You are on page 1of 48

Volume 8, Issue 38 March 2017 ISSN No.

0976-254X

www.railbizindia.com

` 100
FIRST WORDS

Right or wrong, it's very pleasant...

Lost in translation
Even while the Government and IR continue making development related announce-
ments, IR managements have not addressed the public loss of trust and rising
skepticism. Several past commitments that were to be visions for IR have been quietly
dismissed from the budget pronouncements. This mistrust starts from simple actions
like letting passengers know how late a train is: it is now expected that most trains
running late will run even later than any IR information: passengers have an instinctive
lack of trust here. Many of the budget numbers are just plain doctored. Any survey
would reveal the low trust in IR pronouncements being based on serious action plans.
Examples why the messages need correction:
IR has defined semi- high speed corridors for passenger trains @ 160 kph and it was
expected that by now IR would lay out these; instead we just have a few minutes
saving on a single train.
2014 again: for 4 rail based technical universities, a special delegation visited China.
The concept was then reduced to converting the Vadodara based National Academy
of IR to a holding university with affiliation of training institutes in Pune, Secun-
derabad, Nasik, Lucknow and Jamalpur. Proposal lies buried.
Consider dynamic ticket pricing: models, veering more on fixed escalation as the
travel date nears, have been tried. IR is now seemingly back to a fixed price (plus
Tatkal, fixed enhanced pricing on defined set of tickets). IR has never reduced prices
even on trains with low load factor.
Rail Tariff regulator talk, born around 2006 arising out of IR need for tariff revision
when the politicians would not hear of any increases for almost 10 years, is now pass.
Initial IR efforts were to link tariffs to fuel prices but the numbers were not supportive.
The concept, part of IR presentations, has now been rechristened to a Rail Develop-
ment Authority that would make suggestions for tariff disputes, something already
with the Railway Rates Tribunals. IR has gone silent.
Commissioning dates on the dedicated freight corridors, perhaps the biggest in Indias
rail history, remains fluid, amid no explanation for the slippages.
A vision that IR will concentrate on its core transport business and shed the need for
IR owned manufacturing and non-core activities, lies buried with announcements
for new facilities to suit political needs. Witness that commissioning of a station
escalator is still preceded by newspaper advertisements and inaugurations are made
by video links from far, far away. Not much has changed.
And even as freight traffic has shown a negative growth, the 2017 budget is based on
a premise of 71 mt increase, without any reasons.
Next issue: July 2017
IR needs to act to regain the lost trust. That is critical to its wellbeing. Anything else
is just short term expediency.

(Vijay Raina)
Editor

...to break something from time to time.


...Fyodor Dostoyevsky
Volume 8, Issue 38 March 2017

CONTENTS

www.railbizindia.com

Consulting Editor
IR Budget: exclusive opinions
Sumant Chak, AITD
5 Freight wagons 11 Arvind Khare
Stuck at 21 Merged and opaque
Honorary Adviser
G K Mohanty 6 S N Agarwal 12 Alok Johri
SER leads on positives Wither objectives

Editor 8 Chatte Ram 12 Samar Jha


Management through Twitter
V. K. Raina NFR records achievements
1 Mohd. Jamshed 10 Arunendra Kumar
14 Swachh Bharat
Measuring progress on
A transformational agenda A sound start for the budget
For Advertisements and Circulation cleanliness
Dr. Rajni Raina 2 Ravindra Gupta merger
13 Innovation Awards competition
Business Manager Enhanced passenger 10 A Ramji

Phone : +91 80170 62121


experiences Hides more than it says 16 Budget snippets
4 Vivek Sahai 11 KB Sankaran
For better asset productivity Unaddressed resource crunch
Disclaimer :
Views expressed by various authors are
personal and do not necessarily reflect the Construction Operations
views of their corporates. 18 HK Jaggi 30 Jit Sondhi
Bogibeel, a bridge like no other Getting ready for high
European Correspondent: speed trains
Ms Geetha Munikoti, Berlin 36 Dr Manish Kumar
Improving driving crew
performance
IT Support
Dilip & Rajat Innovation
34 Rail fracture detection
Designed & Printed by 37 Appropriate technology
Headliners Advertising Services Pvt. Ltd. Optimal communications on a
87, Monohar Pukur Road branch line
Kolkata 700 029
e-mail: headlinersadvertising@gmail.com Manufacture Potpourri
22 V S Pathak Personality
Chittaranjan locos consolidating 39 Sarabjit A Singh
on gains
Metro A profile in never-say-die
26 SK Luthra 40 From China
DMW Patiala 32 BS Dixit, MD Nagpur Metro Handling millions in the Year of
Marking up the diesel loco fleet A new template for Indian Metros the Rooster

For subscriptions & a complementary copy,


please e-mail at railbizindia@gmail.com

Rail Business
2E Alipore Avenue, Kolkata 700 027, India
Phone : +91 94323 64001, +91 80170 62121, 033 40088827;
e-mail : railbizindia@gmail.com
Five issues published in a calendar year
A sustaining, strengthening and
transformation agenda
Transformative measures have to be undertaken to make IR competitive to
retain their position of pre-eminence.
IR has loaded 23 mt more this year up to January in commodities other than
coal. Steel loading has grown by 4.95 mt, iron ore by 16.65 mt and likewise
raw materials for steel plants, container sector and other goods have also
surpassed last years performance. This is a direct impact of the freight sector
reforms which have resulted in lower rail logistics costs by 20-30% from
initiatives like elimination of 10% port concession charge and a 15% busy
season surcharge for a significant period this year, reduction in documentation,
promotion of ease of doing business by elimination of the dual charging policy
for export and domestic iron ore, permitting 43 additional commodities at
lower (FAK)rates and allowing IRs category I and II goods sheds for container
traffic and facilitating reduced lot sizes (and lowered inventory) for commod-
Mohd. Jamshed, Member (Traffic), IR Board
ities like cement, salt ,food grain and fertilizer transported in covered wagons.

The 2014-15 Economic survey had brought into perspec- works to be funded from the newly announced Safety
tive the historical neglect of IR and the need for sustained Kosh. IR has also increased its focus on non- fare revenue
investments to eliminate distortions and biases in favour generation through monetization of its vast assets.
of other modes of transport, though less economical and
Passenger needs
less environmentally sustainable.
Travel experiences will be eased by measures like a five-
In contrast to sectors such as civil aviation, the two major minute wait time target especially with IT aids, meet
land transport sectors roads and especially railways demand by creation of capacity and fresh customer specific
are dependent on public investments. successive plans train products (Humsufar, Antyodaya etc.). Thus, the
have allocated less resources to the railways compared to decline in the number of passengers, a regular feature
the transport sector. the share of railways in total plan since 2012-13, has been reversed in 2016-17. Data up to
outlay is currently only 5.5 % vis--vis about 11 per cent January 2017 shows a comparative nearly one percent
for the other transport sectors and its share in overall increase in passengers carried, for the first time in last 5
development expenditure has remained low at below 2% years. Measures like competitive ticket booking facility
over the past decade. and withdrawal of service charge on e-tickets should work.
Heightened Capex Freight Coal
The government has ensured that IRs capital and devel- The bad boy is coal, where loading has been adversely
opment expenditure has risen from ` 54000 Cr in 2014- affected due to less offering vis-s-vis potential, reduced
15 to ` 94,000 Cr in 2015-16, is targeted at ` 1.21 lakh imports and non-operationalisation of several coal blocks.
Cr in 2016-17, rising further to 1.31 lakh Cr in coming Initiatives taken in coordination with the Ministry of Coal
FY (a significant ` 55,000 Cr is from government sup- (like rationalization of coal tariff including lower freight
port). Budget 2017 would form an important milestone rates for long lead transportation, Merry-Go-Round pol-
in the overall transformation journey as it takes forward icy, short lead discounts, etc.) are working. Coal India
the growth agenda towards which IR has already been loading, which offers the maximum share of coal traffic,
taking major course corrections over the last two years. has increased from 209 rakes per day last year to 217 up
We recognise that IR faces stiff competition from other to January this year. This has further picked up to 235 in
modes which are dominated by the private sector. Nov, to 242.5 in Dec 2016 and 243.1 rakes per day in
Jan 2017.
Besides the enhanced Government support, various in-
novative financing models are also planned such as loan Ten recently appointed key Customer Managers will be
from LIC, PPP and other models based on cooperative looking closely at the requirements of its customers in
federalism through joint ventures with state governments. each sector and respond quickly to their needs. We will
Infusion of ` 8.56 lakh Cr capital for 2015-19 is sought, strive to help customers with measures like end-to-end
with ` 2 lakh Cr for network decongestion, ` 1 lakh Cr integrated transport solutions, specific rolling stock of-
in station development and logistic parks, ` 1 lakh Cr in fered, customised practices for perishable goods. And
rolling stock, ` 1.27 lakh Cr in safety & 0.65 lakh Cr in above all fixation of tariffs will be taking into consideration
High speed. The Government will lay down clear cut costs, quality of service, social obligations and competition
guidelines and timelines for implementing various safety from other forms of transport.

Rail Business [Focus-India] March 2017 1


I R BUD GET 20 17

Towards better deals for the passengers


Ravindra Gupta, Member Rolling Stock / Railway
Board joined IR Service of Mechanical Engineering
in 1975, starting with apprenticeship in Jamalpur.
His 36 year IR experience has included those as
General Manager, South Central Railway, Chief
Mechanical Engineer, Western Railway, Divisional
Railway Manager, Chakradharpur, besides several
important assignments in RITES and RDSO.
OP Chaube, a senior in Jamalpur comments:
Ravindra has always been a goal-based person,
upright, soft spoken, quiet and effective in his work
life. He is keenly interested in system optimisation
and should leave long lasting impacts in his tenure.
Ravindra Gupta (Centre), Member, IR Board in Kolkata with J K Saha (Left) and R L Gupta,
Chief Mechanical Engineers.

Three months into his charge as Member Rolling Stock units loaded to the capacity and traffic needs. It does
in the IR Board, Ravindra Gupta firmly believes that a however appear that the wagon procurement plans are
key need for senior management is a vision on long term uncertain at present as no tenders have been called for
needs and strategies. In a chat during his review visit to the coming FY needs. Contrary opinions on whether IR
Kolkata, Gupta listed occasions when absence of a vision needs more wagons or not seem to be ruling, with no
has caused poor decision making. It came as no surprise certainty. Currently traffic streams on IR are not growing
that one of the senior IR managers who left deep impres- and hence the ambiguities on wagon purchase.
sion on a very-new-to-the job Gupta (late 1970s, then an
New lines of work
Assistant Mechanical Engineer) was VCA Padmanabhan,
General manager on the Eastern Railway. Gupta recounts Gupta listed some new initiatives on coach maintenance
that in those years the General Manager and an Assistant and upgrades. The budget includes sanction for 16000
officer were separated by a power distance but a young ICF coaches to be retrofitted with center buffer couplers
Gupta was impressed by Padmanabhans vision state- and a series of iterative discussions have taken place with
ments and the efforts he made in developing futuristic potential contractors. Up to 8000 coaches are planned
plans. Another influence he recognises is the 6-lane con- for 2017-18 though tenders are scheduled for call in March
struction of the Howrah Bridge in Calcutta, way back in 2017. This will be ambitious and tough. Gupta also indi-
1940s when the current traffic explosion would have been cated sanction for retrofitment of 2000 of these coaches
the stuff of dreams. These are the legacies Gupta is con- with improved internal furnishings, on par with some
scious of and wants to carry forward in his current position. rakes already fitted at the Bhopal workshops. Gupta hopes
for up to 40 rakes being so fitted in coming year (say 1000
Gupta has moved from his earlier position as General coaches) though the availability of suitable vendors and
Manager on the South Central. In Secunderabad, it was re-furbishers is still less than adequate. The success of
easy to perceive that the growing city passenger traffic this plan will depend increasingly on the vendor and
would not be met by its three terminals at Secunderabad, design development processes. Increasing number of
Hyderabad (Nampali) and Kachiguda. He accordingly LHB coaches will also be equipped with better furnishings,
pushed for a fourth terminal at Cherlapalli. This would like some rakes already commissioned from the Rae Bareli
be a growing terminal with 10 platforms and upgraded Coach factory.
passenger areas. During his earlier tenure, as Divisional
The workshops
Railway Manager in Chakradharpur (the South Eastern)
a similar process led to opening of a second entry to the Additional facility for coach upgrades will be added to in
Tatanagar station. the New Bongaigaon (the North East Frontier zone)
coach workshop under a project estimated at ` 90 Cr.
The 2017 budget The need to significantly upgrade the facilities and ambi-
Adequate funding exists in the coming FY for various ence in various repair locations for coaches and wagons
rolling stock procurement plans, with all the production has been addressed through bulk sanction of ` 100 Cr

2 Rail Business [Focus-India] March 2017


each for maintenance facilities for coaches (pit lines), are stuck with the 5-decade old ICF design bogies and
wagons and the workshops. Right now, his team is work- shell, is not so promising. IR had earlier planned for a JV
ing out the specifics at each location and the physical at Kanchrapara but the tendering effort did not proceed
work should start within 2017. beyond the qualification stages (RFQ). Gupta hopes that
Train sets the purchase process will now be restarted and this could
In a significant new initiative, IR has now sanctioned a lead to new design EMUs in coming years. Even as the
project for development of new train sets by the Chennai issues from successful trial of the imported Talgo train
coach factory. The development is interesting as these sets on the Delhi-Mumbai route are being sorted out by
long-distance EMU train sets will have powered axles on an Additional Members committee, funding in the next
the trailing coaches. Design development efforts have FY is not visible, leading to doubts on follow up action.
been seeded and the prototypes will take some years. The revised structure
A switchover to AC propulsion alone on the Chennai / As reported earlier, the responsibilities between two Board
Kapurthala built EMUs has been planned in 2018. Such Members (Mechanical and Electrical) have been rede-
train sets, equipped with Siemens and Bombardier traction fined and Gupta now looks after electric multiple units
sets, are already working in Mumbai (financed from the (EMUs) train sets, handing over the diesel loco charge.
MRVC project) and additional in -hand vendor develop- Gupta feels that the change has now been well adopted
ments will permit a total switchover to these improved and may even have already paid dividends. Thus, the
designs. effort at developing electric loco manufacture in the
Gupta feels that the loco scene on IR looks good with Varanasi loco factory (that has manufactured only diesels
multiple designs and capacities on offer in next two years so far) has gone smoothly, something that would have
for the Alstom and GE JVs. The outlook on EMUs, that been submerged in departmental battles earlier.

Cleaner and smarter rail


A positive fallout of recent reorganisation has been on clean- indicated that this new approach has removed the responsi-
liness and upkeep, with single responsibility now devolving bility ambiguities that limited qaulity earlier.
on nominated officers in divisions and locations. An Adviser But how good is good? Gupta has current year plans for third
(environment) in the Boards office, assisted by four directors party audit of stations and trains that should pin point future
drawn from mechanical, electrical, civil and traffic cadres, has changes and resourcing required. One area under discussion
developed routines that now make station areas and trains involves changes in the service contracts for housekeeping as
look smarter than these have ever been. The Chief Rolling current bid documents have shown deficiencies, particularly
Stock Engineer in the zonal railways coordinates all actions, in work assessment and control. Gupta expects that a revised
including for premise cleanliness and order, on-board house- bid document will be developed by the Quality Council of
keeping services and clean train station programme. Gupta India in a few months.

The recurring slides at the top


IR has rightly launched a series of actions to evolve a mid and Financial Commissioner (FC, part of the seven member IR
long term action plan for traffic growth and improvement in Board), with three incumbents in last one year: With the
service levels and marketing rail transport. voluntary retirement of one in Sep 2016, a short term looking
Change demands commitment at the top. For viable results, after appointment lasted for three months and the successor
a group of change champions is mandated; otherwise IR will retired in Feb 2017 end. IR has now appointed the senior
flit from one plan to another and never get results on the big most IR Accounting Service Officer (superannuating June
changes envisaged. Government procedures limit long term 2017) to look after the functions. In fact, the average tenure
tenures for senior IR executives, with many Board Members of last 10 FCs has been a discouraging 9.3 months only.
staying on for about a year.
The government had granted a two year service extension to Clearly the Ministry has to look at the procedural policies
the Chairman, presumably with the continuity of a change involved and develop a better way of retaining change
champion thought. This status has got worse in case of the champions.

Rail Business [Focus-India] March 2017 3


I R BU D GET 20 17

Better asset productivity for IR rejuvenation


immediately engaged itself meticulously to diligent task
of rebuilding its reserve funds. This was possible by brining
passenger fares up to realistic levels and improving its
productivity. However, on both these counts IR efforts
were feeble. Consequently, for the 7th Pay Commission
(2016) implementation, IR discovered that it had no
family silver left to disburse the required amount.
IR has been steadily increasing its freight rates only to
subsidise its passenger segment. The high freight rates
became counter-productive as the road mode with its
inherent strength of door-to-door service upstaged rail
as the preferred mode of transportation. Efforts are now
underway to subsidise non-AC segment from the AC
segment by introducing the mechanism of surge pricing.
IR is now losing the creamy AC traffic to civil aviation.
Consequently, growth in both sectors this year is elusive.
Just better productivity
Vivek Sahai, ex. Chairman, IR Board
The need of the hour is to concentrate instead on improv-
ing productivity of IR assets to reduce unit cost of opera-
Massive changes in IR working are underway. 2017 will tions. In the last three years IR has infused nearly ` 3 lakh
be remembered as a watershed in the IRs history as it Cr in its capital expenditure. It has been spent primarily
sounded the bugle for the things to come, by merging the on procuring rolling stock & new line /multiple line
IR Budget with the General Budget. Purportedly, all this projects. It is reasonable to expect that such large invest-
is being designed to spruce up its performance. But why ments should now start showing results in the form of
does IRs performance need spruce up? improved mobility and enhanced transport output.
Enough expertise is available in IR management to make The bulk of capital expenditure goes towards construction
required course corrections. What is required is a focused of new and multiple lines. The doubling projects are taken
attention, intense supervision and a clean conscience up in those sections only where there is a proven dearth
among top echelons of IR hierarchy. of capacity and more traffic is waiting. It can be surmised
Passing the buck that whenever a doubling project is completed there
The prodigality of the 6th Pay Commission (2006) dented should be a discernible relief in congestion on that route,
IRs capacity to generate revenue surpluses year after year. leading to better quality of service and customer satisfac-
In fact, by the time the Railways finished the onerous task tion. This should convert into more demands from freight
of paying arrears in pay and allowances to its 1.3 million customers. Similarly, completion of new lines should lead
strong work force and to 1.2 million pensioners an to increased rail traffic in both passenger and freight.
equally strong non-work force- it had depleted all its But this does not seem to be happening. After nearly four
fund reserves. Prudence demanded that IR should have decades the freight loading is hovering at levels lower
than the previous year, and that too with a much shorter
lead. This is an alarming situation, clearly showing that
IR Operational Indices the investment in procuring locos and wagons in the last
three years has gone waste.
5.2
It is now imperative for IR to act hawk-like to watch its
5.15 21,000 asset productivity. A few of these indices are considered
5.1 10,000 20,000
germane to the issue of assessing how railways are per-
forming. . The first and foremost, the wagon turn around
5.05 8,000 19,000 (WTR), indicates the time that elapses between successive
loading of wagons. In that sense, it is a very fine barometer
5 6,000 18,000 of two facets of railway operations viz. mobility and de-
4.95 4,000 17,000 mand for rail transport. A drop in either of these two will
increase the WTR, reflecting in the reduced freight loading
4.9 2,000 16,000 and earnings. WTR is reported to be about 5% less com-
pared to the previous year.
4.85 0 15,000
2011-12 2012 2013 2014 2015-16 Another operating index of importance is NTKMs (Net
Years t-km) per wagon per day that gives an indication of
Wagon turn round NTKm/wagon day NTKm/engine hour
how well wagons are utilised. As it accounts for only net
tonnes, any increase in empty wagon-km will impair it

4 Rail Business [Focus-India] March 2017


substantially. In addition, any stress on mobility too will should be matched with the declared improvement in
reduce the distance and cause a drop. capacity of that route.
But, the important operating index is NTKMs per engine The huge investment sunk in IR in the last three years
hour in use, which combines the performance of both must support at least 4 % of growth in freight every year.
wagons and locos and has a direct bearing on the profita- If the expected relief is not materializing on the ground,
bility. Any drop in this index reduces the profitability of it calls for a detailed investigation into how such invest-
the organization, a downward trend will inflect on plan- ment is being planned and whether there are any flaws in
ning for acquiring wagons and locos in subsequent years. the process. Similarly, high hp locos with superior tech-
Railways must pinpoint the reasons for the drop in these nology (like IGBT) have been inducted in the system at
three indices and chalk out a strategy to reverse the trend. heavy cost. Also, all BOXNHL/BCNHL/BLC wagons
A suggested course of action would be to make a list of are fit for 100 kph speed. A concerted effort is imperative
traffic facility works completed in the last four years. The to avail of the purported benefits from such capital-
foremost among these are the doubling projects, comple- intensive investments. There is a tendency in the field to
tion of which multiplies the capacity of that route. Next restrain the freight trains from running at their maximum
will be list of loops added on a congested section which potential. Sometimes it is done in the garb of balancing
extends immediate relief in daily operations. Upgradation speed in the case of electric locos and discouraging the
of signalling system, electrification of a route and removal loco drivers to use dynamic brakes in case of diesel locos.
of level crossings too provide relief and should improve All such ambivalent stances cry out for immediate reso-
mobility on that route. An aggregation of these works lution to improve mobility even under existing scenario.

Stuck at 23, or relapsing to 21?


Indian wagon bogie designs, an indigenous development otherwise. The introduction of the 25 t wagons in 2006 had
tracing back to the 1980s, continues to defy any upgrade been cleared by the then Member Engineering, a highly-
solutions. These bogies (CASNUB), like the 3-piece steel respected engineer in IR chronology.
castings based versions popular in North America, exert higher
track forces and are prone to accelerated wheel wear and may Track engineers are also reported to have pointed out that
be the root cause of IR track engineers to accept any increase many old bridges on the network will not be able to withstand
of the max axle loads on IR wagon designs. these heavier loads and prior strengthening or rebuild is called
for. This in effect defers the 25t wagon indeterminately. Pro-
The old CASNUB wagons, initially authorised for 20. 3 t (21!) ponents of the 25t designs point out that a large-scale re-
axle load, have been permitted to load to an axle load of 22.95t certification, including with instrumented trials, was carried
(23!) more through management action than engineering out as a part of the ` 17,000 Cr Special Railway Safety Fund
acceptance. IR increased this on the BOXN design to 25t max (2001-2009) when all suspect bridges on main routes were
by a bogie spring addition. Limited numbers of these EL attended.
wagons have been in operation since 2006 on the iron ore
circuits on the SE, ECoR. SECR, SWR and SR zones. Track These wagons can be introduced in regular service only after
engineers have, in a near concerted view, attributed increase statutory certification by the Commissioner of Railway Safety.
in rail wear and fractures to the operation of such wagons. It At present no application has been processed, possible only
is not surprising that the introduction of the 25 t wagons has after IRs internal clearance. In effect, the new wagons, when
a 2-steps-back-for-each-forward history, and this status may produced, will either lie in a yard for some years or be used
not change in near future. with limited axle loads, and without CRS certifications. The
issues are pending resolution at the IR Board.
The BOXNS story
New designs in the pipeline
IR has designed a higher payload gondola (BOXN series)
wagon version, with lower diameter (840 mm) wheels, at 25t It is not that IR engineers have not reacted to the need for
axle load. A prototype wagon manufactured by Braithwaite replacing the CASNUB over-dependence. Two of its initia-
Kolkata has undergone the required safety certification suc- tives, for a swing motion design from a well-known US man-
cessfully and IR has also released supply contracts of around ufacturer, and design consultancy with a US firm, have both
2000 new wagons. been stuck in procedural issues with no solution in sight. These
would result in designs with less track forces and greatly
The story does not have a happy ending yet. enhanced acceptance by track engineers. But this window
It is learnt that the track engineers have strongly objected to remains shut too as rules become more important than solu-
25 t operation of these wagons, quoting data on anticipated tions to a long-term problem that is eating into IR freight
higher wear and rail fractures. This disregards the international performance and costs.
experience where freight train axle loads now near 40 t in IR may be stuck at the gates, permanently at 23 and if many
some ore circuits. The 25t axle load, with lower wheel diame- conservative track engineers are to be believed, relapse to 21.
ters, is now almost universally accepted for operation and IR
reservations seem to defy these. But IR data seems to show Either way , the ending is not a happy one.

Rail Business [Focus-India] March 2017 5


I R BU D GET 20 17

South Eastern leads on freight growth


This Budget was more of a nut-and-bolt modal transport and synergetic investment.
budget, shorn of populism and aimed at The allocation of ` 3,96,135 Cr in creating
turning IR around and making it what it is and upgrading infrastructure in the next FY
-a national organization carrying the bur- for transportation sector is part of this inte-
den of a billion plus aspirations. It also saw grated infrastructure planning paradigm. The
many firsts and a departure from set tradi- Finance Minister has unveiled the largest ever
tions of 94 years. The core effort of fixing IR budget of ` 1.31 lakhs Cr, an 8.26% in-
tariffs based on cost, quality of service and crease. Of this, budgetary support from general
competition from other modes has been exchequer would be ` 55,000 Cr on which no
underlined. dividend is now payable. The plan for a record
addition of 3500 km of new tracks (2800 km
SE Railway, known as a Blue-Chip zone for
in 2016-2017) is an encouraging milestone.
its outstanding profitability, is primarily a
freight network with 81% earnings contributed Passenger comforts
by freight (`12401 Cr in previous FY 2015- IR has also promised elimination of unmanned
16 and an estimate of `12967 Cr for the cur- level crossings by 2020, provision of bio-toilets
rent fiscal). The budgetary projection for in all coaches by 2019, redevelopment of 25
2017-18 at ` 14251 Cr (83% from freight) new railway stations, making 500 stations
SN Agrawal, General Manager, South Eastern should result in earnings growth at 9.9% over differently-abled-friendly by providing lifts
Railway, Kolkata the current FY. The zonal Operating Ratio is and escalators, launch of dedicated trains for
projected at a blue chip like 77.6% (78.2% pilgrimage and tourism and launch of single
for the current FY). The ratio of net revenue point contact coach mitra (=friend) for on-
to Capital-at-Charge and investment from board complaints.
Capital Fund is 29.5% for 2017-18.
SER is set to receive ` 5046 Cr capital invest-
ment, including ` 803 Cr under EBR-IF, an
enhancement of about ` 900 Crore over the
current FY. Capacity additions and operation-
al improvements should pick up pace.
Multi-modal emphasis
This budget has quite an emphasis on multi-

New lines sanctioned Cost ` Cr


Radhanagar Barachak (10 km) 40
Dumetra C Cabin to Bisra (2.3 km) 35
BadampaharBangriposi (investment through JV/SPV 900
with State Government and stake holder)

Key new projects sanctioned

Capital head Project Cost ` Cr


Traffic facilities Removal of permanent speed restrictions on
3 sections 13.6
Road safety works Improvement and interlocking of 29 level 12.5
crossing gates
Road grade bridges 13 subways 35.5
11 Road over-bridges 269.4
Track renewals Major track renewals: 276 km 335.0
Other track renewals 105.3
Passenger amenities Raising of 4 platforms to high level 3.6
2 foot over bridges with ramps 18.2
Funds allotment: ` 2739.4 Cr. (40% more over current FY)

6 Rail Business [Focus-India] March 2017


I R BU D GET 20 17

The North Frontier: uniting the Northeast


The 2017 budget has been supportive of var- railway land. Guwahati would be reconstruct-
ious NF Railway initiatives, of which some ed as a through station with elevated level
were listed by Chatte Ram, General Manager platforms. The existing goods shed would be
in a chat in his office in Maligaon, Guwahati. relocated out of New Guwahati and a passen-
NFR with its 4076km network has the respon- ger terminal with 4 full lengths washing pits,
sibility of rail connectivity of state capitals of 3 stabling & 2 sick lines will instead augment
the Northeast (including Sikkim). We have existing coach maintenance facilities.
already constructed BG lines to all NE states
Level Crossings
except Sikkim and hope to connect all NE
state capitals by 2020. The zone is also man- 1568 level crossings, 1200 manned and 368
dated to play an important role in the realisa- unmanned (plus the 167 unmanned ones on
tion of the Trans Asian Railway Network of the Darjeeling Narrow Gauge section), dot
UNs ESCAP. the NFR network. The unmanned level cross-
ings will be eliminated in phases. For this year,
Kamakhya Station Redevelopment NFR has targeted elimination of 122 un-
IRs ambitious station re-development plan manned crossings, 101 will be manned and
launched on 8th February 2017 includes Ka- 21 closed by construction of subways/ over-
makhya (Guwahati)station under PPP model. bridges. The remaining unmanned crossings
Chahatey Ram, General Notice inviting tender for selection of Project will be eliminated by early 2019.
Manager, NF Railway, Guwahati
Proponent under this ` 228 Cr project has While 108 Gate Mitras have been provided
already been issued on 9th February 2016. to sensitize road users about danger of ignor-
Kamakhya will undergo major expansion in ing approaching trains, a major safety concern
view of sanctioned Doubling projects of New is construction of unauthorised level crossings
Bongaigaon Goalpara Kamakhya and New in states of Assam, Bihar and West Bengal.
Bongaigaon Rangiya Kamakhya and 550 such unauthorised crossings have been
Quadrupling project of 4-line Elevated Track identified.
from Kamakhya to New Guwahati. It is ex- Track maintenance
pected to handle approximately 40,000 pas- NFR has drastically reduced incidence of rail/
sengers per day. weld failures from 141 in 2008 FY to 36 last
As per the plan, the developer would be pro- year and 28 in current FY (up to Dec 16).
vided 50,000 sq. encumbrance-free railway This has been achieved mainly by accelerated
land for commercial development. In addition, track replacements: during 2015-16, NFR had
they may also do commercial development of covered 94.8 km, almost double the target of
the air space above the station building. It is 50 km. This fiscal (till Dec 2016) 32km of
expected that the developer would fully fi- partial track replacement has been recorded.
nance the station development works and also Other replacement targets like those of sleep-
generate surplus revenue for IR. ers etc. and increasing sleeper density from
1310 to 1660 sleepers per km have already
Important features under this development been surpassed.
include an iconic structure of the station with
modern state of the art facilities, congestion Rail / weld failure trends
free entry/ exit to the premises, segregation Year Rails Rail welds Total
of arrival/departure of passengers, large con- 2008-09 29 112 141
course and circulating area with provision for 2009 26 53 79
drop off, pickup and parking, integration of
the station with bus and the planned Metro 2010 26 51 77
railway , a 4-lane flyover to connect circulating 2011 28 39 67
area on both sides of the station directly with 2012 24 37 61
main city road and a minimum 15 m wide
road connecting with adjoining NH 37. 2013 18 16 34
Kamakhya - New Guwahati 2014 18 35 53
quadrupling 2015 15 21 36
Sanctioned in Works Programme 2017-18 at 2016-17 12 16 28
` 3062 Cr, this will decongest tracks between (till Dec)
Kamakhya and Guwahati and eliminate 10
Elephant first, please
level crossings. A 10-km elevated corridor
The new BG lines present a contrast to the replaced with 4 tracks, envisaged between Kamakhya NFR has an elephantine problem of 21 iden-
MG network. & New Guwahati, is feasible within existing tified Elephant Corridors where permanent

8 Rail Business [Focus-India] March 2017


Of trains and tea: the DEMU train introduced in Tinsukia Division of N F Railway.

speed restrictions have been imposed, in ad- tion system in September 2016, becoming the
dition to temporary speed restrictions at 10 second zone on IR to do so. This provides for
locations. Mainly Alipurduar, Rangiya and paperless purchase and stores processes and
Lumdig Divisions face these issues. Recent promotes seamless linkage between headquar-
increase in incidents of elephant deaths due ters and field units.
to train dashing have been worrisome. Several
proactive measures like intensive patrolling New services
and close coordination with forest depart- The first ever Humsafar Express train in the
ments have helped avoid about 20 cases. A North-East and only the second on IR was
joint workshop with different stake holders, introduced in December. DEMU services
organized at Lumding recently to chalk out have been introduced in Tinsukia Division
plans to mitigate such incidents, produced fulfilling a long-standing demand of the region.
encouraging outcomes. Passenger services on the Karimganj-
Mahisashan section (Lumding Division) have
Railway electrification
been started after gauge conversion.
Electrification of Katihar- New Jalpaiguri-New
Bongaigaon sections is going on, with the Trucks on rail
Katihar-New Jalpaiguri section nearing com- The Railway Minister had made a commit-
pletion. The fresh sanctions for 1102 km at ment at Agartala in July 2016 to help Tripura
` 1432 Cr will cover the entire main-line then reeling under a fuel crisis, owing to de-
section, except the portion South Assam line plorable road conditions. NFR started the
ex Lumding, few branch lines, and Rangiya first-ever Roll-On Roll-Off (RoRo) service
Murkongselek section. for petroleum products to carry loaded trucks
New sanctions Cost ` Cr on flat-wagon goods train, a first in India. the
first POL RoRo service with 30 flat bedded
New Bongaigaon Agthori DBKM wagons, each having a capacity to
via Rangiya (2nd line), 143km 138 carry two loaded trucks, started in August
New Bongaigaon - Kamakhya from Bhanga (near Badarpur in Assam). The
via Goalpara (2nd line), 175 km 282 RoRo scheme helped the loaded trucks to
piggyback on goods train bypassing the dam-
Guwahati to Dibrugarh via aged national highway near Churaibari.
Tinsukia & Simaluguri to
Dibrugarh, 656 km 890 NFR may be small in terms of its freight
volumes but the operational improve-
Raninagar Jalpaiguri
ments, current efforts for rail accessibility
Samuktala 128 km 122
in the seven sister states of the North East
Ease of doing business and the many exciting construction projects
NFR had implemented iMMS a real-time make it unique in many respects. NFR is
web-enabled material management informa- set to make its contribution felt.

Rail Business [Focus-India] March 2017 9


I R B U D GET 20 17

The IR Budget now, a sound start


Now that the 93 years old practice of a sepa- The initiative in setting up of Rastriya Rail
rate IR Budget is history, it is time to assess Sanraksha Fund of ` 1 lakh Cr over 5 years,
the impact of the IR Budget in new avatar. with seed capital by the Government is an
Previously the Ministers Budget speech used encouraging step. It needs to be ensured that
detailed IR vision. In the new Avatar railways the existing allocations for safety from Central
still find a promising place in the Finance Rail Safety Fund etc. for level crossings are
Ministers speech with icing on the cake of IR not used for shoring up this fund. As in previ-
autonomy having remained untouched. IR ous year, the projects should be identified,
Budget merger with the Union Budget has with an added aim of technological infusion
made a sound start. to upgrade safety.
The budget mandates IR to provide end-to- IR financials, current and projected, continue
end transport solutions for select commodi-
to be a matter of concern. IR must look around
ties. That entails IR to arrange for first and
and make up for the rather static million tons
last mile connectivity in association with lo-
and passenger kilometers. The current oper-
gistic providers. A trend towards the synergy
in transportation sector has emerged and this ating ratio is a sign of financial distress.
is an idea for which the time has come. Other initiatives like redeveloping stations,
Arunendra Kumar, ex. Chairman Railway Board
The increased allocation of gross budgetary providing bio-toilets, arranging Coach Mitras,
support of ` 55,000 Cr is in addition to the disabled friendly stations, solar power fed
now avoided dividend liability of approx. stations, all ongoing initiatives have been list-
` 9700 Cr. This substantial financial support ed. However, the game changer could be the
to the planned investment of an estimated railway station re-development for which the
` 131,000 Cr will translate into a challenging ground realities are taking shape. Proposal for
task for IR to manage execution, especially seeking international expertise for asset main-
when this FY performance in funds utilization tenance is a welcome move and, if used intel-
is not encouraging. ligently, can usher in new technology.

Did not click, hides more than it says


The much-publicised merger of IR Budget It was also necessary to inform details on the
with the General Budget did not click. Even thinking in respect of fares and freight tariffs,
considering the negatives connected with the with which users are closely concerned, in-
presentation of a separate IR Budget, it surely stead of sweeping generalisations like costs,
helped to keep the people very well informed quality of service, social obligations and com-
of the current state of the IR, with which al- petition from other forms of transport. All
most everyone in the country is intensely con- these would have taken a few minutes more,
nected. The information in the Budget this with less time about issues like fitment of bio
year did not do justice to the fundamental toilets, solar power etc. I am inclined to agree
concept that it is a financial statement to in- with the apprehension voiced by Vivek Sahai,
form the public of the financial health of a former Chairman, IR Board (in a media arti-
major public carrier like IR. The least that cle) that the new idea of merging the Railway
could have been done is to let the country Budget with the General Budget has been
know of the income and expenditure profile adroitly utilized to mask IR deficiencies.
for 2015-16 and the trends expected to be in, The Railway Budget used to take nearly two
broad details of new lines under construction hours for presentation and the discussion in
and ongoing major projects like workshops both the houses used to take 10 to 15 hours
A Ramji, ex. General Manager, South Eastern
Railway and Botswana Railways; former President,
etc. (since these were finalized much before for debate. With this merger, the time to de-
South African Railways Association announcement of date of elections for 5 states) bate issues concerning Railways in the Parlia-
and relevant information about disturbing ment may also be curtailed. Such develop-
concerns like the fall in the passenger traffic ments will reduce opportunities for the
and the rather sharp decline in freight traffic. involvement of people in the vital issues.

10 Rail Business [Focus-India] March 2017


Raising IR resources is the big how
The IR's paradigm shift in investments and of about 9000 Crores, internal resources
funding of rail projects is encouraging and has should have been at least 24000 Cr.
been sustained in the merged union budget.
With the present charge, only 37 paisa per
A capital outlay of ` 1,31,000 Cr proposed is
kilometer of rail travel against 74 paisa cost,
nearly double that of 2014-15 outlay.
passenger fares ought to have been increased
While this is heartening, a serious concern to augment internal resources, but the budget
about resources mobilization persists as earn- is silent. With inflation, the freight-passenger
ings during 2016-17 presents a dismal picture. cross subsidy will get further skewed and will
Cumulative performance up to Feb 2017 has worsen the situation.
witnessed a shortfall of ` 3065 Cr i.e. a drop
Creation of a Rashtriya Rail Sanraksha Kosh
of about 9% in passenger earnings and
with a ` 1 lakh Cr corpus over a period of 5
` 10,275 Cr i.e. a drop of about 13% in freight.
years is welcome. With only a seed capital
This poor performance is evident from the
from the Government, IR should arrange the
fact that only ` 14000 Cr has been envisaged
balance resources from their own revenues
as the contribution of funds from internal
and other sources. During 2001-17 a rail safety
resources in the total outlay of ` 1,31,000 Cr
cess should have also been announced.
for 2017-18. This is so in spite of the fact that
KB Sankaran, ex. Member Mechanical, IR Board the railways will not be paying any dividend IR needs to actively strategize augmenting
on the capital at charge, from this year onwards internal resources as its ambitious plan outlays
with merged railway and union budget. With & investments will lead to enormous debt
about 15,000 to 16,000 Cr of internal accruals servicing in the years ahead.
as seen from the past and a dividend outflow

Silent on new IR reforms


It seems that Government has forgotten about efficiency, environment friendliness and safety
Debroy Committee report. Several systematic record of railways is far better than roads, at
improvements are required to pull out IR from the least, Central Government should give
its 150 years old traditional management style much higher support and subsidies to railways.
if it has to become a vibrant organisation. All subsidies of railway services, passenger
Various policy announcements are old except services or development of backward areas,
two: a new safety fund, a good development should come from Government.
and removal of service charge on railway tick-
The budget announces increase of 10%
ets booked on IRCTC website, that seems to
throughput in three years. IR has grown 600
be of no consequence whatsoever.
million t from 2007 to 1100 mt in 2016 with
The ` 55,000 Cr Central Government grant meagre investment in infrastructure. With
is less than ` 64,900 Cr to road sector (12% DFC coming up and huge investment on it,
increase from BE of last FY). This is in addi- target growth and planning should be much
tion to what state governments will spend on more that 10% in three years.
roads. Clearly the Government still feels that
spending on road sector is more important
than on railways. It seems that the Govern-
Arvind Khare, Consultant, ex-Additional ment still does not realise that energy
Member, IR Board

Media Associate
10 th UIC World Congress on
High Speed Rail
Postpond to May 8 - 11, 2018, ANKARA TURKEY
uic-highspeed2017.com
Sharing Knowledge for Sustainable and Competitive Operations

Rail Business [Focus-India] March 2017 11


I R BU D GET 20 17

Lacklustre, does not address the objective


If the objective of the merger of the RB into this to obscure corners of remote pages. There
the GB was to end the dichotomy of two sep- does not even seem to be any mention of
arate budgets and consequential time saving targeted operating ratio (traditionally the
of Parliament etc., this has been achieved. most important indicator of IR performance
However, if the provocation was to provide a and current financial health) and how that
financial bail out to the reportedly would be achieved.
beleaguered IR, GB 2017 does not seem to I do not count waiver of service tax on e-tickets
have served or even addressed this objective. as beneficial in any way. Assistance to IR, like
The only sop to the IR seems to be a contri-
service charge waiver on various outsourced
bution of ` 5000 Cr from GB into the safety
jobs like cleaning etc. or doing away with high-
fund corpus of ` 1 lakh Cr, which IR has been
clamouring for since long. The budgetary sup- er price for HSD as a bulk consumer, does not
port of ` 50,000 Cr and overall outlay are only feature. There is no mention of doing away
a marginal increase over the previous years, a with dividend on borrowed capital like the
normal phenomenon each year in line with IRFC borrowings or of how railways would
escalation and increasing economy. raise extra resources without going into a debt
trap.
Alok Johri, ex. Member Mechanical, IR Board
Adequate details of the rail portion of the
general budget are not available, unlike as in All in all, the subsumed budget gives no indi-
earlier years and the media too has consigned cator to IRs turnaround.

Management by tweets replacing reforms


The first General Railway Budget is unique procure a minimum number of wagons is a
from an IR view, as the plans for this key in- pointer to IRs lack of ambition.
frastructure are lost in a maze of taxes, rural
The focus on investments for infrastructure
and industrial growth, social subsidies and
growth is good, but the heavy borrowing, es-
defence priorities. IR issues nestled some- pecially from the market, does not augur well
where in the text, suitably opaque. for IRs financial health. The plan to list IRFC
What emerges after some scrutiny is the lack in the stock market brings in further uncer-
of a vision for growth. Meanwhile, key recom- tainty as with this borrowing arm in private
mendations of the Bibek Debroy Committee hands, cost of capital is likely to go up.
remain neglected. Revised Estimates 2016- While there is emphasis on passenger safety
17 appear to be unrealistic as the operating and service, there is no indication how the
ratio is realistically set to cross 100. Is it pro- loss-making passenger services will be com-
posed to bring it down to 94.9 by some pensated. The Tariff Regulator seems to have
creative adjustments? been given the go by. Funding pattern of the
Freight loading in 2017-18 has been pegged safety fund is also unclear. With no publicly
at 1065 mt, reminding one of the story of the stated financial targets for the IR zones to
Samar Jha, ex. Financial Commissioner, IR Board ant that climbs one feet up a pole and then enforce accountability on the General Man-
slides two. Such tepid growth of IRs main agers, implementation of accounting reforms
revenue points to an assumption of business has been pushed back by, say, two years.
as usual. Growth in IRs main freight income The new avatar of IR as a department will take
generator, coal, is set to fall. The intention of more time to take shape. The fear is that by
partnering logistic companies for end-to-end the time stock is taken of the impact of a
transport solutions for select commodities merged budget, IR may slide further down
is not a major corrective thrust. The plan to red line.

In a TV discussion , an ex Chairman , IR Board , asked to rate the railway budget on a


300 minutes then, 3 now scale of 10,is reported to have remarked that considering that the railway budget got just
3 minutes of mention , he would rate the proposals at just 3.

12 Rail Business [Focus-India] March 2017


IR Appointments

IR has appointed BB Verma (centre), Adviser in Board office to look after the functions of Financial Commissioner. Fresh postings
as General Managers include R K Kulshreshta (left) on the Northern Railway and V K Yadav on the South Central Railway. Both these
officers are from the same batch of the IR Service of Electrical Engineers. M C Chauhan, General Manager, Kolkata Metro has been
deputed to look after the North Central aslo.

Competition for Innovation awards for railways


In an encouraging response to Prime Ministers call for inno- l Increasing passenger carrying capacity of coaches
vation under the Navrachna Initiative IR has launched a public
l Developing new digital capabilities at the stations
innovations challenge, with awards totaling ` 60 lakhs. The
scheme closes on May 20 and a practical deluge of about 1600 This initiative comes on top of similar ones in recent months,
entries is reported (as per the web). including the 3-day strategy meet Rail Vikas Shivir. However,
research and development initiatives under Technical Missions
Innovation challenges offered
for IR (TMIR) continues to be stalled due to procedural
l Identifying new non-fare revenue sources for IR problems and specific research projects that were to begin by
end 2015 have yet not taken off.
l Design of wagons for efficient loading and transportation
of new traffic commodities The previous government had also launched the National
Innovations Council and preparatory work was done by IR
l Easy accessibility to trains from low level platforms
also, even though no specific programme emerged till the
l New idea/suggestion to improve IR working initiative died off, unsung and hardly remembered.

Tunnelling under the Hooghly Kolkata Metro Rail

Both tunnel boring machines, now under the Howrah station progress. Civil structural work completed for all the 6 stations.
area, have made good progress of about 1500 meters with a 5 major buildings & workshops in Central Park Depot are
matching back up of 3,621 nos. (total 4,158 nos.) pre-cast completed substantially. Tunnelling for the 5,409 m Subhas
tunnel rings. These machines are expected to reach below Sarobar to Sealdah segment is complete. For the underground
River Hooghly in March 2017. All the diaphragm walls panels station at Phoolbagan, all civil structural works completed as
& barrettes for the Howrah Maidan station are complete, with also the Sealdah diaphragm wall panels and roof slabs. Column
more than 80% of roof slab casting at station box and 41 & embedded track work in Depot is in progress. For the
diaphragm wall panels in Howrah Station also completed. Sealdah to Sector-V, 5.20 km track plinth casting has been
completed. (Adapted from content by NC Karmali, General
Phase I elevated corridors :4.360 km (total 4.725 km) com-
Manager, Kolkata Metro Corp.)
pleted and girder launching on the Duttabad stretch is in

Rail Business [Focus-India] March 2017 13


I R BU D GET 20 17

Rail cleanliness, much to smile about

Mechanised cleaning, like here on the Sealdah station, is spreading across the IR system.

The 'Swachh Bharat' effort on IR , introduced by the Improvement Group(SIG) and contained parameters
Minister of Railways in his 2015-16 Railway budget which measured the availability of various cleanliness
speech, proposed a new housekeeping department, clean- infrastructure and existence & execution of processes
ing as an integrated activity, including professional agen- which were concerned with maintaining cleanliness of
cies, training staff & settimg up 'waste to energy' the station.
conversion plants in an environment-friendly manner.
Bio-toilets on trains has been an ongoing programme The rating was taken on a scale of 1 to 5 where 1 stood
with total conversion likely by 2019. for 'Poor' and 5 for 'Excellent'. These scores were then
weighted by the importance of the parameter to arrive at
This ongoing effort has now included a survey based weighted parameter score for all 40 parameters for each
dN> ^maV
ranking of major (A nd B class) stations. This survey of the 407 stations. A regression analysis was conducted
EH$ H$X dN>Vm H$s Amoa conducted by a private organisation TNS India for IRs by TNS to find the relative importance of different pa-
IRCTC (Catering and Toursim Corporation) has among rameters of cleanliness in the passengers' overall satisfac-
other things, established a wide variation in standards tion with cleanliness i.e. the 40 parameters of cleanliness
and identified some best kept stations were taken as the independent variables while the passen-
The survey has covered 75 'A1' Category stations. Pas- gers' overall satisfaction was the dependent variable.Based
sengers were the primary respondents with porters and on the footfalls, the stations were classified as less than
vendors in the platform or ticketed area and railway offi- 10 thousand; between 10 and 25 thousand; between 25
cials, who are part of the Service Improvement Group and 50 thousand and more than 50 thousand.
(SIG), also providing feedback. For every A1 category 105 stations are at Cleanliness Level 1 & 2, 166 stations
station 400 passengers were targeted for interview while are at Cleanliness Level 3 and 136 stations are at Cleanli-
in every A category station 300 passengers were targeted ness Level 4 & 5.
for interview. The sample sizes are robust to provide
results within the 95% confidence interval,with an accept- Best Zones - Western, South-Western and Southern Rail-
able margin of error at 4.8% for A1 category stations & way Zones as they have highest proportions of Level 1
5.6% for A category stations. Structured questionnaires
Areas of Cumulative
to understand satisfaction and cleanliness indicators were
cleanliness contribution (%)
used. 47 parameters, 22 pertaining to infrastructure &
enabling provisions,10 pertaining to processes & meth- Ticketed areas - 20 parameters 55
odology and 15 on the outcome of upkeep & cleanliness Waste Management - 8 parameters 23
were listed.
Toilets - 9 Parameters 16
Infrastructure & Process Indicator Questionnaire was
additionally filled by only railway officials in the Service Non-ticketed areas - 3 parameters 7

14 Rail Business [Focus-India] March 2017


and 2 stations (68%, 47% and 46% respectively). Priority similar survey was conducted among 2734 porters and
Zones - Eastern, East Central and North Central Railway vendors and 2186 IR officials as part of Service Improve-
Zones have highest proportions of Level 4 and 5 stations ment Group (SIG). Lower scores on cleanliness of toilets
(47%, 67% and 70% respectively).Cleanliness in ticketed as compared to cleanliness in other aspects across all
areas of station premises is most important for passengers, zones are noticeable.
followed by waste management practices and toilets. A
A. Importance of cleanliness parameters
Based on the passenger responses, combined with weightage contribution of different segments of stations towards
satisfaction of passengers on cleanliness
Parameters of Cleanliness Importance to passengers (%) Importance to non-passengers (%)
Ticketed Areas in Stations 55 45
Waste Management 23 23
Toilets 16 19
Non-Ticketed Area in Stations 7 13
B. Ranking of Stations
Cleanliness Levels Range of scores Number of stations
1 >750 13
2 600-749 92
3 500-599 166
4 400-499 108
5 <400 28

Top 10 stations (in descending order of scores) :


BeasNR GandhidhamWR, Vasco da GamaSW , Jamnagar WR, KumbakonamSR, SuratWR, Nasik
RoadCR, RajkotWR, Salem-SR and AnkleshwarWR.

Purchase powers redefined on IR


In a follow up of the effort to push processes down the organ- tising tenders, processing, limited source contracting etc.
isational ladder, IR had redefined the authority schedules
(Schedule of Powers SOP) for purchase and works contracting, Redefined authority (IR schedule 2017)
permitting General Managers to handle tenders up to a ` 500 Current authority Previous
Cr limit. At the Railway Board level, this redefinition removed Direct tender JAG (level 3): ` 15 lakhs
the Minsters from the purchase/ contracting process and now acceptance ` 45 lakhs
the process stops with the Director General Stores.
Tender committees
IR, may be like most very large organisations, has a culture of
issuing detailed SOPs for various actions. The Jan 2017 in- JAG (level 3) ` 45 lakhs to ` 1.5 to 3 Cr
structions spread over 13 pages must be converted to local ` 5 Cr
re-definitions by the zones/ production units. SAG (level 4) ` 5 to 200 Cr ` 3 to 20 Cr
The delegation should ideally speed up contracting but reser- HAG (level 5) ` 20 t0 40 Cr ` 200 + Cr
vations exist. A senior materials manager in a production unit
summed up that contracts are the biggest career risk, due to A tender committee for purchase/ works contracting is often
often long drawn anti-corruption (vigilance) enquiries a three person one, and their proposal must be accepted by
launched on complaints. Inaction on other matters, even gross one rank higher. Accepting authority: Additional General
mismanagement or indecision is generally not a career risk. Manger up to `500 Cr and General Manager for a higher
value.
IR does not treat major contracting decisions as strategic and
a CEO like the General Manager need never get directly IR management is hierarchical, ranging from an assistant
involved with contract acceptance only when above ` 500 Cr, Manager/ Engineer to a Board Member, 7 steps above on the
something that rarely happens in an IR zone. The new SOP ladder. General Manager is at level 6, the structure is a bit
details levels for multiple actions like direct purchase, adver- more complex Editor.

Rail Business [Focus-India] March 2017 15


I R BU D GET 20 17

Competitive ticketing and more


Ticketing
IR will work on competitive ticketing. IR passengers often face long waits at ticketing counters in
congested stations, and a ticket wait may be 1 hour long. Various efforts at automating the process
have met with at best partial success, mainly in season ticketing in suburban areas.
Long distance tickets on seat reservation are handled (about 60 %) on the IRCTC portal. This is
practically an in-house service .
IR has now waived off the service charges levied for such tickets , in an effort to help more customers
to migrate to internet booking .
The competitive ticketing plan is not defined and may evolve over time; like the case of dynamic
ticket pricing that has seen many versions and perhaps now on the verge of a discard.
The success or failure of the dynamic pricing efforts are not reported on though .

Rail Regulator
Multiple IR announcements on setting up of a Rail Tariff regulator
have proved chimerical. IR has at various stages defined its intentions,
varying from a statutory advisory body that would look at funding for
rail sector development to a pure executive body to settle tariff disputes.
With tariff revisions now effectively in IR executive domain, not
needing parliamentary pre-approval, the raison detre for a Rail
Regulator may have evaporated.

Integrated logistics
IR will work towards offering integrated logistics services, may be in
association with the private sector. CONCOR, IRs container
operations arm, already offers such services as it owns many container
and warehousing depots.

Real estate
The safety fund
IR expects to award contracts for commercial The last IR Special Safety Fund, (SRSF), a non-
development in 25 stations. As reported earlier, IR has lapsable grant of ` 18,000 Cr, was spent in an
awarded a contract for development at Habib Ganj extended period of about eight years, with bulk of
(Bhopal). The Minister has formally launched this the money being spent on signalling upgrades to
effort in an event on Feb 8. electrical (Panel) interlocking replacing the old
mechanical interlocking systems, track upgrades like
replacing the entire track structures to conform to
a standard of 60 kg rails, concrete sleepers and
required ballast depth of 300 mm. Smaller amount
went to other needs. IR will perhaps be now in a
Throughput increase huddle defining the contours of the new SSF , and
A caveat first : we hope that this was a mis-announcement, jostling for departmental allotments must already
that IR expects just a 10% throughput increase in next 3 years; be on .
that should mean a 3% CAGR . With traffic volumes currently
at near static level, and staff/expenditure set to grow at above Unlike the earlier fund that was an outright grant
the inflation level of at least 5%, that would ensure that IR from the government, this time only a seeding
faces a growing revenue red line in coming years. The equation amount has been indicated, with IR expected to
must be upset somehow but the budget documents show no raise the balance from its own and market resources.
light in this tunnel. With IR margins, having taken a beating this FY, and
likely to do so in next FY also, the actual funding for
the new SSF may not be generous. While the thought
is overdue and needed, actual funding uncertainty
is likely to restrict implementation. It is learnt that
the Niti Aayog has been asked to develop the
contours of the safety plan.

16 Rail Business [Focus-India] March 2017


CO N S TRUCTION M EG A BR IDG E

Bogibeel mega-bridge nears commissioning

HK Jaggi , General Manager , North East Frontier Railway (construction) leads


a specialist IR organisation responsible for various national rail projects for North
East connectivity .He has led the Boghibeel team to a likely construction completion
by the year end and commercial operation in 2018.
An IR Service of Engineers Officer, Jaggi was earlier Adviser (Land) in IR Board
and has developed the under-execution station development programmes. He will
superannuate in May 2017.

Bridging the Brahmaputra has been a sign of honour for ical construction. At present the river is spanned by 4
bridge engineers in India, with the first recorded for BC bridges: Saraighat, Guwahati (dual mode), Jogigopa for
Ganguly (Chairman IR Board 1970-72) who, early in his rail only and two road-only structures at Guwahati and
career, was a key project engineer for the Saraighat road Tezpur.
and rail bridge that connects Guwahati. The East-West
Now the king of them all, the dual mode 4.9 km bridge
flow of the river across the Assam plains neatly divides
at Boghibeel near Dibrugarh will see the first trains moving
the region into the North and South banks; it is not
across it in 2018. And it will be the longest rail/road bridge
uncommon for people to indicate their residence as being
in India.
part of the North or the South bank. This was followed
by the Tejpur road bridge, again executed by a railway The construction of this bridge was a part of the Assam
engineer, RR Jaruhar, later a member of the IR Board. political accord in 1985 but that was not converted to a
But in the East, the river remained unbridged, even though project sanction till 1997. Years went by with little activity
it is said that the British had visualized a bridge at a Di- till the project was declared as a part of the National
brugarh location way back in 1929. In any case, technology Railway projects and after which funding has ceased to
and resources available then would have prevented phys- be a major issue. Physical construction in this logistically

The Brahmaputra river follows a tortuous course, spreading wide in full flow (satellite imagery), and bridge sites like that Bogibeel require man-made restrictions. Map
alongside shows the various road and rail links that are a core part of the bridge project.

18 Rail Business [Focus-India] March 2017


CO N S T RU CT I O N ME GA B R I D G E

difficult area, and the inevitable prob- His at-site colleague, Milan Singh,
lems in IR contract management did relatively new to his position as the
hamper progress, that is in any case site in-charge, acknowledges this re-
slow due to the site not being amena- source.
ble to work except in the Nov
Kamei joined IR 10 years back, was
March period. Contract indecisions,
posted for a short while to Saharanpur
mainly by the Board, slowed down
as a track engineer and transferred to
work; it is said that some considera-
NF Railway soon thereafter. Track
tions delayed a contract for two years.
maintenance at Barsoi (Bihar) was
The floods in 2012 that washed away
tough but not exciting. He is now a
the guide bunds did not help either.
know-everything engineer on the
Bheel, a lake in local script, is a village project, depended upon for accurate
and the river at this location was about delivery and information. He can well
10 km in its peak flow. Reportedly 4 think of the many large bridges that
locations were surveyed at the project will span the North East in coming A Bogibeel team at the project site : (L to R) Milan Singh, In-charge
draft stage, and the Boghi village site years. Deputy Chief, A Majumdar, Deputy Chief Design, Rakesh Kumar Singh,
found (should we say that!) least Executive HCC and S Kamei, Deputy Chief (NFR)
Key persons who visualized the
bothersome. Engineers found this lo- ing across the river to the recently
project and delivered the key layouts
cation amenable to restricting the ex- gauge-converted Murkong Selek line
have included KK Gupta, associated
panse through dykes and now the riv- in the neighbouring Arunachal state.
in design (ca 2001), VK Madhukar
er is divided in non-flood season to This track work, completed in 2009,
(2002 -08), SC Rajak (2008-11). The
two channels, with the South channel is now handling passenger trains reg-
project concept was based on the in-
being the active one. This has been a ularly. The bridge structure, built to
itial hydrological surveys conducted
boon for the location but has created IRs BGML standards, can handle 25t
in Roorkee, work coordinated by
many a material flow problem as var- axle load trains and is future fit. Ram-
RITES experts A Garg and AK Math-
ious aggregates and steel structures boll, Denmark carried out the super-
ur. RK Dayal handled the studies for
have to be trans-shipped to the river structure design through RITES, with
river survey and design of the river
island, that has become a local port proof checking by the German com-
training and the guide bunds. This is
of call. pany Anwarikar. The superstructure
a key part of the project design as the
A bridge man in the making river has been restricted to about 5 should cost about ` 1300 Cr.
Unlike some of the iconic projects km, half of its natural flood plain. After Now that the project completion is
elsewhere in the world, which carry the dyke and guide bund constriction, in sight, Pandit recounts a few occa-
the names of their key designers, IR the river is now restricted to 2 main sions of doubt and despair. On the
projects remain faceless, or may be channels, with the South channel that happier front, he could shift to the
get attributed to a political figure. holds 10 piers being the active one. use of spherical bridge bearings, in-
Saraighat bridge does not even carry The uniqueness of the bridge, both stead of the traditional POT/ PTFE
a plaque to acknowledge the pioneer- in design and execution, has ensured ones. Pandit assesses that the spheri-
ing work done by BC Ganguly. Bo- a steady stream of visitors and week- cal bearings, lesser in number, should
gibeel is no exception and it takes end picnickers, partying at the sand be practically maintenance free for
quite some effort to figure out the key island between the two river streams. the 50-year assessed life.
designers and project managers asso- Each trainee engineer of the IR Serv-
ciated with the project. We venture a A constant issue in such projects is
ice of Engineers must spend training the ability to locate and retain skilled
few names, even at the risk of being time at the project. Some of these
less than accurate. One name men- workforce. A walk through the fabri-
would become key persons in IR con- cation and launch yards reveals the
tioned is RVR Kishore of HCC, the struction expertise in future and four
superstructure contractor, who visu- large number of welders and riggers
young executive engineers are already required by HCC for this project.
alized the design and execution con- working at the bridge site, ensuring
cept. Quality assurance is mandated at each
quality and proper scheduling. step and availability of qualified man-
From our conversations during the The top team power from internal resources was
site visits, three IR engineers of vary- practically impossible. NFR has sup-
The bridge project has seen signifi-
ing experience and age have been as- plemented their resources with con-
cant progress under A Pandit, Chief
sociated with the project for a decent tracts for EPC like sourcing, ensuring
Administrative Officer who has been
length of time. And their commit- that progress is never hampered.
associated with the project since
ment to the project stands out as they
2011. Pandit recounts that he was Mohinder Singh, Chief Engineer,
talk of the progress and the challenges.
impressed by the project contours now nine years on the project includ-
Let us start with the youngest, Sahem- when he was Divisional Railway Man- ing at the project sites, too has pro-
lung Kamei, a Deputy Chief at the ager in Lumdig. The project involves gressed in a long association with the
project site. His IR seniors proudly the 4.9 km long bridge on 39 piers as project. Earlier IR engineers were not
say that Kamei was born on the well as a 44-km long track work that too conversant with all- welded gird-
bridge, a total untruth but that con- provides an alternative route to Di- ers, as rivetted girders were the
veys the young engineers association. brugarh/Tinsukhia besides connect- norm. Singh adds that this is bridge

Rail Business [Focus-India] March 2017 19


CO N S TRUCTION M EG A BR IDG E

Substructure Codes and empirical for end spans).


limits, working out foundation mini-
ma, foundation grip lengths, stability l The connecting rail network in-
in extreme conditions etc. The de- cludes new stations at Dibrugarh
signs have proven to be effective but (the old one carries the Town suf-
the hard tests will follow under full fix) and New Tinsukia on the South
traffic and river flow. bank main line and two crossing
stations on the North bank.
Key technical features
The remaining works
l Mean river flow: 3 m /sec., Max
river discharge: 73,000 cusecs Pandit expects the last train of 10 gird-
ers to be in place by August and the
l A high flood mark at about 103 m, track linking by end of the year. With
Ajit Pandit, Chief Administrative Officer and Mohinder Singh, Chief Engineer
head the construction team that is all set to deliver on this national project.
with a minimum level 98.3m in the completion of the bridge launch, steel
active channel. Span arrangements: sleepers and tracks will be installed.
construction without a single rivet, a 32.75 m: 2 end spans, 125 m: 39 Completion of the girder launch will
modern concept that could set pat- spans also permit completion of the road
terns for the future.
l Substructure: 42 double-D Well via ducts, few of which have been held
Project delivery foundations, 16.2 m x10.5 m and back to permit movement of material
The project has a slow growth history, twin circular hollow piers 5.3 m and equipment by HCC. Two decks
a trait it shares with most large IR external dia of the road way have now been cast.
projects. The project cost was esti- Kamei hoped that with the three sets
mated at ` 3230 Cr, since revised to l Guide bunds: North: 2.7 km and of deck shuttering now available (may
` 4857 Cr. Sanctioned in 1997, with South: 2.1 km be increased to 4 soon), he expects
a ceremonial foundation stone in l Flood dykes: 9 km upstream and 7 the road surfaces to be ready by year
April 2002, progress was symbolic, km downstream on both banks end too.
with just about ` 700 Cr spent till the
grant of a national projects status in l Road links: 11.3 km on the South The missing blocks of the giant-sized
2007. Expenditure in last 5 years has and 13.3 km on North banks; road puzzle are all falling into place.
ranged in ` 400 to 500 Cr, peaking at via ducts of about 0.8 km will con- Key construction companies
` 512 Cr in 2015 FY. nect the road-cu rail bridge to the
The bridge contract has been execut-
state highways 37 and 52.
For A Majumdar, Deputy Chief for ed by well-known Indian firms Gam-
designs, the bridge has presented mul- l Warren type truss without verticals, mon and HCC, with Gammon deliv-
tiple challenges of meeting various IR 12.5m high, 10 panels per span (3 ering the substructure piers and HCC

Hell has no fury like a river in spate


forgive. This came about even as the guide bunds built in the
previous season were also washed away forcing the bridge
designers to increase 4 piers to the bridge plan. The rebuilt
was done with tougher tethering cables and a lot of hope.
S Kamei recalls that during the 2012 floods, most surviving
animals in the area found sanctuary on the guide bunds and
the dykes of the bridge project. That was fine till a couple of
young elephants strolled across rushing too to set up panic.
Kabul Majumdar, then an Assistant Engineer recounts that a
steam loco hauled train near Udalguri on the North bank
Murkong Selek MG line was washed away due to a bridge
collapse in 1980 during a flood in a Brahmaputra tributary.
The steam loco was gulped down by the river in its fury and
lay embedded in the nether land till a barely visible portion
of the chimney pushed salvage crews to recover the machine.
Three caissons (a watertight retaining structure used as a Then in 1982 two ferries tethered at Pandu were washed away
bridge pier) were washed away in the 2012 floods on the near to the Bangladesh border in 1982 but could be recovered.
Brahmaputra, in just the second working season, and have
not been located till now. These massive steel fabrications The Bogibeel project must guarantee no-recurrence for the
should be lying somewhere merged under the Brahmaputra expected 50 + years life time of the bridge. Therein lies the
sediment, a mute reminder that a river in spate does not easily skill and the metal of the project designers.

20 Rail Business [Focus-India] March 2017


CO N S T RU CT I O N ME GA B R I D G E

JV currently executing the final phase girders are joined into the girder the road decks have been finished too.
of the superstructure. Each pier is a train by special blocks at the bottom Perhaps it would have been better
mammoth hollow cylinder of steel members and these are removed after that the fabrication workshops were
and concrete, built step by step at the docking. split between the North and South
final location, with a max 58.6m banks but that was not feasible due
depth, uses about 65,000 bags of ce- The fabrication workshops are any- to the topography at the North bank.
ment and 470 t of steel reinforce- thing but small, considering that each
ments. Site engineers pointed out that girder tops at around 1700 t weight,
not all piers were trouble free and and the intermediate girders measure
corrections in tilt were carried out, a out to 125 m. The girder fabrication
difficult task in the middle of a river. is staged across 2 130 m long laydown HCC , the major Indian construc-
30 of the 39 girders are now in place. bays and 2 vertical assembly sheds tion company , leads the super-
(300 m). Six gantry cranes (40 to 80 structure construction consorti-
Pandit indicated that the girder t) move the assemblies between these um , in partnership with DSD
launching follows an incremental aligned bays. Steel Group Germany and VNR
method, a take-off on a Scandinavian
Pandit explained that the girders are Infrastructure .HCC counts the
method, wherein the girder fabrica-
all fabricated from plates only, avoid- construction of the historic Bhor
tion bays are aligned with the bridge
ing the use of rolled sections. The Ghat (the Western Ghats route
in horizontal and vertical levels and
entire structures weigh in at 77,000 t to Mumbai) amongst its earliest
the girders are pushed out one by one,
of steel, mostly of high strength E450 rail projects. Also on the showcase
forming a train of 10, with suitable
plates ranging from the wells to the are the bow string arch girder rail
launching or end noses assembled
reinforcements and the girders. Steel bridge on the Godavari , Kolkata
with high strength bolts (these are
sleepers and some cross beams are and Delhi Metros, the Pir Panjal
removed once the girder train has
fitted on later to minimise the girder rail tunnel that links the Kashmir
docked in its final place). Pulling
launch weights. We could not help valley and the now iconic Bandra
mechanisms installed on piers 1, 11,
21 and 31 pull the train cautiously asking if the road decks add to the -Worli Sealink cable stayed
over specially installed flat bearings strength and the answer was a definite bridge. The Bogibeel site, now at
on the pier caps. These bearings are yes, with Pandit affirming that design its concluding phase, resources
replaced by the spherical bearings at considerations would not permit about 2600 people in various ac-
their final location. For pulling, the opening the bridge to rail traffic till tivities.

IR continues to be in the news and the reasons are many. It


touches every Indian, being the lifeline of the country. The
suggestions to reform are unending and vary from budget
merger, improvement in services with a price tag, accidents or
underinvestment. The investment issue has caught fancy glo-
bally with the coming up of High Speed train and the Dedicated
Freight Corridor. Railways look towards private or non-
Government funding to take a quantum leap.
Messe Frankfurt now plan to organise the 2nd Edition of Rail
India Conference & Expo on May 18-19, 2017 in New Delhi
to deliberate on these current issues and discuss action plans
for the way forward. This conference will showcase what IR
is doing and what is its vision along with the path for the
ambitious goals. And to achieve all this, innovative ideas, be
it revolutionary, are welcome. This is what this conference
shall seek to achieve.
Arunendra Kumar, Former Chairman, IR Board.

Media Associate

Rail Business [Focus-India] March 2017 21


L O C O M OTIVES C HITTAR AN JAN

Chittaranjan set for growing electrification


Vijai Prakash Pathak, General Manager, Chittaranjan Locomotive Works, an
officer of the IR Stores Service, was earlier the Controller of Stores in Diesel
Locomotive Works, Varanasi. He joined IR in March 1982 after graduation
in civil engineering.
Pathak has held various important IR positions including Controller of Stores
in Rail Coach Factory, Eastern, North Western, North Central Railways and
Railway Electrification. Pathak has been trained in Austria & Germany in
Supply Chain Management.

This is a time for CLW to consolidate on its high produc- also likely on future series.
tion levels. We have come a long way to establishing
Khatri, Chief Electric Engineer in charge of loco produc-
internal capacities for 300 locos per year, on top of a good
tion and his young colleague Agarwal, SEE are hopeful
vendor base for traction equipment and various sub-
and may be a bit worried that the need to dispatch the
assemblies. Sourcing for many key components like loco
near 100 locos in three months, to make up the 300-loco
frames, bogies and other fabricated items now comple-
target, may be a little too much. The manufacturing cycle
ment the in-house capabilities. In coming year, these will
is around 36 working days and good back up progress,
be incremented in numbers as well as in technological
visible in the series of locos waiting in the stabling lines,
spread. VS Pathak, General Manager, Chittaranjan Loco
waiting for final inspections and fittings, give them confi-
Works who has taken over in Dec 2016 has quickly de-
dence. The year-end pressures are near normal and they
veloped his outlook for the coming years.
are confident of coping.
Internal manufacturing is well established and growing,
Manufacturing productivity is being continually advanced
as in the Traction Motor manufacture where a 17% in-
and Khatri mentions a series of these, like better harness
crease (to 914 three phase motors till Dec 2016) has been
manufacture to avoid wiring errors and service problems,
achieved and only about 20 % motors are sourced from introduction of better pipe fittings and the like.
vendors. The 2016 -17 manufacture has included 195
IGBT traction based locos and a full shift in coming years Manufacture in CLW has proven very cost effective for
is already in force. Pathak is also sure that the various IR, as it gets modern electric locos at practically less than
technologies will be incorporated in full. half the price quoted for the Dedicated Freight Corridor
locos, a tender that has been dropped for now. Transfer
The assembly unit at Dankuni (near Kolkata) is also prices: WAG 9: ` 13.5 Cr, WAP 7: ` 13.8 Cr and WAP5
operational now, with 7 WAG9 H locos commissioned at ` 14 Cr). Progressive vendor development has now
so far. Dankuni gets its parental feed and guidance' from restricted direct CLW imports to only about 2.5% of the
the mother plant and has developed well. purchase value. The partial shift to electric locos in Vara-
Production plans for electric locos nasi plant as well as the likely supply from Alstom Indias
JV in 2019 will be adequate for anticipated electric loco
CLW DLW Varanasi needs.
2016-17 298 2 All this has been achieved based on efficient contracting
2017-18 325 25
2018-19 350 75 A health resort?
The drive from the Chittaranjan rail station to the
The product mix in 2015 -16 was WAP5: 17, WAP 7: 58, CLW housing colony and the factories is transforma-
WAG9: 140, WAP 4: 30, and WAG7: 35. Manufacture tional, from the typical station traffic chaos to the
of WAP 4 and WAG 7 s has since been discontinued. The many lakes, widespread greenery and the ambience
freight locos will be fit for the Western freight corridor of a health resort. One cannot foresee the factories
operations too, as one of the pantographs fitted is a high- while passing the lakes that abound with migratory
reach design that is needed for the higher level of the birds too. After all, this was a typical tribal area before
overhead 25 kV supply for double stack container opera- its conversion to a steam loco factory in early 1950s.
tions. Fitting of H type couplers on passenger locos is

22 Rail Business [Focus-India] March 2017


LO CO MO T I V E S CH I T TA R A N J A N

procedures. All purchase tenders are The power of social media


now transacted through an electronic On a sunny week day, the 31875
portal under the Procurement and WAG9 H was getting a good
Efficiency (PACE) programme. This shower, to check if even a single
has also added a transparency layer droplet evades the covers and the
to the large volume public procure- sealing rubbers into the cubicles
ment that CLW handles. housing the on board electric
Technical improvements equipment. A meticulous check by
an inspector showed none, earning
A host of modern features are on trial,
a tick on the inspection sheet and
ranging from initial application to
a gate pass for dispatch. And the
series inclusion:
30511 was happy to move for its
l Train Communication Network turn at the shower bay.
OP Kesari, Senior Executive Director, RDSO
Compliant Vehicle Control unit, The shower test room is rather is responsible for various technical
developed indigenously by C- new, having been added in last few
developments on electric locos. The CLW
design and development team coordinates all
DAC, already on two locos, this will months in response to a social me- projects with him.
be expanded as the technology has dia post by a loco driver which
been licensed to six Indian devel- announced last year. Locos under
showed water dripping inside a manufacture are instead provided
opers. This would overcome the loco in service. CLW QA and man-
software compatibility issues faced with a replaceable roof cover that will
agement took that seriously, com- permit retrofitment. This regression
with the OEM. missioning the new high pressure has been forced by the poor service
l IR has an ambitious plan for devel- nozzles that simulates heavy mon- reliability of the ACs fitted earlier.
oping a 9000 hp electric (current soon shower. And a key new addi- Similar fitment has occurred on the
range: 6000 hp) freight loco. Pre- tion to the quality checks which a diesels ex DLW. Unconfirmed indi-
tendering processes completed in- new loco should undergo. cations are that the DC power supply
clude preparation of functional The cab air conditioning used for these units may be the root
specifications and suitable interac- of the problem. Some trials with DC
tions with likely traction system CLW is not fitting any driving cab air
conditioners, even though this was supply units have been mentioned.
vendors. The prototype is expected
to roll out in early 2018.
l Parallel development of bi-modal The family shoot
(diesel and 25 kV electrics) loco- Photos WAG 9 *H WAG7 WAP 5 WAP 7
motives by CLW (5 loco manufac- freight passenger passenger
ture sanctioned) and DLW is in
hand. IR is trying to develop two hp 6000 5400 5400
versions at CLW and DLW. This Bogie type 6 axle 6 axle 4 axle
has also progressed to functional
specifications and expression of in- Starting tractive effort 51 44 26.3
terest by traction system vendors. Max service speed kph 90 100 160
l Crew and voice recording for loco *= heavy haul
driving crews

The CLW Team (L to R): A Agarwal, Chief Public Relations, BR Kanwar, Chief Engineer, Srikant Rai, Controller of Stores, S Bhattacharjee, Financial Adviser, S Toppo,
Chief Mechanical Engineer, VP Pathak, General Manager, BB Singh, Chief Electrical Engineer, A Kumar, Chief Vigilance Officer, AK Majumdar, Chief Medical Officer, G
Sreeniwas Rao, Chief Personnel Officer and PP Raju, Secretary to GM.

Rail Business [Focus-India] March 2017 23


L O C O M OTIVES C HITTAR AN JAN

The bogie manufacturing and assembly shops form a supportive base for loco production in CLW.

IRs 200 kph project Samir Topo, a recent addition to the green sand moulding process.
The WAP7 loco maximum speed can CLW cadre, chips in with his plans to Switch over to no bake moulding
be enhanced to 200 kph by a change ensure a steady growth in back up process in a phased manner from this
in the wheel-motor drive gear ratio. supplies for increasing production. year could lead to a complete shift by
This will be required for IRs 200 kph The bogie fabrication, heavy machin- late 2018. An initial six items are
rake under development in Kapurtha- ing including for traction motor planned for switch over between June,
la plant. One loco based in Ghaziabad frames and the steel foundry are key 2017 to January18.
shed with the modified gear train, team mates to the loco assembly proc-
Narrow gauge wheels
sourced from the well-known Ger- ess.
Casting of NG wheel sets for the Ka-
man company Henschel, has shown The steel foundry is presently casting lka-Shimla section had been posing
good reliability on run (at the lower 14 different types of products, pre- challenges with recurring defects de-
speed). dominantly with a conventional tected during non-destructive testing.

Remote Diagnostics Current operations


GPS/GSM/CDMA SMS
Antenna (As needed) Holding Sheds WAG-9 WAP-7
CONNECTIVITY

Lalaguda 1 17
INTERNET

SERVER BROADBAND
Ajni (Nagpur) 6 2
ROOF EQUIPMENT
Gomoh 7 0
VEHICLE CONTROL UNIT
Serial Data
Fibre optic

110 VDC
MVB DIA Ghaziabad 0 4
Outpur card
Bhilai 1 1
Data from MVB
REMOTE DIAGNOSTIC
EQUIPMENT Fibre optic - DDS Extraction from DIA
Howrah 0 1
WITH MVB GATE WAY
Total 15 25

Communication technology can be utilized for condition monitoring in electric locomotives, with real
time single window reporting of key parameters like temperatures of bogie bearings, converters, control
equipment etc.
The system collects the status of the locomotive or faults developed transmitting to a Remote Server base
station server on a wireless network. The equipment is MVB based, connected to the WAP5/ WAP7/
WAG9/9H classes via an associated roof mounted unit of multiple network interfacing devices (GSM &
CDMA each) and a GPS receiver.

24 Rail Business [Focus-India] March 2017


LO CO MO T I V E S CH I T TA R A N J A N

l SCR- 5 Pairs of WAG7s: mine to


power house segments in Singare-
ni- Bhadrachalam (67 km)
l South Eastern: WAG7, 1 pair &
WAG9, 2 pairs in the Banspani
Dongapsoi Adityapur (Tata
Steel) iron ore belts (152 km)
l South East Central: lone WAG7
pari on Korba-Nagpur (504 km)
l East Coast: WAG7 x 3 pairs on 192
km Talcher-Paradeep Port runs
Head On Generation (HOG)
Nine pairs of trains serving New Del-
hi, Mumbai, Kolkata terminals, Jaipur,
Ahmedabad, Chandigarh and Chen-
nai are saving around 40 Cr per year
PK Khatri, Chief Electric Engineer (centre) responsible for loco production with his lead in terms of fuel and maintenance cost.
assembly line managers Amit Agarwal and BS Meena.
Modification of coaches /power cars
and production of WAP 7 locos is in
Recently switch over to no bake absorption and damping were provid- full swing. The WAP5 s, not fitted
sand process has encouraging results ed to reduce the noise level that re- due to space restrictions on these 4
with the number of defects reduced duced from 90 to 84 dB. These chang- axle locos, is sought to be corrected
by 70%. es are being enforced during periodic by integration of the main traction
overhauls. converter with the HOG converter,
the manufacturing shops have been the
work horse. Water closets a development likely this year.
Besides catering to all the loco wheel A specification for water closet mod- (Content support from MK Gupta,
requirements, these shops fabricate ule with vacuum evacuation and Chief Design and Development, Vipin
and machine 3 phase stators for the anaerobic bio-dischargeable systems
Kumar, Deputy Chief and the Public
traction motor production. The 2016- for WAP-7/WAG9/9H defines an
Relations team of A Agarwal, Chief and
17target is for 720 stators, enhancing intermediate vacuum toilet equipped
Mantaar Singh is acknowledged).
to 1200 in 2017-18. This has been with computerized control. This
addressed by increasing the work sta- module will work on 110V DC supply
tions and the machining increased and air pressure available in loco.
from 3 to 4 per day. Toppo is satisfied A crew voice & video recording will
that 100 stators have been machined ensure effective and tamper proof re-
for the last two months. The plan is cording of activities in locomotive
to undertake the entire stator fabrica- cab. The salient features are a mini-
tion and machining for 350 locos by mum last 90 days data storage on
2018-19. Plans exist to augment ca- FIFO, time and location stamping,
pacity by acquiring new assets viz, analogue and digital video inputs, ex-
CNC Universal Horizontal Machin- port of the desired portion of clipping
ing Centre & Co-ordinate Measuring DVR with at least 8 cameras input
Machine. configurable as IP/Analog and mini-
Noise level in the loco cabs mum four audio inputs.
during run Improving throughput is achieved by
Type Measured running long haul trains and the con-
value dB cept of the distributed power was de-
veloped. On the Distributed Power,
WAP-5 (three phase) 80 Wireless Control System (DPWCS)
WAP-7 (three phase) 83 equipped loco pairs have been devel-
oped; up to 4 remote locomotives can
WAP-4 (conventional) 90
be connected anywhere in the train
WAG-7 (conventional) 89 consist, with the slave locomotives
synchronized with the lead one.
US regulations on cab noise limit av-
erage to 85 dB. Air sealing, sound At present 12 pairs are working:

Rail Business [Focus-India] March 2017 25


L O C O M OTIVES PATIAL A

IR diesel locos set for a Patiala makeover


Engine stop is a system which automatically shuts down
the main engine when the locomotive is in idle state for
more than 10 minutes and restarts the main engine when-
ever the train driver desires so. APU is a small diesel
engine coupled to a baby compressor and an alternator
along with control circuits to maintain the main reservoir
pressure between 8 to 10 Kg/cm2 and keep the locomo-
tive batteries in charged condition.It has huge fuel saving
potential, saving fuel @ 23 litres/hour during idling.

The balance 26 Multi-genset Locos (from an initial


order of 28) are scheduled for assembly and supply in
next FY. The first two locos were built using NRE
gensets with 3 gensets each on top of the standard IR
shunting loco WDS6 motorised bogies and have per-
formed generally well in Itarsi yards. The fresh lot will
however be built with 2 gensets each only, keeping in
view the power demand faced in practice in IR yards.
SK Luthra, Chief administrative Officer, Diesel Modernisation Works, Patiala is hopeful
of delivery on the various improvement projects for the IR diesel loco fleet.
Apart from bulk order for the power/traction equip-
ment of 24 loco sets on NRE USA/Daulat Ram (two
manufactured already), development orders for two
The Diesel Modernisation Works (DMW), Patiala is now
loco sets each have now been placed on BHEL &
a key role player in IR plans for upgrading its diesel loco
Medha. Luthra indicated that the new contracts are
fleet. That is a major shift from its defined role on its
for the full kits, including the gensets and this change
inception in 1980s when it was a supplement to the spares will avoid the supply scheduling and initial performance
supplies for the ALCO/DLW fleet from the parent plant problems faced in the prototypes. IR has now sanc-
in Varanasi. DMW is now adapting its product lines to tioned another 50 locos, indicating satisfaction with
new designs, moving away slowly from the ALCO to the the concept, bringing the genset loco fleet to a healthy
EMD locos. 78 locos in a few years time.
It is easy for SK Luthra, Chief Administrative Officer to
list highlights from the year: first time loco manufacture The first loco with Common Rail Direct Injection CRDi,
for a non-IR customer, rebuild of 1800 hp WDP1 passen- already in last stages of rollout and commissioning in Feb
ger locos (3 so far), major shift towards repair & rehabil- 2017, will be followed by 15 more in next FY. This is a
itation of EMD loco traction machines and overhaul & refinement of a prototype modified by RDSO two years
support to the MEMU traction machines. The ` 1500 back and put through extensive trials on South Central
Cr annual turnover comes from supply of sub-assemblies Railway.
(19 %), spares (25%), rehab of locos (50 %) and new Development of liquefied natural gas (LNG) powered
locos for other customers (8 %) (indicative data). loco in association with RDSO was tendered for but has
High on fuel savings not succeeded as many technical issues remain unresolved.
Also, the ALCO design is now near obsolete and IR
Luthra scans the many technological changes which
electrification is making good progress, inhibiting fresh
DMW is introducing mainly during the rehab of the development investment by the industry.
diesels. The Auxiliary Power Unit APU, that reduces fuel
consumption due to a lower engine output and shut down The issue of adequate engine cooling has been addressed
of the main engine during idling, is now being proliferated, by augmented cooling circuits using higher capacity radi-
with all new + rebuilt ones leaving DMW and Parel (new ator, cooling fan, aftercooler core etc. The prototype loco
WDS6) with APUs. Under a project for retrofitment on is now operational in New Katni and the upgrades will
500 locos, contracts are awarded and managed centrally be proliferated.
from DMW. Multiple sourcing of APUs is being encour- Luthra added that DMW needs to continuously identify
aged to hasten implementation and 3 new sources have new technology increments and two such projects are in
development contracts in addition to MEDHA. This will hand: to replace mechanically driven auxiliaries by electric
come handy for faster retrofitment in the entire fleet of motors and retrofitment of a more fuel efficient and
ALCO & EMD types later when a proposed ADB funded emission compliant engine. Both are under development.
project to finance cuts in.
Adding to the fuel-efficient chain will be the ABB VTG
APU (with ACES) Turbo & Miller cycle turbochargers. These developments
Auxiliary Power Unit APU with Automatic control of are well in hand with the proto turbochargers already

26 Rail Business [Focus-India] March 2017


LO CO MO T I V E S PAT I A L A

An ALCO 16 cylinder, 3300 hp engine set under assembly (left) and CNC based precision machining on a wheel set.

supplied and in last stages of matching attended since the 2011 start. Manu-
at the RDSO Engine Development facture /rehabilitation of AC Traction
laboratory. These futuristic locos machines of HHP EMD loco is being
should be commissioned within the stepped up gradually.
next 6 months.
New rehab line
Electrification and EMD The first WDP1 loco rehabs include
Luthra rules out any worries about many systemic modifications like on
reduction of workload on these ac- the under frame to suit side bearer
counts. In fact, he stresses that DMW assembly and modified lateral and
has the go-ahead to prepare for EMD vertical dampers, modified 4 motor
loco rebuilding (18-year schedule) Bo-Bo Bogies with rubber springs in
for which tooling & facilities are being secondary suspension, crew friendly
actively procured. A new EMD high driver cabin, modified nose and radi-
hp engine test bed has been sanc- ator compartments & maintenance
tioned under the 2017 budget while friendly engine hood & doors. The Samarendra Kumar,
Chief Mechanical Engineer
approvals for less value equipment air circuit now has self-cleaning iner-
are already available. DMW expects tial filtration. The brake circuit now
to handle complete EMD Loco in FY comes with an up-graded air com-
2018-19 even as a beginning will be pressor for a pure air brake and possi-
made in 2017-18 for bogies & engine bility to support computerised con-
power packs. 3 phase traction ma- trols like the CCB.
chines are already being overhauled The engine has been equipped with
in DMW (342 AC traction motors) 3RV cylinder liner kit, microprocessor
till Jan 2017 against 176 last year, 11 based control system with new con-
alternators over 7 last FY). tactor compartment; micro-controller
The first 3100 hp locomotive based governor, mechanical bonded
WDG3A for National Thermal Pow- radiator and plate type enlarged after-
er (not an IR company) was rolled cooler and many useful features
out in March16. So far, 11WDG3A adopted from the EMD designs.
locos have been sold by DLW and Three locomotives have already been Bimal Rautji, Controller of Stores
delivered by DMW to various such rebuilt with a plan to progressively
customers. The two units had decided re-build the entire fleet of 69 locos. A
to work in tandem for external cus- smaller fleet of 28 WDP3 passenger
tomers through an MOU last year. locos, to be tackled next and a begin- Delegation of purchase powers
IRs Lower Parel, Mumbai workshop ning will be made in FY 17-18. has helped pace of ordering/ de-
delivers the standard WDS6 shunting cision making. Cases in point are
locos and all key sourcing is handled Cast Iron Engine Blocks high value tenders for Multi-
by DMW. The ALCO-OEM engine blocks are genset loco parts, engine blocks,
essentially fabricated, using some motors etc., as all such purchase
Traction machines shop has been re- heavy forgings.
habilitating high hp (HHP) EMD al- decisions can now be taken by
DMW management.
ternators since 2008 and has success- Cast Iron engine blocks have been
fully rehabilitated 47 machines. 900 under development since 2010 and
AC Traction Motors have also been various technical and procedural is-

Rail Business [Focus-India] March 2017 27


L O CO M OTIVES PATIAL A

Loco rebuild facilities, a key to DMWs main workload.

sues hindered earlier application. Six reported within 180 days of rebuild are reduced substantially too.
of these blocks are now operational (20 till Sep 2016 against 68 last year).
Modular HVAC unit for Cab
for about 18 months and ten more
DMW has adopted Epoxy cum Poly- DMW has undertaken provision of
under fitment. These have been
urethane painting as PU paints offer Modular HVAC (Heating Ventila-
sourced from Push Foundry, China excellent weather resistance, light-
and regular supplies at around 5 per tion and Air Conditioning) units on
fastness and UV protection to exterior Alco locomotives during rebuild to
month are expected now onwards surfaces.
completing the supply of 50 in next maintain interior cab temperatures
FY. IR expects to meet the future de- CRDi in a comfortable range during high as
mands of new ALCO engine blocks Common Rail Electronic Direct In- well as low temperature weather con-
partly with this casting design and a jection system is the state-of-the-art ditions. It is a split type AC with pow-
tender for 150 numbers is said to be technology that replaces the existing er source located in clean air compart-
due in April 2017. Indian companies mechanical fuel injection system with ment. Prototype units are under
like ISGEC Yamunanagar are also high precision control of Fuel injec- testing, and first locos will be in serv-
said to be interested in developing tion in Diesel Engine. Its high- ice in this summer season.
these intricate castings. pressure pumps maintain fuel oil pres- High capacity radiator cooling
sure in Common Rail at 2000 bar DMW is fitting high capacity Radiator
Quality improvements (from 300bar earlier) and an ECU cooling fan with 1,50,000 CFM air
Higher radius camshaft segments, im- (Engine Control Unit) squarely con- flow from its 8-blades (6 on the con-
provements in gear manufacture trols the speed of engine through pre- ventional fan).
processes (including external consul- cise control of fuel injection timings
tancy from CIIs Institute of Quality), of solenoid operated injectors. Its The increased air flow capacity with
and improvements in engine block main benefit is in saving fuel by 5 to less power consumption improves
repair methods have yielded signifi- 7% and reduction in harmful emis- radiator efficiency and reduces the
cant improvement in service failures sions by 15 to 20%. Mechanical parts thermal loading of engine.

I Mech E Railway Division special event in India


IMechE Railway Division successfully continues to further its objectives of
reaching to the engineering fraternity in India. Richard East, Chairman Railway
Division spoke on Sustaining the Future at well attended event in National
Rail Museum, New Delhi in Feb 2017. The participants included many young
members including from the student chapter of SRM University, Ghaziabad.
Post privatization, the UK rail industry has recorded significant growth in
passenger numbers while freight traffic has remained flat, or grown marginally.
East highlighted the importance of investment in the rail industry in a manner
which sustains the future. (L to R: Ravi Kochak, Allwyn Peter, Richard East
and Pradeep Agrawal)

28 Rail Business [Focus-India] March 2017


H I G H SPEED OP INION

Getting ready for High Speed trains


As India enters the High-Speed Railway (HSR) era, it is continue to work in respective fields throughout their
important to focus on actions that would ensure rapid professional career. It is equally important that localization
technology assimilation and development as well as local- of manufacture is maximized both for technology absorp-
ization of manufacture. It need be emphasized that the tion and reducing costs as well as for creating jobs in the
vision for Mumbai-Ahmedabad HSR should include de- manufacturing sector.
ployment of a dedicated large group of engineers to study
Semi-high speed trains
and absorb the technologies related to standards, specifi-
cations, design, construction, manufacture and mainte- Railways in the speed range 160-200 kph, designated as
nance of such railways. These engineers should be re- Semi High Speed Railways (SHSR), are generally for
quired to work on long term basis in proposed institutions, mixed use with passenger and freight trains. Upgrading
namely NHSR Corporation (for project implementation), existing mainline trunk routes in India to make these
HSR Design Unit (for assimilation of HSR technologies capable of operation at 160-200 kph provides a relatively
and design of various project elements) and HSR Testing lower cost option for improving medium and long distance
and Commissioning Unit (for quality control and com- passenger services. Priority could be given to routes where
pliance with technical standards and specifications). Lo- the Dedicated Freight Corridors (DFC) are under con-
calization of manufacture of light weight EMUs and var- struction since migration of freight trains from existing
ious components for track, signalling, communications tracks shall provide capacity for additional SHSR passen-
and electrification systems should be supported. ger trains on such routes. The Chinese experience is that
such upgrading was implemented by meticulous planning
The first route for the construction of HSR in India, over a reasonable period while the route was still in oper-
between Mumbai and Ahmedabad, has been selected, ation. A 500-800 km route could be upgraded under traffic
funding secured and a separate entity (NHSR Corpo- in say 5 years by giving construction units working blocks
ration) established for its implementation. The best of 4 to 6 hours every day. Most time is required for rea-
possible candidate route has been chosen as the near ligning of track to enlarge radius and redesign of station
500 km distance is ideal for HSR, this route has high yards to allow higher speed over turnouts. For TALGO
ridership and demand, population in the catchment type EMU trains, the requirement of realigning track
area has relatively high per capita income that will would be minimal.
facilitate affordability of higher fares and there are
several other large urban centers that have potential Long term HSR and SHSR plan
of growth that boost ridership. Railways are built with a long-term perspective of 50 years
or more. It is recommended that a priority list of routes
We need to identify initiatives that would help maximize be prepared. A credible time line covering say the next
the benefits from this high investment landmark railway 20 years for the construction of selected projects may
project. then be declared so that construction and manufacturing
Long range development industries in public & private sectors can develop appro-
For technology assimilation and localization of manufac- priate capacity and access required technologies.
ture, the project should include transfer of technology in NHSR Corporation needs to be fully empowered to
design, material specifications, manufacture, technical implement the project and given reasonable freedom in
standards for testing of components and systems etc. as award of contracts as was the case with Delhi Metro. It
an integral part of the contract. Technology assimilation also needs to be populated with engineers and professional
by Indian engineers shall provide the foundation for project managers (not necessarily from IR) who will be
further development of HSR and Semi HSR in the medi- given responsibility for project delivery in agreed time
um term. These technologies would also be applicable frame.
for semi high-speed trains that could be operated by
upgrading the existing tracks. As has been the experience Human resources
in China, technology absorption is feasible only if large A major challenge is in design of various project elements
dedicated teams of engineers are deployed on the project and their integration. The first HSR project is based on
and they are given specific design and development as- Japanese technology and it is imperative that Indian
signments for delivery in a given time frame and they engineers fully understand and assimilate the design
process and criteria for each project element. Similar
Jit Sondhi breadth of knowledge of Japanese and International stand-
ards and technical specifications is required for designs
Independent management and railway consultant for other HSR and SHSR projects in India. This will
with international agencies such as the World Bank, require assembling a large team of young engineers (a
Asian Development Bank, USAID, etc. He has car- few hundred) in various disciplines who are willing to
ried out consulting work in India, China, Chile, dedicate next 10-20 years of their professional life in the
Africa, and Europe. Sondhi has first- hand experience field of HSR.
for past 10 years in planning and implementation
of the HSR program in China. It would be appropriate to set up a HSR Design Unit
which should seek collaboration with Universities, R&D

30 Rail Business [Focus-India] March 2017


H I GH S PE E D O P I N I O N

institutions and industry so that spe- volumes and competitive pricing. generate interest in technology up-
cific domain knowledge available can HSR and SHSR projects will also cre- grade and capacity enhancement out-
be leveraged. This approach was suc- ate several thousand jobs and pro- side the railway system.
cessful when ISRO sought collabora- mote manufacture of modern railway
tion with other institutions. products in India. Maintenance systems
Similarly, an independent HSR Test- The SHSRs would be operated with Maintaining HSR and SHSR systems
ing and Commissioning Unit need to EMU train sets and will require light in good order is also a challenge and
be set up to ensure compliance of weight EMU train sets designed to a requires detailed research and inves-
each project element with technical relatively low axle load of 17-18 t. It tigations to arrive at economical and
standards and specifications to ensure is imperative that India develops in- effective systems. All maintenance
high quality and reliable performance. digenous capability for design and activities related with track, OHE sys-
manufacture of such rolling stock in tem, signalling and communications,
Indigenous manufacture
a time frame of say five years. India information systems, ticketing etc.
Equal emphasis is needed for devel- would need several hundred such are carried out during maintenance
oping manufacturing capability EMU cars in case it embarks on an
equipment, components and systems. blocks of three to four hours each day.
extensive project for introducing The common IR practice of imposing
These would include light weight SHSRs on its trunk routes.
EMU train sets and all infrastructure speed restrictions on track not meet-
elements. Since several of these would A time line for implementing HSR ing required maintenance standard
be common or similar for application and SHSR projects over the next 20 will defeat the basic objectives. Work
on HSR and SHSR projects, the vol- years or so should be formulated and on setting up maintenance standards
ume would justify establishment of announced so that construction con- for various project elements and de-
manufacturing capacity in India. Here tractors as well as manufacturing com- veloping systems to achieve these in
the Maruti model of vendor develop- munity could develop technological an economical manner need to be
ment could be adopted wherein, to skills and physical capacity for carry- taken up sooner than later.
begin with, only two or three vendors ing out such projects. However, only
were selected for the manufacture of a credible implementation plan A guiding vision would be to let
each component to ensure reasonable for HSR and SHSR project would assimilation be the mantra.

Britains HS2 ( high speed rail) Bill has gained Royal assent in
February after three years of Parliamentary scrutiny. With the launch
of 70 million scheme, HS2 will connect London, Birmingham,
Manchester, Glasgow, Liverpool, Preston and Wigan. Set to com-
mission in 2026, the network will also get into Manchester, Leeds,
Darlington, Newcastle and Edinburgh from 2033. HS2 is expected
to create around 25,000 jobs during construction and around
1,00,000 in the wider economy.

Skilling for high speed rail


Demand for highly-skilled rail professionals in Britain has The courses will be delivered through an equal mixture of
rarely been higher; there is a considerable shortfall of skilled classroom teaching and work experience. Students will initially
professionals at a time when rail projects are booming. With take core units for a comprehensive understanding of the HSR
construction scheduled to start on HS2, a brand new high system through its lifecycle. This will then be complemented
speed rail spine linking London, Birmingham, Manchester with units teaching HSR topics in students area of specialism,
and Leeds in 2017, the industry is preparing for the challenge including core skills in those areas. The college expects to
of training and upskilling the 25,000-strong workforce needed accommodate nearly 2,000 full-time students each year when
for the 550 km HS2 and future projects. fully operational.
Opening in 2017 in Birmingham and Doncaster, the National The college will teach critical work-ready skills; personal
College for HSR will offer courses developed with industry attribute development will be integrated into the technical
employers to those entering further education for the first units and service design for people experience will also be a
time to experienced rail professionals. The objective is to key theme. More combinations of studies for each specializa-
reestablish a highly-skilled, world-class workforce, actively tion will enable all students to tailor their learning and ensure
collaborating with the industry. that their skills are transferable.

Rail Business [Focus-India] March 2017 31


M E TRO NA GPU R

Nagpur, a new template for Indian Metros


Brijesh Dixit, Managing Director, Nagpur Metro Rail Corporation since Feb
2015 has been with IR for over 30 years, that has included a more than 15-year
association with Mumbai suburban and urban rail transport. He has been
hands-on at planning, designing, constructing and maintaining large scale rail
infrastructure. operation of services and administration on Western and Central
Railways. His earlier stint as Divisional Railway Manager in Nagpur would
naturally help in quick problem solution for this complex project. Dixit ensured
a very expeditious start and fast progress through quick and smooth land
acquisition, a fast tie up with KfW Germany and AFD France and quick
consultancies and construction contracts. Dixit has a keen interest in promoting
affordable quality higher education in rural and backward areas. A 1980
graduate in civil engineering, he has a PhD from the University of Mumbai.
A favourite management axiom: ordinary people only do extraordinary jobs
given the enabling environment which is the responsibility of seniors.

We are developing on the experience of other Indian The two depots at Mihan & Hingna have similarly been
Metros. While the basic features of a standard gauge, via optimised for a ` 100 Cr dip in costs.
duct routing, 25 kV overhead traction etc. have been
retained, improvements in details and greater eco- Beginning with the foundation laying by the Prime Min-
concerns will make the 38 km Nagpur Metro a better siter in Oct 2014, Dixit has made visible progress on the
model for the emerging Indian cities Brijesh Dixit, ground and with the likely lease of train sets from Chennai
Managing Director, Maharashtra Metro, Nagpur. The Metro, he expects to run the first trains on the section
38-km network will cover two lines, North- South at 15 (phase 1) before the year end. This seems likely with the
km & 17 stations and the East-West at 18 km over 19 current 32 % physical progress on the project, visible with
stations. 70 pillars (total) and 50 spans having been launched.
The initial vision for the Nagpur Metro corporation was That converts to about 22 km of the 38-km planned. 22
limited to this orange city but that has now been enlarged station sites (total 38) are near finishing. Signalling works,
to cover Pune also and the newly christened Maharashtra
Metro will deliver both projects. Dixit stresses that this l Gauge - Standard (1435 mm) l Traction - 25 KV AC OHE
route will lead to better project utilisation of resources l Maximum Operating Speed - 80 kmph
and each project delivering better performance over the l Lines/Stations
precursors. In a way, Nagpur will set up a new template Elevated At Grade Elevated At Grade Total
for Metro projects in Class B cities. Stations Stations (kms) (kms) (kms)
Line 1 - North-South Corridor: Automotive Square to MIHAN
Like other Indian Metros (except Kolkata), Nagpur
15 2 15.0 4.6 19.6
Metro is also a JV between the state government and the
Line 2 - East West Corridor: Prajapati Nagar to Lokmanya Nagar
Central Ministry of Urban Development.
19 - 18.6 - 18.6
Cost control Total 34 2 33.8 4.6 38.2
The cost cutting efforts started with the engineering
l Rolling Stock And Technical Parameters
reviews, like for the via-duct columns where the duct
Particulars Length Width Height
segment width has been reduced to 8.5 m (from 10.3m)
Driving Motor Car (DMC) in 21.64 2.9 3.9
with weight reduction of about 15 % per span. The exe-
Trailer Cars 21.34 2.9 3.9
cution has involved casting of the 70-m parapet integrated
Train Composition : 3-Car train: *DMC+TC+DMC
with the segment, with all these changes leading to a
` 120 Cr anticipated savings. The right of way reduction Seating Arrangement : Longitudinal

from 20 to 18 m has reduced land acquisition issues. Axle load t : 16


Station platforms have been truncated to 75 m, mainly Max Acceleration : 1.0 m/s2
due to shorter train consist (3 coaches only). Signalling Max Deceleration : 1.0 m/s2 (Normal braking)
changes like elimination of master clocks at stations, Maximum Operating Speed : 85 kph
virtualization of telecom servers in operations control Schedule Speed :
centre, elimination of 48 V Dc supply should save around North-South : 32-34 kph
` 25 Cr. Reduction of traction power substations from East-West : 30 kph
four to two and optimisation on transformer ratings and Car Depots : at MIHAN & Hingna
cable sizes should moderate the costs by another 180Cr. *Driving motor + trailer + driving motor

32 Rail Business [Focus-India] March 2017


ME T RO N A G P UR

Nagpur Metro will have two corridors, totaling 34 km over 36 stations.

under execution by Siemens, are on substantial area and revenue streams. uldi exchange point and the Zero Mile
par progress. The project does not location.
Residential development of 60 lakh
involve any tunnelling. Premier con-
sq. ft. is hoped for at the two depots The project execution is set for a fast
struction companies like AFCONS,
at Mihan and Hingna. An internation- pace, centered about deployment of
Pratibha, IL&FS etc. are executing
al architect has been engaged for con- special software like 5D Information
key segments. The expected peak rid-
cept plans for development at Sitab- Modelling (BIM) & ERP for project
ership on completion will be 3.5 lakh
per day, handled by 3 car train sets.
Already 69 coaches have been or-
dered on the Chinese CRRC, at
around ` 8.2 Cr per coach, the lowest
by any Indian Metro so far. This is
attributed in part to the re-assessing
the eligibility criteria for the vendor
to ensure widest participation.
Project funding under SPV model
Total project cost: ` 8680 Cr
GoI equity: 14.3%
Maharashtra state equity: 14.3%
GoI subordinate debt : 50%
Grant from Nagpur Municipal
Corporation: 0.98%
Market loan: 58 .1%.
The state agencies have chipped in
with about ` 1000 Cr through state
taxes and land acquisition costs. The
project has external funding of Euro
500 m (` 3750 Cr) from the German
KfW and the French AFD (Euro 150
m, ` 975 Cr).
Real estate development
Integrated station and other area de-
velopment is a core business segment
for Metros and Nagpur has planned

Rail Business [Focus-India] March 2017 33


M E T R O NAGPU R

monitoring and execution. Dixit has ban Metro transport has been en- station and depot roof tops and va-
built in plans for non-fare box reve- hanced by special provisions; it claims cant ground spaces and walls will be
nues of near 20 % of the total. The that 65 % of energy requirements will mounted with PV panels. Right now,
Transit Oriented Development will be solar based and this source will a 14 MW generation (likely to in-
include increase in stamp duty by 1%. progressively increase to 34 m kWH crease to 36 MW) is in construct.
The ECO drive
energy units by 2026. Maximum solar
tapping will be available as all possible
The inherent eco-friendliness of ur-

New Metro Policy the Metro sites could be given a special proviso so that
The Finance Minister has announced that a new policy development by the Metro JVs is faster and avoids the
document will be released during the year. This is many points of interaction with local authorities. An-
expected to provide improvements over the current other need is the setup of integrated Metro Transport
template of projects executed and operated by a Cen- authorities for handling rail, road (and may be ferry)
tral-State government JVs, with debt funding and ex- traffic under one umbrella. The current fragmented
ternal aid or soft loan support. While the Budget an- structures in Indian cities, unlike the integrated set ups
nouncement has not laid out the likely changes, the in developed country cities, leads to poor multi-modal
new policy could address issues on investment patterns, coordination, adding to some chaos at Metro stations
and improved viability. Real estate development on and increased travel time for commuters.

Rail facture detection


Rx1 Rx
Theory of Operation

Magnetically
Rx Tx2 coupled signal
injection
3rd Axle 4th Axle

I1, 2 = Max Good Rail Current flows in


rail/axle loop
Waveform
#3 axle #4 axle

I1, 2 = 0 Broken Rail Detect current


in rail/axle loop

I1 I2 Crossing
Tx2 Shunt, Shorts Signal
Rx processing

68 of the 146 train accidents, mostly causing fatal injuries, ` 12 lakh per km (earlier reported in Rail Business, Jan 2017).
have been attributed to rail/weld fractures. While multiple
efforts are being bade by IR to arrest the occurrence, new The idea presented involves real time detection of integrity
technologies are also being assessed and deployed. of track by injection of two magnetically coupled signals
through a passing loco. Signals will operate at narrowband
One emerging method of continuous monitoring of rail health frequencies of 4.6 to 3.8 kHz that will not interfere with other
with loco mounted equipment was flagged in the November roadside signals. Current loops are monitored real time for
2016 Rail Vikas Shivir. Existing track circuits (part of the waveforms which are compared with signature waveforms of
signalling system) can provide an indication of discontinuity known track features like rail joints and crossings. It will raise
but the cause must be physically verified by on-foot site checks. immediate audio-visual alarm upon detection of unknown
This is cumbersome particularly as trained staff may have to signatures for rail failures, pin pointing the geographical loca-
move from a different location. Further, a track circuit can tion.
detect such a discontinuity only in the positive rail of a DC
circuit. The IR presentation indicated that ultra-sonic flaw The presentation listed that the concept has been successfully
detection is about 75% reliable, being able to detect fatigue implemented over BNSF, USA, where 68,000 events (usual
flaws that have a nucleus and grow over time to a threshold and unusual) have been detected over about 1,44,900 km of
level. A pilot project for real time rail fracture detection, under track. Execution timeframe of two years, if approved by IR,
trial by RDSO on the Northern and North Central zones has been indicated. (Based on a presentation by Kolkata Metro
presents a possibility but is theft prone and likely to cost about at the IR Rail Vikas Shivir.)

34 Rail Business [Focus-India] March 2017


O P E RATIONS CREWS

CREWLOGIC optimises rail crew links


IR runs nearly 6420 express and passenger (excluding
IMPROVEMENTS IN FIROZPUR CREW LINKS
suburban) trains every day. Train crew scheduling for
Actual Improved
such a large operation is a complex task, handled currently

224
200
by human skills and optimised solutions do not exist.

192
184
Crew schedules as of now often optimize crew utilization

138
124
within a railway division and train runs are divided be-
tween crew lobbies due to legacy reasons, some originat-

81

77
71
66
ing from steam loco operation era but without any scien-
tific approach. Local optimization at divisional level does
not result in global optimization. CREW SETS OS REST HQ REST DUTY TKM PER
HRS/14DAYS HRS/14 HRS/14 CREW/DAY
Crew scheduling is a known non-parametric hard prob- DAYS DAYS

lem. Nobody knows the minimum crew needed to run


all the coaching trains such that all the rules are followed
and crews get defined rest.
There is a saving of 14 crew, 10 percent of 138 existing
A coaching train is run by a driver, assistant driver and express crew in FZR division. Outstation rest is reduced
guard, collectively called a crew. Crews works a train for from 81 hours to 66 hours per crew per 14 days, an im-
around eight hours before another takes over. After rest provement of 18%. Absolute improvement in outstation
in an outstation rest (running) room, they round-trip a rest was from 5589 hours per week to 4101 hours per
train back towards the base station. Crew gets headquarter week, a 27% reduction. Reduction in absolute outstation
rest after a round trip, every week the crew should get a rest will also reduce the workload for running room staff.
long headquarter rest called periodic rest. Crews work all Headquarter rest hours go up from 184 to 192 hours per
trains assigned to its base station such that rules for max- crew per fortnight, an improvement of 4.5%. Duty hours
imum continuous duty and minimum prescribed rest are per fortnight went up 9% from 71 to 77 hours. Crew
followed. These crew schedules, popularly known as crew productivity went up by 12% from 200 to 224 km per
links, are drawn for all crew bases covering all coaching crew per day.
trains. Such crews are a very costly resource that, per a
On an all-India basis, a 10% saving in coaching crew will
planning commission conducted study (Total Transpor-
save 6000 employees (more than 60,000 driver guards
tation Study), costs 7.9% of IR operating expenses.
and assistant drivers are running coaching trains). The
An untapped area saving in coaching crew will reduce the requirements of
Mathologic has created a software product CREWLOG- goods crew working in coaching. There is perennial short-
IC, essentially a decision support system, after research age in goods crew and they earn overtime at double the
for over three years. The complete crew link making rate. Thus, the coaching crew saved will reduce the over-
process is divided in stages and CREWLOGIC includes time in goods crew at double the rate of salary.
algorithms for optimization at every stage with a designed Complexity for freight crews
intuitive user interface so that railway users can use it
This question is repeatedly asked: crew links are planned
easily without having to be mathematicians. The software
based on a time table. If some trains run late frequently,
can be hosted on Cloud or on local servers and easily
additional slack is provided in the form of extra rest to
accessed from a web browser. Any division or zone, or
Dr Manish Kumar, accommodate perennial late runners. The crew links are
even the entire IR, can make efficient crew links using it.
Mathologic not dynamic in nature and dynamic scheduling is out of
Technologies
Innovation Center, For every crew in the link there is 15% leave and 15% scope of this innovation. With most freight trains running
IIIT Bangalore training reserve. For 25 drivers, there is one Loco Inspector to open timings, the crew assignment for these is riven
(4%) and for every 50 Guards, one Traffic Inspector with greater inefficiencies. These can be addressed only
(2%). In effect, every one crew set in the link averages by a dynamic scheduling software that can be developed
4.34 employees. Average salary and perks of such staff based on the experience with CREWLOGIC on passenger
can be taken as ` 12 lakhs per year leading to financial train crews. That would be tougher and more exciting,
impact of one crew set at ` 52 lakhs. but worth a try.
Prove outs Dr Manish Kumar, a PhD from IIM Calcutta and MTech
Two field assessments have been carried out. In one a from IIT Delhi leads Mathologic Technologies, an inno-
zero-base plan was made to run trains in Northern Rail- vative startup company. He is a former Indian IR Service
Prof. Bodhibrata Nag
Indian Institute of way. With the software, a 28% more productivity per crew officer, an academic and former software Infosys research-
Management was achieved. In the second trial, the running room rest er. The startup is mentored by an Operations Research
Kolkata
in Firozpur Divisions (FZR) express crew links was im- Professor from IIM Calcutta and has been incubated at
proved with saving of 10 % crew. In both the cases, the IIIT Bangalore. a patent issue is likely soon. man-
crews spent more time at home. ish@mathologic.com

36 Rail Business [Focus-India] March 2017


I N N O VAT I O N S CO MMU N IC AT I O N S

Appropriate communication technology


IRs no unmanned level crossings plan has brought forth
a cost-effective use of modern technologies in a good Typical set diagram, as for Tatanagar Station
illustration of how to use technologies appropriately. In Solar Panel (100 Watt peak)
a first of its kind on IR, GSM network based voice com-
munication, backed by suitable interlocks conforming to
L.C.Gate TB-11(Gate lodge)
operational safety protocols, has been successfully in-
stalled. By utilizing available infrastructure of mobile Securely locked inside
networks, cost for providing telephone has been reduced equipment box
(immovable) and not
by 95%, saving more than ` 2 Cr on the project cost. accessible to Gateman)

Manned level crossing (LC) gates require that a gateman


should have voice communication with station operations 12V/0.5A
staff to communicate about approaching trains. Tradi- Charge controller 75AH battery
FCT
tional telephone through buried copper cables is vandal- (>100Hrs backup)

ism prone and expensive to install and maintain, particu-


larly on sections with low train density. FCT device having SIM (with outgoing limited to SM/RRI Tata only Normal Desktop telephone: with Caller ID
and with one touch speed dial key set to SM/RRI TATA

LC gate manning had been sanctioned for 12 locations


on the 45 km Tatanagar and Belpahar (BDO) section Appropriate technology using a high-technology solution in a traditional area. A wireless
communication solution, low on capital and running costs, for a sparsely used train section
that handles limited traffic but has a historical place in IR has been developed successfully.
lore having been the first rail route to handle iron ore that
built the Tatanagar steel complex. The low traffic density was chalked out to provide IP telephone at each gate and
has limited working to train staff and ticket system, connected to stations through dedicated fibre terminated
without block section working, possible without inter- at each gate. Here 45 km of 24 fibre OFC cable were to
locked communication between stations. The two termi- be laid throughout the section, a dedicated fibre be ter-
nal stations at TATA and BDO are connected through minated at each gate, connecting to adjacent station
land line phones but the main challenge was to provide through OFC media converter and IP phone. The VOIP
connectivity for these 12 LCs. A conventional method server (each under ` 1 Lakh) would be provided at
through connectivity is a buried 6-quad copper cable. TATA and BDO. The IP phone would be converted to
Ten of these gates fall in the mid area (13 km from TATA conventional push button with programmed speed dial
and 12 km from BDO). Working of telephone on copper keys. The power requirement in this case is very low
cable over such long distance is practically difficult due (typically 20-30 W), within solar power capability. The
to reasons like voltage attenuation. Normally, rail block estimated cost for this system worked to ` 1.1 Cr (` 2.2
sections between two adjacent stations are 10-12km long, crores for copper cable).
with gates falling within 6 km from nearest controlling The mother of invention
station and attenuation is controllable. Trenching and
Procurement of 65 km Quad cable had been delayed due
laying of 45 km of 6-quad cable would take months.
to pressing demand of more important works and this
Plus, theft of copper cables, even if buried, is high due fortuitous non-availability of copper and OFC cables
to less trains density, something that had already been forced the road to an appropriate technology as we opted Rajendra Prasad
Divisional Railway
experienced when laying the cable in this section was to utilize the mobile network and worked in this direction
Manager, South
dropped by construction without completion earlier by utilizing the existing cellphone facility instead of IR Eastern Railway,
in 2004. Copper cables were pulled out by miscreants infrastructure. The expected expenditure was much lower Chakradharpur
with tractors, and in many patches the laid cable was with implementation in a very short time.
taken away immediately after laying. A search for al-
ternate solution to provide telephonic connectivity GSM based FCT phone
was needed. For operational safety, a public mobile system has limita-
tions like:
The OFC option
A second option was optical fibre (OFC) based commu- l An outsider may call a gateman from any public booth
nication as this cable is not theft prone, lacking a resale or mobile phone and give unauthorized instructions.
value. For maintainers, the cut location can be exactly pin l The gateman may misuse the GSM based phone for
pointed. OFC is cheaper than the copper cable but the unwanted calls and miss an operations instruction. M Mubashshir
equipment is to be installed at each location with a stable Waris,
power supply which this unelectrified section mostly l The mobile phone can be carried by gateman to his Sr Divisional Signal
residence and operate from there, considering a max 3 & Telecom Engineer,
lacks. Required: an out-of-the-box concept which does
South Eastern
not require full OFC equipment running on low power. trains in a day.
Railway,
The answer for such an OFC solution lies in data net- After many trials and improvements, a working system Chakradharpur
works, where we can provide video conference for remote using GSM based fixed Cellular Telephone (FCT) has
locations with small media converter device. The system been developed.

Rail Business [Focus-India] March 2017 37


I N N O VATIONS COM MUNIC ATIONS

The system person as its access is restricted by only difference is that we are using
The telephone to the gateman can be PIN number and specific program- different media for establishing tele-
provided through existing GSM net- ming is required communication. The GSM based me-
work. A fixed table top conventional dia is well established and using that
Blocking of Incoming calls: with the infrastructure is highly recommended
telephone handset (with a dedicated Airtel Call Manager service, inward
push button call to the controlling for saving of cost and long project
calls are not possible to the gate FCT work. The integrity of the GSM based
station master) connected through phone from any number except the
RJ11 cord to FCT instrument secure- FCT based telephone is already es-
Station Master. This feature is feasible tablished and, in fact, the voice clarity
ly locked inside Instrument box was by using latest Value added Service
provided. All outgoing and incoming of FCT phone is also better. Provision
Airtel Call Manager (activated by of voice logger is also possible for the
calls to other mobile numbers except dialing *323#). A custom profile is set
controlling station were blocked. Fur- FCT based telephone.
where one number is set as always
ther to add up security, the keypad of allowed list and all numbers other This system is recommended for pro-
telephone was removed. Similarly, than this are rejected at network level viding telephone connection for man-
the phone at station end was provided with the caller getting a suitable voice ning in other zones, especially where
with same features but with one dif- message. The FCT will not ring as traffic is less. In fact, it is an ideal sys-
ference: authorized to speak to any unknown incoming call is blocked at tem due to fast execution, less main-
of gates with dedicated 12 keys with network level, while calls between tenance and low infrastructure cost.
all calls limited to these 12 locations Station Master and gate FCTs can be In addition the concept can also be
only. possible. The monthly service charge used for other purpose like hotline
In case of outage of mobile network, is ` 30 per SIM. telephone requiring limited user calls
rule based provision for operation in in control, FOIS locations, traction
Reliability and maintainability substations and similar uses.
case of loss of communication would
The GSM cellular network is a stable
be followed. After a vigorous marketing of the
communication with rare outage. The
Technical system gate areas have been tested with Rx idea, with compliance of all doubts
An independent 12V supply solar level of mobile network and found to and observations, the system has been
panel is provided for FCT to make have good coverage. Many models of cleared with issue of a procedure or-
the system run without local power FCT phones are now available, with der and clearance by the statutory
in the non-electrified area. proven technology and robust design. Commissioner of Railway Safety.
The facility of battery backup in many
l Simado FCT equipment, with models adds to their reliability during Idea to Reality timeline
many functionalities, is robust in local power failure. System can run l August 2016: Idea for FCT
design and supports 2G & 3G net- for more than 48 hours without exter- phone.
works. The power supply is 12V nal power supply if higher capacity
DC with a 5Watt consumption, im- l August 2016: proposal for zonal
batteries are used. The system is
plying that a 75Ah battery can run approval
based on handy small equipment
for 5 days, even assuming 30% pow- which can be replaced easily by staff l Sep 2016: trial of FCT phone
er loss due to non-ideal conditions. with limited training. conducted at one gate in Tatan-
l Solar Panel: 12V/100W(peak) agar
Advantages
Tata made solar modules are used Nov 2016: Trial conducted at a
For such an FCT instrument system l
to charge the battery. gate ready for manning. The fea-
the estimated expenditure is only
l Charge controller: of 10 Amps ca- ` 10 lakhs with recurring yearly charg- tures for blocking outgoing call
pacity is used to charge battery and es of, may be, ` 50,000, much less at SIM level and for blocking in-
supply load current to FCT during than maintenance cost of a 6 Quad coming calls other than required
daytime. In night, the FCT will cable throughout the section. Trench- number introduced, completing
work on battery. ing and laying of 45 km of cable often all requirements for system integ-
takes months and the practical diffi- rity.
l Push button telephone with speed
culties of rocky area and other unfore- Dec 2016: Approval by zonal
dial keys, where the number keypad l
seen reasons can further delay execu- HQ along with a procedure or-
is covered under metal with limited
tion. With available commercial voice der.
accessibility for speed dial key and
loggers at around ` 15,000 each, voice
caller ID. l Jan 2017: CRS sanction
communication recording is possible
l Airtel SIM (Postpaid CUG) in FCT instrument. The voice quality l January, 2017: Commissioning
is very clear as compared to humming,
Blocking of outgoing calls other
noisy sound experienced in magneto
than station, achieved by utilizing
phone due to cable joint leakage, ca- The fast completion of this long-
the general feature of SIM card chip
ble low insulation, Electromagnetic postponed project in fraction of the
for Fixed Dialling Numbers. By
induction, etc. cost is an example of how appropriate
this outgoing call is barred outside
the list of numbers which are fed in There is no difference between GSM technology, using all modern ele-
the SIM card. This cannot be based FCT phone and conventional ments, can be adapted for optimised
changed by any unauthorised Magneto push button phone. The solutions.

38 Rail Business [Focus-India] March 2017


PE RS O N ALI T Y S A SI N G H

Straddling administration, fate and adversity


by the thought: would I ever see her again. But then a voice
filled my head assuring me that things would be just fine. I
cannot explain the calm that descended over me after that so
much so, when my wife came back I could tell her not to worry
and just take me to hospital and I would be fine. And just as
the voice had said, everything fell into place; I was in hospital
within what is called the golden hour, which of course saved
us both. And the voice has always stayed with me.
My disability was such that I would never walk again. A life
on a wheelchair stared me in the face. But the seven-month
long rehabilitation in Stoke Mandeville Hospital in UK taught
me that all was not lost and life on a wheelchair could be near
normal. The support of my wife and children, friends and
Never looking back in anger: Sarabjit A Singh and Mrs. Kitty (Kanchan) Singh family pulled us through this very challenging period. However,
look back at an unfortunate event in 1989, that changed their lives.
all this would never have been possible without the institutional
An after-dinner walk on the June 23, 1989 changed our way support of the railways and colleagues. Everyone pitched into
of life from how we thought we would live our lives to how to make it possible for me to work as near normal as it could
we had to live it. My wife and I were both shot by people we be. The struggle of getting back to work and normal life taught
did not know, for reasons that never became quite clear. The me to be grateful for what you have and things are never as
place, an under-construction colony of the Rail Coach Factory, bad as they seem.
Kapurthala.
Never give in for you will never know what you can do if you
But then things are never so simple. You take decisions as part do not do what you can do.
of your job and someone feels aggrieved. The times were bad
as militancy in Punjab was at its peak and every day brought I would be amiss if I did not mention that I am grateful to the
news of people, of some we knew, being shot and killed. But almighty for multiple mercies that he has bestowed on us. If
the thought that we could be targeted never crossed my mind. we had not been saved my two daughters, then sixteen and
We were here to build a factory to give people jobs, why should eleven, would have had to fend for themselves. If I did not
anyone want to hurt us? With militancy in the air, it was easy have the support that I have had, especially of my wife, and I
to hit and run to make it look like another terrorist attack. We continue to have I would not have been able to lead the life
became victims of such an environment. that I have led. How can I forget the RCF employees who
slept for six months in the hospital verandas to turn me every
I was shot thrice, my wife once. One of the bullets broke my three hours to keep me free from pressure sores or the forty
spine and as I collapsed to the ground, with it collapsed the that lined up to donate blood?
world I knew. With a bullet logged in her jaw my brave and
wonderful wife ran for help. As I saw her go I was possessed I have much to be thankful for.

incident the posting was great... I could recruit about 3000


artisans and train them in two years.
Where is Chiqualaquala?
In 1978 Singh had led a team of 20 technicians to Mozambique
Railways for managing the diesel locomotive fleet. , the first
Indian expert to reach Mozambique after it attained independ-
ence. In the prevailing cold war struggle with South Africa
and Zimbabwe (not yet free), the endeavour was to run a
train, if not every day but occasionally, between Maputo &
Chiqualaquala to show that the line was functional.
The adviser heading the workshop had fled to Portugal (he
was white and worried) and Singh became the Advisor. When
Down the memory lane: A young S A Singh ushering in Prime Minister
Indira Gandhi on a visit in Botswana.
Prime Minister Indira Gandhi came on a state visit, Singh had
the privilege of taking her around. Singh recounts that she
In 1986 at the height of militancy in the Punjab, SA Singh was very gracious and looked for me in the crowd before she
joined the team for establishing the Rail Coach Factory in got into the car and said, I am very pleased with your work
Kapurthala. He adds that apart from this very unfortunate and you have my good wishes.

Rail Business [Focus-India] March 2017 39


L A S T W ORD S

Of gunshots and drifted ferries because of a sudden rise of the river. The resulting uproar in
Singhs IR career started as an apprentice in Jamalpur. After Parliament forced the railway minister to visit Patna. Com-
a short stint in 1966 in Gorakhpur workshop, he was posted pared to what can happen today, I escaped with a minor wrap
to the Fategarh district, a heady stuff for a 26-year-old. I found on the wrist. A posting in RDSO followed.
myself like the head of a small principality stretching from Eventful years of grit
Agra to Kanpur and from Kasganj to Bareilly. It was like being
asked to learn swimming by being thrown into the deep end. From Mozambique to Chakradharpur to Kapurthala to 14
I can never forget being forced to carry in my saloon a man months of hospitalization! Postings on the Northern and
with a gunshot injury by a group of armed men. COFMOW followed till retirement in 2003. Singh was ap-
pointed a Member of the Principle Bench of the Central
In a later posting in 1971 he was also Marine Superintendent Administrative Tribunal, demitting office in 2005. He later
for the ferries that linked the South and North banks of the worked for some time with the World Bank. Singh has been
Ganges at Patna, Mokamah and Bhagalpur. It was also the a beacon of what grit can achieve and has associated with
first brush with politicians. A steamer carrying the then Chief disability issues. He was also part of the group that drafted
Minister of Bihar, Kapoori Thakur, drifted 16 km downstream the Disabilities Act 1995.

The largest annual human migration, mostly by train


The largest annual end of 2016. Over 350 million trips were made by train of
human migration on which some were over very long distances such as 1,500-2,000
earth takes place every km. The average train travel per trip was over 400 km. It is
year in China during estimated that more than 10% of passengers departed from
the Chinese New Year the country's capital, Beijing, followed by Shanghai (9%) and
or Spring Festival. This Shenzhen (7%).
year about three billion
trips were made by During this period, the inter-city rail transportation faces great
Chinese people during challenges. The demand for tickets far exceeds the supply.
the Spring Festival The online system for ticket purchase has alleviated the diffi-
travel rush over a period of 40 days commencing from January culty in buying tickets and effectively discouraged scalpers
13. Millions of people working or studying out of their home- who profit a lot during this period. However, travelling by
towns travelled home to reunite with families to celebrate the train during the Chinese Spring Festival is still a challenge,
Chinese New Year. especially to foreigners. Trains are sardine-packed with thou-
In 2017-the Year of the Rooster-Chinese authorities expected sands of snoozing students, as a result of greatly expanded
holiday makers to make 2.5 billion trips by land, 356 million number of university places over the past decade.
by rail, 58 million by plane and 43 million by water transport The Beijing West station was used by over 2,25,000 passengers
over the 40-day period from January 13. daily during the festival period. This station handled 204 train
China's total rail network stands at more than 1,24,000 Km arrivals and departures a day, meaning a bullet train arrived
and includes 22,000 route km of high speed railways by the every 4 minutes and a regular train every five minutes.

Railway 'mothers' About 200 female conductors from


Chengdu railway section of Sichuan
province have been dubbed "railway
taking the children to spend the Spring
Festival with their mother this year. But
the two girls had grown up with their
mothers" after they volunteered to pay grandmother and felt strange with their
special attention to children travelling father, who did not have much experience
with their parents or grandparents during of taking care of children. To comfort
the Spring Festival. Conductor Zhao Jingjing, Zhao held her and talked to her.
Congying is one of them. On Jan 25, The girl gradually stopped crying and
2016, two girls, both less than three years even agreed to eat with Zhao's help.
old, boarded her train with their father.
(based on inputs from Nanyan Zhou,
The elder sister, nicknamed Jingjing, was
Transport consultant, Beijing)
crying continuously which caught Zhao's
attention. Zhao found that the father was

40 Rail Business [Focus-India] March 2017

You might also like