CLASE 17
Desarrollo prctico de VSM en Construccin
Agenda
Resumen
Repaso VSM
Desarrollo paso a paso de
ejemplo de VSM
Problemas de calidad
Probelmas de
Demoras Seguridad
Lean Green
Green-Lean
Construction Building
3 6 5
CT= 1 hrs/m2
VP= 33%
3 Day Order
Concrete Planning & Control
Steel Plant
Daily Route
R-bar Last
Planner
Procurement Cut & Bent
Labels
FIFO
improvements 3 Day Route Last Planner
-R-bars implementation
Reception
FIFO lanes
Formwork Concrete Pouring
Rebars & Spacers Installation Formwork Removal
FIFO
FIFO
Installation
FIFO
FIFO FIFO
FIFO Work standardization
5 6 5 3
Continuos activities max. 1 Section max. 1 Section max. 3 Sections
Environmental improvement Recycling. & recycling FW = 13% (0,1 L/m2) -Concrete re-use
- Pump control
Waste management
JTP
Value stream Sync
4 min/m2 2 min/m2 8 min/m2
17 min/m2 4 min/m2 3 min/m2 2 min/m2
Timeline
Flujos material
Lnea de tiempo
Simbologa
Mauricio Toledo 2014 LEAN - Clase 17 18
Smbolos