERRENO NORMAL PARA CAJA 0.40X0.60X0.35 m3 30.00 48.02 1,440.60 1440.6 30.00 100% 0.00 0%
10.02.02 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 2,088.00 19.21 40,110.48 13608.91 708.43 34% 26,501.57 1379.57 66%
10.02.03 REFINE Y NIVELACION EN TERRENO NORMAL m 2,088.00 1.50 3,132.00 0.00 0% 3,132.00 2088.00 100%
10.02.04 CAMA DE APOYO PARA TUBERIA m 2,088.00 20.41 42,616.08 0.00 0% 42,616.08 2088.00 100%
10.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,088.00 31.75 66,294.00 0.00 0% 0.00 0%
10.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 125.39 24.01 3,010.61 0.00 0% 0.00 0%
10.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 125.39 23.55 2,952.93 0.00 0% 0.00 0%
10.03 TUBERIAS Y ACCESORIOS
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
09.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 1,763.26 19.21 33,872.22 0.00 0% 0.00 0%
09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 1,763.26 2.27 4,002.60 0.00 0% 0.00 0%
09.02.03 CAMA DE APOYO PARA TUBERIA m 1,763.26 46.52 82,026.86 0.00 0% 0.00 0%
09.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 1,763.26 31.75 55,983.51 0.00 0% 0.00 0%
09.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.13 24.01 2,620.21 2,333.62 97.19 89% 0.00 0%
09.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.28 23.55 2,573.54 2573.54 109.28 100% 0.00 0%
09.03 SUMINISTRO DE INSTALACION DE TUBERIA
09.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 405.88 31.25 12,683.75 0.00 0% 0.00 0%
09.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC D=2" m 55.30 11.17 617.70 0.00 0% 0.00 0%
09.03.03 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1 1/2" m 563.97 9.71 5,476.15 0.00 0% 0.00 0%
09.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1" m 738.11 6.81 5,026.53 0.00 0% 0.00 0%
09.03.05 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 1,763.26 2.93 5,166.35 0.00 0% 0.00 0%
09.04 SUMINISTRO DE INSTALACION DE ACCESORIOS
09.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED DE DISTRIBUCION GLB 0.50 7,547.31 3,773.66 0.00 0% 0.00 0%
09.05 ROTURA Y REPOSICION DE PAVIMENTO
09.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 365.49 96.59 35,302.68 5058.49 52.37 14% 0.00 0%
09.05.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 45.69 24.01 1,097.02 1097.02 45.69 100% 0.00 0%
09.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55 1,076.00 1076 45.69 100% 0.00 0%
10 CONEXIONES DOMICILIARIAS DE AGUA POTABLE
10.01 TRABAJOS PRELIMINARES
10.01.01 TRAZO, NIVELACION Y REPLANTEO EN ZANJAS m 2,088.00 1.33 2,777.04 0.00 0% 0.00 0%
10.02 MOVIMIENTO DE TIERRAS
10.02.01 EXCAVACION MANUAL EN TERRENO NORMAL PARA CAJA 0.40X0.60X0.35 m3 30.00 48.02 1,440.60 0.00 0% 0.00 0%
10.02.02 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 2,088.00 19.21 40,110.48 0.00 0% 0.00 0%
10.02.03 REFINE Y NIVELACION EN TERRENO NORMAL m 2,088.00 1.50 3,132.00 0.00 0% 0.00 0%
10.02.04 CAMA DE APOYO PARA TUBERIA m 2,088.00 20.41 42,616.08 0.00 0% 0.00 0%
10.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,088.00 31.75 66,294.00 48684.66 1533.38 73% 17609.34 554.62 27%
10.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 125.39 24.01 3,010.61 0.00 0% 3,010.61 125.39 100%
10.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 125.39 23.55 2,952.93 0.00 0% 2,952.93 125.39 100%
10.03 TUBERIAS Y ACCESORIOS
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
10.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, PARA CONEXION DOMICILIARIA m 2,088.00 5.12 10,690.56 0.00 0% 6240.9 1218.93 58%
10.03.02 CONEXION AGUA 1/2" TERRENO NORMAL, INCLUYE LOSA 1X1X0.1 M und 261.00 307.80 80,335.80 0.00 0% 0.00 0%
10.03.03 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 2,088.00 2.93 6,117.84 0.00 0% 0.00 0%
10.04 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS
10.04.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 0.00 0%
10.04.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 4.90 80.55 394.70 0.00 0% 0.00 0%
10.04.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 8.18 24.01 196.40 0.00 0% 0.00 0%
10.04.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.18 23.55 192.64 0.00 0% 0.00 0%
11 RED DE ALCANTARILLADO - COLECTOR
11.01 TRABAJOS PRELIMINARES
11.01.01 LIMPIEZA DEL TERRENO MANUAL m2 2,429.46 0.96 2,332.28 2332.28 2429.46 100% 0.00 0%
11.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 2,858.19 1.36 3,887.14 3887.14 2858.19 100% 0.00 0%
11.02 MOVIMIENTO DE TIERRAS
11.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 2,244.59 85.15 191,126.84 64966.05 762.96 34% 126160.79 1481.63 66%
11.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 591.12 48.02 28,385.58 9314.02 193.96 33% 19071.56 397.16 67%
11.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 2,858.19 4.35 12,433.13 0.00 0% 12433.13 2858.19 100%
11.02.04 CONFORMACION DE CAMA DE APOYO m 2,858.19 11.88 33,955.30 0.00 0% 33955.3 2858.19 100%
11.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,858.19 31.75 90,747.53 0.00 0% 0.00 0%
11.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 391.98 24.01 9,411.44 0.00 0% 0.00 0%
11.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 391.98 23.55 9,231.13 0.00 0% 0.00 0%
11.03 SUMINISTRO DE INSTALACION DE TUBERIA
11.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 2,858.19 32.08 91,690.74 0.00 0% 91690.74 2858.19 100%
11.04 PRUEBA HIDRAULICA
11.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 2,858.19 3.29 9,403.45 0.00 0% 6913.25 2101.29 74%
11.05 BUZONES O CAMARAS DE INSPECCION
11.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 54.00 2,268.00 122,472.00 0.00 0% 122472 54.00 100%
11.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 9.00 2,399.94 21,599.46 0.00 0% 21599.46 9.00 100%
11.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 66.00 442.89 29,230.74 0.00 0% 29,230.74 66.00 100%
11.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 66.00 460.19 30,372.54 0.00 0% 30,372.54 66.00 100%
11.06 ROTURA Y REPOSICION DE PAVIMENTO
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
10.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, PARA CONEXION DOMICILIARIA m 2,088.00 5.12 10,690.56 4449.66 869.07 42% 0.00 0%
10.03.02 CONEXION AGUA 1/2" TERRENO NORMAL, INCLUYE LOSA 1X1X0.1 M und 261.00 307.80 80,335.80 80335.8 261.00 100% 0.00 0%
10.03.03 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 2,088.00 2.93 6,117.84 6,117.84 2088.00 100% 0.00 0%
10.04 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS
10.04.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 12,170.34 126.00 100%
10.04.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 4.90 80.55 394.70 0.00 0% 394.70 4.90 100%
10.04.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 8.18 24.01 196.40 0.00 0% 196.4 8.18 100%
10.04.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.18 23.55 192.64 0.00 0% 192.64 8.18 100%
11 RED DE ALCANTARILLADO - COLECTOR
11.01 TRABAJOS PRELIMINARES
11.01.01 LIMPIEZA DEL TERRENO MANUAL m2 2,429.46 0.96 2,332.28 0.00 0% 0.00 0%
11.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 2,858.19 1.36 3,887.14 0.00 0% 0.00 0%
11.02 MOVIMIENTO DE TIERRAS
11.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 2,244.59 85.15 191,126.84 0.00 0% 0.00 0%
11.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 591.12 48.02 28,385.58 0.00 0% 0.00 0%
11.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 2,858.19 4.35 12,433.13 0.00 0% 0.00 0%
11.02.04 CONFORMACION DE CAMA DE APOYO m 2,858.19 11.88 33,955.30 0.00 0% 0.00 0%
11.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,858.19 31.75 90,747.53 90,747.53 2858.19 100% 0.00 0%
11.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 391.98 24.01 9,411.44 9411.44 391.98 100% 0.00 0%
11.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 391.98 23.55 9,231.13 9,231.13 391.98 100% 0.00 0%
11.03 SUMINISTRO DE INSTALACION DE TUBERIA
11.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 2,858.19 32.08 91,690.74 0.00 0% 0.00 0%
11.04 PRUEBA HIDRAULICA
11.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 2,858.19 3.29 9,403.45 2490.2 756.90 26% 0.00 0%
11.05 BUZONES O CAMARAS DE INSPECCION
11.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 54.00 2,268.00 122,472.00 0.00 0% 0.00 0%
11.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 9.00 2,399.94 21,599.46 0.00 0% 0.00 0%
11.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 66.00 442.89 29,230.74 0.00 0% 0.00 0%
11.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 66.00 460.19 30,372.54 0.00 0% 0.00 0%
11.06 ROTURA Y REPOSICION DE PAVIMENTO
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
11.06.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 363.49 96.59 35,109.50 0.00 0% 0.00 0%
11.06.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55 1,076.00 0.00 0% 0.00 0%
12 CONEXIONES DOMICILIARIAS DE DESAGE
12.01 TRABAJOS PRELIMINARES
12.01.01 TRAZO, NIVELES Y REPLANTEO m2 1,296.00 1.75 2,268.00 2268 1296.00 100% 0.00 0%
12.02 MOVIMIENTO DE TIERRAS
12.02.01 EXCAVACION DE ZANJA T. NORMAL - CONEXION DESAGE m 1,528.00 16.01 24,463.28 17328.16 1082.33 71% 7135.12 445.67 29%
12.02.02 REFINE Y NIVELACION ZANJA TERR.NORMAL"C" PARA TUB. 4"-6" m 1,528.00 2.18 3,331.04 0.00 0% 3331.04 1528.00 100%
12.02.03 CONFORMACION DE CAMA DE APOYO m 1,528.00 11.38 17,388.64 0.00 0% 17388.64 1528.00 100%
12.02.04 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,528.00 6.18 9,443.04 0.00 0% 9443.04 1528.00 100%
12.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 152.80 24.01 3,668.73 0.00 0% 1757.93 73.22 48%
12.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 152.80 23.55 3,598.44 0.00 0% 0.00 0%
12.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS
12.03.01 ACCESORIOS DE DESAGE und 110.00 138.58 15,243.80 0.00 0% 15243.8 110.00 100%
12.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 160 MM m 1,528.00 20.67 31,583.76 0.00 0% 31583.76 1528.00 100%
12.04 CAJAS DE INSPECCION Y/O REGISTROS
12.04.01 CAJA DE REGISTRO DE 12" x 24" C/TAPA DE CONCRETO pza 110.00 188.71 20,758.10 0.00 0% 20707.42 109.73 100%
12.05 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS
12.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 12170.34 126.00 100%
12.05.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 14.70 80.55 1,184.09 0.00 0% 1109.29 13.77 94%
12.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.79 23.55 207.00 0.00 0% 0.00 0%
13 EMISOR
13.01 TRABAJOS PRELIMINARES
13.01.01 LIMPIEZA DEL TERRENO MANUAL m2 876.47 0.96 841.41 0.00 0% 841.41 876.47 100%
13.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 1,031.14 1.36 1,402.35 0.00 0% 1402.35 1031.14 100%
13.02 MOVIMIENTO DE TIERRAS
13.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 1,031.14 85.15 87,801.57 0.00 0% 84312.53 990.16 96%
13.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 78.41 48.02 3,765.25 0.00 0% 882.48 18.38 23%
13.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 1,031.14 3.16 3,258.40 0.00 0% 0.00 0%
13.02.04 CONFORMACION DE CAMA DE APOYO m 1,031.14 11.38 11,734.37 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
11.06.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 363.49 96.59 35,109.50 35109.5 363.49 100% 0.00 0%
11.06.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55 1,076.00 1,076.00 45.69 100% 0.00 0%
12 CONEXIONES DOMICILIARIAS DE DESAGE
12.01 TRABAJOS PRELIMINARES
12.01.01 TRAZO, NIVELES Y REPLANTEO m2 1,296.00 1.75 2,268.00 0.00 0% 0.00 0%
12.02 MOVIMIENTO DE TIERRAS
12.02.01 EXCAVACION DE ZANJA T. NORMAL - CONEXION DESAGE m 1,528.00 16.01 24,463.28 0.00 0% 0.00 0%
12.02.02 REFINE Y NIVELACION ZANJA TERR.NORMAL"C" PARA TUB. 4"-6" m 1,528.00 2.18 3,331.04 0.00 0% 0.00 0%
12.02.03 CONFORMACION DE CAMA DE APOYO m 1,528.00 11.38 17,388.64 0.00 0% 0.00 0%
12.02.04 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,528.00 6.18 9,443.04 0.00 0% 0.00 0%
12.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 152.80 24.01 3,668.73 1,910.80 79.58 52% 0.00 0%
12.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 152.80 23.55 3,598.44 3598.44 152.80 100% 0.00 0%
12.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS
12.03.01 ACCESORIOS DE DESAGE und 110.00 138.58 15,243.80 0.00 0% 0.00 0%
12.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 160 MM m 1,528.00 20.67 31,583.76 0.00 0% 0.00 0%
12.04 CAJAS DE INSPECCION Y/O REGISTROS
12.04.01 CAJA DE REGISTRO DE 12" x 24" C/TAPA DE CONCRETO pza 110.00 188.71 20,758.10 50.68 0.27 0% 0.00 0%
12.05 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS
12.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 0.00 0%
12.05.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 14.70 80.55 1,184.09 74.8 0.93 6% 0.00 0%
12.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.79 23.55 207.00 207 8.79 100% 0.00 0%
13 EMISOR
13.01 TRABAJOS PRELIMINARES
13.01.01 LIMPIEZA DEL TERRENO MANUAL m2 876.47 0.96 841.41 0.00 0% 0.00 0%
13.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 1,031.14 1.36 1,402.35 0.00 0% 0.00 0%
13.02 MOVIMIENTO DE TIERRAS
13.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 1,031.14 85.15 87,801.57 3489.04 40.98 4% 0.00 0%
13.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 78.41 48.02 3,765.25 2,882.77 60.03 77% 0.00 0%
13.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 1,031.14 3.16 3,258.40 3,258.40 1031.14 100% 0.00 0%
13.02.04 CONFORMACION DE CAMA DE APOYO m 1,031.14 11.38 11,734.37 11,734.37 1031.14 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
13.02.05 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,031.14 6.18 6,372.45 0.00 0% 0.00 0%
13.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.56 24.01 2,630.54 0.00 0% 0.00 0%
13.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.56 23.55 2,580.14 0.00 0% 0.00 0%
13.03 SUMINISTRO DE INSTALACION DE TUBERIA
13.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 1,031.14 32.08 33,078.97 0.00 0% 0.00 0%
13.04 PRUEBA HIDRAULICA
13.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 1,031.14 3.29 3,392.45 0.00 0% 0.00 0%
13.05 BUZONES O CAMARAS DE INSPECCION
13.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 12.00 2,268.00 27,216.00 0.00 0% 0.00 0%
13.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 1.00 2,399.94 2,399.94 0.00 0% 0.00 0%
13.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 13.00 528.40 6,869.20 0.00 0% 0.00 0%
13.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 13.00 460.19 5,982.47 0.00 0% 0.00 0%
14 CAJA DE INGRESO
14.01 TRABAJOS PRELIMINARES
14.01.01 TRAZO, NIVELACION Y REPLANTEO m2 0.64 2.77 1.77 0.00 0% 1.77 0.64 100%
14.01.02 LIMPIEZA DEL TERRENO MANUAL m2 0.64 2.40 1.54 0.00 0% 1.54 0.64 100%
14.02 MOVIMIENTO DE TIERRAS
14.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 0.66 42.02 27.73 0.00 0% 27.73 0.66 100%
14.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.85 24.01 20.41 0.00 0% 20.41 0.85 100%
14.03 CONCRETO ARMADO
14.03.01 CONCRETO f'c= 210 KG/CM2 m3 0.83 586.34 486.66 0.00 0% 486.66 0.83 100%
14.03.02 ENCOFRADO Y DESENCOFRADO m2 6.45 62.74 404.67 0.00 0% 404.67 6.45 100%
14.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 25.29 6.53 165.14 0.00 0% 165.14 25.29 100%
14.04 REVOQUES Y ENLUCIDOS
14.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 3.32 28.46 94.49 0.00 0% 94.49 3.32 100%
14.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 4.43 22.64 100.30 0.00 0% 100.3 4.43 100%
15 CAMARA DE REJAS
15.01 TRABAJOS PRELIMINARES
15.01.01 TRAZO, NIVELACION Y REPLANTEO m2 2.27 2.77 6.29 0.00 0% 6.29 2.27 100%
15.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.27 2.40 5.45 0.00 0% 5.45 2.27 100%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
13.02.05 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,031.14 6.18 6,372.45 6372.45 1031.14 100% 0.00 0%
13.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.56 24.01 2,630.54 2630.54 109.56 100% 0.00 0%
13.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.56 23.55 2,580.14 2257.62 95.86 87% 322.52 13.70 13%
13.03 SUMINISTRO DE INSTALACION DE TUBERIA
13.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 1,031.14 32.08 33,078.97 33078.97 1031.14 100% 0.00 0%
13.04 PRUEBA HIDRAULICA
13.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 1,031.14 3.29 3,392.45 3392.45 1031.14 100% 0.00 0%
13.05 BUZONES O CAMARAS DE INSPECCION
13.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 12.00 2,268.00 27,216.00 27216 12.00 100% 0.00 0%
13.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 1.00 2,399.94 2,399.94 2399.94 1.00 100% 0.00 0%
13.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 13.00 528.40 6,869.20 6869.2 13.00 100% 0.00 0%
13.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 13.00 460.19 5,982.47 5982.47 13.00 100% 0.00 0%
14 CAJA DE INGRESO
14.01 TRABAJOS PRELIMINARES
14.01.01 TRAZO, NIVELACION Y REPLANTEO m2 0.64 2.77 1.77 0.00 0% 0.00 0%
14.01.02 LIMPIEZA DEL TERRENO MANUAL m2 0.64 2.40 1.54 0.00 0% 0.00 0%
14.02 MOVIMIENTO DE TIERRAS
14.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 0.66 42.02 27.73 0.00 0% 0.00 0%
14.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.85 24.01 20.41 0.00 0% 0.00 0%
14.03 CONCRETO ARMADO
14.03.01 CONCRETO f'c= 210 KG/CM2 m3 0.83 586.34 486.66 0.00 0% 0.00 0%
14.03.02 ENCOFRADO Y DESENCOFRADO m2 6.45 62.74 404.67 0.00 0% 0.00 0%
14.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 25.29 6.53 165.14 0.00 0% 0.00 0%
14.04 REVOQUES Y ENLUCIDOS
14.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 3.32 28.46 94.49 0.00 0% 0.00 0%
14.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 4.43 22.64 100.30 0.00 0% 0.00 0%
15 CAMARA DE REJAS
15.01 TRABAJOS PRELIMINARES
15.01.01 TRAZO, NIVELACION Y REPLANTEO m2 2.27 2.77 6.29 0.00 0% 0.00 0%
15.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.27 2.40 5.45 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
15.02 MOVIMIENTO DE TIERRAS
15.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 58.83 1.40 100%
15.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70 0.00 0% 43.70 1.82 100%
15.03 CONCRETO ARMADO
15.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 844.33 1.44 100%
15.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92 0.00 0% 1023.92 16.32 100%
15.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23 0.00 0% 922.23 141.23 100%
15.04 REVOQUES Y ENLUCIDOS
15.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 272.36 9.57 100%
15.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 6.02 22.64 136.29 0.00 0% 136.29 6.02 100%
15.05 OTROS
15.05.01 SISTEMA DE REJAS DE ACERO INOXIDABLE und 1.00 539.54 539.54 0.00 0% 539.54 1.00 100%
16 TANQUE IMHOFF
16.01 TRABAJOS PRELIMINARES
16.01.01 TRAZO, NIVELACION Y REPLANTEO m2 52.46 2.77 145.31 0.00 0% 145.31 52.46 100%
16.01.02 LIMPIEZA DEL TERRENO MANUAL m2 52.46 2.40 125.90 0.00 0% 125.9 52.46 100%
16.02 MOVIMIENTO DE TIERRAS
16.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 387.35 42.02 16,276.45 0.00 0% 16276.45 387.35 100%
16.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 52.46 8.01 420.20 0.00 0% 420.2 52.46 100%
16.02.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 503.55 24.01 12,090.24 0.00 0% 7367.49 306.85 61%
16.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 503.55 23.55 11,858.60 0.00 0% 0.00 0%
16.03 CONCRETO SIMPLE
16.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 52.46 36.01 1,889.08 0.00 0% 1889.08 52.46 100%
16.03.02 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 12.56 486.26 6,107.43 0.00 0% 6,107.43 12.56 100%
16.04 CONCRETO ARMADO
16.04.01 LOSA DE CIMENTACION
16.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 17.11 486.26 8,319.91 0.00 0% 8120.25 16.70 98%
16.04.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.36 6.53 6,676.01 0.00 0% 6676.01 1022.36 100%
16.04.02 MURO REFORZADO
16.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 44.66 586.34 26,185.94 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
15.02 MOVIMIENTO DE TIERRAS
15.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 0.00 0%
15.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70 0.00 0% 0.00 0%
15.03 CONCRETO ARMADO
15.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 0.00 0%
15.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92 0.00 0% 0.00 0%
15.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23 0.00 0% 0.00 0%
15.04 REVOQUES Y ENLUCIDOS
15.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 0.00 0%
15.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 6.02 22.64 136.29 0.00 0% 0.00 0%
15.05 OTROS
15.05.01 SISTEMA DE REJAS DE ACERO INOXIDABLE und 1.00 539.54 539.54 0.00 0% 0.00 0%
16 TANQUE IMHOFF
16.01 TRABAJOS PRELIMINARES
16.01.01 TRAZO, NIVELACION Y REPLANTEO m2 52.46 2.77 145.31 0.00 0% 0.00 0%
16.01.02 LIMPIEZA DEL TERRENO MANUAL m2 52.46 2.40 125.90 0.00 0% 0.00 0%
16.02 MOVIMIENTO DE TIERRAS
16.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 387.35 42.02 16,276.45 0.00 0% 0.00 0%
16.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 52.46 8.01 420.20 0.00 0% 0.00 0%
16.02.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 503.55 24.01 12,090.24 4,722.75 196.70 39% 0.00 0%
16.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 503.55 23.55 11,858.60 11,858.60 503.55 100% 0.00 0%
16.03 CONCRETO SIMPLE
16.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 52.46 36.01 1,889.08 0.00 0% 0.00 0%
16.03.02 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 12.56 486.26 6,107.43 0.00 0% 0.00 0%
16.04 CONCRETO ARMADO
16.04.01 LOSA DE CIMENTACION
16.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 17.11 486.26 8,319.91 199.66 0.41 2% 0.00 0%
16.04.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.36 6.53 6,676.01 0.00 0% 0.00 0%
16.04.02 MURO REFORZADO
16.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 44.66 586.34 26,185.94 26185.94 44.66 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
16.04.02.02 ENCOFRADO Y DESENCOFRADO m2 357.24 62.74 22,413.24 0.00 0% 13558.09 216.10 60%
16.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,705.09 6.53 11,134.24 0.00 0% 11134.24 1705.09 100%
16.04.03 SEDIMENTADOR
16.04.03.01 CONCRETO f'c= 210 KG/CM2 m3 7.35 586.34 4,309.60 0.00 0% 0.00 0%
16.04.03.02 ENCOFRADO Y DESENCOFRADO m2 97.95 62.74 6,145.38 0.00 0% 4131.96 65.86 67%
16.04.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 746.63 6.53 4,875.49 0.00 0% 4875.49 746.63 100%
16.04.04 CANAL DE REUNION
16.04.04.01 CONCRETO f'c= 210 KG/CM2 m3 0.62 586.34 363.53 0.00 0% 363.53 0.62 100%
16.04.04.02 ENCOFRADO Y DESENCOFRADO m2 8.34 62.74 523.25 0.00 0% 523.25 8.34 100%
16.04.04.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 82.87 6.53 541.14 0.00 0% 541.14 82.87 100%
16.05 REVOQUES Y ENLUCIDOS
16.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 478.95 28.46 13,630.92 0.00 0% 0.00 0%
16.06 OTROS
16.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS VARIOS EN TANQUE IMHOFF GLB 1.00 4,152.22 4,152.22 0.00 0% 0.00 0%
17 LECHO DE SECADO
17.01 TRABAJOS PRELIMINARES
17.01.01 TRAZO Y REPLANTEO m2 161.65 7.16 1,157.41 0.00 0% 1157.41 161.65 100%
17.01.02 LIMPIEZA DEL TERRENO MANUAL m2 161.65 2.40 387.96 0.00 0% 387.96 161.65 100%
17.02 MOVIMIENTO DE TIERRAS
17.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 160.57 60.90 9,778.71 0.00 0% 9642.89 158.34 99%
17.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 208.74 24.01 5,011.85 0.00 0% 0.00 0%
17.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 208.74 23.55 4,915.83 0.00 0% 0.00 0%
17.03 CONCRETO ARMADO
17.03.01 LOSA DE CIMENTACION
17.03.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 44.82 486.26 21,794.17 0.00 0% 0.00 0%
17.03.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.42 6.53 6,676.40 0.00 0% 0.00 0%
17.03.02 MURO REFORZADO
17.03.02.01 CONCRETO f'c= 210 KG/CM2 m3 16.25 586.34 9,528.03 0.00 0% 0.00 0%
17.03.02.02 ENCOFRADO Y DESENCOFRADO m2 216.62 62.74 13,590.74 0.00 0% 0.00 0%
17.03.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 663.75 6.53 4,334.29 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
16.04.02.02 ENCOFRADO Y DESENCOFRADO m2 357.24 62.74 22,413.24 8855.15 141.14 40% 0.00 0%
16.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,705.09 6.53 11,134.24 0.00 0% 0.00 0%
16.04.03 SEDIMENTADOR
16.04.03.01 CONCRETO f'c= 210 KG/CM2 m3 7.35 586.34 4,309.60 4309.6 7.35 100% 0.00 0%
16.04.03.02 ENCOFRADO Y DESENCOFRADO m2 97.95 62.74 6,145.38 2013.42 32.09 33% 0.00 0%
16.04.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 746.63 6.53 4,875.49 0.00 0% 0.00 0%
16.04.04 CANAL DE REUNION
16.04.04.01 CONCRETO f'c= 210 KG/CM2 m3 0.62 586.34 363.53 0.00 0% 0.00 0%
16.04.04.02 ENCOFRADO Y DESENCOFRADO m2 8.34 62.74 523.25 0.00 0% 0.00 0%
16.04.04.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 82.87 6.53 541.14 0.00 0% 0.00 0%
16.05 REVOQUES Y ENLUCIDOS
16.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 478.95 28.46 13,630.92 13630.92 478.95 100% 0.00 0%
16.06 OTROS
16.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS VARIOS EN TANQUE IMHOFF GLB 1.00 4,152.22 4,152.22 4152.22 1.00 100% 0.00 0%
17 LECHO DE SECADO
17.01 TRABAJOS PRELIMINARES
17.01.01 TRAZO Y REPLANTEO m2 161.65 7.16 1,157.41 0.00 0% 0.00 0%
17.01.02 LIMPIEZA DEL TERRENO MANUAL m2 161.65 2.40 387.96 0.00 0% 0.00 0%
17.02 MOVIMIENTO DE TIERRAS
17.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 160.57 60.90 9,778.71 135.82 2.23 1% 0.00 0%
17.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 208.74 24.01 5,011.85 5011.85 208.74 100% 0.00 0%
17.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 208.74 23.55 4,915.83 4915.83 208.74 100% 0.00 0%
17.03 CONCRETO ARMADO
17.03.01 LOSA DE CIMENTACION
17.03.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 44.82 486.26 21,794.17 21794.17 44.82 100% 0.00 0%
17.03.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.42 6.53 6,676.40 6676.4 1022.42 100% 0.00 0%
17.03.02 MURO REFORZADO
17.03.02.01 CONCRETO f'c= 210 KG/CM2 m3 16.25 586.34 9,528.03 9528.03 16.25 100% 0.00 0%
17.03.02.02 ENCOFRADO Y DESENCOFRADO m2 216.62 62.74 13,590.74 13590.74 216.62 100% 0.00 0%
17.03.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 663.75 6.53 4,334.29 4,334.29 663.75 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
17.04 REVOQUES Y ENLUCIDOS
17.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 366.12 28.46 10,419.78 0.00 0% 0.00 0%
17.05 OTROS
17.05.01 GRAVA PARA LECHO DE SECADO TM=3/4"-2" m3 42.31 139.01 5,881.51 0.00 0% 0.00 0%
17.05.02 GRAVA PARA LECHO DE SECADO TM=1/4" m3 5.23 143.46 750.30 0.00 0% 0.00 0%
17.05.03 GRAVA PARA LECHO DE SECADO TM=1/16" m3 11.21 143.46 1,608.19 0.00 0% 0.00 0%
17.05.04 ARENA GRUESA PARA LECHO DE SECADO m3 4.49 108.52 487.25 0.00 0% 0.00 0%
18 FILTRO PERCOLADOR
18.01 TRABAJOS PRELIMINARES
18.01.01 TRAZO Y REPLANTEO m2 42.98 7.16 307.74 0.00 0% 307.74 42.98 100%
18.01.02 LIMPIEZA DEL TERRENO MANUAL m2 42.98 2.40 103.15 0.00 0% 103.15 42.98 100%
18.02 MOVIMIENTO DE TIERRAS
18.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 105.84 60.90 6,445.66 0.00 0% 6445.66 105.84 100%
18.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 137.59 24.01 3,303.54 0.00 0% 1238.83 51.60 38%
18.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 137.59 23.55 3,240.24 0.00 0% 0.00 0%
18.03 CONCRETO SIMPLE
18.03.01 CONCRETO f'c= 210 KG/CM2 - CANALES DE DIST. Y RECOLECCION m3 2.60 586.34 1,524.48 0.00 0% 1449.93 2.47 95%
18.03.02 ENCOFRADO Y DESENCOFRADO EN CANALES m2 10.56 62.74 662.53 0.00 0% 662.53 10.56 100%
18.04 CONCRETO ARMADO
18.04.01 LOSA DE CIMENTACION
18.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 10.14 486.26 4,930.68 0.00 0% 640.32 1.32 13%
18.04.01.02 ENCOFRADO Y DESENCOFRADO m2 6.50 62.74 407.81 0.00 0% 0.00 0%
18.04.02 MURO REFORZADO
18.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 14.90 586.34 8,736.47 0.00 0% 6310.37 10.76 72%
18.04.02.02 ENCOFRADO Y DESENCOFRADO m2 118.75 62.74 7,450.38 0.00 0% 0.00 0%
18.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 820.00 6.53 5,354.60 0.00 0% 0.00 0%
18.04.02.04 VIGUETA PREFABRICADA DE CONCRETO f'c=175 KG/CM2 und 18.00 102.58 1,846.44 0.00 0% 0.00 0%
18.05 FILTROS
18.05.01 FILTRO DE PIEDRA m3 27.72 177.44 4,918.64 0.00 0% 0.00 0%
18.06 REVOQUES Y ENLUCIDOS
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
17.04 REVOQUES Y ENLUCIDOS
17.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 366.12 28.46 10,419.78 10,419.78 366.12 100% 0.00 0%
17.05 OTROS
17.05.01 GRAVA PARA LECHO DE SECADO TM=3/4"-2" m3 42.31 139.01 5,881.51 5,881.51 42.31 100% 0.00 0%
17.05.02 GRAVA PARA LECHO DE SECADO TM=1/4" m3 5.23 143.46 750.30 750.30 5.23 100% 0.00 0%
17.05.03 GRAVA PARA LECHO DE SECADO TM=1/16" m3 11.21 143.46 1,608.19 1,608.19 11.21 100% 0.00 0%
17.05.04 ARENA GRUESA PARA LECHO DE SECADO m3 4.49 108.52 487.25 487.25 4.49 100% 0.00 0%
18 FILTRO PERCOLADOR
18.01 TRABAJOS PRELIMINARES
18.01.01 TRAZO Y REPLANTEO m2 42.98 7.16 307.74 0.00 0% 0.00 0%
18.01.02 LIMPIEZA DEL TERRENO MANUAL m2 42.98 2.40 103.15 0.00 0% 0.00 0%
18.02 MOVIMIENTO DE TIERRAS
18.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 105.84 60.90 6,445.66 0.00 0% 0.00 0%
18.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 137.59 24.01 3,303.54 2064.71 85.99 62% 0.00 0%
18.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 137.59 23.55 3,240.24 3240.24 137.59 100% 0.00 0%
18.03 CONCRETO SIMPLE
18.03.01 CONCRETO f'c= 210 KG/CM2 - CANALES DE DIST. Y RECOLECCION m3 2.60 586.34 1,524.48 74.55 0.13 5% 0.00 0%
18.03.02 ENCOFRADO Y DESENCOFRADO EN CANALES m2 10.56 62.74 662.53 0.00 0% 0.00 0%
18.04 CONCRETO ARMADO
18.04.01 LOSA DE CIMENTACION
18.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 10.14 486.26 4,930.68 4,290.36 8.82 87% 0.00 0%
18.04.01.02 ENCOFRADO Y DESENCOFRADO m2 6.50 62.74 407.81 407.81 6.50 100% 0.00 0%
18.04.02 MURO REFORZADO
18.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 14.90 586.34 8,736.47 2426.1 4.14 28% 0.00 0%
18.04.02.02 ENCOFRADO Y DESENCOFRADO m2 118.75 62.74 7,450.38 7450.38 118.75 100% 0.00 0%
18.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 820.00 6.53 5,354.60 5,354.60 820.00 100% 0.00 0%
18.04.02.04 VIGUETA PREFABRICADA DE CONCRETO f'c=175 KG/CM2 und 18.00 102.58 1,846.44 1,846.44 18.00 100% 0.00 0%
18.05 FILTROS
18.05.01 FILTRO DE PIEDRA m3 27.72 177.44 4,918.64 4,918.64 27.72 100% 0.00 0%
18.06 REVOQUES Y ENLUCIDOS
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
18.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 15.93 28.46 453.37 0.00 0% 0.00 0%
18.07 OTROS
18.07.01 SUMINISTRO E INSTALACION DE CANALETA DE RAPARTICION L=4m und 24.00 211.08 5,065.92 0.00 0% 5065.92 24.00 100%
19 CAMARA DE CLORACION
19.01 TRABAJOS PRELIMINARES
19.01.01 TRAZO Y REPLANTEO m2 2.77 7.16 19.83 0.00 0% 19.83 2.77 100%
19.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.77 2.40 6.65 0.00 0% 6.65 2.77 100%
19.02 MOVIMIENTO DE TIERRAS
19.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 58.83 1.40 100%
19.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70 0.00 0% 43.7 1.82 100%
19.03 CONCRETO ARMADO
19.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 844.33 1.44 100%
19.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92 0.00 0% 1023.92 16.32 100%
19.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23 0.00 0% 922.23 141.23 100%
19.04 REVOQUES Y ENLUCIDOS
19.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 272.36 9.57 100%
19.05 OTROS
19.05.01 ACCESORIOS CAMARA DE CLORACION GLB 1.00 1,943.24 1,943.24 1943.24 1.00 100% 0.00 0%
20 CAPACITACION
20.01 CAPACITACIONES A POBLADORES GLB 1.00 13,320.02 13,320.02 0.00 0% 0.00 0%
20.02 CAPACITACIONES A JASS GLB 1.00 6,320.02 6,320.02 0.00 0% 0.00 0%
21 MITIGACION AMBIENTAL
21.01 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN OBRAS CIVILES GLB 1.00 22,936.97 22,936.97 3822.83 0.17 17% 7645.66 0.33 33%
21.02 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE AGUA POTABLE GLB 1.00 66,516.64 66,516.64 11086.11 0.17 17% 22172.21 0.33 33%
21.03 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE ALCANTARILLADOGLB 1.00 17,094.26 17,094.26 2849.04 0.17 17% 5698.09 0.33 33%
21.04 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN CONEXIONES DOMICILIARIAGLB 1.00 14,836.06 14,836.06 2472.68 0.17 17% 4945.35 0.33 33%
22 PLAN DE MONITOREO ARQUEOLOGICO
22.01 PLAN DE MONITOREO ARQUEOLOGICO GLB 1.00 71,583.60 71,583.60 11930.60 0.17 17% 23861.20 0.33 33%
Costo Directo S/. 2,768,888.53 354,485.83 1,474,723.03
Gastos Generales 8.00% S/. 221511.08 28,358.87 117,977.84
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
18.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 15.93 28.46 453.37 453.37 15.93 100% 0.00 0%
18.07 OTROS
18.07.01 SUMINISTRO E INSTALACION DE CANALETA DE RAPARTICION L=4m und 24.00 211.08 5,065.92 0.00 0% 0.00 0%
19 CAMARA DE CLORACION
19.01 TRABAJOS PRELIMINARES
19.01.01 TRAZO Y REPLANTEO m2 2.77 7.16 19.83 0.00 0% 0.00 0%
19.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.77 2.40 6.65 0.00 0% 0.00 0%
19.02 MOVIMIENTO DE TIERRAS
19.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 0.00 0%
19.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70 0.00 0% 0.00 0%
19.03 CONCRETO ARMADO
19.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 0.00 0%
19.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92 0.00 0% 0.00 0%
19.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23 0.00 0% 0.00 0%
19.04 REVOQUES Y ENLUCIDOS
19.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 0.00 0%
19.05 OTROS
19.05.01 ACCESORIOS CAMARA DE CLORACION GLB 1.00 1,943.24 1,943.24 0.00 0% 0.00 0%
20 CAPACITACION
20.01 CAPACITACIONES A POBLADORES GLB 1.00 13,320.02 13,320.02 0.00 0% 13320.02 1.00 100%
20.02 CAPACITACIONES A JASS GLB 1.00 6,320.02 6,320.02 0.00 0% 6320.02 1.00 100%
21 MITIGACION AMBIENTAL
21.01 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN OBRAS CIVILES GLB 1.00 22,936.97 22,936.97 7645.66 0.33 33% 3822.83 0.17 17%
21.02 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE AGUA POTABLE GLB 1.00 66,516.64 66,516.64 22172.21 0.33 33% 11086.11 0.17 17%
21.03 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE ALCANTARILLADOGLB 1.00 17,094.26 17,094.26 5698.09 0.33 33% 2849.04 0.17 17%
21.04 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN CONEXIONES DOMICILIARIAGLB 1.00 14,836.06 14,836.06 4945.35 0.33 33% 2472.68 0.17 17%
22 PLAN DE MONITOREO ARQUEOLOGICO
22.01 PLAN DE MONITOREO ARQUEOLOGICO GLB 1.00 71,583.60 71,583.60 23861.20 0.33 33% 11930.60 0.17 17%
Costo Directo S/. 2,768,888.53 850,878.90 88,800.77
Gastos Generales 8.00% S/. 221511.08 68,070.31 7,104.06
CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 16 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
Utilidades 7.00% S/. 193822.20 24,814.01 103,230.61
Sub-Total S/. 3,184,221.81 407,658.71 1,695,931.48
IGV 18.00% S/. 573159.93 73,378.57 305,267.68
Costo de Obra 3,757,381.74 481,037.28 2,001,199.16
Avance Mensual (%) 12.8% 53.3%
Avance Acumulado (%) 12.8% 66.1%
CRONOGRAMA VALORIZADO DE OBRA CRONOGRAMA VALORIZADO DE OBRA

a potable PROYECTO:
y alcantarillado
"Mejoramiento
del distrito de
delLasistema
Pampa,deprovincia
agua potable
de Corongo
y alcantarillado
- Ancash"del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 15) = 15 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
Utilidades 7.00% S/. 193822.20 59,561.52 6,216.05
Sub-Total S/. 3,184,221.81 978,510.73 102,120.88
IGV 18.00% S/. 573159.93 176,131.93 18,381.76
Costo de Obra 3,757,381.74 1,154,642.66 120,502.64
Avance Mensual (%) 30.7% 3.2%
Avance Acumulado (%) 96.8% 100.0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
01 OBRAS PROVICIONALES

01.01 CARTEL DE IDENTIFICACION DE LA OBRA 7.20x3.60 m und 1.00 350.00 350.00 350.00 1.00 100%

01.02 ALQUILER DE LOCAL PARA ALMACEN DE OBRA mes 3.00 300.00


---------
900.00
-----
---------
150.00 0.50 17% 300.00 1.00 33%

01.03 FLETE TERRESTRE GLB 1.00 136,796.89 136,796.89


---------
-----
---------
-----
20519.53
---------
-----0.15 15% 61558.60

01.04 FLETE RURAL GLB 1.00 65,584.72


---------
65,584.72
-----
---------
-----
65584.72 1.00 100%

01.05 ACARREO DE AGREGADO DESDE EL ALMACEN Dprom=0.50km m3 2,011.40 34.48


---------
69,353.07
-----
---------
18048.85 523.46 26% 35245.00 1022.19 51%

01.06 TRANSPORTE DE EQUIPO Y MAQUINARIA A OBRA GLB 1.00 1,000.00


---------
1,000.00
-----
---------
-----
1000.00
---------
-----1.00 100% 0.00 0%

01.07 PARANTES DE H=1.00 M. PROV. P/SEALIZACION Y PROTECCION und 10.00 73.67


---------
736.70
-----
------------------
632.67
-----8.59 86% 71.47 0.97 10%

01.08 CONO DE VIDRIO FOSFORESCENTE und 2.00 45.00


---------
90.00
-----
---------
-----
---------
90.00
-----2.00 100% 0.00 0%

---------
-----
------------------
-----
01.09 CINTA PLASTICA SEALIZADORA P/LIMITE DE SEGURIDAD DE OBRA m 100.00 5.65 565.00 556.75 98.54 99% 8.25 1.46 1%

---------
-----
---------
-----
---------
-----
01.10 PUENTE DE MADERA PROVISIONAL, PASE VEHICULAR Y PEATONAL SOBRE ZANJAS und 13.00 125.75 1,634.75 1634.75 13.00 100% 0.00 0%

---------
-----
------------------
-----
01.11 SEGURIDAD Y SALUD EN OBRA GLB 0.30 59,083.58 17,725.07 17725.07 0.30 100% 0.00 0%

02 CAPTACION TIPO BARRAGE


---------
-----
------------------
-----
02.01 TRABAJOS PRELIMINARES

02.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 9.00 2.40 21.60 21.60 9.00 100% 0.00 0%

02.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 9.00 5.04


---------
45.36
-----
------------------
45.36
-----9.00 100% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
01 OBRAS PROVICIONALES

01.01 CARTEL DE IDENTIFICACION DE LA OBRA 7.20x3.60 m und 1.00 350.00 350.00

01.02 ALQUILER DE LOCAL PARA ALMACEN DE OBRA mes 3.00 300.00


---------
900.00 300 1.00 33% 150.00 0.50 17%

01.03 FLETE TERRESTRE GLB 1.00 136,796.89


---------
---------
136,796.89
-----
---------
-----
54718.756
---------
-----0.40 40%

01.04 FLETE RURAL GLB 1.00 65,584.72


---------
---------
65,584.72
-----
---------
01.05 ACARREO DE AGREGADO DESDE EL ALMACEN Dprom=0.50km m3 2,011.40 34.48
---------
69,353.07 16059.22 465.75 23%

01.06 TRANSPORTE DE EQUIPO Y MAQUINARIA A OBRA GLB 1.00 1,000.00


---------
---------
1,000.00
-----
--------- 0.00 0%

01.07 PARANTES DE H=1.00 M. PROV. P/SEALIZACION Y PROTECCION und 10.00 73.67


---------
736.70
-----
---------
32.56 0.44 4%

01.08 CONO DE VIDRIO FOSFORESCENTE und 2.00 45.00


---------
---------
90.00
-----
--------- 0.00 0%

---------
-----
---------
01.09 CINTA PLASTICA SEALIZADORA P/LIMITE DE SEGURIDAD DE OBRA m 100.00 5.65 565.00 0.00 0%

---------
-----
---------
01.10 PUENTE DE MADERA PROVISIONAL, PASE VEHICULAR Y PEATONAL SOBRE ZANJAS und 13.00 125.75 1,634.75 0.00 0%

---------
-----
---------
01.11 SEGURIDAD Y SALUD EN OBRA GLB 0.30 59,083.58 17,725.07 0.00 0%

02 CAPTACION TIPO BARRAGE


---------
-----
---------
02.01 TRABAJOS PRELIMINARES

02.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 9.00 2.40 21.60 0.00 0%

02.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 9.00 5.04


---------
45.36
-----
--------- 0.00 0%

---------
-----
---------
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
02.02 MOVIMIENTO DE TIERRAS

02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 2.29 42.02 96.23 96.23 2.29 100% 0.00 0%

02.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.96 8.01


---------
31.72
-----
------------------
31.72
-----3.96 100% 0.00 0%

02.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.68 24.01


---------
16.33
-----
------------------
16.33
-----0.68 100% 0.00 0%

02.03 OBRAS DE CONCRETO SIMPLE


---------
-----
------------------
-----
02.03.01 CONCRETO f'c=140 KG/CM2 m3 1.10 389.79 428.77 428.77 1.10 100% 0.00 0%

02.03.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 14.55 62.74


---------
912.87
-----
------------------
912.87
-----
14.55 100% 0.00 0%

02.04 OBRAS DE CONCRETO ARMADO


---------
-----
------------------
-----
02.04.01 CONCRETO f'c=175 KG/CM2, EN CAPTACION m3 1.07 425.25 455.02 455.02 1.07 100% 0.00 0%

02.04.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 11.76 62.74


---------
737.82
-----
------------------
737.82
-----
11.76 100% 0.00 0%

02.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 430.89 6.18


---------
2,662.90
-----
------------------
2662.90
-----
430.89 100% 0.00 0%

02.05 TARRAJEO EN CAPTACIONES


---------
-----
------------------
-----
02.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 2.52 28.46 71.72 71.72 2.52 100% 0.00 0%

02.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 19.66 22.64


---------
445.10
-----
------------------
445.10
-----
19.66 100% 0.00 0%

02.05.03 CURADO DE CONCRETO m2 22.18 3.61


---------
80.07
-----
------------------
80.07
-----
22.18 100% 0.00 0%

02.06 VALVULAS Y ACCESORIOS EN CAPTACION


---------
-----
------------------
-----
02.06.01 SUMINISTRO E INSTALACION DE VALVULAS Y ACCESORIOS EN CAPTACION und 1.00 1,026.40 1,026.40 1026.40 1.00 100% 0.00 0%

02.06.02 PINTURA EN MUROS EXTERIORES m2 19.66 15.21


---------
299.03
-----
------------------
299.03
-----
19.66 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
02.02 MOVIMIENTO DE TIERRAS

02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 2.29 42.02 96.23 0.00 0%

02.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.96 8.01


---------
31.72
-----
--------- 0.00 0%

02.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.68 24.01


---------
16.33
-----
--------- 0.00 0%

02.03 OBRAS DE CONCRETO SIMPLE


---------
-----
---------
02.03.01 CONCRETO f'c=140 KG/CM2 m3 1.10 389.79 428.77 0.00 0%

02.03.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 14.55 62.74


---------
912.87
-----
--------- 0.00 0%

02.04 OBRAS DE CONCRETO ARMADO


---------
-----
---------
02.04.01 CONCRETO f'c=175 KG/CM2, EN CAPTACION m3 1.07 425.25 455.02 0.00 0%

02.04.02 ENCOFRADO Y DESENCOFRADO PARA CAPTACION m2 11.76 62.74


---------
737.82
-----
--------- 0.00 0%

02.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 430.89 6.18


---------
2,662.90
-----
--------- 0.00 0%

02.05 TARRAJEO EN CAPTACIONES


---------
-----
---------
02.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 2.52 28.46 71.72 0.00 0%

02.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 19.66 22.64


---------
445.10
-----
--------- 0.00 0%

02.05.03 CURADO DE CONCRETO m2 22.18 3.61


---------
80.07
-----
--------- 0.00 0%

02.06 VALVULAS Y ACCESORIOS EN CAPTACION


---------
-----
---------
02.06.01 SUMINISTRO E INSTALACION DE VALVULAS Y ACCESORIOS EN CAPTACION und 1.00 1,026.40 1,026.40 0.00 0%

02.06.02 PINTURA EN MUROS EXTERIORES m2 19.66 15.21


---------
299.03
-----
--------- 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

02.07 VARIOS
---------
-----
------------------
-----
02.07.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 2.00 216.77 433.54 433.54 2.00 100% 0.00 0%

02.07.02 TAPA SANITARIA METALICA DE 0.40x0.40 M und 1.00 216.77


---------
216.77
-----
------------------
216.77
-----1.00 100% 0.00 0%

02.07.03 CERCO DE PROTECCION DE ESTRUCTURAS m 30.00 11.95


---------
358.50
-----
------------------
358.50
-----
30.00 100% 0.00 0%

02.07.04 PIEDRA ASENTADA CON MORTERO 1:8 CEMENTO HORMIGON m2 0.72 322.29
---------
232.05
-----
------------------
232.05
-----0.72 100% 0.00 0%

02.07.05 FILTRO DE GRAVAS m3 1.35 72.44


---------
97.79
-----
------------------
97.79
-----1.35 100% 0.00 0%

03 PASE AEREO L=40 M


---------
-----
------------------
-----
03.01 TRABAJOS PRELIMINARES

03.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 400.00 2.40 960.00 960.00 400.00 100% 0.00 0%

03.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 400.00 5.04


---------
2,016.00
-----
------------------
2016.00
-----
400.00 100% 0.00 0%

03.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
03.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 77.50 42.02 3,256.55 3256.55 77.50 100% 0.00 0%

03.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 12.50 8.01


---------
100.13
-----
------------------
100.13
-----
12.50 100% 0.00 0%

03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 32.81 24.01


---------
787.77
-----
------------------
787.77
-----
32.81 100% 0.00 0%

03.03 OBRAS DE CONCRETO SIMPLE


---------
-----
------------------
-----
03.03.01 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. PARA DADOS DE APOYO m3 5.00 1,503.07 7,515.35 7515.35 5.00 100% 0.00 0%

03.04 OBRAS DE CONCRETO ARMADO


---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

02.07 VARIOS
---------
-----
---------
02.07.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 2.00 216.77 433.54 0.00 0%

02.07.02 TAPA SANITARIA METALICA DE 0.40x0.40 M und 1.00 216.77


---------
216.77
-----
--------- 0.00 0%

02.07.03 CERCO DE PROTECCION DE ESTRUCTURAS m 30.00 11.95


---------
358.50
-----
--------- 0.00 0%

02.07.04 PIEDRA ASENTADA CON MORTERO 1:8 CEMENTO HORMIGON m2 0.72 322.29
---------
232.05
-----
--------- 0.00 0%

02.07.05 FILTRO DE GRAVAS m3 1.35 72.44


---------
97.79
-----
--------- 0.00 0%

03 PASE AEREO L=40 M


---------
-----
---------
03.01 TRABAJOS PRELIMINARES

03.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 400.00 2.40 960.00 0.00 0%

03.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 400.00 5.04


---------
2,016.00
-----
--------- 0.00 0%

03.02 MOVIMIENTO DE TIERRAS


---------
-----
---------
03.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 77.50 42.02 3,256.55 0.00 0%

03.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 12.50 8.01


---------
100.13
-----
--------- 0.00 0%

03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 32.81 24.01


---------
787.77
-----
--------- 0.00 0%

03.03 OBRAS DE CONCRETO SIMPLE


---------
-----
---------
03.03.01 CONCRETO CICLOPEO C:H 1:8 + 25% P.M. PARA DADOS DE APOYO m3 5.00 1,503.07 7,515.35 0.00 0%

03.04 OBRAS DE CONCRETO ARMADO


---------
-----
---------
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
03.04.01 CONCRETO f'c=140 KG/CM2 PARA ZAPATAS m3 15.00 446.83 6,702.45 6702.45 15.00 100% 0.00 0%

03.04.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 190.46 6.18


---------
1,177.04
-----
------------------
1177.04
-----
190.46 100% 0.00 0%

03.04.03 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 3.08 469.08


---------
1,444.77
-----
------------------
-----0.00 0% 1444.77 3.08 100%

03.04.04 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 27.72 52.90 1,466.39


-----
---------
-----
1230.00
---------
-----
23.25 84% 236.39 4.47 16%

03.04.05 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 415.87 6.33


---------
2,632.46
-----
---------
-----
2632.46
---------
-----
415.87 100% 0.00 0%

03.05 MONTAJE EN PENDOLAS Y CABLES


---------
-----
------------------
-----
03.05.01 PENDOLA DE ACERO D=1/4" INC. INS. m 67.87 9.53 646.80 0.00 0% 646.80 67.87 100%

03.05.02 TABLERO DE CABLE VIGA H INC. VIGAS H L=1.30 M und 2.00 575.60 1,151.20
-----
---------
-----
---------
0.00
-----
0% 1151.20 2.00 100%

03.05.03 SUMINISTRO E INSTALACION DE ABRAZADERA und 20.00 40.42 808.40


-----
---------
-----
---------
0.00
-----
0% 808.40 20.00 100%

03.05.04 CABLE DE ACERO TIPO BOA D=5/8" INC. INSTALACION m 43.87 28.62 1,255.56
-----
---------
-----
---------
0.00
-----
0% 1255.56 43.87 100%

03.06 REVOQUES Y ENLUCIDOS


-----
---------
-----
---------
-----
03.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 27.72 22.64 627.58 0.00 0% 627.58 27.72 100%

03.07 PINTURA
-----
---------
-----
---------
-----
03.07.01 PINTURA ANTICORROSIVA EN PENDOLAS Y CABLES m2 111.74 11.73 1,310.71 0.00 0% 1310.71 111.74 100%

04 CAMARA ROMPE PRESION


-----
---------
-----
---------
-----
04.01 TRABAJOS PRELIMINARES

04.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 14.67 1.50 22.01 22.01 14.67 100% 0.00 0%

04.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 14.67 5.04


---------
73.94
-----
------------------
65.12
-----
12.92 88% 8.82 1.75 12%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
03.04.01 CONCRETO f'c=140 KG/CM2 PARA ZAPATAS m3 15.00 446.83 6,702.45 0.00 0%

03.04.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 190.46 6.18


---------
1,177.04
-----
--------- 0.00 0%

03.04.03 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 3.08 469.08


---------
1,444.77
-----
--------- 0.00 0%

03.04.04 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 27.72 52.90 1,466.39


-----
--------- 0.00 0%

03.04.05 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 415.87 6.33


---------
2,632.46
-----
--------- 0.00 0%

03.05 MONTAJE EN PENDOLAS Y CABLES


---------
-----
---------
03.05.01 PENDOLA DE ACERO D=1/4" INC. INS. m 67.87 9.53 646.80 0.00 0%

03.05.02 TABLERO DE CABLE VIGA H INC. VIGAS H L=1.30 M und 2.00 575.60 1,151.20
-----
---------
0.00 0%

03.05.03 SUMINISTRO E INSTALACION DE ABRAZADERA und 20.00 40.42 808.40


-----
---------
0.00 0%

03.05.04 CABLE DE ACERO TIPO BOA D=5/8" INC. INSTALACION m 43.87 28.62 1,255.56
-----
---------
0.00 0%

03.06 REVOQUES Y ENLUCIDOS


-----
---------
03.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 27.72 22.64 627.58 0.00 0%

03.07 PINTURA
-----
---------
03.07.01 PINTURA ANTICORROSIVA EN PENDOLAS Y CABLES m2 111.74 11.73 1,310.71 0.00 0%

04 CAMARA ROMPE PRESION


-----
---------
04.01 TRABAJOS PRELIMINARES

04.01.01 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 14.67 1.50 22.01 0.00 0%

04.01.02 TRAZO Y REPLANTEO EN OBRAS DE ARTE MENOR m2 14.67 5.04


---------
73.94
-----
--------- 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

04.02 MOVIMIENTO DE TIERRAS


---------
-----
---------
-----
---------
-----
04.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.97 42.02 671.06 0.00 0% 671.06 15.97 100%

04.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 16.83 8.01 134.81


-----
---------
-----
---------
0.00
-----
0% 134.81 16.83 100%

04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 19.96 24.01 479.24


-----
---------
-----
---------
0.00
-----
0% 479.24 19.96 100%

04.03 OBRAS DE CONCRETO SIMPLE


-----
---------
-----
---------
-----
04.03.01 SOLADO E=2" MEZCLA 1:12 C:H m2 12.15 40.80 495.72 0.00 0% 495.72 12.15 100%

04.04 OBRAS DE CONCRETO ARMADO


-----
---------
-----
---------
-----
04.04.01 CONCRETO f'c=210 KG/CM2 EN CAMARA ROMPE PRESION m3 8.26 433.46 3,580.38 0.00 0% 3,580.38 8.26 100%

04.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA ROMPE PRESION m2 61.38 51.55 3,164.14


-----
---------
-----
---------
0.00
-----
0% 3,164.14 61.38 100%

04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 372.97 6.05 2,256.47


-----
---------
-----
---------
0.00
-----
0% 2256.47 372.97 100%

04.05 REVOQUES Y ENLUCIDOS


-----
---------
-----
---------
-----
04.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 17.64 28.46 502.03 0.00 0% 502.03 17.64 100%

04.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 49.14 22.64 1,112.53


-----
---------
-----
---------
0.00
-----
0% 1,112.53 49.14 100%

04.05.03 CURADO DE CONCRETO m2 66.78 3.61 241.08


-----
---------
-----
---------
0.00
-----
0% 241.08 66.78 100%

04.06 OTROS
-----
---------
-----
---------
-----
04.06.01 ACCESORIOS CRP-6, TUB. INGRESO, SALIDA Y REBOSE, Lc=3 1/2" und 4.00 315.55 1,262.20 0.00 0% 1,262.20 4.00 100%

04.06.02 ACCESORIOS INGRESO CRP-7, LD=3 1/2" und 3.00 1,063.34 3,190.02
-----
---------
-----
---------
0.00
-----
0% 3,190.02 3.00 100%

-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

04.02 MOVIMIENTO DE TIERRAS


---------
-----
---------
04.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.97 42.02 671.06 0.00 0%

04.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 16.83 8.01 134.81


-----
---------
0.00 0%

04.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 19.96 24.01 479.24


-----
---------
0.00 0%

04.03 OBRAS DE CONCRETO SIMPLE


-----
---------
04.03.01 SOLADO E=2" MEZCLA 1:12 C:H m2 12.15 40.80 495.72 0.00 0%

04.04 OBRAS DE CONCRETO ARMADO


-----
---------
04.04.01 CONCRETO f'c=210 KG/CM2 EN CAMARA ROMPE PRESION m3 8.26 433.46 3,580.38 0.00 0%

04.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA ROMPE PRESION m2 61.38 51.55 3,164.14


-----
---------
0.00 0%

04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 372.97 6.05 2,256.47


-----
---------
0.00 0%

04.05 REVOQUES Y ENLUCIDOS


-----
---------
04.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 17.64 28.46 502.03 0.00 0%

04.05.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 49.14 22.64 1,112.53


-----
---------
0.00 0%

04.05.03 CURADO DE CONCRETO m2 66.78 3.61 241.08


-----
---------
0.00 0%

04.06 OTROS
-----
---------
04.06.01 ACCESORIOS CRP-6, TUB. INGRESO, SALIDA Y REBOSE, Lc=3 1/2" und 4.00 315.55 1,262.20 0.00 0%

04.06.02 ACCESORIOS INGRESO CRP-7, LD=3 1/2" und 3.00 1,063.34 3,190.02
-----
---------
0.00 0%

-----
---------
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
04.06.03 ACCESORIOS INGRESO CRP-7, LD=2 1/2" und 2.00 676.00 1,352.00 0.00 0% 1352 2.00 100%

04.06.04 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=3 1/2" und 3.00 155.66 466.98
-----
---------
-----
---------
0.00
-----
0% 466.98 3.00 100%

04.06.05 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=2 1/2" und 2.00 126.85 253.70
-----
---------
-----
---------
0.00
-----
0% 253.7 2.00 100%

04.06.06 SISTEMA DE VENTILACION - CRP und 9.00 20.94 188.46


-----
---------
-----
---------
0.00
-----
0% 188.46 9.00 100%

05 POZA DE FILTRACION
-----
---------
-----
---------
-----
05.01 TRABAJOS PRELIMINARES

05.01.01 TRAZO, NIVELACION Y REPLANTEO m2 88.40 2.77 244.87 0.00 0% 244.87 88.40 100%

05.01.02 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 88.40 2.40 212.16


-----
---------
-----
---------
0.00
-----
0% 212.16 88.40 100%

05.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
05.02.01 EXCAVACION DE ZANJAS PARA ESTRUCTURA EN TERRENO SEMI-ROCOSO m3 282.54 14.67 4,144.86 0.00 0% 4144.86 282.54 100%

05.02.02 REFINE Y NIVELACION EN TERRENO SEMI ROCOSO m2 87.75 4.01 351.88


-----
---------
-----
---------
0.00
-----
0% 351.88 87.75 100%

05.02.03 FILTRO DE GRAVA DE 3/4" A 1 1/2" m3 72.00 167.10 12,031.20


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

05.02.04 ELIMINACION DE MATERIAL EXCEDENTE HASTA D=30 MTS. MANUAL C/CARRETILLA m3 353.18 11.43 4,036.85
-----
------------------
0.00
-----
0% 4036.85 353.18 100%

05.03 OBRAS DE CONCRETO SIMPLE


-----
---------
-----
---------
-----
05.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 88.40 36.01 3,183.28 0.00 0% 3183.28 88.40 100%

05.03.02 DADOS DE CONCRETO SIMPLE DE 0.40x0.40x0.60, INCLUYE COLOCACION DE MADERA 4"x8" m 4.00 20.32 81.28
-----
---------
-----
---------
0.00
-----
0% 81.28 4.00 100%

05.04 OBRAS DE CONCRETO ARMADO


-----
---------
-----
---------
-----
05.04.01 LOSA DE FONDO
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
04.06.03 ACCESORIOS INGRESO CRP-7, LD=2 1/2" und 2.00 676.00 1,352.00 0.00 0%

04.06.04 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=3 1/2" und 3.00 155.66 466.98
-----
---------
0.00 0%

04.06.05 ACCESORIOS TUB. SALIDA Y DESAGUE CRP-7, LD=2 1/2" und 2.00 126.85 253.70
-----
---------
0.00 0%

04.06.06 SISTEMA DE VENTILACION - CRP und 9.00 20.94 188.46


-----
---------
0.00 0%

05 POZA DE FILTRACION
-----
---------
05.01 TRABAJOS PRELIMINARES

05.01.01 TRAZO, NIVELACION Y REPLANTEO m2 88.40 2.77 244.87 0.00 0%

05.01.02 LIMPIEZA, DESBROCE Y ELIMINACION DE VEGETACION MANUAL. m2 88.40 2.40 212.16


-----
---------
0.00 0%

05.02 MOVIMIENTO DE TIERRAS


-----
---------
05.02.01 EXCAVACION DE ZANJAS PARA ESTRUCTURA EN TERRENO SEMI-ROCOSO m3 282.54 14.67 4,144.86 0.00 0%

05.02.02 REFINE Y NIVELACION EN TERRENO SEMI ROCOSO m2 87.75 4.01 351.88


-----
--------- 0.00 0%

05.02.03 FILTRO DE GRAVA DE 3/4" A 1 1/2" m3 72.00 167.10 12,031.20


-----
---------
12031.2 72.00 100%

05.02.04 ELIMINACION DE MATERIAL EXCEDENTE HASTA D=30 MTS. MANUAL C/CARRETILLA m3 353.18 11.43
---------
4,036.85
-----
--------- 0.00 0%

05.03 OBRAS DE CONCRETO SIMPLE


-----
---------
05.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 88.40 36.01 3,183.28 0.00 0%

05.03.02 DADOS DE CONCRETO SIMPLE DE 0.40x0.40x0.60, INCLUYE COLOCACION DE MADERA 4"x8" m 4.00 20.32 81.28
-----
---------
0.00 0%

05.04 OBRAS DE CONCRETO ARMADO


-----
---------
05.04.01 LOSA DE FONDO
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

05.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 19.52 486.26 9,491.80 0.00 0% 9491.80 19.52 100%

05.04.01.02 ENCOFRADO Y DESENCOFRADO PARA LOSA DE FONDO m2 24.48 48.23 1,180.67


-----
---------
-----
---------
0.00
-----
0% 1180.67 24.48 100%

05.04.01.03 ACERO ESTRUCTURAL TRABAJADO PARA LOSA DE FONDO kg 972.16 6.33 6,153.77
-----
---------
-----
---------
0.00
-----
0% 6153.77 972.16 100%

05.04.02 MUROS REFORZADOS


-----
---------
-----
---------
-----
05.04.02.01 ENCOFRADO Y DESENCOFRADO PARA MUROS m2 321.23 47.68 15,316.25 0.00 0% 15316.25 321.23 100%

05.04.02.02 CONCRETO f'c= 210 KG/CM2 PARA MUROS REFORZADOS m3 39.13 475.06 18,589.10
-----
---------
-----
---------
0.00
-----
0% 18589.10 39.13 100%

05.04.02.03 ACERO ESTRUCTURAL TRABAJADO PARA MUROS REFORZADOS kg 521.56 6.24 3,254.53
-----
---------
-----
---------
0.00
-----
0% 3254.53 521.56 100%

05.04.03 COLUMNAS
-----
---------
-----
---------
-----
05.04.03.01 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 4.29 424.28 1,820.16 0.00 0% 1820.16 4.29 100%

05.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 42.88 49.81 2,135.85


-----
---------
-----
---------
0.00
-----
0% 2135.85 42.88 100%

05.04.03.03 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 383.95 6.33 2,430.40


-----
---------
-----
---------
0.00
-----
0% 2430.40 383.95 100%

05.04.04 VIGAS
-----
---------
-----
---------
-----
05.04.04.01 CONCRETO f'c=175 KG/CM2 PARA VIGAS m3 3.58 424.28 1,518.92 0.00 0% 1518.92 3.58 100%

05.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS m2 71.68 49.81 3,570.38


-----
---------
-----
---------
0.00
-----
0% 3570.38 71.68 100%

05.04.04.03 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg 265.73 6.33 1,682.07


-----
---------
-----
---------
0.00
-----
0% 1682.07 265.73 100%

05.05 MURO DE ALBAILERIA


-----
---------
-----
---------
-----
05.05.01 MURO DE CABEZA LADRILLO KING KONG DE ARCILLA CON CEMENTO-ARENA m2 33.60 96.96 3,257.86 0.00 0% 3257.86 33.60 100%

-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

05.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 19.52 486.26 9,491.80 0.00 0%

05.04.01.02 ENCOFRADO Y DESENCOFRADO PARA LOSA DE FONDO m2 24.48 48.23 1,180.67


-----
---------
0.00 0%

05.04.01.03 ACERO ESTRUCTURAL TRABAJADO PARA LOSA DE FONDO kg 972.16 6.33 6,153.77
-----
---------
0.00 0%

05.04.02 MUROS REFORZADOS


-----
---------
05.04.02.01 ENCOFRADO Y DESENCOFRADO PARA MUROS m2 321.23 47.68 15,316.25 0.00 0%

05.04.02.02 CONCRETO f'c= 210 KG/CM2 PARA MUROS REFORZADOS m3 39.13 475.06 18,589.10
-----
---------
0.00 0%

05.04.02.03 ACERO ESTRUCTURAL TRABAJADO PARA MUROS REFORZADOS kg 521.56 6.24 3,254.53
-----
---------
0.00 0%

05.04.03 COLUMNAS
-----
---------
05.04.03.01 CONCRETO f'c=175 KG/CM2 PARA COLUMNAS m3 4.29 424.28 1,820.16 0.00 0%

05.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 42.88 49.81 2,135.85


-----
---------
0.00 0%

05.04.03.03 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 383.95 6.33 2,430.40


-----
---------
0.00 0%

05.04.04 VIGAS
-----
---------
05.04.04.01 CONCRETO f'c=175 KG/CM2 PARA VIGAS m3 3.58 424.28 1,518.92 0.00 0%

05.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS m2 71.68 49.81 3,570.38


-----
---------
0.00 0%

05.04.04.03 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg 265.73 6.33 1,682.07


-----
---------
0.00 0%

05.05 MURO DE ALBAILERIA


-----
---------
05.05.01 MURO DE CABEZA LADRILLO KING KONG DE ARCILLA CON CEMENTO-ARENA m2 33.60 96.96 3,257.86 0.00 0%

-----
---------
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
05.06 REVOQUES Y ENLUCIDOS

05.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 212.40 28.46 6,044.90 0.00 0% 4604.01 161.77 76%

05.06.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 109.00 22.64 2,467.76


-----
---------
-----
---------
0.00
-----
0% 2344.56 103.56 95%

05.07 TUBERIAS Y ACCESORIOS


-----
---------
-----
---------
-----
05.07.01 COMPUERTA MANUAL DE MADERA 0.30x0.60 M und 2.00 823.71 1,647.42 0.00 0% 0.00 0%

05.07.02 EQUIPO CON TUBOS Y VALVULA GLB 1.00 3,634.70 3,634.70


-----
------------------
0.00
-----
0% 0.00 0%

06 RESERVORIO CIRCULAR APOYADO V=55 m3


-----
------------------
-----
06.01 TRABAJOS PRELIMINARES

06.01.01 TRAZO, NIVELACION Y REPLANTEO m2 19.64 2.77 54.40 0.00 0% 54.40 19.64 100%

06.01.02 LIMPIEZA DEL TERRENO MANUAL m2 19.64 2.40 47.14


-----
---------
-----
---------
0.00
-----
0% 41.25 17.19 88%

06.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
06.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 13.99 42.02 587.86 0.00 0% 0.00 0%

06.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 18.85 8.01 150.99


-----
------------------
0.00
-----
0% 0.00 0%

06.02.03 CONFORMACION DE SUB RASANTE PARA PISOS Y VEREDAS m3 19.64 5.14 100.95
-----
------------------
0.00
-----
0% 0.00 0%

06.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 17.48 24.01 419.69


-----
------------------
0.00
-----
0% 0.00 0%

06.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 17.48 23.55 411.65


-----
------------------
0.00
-----
0% 0.00 0%

06.03 OBRAS DE CONCRETO SIMPLE


-----
------------------
-----
06.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 3.93 36.01 141.52 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
05.06 REVOQUES Y ENLUCIDOS

05.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 212.40 28.46 6,044.90 1,440.89 50.63 24%

05.06.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 109.00 22.64


---------
2,467.76
-----
---------
123.2 5.44 5%

05.07 TUBERIAS Y ACCESORIOS


---------
-----
---------
05.07.01 COMPUERTA MANUAL DE MADERA 0.30x0.60 M und 2.00 823.71 1,647.42 1,647.42 2.00 100%

05.07.02 EQUIPO CON TUBOS Y VALVULA GLB 1.00 3,634.70


---------
3,634.70
-----
---------
3,634.70 1.00 100%

06 RESERVORIO CIRCULAR APOYADO V=55 m3


---------
-----
---------
06.01 TRABAJOS PRELIMINARES

06.01.01 TRAZO, NIVELACION Y REPLANTEO m2 19.64 2.77 54.40 0.00 0%

06.01.02 LIMPIEZA DEL TERRENO MANUAL m2 19.64 2.40 47.14


-----
---------
5.89 2.45 12%

06.02 MOVIMIENTO DE TIERRAS


---------
-----
---------
06.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 13.99 42.02 587.86 587.86 13.99 100%

06.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 18.85 8.01


---------
150.99
-----
---------
150.99 18.85 100%

06.02.03 CONFORMACION DE SUB RASANTE PARA PISOS Y VEREDAS m3 19.64 5.14


---------
100.95
-----
---------
100.95 19.64 100%

06.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 17.48 24.01


---------
419.69
-----
---------
419.69 17.48 100%

06.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 17.48 23.55


---------
411.65
-----
---------
411.65 17.48 100%

06.03 OBRAS DE CONCRETO SIMPLE


---------
-----
---------
06.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 3.93 36.01 141.52 141.52 3.93 100%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

06.04 OBRAS DE CONCRETO ARMADO


-----
------------------
-----
06.04.01 VIGA CIRCULAR INFERIOR

06.04.01.01 CONCRETO f'c=245 KG/CM2 m3 5.66 471.42 2,668.24 0.00 0% 0.00 0%

06.04.01.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 371.44 6.05 2,247.21


-----
------------------
0.00
-----
0% 0.00 0%

06.04.01.03 CURADO DE CONCRETO m2 9.43 3.61 34.04


-----
------------------
0.00
-----
0% 0.00 0%

06.04.02 LOSA DE FONDO


-----
------------------
-----
06.04.02.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 3.93 472.06 1,855.20 0.00 0% 0.00 0%

06.04.02.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 373.96 6.05 2,262.46


-----
------------------
0.00
-----
0% 0.00 0%

06.04.02.03 CURADO DE CONCRETO m2 95.03 3.61 343.06


-----
------------------
0.00
-----
0% 0.00 0%

06.04.03 MURO CILINDRICO


-----
------------------
-----
06.04.03.01 CONCRETO f'c=245 KG/CM2 m3 7.25 471.42 3,417.80 0.00 0% 0.00 0%

06.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE MURO CILINDRICO m2 111.54 69.07 7,704.07


-----
------------------
0.00
-----
0% 0.00 0%

06.04.03.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 1,368.79 6.05 8,281.18


-----
------------------
0.00
-----
0% 0.00 0%

06.04.03.04 CURADO DE CONCRETO m2 111.54 3.61 402.66


-----
------------------
0.00
-----
0% 0.00 0%

06.04.04 VIGA CIRCULAR SUPERIOR


-----
------------------
-----
06.04.04.01 CONCRETO f'c=245 KG/CM2 m3 3.73 471.42 1,758.40 0.00 0% 0.00 0%

06.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGA CIRCULAR SUPERIOR m2 12.57 69.07 868.21
-----
------------------
0.00
-----
0% 0.00 0%

-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

06.04 OBRAS DE CONCRETO ARMADO


---------
-----
---------
06.04.01 VIGA CIRCULAR INFERIOR

06.04.01.01 CONCRETO f'c=245 KG/CM2 m3 5.66 471.42 2,668.24 2,668.24 5.66 100%

06.04.01.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 371.44 6.05


---------
2,247.21
-----
---------
2,247.21 371.44 100%

06.04.01.03 CURADO DE CONCRETO m2 9.43 3.61


---------
34.04
-----
---------
34.04 9.43 100% 0.00 0%

06.04.02 LOSA DE FONDO


---------
-----
------------------
-----
06.04.02.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 3.93 472.06 1,855.20 1,855.20 3.93 100% 0.00 0%

06.04.02.02 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 373.96 6.05


---------
2,262.46
-----
------------------
2262.46
-----
373.96 100% 0.00 0%

06.04.02.03 CURADO DE CONCRETO m2 95.03 3.61


---------
343.06
-----
------------------
343.06
-----
95.03 100% 0.00 0%

06.04.03 MURO CILINDRICO


---------
-----
------------------
-----
06.04.03.01 CONCRETO f'c=245 KG/CM2 m3 7.25 471.42 3,417.80 3417.8 7.25 100% 0.00 0%

06.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE MURO CILINDRICO m2 111.54 69.07


---------
7,704.07
-----
------------------
7704.07
-----
111.54 100% 0.00 0%

06.04.03.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 1,368.79 6.05


---------
8,281.18
-----
------------------
8281.18
-----
1368.79 100% 0.00 0%

06.04.03.04 CURADO DE CONCRETO m2 111.54 3.61


---------
402.66
-----
------------------
402.66
-----
111.54 100% 0.00 0%

06.04.04 VIGA CIRCULAR SUPERIOR


---------
-----
------------------
-----
06.04.04.01 CONCRETO f'c=245 KG/CM2 m3 3.73 471.42 1,758.40 1758.4 3.73 100% 0.00 0%

06.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGA CIRCULAR SUPERIOR m2 12.57 69.07


---------
868.21
-----
------------------
868.21
-----
12.57 100% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
06.04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 214.51 6.05 1,297.79 0.00 0% 0.00 0%

06.04.04.04 CURADO DE CONCRETO m2 12.57 3.61 45.38


-----
------------------
0.00
-----
0% 0.00 0%

06.04.05 CUPULA
-----
------------------
-----
06.04.05.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 2.36 472.06 1,114.06 0.00 0% 0.00 0%

06.04.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE CUPULA m2 23.62 69.07 1,631.43


-----
------------------
0.00
-----
0% 0.00 0%

06.04.05.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 461.93 6.05 2,794.68


-----
------------------
0.00
-----
0% 0.00 0%

06.04.05.04 CURADO DE CONCRETO m2 23.62 3.61 85.27


-----
------------------
0.00
-----
0% 0.00 0%

06.04.06 VERTEDERO
-----
------------------
-----
06.04.06.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 0.18 472.06 84.97 0.00 0% 0.00 0%

06.04.06.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VERTEDERO m2 2.60 69.07 179.58


-----
------------------
0.00
-----
0% 0.00 0%

06.04.06.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 17.17 6.05 103.88


-----
------------------
0.00
-----
0% 0.00 0%

06.04.06.04 CURADO DE CONCRETO m2 2.60 3.61 9.39


-----
------------------
0.00
-----
0% 0.00 0%

06.05 REVOQUES Y ENLUCIDOS


-----
------------------
-----
06.05.01 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 20.79 28.10 584.20 0.00 0% 0.00 0%

06.05.02 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 110.52 28.10 3,105.61
-----
------------------
0.00
-----
0% 0.00 0%

06.05.03 MORTERO 1:3 + IMPERMEABILIZANTE P/JUNTA DE CONSTRUCCION m3 151.52 29.80 4,515.30


-----
------------------
0.00
-----
0% 0.00 0%

06.06 PINTURA
-----
------------------
-----
06.06.01 PINTADO DE MUROS DE CUBA CON SIKATOP 144 O SIMILAR m2 221.04 15.04 3,324.44 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
06.04.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 214.51 6.05 1,297.79 1297.79 214.51 100% 0.00 0%

06.04.04.04 CURADO DE CONCRETO m2 12.57 3.61


---------
45.38
-----
------------------
45.38
----- 12.57 100% 0.00 0%

06.04.05 CUPULA
---------
-----
------------------
-----
06.04.05.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 2.36 472.06 1,114.06 1114.06 2.36 100% 0.00 0%

06.04.05.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE CUPULA m2 23.62 69.07


---------
1,631.43
-----
------------------
1631.43
----- 23.62 100% 0.00 0%

06.04.05.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 461.93 6.05


---------
2,794.68
-----
------------------
2794.68
-----
461.93 100% 0.00 0%

06.04.05.04 CURADO DE CONCRETO m2 23.62 3.61


---------
85.27
-----
------------------
85.27
----- 23.62 100% 0.00 0%

06.04.06 VERTEDERO
---------
-----
------------------
-----
06.04.06.01 CONCRETO f'c=245 KG/CM2 P/LOSA Y VERTEDERO m3 0.18 472.06 84.97 84.97 0.18 100% 0.00 0%

06.04.06.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VERTEDERO m2 2.60 69.07


---------
179.58
-----
------------------
179.58
----- 2.60 100% 0.00 0%

06.04.06.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 17.17 6.05


---------
103.88
-----
------------------
103.88
----- 17.17 100% 0.00 0%

06.04.06.04 CURADO DE CONCRETO m2 2.60 3.61


---------
9.39
-----
------------------
9.39
----- 2.60 100% 0.00 0%

06.05 REVOQUES Y ENLUCIDOS


---------
-----
------------------
-----
06.05.01 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 20.79 28.10 584.20 584.2 20.79 100% 0.00 0%

06.05.02 TARRAJEO CON IMPERMEABILIZANTE DE LOZA DE FONDO PISO DE CANALES m2 110.52 28.10
---------
3,105.61
-----
------------------
3105.61
-----
110.52 100% 0.00 0%

06.05.03 MORTERO 1:3 + IMPERMEABILIZANTE P/JUNTA DE CONSTRUCCION m3 151.52 29.80


---------
4,515.30
-----
------------------
4515.3
-----
151.52 100% 0.00 0%

06.06 PINTURA
---------
-----
------------------
-----
06.06.01 PINTADO DE MUROS DE CUBA CON SIKATOP 144 O SIMILAR m2 221.04 15.04 3,324.44 3,324.44 221.04 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

06.07 DOBLE PRUEBA HIDRAULICA


-----
------------------
-----
06.07.01 PRUEBA HIDRAULICA C/EMPLEO DE LA LINEA DE INGRESO(CAPTACION) m 55.00 11.25 618.75 0.00 0% 0.00 0%

06.07.02 EVACUACION AGUA DE PRUEBA C/EMPLEO DE LINEA DE SALIDA m 55.00 1.01 55.55
-----
------------------
0.00
-----
0% 0.00 0%

06.07.03 LIMPIEZA Y DESINFECCION DE RESERVORIOS APOYADOS und 229.81 1.38 317.14


-----
------------------
0.00
-----
0% 0.00 0%

06.08 CARPINTERIA METALICA


-----
------------------
-----
06.08.01 ESCALERA TUB. F. GVZDO. C/PARANTES DE 2" X PELDAOS DE 3/4" und 10.00 172.34 1,723.40 0.00 0% 0.00 0%

06.08.02 MARCO Y TAPA PLANCHA LAC 1/4" C/MECANISM. DE SEG. S/DISEO und 1.00 286.40 286.40
-----
------------------
0.00
-----
0% 0.00 0%

06.08.03 VENTILACION C/TUBERIA DE ACERO S/DISEO DE 4" und 4.00 55.72 222.88
-----
------------------
0.00
-----
0% 0.00 0%

06.08.04 SOPORTE METALICO T/ABRAZADERA P/TUB. DE DIAMETRO 8"-10" und 4.00 44.91 179.64
-----
------------------
0.00
-----
0% 0.00 0%

06.08.05 CANDADO INCLUYE ALDABAS und 3.00 65.14 195.42


-----
------------------
0.00
-----
0% 0.00 0%

06.09 VEREDAS
-----
------------------
-----
06.09.01 VEREDA DE CONCRETO f'c=140 KG/CM2 E=10 CM m2 25.00 64.13 1,603.25 0.00 0% 0.00 0%

06.09.02 CURADO DE CONCRETO PARA VEREDAS m2 40.00 2.31 92.40


-----
------------------
0.00
-----
0% 0.00 0%

06.09.03 JUNTAS ASFALTICAS EN VEREDAS m 18.00 10.47 188.46


-----
------------------
0.00
-----
0% 0.00 0%

06.10 JUNTAS DE DILATACION


-----
------------------
-----
06.10.01 WATER STOP DE PVC DE 6". PROVISION Y COLOCADO DE JUNTA m 35.13 20.44 718.06 0.00 0% 0.00 0%

06.10.02 PROVISION Y COLOCADO DE SELLO IGAS NEGRO gln 35.13 72.66 2,552.55
-----
------------------
0.00
-----
0% 0.00 0%

-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

06.07 DOBLE PRUEBA HIDRAULICA


---------
-----
------------------
-----
06.07.01 PRUEBA HIDRAULICA C/EMPLEO DE LA LINEA DE INGRESO(CAPTACION) m 55.00 11.25 618.75 618.75 55.00 100% 0.00 0%

06.07.02 EVACUACION AGUA DE PRUEBA C/EMPLEO DE LINEA DE SALIDA m 55.00 1.01


---------
55.55
-----
------------------
55.55
-----
55.00 100% 0.00 0%

06.07.03 LIMPIEZA Y DESINFECCION DE RESERVORIOS APOYADOS und 229.81 1.38


---------
317.14
-----
------------------
317.14
-----
229.81 100% 0.00 0%

06.08 CARPINTERIA METALICA


---------
-----
------------------
-----
06.08.01 ESCALERA TUB. F. GVZDO. C/PARANTES DE 2" X PELDAOS DE 3/4" und 10.00 172.34 1,723.40 1,723.40 10.00 100% 0.00 0%

06.08.02 MARCO Y TAPA PLANCHA LAC 1/4" C/MECANISM. DE SEG. S/DISEO und 1.00 286.40
---------
286.40
-----
------------------
286.40
-----1.00 100% 0.00 0%

06.08.03 VENTILACION C/TUBERIA DE ACERO S/DISEO DE 4" und 4.00 55.72


---------
222.88
-----
------------------
222.88
-----4.00 100% 0.00 0%

06.08.04 SOPORTE METALICO T/ABRAZADERA P/TUB. DE DIAMETRO 8"-10" und 4.00 44.91
---------
179.64
-----
------------------
179.64
-----4.00 100% 0.00 0%

06.08.05 CANDADO INCLUYE ALDABAS und 3.00 65.14


---------
195.42
-----
------------------
195.42
-----3.00 100% 0.00 0%

06.09 VEREDAS
---------
-----
------------------
-----
06.09.01 VEREDA DE CONCRETO f'c=140 KG/CM2 E=10 CM m2 25.00 64.13 1,603.25 1,603.25 25.00 100% 0.00 0%

06.09.02 CURADO DE CONCRETO PARA VEREDAS m2 40.00 2.31


---------
92.40
-----
------------------
92.4
-----
40.00 100% 0.00 0%

06.09.03 JUNTAS ASFALTICAS EN VEREDAS m 18.00 10.47


---------
188.46
-----
------------------
188.46
-----
18.00 100% 0.00 0%

06.10 JUNTAS DE DILATACION


---------
-----
------------------
-----
06.10.01 WATER STOP DE PVC DE 6". PROVISION Y COLOCADO DE JUNTA m 35.13 20.44 718.06 718.06 35.13 100% 0.00 0%

06.10.02 PROVISION Y COLOCADO DE SELLO IGAS NEGRO gln 35.13 72.66


---------
2,552.55
-----
------------------
2,552.55
-----
35.13 100% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
07 CASETA DE VALVULAS

07.01 TRABAJOS PRELIMINARES

07.01.01 TRAZO, NIVELACION Y REPLANTEO m2 3.06 2.77 8.48 0.00 0% 8.48 3.06 100%

07.01.02 LIMPIEZA DEL TERRENO MANUAL m2 3.06 2.40 7.34


-----
---------
-----
---------
0.00
-----
0% 6.42 2.68 87%

07.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
07.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.32 33.62 582.30 0.00 0% 0.00 0%

07.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.06 8.01 24.51


-----
------------------
0.00
-----
0% 0.00 0%

07.02.03 RELLENO Y COMPACTACION CON MATERIAL AFIRMADO E=10 CM m2 3.06 4.81 14.72
-----
------------------
0.00
-----
0% 0.00 0%

07.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 1.20 24.01 28.81


-----
------------------
0.00
-----
0% 0.00 0%

07.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1.20 23.55 28.26


-----
------------------
0.00
-----
0% 0.00 0%

07.03 OBRAS DE CONCRETO SIMPLE


-----
------------------
-----
07.03.01 CIMIENTO CORRIDO 1:10 CEMENTO-HORMIGON 30% PIEDRA GRANDE m3 4.26 255.59 1,088.81 0.00 0% 0.00 0%

07.03.02 SOBRECIMIENTO MEZCLA 1:8 CEMENTO-HORMIGON 25% PIEDRA MEDIANA m3 1.58 263.16 415.79
-----
------------------
0.00
-----
0% 0.00 0%

07.03.03 FALSO PISO MEZCLA 1:10 CEMENTO-HORMIGON e=4" m2 5.00 36.07 180.35
-----
------------------
0.00
-----
0% 0.00 0%

07.03.04 PISO DE CONCRETO DE 2" SIN COLOREAR m2 5.00 32.15 160.75


-----
------------------
0.00
-----
0% 0.00 0%

07.04 OBRAS DE CONCRETO ARMADO


-----
------------------
-----
07.04.01 CONCRETO f'c=175 KG/CM2 m3 5.01 198.96 996.79 0.00 0% 0.00 0%

07.04.02 ENCOFRADO Y DESENCOFRADO EN CASETA DE VALVULAS m2 57.70 70.67 4,077.66


-----
------------------
0.00
-----
0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
07 CASETA DE VALVULAS

07.01 TRABAJOS PRELIMINARES

07.01.01 TRAZO, NIVELACION Y REPLANTEO m2 3.06 2.77 8.48 0.00 0% 0.00 0%

07.01.02 LIMPIEZA DEL TERRENO MANUAL m2 3.06 2.40 7.34


-----
------------------
0.92
----- 0.38 13% 0.00 0%

07.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
07.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.32 33.62 582.30 582.3 17.32 100% 0.00 0%

07.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 3.06 8.01


---------
24.51
-----
------------------
24.51
----- 3.06 100% 0.00 0%

07.02.03 RELLENO Y COMPACTACION CON MATERIAL AFIRMADO E=10 CM m2 3.06 4.81


---------
14.72
-----
------------------
14.72
----- 3.06 100% 0.00 0%

07.02.04 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 1.20 24.01


---------
28.81
-----
------------------
28.81
----- 1.20 100% 0.00 0%

07.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1.20 23.55


---------
28.26
-----
------------------
28.26
----- 1.20 100% 0.00 0%

07.03 OBRAS DE CONCRETO SIMPLE


---------
-----
------------------
-----
07.03.01 CIMIENTO CORRIDO 1:10 CEMENTO-HORMIGON 30% PIEDRA GRANDE m3 4.26 255.59 1,088.81 1088.81 4.26 100% 0.00 0%

07.03.02 SOBRECIMIENTO MEZCLA 1:8 CEMENTO-HORMIGON 25% PIEDRA MEDIANA m3 1.58 263.16
---------
415.79
-----
------------------
415.79
----- 1.58 100% 0.00 0%

07.03.03 FALSO PISO MEZCLA 1:10 CEMENTO-HORMIGON e=4" m2 5.00 36.07


---------
180.35
-----
------------------
180.35
----- 5.00 100% 0.00 0%

07.03.04 PISO DE CONCRETO DE 2" SIN COLOREAR m2 5.00 32.15


---------
160.75
-----
------------------
160.75
----- 5.00 100% 0.00 0%

07.04 OBRAS DE CONCRETO ARMADO


---------
-----
------------------
-----
07.04.01 CONCRETO f'c=175 KG/CM2 m3 5.01 198.96 996.79 996.79 5.01 100% 0.00 0%

07.04.02 ENCOFRADO Y DESENCOFRADO EN CASETA DE VALVULAS m2 57.70 70.67


---------
4,077.66
-----
------------------
4,077.66
----- 57.70 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

07.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 769.02 6.05 4,652.57


-----
------------------
0.00
-----
0% 0.00 0%

07.04.04 CURADO DE CONCRETO m2 57.70 3.61 208.30


-----
------------------
0.00
-----
0% 0.00 0%

07.05 MUROS Y TABIQUES DE ALBAILERIA


-----
------------------
-----
07.05.01 MURO DE LADRILLO K.K. 9x14x24, CEMENTO-ARENA 1:5, JUNTA 1.50cm m2 24.94 125.12 3,120.49 0.00 0% 0.00 0%

07.06 REVOQUES, ENLUCIDOS Y PINTURA EN CASETA DE VALVULAS


-----
------------------
-----
07.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 106.54 22.64 2,412.07 0.00 0% 0.00 0%

07.06.02 PINTURA ESMALTE EN EXTERIOR DE ESTRUCTURAS m2 106.54 11.35 1,209.23


-----
------------------
0.00
-----
0% 0.00 0%

07.07 VALVULAS Y ACCESORIOS EN CASETA DE VALVULAS


-----
------------------
-----
07.07.01 SUMINISTRO E INSTALACION DE VALVULA EN CASETA DE VALVULAS und 1.00 3,150.33 3,150.33 0.00 0% 0.00 0%

07.08 TUBERIAS EN CASETA DE VALVULAS


-----
------------------
-----
07.08.01 SUMINISTRO E INSTALACION DE TUBERIAS 4" EN CASETA DE VALVULAS m 6.00 103.23 619.38 0.00 0% 0.00 0%

07.08.02 SUMINISTRO E INSTALACION DE TUBERIAS 3 1/2" EN CASETA DE VALVULAS m 18.00 72.26 1,300.68
-----
------------------
0.00
-----
0% 0.00 0%

07.09 VARIOS
-----
------------------
-----
07.09.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 1.00 216.77 216.77 0.00 0% 0.00 0%

08 LINEA DE CONDUCCION
-----
------------------
-----
08.01 TRABAJOS PRELIMINARES

08.01.01 LIMPIEZA DEL TERRENO MANUAL m2 746.59 0.96 716.73 716.73 746.59 100% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

07.04.03 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 kg 769.02 6.05


---------
4,652.57
-----
------------------
4652.57
-----
769.02 100% 0.00 0%

07.04.04 CURADO DE CONCRETO m2 57.70 3.61


---------
208.30
-----
------------------
208.30
-----
57.70 100% 0.00 0%

07.05 MUROS Y TABIQUES DE ALBAILERIA


---------
-----
------------------
-----
07.05.01 MURO DE LADRILLO K.K. 9x14x24, CEMENTO-ARENA 1:5, JUNTA 1.50cm m2 24.94 125.12 3,120.49 3120.49 24.94 100% 0.00 0%

07.06 REVOQUES, ENLUCIDOS Y PINTURA EN CASETA DE VALVULAS


---------
-----
------------------
-----
07.06.01 TARRAJEO DE INTERIOR Y EXTERIOR m2 106.54 22.64 2,412.07 2,412.07 106.54 100% 0.00 0%

07.06.02 PINTURA ESMALTE EN EXTERIOR DE ESTRUCTURAS m2 106.54 11.35


---------
1,209.23
-----
------------------
1209.23
-----
106.54 100% 0.00 0%

07.07 VALVULAS Y ACCESORIOS EN CASETA DE VALVULAS


---------
-----
------------------
-----
07.07.01 SUMINISTRO E INSTALACION DE VALVULA EN CASETA DE VALVULAS und 1.00 3,150.33 3,150.33 3150.33 1.00 100% 0.00 0%

07.08 TUBERIAS EN CASETA DE VALVULAS


---------
-----
------------------
-----
07.08.01 SUMINISTRO E INSTALACION DE TUBERIAS 4" EN CASETA DE VALVULAS m 6.00 103.23 619.38 619.38 6.00 100% 0.00 0%

07.08.02 SUMINISTRO E INSTALACION DE TUBERIAS 3 1/2" EN CASETA DE VALVULAS m 18.00 72.26


---------
1,300.68
-----
------------------
1300.68
-----
18.00 100% 0.00 0%

07.09 VARIOS
---------
-----
------------------
-----
07.09.01 TAPA SANITARIA METALICA DE 0.60x0.60 M und 1.00 216.77 216.77 216.77 1.00 100% 0.00 0%

08 LINEA DE CONDUCCION
---------
-----
------------------
-----
08.01 TRABAJOS PRELIMINARES

08.01.01 LIMPIEZA DEL TERRENO MANUAL m2 746.59 0.96 716.73 0.00 0% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
08.01.02 TRAZO Y REPLANTEO LINEA DE CONDUCCION m 933.24 1.01 942.57 942.57 933.24 100% 0.00 0%

08.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
08.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 933.24 19.21 17,927.54 14192.64 738.82 79% 3734.9 194.42 21%

08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 933.24 1.50


---------
1,399.86
-----
---------
-----
670.77
---------
-----
447.18 48% 729.09 486.06 52%

08.02.03 CAMA DE APOYO PARA TUBERIA m 933.24 11.00


---------
10,265.64
-----
---------
-----
8,603.31
---------
-----
782.12 84% 1,662.33 151.12 16%

08.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 933.24 31.75
---------
29,630.37
-----
---------
-----
---------
-----
0.00 0% 29,630.37 933.24 100%

08.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS


-----
---------
-----
---------
-----
08.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 933.24 31.25 29,163.75 0.00 0% 29,163.75 933.24 100%

08.03.02 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 933.24 2.93 2,734.39


-----
---------
-----
---------
0.00
-----
0% 2,734.39 933.24 100%

09 RED DE DISTRIBUCION DE AGUA POTABLE


-----
---------
-----
---------
-----
09.01 TRABAJOS PRELIMINARES

09.01.01 LIMPIEZA DEL TERRENO MANUAL m2 461.74 0.96 443.27 443.27 461.74 100% 0.00 0%

09.01.02 TRAZO Y REPLANTEO RED DE DISTRIBUCION DE AGUA POTABLE m 1,577.17 1.01


---------
1,592.94
-----
------------------
1592.94
-----
1577.17 100% 0.00 0%

09.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
09.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 1,763.26 19.21 33,872.22 13870.09 722.02 41% 20,002.13 1041.24 59%

09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 1,763.26 2.27


---------
4,002.60
-----
---------
-----
---------
-----
0.00 0% 4002.6 1763.26 100%

09.02.03 CAMA DE APOYO PARA TUBERIA m 1,763.26 46.52 82,026.86


-----
---------
-----
---------
-----
0.00 0% 82026.86 1763.26 100%

09.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 1,763.26 31.75 55,983.51
-----
---------
-----
---------
-----
0.00 0% 55983.51 1763.26 100%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
08.01.02 TRAZO Y REPLANTEO LINEA DE CONDUCCION m 933.24 1.01 942.57 0.00 0% 0.00 0%

08.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
08.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 933.24 19.21 17,927.54 0.00 0% 0.00 0%

08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 933.24 1.50


---------
1,399.86
-----
------------------
-----
0.00 0% 0.00 0%

08.02.03 CAMA DE APOYO PARA TUBERIA m 933.24 11.00


---------
10,265.64
-----
------------------
-----
0.00 0% 0.00 0%

08.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 933.24 31.75
---------
29,630.37
-----
------------------
-----
0.00 0% 0.00 0%

08.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS


-----
------------------
-----
08.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 933.24 31.25 29,163.75 0.00 0% 0.00 0%

08.03.02 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 933.24 2.93 2,734.39


-----
------------------
0.00 0%
----- 0.00 0%

09 RED DE DISTRIBUCION DE AGUA POTABLE


-----
------------------
-----
09.01 TRABAJOS PRELIMINARES

09.01.01 LIMPIEZA DEL TERRENO MANUAL m2 461.74 0.96 443.27 0.00 0% 0.00 0%

09.01.02 TRAZO Y REPLANTEO RED DE DISTRIBUCION DE AGUA POTABLE m 1,577.17 1.01


---------
1,592.94
-----
------------------
-----
0.00 0% 0.00 0%

09.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
09.02.01 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 1,763.26 19.21 33,872.22 0.00 0% 0.00 0%

09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m 1,763.26 2.27


---------
4,002.60
-----
------------------
-----
0.00 0% 0.00 0%

09.02.03 CAMA DE APOYO PARA TUBERIA m 1,763.26 46.52 82,026.86


-----
------------------
-----
0.00 0% 0.00 0%

09.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 1,763.26 31.75 55,983.51
-----
------------------
-----
0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

09.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.13 24.01 2,620.21


-----
---------
-----
---------
0.00
-----
0% 286.59 11.94 11%

09.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.28 23.55 2,573.54


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

09.03 SUMINISTRO DE INSTALACION DE TUBERIA


-----
------------------
-----
09.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 405.88 31.25 12,683.75 0.00 0% 12683.75 405.88 100%

09.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC D=2" m 55.30 11.17 617.70


-----
---------
-----
---------
0.00
-----
0% 617.7 55.30 100%

09.03.03 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1 1/2" m 563.97 9.71 5,476.15
-----
---------
-----
---------
0.00
-----
0% 5476.15 563.97 100%

09.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1" m 738.11 6.81 5,026.53


-----
---------
-----
---------
0.00
-----
0% 5026.53 738.11 100%

09.03.05 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 1,763.26 2.93 5,166.35


-----
---------
-----
---------
0.00
-----
0% 5166.35 1763.26 100%

09.04 SUMINISTRO DE INSTALACION DE ACCESORIOS


-----
---------
-----
---------
-----
09.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED DE DISTRIBUCION GLB 0.50 7,547.31 3,773.66 0.00 0% 3773.66 0.50 100%

09.05 ROTURA Y REPOSICION DE PAVIMENTO


-----
---------
-----
---------
-----
09.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 365.49 96.59 35,302.68 0.00 0% 30244.19 313.12 86%

09.05.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 45.69 24.01 1,097.02


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

09.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55 1,076.00


-----
------------------
0.00
-----
0% 0.00 0%

10 CONEXIONES DOMICILIARIAS DE AGUA POTABLE


-----
------------------
-----
10.01 TRABAJOS PRELIMINARES

10.01.01 TRAZO, NIVELACION Y REPLANTEO EN ZANJAS m 2,088.00 1.33 2,777.04 2777.04 2088.00 100% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

09.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.13 24.01 2,620.21


-----
------------------
2,333.62
-----
97.19 89% 0.00 0%

09.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.28 23.55


---------
2,573.54
-----
------------------
2573.54
-----
109.28 100% 0.00 0%

09.03 SUMINISTRO DE INSTALACION DE TUBERIA


---------
-----
------------------
-----
09.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, NTP ISO 1452 DN 90 MM (3 1/2") m 405.88 31.25 12,683.75 0.00 0% 0.00 0%

09.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC D=2" m 55.30 11.17 617.70


-----
------------------
0.00 0%
----- 0.00 0%

09.03.03 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1 1/2" m 563.97 9.71 5,476.15
-----
------------------
0.00 0%
----- 0.00 0%

09.03.04 SUMINISTRO E INSTALACION DE TUBERIA PVC D=1" m 738.11 6.81 5,026.53


-----
------------------
0.00 0%
----- 0.00 0%

09.03.05 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 1,763.26 2.93 5,166.35


-----
------------------
0.00 0%
----- 0.00 0%

09.04 SUMINISTRO DE INSTALACION DE ACCESORIOS


-----
------------------
-----
09.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED DE DISTRIBUCION GLB 0.50 7,547.31 3,773.66 0.00 0% 0.00 0%

09.05 ROTURA Y REPOSICION DE PAVIMENTO


-----
------------------
-----
09.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 365.49 96.59 35,302.68 5058.49 52.37 14% 0.00 0%

09.05.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 45.69 24.01


---------
1,097.02
-----
------------------
1097.02
-----
45.69 100% 0.00 0%

09.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55


---------
1,076.00
-----
------------------
1076
-----
45.69 100% 0.00 0%

10 CONEXIONES DOMICILIARIAS DE AGUA POTABLE


---------
-----
------------------
-----
10.01 TRABAJOS PRELIMINARES

10.01.01 TRAZO, NIVELACION Y REPLANTEO EN ZANJAS m 2,088.00 1.33 2,777.04 0.00 0% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
10.02 MOVIMIENTO DE TIERRAS

10.02.01 EXCAVACION MANUAL EN TERRENO NORMAL PARA CAJA 0.40X0.60X0.35 m3 30.00 48.02 1,440.60 1440.6 30.00 100% 0.00 0%

10.02.02 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 2,088.00 19.21


---------
40,110.48
-----
------------------
13608.91
-----
708.43 34% 26,501.57 1379.57 66%

10.02.03 REFINE Y NIVELACION EN TERRENO NORMAL m 2,088.00 1.50


---------
3,132.00
-----
---------
-----
---------
-----
0.00 0% 3,132.00 2088.00 100%

10.02.04 CAMA DE APOYO PARA TUBERIA m 2,088.00 20.41 42,616.08


-----
---------
-----
---------
-----
0.00 0% 42,616.08 2088.00 100%

10.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,088.00 31.75 66,294.00
-----
---------
-----
---------
-----
0.00 0% 0.00 0%

10.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 125.39 24.01 3,010.61


-----
------------------
-----
0.00 0% 0.00 0%

10.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 125.39 23.55 2,952.93


-----
------------------
-----
0.00 0% 0.00 0%

10.03 TUBERIAS Y ACCESORIOS


-----
------------------
-----
10.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, PARA CONEXION DOMICILIARIA m 2,088.00 5.12 10,690.56 0.00 0% 6240.9 1218.93 58%

10.03.02 CONEXION AGUA 1/2" TERRENO NORMAL, INCLUYE LOSA 1X1X0.1 M und 261.00 307.80 80,335.80
-----
---------
-----
---------
0.00
-----
0% 0.00 0%

10.03.03 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 2,088.00 2.93 6,117.84


-----
------------------
0.00
-----
0% 0.00 0%

10.04 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS


-----
------------------
-----
10.04.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 0.00 0%

10.04.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 4.90 80.55 394.70
-----
------------------
0.00
-----
0% 0.00 0%

10.04.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 8.18 24.01 196.40


-----
------------------
0.00
-----
0% 0.00 0%

10.04.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.18 23.55 192.64


-----
------------------
0.00
-----
0% 0.00 0%

11 RED DE ALCANTARILLADO - COLECTOR


-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
10.02 MOVIMIENTO DE TIERRAS

10.02.01 EXCAVACION MANUAL EN TERRENO NORMAL PARA CAJA 0.40X0.60X0.35 m3 30.00 48.02 1,440.60 0.00 0% 0.00 0%

10.02.02 EXCAVACION MANUAL DE ZANJAS (0.50 X 0.80) EN CONGLOMERADO m 2,088.00 19.21


---------
40,110.48
-----
------------------
-----0.00 0% 0.00 0%

10.02.03 REFINE Y NIVELACION EN TERRENO NORMAL m 2,088.00 1.50


---------
3,132.00
-----
------------------
-----0.00 0% 0.00 0%

10.02.04 CAMA DE APOYO PARA TUBERIA m 2,088.00 20.41 42,616.08


-----
------------------
-----0.00 0% 0.00 0%

10.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,088.00 31.75 66,294.00
-----
------------------
48684.66
-----
1533.38 73% 17609.34 554.62 27%

10.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 125.39 24.01


---------
3,010.61
-----
---------
-----
---------
-----0.00 0% 3,010.61 125.39 100%

10.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 125.39 23.55 2,952.93


-----
---------
-----
---------
-----0.00 0% 2,952.93 125.39 100%

10.03 TUBERIAS Y ACCESORIOS


-----
---------
-----
---------
-----
10.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10, PARA CONEXION DOMICILIARIA m 2,088.00 5.12 10,690.56 4449.66 869.07 42% 0.00 0%

10.03.02 CONEXION AGUA 1/2" TERRENO NORMAL, INCLUYE LOSA 1X1X0.1 M und 261.00 307.80
---------
80,335.80
-----
------------------
80335.8
-----
261.00 100% 0.00 0%

10.03.03 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA m 2,088.00 2.93


---------
6,117.84
-----
------------------
6,117.84
-----
2088.00 100% 0.00 0%

10.04 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS


---------
-----
------------------
-----
10.04.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 12,170.34 126.00 100%

10.04.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 4.90 80.55 394.70
-----
---------
-----
0.00
---------
0%
----- 394.70 4.90 100%

10.04.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 8.18 24.01 196.40


-----
---------
-----
0.00
---------
0%
----- 196.4 8.18 100%

10.04.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.18 23.55 192.64


-----
---------
-----
0.00
---------
0%
----- 192.64 8.18 100%

11 RED DE ALCANTARILLADO - COLECTOR


-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

11.01 TRABAJOS PRELIMINARES

11.01.01 LIMPIEZA DEL TERRENO MANUAL m2 2,429.46 0.96 2,332.28 2332.28 2429.46 100% 0.00 0%

11.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 2,858.19 1.36


---------
3,887.14
-----
------------------
3887.14
-----
2858.19 100% 0.00 0%

11.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
11.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 2,244.59 85.15 191,126.84 64966.05 762.96 34% 126160.79 1481.63 66%

11.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 591.12 48.02
---------
28,385.58
-----
---------
-----
9314.02
---------
-----
193.96 33% 19071.56 397.16 67%

11.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 2,858.19 4.35
---------
12,433.13
-----
---------
-----
---------
-----
0.00 0% 12433.13 2858.19 100%

11.02.04 CONFORMACION DE CAMA DE APOYO m 2,858.19 11.88 33,955.30


-----
---------
-----
---------
-----
0.00 0% 33955.3 2858.19 100%

11.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,858.19 31.75 90,747.53
-----
---------
-----
---------
-----
0.00 0% 0.00 0%

11.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 391.98 24.01 9,411.44


-----
------------------
-----
0.00 0% 0.00 0%

11.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 391.98 23.55 9,231.13


-----
------------------
-----
0.00 0% 0.00 0%

11.03 SUMINISTRO DE INSTALACION DE TUBERIA


-----
------------------
-----
11.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 2,858.19 32.08 91,690.74 0.00 0% 91690.74 2858.19 100%

11.04 PRUEBA HIDRAULICA


-----
---------
-----
---------
-----
11.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 2,858.19 3.29 9,403.45 0.00 0% 6913.25 2101.29 74%

11.05 BUZONES O CAMARAS DE INSPECCION


-----
---------
-----
---------
-----
11.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 54.00 2,268.00 122,472.00 0.00 0% 122472 54.00 100%

-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

11.01 TRABAJOS PRELIMINARES

11.01.01 LIMPIEZA DEL TERRENO MANUAL m2 2,429.46 0.96 2,332.28 0.00 0% 0.00 0%

11.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 2,858.19 1.36


---------
3,887.14
-----
------------------
-----
0.00 0% 0.00 0%

11.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
11.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 2,244.59 85.15 191,126.84 0.00 0% 0.00 0%

11.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 591.12 48.02
---------
28,385.58
-----
------------------
-----0.00 0% 0.00 0%

11.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 2,858.19 4.35
---------
12,433.13
-----
------------------
-----0.00 0% 0.00 0%

11.02.04 CONFORMACION DE CAMA DE APOYO m 2,858.19 11.88 33,955.30


-----
------------------
-----0.00 0% 0.00 0%

11.02.05 RELLENO Y COMPACTACION CON MATERIAL PROPIO EN CAPAS DE 10-20cm m 2,858.19 31.75 90,747.53
-----
------------------
90,747.53
-----
2858.19 100% 0.00 0%

11.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 391.98 24.01


---------
9,411.44
-----
------------------
9411.44
-----
391.98 100% 0.00 0%

11.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 391.98 23.55


---------
9,231.13
-----
------------------
9,231.13
-----
391.98 100% 0.00 0%

11.03 SUMINISTRO DE INSTALACION DE TUBERIA


---------
-----
------------------
-----
11.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 2,858.19 32.08 91,690.74 0.00 0% 0.00 0%

11.04 PRUEBA HIDRAULICA


-----
------------------
-----
11.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 2,858.19 3.29 9,403.45 2490.2 756.90 26% 0.00 0%

11.05 BUZONES O CAMARAS DE INSPECCION


---------
-----
------------------
-----
11.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 54.00 2,268.00 122,472.00 0.00 0% 0.00 0%

-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
11.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 9.00 2,399.94 21,599.46 0.00 0% 21599.46 9.00 100%

11.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 66.00 442.89 29,230.74
-----
---------
-----
---------
0.00 0%
----- 29,230.74 66.00 100%

11.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 66.00 460.19 30,372.54
-----
---------
-----
---------
0.00 0%
----- 30,372.54 66.00 100%

11.06 ROTURA Y REPOSICION DE PAVIMENTO


-----
---------
-----
---------
-----
11.06.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 363.49 96.59 35,109.50 0.00 0% 0.00 0%

11.06.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55 1,076.00


-----
------------------
0.00 0%
----- 0.00 0%

12 CONEXIONES DOMICILIARIAS DE DESAGE


-----
------------------
-----
12.01 TRABAJOS PRELIMINARES

12.01.01 TRAZO, NIVELES Y REPLANTEO m2 1,296.00 1.75 2,268.00 2268 1296.00 100% 0.00 0%

12.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
12.02.01 EXCAVACION DE ZANJA T. NORMAL - CONEXION DESAGE m 1,528.00 16.01 24,463.28 17328.16 1082.33 71% 7135.12 445.67 29%

12.02.02 REFINE Y NIVELACION ZANJA TERR.NORMAL"C" PARA TUB. 4"-6" m 1,528.00 2.18
---------
3,331.04
-----
---------
-----
---------
-----
0.00 0% 3331.04 1528.00 100%

12.02.03 CONFORMACION DE CAMA DE APOYO m 1,528.00 11.38 17,388.64


-----
---------
-----
---------
-----
0.00 0% 17388.64 1528.00 100%

12.02.04 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,528.00 6.18 9,443.04
-----
---------
-----
---------
-----
0.00 0% 9443.04 1528.00 100%

12.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 152.80 24.01 3,668.73


-----
---------
-----
---------
-----
0.00 0% 1757.93 73.22 48%

12.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 152.80 23.55 3,598.44


-----
---------
-----
---------
-----
0.00 0% 0.00 0%

12.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS


-----
------------------
-----
12.03.01 ACCESORIOS DE DESAGE und 110.00 138.58 15,243.80 0.00 0% 15243.8 110.00 100%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
11.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 9.00 2,399.94 21,599.46 0.00 0% 0.00 0%

11.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 66.00 442.89 29,230.74
-----
------------------
0.00 0%
----- 0.00 0%

11.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 66.00 460.19 30,372.54
-----
------------------
0.00 0%
----- 0.00 0%

11.06 ROTURA Y REPOSICION DE PAVIMENTO


-----
------------------
-----
11.06.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 363.49 96.59 35,109.50 35109.5 363.49 100% 0.00 0%

11.06.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 45.69 23.55


---------
1,076.00
-----
------------------
1,076.00
-----
45.69 100% 0.00 0%

12 CONEXIONES DOMICILIARIAS DE DESAGE


---------
-----
------------------
-----
12.01 TRABAJOS PRELIMINARES

12.01.01 TRAZO, NIVELES Y REPLANTEO m2 1,296.00 1.75 2,268.00 0.00 0% 0.00 0%

12.02 MOVIMIENTO DE TIERRAS


---------
-----
------------------
-----
12.02.01 EXCAVACION DE ZANJA T. NORMAL - CONEXION DESAGE m 1,528.00 16.01 24,463.28 0.00 0% 0.00 0%

12.02.02 REFINE Y NIVELACION ZANJA TERR.NORMAL"C" PARA TUB. 4"-6" m 1,528.00 2.18
---------
3,331.04
-----
------------------
-----0.00 0% 0.00 0%

12.02.03 CONFORMACION DE CAMA DE APOYO m 1,528.00 11.38 17,388.64


-----
------------------
-----0.00 0% 0.00 0%

12.02.04 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,528.00 6.18 9,443.04
-----
------------------
-----0.00 0% 0.00 0%

12.02.05 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 152.80 24.01 3,668.73


-----
------------------
1,910.80
-----
79.58 52% 0.00 0%

12.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 152.80 23.55


---------
3,598.44
-----
------------------
3598.44
-----
152.80 100% 0.00 0%

12.03 SUMINISTRO DE INSTALACION DE TUBERIA Y ACCESORIOS


---------
-----
------------------
-----
12.03.01 ACCESORIOS DE DESAGE und 110.00 138.58 15,243.80 0.00 0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

12.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 160 MM m 1,528.00 20.67 31,583.76


-----
---------
-----
---------
0.00
-----
0% 31583.76 1528.00 100%

12.04 CAJAS DE INSPECCION Y/O REGISTROS


-----
---------
-----
---------
-----
12.04.01 CAJA DE REGISTRO DE 12" x 24" C/TAPA DE CONCRETO pza 110.00 188.71 20,758.10 0.00 0% 20707.42 109.73 100%

12.05 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS


-----
---------
-----
---------
-----
12.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 12170.34 126.00 100%

12.05.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 14.70 80.55 1,184.09
-----
---------
-----
---------
0.00
-----
0% 1109.29 13.77 94%

12.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.79 23.55 207.00


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

13 EMISOR
-----
------------------
-----
13.01 TRABAJOS PRELIMINARES

13.01.01 LIMPIEZA DEL TERRENO MANUAL m2 876.47 0.96 841.41 0.00 0% 841.41 876.47 100%

13.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 1,031.14 1.36 1,402.35


-----
---------
-----
---------
0.00
-----
0% 1402.35 1031.14 100%

13.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
13.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 1,031.14 85.15 87,801.57 0.00 0% 84312.53 990.16 96%

13.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 78.41 48.02 3,765.25
-----
---------
-----
---------
0.00
-----
0% 882.48 18.38 23%

13.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 1,031.14 3.16 3,258.40
-----
---------
-----
---------
0.00
-----
0% 0.00 0%

13.02.04 CONFORMACION DE CAMA DE APOYO m 1,031.14 11.38 11,734.37


-----
------------------
0.00
-----
0% 0.00 0%

13.02.05 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,031.14 6.18 6,372.45
-----
------------------
0.00
-----
0% 0.00 0%

-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

12.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 160 MM m 1,528.00 20.67 31,583.76


-----
------------------
0.00 0%
----- 0.00 0%

12.04 CAJAS DE INSPECCION Y/O REGISTROS


-----
------------------
-----
12.04.01 CAJA DE REGISTRO DE 12" x 24" C/TAPA DE CONCRETO pza 110.00 188.71 20,758.10 50.68 0.27 0% 0.00 0%

12.05 ROTURA Y REPOSICION DE PAVIMENTO Y VEREDAS


---------
-----
------------------
-----
12.05.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO E=0.15 M m2 126.00 96.59 12,170.34 0.00 0% 0.00 0%

12.05.02 ROTURA Y REPOSICION VEREDA f'c=140 KG/CM2 X 10 CM (PARCHE) m2 14.70 80.55 1,184.09
-----
------------------
74.8
-----0.93 6% 0.00 0%

12.05.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 8.79 23.55


---------
207.00
-----
------------------
207
-----8.79 100% 0.00 0%

13 EMISOR
---------
-----
------------------
-----
13.01 TRABAJOS PRELIMINARES

13.01.01 LIMPIEZA DEL TERRENO MANUAL m2 876.47 0.96 841.41 0.00 0% 0.00 0%

13.01.02 TRAZO Y REPLANTEO PARA ALCANTARILLADO m 1,031.14 1.36 1,402.35


-----
------------------
0.00 0%
----- 0.00 0%

13.02 MOVIMIENTO DE TIERRAS


-----
------------------
-----
13.02.01 EXCAVACION DE ZANJA TERRENO SEMIROCOSO, TUBERIA 8" Hprom=2.00m m 1,031.14 85.15 87,801.57 3489.04 40.98 4% 0.00 0%

13.02.02 EXCAVACION DE ZANJAS PARA BUZONES HASTA 2.00 M DE PROFUNDIDAD PROM. m3 78.41 48.02
---------
3,765.25
-----
------------------
2,882.77
-----
60.03 77% 0.00 0%

13.02.03 REFINE Y NIVELACION ZANJA TERRENO SEMIROCA PARA TUBERIA 8"-10" m 1,031.14 3.16
---------
3,258.40
-----
------------------
3,258.40
-----
1031.14 100% 0.00 0%

13.02.04 CONFORMACION DE CAMA DE APOYO m 1,031.14 11.38


---------
11,734.37
-----
------------------
11,734.37
-----
1031.14 100% 0.00 0%

13.02.05 RELLENO COMPACTADO INC. MATERIAL SELECCIONADO - MATERIAL PROPIO m 1,031.14 6.18
---------
6,372.45
-----
------------------
6372.45
-----
1031.14 100% 0.00 0%

---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
13.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.56 24.01 2,630.54 0.00 0% 0.00 0%

13.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.56 23.55 2,580.14


-----
------------------
0.00
-----
0% 0.00 0%

13.03 SUMINISTRO DE INSTALACION DE TUBERIA


-----
------------------
-----
13.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 1,031.14 32.08 33,078.97 0.00 0% 0.00 0%

13.04 PRUEBA HIDRAULICA


-----
------------------
-----
13.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 1,031.14 3.29 3,392.45 0.00 0% 0.00 0%

13.05 BUZONES O CAMARAS DE INSPECCION


-----
------------------
-----
13.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 12.00 2,268.00 27,216.00 0.00 0% 0.00 0%

13.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 1.00 2,399.94 2,399.94
-----
------------------
0.00
-----
0% 0.00 0%

13.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 13.00 528.40 6,869.20
-----
------------------
0.00
-----
0% 0.00 0%

13.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 13.00 460.19 5,982.47
-----
------------------
0.00
-----
0% 0.00 0%

14 CAJA DE INGRESO
-----
------------------
-----
14.01 TRABAJOS PRELIMINARES

14.01.01 TRAZO, NIVELACION Y REPLANTEO m2 0.64 2.77 1.77 0.00 0% 1.77 0.64 100%

14.01.02 LIMPIEZA DEL TERRENO MANUAL m2 0.64 2.40 1.54


-----
---------
-----
---------
0.00
-----
0% 1.54 0.64 100%

14.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
14.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 0.66 42.02 27.73 0.00 0% 27.73 0.66 100%

14.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.85 24.01 20.41


-----
---------
-----
---------
0.00
-----
0% 20.41 0.85 100%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
13.02.06 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 109.56 24.01 2,630.54 2630.54 109.56 100% 0.00 0%

13.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.56 23.55


---------
2,580.14
-----
------------------
2257.62
----- 95.86 87% 322.52 13.70 13%

13.03 SUMINISTRO DE INSTALACION DE TUBERIA


---------
-----
---------
-----
---------
-----
13.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC UF 200 MM m 1,031.14 32.08 33,078.97 33078.97 1031.14 100% 0.00 0%

13.04 PRUEBA HIDRAULICA


---------
-----
------------------
-----
13.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC DN 200 MM m 1,031.14 3.29 3,392.45 3392.45 1031.14 100% 0.00 0%

13.05 BUZONES O CAMARAS DE INSPECCION


---------
-----
------------------
-----
13.05.01 BUZON TIPO I TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 12.00 2,268.00 27,216.00 27216 12.00 100% 0.00 0%

13.05.02 BUZON TIPO II TERR. NORMAL DIAM. 1.20 M HASTA 3.00 M PF und 1.00 2,399.94
---------
2,399.94
-----
------------------
2399.94
----- 1.00 100% 0.00 0%

13.05.03 SUMINISTRO E INSTALACION DE TECHO DE BUZON - DIAM. 1.20 M und 13.00 528.40
---------
6,869.20
-----
------------------
6869.2
----- 13.00 100% 0.00 0%

13.05.04 SUMINISTRO E INSTALACION DE TAPA DE BUZON C A - DIAM. 0.60 M und 13.00 460.19
---------
5,982.47
-----
------------------
5982.47
----- 13.00 100% 0.00 0%

14 CAJA DE INGRESO
---------
-----
------------------
-----
14.01 TRABAJOS PRELIMINARES

14.01.01 TRAZO, NIVELACION Y REPLANTEO m2 0.64 2.77 1.77 0.00 0% 0.00 0%

14.01.02 LIMPIEZA DEL TERRENO MANUAL m2 0.64 2.40 1.54


-----
------------------
0.00 0%
----- 0.00 0%

14.02 MOVIMIENTO DE TIERRAS


-----
------------------
-----
14.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 0.66 42.02 27.73 0.00 0% 0.00 0%

14.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.85 24.01 20.41


-----
------------------
0.00 0%
----- 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

14.03 CONCRETO ARMADO


-----
---------
-----
---------
-----
14.03.01 CONCRETO f'c= 210 KG/CM2 m3 0.83 586.34 486.66 0.00 0% 486.66 0.83 100%

14.03.02 ENCOFRADO Y DESENCOFRADO m2 6.45 62.74 404.67


-----
---------
-----
---------
0.00
-----
0% 404.67 6.45 100%

14.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 25.29 6.53 165.14


-----
---------
-----
---------
0.00
-----
0% 165.14 25.29 100%

14.04 REVOQUES Y ENLUCIDOS


-----
---------
-----
---------
-----
14.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 3.32 28.46 94.49 0.00 0% 94.49 3.32 100%

14.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 4.43 22.64 100.30


-----
---------
-----
---------
0.00
-----
0% 100.3 4.43 100%

15 CAMARA DE REJAS
-----
---------
-----
---------
-----
15.01 TRABAJOS PRELIMINARES

15.01.01 TRAZO, NIVELACION Y REPLANTEO m2 2.27 2.77 6.29 0.00 0% 6.29 2.27 100%

15.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.27 2.40 5.45


-----
---------
-----
---------
0.00
-----
0% 5.45 2.27 100%

15.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
15.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 58.83 1.40 100%

15.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70


-----
---------
-----
---------
0.00
-----
0% 43.70 1.82 100%

15.03 CONCRETO ARMADO


-----
---------
-----
---------
-----
15.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 844.33 1.44 100%

15.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92


-----
---------
-----
---------
0.00
-----
0% 1023.92 16.32 100%

-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

14.03 CONCRETO ARMADO


-----
------------------
-----
14.03.01 CONCRETO f'c= 210 KG/CM2 m3 0.83 586.34 486.66 0.00 0% 0.00 0%

14.03.02 ENCOFRADO Y DESENCOFRADO m2 6.45 62.74 404.67


-----
------------------
0.00 0%
----- 0.00 0%

14.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 25.29 6.53 165.14


-----
------------------
0.00 0%
----- 0.00 0%

14.04 REVOQUES Y ENLUCIDOS


-----
------------------
-----
14.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 3.32 28.46 94.49 0.00 0% 0.00 0%

14.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 4.43 22.64 100.30


-----
------------------
0.00 0%
----- 0.00 0%

15 CAMARA DE REJAS
-----
------------------
-----
15.01 TRABAJOS PRELIMINARES

15.01.01 TRAZO, NIVELACION Y REPLANTEO m2 2.27 2.77 6.29 0.00 0% 0.00 0%

15.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.27 2.40 5.45


-----
------------------
0.00 0%
----- 0.00 0%

15.02 MOVIMIENTO DE TIERRAS


-----
------------------
-----
15.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 0.00 0%

15.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70


-----
------------------
0.00 0%
----- 0.00 0%

15.03 CONCRETO ARMADO


-----
------------------
-----
15.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 0.00 0%

15.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92


-----
------------------
0.00 0%
----- 0.00 0%

-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
15.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23 0.00 0% 922.23 141.23 100%

15.04 REVOQUES Y ENLUCIDOS


-----
---------
-----
---------
-----
15.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 272.36 9.57 100%

15.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 6.02 22.64 136.29


-----
---------
-----
---------
0.00
-----
0% 136.29 6.02 100%

15.05 OTROS
-----
---------
-----
---------
-----
15.05.01 SISTEMA DE REJAS DE ACERO INOXIDABLE und 1.00 539.54 539.54 0.00 0% 539.54 1.00 100%

16 TANQUE IMHOFF
-----
---------
-----
---------
-----
16.01 TRABAJOS PRELIMINARES

16.01.01 TRAZO, NIVELACION Y REPLANTEO m2 52.46 2.77 145.31 0.00 0% 145.31 52.46 100%

16.01.02 LIMPIEZA DEL TERRENO MANUAL m2 52.46 2.40 125.90


-----
---------
-----
---------
0.00
-----
0% 125.9 52.46 100%

16.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
16.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 387.35 42.02 16,276.45 0.00 0% 16276.45 387.35 100%

16.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 52.46 8.01 420.20


-----
---------
-----
---------
0.00
-----
0% 420.2 52.46 100%

16.02.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 503.55 24.01 12,090.24


-----
---------
-----
---------
0.00
-----
0% 7367.49 306.85 61%

16.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 503.55 23.55 11,858.60


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

16.03 CONCRETO SIMPLE


-----
------------------
-----
16.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 52.46 36.01 1,889.08 0.00 0% 1889.08 52.46 100%

16.03.02 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 12.56 486.26 6,107.43
-----
---------
-----
---------
0.00
-----
0% 6,107.43 12.56 100%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
15.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23 0.00 0% 0.00 0%

15.04 REVOQUES Y ENLUCIDOS


-----
------------------
-----
15.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 0.00 0%

15.04.02 TARRAJEO DE INTERIOR Y EXTERIOR m2 6.02 22.64 136.29


-----
------------------
0.00 0%
----- 0.00 0%

15.05 OTROS
-----
------------------
-----
15.05.01 SISTEMA DE REJAS DE ACERO INOXIDABLE und 1.00 539.54 539.54 0.00 0% 0.00 0%

16 TANQUE IMHOFF
-----
------------------
-----
16.01 TRABAJOS PRELIMINARES

16.01.01 TRAZO, NIVELACION Y REPLANTEO m2 52.46 2.77 145.31 0.00 0% 0.00 0%

16.01.02 LIMPIEZA DEL TERRENO MANUAL m2 52.46 2.40 125.90


-----
------------------
0.00 0%
----- 0.00 0%

16.02 MOVIMIENTO DE TIERRAS


-----
------------------
-----
16.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 387.35 42.02 16,276.45 0.00 0% 0.00 0%

16.02.02 NIVELACION Y COMPACTADO C/MATERIAL PROPIO C/EQUIPO m2 52.46 8.01 420.20


-----
------------------
-----0.00 0% 0.00 0%

16.02.03 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 503.55 24.01 12,090.24


-----
------------------
4,722.75
-----
196.70 39% 0.00 0%

16.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 503.55 23.55


---------
11,858.60
-----
------------------
11,858.60
-----
503.55 100% 0.00 0%

16.03 CONCRETO SIMPLE


---------
-----
------------------
-----
16.03.01 SOLADO DE CONCRETO DE 4" (C:H-1:12) m2 52.46 36.01 1,889.08 0.00 0% 0.00 0%

16.03.02 CONCRETO f'c=210 KG/CM2 PARA LOSA DE FONDO m3 12.56 486.26 6,107.43
-----
------------------
0.00 0%
----- 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

16.04 CONCRETO ARMADO


-----
---------
-----
---------
-----
16.04.01 LOSA DE CIMENTACION

16.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 17.11 486.26 8,319.91 0.00 0% 8120.25 16.70 98%

16.04.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.36 6.53 6,676.01


-----
---------
-----
---------
0.00
-----
0% 6676.01 1022.36 100%

16.04.02 MURO REFORZADO


-----
---------
-----
---------
-----
16.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 44.66 586.34 26,185.94 0.00 0% 0.00 0%

16.04.02.02 ENCOFRADO Y DESENCOFRADO m2 357.24 62.74 22,413.24


-----
------------------
0.00
-----
0% 13558.09 216.10 60%

16.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,705.09 6.53 11,134.24


-----
---------
-----
---------
0.00
-----
0% 11134.24 1705.09 100%

16.04.03 SEDIMENTADOR
-----
---------
-----
---------
-----
16.04.03.01 CONCRETO f'c= 210 KG/CM2 m3 7.35 586.34 4,309.60 0.00 0% 0.00 0%

16.04.03.02 ENCOFRADO Y DESENCOFRADO m2 97.95 62.74 6,145.38


-----
------------------
0.00
-----
0% 4131.96 65.86 67%

16.04.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 746.63 6.53 4,875.49


-----
---------
-----
---------
0.00
-----
0% 4875.49 746.63 100%

16.04.04 CANAL DE REUNION


-----
---------
-----
---------
-----
16.04.04.01 CONCRETO f'c= 210 KG/CM2 m3 0.62 586.34 363.53 0.00 0% 363.53 0.62 100%

16.04.04.02 ENCOFRADO Y DESENCOFRADO m2 8.34 62.74 523.25


-----
---------
-----
---------
0.00
-----
0% 523.25 8.34 100%

16.04.04.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 82.87 6.53 541.14


-----
---------
-----
---------
0.00
-----
0% 541.14 82.87 100%

16.05 REVOQUES Y ENLUCIDOS


-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

16.04 CONCRETO ARMADO


-----
------------------
-----
16.04.01 LOSA DE CIMENTACION

16.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 17.11 486.26 8,319.91 199.66 0.41 2% 0.00 0%

16.04.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.36 6.53


---------
6,676.01
-----
------------------
-----0.00 0% 0.00 0%

16.04.02 MURO REFORZADO


-----
------------------
-----
16.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 44.66 586.34 26,185.94 26185.94 44.66 100% 0.00 0%

16.04.02.02 ENCOFRADO Y DESENCOFRADO m2 357.24 62.74


---------
22,413.24
-----
------------------
8855.15
-----
141.14 40% 0.00 0%

16.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,705.09 6.53


---------
11,134.24
-----
------------------
-----0.00 0% 0.00 0%

16.04.03 SEDIMENTADOR
-----
------------------
-----
16.04.03.01 CONCRETO f'c= 210 KG/CM2 m3 7.35 586.34 4,309.60 4309.6 7.35 100% 0.00 0%

16.04.03.02 ENCOFRADO Y DESENCOFRADO m2 97.95 62.74


---------
6,145.38
-----
------------------
2013.42
-----
32.09 33% 0.00 0%

16.04.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 746.63 6.53


---------
4,875.49
-----
------------------
-----0.00 0% 0.00 0%

16.04.04 CANAL DE REUNION


-----
------------------
-----
16.04.04.01 CONCRETO f'c= 210 KG/CM2 m3 0.62 586.34 363.53 0.00 0% 0.00 0%

16.04.04.02 ENCOFRADO Y DESENCOFRADO m2 8.34 62.74 523.25


-----
------------------
0.00 0%
----- 0.00 0%

16.04.04.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 82.87 6.53 541.14


-----
------------------
0.00 0%
----- 0.00 0%

16.05 REVOQUES Y ENLUCIDOS


-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
16.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 478.95 28.46 13,630.92 0.00 0% 0.00 0%

16.06 OTROS
-----
------------------
-----
16.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS VARIOS EN TANQUE IMHOFF GLB 1.00 4,152.22 4,152.22 0.00 0% 0.00 0%

17 LECHO DE SECADO
-----
------------------
-----
17.01 TRABAJOS PRELIMINARES

17.01.01 TRAZO Y REPLANTEO m2 161.65 7.16 1,157.41 0.00 0% 1157.41 161.65 100%

17.01.02 LIMPIEZA DEL TERRENO MANUAL m2 161.65 2.40 387.96


-----
---------
-----
---------
0.00
-----
0% 387.96 161.65 100%

17.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
17.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 160.57 60.90 9,778.71 0.00 0% 9642.89 158.34 99%

17.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 208.74 24.01 5,011.85


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

17.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 208.74 23.55 4,915.83


-----
------------------
0.00
-----
0% 0.00 0%

17.03 CONCRETO ARMADO


-----
------------------
-----
17.03.01 LOSA DE CIMENTACION

17.03.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 44.82 486.26 21,794.17 0.00 0% 0.00 0%

17.03.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.42 6.53 6,676.40


-----
------------------
0.00
-----
0% 0.00 0%

17.03.02 MURO REFORZADO


-----
------------------
-----
17.03.02.01 CONCRETO f'c= 210 KG/CM2 m3 16.25 586.34 9,528.03 0.00 0% 0.00 0%

17.03.02.02 ENCOFRADO Y DESENCOFRADO m2 216.62 62.74 13,590.74


-----
------------------
0.00
-----
0% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
16.05.01 TARRAJEO CON IMPERMEABILIZANTE m2 478.95 28.46 13,630.92 13630.92 478.95 100% 0.00 0%

16.06 OTROS
---------
-----
------------------
-----
16.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS VARIOS EN TANQUE IMHOFF GLB 1.00 4,152.22 4,152.22 4152.22 1.00 100% 0.00 0%

17 LECHO DE SECADO
---------
-----
------------------
-----
17.01 TRABAJOS PRELIMINARES

17.01.01 TRAZO Y REPLANTEO m2 161.65 7.16 1,157.41 0.00 0% 0.00 0%

17.01.02 LIMPIEZA DEL TERRENO MANUAL m2 161.65 2.40 387.96


-----
------------------
0.00 0%
----- 0.00 0%

17.02 MOVIMIENTO DE TIERRAS


-----
------------------
-----
17.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 160.57 60.90 9,778.71 135.82 2.23 1% 0.00 0%

17.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 208.74 24.01


---------
5,011.85
-----
------------------
5011.85
-----
208.74 100% 0.00 0%

17.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 208.74 23.55


---------
4,915.83
-----
------------------
4915.83
-----
208.74 100% 0.00 0%

17.03 CONCRETO ARMADO


---------
-----
------------------
-----
17.03.01 LOSA DE CIMENTACION

17.03.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 44.82 486.26 21,794.17 21794.17 44.82 100% 0.00 0%

17.03.01.02 ACERO DE REFUERZO fy=4200 KG/CM2 kg 1,022.42 6.53


---------
6,676.40
-----
------------------
6676.4
-----
1022.42 100% 0.00 0%

17.03.02 MURO REFORZADO


---------
-----
------------------
-----
17.03.02.01 CONCRETO f'c= 210 KG/CM2 m3 16.25 586.34 9,528.03 9528.03 16.25 100% 0.00 0%

17.03.02.02 ENCOFRADO Y DESENCOFRADO m2 216.62 62.74


---------
13,590.74
-----
------------------
13590.74
-----
216.62 100% 0.00 0%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

17.03.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 663.75 6.53 4,334.29


-----
------------------
0.00
-----
0% 0.00 0%

17.04 REVOQUES Y ENLUCIDOS


-----
------------------
-----
17.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 366.12 28.46 10,419.78 0.00 0% 0.00 0%

17.05 OTROS
-----
------------------
-----
17.05.01 GRAVA PARA LECHO DE SECADO TM=3/4"-2" m3 42.31 139.01 5,881.51 0.00 0% 0.00 0%

17.05.02 GRAVA PARA LECHO DE SECADO TM=1/4" m3 5.23 143.46 750.30


-----
------------------
0.00
-----
0% 0.00 0%

17.05.03 GRAVA PARA LECHO DE SECADO TM=1/16" m3 11.21 143.46 1,608.19


-----
------------------
0.00
-----
0% 0.00 0%

17.05.04 ARENA GRUESA PARA LECHO DE SECADO m3 4.49 108.52 487.25


-----
------------------
0.00
-----
0% 0.00 0%

18 FILTRO PERCOLADOR
-----
------------------
-----
18.01 TRABAJOS PRELIMINARES

18.01.01 TRAZO Y REPLANTEO m2 42.98 7.16 307.74 0.00 0% 307.74 42.98 100%

18.01.02 LIMPIEZA DEL TERRENO MANUAL m2 42.98 2.40 103.15


-----
---------
-----
---------
0.00
-----
0% 103.15 42.98 100%

18.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
18.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 105.84 60.90 6,445.66 0.00 0% 6445.66 105.84 100%

18.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 137.59 24.01 3,303.54


-----
---------
-----
---------
0.00
-----
0% 1238.83 51.60 38%

18.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 137.59 23.55 3,240.24


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

18.03 CONCRETO SIMPLE


-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

17.03.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 663.75 6.53


---------
4,334.29
-----
------------------
4,334.29
-----
663.75 100% 0.00 0%

17.04 REVOQUES Y ENLUCIDOS


---------
-----
------------------
-----
17.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 366.12 28.46 10,419.78 10,419.78 366.12 100% 0.00 0%

17.05 OTROS
---------
-----
------------------
-----
17.05.01 GRAVA PARA LECHO DE SECADO TM=3/4"-2" m3 42.31 139.01 5,881.51 5,881.51 42.31 100% 0.00 0%

17.05.02 GRAVA PARA LECHO DE SECADO TM=1/4" m3 5.23 143.46


---------
750.30
-----
------------------
750.30
-----5.23 100% 0.00 0%

17.05.03 GRAVA PARA LECHO DE SECADO TM=1/16" m3 11.21 143.46


---------
1,608.19
-----
------------------
1,608.19
-----
11.21 100% 0.00 0%

17.05.04 ARENA GRUESA PARA LECHO DE SECADO m3 4.49 108.52


---------
487.25
-----
------------------
487.25
-----4.49 100% 0.00 0%

18 FILTRO PERCOLADOR
---------
-----
------------------
-----
18.01 TRABAJOS PRELIMINARES

18.01.01 TRAZO Y REPLANTEO m2 42.98 7.16 307.74 0.00 0% 0.00 0%

18.01.02 LIMPIEZA DEL TERRENO MANUAL m2 42.98 2.40 103.15


-----
------------------
0.00 0%
----- 0.00 0%

18.02 MOVIMIENTO DE TIERRAS


-----
------------------
-----
18.02.01 EXCAVACION MANUAL EN CONGLOMERADO-GRAVA ARCILLA m3 105.84 60.90 6,445.66 0.00 0% 0.00 0%

18.02.02 ACARREO DE MATERIAL EXCEDENTE DPROM=30m m3 137.59 24.01 3,303.54


-----
------------------
2064.71
-----
85.99 62% 0.00 0%

18.02.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 137.59 23.55


---------
3,240.24
-----
------------------
3240.24
-----
137.59 100% 0.00 0%

18.03 CONCRETO SIMPLE


---------
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
18.03.01 CONCRETO f'c= 210 KG/CM2 - CANALES DE DIST. Y RECOLECCION m3 2.60 586.34 1,524.48 0.00 0% 1449.93 2.47 95%

18.03.02 ENCOFRADO Y DESENCOFRADO EN CANALES m2 10.56 62.74 662.53


-----
---------
-----
---------
0.00
-----
0% 662.53 10.56 100%

18.04 CONCRETO ARMADO


-----
---------
-----
---------
-----
18.04.01 LOSA DE CIMENTACION

18.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 10.14 486.26 4,930.68 0.00 0% 640.32 1.32 13%

18.04.01.02 ENCOFRADO Y DESENCOFRADO m2 6.50 62.74 407.81


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

18.04.02 MURO REFORZADO


-----
------------------
-----
18.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 14.90 586.34 8,736.47 0.00 0% 6310.37 10.76 72%

18.04.02.02 ENCOFRADO Y DESENCOFRADO m2 118.75 62.74 7,450.38


-----
---------
-----
---------
0.00
-----
0% 0.00 0%

18.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 820.00 6.53 5,354.60


-----
------------------
0.00
-----
0% 0.00 0%

18.04.02.04 VIGUETA PREFABRICADA DE CONCRETO f'c=175 KG/CM2 und 18.00 102.58 1,846.44
-----
------------------
0.00
-----
0% 0.00 0%

18.05 FILTROS
-----
------------------
-----
18.05.01 FILTRO DE PIEDRA m3 27.72 177.44 4,918.64 0.00 0% 0.00 0%

18.06 REVOQUES Y ENLUCIDOS


-----
------------------
-----
18.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 15.93 28.46 453.37 0.00 0% 0.00 0%

18.07 OTROS
-----
------------------
-----
18.07.01 SUMINISTRO E INSTALACION DE CANALETA DE RAPARTICION L=4m und 24.00 211.08 5,065.92 0.00 0% 5065.92 24.00 100%

19 CAMARA DE CLORACION
-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
18.03.01 CONCRETO f'c= 210 KG/CM2 - CANALES DE DIST. Y RECOLECCION m3 2.60 586.34 1,524.48 74.55 0.13 5% 0.00 0%

18.03.02 ENCOFRADO Y DESENCOFRADO EN CANALES m2 10.56 62.74


---------
662.53
-----
------------------
-----0.00 0% 0.00 0%

18.04 CONCRETO ARMADO


-----
------------------
-----
18.04.01 LOSA DE CIMENTACION

18.04.01.01 CONCRETO f'c=210 KG/CM2 PARA LOSA DE CIMENTACION m3 10.14 486.26 4,930.68 4,290.36 8.82 87% 0.00 0%

18.04.01.02 ENCOFRADO Y DESENCOFRADO m2 6.50 62.74


---------
407.81
-----
------------------
407.81
-----6.50 100% 0.00 0%

18.04.02 MURO REFORZADO


---------
-----
------------------
-----
18.04.02.01 CONCRETO f'c= 210 KG/CM2 m3 14.90 586.34 8,736.47 2426.1 4.14 28% 0.00 0%

18.04.02.02 ENCOFRADO Y DESENCOFRADO m2 118.75 62.74


---------
7,450.38
-----
------------------
7450.38
-----
118.75 100% 0.00 0%

18.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 820.00 6.53


---------
5,354.60
-----
------------------
5,354.60
-----
820.00 100% 0.00 0%

18.04.02.04 VIGUETA PREFABRICADA DE CONCRETO f'c=175 KG/CM2 und 18.00 102.58


---------
1,846.44
-----
------------------
1,846.44
-----
18.00 100% 0.00 0%

18.05 FILTROS
---------
-----
------------------
-----
18.05.01 FILTRO DE PIEDRA m3 27.72 177.44 4,918.64 4,918.64 27.72 100% 0.00 0%

18.06 REVOQUES Y ENLUCIDOS


---------
-----
------------------
-----
18.06.01 TARRAJEO CON IMPERMEABILIZANTE m2 15.93 28.46 453.37 453.37 15.93 100% 0.00 0%

18.07 OTROS
---------
-----
------------------
-----
18.07.01 SUMINISTRO E INSTALACION DE CANALETA DE RAPARTICION L=4m und 24.00 211.08 5,065.92 0.00 0% 0.00 0%

19 CAMARA DE CLORACION
-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

19.01 TRABAJOS PRELIMINARES

19.01.01 TRAZO Y REPLANTEO m2 2.77 7.16 19.83 0.00 0% 19.83 2.77 100%

19.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.77 2.40 6.65


-----
---------
-----
---------
0.00
-----
0% 6.65 2.77 100%

19.02 MOVIMIENTO DE TIERRAS


-----
---------
-----
---------
-----
19.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 58.83 1.40 100%

19.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70


-----
---------
-----
---------
0.00
-----
0% 43.7 1.82 100%

19.03 CONCRETO ARMADO


-----
---------
-----
---------
-----
19.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 844.33 1.44 100%

19.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92


-----
---------
-----
---------
0.00
-----
0% 1023.92 16.32 100%

19.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23


-----
---------
-----
---------
0.00
-----
0% 922.23 141.23 100%

19.04 REVOQUES Y ENLUCIDOS


-----
---------
-----
---------
-----
19.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 272.36 9.57 100%

19.05 OTROS
-----
---------
-----
---------
-----
19.05.01 ACCESORIOS CAMARA DE CLORACION GLB 1.00 1,943.24 1,943.24 1943.24 1.00 100% 0.00 0%

20 CAPACITACION
---------
-----
------------------
-----
20.01 CAPACITACIONES A POBLADORES GLB 1.00 13,320.02 13,320.02 0.00 0% 0.00 0%

20.02 CAPACITACIONES A JASS GLB 1.00 6,320.02 6,320.02


-----
------------------
0.00
-----
0% 0.00 0%

-----
------------------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %

19.01 TRABAJOS PRELIMINARES

19.01.01 TRAZO Y REPLANTEO m2 2.77 7.16 19.83 0.00 0% 0.00 0%

19.01.02 LIMPIEZA DEL TERRENO MANUAL m2 2.77 2.40 6.65


-----
------------------
0.00 0%
----- 0.00 0%

19.02 MOVIMIENTO DE TIERRAS


-----
------------------
-----
19.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1.40 42.02 58.83 0.00 0% 0.00 0%

19.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.82 24.01 43.70


-----
------------------
0.00 0%
----- 0.00 0%

19.03 CONCRETO ARMADO


-----
------------------
-----
19.03.01 CONCRETO f'c= 210 KG/CM2 m3 1.44 586.34 844.33 0.00 0% 0.00 0%

19.03.02 ENCOFRADO Y DESENCOFRADO m2 16.32 62.74 1,023.92


-----
------------------
0.00 0%
----- 0.00 0%

19.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 kg 141.23 6.53 922.23


-----
------------------
0.00 0%
----- 0.00 0%

19.04 REVOQUES Y ENLUCIDOS


-----
------------------
-----
19.04.01 TARRAJEO CON IMPERMEABILIZANTE m2 9.57 28.46 272.36 0.00 0% 0.00 0%

19.05 OTROS
-----
------------------
-----
19.05.01 ACCESORIOS CAMARA DE CLORACION GLB 1.00 1,943.24 1,943.24 0.00 0% 0.00 0%

20 CAPACITACION
---------
-----
------------------
-----
20.01 CAPACITACIONES A POBLADORES GLB 1.00 13,320.02 13,320.02 0.00 0% 13320.02 1.00 100%

20.02 CAPACITACIONES A JASS GLB 1.00 6,320.02 6,320.02


-----
---------
-----
0.00
---------
0%
----- 6320.02 1.00 100%

-----
---------
-----
---------
-----
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO A INICIO DE OBRA

PROYECTO: "Mejoramiento del sistema de agua potable y alcantarillado del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

December-2016 January-2017
P. Unit. Parcial
Item Descripcin Und Metrado (15 - 31 ) = 17 DIAS (1 - 31) = 31 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
21 MITIGACION AMBIENTAL

21.01 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN OBRAS CIVILES GLB 1.00 22,936.97 22,936.97 3822.83 0.17 17% 7645.66 0.33 33%

21.02 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE AGUA POTABLE GLB 1.00 66,516.64 66,516.64
---------
-----
---------
-----
11086.11
---------
-----
0.17 17% 22172.21 0.33 33%

21.03 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE ALCANTARILLADOGLB 1.00 17,094.26 17,094.26
---------
-----
---------
-----
2849.04
---------
-----
0.17 17% 5698.09 0.33 33%

21.04 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN CONEXIONES DOMICILIARIAGLB 1.00 14,836.06 14,836.06
---------
-----
---------
-----
2472.68
---------
-----
0.17 17% 4945.35 0.33 33%

22 PLAN DE MONITOREO ARQUEOLOGICO


---------
-----
---------
-----
---------
-----
22.01 PLAN DE MONITOREO ARQUEOLOGICO GLB 1.00 71,583.60 71,583.60 11930.60 0.17 17% 23861.20 0.33 33%

Costo Directo S/. 2,768,888.53


---------
-----
---------
354,485.83
-----
---------
----- 1,474,723.03
Gastos Generales 8.00% S/. 221511.08 28,358.87 117,977.84
Utilidades 7.00% S/. 193822.20 24,814.01 103,230.61
Sub-Total S/. 3,184,221.81 407,658.71 1,695,931.48
IGV 18.00% S/. 573159.93 73,378.57 305,267.68
Costo de Obra 3,757,381.74 481,037.28 2,001,199.16
Avance Mensual (%) 12.8% 53.3%
Avance Acumulado (%) 12.8% 66.1%
CRONOGRAMA VALORIZADO DE OBRA - ACTUALIZADO
CRONOGRAMA
A INICIO DE
VALORIZADO
OBRA DE OBRA - ACTUALIZADO A INICIO DE OBRA

table y alcantarillado
PROYECTO: del
"Mejoramiento
distrito de Ladel
Pampa,
sistema
provincia
de aguadepotable
Corongoy alcantarillado
- Ancash" del distrito de La Pampa, provincia de Corongo - Ancash"
Cliente MUNICIPALIDAD DISTRITAL DE LA PAMPA

Ubicacin : LA PAMPA - CORONGO - ANCASH

February-2017 March-2017
P. Unit. Parcial
Item Descripcin Und Metrado (1 - 28) = 28 DIAS (1 - 14) = 14 DIAS
S/. S/.
Parcial S/. Metrado % Parcial S/. Metrado %
21 MITIGACION AMBIENTAL

21.01 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN OBRAS CIVILES GLB 1.00 22,936.97 22,936.97 7645.66 0.33 33% 3822.83 0.17 17%

21.02 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE AGUA POTABLE GLB 1.00 66,516.64
---------
---------
66,516.64
-----
---------
-----
---------
22172.21
----- 0.33 33% 11086.11 0.17 17%

21.03 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN REDES DE ALCANTARILLADOGLB 1.00 17,094.26
---------
---------
17,094.26
-----
---------
-----
---------
5698.09
----- 0.33 33% 2849.04 0.17 17%

21.04 SEGURIDAD E HIGIENE, SALUD OCUPACIONAL Y MITIGACION AMBIENTAL EN CONEXIONES DOMICILIARIAGLB 1.00 14,836.06
---------
---------
14,836.06
-----
---------
-----
---------
4945.35
----- 0.33 33% 2472.68 0.17 17%

22 PLAN DE MONITOREO ARQUEOLOGICO


---------
---------
-----
---------
-----
---------
-----
22.01 PLAN DE MONITOREO ARQUEOLOGICO GLB 1.00 71,583.60 71,583.60 23861.20 0.33 33% 11930.60 0.17 17%

Costo Directo S/.


---------
---------
2,768,888.53
-----
---------
-----
850,878.90
---------
----- 88,800.77
Gastos Generales 8.00% S/. 221511.08 68,070.31 7,104.06
Utilidades 7.00% S/. 193822.20 59,561.52 6,216.05
Sub-Total S/. 3,184,221.81 978,510.73 102,120.88
IGV 18.00% S/. 573159.93 176,131.93 18,381.76
Costo de Obra 3,757,381.74 1,154,642.66 120,502.64
Avance Mensual (%) 30.7% 3.2%
Avance Acumulado (%) 96.8% 100.0%