AVANCES

METRADO
TEM DESCRIPCIN UND EXPED. METRADO METRADO METRADO
TCNICO ANTERIOR ACTUAL ACUM.

01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACIN DE LA OBRA DE 5.40 x 3.60 m u 1.00 1.00 0.00 1.00
01.02 MOVILIZACIN Y DESMOVILIZACIN DE EQUIPOS u 1.00 1.00 0.00 1.00

01.03 CERCADO DE OBRA C/CINTA PLSTICA Y POSTES DE MADERA DE 4X4 m 292.60 292.60 0.00 292.60

01.04 MANTENIMIENTO Y DESVIACIN DE TRNSITO u 38.00 38.00 0.00 38.00


01.05 CASETA ADICIONAL P/GUARDIANA Y/O ALMACN m2 72.00 72.00 0.00 72.00
02 OBRAS PRELIMINARES
02.01 LIMPIEZA Y DEFORESTACIN DE OBRA C/EQUIPO m2 10,275.00 10,275.00 0.00 10,275.00
02.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 6,143.55 6,143.55 0.00 6,143.55

DEMOLICIN Y CONSTRUCCIN DE ESTRUCTURA DE


03
CONCRETO
03.01 DEMOLICIN DE ESTRUCTURAS DE CONCRETO EXISTENTES m3 395.61 69.09 0.00 69.09
03.02 DEMOLICIN DE TABIQUERA DE LADRILLO m2 197.81 51.66 0.00 51.66
03.03 DEMOLICIN DE LOSAS ALIGERADAS EXISTENTES m3 40.00 7.72 0.00 7.72

MURO DE BLOQUE HUECO DE CONCRETO E=15CM MEZCLA 1:5


03.04
(CEMENTO:ARENA)
m2 177.81 63.48 0.00 63.48

03.05 PISO DE CONCRETO E=2" f'c=140 kg/cm2 x 4 cm PULIDO 1:2 X 1 CM m2 160.01 20.01 0.00 20.01
ELIMINACIN DE DESMONTE PROVENIENTE DE LA DEMOLICIN
03.06
(Dm=5.00 KM)
m3 487.13 120.10 0.00 120.10

04 ESTRUCTURAS
04.01 DESARENADOR
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 175.00 0.00 175.00 175.00
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 129.50 0.00 129.50 129.50
04.01.02 MOVIMIENTO DE TIERRAS
04.01.02.01 EXCAVACIN MANUAL DE ALCANTARILLA m3 103.60 0.00 53.72 53.72
04.01.02.02 BASE GRANULAR E=0.15m m3 19.43 0.00 19.43 19.43
04.01.02.03 RELLENO COMPACTADO MANUAL - CON MATERIAL DE PRSTAMO m3 25.90 0.00 25.90 25.90
04.01.02.04 ELIMINACIN DE MATERIAL EXCEDENTE (Dm=5.00 KM) m3 124.32 0.00 67.16 67.16
04.01.03 OBRAS DE CONCRETO SIMPLE
04.01.03.01 SOLADOS e=0.10m, F'c=140 Kg/cm2 m2 129.50 0.00 129.50 129.50
04.01.04 OBRAS DE CONCRETO ARMADO
04.01.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 448.70 0.00 448.70 448.70
04.01.04.02 CONCRETO f'c=210 Kg/cm2 m3 83.72 0.00 83.72 83.72
04.01.04.03 ACERO DE REFUERZO fy=4200 kg/cm2 kg 8,208.58 0.00 8,208.58 8,208.58
04.01.05 JUNTAS DE DILATACIN
04.01.05.01 JUNTAS ASFLTICAS m 22.10 0.00 0.00 0.00

04.02 ALCANTARILLA 2.25 x 2.25 m

04.02.01 TRABAJOS PRELIMINARES


04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 522.15 522.15 0.00 522.15
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 522.15 522.15 0.00 522.15
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACIN MANUAL DE ALCANTARILLA m3 208.06 208.06 0.00 208.06
04.02.02.02 BASE GRANULAR E=0.15m m3 59.04 59.04 0.00 59.04
04.02.02.03 RELLENO COMPACTADO MANUAL - CON MATERIAL DE PRSTAMO m3 751.09 751.09 0.00 751.09
04.02.02.04 ELIMINACIN DE MATERIAL EXCEDENTE (Dm=5.00 KM) m3 250.63 250.63 0.00 250.63
04.02.03 OBRAS DE CONCRETO SIMPLE
04.02.03.01 SOLADOS e=0.10m, F'c=140 Kg/cm2 m2 441.82 421.85 0.00 421.85
04.02.04 OBRAS DE CONCRETO ARMADO
04.02.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 2,215.33 1,657.20 0.00 1,657.20
04.02.04.02 CONCRETO F'c=210 Kg/cm2 m3 401.65 336.79 0.00 336.79
04.02.04.03 ACERO DE REFUERZO fy=4200 kg/cm2 kg 12,668.26 12,668.26 0.00 12,668.26
04.02.05 JUNTAS DE DILATACIN
04.02.05.01 JUNTAS ASFLTICAS m 90.00 90.00 0.00 90.00

ALCANTARILLA DE CRUCE DE CALLE Y CUNETA DE ENTREGA CON


04.03
REJILLA METLICA

04.03.01 TRABAJOS PRELIMINARES


04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 146.25 135.00 0.00 135.00
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 146.25 135.00 0.00 135.00
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACIN MANUAL DE ALCANTARILLA m3 198.00 198.00 0.00 198.00
04.03.02.02 BASE GRANULAR E=0.15m m3 21.94 21.94 0.00 21.94
04.03.02.03 RELLENO COMPACTADO MANUAL - CON MATERIAL DE PRSTAMO m3 123.75 123.75 0.00 123.75
04.03.02.04 ELIMINACIN DE MATERIAL EXCEDENTE (Dm=5.00 KM) m3 120.94 120.94 0.00 120.94
04.03.03 OBRAS DE CONCRETO SIMPLE
04.03.03.01 SOLADOS e=0.10m, F'c=140 Kg/cm2 m2 155.25 106.20 0.00 106.20
04.03.04 OBRAS DE CONCRETO ARMADO
04.03.04.01 CONCRETO F'c=210 Kg/cm2 m3 344.99 97.70 0.00 97.70
04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 459.00 459.00 0.00 459.00
04.03.04.03 ACERO DE REFUERZO fy=4200 kg/cm2 kg 6,100.62 6,100.62 0.00 6,100.62
04.03.05 REJILLAS DE PROTECCIN
04.02.05.01 REJILLA FIERRO 1/2" CORRUGADO u 40.00 0.00 0.00 0.00
04.04 TRANSICIN DE ENTRADA Y SALIDA EN PONTONES
04.04.01 TRABAJOS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 396.00 245.40 0.00 245.40
04.04.01.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 396.00 245.40 0.00 245.40
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACIN MANUAL DE ALCANTARILLA m3 158.40 140.52 0.00 140.52
04.04.02.02 RELLENO COMPACTADO MANUAL - CON MATERIAL DE PRSTAMO m3 158.40 147.12 11.28 158.40
04.04.02.03 ELIMINACIN DE MATERIAL EXCEDENTE (Dm=5.00 KM) m3 198.00 175.65 0.00 175.65
04.04.03 OBRAS DE CONCRETO SIMPLE
04.04.03.01 SOLADOS e=0.10m, F'c=140 Kg/cm2 m2 264.00 245.40 0.00 245.40
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 758.34 758.34 0.00 758.34
04.04.04.02 CONCRETO F'c=210 Kg/cm2 m3 149.51 142.54 6.97 149.51
04.04.04.03 ACERO DE REFUERZO fy=4200 kg/cm2 kg 9,459.84 9,459.84 0.00 9,459.84
04.04.05 JUNTAS DE DILATACIN
04.04.05.01 JUNTAS ASFLTICAS m 109.20 91.40 0.00 91.40

04.05 CUNETA LATERAL


04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 260.00 0.00 0.00 0.00
04.05.01.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 260.00 0.00 0.00 0.00
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACIN MANUAL DE ALCANTARILLA m3 144.00 0.00 0.00 0.00
04.05.02.02 RELLENO COMPACTADO MANUAL - CON MATERIAL DE PRSTAMO m3 40.00 0.00 0.00 0.00
04.05.02.03 ELIMINACIN DE MATERIAL EXCEDENTE (Dm=5.00 KM) m3 130.00 0.00 0.00 0.00
04.05.03 OBRAS DE CONCRETO SIMPLE
04.05.03.01 SOLADOS e=0.10m, F'c=140 Kg/cm2 m2 240.00 0.00 0.00 0.00
04.05.04 OBRAS DE CONCRETO ARMADO
04.05.04.01 CONCRETO F'c=175 Kg/cm2 m3 82.50 0.00 0.00 0.00
04.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 800.00 0.00 0.00 0.00
04.05.04.03 ACERO DE REFUERZO fy=4200 kg/cm2 kg 4,562.00 0.00 0.00 0.00
04.05.05 JUNTAS DE DILATACIN
04.05.05.01 JUNTAS ASFLTICAS m 180.00 0.00 0.00 0.00

04.06 BUZONES DE INSPECCIN


04.06.01 OBRAS DE CONCRETO SIMPLE
04.06.01.01 BUZN TIPO CHIMENEA D=1.20, H=4.60 m. u 47.00 0.00 0.00 0.00
04.06.02 CADA VERTICAL
04.06.02.01 TRABAJOS PRELIMINARES
04.06.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 257.60 0.00 151.34 151.34
04.06.02.01.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 257.60 0.00 152.34 152.34
04.06.02.02 MOVIMIENTO DE TIERRAS
04.06.02.02.01 EXCAVACIN MANUAL PARA CUNETAS m3 644.00 0.00 133.95 133.95
04.06.02.02.02 REFINE, NIVELACIN Y COMPACTACIN m2 257.60 0.00 151.34 151.34
04.06.02.02.03 RELLENO COMPACTADO MANUAL - CON MATERIAL DE PRSTAMO m3 62.10 0.00 62.10 62.10
04.06.02.02.04 ELIMINACIN DE MATERIAL EXCEDENTE (Dm=5.00 KM) m3 727.38 0.00 167.44 167.44
04.06.02.03 OBRAS DE CONCRETO SIMPLE
04.06.02.03.01 SOLADOS e=0.10m, F'c=140 Kg/cm2 m2 257.60 0.00 131.74 131.74
04.06.02.04 OBRAS DE CONCRETO ARMADO
04.06.02.04.01 CONCRETO F'c=175 Kg/cm2 m3 24.00 0.00 0.00 0.00
04.06.02.04.02 CONCRETO F'c=210 Kg/cm2 m3 141.31 0.00 61.72 61.72
04.06.02.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 346.89 0.00 346.89 346.89
04.06.02.04.04 ACERO DE REFUERZO fy=4200 kg/cm2 kg 10,471.75 0.00 4,898.78 4,898.78
04.06.02.05 JUNTAS DE DILATACIN
04.06.02.05.01 JUNTAS ASFLTICAS m 10.00 0.00 0.00 0.00
04.06.02.06 OTROS
04.06.02.06.01 ASENTADO CON MAMPOSTERA DE PIEDRA MEZCLA 1:5 = 70% P.G m2 7.96 0.00 0.00 0.00
04.06.02.06.02 WATER STOPO DE PVC 6" PROVISIN Y COLOCADO DE JUNTA m 9.80 0.00 0.00 0.00

04.07 ALCANTARILLAS PERFILADA PVC 2.25m, DE DIMETRO


04.07.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 6,491.65 2,144.12 1,646.42 3,790.54
04.05.01.02 TRAZO Y REPLANTEO PRELIMINAR EN TERRENO ACCIDENTADO m2 4,219.57 2,144.12 1,646.42 3,790.54
04.07.02 MOVIMIENTO DE TIERRAS
04.07.02.01 EXCAVACIN DE ZANJA CON MAQUINARIA m3 12,576.46 4,000.72 772.46 4,773.18

RELLENO COMPACTADO MANUAL - CON MATERIAL SELECCIONADO CON


04.07.02.02
EQUIPO LIVIANO
m3 7,530.31 124.50 0.00 124.50

04.07.02.03 REFINE, NIVELACIN Y COMPACTACIN m2 4,219.58 286.81 0.00 286.81


04.07.02.04 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 10,648.71 0.00 0.00 0.00
04.07.02.05 RELLENO COMPACTADO MANUAL - CON MATERIAL DE PRSTAMO m3 4,240.00 1,140.83 0.00 1,140.83
04.07.02.06 ELIMINACIN DE MATERIAL EXCEDENTE (Dm=5.00 KM) m3 1,927.75 1,430.13 497.62 1,927.75
04.07.03 SUM. E INST. DE ESTRUCTURA DE ALCANTARILLA
04.07.03.01 CAMA DE ARENA e=0.20m P/ALCANTARILLA m2 4,219.58 286.81 0.00 286.81
04.07.03.02 SUMINISTRO E INST. ALCANTARILLA PVC D=2.25 m m 1,298.33 88.25 0.00 88.25

05 PLAN DE MANEJO AMBIENTAL


05.01 CHARLA DE SENSIBILIZACIN AMBIENTAL u 1.00 0.40 0.20 0.60
05.02 PLAN DE RECUPERACIN DE REAS VERDES m2 1,200.00 0.00 0.00 0.00
05.03 MITIGACIN AMBIENTAL u 1.00 0.50 0.00 0.50
06 SEALIZACIN
06.01 SELIZACIN Y SEGURIDAD EN OBRA mes 9.00 3.00 1.00 4.00
06.02 LETREROS INFORMATIVOS u 40.00 40.00 0.00 40.00