QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 04-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural Pre- Cast Double


1 PSAL-QAN-SITEPC-0568 OME-241 9:00 AM
T slab OME-241 R10, R12, R13, R14 & R15 (05Nos.)

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0569 Architectural Pre- Cast Concrete Wall panel OME--250 W24, OME-250 9:30 AM
W25, W26, W27 & W29 (05 NOS.)

Erection Inspection of pre-cast Design panel for SS-442 Grid line Substation 442
3 PSAL-QAN-SITEPC-0570 1/A-D & 18/A-D outside wall panel W37, W39, W41, W43, W45, 8:00 AM
Train 2
W85, W87, W89, W91, W93 & W95.

Erection Inspection of pre-cast Design panel for SS-444 Grid line Substation 444
4 PSAL-QAN-SITEPC-0571 1/A-D & 18/A-D outside wall panel W37, W39, W41, W43, W45, 8:20 AM
Train 4
W85, W87, W89, W91, W93 & W95.

Erection Inspection of pre-cast Design panel for SS-446 Grid line Substation 446
5 PSAL-QAN-SITEPC-0572 1/A-D & 18/A-D outside wall panel W37, W39, W41, W43, W45, 8:40 AM
Train 6
W85, W87, W89, W91, W93 & W95.

Saudi Aramco: Company General Use


Surface Preparation inspection for the vertical connections at
6 PSAL-QAN-SITEPC-0573 PIOB-350 Grid line 2/A-K & 1-2/K wall panel W01 to W43 prior PIOB 350 7:00 AM
to grout

Mixing placement and testing inspection of Grouting vertical


7 PSAL-QAN-SITEPC-0574 connections at PIOB-350 Grid line 2/A-K & 1-2/K wall panel W01 PIOB 350 8:00 AM
to W43

Crushing of Non-Shrink Grout testing & sample Area PIB-342


8 PSAL-QAN-SITEPC-0575 Grid line 1/A-D W46, W48, W50, W52, W54, W56, W58 & W60 PIB 342 Train-2 2:00 PM
for 07 days RFI ref. PSAL-QAN-SITE-PC-0536 (Fugro Jubail)

Crushing of Non-Shrink Grout testing & sample Area SS-444 Grid


line 16-18/D & 18/A-D wall panels W30 to W36, W38, W40, Substation 444
9 PSAL-QAN-SITEPC-0576 2:00 PM
W42, W44, W46 & W48 up to end of the panel for 28 days RFI Train 4
ref. PSAL-QAN-SITE-PC-0427 (Fugro Jubail)

PAINT/CAOTING RFI's

surface preparation Inspection of Repair & Touch-up of 6


1 PSAL-QAN-SITEPC-0577 Corners & under the Roof Galvanized Plates (Embeded) In PIB- PIB 346 Train-6 8:00 AM
346 See highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 04-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht. 01
Rev. 0

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 113224 Sht. 01
Rev. 0

D44-M-RB-
F. Ali/ Ahmad.
Q-012-01 Q-1066 H W W D.Dano Arturo Cabile Alzharani 111682 Sht. 01,
R
02 Rev.01

D44-M-RB-
F. Ali/ Ahmad.
Q-012-01 Q-1066 H W W D.Dano Faisal H. Alzharani 111682 Sht. 01,
R 02 Rev.01

D44-M-RB-
F. Ali/ Ahmad.
Q-012-01 Q-1066 H W W D.Dano Irfan R. Alzharani 111682 Sht. 01,
R 02 Rev.01

Saudi Aramco: Company General Use


D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 111523 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Faisal H. Alzharani 111682 Sht. 01,
R 02 Rev.01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111523 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK & Excluded
W24, W25

OK

OK

OK

Saudi Aramco: Company General Use


Reschedule

Reschedule

OK

OK

Pending

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 05-

Scheduled
SL No RFI No. Description Location Inspection Time

Surface Preparation inspection for the vertical connections at


1 PSAL-QAN-SITEPC-0573 PIOB 350 7:00 AM
PIOB-350 Grid line 1/A-K wall panel W42 to W76 prior to grout

Mixing placement and testing inspection of Grouting vertical


2 PSAL-QAN-SITEPC-0574 PIOB 350 8:00 AM
connections at PIOB-350 Grid line 1/A-K wall panel W42 to W76

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0578 Architectural Pre- Cast Concrete Wall panel OME--250 W20, OME-250 9:30 AM
W21, W22, W23, W24 & W25 (06 NOS.)

Receiving and Storage Inspection for Structural Pre- Cast Double


4 PSAL-QAN-SITEPC-0579 PIOB 350 8:00 AM
T slab PIOB-350 R32 (01 Nos.)

Final Bolt snug Tightening of verticle connections at PIB 344


5 PSAL-QAN-SITEPC-0580 Grid line 1/A-D, 1-5/A, 1-5/B, 1-5/D & 5/A-D inside wall panels PIB 344 Train-4 9:15 AM
W01 to W75 prior to Plastering

Saudi Aramco: Company General Use


Final Bolt snug Tightening of verticle connections at PIB 346
Grid line 1/A-D, 1-5/A & 5/A-D outside wall panels W16, W18, PIB 346 Train-6
6 PSAL-QAN-SITEPC-0581 9:15 AM
W20, W22, W24, W26, W28, W30, W46, W48, W50, W52, W54,
W56, W58 & W60 prior to Plastering

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 05-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 113224 Sht. 01
Rev. 0

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 112580 Sht. 01
Rev. 0

D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111523 Sht. 01
Ali Rev. 01

Saudi Aramco: Company General Use


D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111523 Sht. 01
Ali Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK & Excluded
W20, W21, W22
& W24

OK

Reschedule

Saudi Aramco: Company General Use


Reschedule

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 06-

Scheduled
SL No RFI No. Description Location Inspection Time

Final Bolt snug Tightening of verticle connections at PIB 344


1 PSAL-QAN-SITEPC-0580 Grid line 1/A-D, 1-5/A, 1-5/B, 1-5/D & 5/A-D inside wall panels PIB 344 Train-4 9:15 AM
W01 to W75 prior to Plastering

Final Bolt snug Tightening of verticle connections at PIB 346


Grid line 1/A-D, 1-5/A & 5/A-D outside wall panels W16, W18, PIB 346 Train-6
2 PSAL-QAN-SITEPC-0581 9:15 AM
W20, W22, W24, W26, W28, W30, W46, W48, W50, W52, W54,
W56, W58 & W60 prior to Plastering

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0582 Architectural Pre- Cast Concrete Wall panel OME--250 W17, OME-250 9:30 AM
W18, W19, W20, W21 & W24 (06 NOS.)

Receiving and Storage Inspection for Structural Pre- Cast Double


4 PSAL-QAN-SITEPC-0583 T slab OME-250 R01, R02, R03, R04, R05, R06, R09 & R12 OME-250 9:30 AM
(08Nos.)

Receiving and Storage Inspection for Structural Pre- Cast Double


5 PSAL-QAN-SITEPC-0584 OME-241 8:00 AM
T slab OME-241 R16, R17, R18 & R25 (04Nos.)

Saudi Aramco: Company General Use


Surface Preparation inspection for the vertical connections at
6 PSAL-QAN-SITEPC-0585 PIOB-350 Grid line 1-2/A, 2/J-K & 1-2/K wall panel W28 to W41 PIOB 350 7:00 AM
& W77 to W82 prior to grout

Mixing placement and testing inspection of Grouting vertical


7 PSAL-QAN-SITEPC-0586 connections at PIOB-350 Grid line 1-2/A, 2/J-K & 1-2/K wall PIOB 350 8:00 AM
panel W28 to W41 & W77 to W82

Crushing of Non-Shrink Grout testing & sample Area PIB-342


W01/W60, W15/W16, W26/W75, W30/W31, W45/W46 &
8 PSAL-QAN-SITEPC-0587 PIB 342 Train-2 2:00 PM
W50/W61 for 07 days RFI ref. PSAL-QAN-SITE-PC-0550 (Fugro
Jubail)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 06-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111523 Sht. 01
Ali Rev. 01

D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111523 Sht. 01
Ali Rev. 01

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 113224 Sht. 01
Rev. 0

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 113224 Sht. 01
Rev. 0

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht. 01
Rev. 0

Saudi Aramco: Company General Use


D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 111523 Sht. 01
R
Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

Reschedule

Reschedule

OK

OK

OK

Saudi Aramco: Company General Use


OK

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 07-

Scheduled
SL No RFI No. Description Location Inspection Time

Final Bolt snug Tightening of verticle connections at PIB 344


1 PSAL-QAN-SITEPC-0580 Grid line 1/A-D, 1-5/A, 1-5/B, 1-5/D & 5/A-D inside wall panels PIB 344 Train-4 9:15 AM
W01 to W75 prior to Plastering

Final Bolt snug Tightening of verticle connections at PIB 346


Grid line 1/A-D, 1-5/A & 5/A-D outside wall panels W16, W18, PIB 346 Train-6
2 PSAL-QAN-SITEPC-0581 9:15 AM
W20, W22, W24, W26, W28, W30, W46, W48, W50, W52, W54,
W56, W58 & W60 prior to Plastering

Receiving and Storage Inspection for Structural Pre- Cast Double


3 PSAL-QAN-SITEPC-0588 OME-250 8:30 AM
T slab OME-250 R08, R13 & R19 (03Nos.)

Receiving and Storage Inspection for Structural and


4 PSAL-QAN-SITEPC-0589 Architectural Pre- Cast Concrete Wall panel TDB 750 W01, W05 TDB 750 8:00 AM
& W06 (03 NOS.)

Receiving and Storage Inspection for Structural Pre- Cast Double


5 PSAL-QAN-SITEPC-0590 OME-241 8:00 AM
T slab OME-241 R19 (01Nos.)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 07-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111523 Sht. 01
Ali Rev. 01

D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111523 Sht. 01
Ali Rev. 01

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht. 01
Rev. 0

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 08-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural Pre- Cast Double


1 PSAL-QAN-SITEPC-0591 OME-250 8:30 AM
T slab OME-250 R10, R14, R15, R18 & R21 (05Nos.)

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0592 Architectural Pre- Cast Concrete Wall panel TDB 750 W04, W05, TDB 750 8:00 AM
W07, W08 & W09 (05 NOS.)

Pre-Installation Inspection for Structural and Architectural Pre-


3 PSAL-QAN-SITEPC-0593 cast Wall panel prior to Erection at OME 245 Grid line 1/A-C, 1- OME 245 Train-5 8:30 AM
3/A, 1-3/C & 2/A-C Wall panels W10 to W32

Surface Preparation & Final Formwork Inspection at PIB-346


Grid line 1/A-D & 5/A-D outside wall panel W16, W18, W20,
PSAL-QAN-SITEPC-0594 W22, W24, W26, W28, W30, W46, W48, W50, W52, W54, W56, PIB 346 Train-6
4 7:00 AM
W58 & W60 prior to Plastering

Plastering for verticle connections at PIB-346 Grid line 1/A-D &


5 PSAL-QAN-SITEPC-0595 5/A-D outside wall panel W16, W18, W20, W22, W24, W26, PIB 346 Train-6 7:30 AM
W28, W30, W46, W48, W50, W52, W54, W56, W58 & W60

Saudi Aramco: Company General Use


Surface Preparation inspection for the vertical connections at
6 PSAL-QAN-SITEPC-0596 PIOB 350 7:00 AM
PIOB-350 Grid line 2/A-J wall panel W01 to W28 prior to grout

Mixing placement and testing inspection of Grouting vertical


7 PSAL-QAN-SITEPC-0597 PIOB 350 8:00 AM
connections at PIOB-350 Grid line 2/A-J wall panel W01 to W28

Inspection of Mook-up installation of Sealant (color selection) at Substation 442


8 PSAL-QAN-SITEPC-0598 9:30 AM
SS-442 1M length. Train 2

Crushing of Non-Shrink Grout testing & sample Area SS-446 Grid


line 1-7/A, W1-7/D & 7/A-D Double side wall panels W01 to Substation 446
9 PSAL-QAN-SITEPC-0599 2:00 PM
W12, W72 to W83, & W97 to W110 for 28 days RFI ref. PSAL- Train 6
QAN-SITE-PC-0437 (Fugro Jubail)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 08-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D44-M-RB-
Q-012-01 Q-1065 H H H F. Ali D.Dano Irfan R. Alzharani 116341 Sht. 01
Rev. 02

D44-M-RB-
Q-010-01 Q-1048 H W H F. Ali D.Dano Richard Alzharani 111668 Sht. 01
Rev. 01

D44-M-RB-
N/A N/A W W W F. Ali D.Dano Richard Alzharani 111668 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 0

D44-M-RB-
QDC-ITP-010 QDC-CL-C-012 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 111682 Sht. 01,
02 Rev.01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Irfan R. Alzharani 112494 Sht. 01,
R 02 Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK & Excluded
W04, W05 &
W07

Reschedule

OK

OK

Saudi Aramco: Company General Use


OK

OK

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 09-

Scheduled
SL No RFI No. Description Location Inspection Time

Pre-Installation Inspection for Structural and Architectural Pre-


1 PSAL-QAN-SITEPC-0593 cast Wall panel prior to Erection at OME 245 Grid line 1/A-C, 1- OME 245 Train-5 8:30 AM
3/A, 1-3/C & 2/A-C Wall panels W10 to W32

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0600 Architectural Pre- Cast Concrete Wall panel OME-250 W51, OME-250 Area-B 8:30 AM
W53, W55 & W56 (04 NOS.)

Receiving and Storage Inspection for Structural Pre- Cast Double OME-250 Area-B
3 PSAL-QAN-SITEPC-0601 8:30 AM
T slab OME-250 R11, R17, R16, R25, R26 & R28 (06Nos.)

Receiving and Storage Inspection for Structural and


4 PSAL-QAN-SITEPC-0602 Architectural Pre- Cast Concrete Wall panel OME-241 W13, W16 OME-241 Train-1 8:00 AM
& W23 (03 NOS.)

Receiving and Storage Inspection for Structural and


5 PSAL-QAN-SITEPC-0603 Architectural Pre- Cast Concrete Wall panel TDB 750 W04, W05, TDB 750 Area-B 8:00 AM
W07, W10, W11 & W12 (06 NOS.)

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area SS-446 Grid Substation 446
6 PSAL-QAN-SITEPC-0604 line 7-18/A wall panels W49 to W71 for 28 days RFI ref. PSAL- 2:00 PM
Train 6
QAN-SITE-PC-0453 (Fugro Jubail)

PAINT/CAOTING RFI's
surface preparation Inspection of Repair & Touch-up of 6
1 PSAL-QAN-SITEPC-0577 Corners & under the Roof Galvanized Plates (Embeded) In PIB- PIB 346 Train-6 8:00 AM
346 See highlights on the attached drawings)

surface preparation Inspection of Repair & Touch-up of under


Substation 446
2 PSAL-QAN-SITEPC-0605 the Roof Galvanized Plates (Embeded) In SS-446 See highlights 8:00 AM
Train 6
on the attached drawings)

surface preparation Inspection of Repair & Touch-up of Upside


3 PSAL-QAN-SITEPC-0606 the Roof Galvanized Plates (Embeded) In PIOB-350 See PIOB 350 Area-B 8:00 AM
highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 09-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
D.Dano / Vincent
Q-012-01 Q-1065 H H H F. Ali Irfan R. Alzharani 116341 Sht. 01
M Rev. 02

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

Saudi Aramco: Company General Use


D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112494 Sht. 01,
R 02 Rev.01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111668 Sht. 01
Rev. 01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Irfan R. Mark Castillo 112494 Sht. 01,
02 Rev.01

D45-M-RB-
H-100-04 H-2034 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

OK

OK & Ecluded
W05, W11 & W12

Saudi Aramco: Company General Use


OK

Ok

Pending

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 10-

Scheduled
SL No RFI No. Description Location Inspection Time

Crushing of Non-Shrink Grout testing & sample Area SS-446 Grid Substation 446
1 PSAL-QAN-SITE-PC-0607 line 7-18/D wall panels W13 to W35 for 28 days RFI ref. PSAL- 9:00 AM
Train 6
QAN-SITE-PC-0455 (Fugro Jubail)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 10-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-010-01 Q-1049 H W W F. Ali D.Dano Isack Alzharani 112494 Sht. 01,
02 Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 11-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural Pre- Cast Double OME-250 Area-B
1 PSAL-QAN-SITEPC-0608 8:50 AM
T slab OME-250 R07, R14, R20, R22, R23, R24 & R27 (07Nos.)

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0609 Architectural Pre- Cast Concrete Wall panel OME-250 W52, OME-250 Area-B 8:20 AM
W54, W57 & W58 (04 NOS.)

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0610 Architectural Pre- Cast Concrete Wall panel OME-241 W12, W15 OME-241 Train-1 8:40 AM
& W18 (03 NOS.)

Receiving and Storage Inspection for Structural and


4 PSAL-QAN-SITEPC-0611 Architectural Pre- Cast Concrete Wall panel TDB 750 W03, W05, TDB 750 Area-B 8:00 AM
W11, W12, W13 & W14 (06 NOS.)

Surface Preparation inspection for the vertical connections at


5 PSAL-QAN-SITEPC-0612 PIB-346 Grid line 1-5/B & 1-5/D wall panel W01 to W15 & W61 PIB 346 Train-6 7:00 AM
to W75 prior to grout

Mixing placement and testing inspection of Grouting vertical


6 PSAL-QAN-SITEPC-0613 connections at PIB-346 Grid line 1-5/B & 1-5/D wall panel W01 PIB 346 Train-6 8:00 AM
to W15 & W61 to W75

Saudi Aramco: Company General Use


Surface Preparation & Final Formwork Inspection at PIB-344
7 PSAL-QAN-SITEPC-0614 Grid line 1/A-D, 1-5/A, 1-5/B, 1-5/D & 5/A-D inside wall panel PIB 344 Train-4 7:00 AM
W01 to W75 prior to Plastering

Plastering for verticle connections at PIB-344 Grid line 1/A-D, 1-


8 PSAL-QAN-SITEPC-0615 PIB 344 Train-4 7:30 AM
5/A, 1-5/B, 1-5/D & 5/A-D inside wall panel W01 to W75

Crushing of Non-Shrink Grout testing & sample Area SS-446 Grid


line 13-18/D, 18/A-D & 1A-D wall panels W36, W38, W40, W42, Substation 446
9 PSAL-QAN-SITEPC-0616 2:00 PM
W44, W46, W48 to W59, W84, W86, W88, W90, W92, W94 & Train 6
W96 for 28 days RFI ref. PSAL-QAN-SITE-PC-0459 (Fugro Fadhili)

PAINT/CAOTING RFI's
Final Inspection of Repair & Touch-up of 6 Corners & under the
1 PSAL-QAN-SITEPC-0617 Roof Galvanized Plates (Embeded) In PIB-346 See highlights on PIB 346 Train-6 8:00 AM
the attached drawings)

Final Inspection of Repair & Touch-up of Upside the Roof


2 PSAL-QAN-SITEPC-0618 Galvanized Plates (Embeded) In PIOB-350 See highlights on the PIOB 350 Area-B 2:00 PM
attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 11-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Richard Alzharani 111668 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Richard Alzharani 111668 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
N/A N/A W W W D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112494 Sht. 01,
R 02 Rev.01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111668 Sht. 01
Rev. 01

D45-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

OK & Excluded
W05, W11,
W12, W13 &
W14

OK

OK & Excluded
Grid line 3-5/D

Saudi Aramco: Company General Use


OK

OK

OK

OK

Pending

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 12-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0619 Architectural Pre- Cast Concrete Wall panel OME-241 W11, OME-241 Train-1 8:40 AM
W14, W17, W19, W20 & W22 (06 NOS.)

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0620 Architectural Pre- Cast Concrete Wall panel TDB 750 W05, W11, TDB 750 Area-B 8:00 AM
W12, W13 & W14 (05 NOS.)

Surface Preparation inspection for the vertical connections at


3 PSAL-QAN-SITEPC-0621 PIB-346 Grid line 1/A-D & 1-5/A wall panel W31 to W46, W48, PIB 346 Train-6 7:00 AM
W50, W52, W54, W56, W58 & W60 prior to grout

Mixing placement and testing inspection of Grouting vertical


connections at PIB-346 Grid line 1/A-D, 1-5/A & 3-5/D wall panel PIB 346 Train-6
4 PSAL-QAN-SITEPC-0622 8:00 AM
W07 to W15, W31 to W46, W48, W50, W52, W54, W56, W58 &
W60

Final inspection of Vertical connection steel plate joints


5 PSAL-QAN-SITEPC-0623 PIOB 350 9:00 AM
between 2 wall panels W54 & W55 at PIOB 350

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area PIOB-350
6 PSAL-QAN-SITEPC-0624 Grid line 2/A-K & 1-2/K wall panel W01 to W43 for 07 days RFI PIOB 350 2:00 PM
ref. PSAL-QAN-SITE-PC-0574 (Fugro Fadhili)

PAINT/CAOTING RFI's
Final Inspection of Repair & Touch-up of Upside the Roof
1 PSAL-QAN-SITEPC-0618 Galvanized Plates (Embeded) In PIOB-350 See highlights on the PIOB 350 Area-B 8:00 AM
attached drawings)

surface preparation Inspection of Repair & Touch-up of upside


2 PSAL-QAN-SITEPC-0625 the Roof Galvanized Plates (Embeded) In PIB-346 See highlights PIB 346 Train-6 9:00 AM
on the attached drawings)

surface preparationl Inspection of Repair & Touch-up of Under


3 PSAL-QAN-SITEPC-0626 the Roof & all vertical cornera Galvanized Plates (Embeded) In PIOB 350 Area-B 10:00 AM
PIOB-350 See highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 12-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Richard Alzharani 111668 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Richard Alzharani 111668 Sht. 01
R Rev. 01

D45-M-RB-
F. Ali/ Ahmad.
M-100-03 M-1072 I W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 01

D45-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111668 Sht. 01
Rev. 01

D45-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

Reschedule

OK

OK

Delete

Saudi Aramco: Company General Use


OK

Open

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 13-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0620 Architectural Pre- Cast Concrete Wall panel TDB 750 W05, W11, TDB 750 Area B 8:00 AM
W12, W13 & W14 (05 NOS.)

Final inspection of Vertical connection steel plate joints


2 PSAL-QAN-SITEPC-0623 PIOB 350 Area B 9:00 AM
between 2 wall panels W54 & W55 at PIOB 350

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0627 Architectural Pre- Cast Concrete Wall panel OME-241 W21, W24 OME-241 Train-1 8:40 AM
& W27 (03 NOS.)

Receiving and Storage Inspection for Structural connections


4 PSAL-QAN-SITEPC-0628 Angle bars 100X100X8MM (505 pcs) OME 250, PIB-344 (228 OME-250 Area-B 10:00 AM
Pcs) & PIB 346 (276 pcs).

Receiving and Storage Inspection for Grouting Material


5 PSAL-QAN-SITEPC-0629 OME-250 Area-B 8:00 AM
Conbextra GP 1000 (bags) & Renderoc TG Xtra 280 (Bags)

Final Bolt snug Tightening of verticle connections at PIB 344


Grid line 1/A-D, 1-5/A & 5/A-D outside wall panels W16, W18, PIB 344 Train-4
6 PSAL-QAN-SITEPC-0630 9:15 AM
W20, W22, W24, W26, W28, W30, W46, W48, W50, W52, W54,
W56, W58 & W60 prior to Plastering

Saudi Aramco: Company General Use


Surface Preparation Inspection for vertical connections at PIB-
344 Grid line 1/A-D & 5/A-D outside wall panel W16, W18, W20, PIB 344 Train-4
7 PSAL-QAN-SITEPC-0631 7:00 AM
W22, W24, W26, W28, W30, W46, W48, W50, W52, W54, W56,
W58 & W60 prior to Plastering

Plastering for verticle connections at PIB-344 Grid line 1/A-D &


8 PSAL-QAN-SITEPC-0632 5/A-D outside wall panel W16, W18, W20, W22, W24, W26, PIB 344 Train-4 7:30 AM
W28, W30, W46, W48, W50, W52, W54, W56, W58 & W60

Surface Preparation Inspection for vertical connections 6


9 PSAL-QAN-SITEPC-0633 corners at PIB 346 wall panels W01/W60, W15/W16, PIB 346 Train-6 7:00 AM
W26/W75, W30/W31, W45/W46 & W50/61 prior to Plastering

Plastering for verticle connections 6 corners at PIB 346 wall


10 PSAL-QAN-SITEPC-0634 panels W01/W60, W15/W16, W26/W75, W30/W31, W45/W46 PIB 346 Train-6 7:30 AM
& W50/61

Surface Preparation Inspection for vertical connections all


11 PSAL-QAN-SITEPC-0635 corners & upside the Roof at PIOB 350 Full building prior to PIOB 350 Area-B 8:30 AM
Plastering

Plastering for verticle connections all corners & upside the Roof PIOB 350 Area-B
12 PSAL-QAN-SITEPC-0636 8:40 AM
at PIOB 350 Full building

Crushing of Non-Shrink Grout testing & sample Area PIOB-350


13 PSAL-QAN-SITEPC-0637 Grid line 1-2/A, 2/J-K & 1-2/K wall panel W28 to W41 & W77 to PIOB 350 Area-B 2:00 PM
W82 for 07 days RFI ref. PSAL-QAN-SITE-PC-0586 (Fugro Fadhili)

PAINT/CAOTING RFI's

Saudi Aramco: Company General Use


Final Inspection of Repair & Touch-up of Under the Roof & all
1 PSAL-QAN-SITEPC-0638 vertical corners Galvanized Plates (Embeded) In PIOB-350 See PIOB 350 Area-B 8:00 AM
highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 13-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D45-M-RB-
F. Ali/ Ahmad.
M-100-03 M-1072 I W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 01

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D45-M-RB-
Q-012-01 Q-1064 H W W F. Ali Carlus Isack Alzharani 116355 Sht. 01
Rev. 2

D45-M-RB-
Q-010-01 Q-1047 I I W F. Ali Carlus Isack Alzharani 116355 Sht. 01
Rev. 2

D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111537 Sht. 01
Ali Rev. 01

Saudi Aramco: Company General Use


D44-M-RB-
Q-010-01 Q-1048 H W H F. Ali D.Dano Richard Alzharani 111537 Sht. 01
Rev. 01

D44-M-RB-
N/A N/A W W W F. Ali D.Dano Richard Alzharani 111537 Sht. 01
Rev. 01

D44-M-RB-
Q-010-01 Q-1048 H W H F. Ali D.Dano Richard Alzharani 111668 Sht. 01
Rev. 01

D44-M-RB-
N/A N/A W W W F. Ali D.Dano Richard Alzharani 111668 Sht. 01
Rev. 01

D45-M-RB-
Q-010-01 Q-1048 H W H F. Ali D.Dano Isack Alzharani 112580 Sht.01
Rev.01

D45-M-RB-
N/A N/A W W W F. Ali D.Dano Isack Alzharani 112580 Sht.01
Rev.01

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


D45-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK & Excluded
W05, W11, W12
& W14

Pending

OK

OK

OK

OK

Saudi Aramco: Company General Use


OK

OK

OK

OK

OK

OK

OK

Saudi Aramco: Company General Use


Pending

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 14-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0639 Architectural Pre- Cast Concrete Wall panel OME-241 W25, OME-241 Train-1 8:00 AM
W26, W28, W29 & W30 (05 NOS.)

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0640 Architectural Pre- Cast Concrete Wall panel TDB 750 W05,W11, TDB 750 Area-B 2:30 PM
W12, W14, W15 & W16 (06 NOS.)

Receiving and Storage Inspection for Structural and


Architectural Pre- Cast Concrete Wall panel PIB 342 W17,W19,
3 PSAL-QAN-SITEPC-0641 PIB 342 Train-2 8:45 AM
W21, W23, W25, W27, W29, W47, W49, W51, W53, W55, W57
& W59 (14 NOS.)

Receiving and Storage Inspection for Structural and


Architectural Pre- Cast Concrete Wall panel PIB 346 W17,W19,
4 PSAL-QAN-SITEPC-0642 PIB 346 Train-6 10:15 AM
W21, W23, W25, W27, W29, W47, W49, W51, W53, W55, W57
& W59 (14 NOS.)

PAINT/CAOTING RFI's
surface preparation Inspection of Repair & Touch-up of under Substation 446
1 PSAL-QAN-SITEPC-0605 the Roof Galvanized Plates (Embeded) In SS-446 See highlights 8:00 AM
Train 6
on the attached drawings)

Saudi Aramco: Company General Use


Final Inspection of Repair & Touch-up of Under the Roof & all
2 PSAL-QAN-SITEPC-0638 vertical corners Galvanized Plates (Embeded) In PIOB-350 See PIOB 350 Area-B 8:00 AM
highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 14-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 116355 Sht. 01
Rev. 2

D45-M-RB-
Q-010-01 Q-1047 I I W Ahmad. R D.Dano Richard Alzharani 116355 Sht. 01
Rev. 2

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Irfan R. Mark Castillo 112494 Sht. 01,
02 Rev.01

Saudi Aramco: Company General Use


D45-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK & Excluded
W29

Reschedule

OK

OK

Pending

Saudi Aramco: Company General Use


OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 15-

Scheduled
SL No RFI No. Description Location Inspection Time

Final inspection of installation bolt Vertical connection steel


1 PSAL-QAN-SITEPC-0623 plate joints between 2 wall panels W54 & W55 at PIOB 350 for PIOB 350 Area B 9:00 AM
Closing the INCR No. JI2032/QDC/FSRU/NCR/0003

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0640 Architectural Pre- Cast Concrete Wall panel TDB 750 W05,W11, TDB 750 Area B 2:30 PM
W12, W14, W15 & W16 (06 NOS.)

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0643 Architectural Pre- Cast Concrete Wall panel OME-245 W16 & OME 245 Train 5 9:30 AM
W33 (02 NOS.)

Receiving and Storage Inspection for Structural and


Architectural Pre- Cast Concrete Wall panel PIB 344 W17,W19,
4 PSAL-QAN-SITEPC-0644 PIB 344 Train 4 8:45 AM
W21, W23, W25, W27, W29, W47, W49, W51, W53, W55, W57
& W59 (14 NOS.)

Final inspection of installation bolt Vertical connection steel


5 PSAL-QAN-SITEPC-0645 plate joints between 2 wall panels W74 & W75 at PIB 344 for PIB 344 Train 5 9:00 AM
Closing the INCR No. JI2032/QDC/FSRU/NCR/0005

Saudi Aramco: Company General Use


Erection & Alignment Inspection of Pre-cast Wall Panels for
6 PSAL-QAN-SITEPC-0646 OME 250 Grid line 1/A-C, 1-5/A , 1-5/C & 5/A-C wall panels OME 250 Area B 8:15 AM
W01 to W50

PAINT/CAOTING RFI's
surface preparation Inspection of Repair & Touch-up of under Substation 446
1 PSAL-QAN-SITEPC-0605 the Roof Galvanized Plates (Embeded) In SS-446 See highlights 8:00 AM
Train 6
on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 15-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
F. Ali/ Ahmad.
M-100-03 M-1072 I W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 01

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Richard Alzharani 111537 Sht. 01
Rev. 1

D44-M-RB-
F. Ali/ Ahmad.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 1

Saudi Aramco: Company General Use


D45-M-RB-
Q-012-01 Q-1066 H W W F. Ali D.Dano Isack Alzharani 116355 Sht. 01
Rev. 2

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Irfan R. Mark Castillo 112494 Sht. 01,
02 Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

Pending

Reschedule

Reschedule

Reschedule

Saudi Aramco: Company General Use


OK

Ok

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 16-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0643 Architectural Pre- Cast Concrete Wall panel OME-245 W16 & OME 245 Train 5 9:30 AM
W33 (02 NOS.)

Receiving and Storage Inspection for Structural and


Architectural Pre- Cast Concrete Wall panel PIB 344 W17,W19,
2 PSAL-QAN-SITEPC-0644 PIB 344 Train 4 8:45 AM
W21, W23, W25, W27, W29, W47, W49, W51, W53, W55, W57
& W59 (14 NOS.)

Final inspection of installation bolt Vertical connection steel


3 PSAL-QAN-SITEPC-0645 plate joints between 2 wall panels W74 & W75 at PIB 344 for PIB 344 Train 5 8:00 AM
Closing the INCR No. JI2032/QDC/FSRU/NCR/0005

Crushing of Non-Shrink Grout testing & sample Area PIOB-350


4 PSAL-QAN-SITEPC-0647 Grid line 2/A-J wall panel W01 to W28 for 07 days RFI ref. PSAL- PIOB 350 Area-B 2:00 PM
QAN-SITE-PC-0597 (Fugro Fadhili)

Final Bolt Snug Tightening of Horizontal Base connections at


5 PSAL-QAN-SITEPC-0648 OME 250 Grid line 1/A-C, 1-5/A , 1-5/C & 5/A-C wall panels W01 OME 250 Area B 9:30 AM
to W50 prior to grout

PAINT/CAOTING RFI's
Saudi Aramco: Company General Use
Final Inspection of Repair & Touch-up of upside the Roof
1 PSAL-QAN-SITEPC-0649 Galvanized Plates (Embeded) In PIB-346 See highlights on the PIB 346 Train-6 9:00 AM
attached drawings)

surface preparation Inspection of Repair & Touch-up of upside


the Roof jv mini Squir between DoubleT to DoubleT Galvanized
2 PSAL-QAN-SITEPC-0651 PIB 346 Train-6 10:00 AM
Plates (Embeded) In PIB-346 See highlights on the attached
drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 16-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Richard Alzharani 111537 Sht. 01
Rev. 1

D44-M-RB-
F. Ali/ Ahmad.
M-100-03 M-1072 I W W D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 1

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 112580 Sht. 01
R Rev. 01

D45-M-RB-
M-100-03 M-1072 I W W F. Ali D.Dano Isack Alzharani 116355 Sht. 01
Rev. 2

Saudi Aramco: Company General Use


D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111668 Sht. 01
Rev. 01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111668 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

OK

OK

Saudi Aramco: Company General Use


OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 17-

Scheduled
SL No RFI No. Description Location Inspection Time

Crushing of Non-Shrink Grout testing & sample Area PIOB 350


1 PSAL-QAN-SITE-PC-0650 Grid line 1/A-K & 1/K wall panels W40 to W76 for 28 days RFI PIOB-350 Area B 9:00 AM
ref. PSAL-QAN-SITE-PC-0476 (Fugro Jubail)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 17-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
Q-010-01 Q-1049 H W W F. Ali D.Dano Isack Alzharani 112580 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 18-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0652 Architectural Pre- Cast Concrete Wall panel OME-245 W11, OME 245 Train 5 9:00 AM
W12, W13, W15 & W17 (05 NOS.)

Receiving and Storage Inspection for Structural Pre- Cast Double


T slab OME-250 R01, R02, R03, R04, R05, R06, R07, R08, R09, OME 245 Train 5
2 PSAL-QAN-SITEPC-0653 8:30 AM
R10, R11, R12, R13, R14, R15, R16, R17, R18, R19, R20, R21,
R22, R23, R24, R25, R26, R27 & R28 (28 Nos.)

Surface Preparation inspection for the vertical connections at


PIB-346 Grid line 5/A-D wall panel W16, W18, W20, W22, W24,
3 PSAL-QAN-SITEPC-0654 PIB 346 Train-6 7:00 AM
W26, W28 & W30 & 6 corners W01/W60, W15/W16,
W26/W75, W30/W31, W45/W46 & W50/W61 prior to grout

Mixing placement and testing inspection of Grouting vertical


connections at PIB-346 Grid line 5/A-D wall panel W16, W18,
4 PSAL-QAN-SITEPC-0655 PIB 346 Train-6 8:00 AM
W20, W22, W24, W26, W28 & W30 & 6 corners W01/W60,
W15/W16, W26/W75, W30/W31, W45/W46 & W50/W61

Saudi Aramco: Company General Use


Surface Preparation inspection for the vertical connections at
5 PSAL-QAN-SITEPC-0656 PIB-344 Grid line 1/A-D & 1-5/D wall panel W01 to W15, W46, PIB 344 Train-4 7:00 AM
W48, W50, W52, W54, W56, W58 & W60 prior to grout

Mixing placement and testing inspection of Grouting vertical


6 PSAL-QAN-SITEPC-0657 connections at PIB-344 Grid line 1/A-D & 1-5/D wall panel W01 PIB 344 Train-4 2:00 PM
to W15, W46, W48, W50, W52, W54, W56, W58 & W60

Surface Preparation Inspection for vertical connections 4 Substation 446


7 PSAL-QAN-SITEPC-0658 corners at SS-446 Big room wall panels W13/W97, W35/W36, 7:00 AM
Train 6
W48/W49 & W71/103 prior to Plastering

Plastering for verticle connections 4 corners at SS-446 Big room Substation 446
8 PSAL-QAN-SITEPC-0659 7:30 AM
wall panels W13/W97, W35/W36, W48/W49 & W71/103 Train 6

Crushing of Non-Shrink Grout testing & sample Area PIB-346


9 PSAL-QAN-SITEPC-0660 Grid line 1-5/B & 1-5/D wall panel W01 to W15 & W61 to W75 PIB 346 Train-6 2:00 PM
for 07 days RFI ref. PSAL-QAN-SITE-PC-0613 (Fugro Fadhili)

Crushing of Non-Shrink Grout testing & sample Area PIOB 350


10 PSAL-QAN-SITEPC-0661 Grid line1-2/A, 1/A-E wall panels W62 to W82 for 28 days RFI PIOB-350 2:00 PM
ref. PSAL-QAN-SITE-PC-0492 (Fugro Fadhili)

PAINT/CAOTING RFI's
Final Inspection of Repair & Touch-up of under the Roof & 4 Substation 446
1 PSAL-QAN-SITEPC-0662 corners Galvanized Plates (Embeded) In SS-446 Big room See 8:00 AM
Train 6
highlights on the attached drawings)

Saudi Aramco: Company General Use


Final Inspection of Repair & Touch-up of upside the Roof jv mini
2 PSAL-QAN-SITEPC-0663 Squir between DoubleT to DoubleT Galvanized Plates PIB 346 Train-6 8:30 AM
(Embeded) In PIB-346 See highlights on the attached drawings)

surface preparation Inspection of Repair & Touch-up of upside


3 PSAL-QAN-SITEPC-0664 the Roof remaining 4 bent Galvanized Plates (Embeded) In PIOB- PIOB 350 Area-B 8:00 AM
350 See highlights on the attached drawings)

Final Inspection of Repair & Touch-up of upside the Roof


4 PSAL-QAN-SITEPC-0665 remaining 4 bent Galvanized Plates (Embeded) In PIOB-350 See PIOB 350 Area-B 2:00 PM
highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 18-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Richard Alzharani 111668 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Richard Alzharani 111668 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Rasual Alzharani 112494 Sht. 01,
R 02 Rev.01

D44-M-RB-
F. Ali/ Ahmad.
N/A N/A W W W D.Dano Rasual Alzharani 112494 Sht. 01,
R 02 Rev.01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111668 Sht. 01
R Rev. 01

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 112580 Sht. 01
R Rev. 01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Irfan R. Mark Castillo 112494 Sht. 01,
02 Rev.01

Saudi Aramco: Company General Use


D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111668 Sht. 01
Rev. 01

D45-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

D45-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Isack Mark Castillo 112580 Sht.01
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

Reschedule

OK

OK

Saudi Aramco: Company General Use


OK

OK

OK

OK

OK

OK

OK

Saudi Aramco: Company General Use


Reschedule

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 19-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural Pre- Cast Double


T slab OME-250 R01, R02, R03, R04, R05, R06, R07, R08, R09, OME 245 Train 5
1 PSAL-QAN-SITEPC-0653 8:30 AM
R10, R11, R12, R13, R14, R15, R16, R17, R18, R19, R20, R21,
R22, R23, R24, R25, R26, R27 & R28 (28 Nos.)

Surface Preparation inspection for the vertical connections at


PIB-344 Grid line 1-5/A, 1-5/B & 5/A-D wall panel W16, W18,
2 PSAL-QAN-SITEPC-0666 PIB 344 Train-4 7:00 AM
W20, W22, W24, W26, W28, W30 to W45 & W61 to W75 prior
to grout

Mixing placement and testing inspection of Grouting vertical


connections at PIB-344 Grid line 1-5/A, 1-5/B & 5/A-D wall panel PIB 344 Train-4
3 PSAL-QAN-SITEPC-0667 8:00 AM
W16, W18, W20, W22, W24, W26, W28, W30 to W45 & W61 to
W75

4 PSAL-QAN-SITEPC-0668 Sampling & testing of Mixing water for Grout Monthly. PIOB-350 8:30 AM

Crushing of Non-Shrink Grout testing & sample Area PIB-346


Grid line 1/A-D, 1-5/A & 3-5/D wall panel W07 to W15, W31 to
5 PSAL-QAN-SITEPC-0669 PIB 346 Train-6 2:00 PM
W46, W48, W50, W52, W54, W56, W58 & W60 for 07 days RFI
ref. PSAL-QAN-SITE-PC-0622 (Fugro Fadhili)

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area PIOB 350
6 PSAL-QAN-SITEPC-0670 Grid line1-2/A, 2/A-G wall panels W01 to W18 & W75 to W82 PIOB-350 Area B 2:00 PM
for 28 days RFI ref. PSAL-QAN-SITE-PC-0500 (Fugro Fadhili)

PAINT/CAOTING RFI's

Final Inspection of Repair & Touch-up of upside the Roof jv mini


1 PSAL-QAN-SITEPC-0663 Squir between DoubleT to DoubleT Galvanized Plates PIB 346 Train-6 8:30 AM
(Embeded) In PIB-346 See highlights on the attached drawings)

surface preparation Inspection of Repair & Touch-up of upside


the Roof & JV mini Square between Double T to Double T
2 PSAL-QAN-SITEPC-0671 PIB 344 Train-4 8:00 AM
Galvanized Plates (Embeded) In PIB-344 See highlights on the
attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 19-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Richard Alzharani 111537 Sht. 01
R
Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 01

D44-M-RB-
Q-010-01 Q-1045 H RH/H RH/H F. Ali D.Dano Richard Alzharani 111537 Sht. 01
Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111668 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 112580 Sht. 01
R Rev. 01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Nicolas Richard Mark Castillo 111668 Sht. 01
Rev. 01

D44-M-RB-
H-100-03 H-2033 H W W F. Ali Anecito Richard Mark Castillo 111537 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK & Excluded
R27 & R28

OK

OK

Reschedule

OK

Saudi Aramco: Company General Use


OK

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 20-

Scheduled
SL No RFI No. Description Location Inspection Time

4 PSAL-QAN-SITEPC-0668 Sampling & testing of Mixing water for Grout Monthly. PIOB-350 8:30 AM

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0672 Architectural Pre- Cast Concrete Wall panel OME-241 W29 (01 OME-241 Train-1 8:30 AM
NOS.)

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0673 Architectural Pre- Cast Concrete Wall panel OME-245 W14, OME 245 Train 5 9:00 AM
W18, W19, W21 & W27 (05 NOS.)

Surface Preparation inspection for the Base connections at OME


4 PSAL-QAN-SITEPC-0674 250 Grid line 1-5/C & 5/A-C wall panel W17 to W41 prior to OME 250 Area A 7:00 AM
grout

Mixing placement and testing inspection of Grouting Base


5 PSAL-QAN-SITEPC-0675 connections at OME 250 Grid line 1-5/C & 5/A-C wall panel W17 OME 250 Area A 8:00 AM
to W41

Receiving and Storage Inspection for Structural connections


6 PSAL-QAN-SITEPC-0676 OME-241 Train-1 8:00 AM
Angle bars 100X150X12MM (143 pcs).

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area PIOB 350
7 PSAL-QAN-SITEPC-0677 Grid line 2/G-K, 2/K wall panels W20 to W39 for 28 days RFI ref. PIOB-350 Area B 2:00 PM
PSAL-QAN-SITE-PC-0505 (Fugro Fadhili)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 20-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID
D44-M-RB-
Q-010-01 Q-1045 H RH/H RH/H F. Ali D.Dano Richard Alzharani 111537 Sht. 01
Rev. 01
D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Isack Alzharani 116355 Sht. 01
R Rev. 02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 116355 Sht. 01
R Rev. 02

D44-M-RB-
F. Ali/ Ahmad.
Q-012-01 Q-1064 H W W Carlos Arturo Cabile Alzharani 113224 Sht.01
R Rev.01

Saudi Aramco: Company General Use


D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 112580 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

Actual Done
Grid line 1/A-C
& 1-5/C W17 to
W41

Actual Done
Grid line 1/A-C
& 1-5/C W17 to
W41

OK

Saudi Aramco: Company General Use


OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 21-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0678 Architectural Pre- Cast Concrete Wall panel OME-245 W23, OME 245 Train 5 9:00 AM
W28, W36 & W39 (04 NOS.)

Surface Preparation inspection for the Base connections at OME


2 PSAL-QAN-SITEPC-0679 250 Grid line 1-5/A & 5/A-C wall panel W01 to W16 & W42 to OME 250 Area A 7:00 AM
W50 prior to grout

Mixing placement and testing inspection of Grouting Base


3 PSAL-QAN-SITEPC-0680 connections at OME 250 Grid line 1-5/A & 5/A-C wall panel W01 OME 250 Area A 8:00 AM
to W16 & W42 to W50

Final Bolt snug Tightening of verticle connections at OME 250


4 PSAL-QAN-SITEPC-0681 Grid line 1/A-C, 1-5/A , W1-5/C & 5/A-C wall panels W01 & W50 OME 250 Area A 9:15 AM
prior to Plastering

PAINT/CAOTING RFI's

Final Inspection of Repair & Touch-up of upside the Roof & JV


1 PSAL-QAN-SITEPC-0682 mini Square between Double T to Double T Galvanized Plates PIB 344 Train-4 9:00 AM
(Embeded) In PIB-344 See highlights on the attached drawings)

Saudi Aramco: Company General Use


surface preparation Inspection of Repair & Touch-up of under Substation 446
2 PSAL-QAN-SITEPC-0683 the Roof & 4 corners Galvanized Plates (Embeded) In SS-446 8:00 AM
Train 6
Small Room See highlights on the attached drawings)

surface preparation Inspection of Repair & Touch-up of under Substation 444


3 PSAL-QAN-SITEPC-0684 the Roof Galvanized Plates (Embeded) In SS-444 Big Room See 8:30 AM
Train 4
highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 21-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Isack Alzharani 116355 Sht. 01
R Rev. 02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Isack Alzharani 116355 Sht. 01
R Rev. 02

D44-M-RB-
Ahmad. R/ F.
M-100-03 M-1072 I W W D.Dano Isack Alzharani 116355 Sht. 01
Ali Rev. 02

D44-M-RB-
H-100-03 H-2032 H W W F. Ali Nicolas Richard Mark Castillo 111537 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


D44-M-RB-
H-100-03 H-2032 H W W F. Ali Nicolas Irfan R. Mark Castillo 112494 Sht. 01,
02 Rev.01

D44-M-RB-
H-100-03 H-2032 H W W F. Ali Nicolas Faisal H. Mark Castillo 112480 Sht. 01,
02 Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

Ok

OK

Saudi Aramco: Company General Use


OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 22-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0685 Architectural Pre- Cast Concrete Wall panel OME-245 W25, W29 OME 245 Train 5 9:00 AM
& W34 (03 NOS.)

Surface Preparation inspection for the vertical connections at


2 PSAL-QAN-SITEPC-0686 PIB-344 6 corners wall panels W01/W60, W15/W16, W26/W75, PIB 344 Train-4 7:00 AM
W30/W31, W45/W46 & W50/W61 prior to grout

Mixing placement and testing inspection of Grouting vertical


3 PSAL-QAN-SITEPC-0687 connections at PIB-344 6 corners wall panels W01/W60, PIB 344 Train-4 8:00 AM
W15/W16, W26/W75, W30/W31, W45/W46 & W50/W61

Erection Inspection of Pre-cast Design Wall Panels for PIB


4 PSAL-QAN-SITEPC-0688 342 W17, W19, W21, W23, W25, W27, W29, W47, W49, PIB 342 Train-2 8:15 AM
W51, W53, W55, W57 & W59 (14 Nos).

Erection Inspection of Pre-cast Design Wall Panels for PIB


5 PSAL-QAN-SITEPC-0689 344 W17, W19, W21, W23, W25, W27, W29, W47, W49, PIB 344 Train-4 9:15 AM
W51, W53, W55, W57 & W59 (14 Nos).

Erection Inspection of Pre-cast Design Wall Panels for PIB


6 PSAL-QAN-SITEPC-0690 346 W17, W19, W21, W23, W25, W27, W29, W47, W49, PIB 346 Train-6 10:15 AM
W51, W53, W55, W57 & W59 (14 Nos).

Saudi Aramco: Company General Use


PAINT/CAOTING RFI's
surface preparation Inspection of Repair & Touch-up of under Substation 444
1 PSAL-QAN-SITEPC-0691 the Roof Galvanized Plates (Embeded) In SS-444 Small Room 8:30 AM
Train 4
See highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 22-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Richard Alzharani 111537 Sht. 01
R Rev. 01

D44-M-RB-
Q-012-01 Q-1066 H W W F. Ali D.Dano Arturo Cabile Alzharani 111523 Sht. 01
Rev. 01

D44-M-RB-
Q-012-01 Q-1066 H W W F. Ali D.Dano Richard Alzharani 111537 Sht. 01
Rev. 01

D44-M-RB-
Q-012-01 Q-1066 H W W F. Ali D.Dano Richard Alzharani 111668 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


D44-M-RB-
H-100-03 H-2032 H W W F. Ali Nicolas Faisal H. Mark Castillo 112480 Sht. 01,
02 Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

OK

OK

OK

Saudi Aramco: Company General Use


OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 23-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0692 Architectural Pre- Cast Concrete Wall panel OME-245 W22, OME 245 Train 5 9:00 AM
W24, W27, W30, W35 & W37 (06 NOS.)

Surface Preparation Inspection for vertical connections at SS- Substation 446


2 PSAL-QAN-SITEPC-0693 446 Small Room 4 corners wall panels W01/W96, W12/W110, 7:00 AM
Train 6
W72/W104 & W83/W84 prior to Plastering

Plastering for verticle connections at SS-446 Small Room 4 Substation 446


3 PSAL-QAN-SITEPC-0694 corners wall panels W01/W96, W12/W110, W72/W104 & 7:30 AM
Train 6
W83/W84

Surface Preparation Inspection for vertical connections at OME


4 PSAL-QAN-SITEPC-0695 250 Grid line 1/A-C, 1-5/A , W1-5/C & 5/A-C wall panels W01 & OME 250 Area A 7:00 AM
W50 prior to Plastering

Plastering for verticle connections at OME 250 Grid line 1/A-C,


5 PSAL-QAN-SITEPC-0696 OME 250 Area A 7:30 AM
1-5/A , W1-5/C & 5/A-C wall panels W01 & W50

Crushing of Non-Shrink Grout testing & sample Area PIB-342


6 PSAL-QAN-SITEPC-0697 Grid line 1-5/D & 1-5/B wall panels W01 to W15 & W61 to W75 PIB 342 Train-2 2:00 PM
for 28 days RFI ref. PSAL-QAN-SITE-PC-0517 (Fugro Fadhili)

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area PIB-342
Grid line 1/A-D, 1-5/A & 5/A-D wall panels W16 to W18, W20,
7 PSAL-QAN-SITEPC-0698 W22, W24, W26, W28, W30 to W46, W48, W50, W52, W54, PIB 342 Train-2 2:00 PM
W56, W58 & W60 for 28 days RFI ref. PSAL-QAN-SITE-PC-0525
(Fugro Fadhili)

PAINT/CAOTING RFI's
Final Inspection of Repair & Touch-up of under the Roof Substation 444
1 PSAL-QAN-SITEPC-0699 Galvanized Plates (Embeded) In SS-444 Full Room See highlights 2:00 PM
Train 4
on the attached drawings)

Final Inspection of Repair & Touch-up of under the Roof & 4 Substation 446
2 PSAL-QAN-SITEPC-0700 corners Galvanized Plates (Embeded) In SS-446 Small Room See 8:00 AM
Train 6
highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 23-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-010-01 Q-1048 H W H F. Ali D.Dano Rasual Alzharani 112494 Sht. 01,
02 Rev.01

D44-M-RB-
N/A N/A W W W F. Ali D.Dano Rasual Alzharani 112494 Sht. 01,
02 Rev.01

D44-M-RB-
Q-010-01 Q-1048 H W H F. Ali D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D44-M-RB-
N/A N/A W W W F. Ali D.Dano Isack Alzharani 116355 Sht. 01
Rev. 02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111523 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111523 Sht. 01
R Rev. 01

D44-M-RB-
H-100-03 H-2032 H W W F. Ali Nicolas Faisal H. Mark Castillo 112480 Sht. 01,
02 Rev.01

D44-M-RB-
H-100-03 H-2032 H W W F. Ali Nicolas Irfan R. Mark Castillo 112494 Sht. 01,
02 Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK & Excluded
W27 & W37

OK

OK

OK

OK

Advance
Inspection Done

Saudi Aramco: Company General Use


OK

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 25-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0701 Architectural Pre- Cast Concrete Wall panel OME-245 W37 & OME 245 Train 5 9:00 AM
W38 (02 NOS.)

Receiving and Storage Inspection for Structural Pre- Cast Double OME 245 Train 5
2 PSAL-QAN-SITEPC-0702 8:30 AM
T slab OME-250 R27 & R28 (02 Nos.)

Surface Preparation inspection for the vertical connections at


SS-444 8 corners full building wall panels W01/W96, Substation 444
3 PSAL-QAN-SITEPC-0703 7:00 AM
W12/W110, W72/W104, W83/W84, W13/W97, W35/36, Train 4
W48/W49 & W71/W103 prior to grout

Mixing placement and testing inspection of Grouting vertical


connections at SS-444 8 corners full building wall panels Substation 444
4 PSAL-QAN-SITEPC-0704 8:00 AM
W01/W96, W12/W110, W72/W104, W83/W84, W13/W97, Train 4
W35/36, W48/W49 & W71/W103

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area PIB-346
Grid line 5/A-D wall panel W16, W18, W20, W22, W24, W26,
W28 & W30 & 6 corners W01/W60, W15/W16, W26/W75,
5 PSAL-QAN-SITEPC-0705 W30/W31, W45/W46 & W50/W61 & PIB-344 Grid line 1/A-D & PIB 346 Train-6 2:00 PM
1-5/D wall panel W01 to W15, W46, W48, W50, W52, W54,
W56, W58 & W60 for 07 days RFI ref. PSAL-QAN-SITE-PC-
0655/0657 (Fugro Fadhili)

Crushing of Non-Shrink Grout testing & sample Area PIB-342


6 PSAL-QAN-SITEPC-0706 Grid line 1/A-D W46, W48, W50, W52, W54, W56, W58 & W60 PIB 342 Train-2 2:00 PM
for 28 days RFI ref. PSAL-QAN-SITE-PC-0536 (Fugro Fadhili)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 25-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Faisal H. Alzharani 112480 Sht. 01,
R 02 Rev.01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Faisal H. Alzharani 112480 Sht. 01,
R
02 Rev.01

Saudi Aramco: Company General Use


D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111668 Sht. 01
R Rev. 01

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 112580 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

OK

Saudi Aramco: Company General Use


OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 26-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0640 Architectural Pre- Cast Concrete Wall panel TDB 750 W11, W12, TDB 750 Area B 2:30 PM
W14 & W15 (04 NOS.)

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0707 Architectural Pre- Cast Concrete Wall panel OME-245 W26 & OME 245 Train 5 9:00 AM
W31 (02 NOS.)

Receiving and Storage Inspection for Grouting Material


3 PSAL-QAN-SITEPC-0708 OME 241 Train 1 8:00 AM
Conbextra GP 224 (bags)

Receiving and Storage Inspection for Structural connections


Angle bars 100X100X8MM (400 pcs), 120X90X100MM (309 pcs) OME 245 Train 5
4 PSAL-QAN-SITEPC-0709 10:00 AM
& 100X150X12MM (332 pcs) & steel plates 170X190X8MM (176
pcs)

Erection Inspection of pre-cast Double T slab for PIB-344 Double PIB 344 Train-4
5 PSAL-QAN-SITEPC-0710 8:00 AM
T slab No. R01 to R30

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area PIB-344
Grid line 1-5/A, 1-5/B & 5/A-D wall panel W16, W18, W20, W22, PIB 346 Train-6
6 PSAL-QAN-SITEPC-0711 2:00 PM
W24, W26, W28, W30 to W45 & W61 to W75 for 07 days RFI
ref. PSAL-QAN-SITE-PC-0655/0657 (Fugro Fadhili)

PAINT/CAOTING RFI's

1 PSAL-QAN-SITEPC-0712 Receiving Inspection of Paint Materials Qanbar Store


7:30 AM
Room

2 PSAL-QAN-SITEPC-0713 Storage, Handling and Preservation of Paint Materials Qanbar Store


8:00 AM
Room

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 26-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 116503 Sht. 01
Rev. 1

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-010-01 Q-1047 I I W F. Ali Carlus Arturo Cabile Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1064 H W W F. Ali Carlus Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1066 H W W F. Ali D.Dano Richard Alzharani 111537 Sht. 01,
Rev.01

Saudi Aramco: Company General Use


D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111668 Sht. 01
R Rev. 01

D44-M-RB-
H-100-01 H-2024 H W W F. Ali Nicolas Richard Mark Castillo 111537 Sht. 01,
Rev.01
D44-M-RB-
H-100-01 H-2025 H W W F. Ali Nicolas Richard Mark Castillo 111537 Sht. 01,
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

Re-Issue Reply
OK

OK

OK

Reply Hold

Reschedule

Saudi Aramco: Company General Use


OK

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 27-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural connections


Angle bars 100X100X8MM (400 pcs), 120X90X100MM (309 pcs) OME 245 Train 5
1 PSAL-QAN-SITEPC-0709 10:00 AM
& 100X150X12MM (332 pcs) & steel plates 170X190X8MM (176
pcs)

Erection Inspection of pre-cast Double T slab for PIB-344 Double PIB 344 Train-4
2 PSAL-QAN-SITEPC-0710 8:00 AM
T slab No. R01 to R30

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0714 Architectural Pre- Cast Concrete Wall panel OME-245 W51, OME 245 Train 5 9:00 AM
W53, W54 & W56 (04 NOS.)

Receiving and Storage Inspection for Structural and


4 PSAL-QAN-SITEPC-0715 Architectural Pre- Cast Concrete Wall panel OME-241 W52, OME-241 Train-1 8:30 AM
W53, W55 & W56 (04 NOS.)

Receiving and Storage Inspection for Structural connections


5 PSAL-QAN-SITEPC-0716 OME 245 Train 5 8:00 AM
Angle bars 100X150X10MM (274 pcs)

Crushing of Non-Shrink Grout testing & sample Area OME 250


6 PSAL-QAN-SITEPC-0717 Grid line 1-5/C & 5/A-C wall panel W17 to W41 for 07 days RFI OME 250 Area B 2:00 PM
ref. PSAL-QAN-SITE-PC-0675 (Fugro Fadhili)

Saudi Aramco: Company General Use


Crushing of Non-Shrink Grout testing & sample Area PIB-342
W01/W60, W15/W16, W26/W75, W30/W31, W45/W46 &
7 PSAL-QAN-SITEPC-0718 PIB 342 Train-2 2:00 PM
W50/W61 for 28 days RFI ref. PSAL-QAN-SITE-PC-0550 (Fugro
Fadhili)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 27-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W F. Ali Carlus Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1066 H W W F. Ali D.Dano Richard Alzharani 111537 Sht. 01,
Rev.01

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D44-M-RB-
Q-012-01 Q-1064 H W W F. Ali Carlus Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 116355 Sht. 01
R Rev. 02

Saudi Aramco: Company General Use


D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111523 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

Tomorrow

OK

Tomorrow

OK

Saudi Aramco: Company General Use


OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 28-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0714 Architectural Pre- Cast Concrete Wall panel OME-245 W51, OME 245 Train 5 9:00 AM
W53, W54 & W56 (04 NOS.)

Receiving and Storage Inspection for Structural connections


2 PSAL-QAN-SITEPC-0716 OME 245 Train 5 8:00 AM
Angle bars 100X150X10MM (274 pcs)

Crushing of Non-Shrink Grout testing & sample Area PIB-344 6


corners wall panels W01/W60, W15/W16, W26/W75,
3 PSAL-QAN-SITEPC-0719 PIB 344 Train-4 2:00 PM
W30/W31, W45/W46 & W50/W61 for 07 days RFI ref. PSAL-
QAN-SITE-PC-0687 (Fugro Fadhili)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 28-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
Q-012-01 Q-1064 H W W F. Ali Carlus Rasual Alzharani 116341 Sht.01
Rev.02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 111537 Sht. 01
R Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

Reschedule

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 29-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0720 Architectural Pre- Cast Concrete Wall panel OME-241 W51, OME-241 Train-1 8:30 AM
W54, W57 & W58 (04 NOS.)

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0721 Architectural Pre- Cast Concrete Wall panel OME-245 W52, OME 245 Train 5 9:00 AM
W55, W57 & W58 (04 NOS.)

Receiving and Storage Inspection for Structural and


3 PSAL-QAN-SITEPC-0722 Architectural Pre- Cast Concrete Wall panel TDB 750 W16 (01 TDB 750 Area B 8:00 AM
NOS.)

Crushing of Non-Shrink Grout testing & sample Area OME 250


4 PSAL-QAN-SITEPC-0723 Grid line 1-5/A & 5/A-C wall panel W01 to W16 & W42 to W50 OME 250 Area B 2:00 PM
for 07 days RFI ref. PSAL-QAN-SITE-PC-0680 (Fugro Fadhili)

PAINT/CAOTING RFI's
surface preparation Inspection of Repair & Touch-up of under
1 PSAL-QAN-SITEPC-0724 the Roof Galvanized Plates (Embeded) In PIB-344 Full building PIB 344 Train-4 8:30 AM
See highlights on the attached drawings)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 29-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Rasual Alzharani 116341 Sht.01
Rev.02

D45-M-RB-
Q-012-01 Q-1064 H W W F. Ali Carlus Rasual Alzharani 116503 Sht. 01
Rev. 1

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 116355 Sht. 01
R Rev. 02

D44-M-RB-
H-100-03 H-2032 H W W F. Ali Nicolas Faisal H. Mark Castillo 111537 Sht. 01
Rev. 01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK

OK

OK

Hold

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 30-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Grouting Material


1 PSAL-QAN-SITEPC-0725 Conbextra GP (550 bags), Conbextra TS (02 bags), Rendroc TG OME 250 Area A 8:00 AM
Xtra (168 bags) & Master flow 544 (300 bags).

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0726 Architectural Pre- Cast Concrete Wall panel EDGB-550 W01, EDGB 550 Area A 8:30 AM
W02, W03, W04, W05 & W06 (06 NOS.)

Pre-Installation Inspection for Structural and Architectural Pre- EDGB 550 Area A
3 PSAL-QAN-SITEPC-0727 8:00 AM
cast Wall panel prior to Erection at EDGB 550 Full Building.

Receiving and Storage Inspection for Structural and


4 PSAL-QAN-SITEPC-0728 Architectural Pre- Cast Concrete Wall panel OME-241 W32 (01 OME-241 Train-1 8:30 AM
NOS.)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 30-Nov-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
Q-010-01 Q-1047 I I W F. Ali Carlus Isack Alzharani 116355 Sht. 01
Rev. 02

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 113208 Sht. 01
Rev. 02

D45-M-RB-
Q-012-01 Q-1065 H H H F. Ali D.Dano Isack Alzharani 113208 Sht. 01
Rev. 02

D44-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK

OK & Excluded
wall panel W01,
W02, W05, W06

OK

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG

PETROFAC SAUDI AR
Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACK
DAILY INSPECTION
DATE : 02-

Scheduled
SL No RFI No. Description Location Inspection Time

Receiving and Storage Inspection for Structural and


1 PSAL-QAN-SITEPC-0729 Architectural Pre- Cast Concrete Wall panel EDGB-550 W01, EDGB 550 Area A 8:30 AM
W02, W05, W06, W07 & W08 (06 NOS.)

Erection & Alignment Inspection of Pre-cast Wall Panels for


2 PSAL-QAN-SITEPC-0730 OME 241 Grid line 1/A-C, 1-5/A , 1-5/C & 5/A-C wall panels OME 241 Train 1 8:15 AM
W01 to W50

Final Bolt Snug Tightening of Horizontal Base connections at


3 PSAL-QAN-SITEPC-0731 OME 241 Grid line 1/A-C, 1-5/A , 1-5/C & 5/A-C wall panels W01 OME 241 Train 1 9:00 AM
to W50 prior to grout

Crushing of Non-Shrink Grout testing & sample Area SS-444 8


corners full building wall panels W01/W96, W12/W110, Substation 444
4 PSAL-QAN-SITEPC-0732 W72/W104, W83/W84, W13/W97, W35/36, W48/W49 & 2:00 PM
Train 4
W71/W103 for 07 days RFI ref. PSAL-QAN-SITE-PC-0704 (Fugro
Fadhili)

Saudi Aramco: Company General Use


R DYWIDAG PRE-CAST CO.

AC SAUDI ARABIA LIMITED


PLANT (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No
Y INSPECTION SCHEDULE (CIVIL)
DATE : 02-Dec-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 113208 Sht. 01
Rev. 02

D44-M-RB-
Q-012-01 Q-1066 H W W F. Ali D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D44-M-RB-
M-100-03 M-1072 I W W F. Ali D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 112480 Sht. 01,
R 02 Rev.01

Saudi Aramco: Company General Use


JOB No. JI2032

Remarks

OK & Excluded
W05, W06 &
W07

OK

Reschedule

OK

Saudi Aramco: Company General Use


QANBAR DYWIDAG PRE-C

PETROFAC SAUDI ARABIA


Contarct No. 6600036254 (IK) FADHILI GAS PLANT (PACKAGE-
DAILY INSPECTION SCHED
DATE : 03-Dec-2

Scheduled
SL No RFI No. Description Location Inspection Time

Final Bolt Snug Tightening of Horizontal Base connections at


1 PSAL-QAN-SITEPC-0731 OME 241 Grid line 1/A-C, 1-5/A , 1-5/C & 5/A-C wall panels W01 OME 241 Train 1 9:00 AM
to W50 prior to grout

Receiving and Storage Inspection for Structural and


2 PSAL-QAN-SITEPC-0733 Architectural Pre- Cast Concrete Wall panel EDGB-550 W05, EDGB 550 Area A 8:30 AM
W06, W07, W09 & W10 (06 NOS.)

Surface Preparation inspection for the vertical connections at


SS-446 8 corners full building wall panels W01/W96, Substation 446
3 PSAL-QAN-SITEPC-0734 7:00 AM
W12/W110, W72/W104, W83/W84, W13/W97, W35/36, Train 6
W48/W49 & W71/W103 prior to grout

Mixing placement and testing inspection of Grouting vertical


connections at SS-446 8 corners full building wall panels Substation 446
4 PSAL-QAN-SITEPC-0735 8:00 AM
W01/W96, W12/W110, W72/W104, W83/W84, W13/W97, Train 6
W35/36, W48/W49 & W71/W103

Crushing of Non-Shrink Grout testing & sample Area PIOB-350


5 PSAL-QAN-SITEPC-0736 Grid line 2/A-K & 1-2/K wall panel W01 to W43 for 28 days RFI PIOB 350 Area A 2:00 PM
ref. PSAL-QAN-SITE-PC-0574 (Fugro Fadhili)

Saudi Aramco: Company General Use


PAINT/CAOTING RFI's
surface preparation Inspection of Repair & Touch-up of upside
1 PSAL-QAN-SITEPC-0737 the Roof Galvanized Plates (Embeded) In OME 250 Full building OME 250 Area A 8:30 AM
See highlights on the attached drawings)

Saudi Aramco: Company General Use


WIDAG PRE-CAST CO.

AUDI ARABIA LIMITED


T (PACKAGE-3; SULFUR RECOVERY UNIT) BI-10-01900-0004 JOB No. JI2032
PECTION SCHEDULE (CIVIL)
ATE : 03-Dec-2017

Inspection Level Inspector Name ARAMCO PMT


SATIP No. SAIC No. Drawing No.
Name
PSAL/QDC PMT PID QDC PSAL PID

D44-M-RB-
M-100-03 M-1072 I W W F. Ali D.Dano Arturo Cabile Alzharani 113224 Sht.01
Rev.01

D45-M-RB-
Q-012-01 Q-1064 H W W Ahmad. R D.Dano Isack Alzharani 113208 Sht. 01
Rev. 02

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1048 H W H D.Dano Rasual Alzharani 112494 Sht. 01,
R 02 Rev.01

D44-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W D.Dano Rasual Alzharani 112494 Sht. 01,
R 02 Rev.01

D45-M-RB-
F. Ali/ Ahmad.
Q-010-01 Q-1049 H W W Stalin Isack Alzharani 112580 Sht. 01
R Rev. 0

Saudi Aramco: Company General Use


D44-M-RB-
H-100-03 H-2032 H W W F. Ali Anecito Isack Mark Castillo 111537 Sht. 01