Professional Documents
Culture Documents
TRANSFER HOUSE 1
TRANSFER TOWER 2
CONVEYOR 1A & 1B
1 CHP
CONVEYOR 2A &2B
1 CHP
CONVEYOR 3A &3B
CONVEYOR 4A & 4B
CONVEYOR 5A & 5B
STRUCTURAL
PRESSURE PART
ROTATING EQUIPMENTS
FUEL PATH
INSULATION
ESP
BOILER -II
STRUCTURAL
PRESSURE PART
FUEL PATH
INSULATION
ESP
TG TO BOILER INTERCONNECTION
RAW WATER PUMP HOUSE
COMPRESSOR HOUSE
3 LP PIPING
FIRE FIGHTING SYSTEM
LDO SYSTEM
PIPE RACK
TURBINE
TURBOGENERATOR
CONDENSER
5 TG BUILDING
AUXILLARIES
STRUCTURAL
STRUCTURAL
EQUIPMENT ERECTION
WATER
7 TREATMENT
PLANT
WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING
CHEMICAL HOUSE
WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 32
(HAZEMAG)
2 THERMAX 167
3 GPR 21
4 APT 13
5 SUVENDU SAHU 10
JOSEPH
6 11
CONSTRUCTIONS
7 ION EXCHANGE 4
REPORT (MECHANICAL- CPP) DATE-21.09.13
PLANNED FOR
ACTIVITY AT SITE TOMORROW
No activity
Completed
Completed
Completed
No activity
Completed
No activity
Fire fighting pumps have reached transporters Fixing of Fire Sensor Cables
Godown.GPR informed and freight clearance by GPR is and Conduits to continue.
awaited
Expansion work of tube end & welding of vaccum pipes Erection of Condenser dome
to condenser completed. Surface finishing work for assembly will be taken up.
Condenser dome assembly is in progress
No activity No activity
No activity
No activity
Completed
Erection of Two numbers of pumps for sludge transfer Pipe assembly work to be
near clarifier completed. Erection of Two numbers of taken up. Alignment of erected
pumps for ultra filter with all pipe fittings is in pumps to start.Shifting of sand
progress. Shifting of sand bags to cooling tower in bags to cooling tower will be
progress. 6 nos chemical dosing Pumps of chemical continued.
house were shifted to chemical house.
No activity
No activity
REMARK
same as above
same as above