Professional Documents
Culture Documents
List a
step-by-step procedure to construct the slab safely. (Max 1 page)
1. Level ground on which the warehouse will be constructed. Ensure all organic materials
are removed to prevent future settlement of the slab.
2. Use an excavator, or similar, to dig trenches for the warehouse slab on grade shallow
foundation.
3. Ensure sufficient room is spared when trenching and excavating for pipes and conduits.
Increased reinforcement is necessary if pipe is not within middle 1/3 of the total depth.
4. Recesses are dug out for bathrooms to ensure egress of water.
5. Formwork is then established around the outer perimeter of the foundation. Plywood is
highly recommended due to its low cost; use wooden pegs to provide lateral support.
6. A bed of compacting sand is screeded and compacted evenly throughout the trenches
according to the engineering drawings.
7. A 0.2 mm black damp proof membrane is laid on top of the sand bed. Ensure all surfaces
are covered with 200 mm lap when required.
8. Reinforcements are laid on the slab on grade, which include trench meshes and reo
cages. Bar chairs and ties ensure the reinforcement is elevated according to the design.
9. Pour the concrete monolithically to avoid cold joints; ensure the pour is not too fast to
reduce lateral pressure from plastic concrete.
10. Screed the newly poured concrete with a power screed or a level straightaway for a clean
and smooth finish.
11. The concrete is then cured to obtain the desired strength, durability, and water tightness.
3 days minimum for 25 MPa concrete; 7 days minimum for 50 MPa concrete.
List a four-step procedure to erect a tower crane. (Max 1 page)
1. The crane hoists a new tower section and moves it next to the erecting section of the
crane.
2. The new tower section is then attached to the erecting section of the tower crane.
3. A hydraulic jack is used to jack the slewing ring and jib of the crane and the new section
is placed where the old section was previously.
4. The hydraulic jack is released and the slewing ring and jib are repositioned.
Describe the erection and use of sheet piles and shoring systems. (Max
1 page)
A common shoring method to prevent wall collapse in deep excavations are driven sheet
piles. They are driven in the same way as regular driven piles, but are made out of thin
corrugated metal sheets which are then rock anchored to the soil at a 15 degrees angle of
depression. Other means of shoring include contiguous piling and slurry walls.
Describe techniques to prevent accidents from occurring. (Max 1 page)
1. Eliminate hazard if possible such as avoiding hazardous substances.
2. Tackling risks at the source such as spraying dust with water.
3. Design work areas to suit individual.
4. Use technology to improve working conditions such as quieter machines.
5. Protect the whole workplace rather than relying on PPE since it is not 100% effective.
6. Ensure everyone understands what they have to do to be safe and healthy at work.
7. Ensure health and safety management is accepted by everyone and apply it to all aspects
of organisation activities.