You are on page 1of 11

Electric Power Systems Research 140 (2016) 984994

Contents lists available at ScienceDirect

Electric Power Systems Research


journal homepage: www.elsevier.com/locate/epsr

Review

High voltage AC underground cable systems for power transmission


A review of the Danish experience, part 1
Claus Leth Bak , F. Faria da Silva
Department of Energy Technology, Aalborg University, Pontoppidanstrde 111, 9220 Aalborg, Denmark

a r t i c l e i n f o a b s t r a c t

Article history: This paper is a rst of two presenting a review of research results in underground cable transmis-
Received 4 November 2014 sion obtained by the Department of Energy Technology, Aalborg University ET/AAU and Danish TSO
Received in revised form 12 May 2016 Energinet.dk within the last 6 years. The main core of the results are obtained by PhD students research-
Accepted 27 May 2016
ing electrical engineering topics related to using underground cables for power transmission at EHV level
Available online 23 June 2016
and including the 420 kV level. The research topics were laid down by ET/AAU and Energinet.dk in the
DANPAC (DANish Power systems with AC Cables) research project. The main topics are discussed on the
Keywords:
basis of 39 references published by ET/AAU and Energinet.dk.
Underground cable transmission
Time domain simulations
Part I of the paper explains the events that lead to the research project, reactive power compensation,
Electromagnetic transients modelling for transient studies, including eld measurements and improvements to the existing models,
Cable modelling and temporary overvoltages due to resonances.
Insulation coordination Part II covers transient phenomena, harmonics in cables, system modelling for different phenomena,
Fault location main and backup protections in cable-based networks, online fault detection and future trends.
2016 Elsevier B.V. All rights reserved.

Contents

1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 985
2. Transmission cable system description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 987
3. Reactive power compensation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 988
3.1. Reactive power compensation considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 988
3.1.1. Maximum unit size of shunt reactors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 989
3.1.2. Compensation patterns . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 989
3.1.3. Case example . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 989
3.2. Summary of reactive power compensation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 989
4. Modelling of long high voltage AC cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 989
4.1. Introduction to transmission cable modelling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 989
4.2. Field measurements at transmission cable systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 990
4.3. Cable model improvement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 990
4.4. Summary of cable modelling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 992
5. Overvoltage analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 992
5.1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 992
5.2. Series resonance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 992
5.3. Parallel resonance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 993
5.4. Fault clearing and system islanding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 993
6. Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 993
References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 993

Corresponding author.
E-mail address: clb@et.aau.dk (C.L. Bak).

http://dx.doi.org/10.1016/j.epsr.2016.05.034
0378-7796/ 2016 Elsevier B.V. All rights reserved.
C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994 985

1. Introduction beauty, a fjord and a river, and the OHL was replaced by 400 kV
XLPE cable in these areas [11], see Fig. 2.
Electric power is an essential part of modern societys infrastruc- The line consisted of three overhead line sections, two cable
ture. The transmission network is an unavoidable part of the overall sections and a permanently connected shunt reactor in Hornbk
concept of producing and consuming electrical energy; it is sim- with Q = 100 MVar. A single line diagram is shown in Fig. 3.
ply necessary for enabling transport of electrical energy between The line was energised for the rst time in 2004 and as the Dan-
various sources of production and load centres. Furthermore, it is ish transmission system operator Energinet.dk did not have much
necessary to interconnect several sources both in-country and also experience with such a hybrid line, much emphasis was put on
with respect to neighbouring countries in order to achieve power thorough registration of the lines electrical behaviour. Chief engi-
exchange and to improve a fair reliability of the power system. The neer H.P. Elmer monitored voltages and currents of the line when
electric power transmission network undertakes this important energised for the rst time, and he found that nothing much special
role and all societies having gone through the industrial revolution happened, except for the DC offset due to the shunt reactor. How-
has a transmission system. In order to transmit large quantities of ever, when they switched off the line, he certainly saw something
electric power, voltage of the transmission lines has been gradually he had never seen in his long career. This rst switch-off measure-
increasing during the last century [1], see Fig. 1. ment presented in Fig. 4 is obtained by monitoring the voltage at
Most recent development includes a circuit breaker for a 1.2 MV the line when the last of the two line circuit breakers is opened
test plant in India [2]. Overhead lines are almost exclusively used and the line is liberated from the rest of the power system. As can
for power transmission, except in urban areas, in locations hav- be seen from Fig. 4, the voltage at the line did not immediately go
ing natural beauty preservation status and for water crossing. An towards zero as for a usual line, but kept oscillating in a modulated
example of water crossing is the 500 kV the cable link between way for several seconds. Even more worrying was the fact that the
mainland Canada and Vancouver Island installed in 1984 [3]. Tokyo line experienced overvoltage in two of the phases and that these
is an example of a large urban area having employed 500 kV AC were only decaying slowly.
transmission cable systems with a cable length of 40 km and com- Apparently, there was a kind of behaviour here which demanded
missioned in 2000 [4]. Italy has also employed cable technology, an explanation. The rst attempts pointed towards the likelihood of
notable examples are the 400 kV AC submarine cable link between some kind of oscillation between capacitances, mainly of the cable
the mainland and Sicily [5], the 380 kV double-circuit cable in a and the shunt reactor inductance, but why did we see different
hybrid cable-OHL line between Turbigo and Rho [6] or the 118 km modes of oscillation which were different in all three phases and
long connection between Sicily and Malta [7]. Another important where did the overvoltage come from? These questions gave rise to
milestone in cable development was the rst 400 kV XLPE cable in cooperation between Department of Energy Technology at Aalborg
Berlin in 1998 [8]. An economic and technical comparison between University and Energinet.dk as a masters student, Kim Sgaard,
undergrounding and overhead lines is available at [9], whereas [10] undertook the task of explaining the above questions in his mas-
presents a comparison between different undergrounding options. ters thesis. The main ndings are published in [1114] and will
In the years before 2000, Denmark has mainly used cables for be outlined briey in this introduction, as they belong to a certain
transmission purposes at 145 and 170 kV in larger cities, for con- category of cable transient phenomena.
necting power plant units located close to or in city centres and Three frequencies are recognisable in the voltage measurement,
when crossing short paths of land having natural beauty. Thus, the a change from 50 Hz to a lower (app. 35 Hz) when switching off and
cables installed in Denmark up to 2000 have either been of short two modulating frequencies (app. 3 Hz for all three phases and app.
length or part of an OHL transmission line. The rst experience 0.4 Hz for phase S and T). Overvoltages are visible in phase R and S.
in Denmark leading to an increased focus on the highly different The overall explanations to such ndings are straightforward, when
electrical characteristics and the thereby associated behaviour of realised
cable transmission systems comes from the putting into operation
of a combined 400 kV OHL/cable line in Jutland, between the cities When switching the line off the 50 Hz system, it will start res-
of Aarhus and Aalborg. The line had to cross two areas of natural onating with a frequency equal to its resonant frequency given
by its inductances and capacitances, which are dominated by the
shunt reactor inductance and the cable capacitance. In this case,
this frequency is around 35 Hz.
The differences in appearance for the three phases are due to the
slightly different resonant frequencies of each phase (caused by
reactor and line asymmetries), which are coupled by mutual cou-
plings (also unsymmetrical, both inductive and capacitive, or just
inductive, as the phenomenon was also registered in a pure cable
line [15]) between phases and thereby added. Adding two sinu-
soidal with slightly different frequency yields such low-frequent
modulations. In this way, numerous shapes and appearances
(frequencies, amplications, attenuations) of last-end switch off
voltage decay can form [12,13].
The overvoltage stems from the summation of both the capacitive
and inductive induced voltages as the frequencies are slightly dif-
ferent per phase, and thereby, the induced voltages in one phase
(from the other two) will either more or less add to the phase volt-
age and thereby increase the voltage or subtract from the phase
voltage lowering it [12,13].
The fact that the three phases are not switched off at exactly
the same time, due to current interruption in current zero in
the circuit breaker, adds to the non-aligned adding of the phase
Fig. 1. Major AC systems in chronological order of their installations [1]. voltages.
986 C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994

Fig. 2. Danish 400 kV line from Nordjyllandsvrket (Aalborg) to Trige (Aarhus) [11].

Fig. 3. Single line diagram of the 400 kV line showing OHL sections as well as the to cable sections of 4.5 km and 2.8 km [11].

A further question came up as the line is a hybrid line and single- research in order to have full knowledge of transmission cable
phase autoreclosure is used for the overhead line. Suppose the systems, so such could be designed and operated with the same
feeder protection opens one phase due to a fault, could we expect condence and reliability as overhead lines at transmission level.
that the energy induced into the switched-off phase would be suf- In Denmark, receiving public and political pressures to under-
cient to maintain the fault arc and thereby preventing a successful ground its OHLs, Energinet.dk published a report on the future
autoreclosure [14]? expansion and undergrounding of its transmission grid on the 3rd
The recognition that a line, mainly laid out as OHL and only hav- of April 2008 [16]. The report proposed and compared six principles
ing cable around 8% of the line length, was able to react so different (AF in Fig. 5). From these six principles, the Danish government
to an ordinary OHL, not even considering cross-bondings or having has selected Principle C in which all new 400 kV lines will basically
a line utilising full length cable, gave rise to a decision to conduct be undergrounded.

Fig. 4. Phase voltages for the 400 kV line NVV-TRI when performing last-end disconnection. Timescale horizontal 6.5 s between bars and voltage peak before instant of
switching (before left bar) is equal to 335 kV.
C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994 987

Fig. 5. Six principles for the future grid expansion [16].

Realising this as a major technical challenge, because all 132 conductor cross sectional area in order to obtain the same current
and 150 kV OHL should be replaced with cable lines over a period capacity as for Al conductor. The advantage of Al compared to Cu is
of approximately 20 years and almost all new 400 kV should be laid that Al has lower density. The cable in Fig. 6 has a stranded Al con-
as cable, Energinet.dk launched a research programme together ductor. Typically, for sections larger than 1200 mm2 of copper and
with the Department of Energy Technology, Aalborg University. 1600 mm2 of aluminium, the conductor has a segmented design
This project has investigated the electrical research challenges of which is commonly known as Milliken conductor [23,24]. More-
undergrounding the transmission system and laid a path, from a over, in order to achieve very high ampacity levels some special
level of knowledge almost only related to the use of cable technol- solutions can be used [25].
ogy for very short lines and towards the nal goal of being able There are two main types of dielectrics for extruded HV and EHV
to design and operate an entirely cable-based transmission system cables, cross-linked polyethylene (XLPE) and ethylene-propylene
with full knowledge of all important design studies and param- rubber (EPR). The difference is that EPR is less sensitive to insu-
eters. The work was carried out by 4 PhD students, a number of lation impurities than XLPE, while XLPE has less dielectric losses
masters students, Energinet.dk employees and Aalborg University. in comparison to EPR. The purpose of the insulation is to ensure
The major ndings of this research study are reviewed in this paper. no electrical connection between the two current-carrying com-
Full insight into every detail can be accessed through the PhD the- ponents of the cable, the conductor and the metallic screen. The
ses [1720] which eventually have led to further work resulting in insulation between the two conducting layers resembles a very
as well a book published [21], as a Cigr technical Brochure [22] long cylindrical capacitor. AC loads will therefore draw a capaci-
and numerous publications of which the most important are used tive charging current IC which is superimposed on the load current.
throughout this paper and listed in the references. The semi-conductive (SC) layers are placed between the insulation
and the conductor and between insulation and the metallic screen.
The purpose of the SC is to make an electrical eld stress optimised
2. Transmission cable system description
transition between potential surfaces of conductor and screen and
the main insulation.
Transmission systems using underground cables differ strongly
Cable models do normally not include SC layers. Instead, the SC
from overhead lines, not only due to their inherent different
layers are considered part of the insulation, where the thickness
appearance, but also their mechanical, electrical and thermal
and the permittivity of the insulation are changed accordingly.
behaviour is highly different. The description in this chapter mainly
The purpose of the cables metallic screen is to have a metallic
originates from [17].
covering used as an electrostatic screening as well as a return path
The use of extruded cables at transmission level began in
the 1960s. Since then, XLPE (cross-linked polyethylene) cables
on higher voltage levels have become more popular than FF
(uid-lled) cables and GF (gas-lled) cables. This is due to less
environmental hazards, as gas or oil leaks are no longer an
issue and lower costs because no external accessories such as
pumping and pressurising systems are needed. A typical HVAC
underground power cable is formed by 4 main layers, namely;
conductorinsulationscreeninsulation. In addition to these main
layers, the cable also has semi-conductive screens, swelling tapes
and metal foil. A cross section of a 400 kV 1200 mm2 XLPE single
core cable is shown in Fig. 6.
The purpose of the conductor is to transmit the required current
with low losses. The transmission capacity of cable systems with
natural cooling is signicantly lower than the transmission capac-
ity of OHL of the same nominal voltage and cross-section, because
of thermal resistance in the surrounding soil. It is therefore often
necessary to use several parallel cable systems, even though such
can increase the risk for resonance circuits. The conductor in HV
and EHV cables is either made of copper (Cu) or aluminium (Al)
where Cu has a lower specic resistance which leads to a smaller Fig. 6. Cross section and layers of a typical XLPE cable [17].
988 C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994

Fig. 7. Cross-bonding scheme for underground cables [17].

for the cables charging current and a conduction path for earth seen that grounding in cable systems can be done by lumped ele-
fault current in case of a fault on the cable [26]. ments, except for some high frequency cases where the substation
To avoid screen over-voltages at cable terminals, the metallic grounding network must be represented with higher resolution in
screen is grounded, except for very short cables not suffering from order to get results, which compares fully to measurements.
unallowable sheath voltages during faults [17]. In normal oper-
ation, the metallic screen will carry the cable charging current, 3. Reactive power compensation
which would result in steady-state losses, due to the metallic screen
being grounded in both ends. Grounding the metallic screen only at Transmission cables high capacitance makes reactive power
one terminal can lead to overvoltage at the ungrounded end. Long compensation a must for cables with a length similar to usual OHL
cables employ cross-bonded screens to lower the losses, see Fig. 7. transmission lines.
By using this cross-bonding method, the induced screen
currents can be largely cancelled, and by grounding in between, 3.1. Reactive power compensation considerations
the screen overvoltage can be reduced. The cross-bonding points
demarcate part of the cable, called a minor section, and the ground- Reactive power compensation design is thoroughly covered in
ing points demarcate a so-called major section. The cables metallic [19,22,30] and the following accumulates the most important nd-
screen is usually formed by a wired screen and a metallic tape (lam- ings.
inate layer), separated by a thin SC swelling tape, but it can also be The reactive power compensation is necessary due to the fol-
made of lead in combination with the above [22]. In some cases lowing reasons:
the screen may also consist only in a metallic tape or a corrugated
sheath. The wired screen and metallic tape are directly connected - Suppress the steady-state overvoltage around the cable line
together both at each junction and cable ends and therefore consid- - Suppress the steady-state overvoltage at the cable open terminal
ered as a single conducting layer in cable modelling. The laminate - Prevent the reduction of the active power transmission capacity
layer is included for water resistance. The swelling tape between both in the cable and system due to the large charging current;
the wired screen layer and the laminate layer is SC in order to however, in order to prevent the reduction of transmission capac-
ensure no potential difference between the two conducting screen ity in the cable itself, the reactive power compensation must be
layers. The two conducting layers are not touching each other in installed along the cable, ideally distributed by several points
order to protect the laminate from mechanical stress because of - Reduce the leading current owing through the line breaker so
bending and for thermal protection. It is common practise when that it becomes lower than the leading current interruption capa-
modelling the screen in EMT-based software to model it as a single bility of the line breaker
solid hollow conductor with the resistivity being a function of both
conducting layers, with a correction done in function of the number When a compensation rate of 100% is adopted, the installation of
of wires as explained in [22]. the cable line does not affect the reactive power balance around the
Cables are usually laid in a at formation in order to improve cable line. Hence, a compensation rate of 100% is usually preferred
heat dissipation and thereby increasing the ampacity, but they may in the planning of cable lines.
also be laid in trefoil formation that is advantageous regarding However, in some cases, the compensation rate near 100%
space, costs and electromagnetic eld issues. cannot be achieved due to the unit size of shunt reactors and near-
The at formation laying and the cross-bonding are sources of power frequency resonances. For example, when a cable line has a
both asymmetric and discontinuous impedances, respectively, and charging capacity 250 MVar, two units of 100 MVar shunt reactors
an electric behaviour which poses additional design efforts as com- may be installed for the compensation, resulting in a compensa-
pared to overhead lines. tion rate of 80%. In order to raise the compensation rate, the unit
Research conducted in the area of dynamic impedance of size needs to be increased to, for example, 120 MVar, but this is not
grounding systems [2729] has proven that the proper representa- always a cost-effective selection as it depends on the manufacturer.
tion of grounding impedance networks is of paramount importance When the compensation rate becomes lower than 100%, it will lead
in order to get correct results when simulating higher frequency to steady-state overvoltage.
dynamics in the time domain and a hybrid MATLAB/PSCAD-EMTDC The low compensation rate also leads to higher temporary over-
method is proposed in [27]. The similar behaviour to this is to be voltage [19]. It is highly recommended to study the temporary
expected for cross-bonded cable systems so attention should be overvoltage in the feasibility study or at an earlier stage as this
paid to a proper representation of ground connections. Such must may affect the decision on the reactive power compensation in the
be assured and validated via measurements in order split occur- planning process.
rence of dynamics between the cable model itself and dynamics Precise reactive power compensation requires the impedances
originating from grounding system and methods. Generally, it is and admittances of the cable to be precisely calculated. Derivation
C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994 989

Table 1 As an example, voltage variations and transmission capacity for


Examples of compensation patterns [19].
an 800 MW power ow is shown in Fig. 8.
Pattern 1 Pattern 2 Pattern 3 Pattern 4 Patterns 1 and 2 provide the same voltage prole, as the only
Sending end 300 Mvar 250 MVar 150 MVar 150 MVar difference is the reactive power of the reactor in the sending end
Middle of line 0 MVar 0 MVar 300 MVar 250 MVar in which voltage is kept constant in the study. As can be seen from
Receiving end 300 MVar 300 MVar 150 MVar 150 MVar Fig. 8, the installation of a shunt reactor in the middle of the line
Compensation rate 100.7% 92.2% 100.7% 92.2% attens the voltage prole and increases transmission capacity. It
should be noted that the actual reactive power ow can be affected
by the network surrounding the cable line. Therefore, the compar-
of theoretical formulas for sequence currents is presented in [31]
ison only gives a relative comparison between the four patterns. In
as the usual formulas given by IEC 60909-2 are for normal bonding
this case, all four patterns showed satisfactory performance com-
and ignore grounding resistance at substations [19]. The devel-
pared to design criteria, hence, pattern 1 was chosen because
oped method is relatively easy to use and gives results which are
very close to sequence currents obtained by means of time domain
simulations. It will be the cheapest solution due to the small number of shunt
reactor units.
It uses only 300 MVar units, which is an advantage in keeping
3.1.1. Maximum unit size of shunt reactors
Maximum unit size can be determined from the allowable volt- spare reactors in stock.
age variation in switching operations, which usually is in the range
of few percent (in Denmark 4%). Shunt reactors connected to the 3.2. Summary of reactive power compensation
400 kV buses are switched in normal operating condition for volt-
age control. In this case, the switching of the shunt reactor should Reactive power compensation can hardly be avoided in laying
not cause voltage variation exceeding the limits. In contrast, shunt realistic length transmission lines as underground cables. The rat-
reactors connected directly to the cable line are generally not ing and location of shunt reactors and whether they are directly
switched for the voltage control since they are installed to meet connected to the line or switchable makes a difference both with
leading current interruption or to suppress temporary overvoltage regards to compensation of reactive power in steady-state oper-
and usually have no circuit breaker. Severe conditions of the net- ation as well as switching states of the cable. The latter can for
work as i.e. off-peak conditions and varying short circuit power instance be switching overvoltage and zero-miss, which is a severe
must be considered [19,30]. condition for the line circuit breaker. These issues are addressed in
later chapters of this paper and part 2 of this paper.
3.1.2. Compensation patterns
In addition to the unit size limitation, the switching of the cable 4. Modelling of long high voltage AC cables
with the shunt reactors should not cause a voltage variation exceed-
ing 4%. This requirement can set restrictions on the compensation 4.1. Introduction to transmission cable modelling
rate.
The following items are considered to determine compensation Chapters II and III as well as the introductory example in chapter
patterns, and they suggest that a compensation rate near 100% is I reveal that a cable transmission line is a highly complex electrical
preferable: machine which behaviour is governed by the laws of physics.
Cable transmission lines are appreciably different than OHL with
- Voltage variation when switching the cable with shunt reactors regards to most electrical and physical quantities. Moreover, we
- Leading current interruption can expect cable systems to perform differently compared to OHL
- Ferranti phenomenon (sustained temporary overvoltage) with regards to switching transients, lightning propagation and
- Voltage prole under normal operating conditions (no-load and harmonic phenomena [32]. The power system sound operation
maximum load) relies on a number of conditions fullled with a certain safety
- Active power losses or margin. Insulation coordination or, in other words, the power
- Effect on transmission capacity systems ability to sustain and survive overvoltage conditions
without short- or long-term damage to the electrical insulation is a
3.1.3. Case example paramount design study to conduct for transmission systems. The
During the design of a new 400 kV line in Denmark, the com- computation of overvoltage in a widespread transmission system
pensation patterns in Table 1 were examined with respect to the demands accurate simulation models of each of power systems
above criteria. Detailed results are to be found in [19]. components. For a long time, models for OHL have been considered

Fig. 8. Consequence of 4 different compensation patterns, left gure showing system voltage along line, and right showing transmission capacity [19].
990 C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994

Fig. 9. The 400 kV cable system for measurement #1 [22].

and validated as being sufciently accurate for the simulation stud- 6 m between the two systems, and 1.3 m below the surface (see
ies used to analyse and thoroughly design a transmission system. Fig. 9).
This is not the case with the models for the cables in a cable-based The measurement setup is shown in Fig. 10. One of the outer
transmission system. A cable can be modelled with simple means phases is energised with an impulse voltage (phase 1), while the
such as the pi-section for non-frequency dependent studies. How- other two phases are grounded through a 500  resistor. A 500 
ever, studies which demand an accurate representation of several load is connected to the receiving end of all phases. All sheaths are
frequencies and need to consider travelling waves must use fre- grounded at the sending and receiving end through a 1  resistor
quency dependent models. The PSCAD/EMTDC software is widely [17]. Core voltages and core currents are measured, and the impulse
used for power system transient simulation and it includes the fre- generator used is a HAEFELY PC6-288.1 surge tester. Sending end
quency dependent phase model (also known as the universal line voltage is set to 4.08 kV 1.2/50 s. The voltage and current were
model [33]). Such models must be trustworthy if one is to trust sim- measured in all three phases at both cable ends.
ulation results. Models can only be trustworthy if they represent the One measurement result, both phase quantities and the asso-
real-life behaviour of the component they intend to model. Ranges ciated modal quantities obtained after mathematical treatment, is
of validity must be known; can one use the model to accurately shown in Fig. 11, which will be seen to provide a very important
predict for instance travelling wave phenomena? The only way to clue to discrepancies between measurements and a PSCAD/EMTDC
validate a model is by using high quality real-life measurements to frequency dependent phase model simulation.
compare with the model output. Hence, we must have credible and Around 50 s, some deviation appears between measured cur-
solid measurement results for cable systems in order to validate rent (black curve in Fig. 11b) and simulated current (blue curve in
the simulation models. Such measurements reveal discrepancies Fig. 11b). This is explained by the presence of the intersheath mode
between model output and the true behaviour of the cables and at exactly the same instant (pink curve Fig. 11a). In other words; the
thereby form the basis for further improvement of the models. presence of intersheath mode current, which is strongly affected
by the actual current distribution in the sheaths, will give rise to a
4.2. Field measurements at transmission cable systems lack of model accuracy. The current distribution in the intersheath
modes is strongly dependent on proximity effect [36] which is not
The thesis by Gudmundsdottir [17] documents four sets of mea- modelled in the simulation model.
surements of sending and receiving end voltages and currents. The presence of cross-bonding points in long cables causes exci-
tation of intersheath modes in a different way compared to having
no cross-bondings [37,38]. This reveals the need for an improve-
#1 400 kV at prole cross-bonded cable system
ment of the simulation model to better represent the intersheath
#2 150 kV tight trefoil single minor section
mode wave propagation.
#3 150 kV tight trefoil single major section
#4 150 kV tight trefoil multiple major section
4.3. Cable model improvement
Methods and results of #1 will be described in the following. Full
details are available in [17,34,35] of which the latter paper describes As suggested by the measurements campaign, one way to con-
both frequency sweep measurements as well as impulse testing. tribute to a better model accuracy, especially at higher frequencies,
The cable line for #1 consists of two parallel three-phase cable would be to make a better model of the screen conductive path. The
systems with a 400 kV single core 1200-mm XLPE cables. The cross screen is usually modelled as a solid cylindrical shell, but as can be
section of the single core cable is shown in Fig. 9. The cables are laid seen from Fig. 9, this is not the case, as the screen is made of a
in at formation with 0.3-m lateral distance between the phases, number of spiralled single conductors and a metallic tape as well
C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994 991

Fig. 10. Measurement setup for obtaining sending and receiving end quantities for a 400 kV cross-bonded cable system [14,22].

as semi-conductive layer. Furthermore, screens can, especially in is needed. This is developed in [17] and relies on dividing the
tight trefoil, be placed so close that proximity effect will play a screen conductor into exponentially distributed sub-conductors
role for the current distribution and thereby for both resistive and (see Fig. 12) and calculating self- and mutual GMD, thereby obtain-
inductive behaviour of the screen. ing an impedance matrix including proximity effect in a way which
The model is improved in two steps: First, the layering of the is similar to the method used in OHLs.
screen is modelled accurately [39] which gives rise to an impedance The mathematical development is lengthy and can be found in
matrix of higher accuracy, yielding a better damping of the simula- detail in [17]. Left to present here is the outstanding accuracy of the
tion results compared to measurements. High frequency damping improved cable model when including layering of the sheath and
still shows to be inadequate, so the next step is to model proximity proximity effect. Validation against measurement #3 is shown in
effect for the screens and include this in the model. Fig. 13.
Secondly, the proximity effect is well-known and can be It is evident that the inclusion of layering of the screen and
included in impedance calculations for a number of simple geome- proximity effect yields a much better resemblance between the
tries. However; the degrees of freedom for the physical location measured results and the simulation (red curve) as the damping
and shape of a cable systems screen conductors put up so many becomes larger when including the proximity effect and the effect
difculties compared to traditional methods that a new approach of layering the screen.

Fig. 11. Comparison of simulated and measured receiving end current (a) modal quantities and (b) phase quantities [17,35]. (For interpretation of the references to colour
in the text, the reader is referred to the web version of this article.)
992 C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994

Fig. 12. Distribution of elements and element types for subdivision of conductors [17].

Fig. 15. Example of TOV due to series resonance [19].

5. Overvoltage analysis
Fig. 13. Comparison of the measured (black) and simulated core current at the
sending end of the energised phase for the single major section cable line. (For 5.1. Introduction
interpretation of the references to colour in the text, the reader is referred to the
web version of this article.) Due to the larger capacitances of cables and the presence of
shunt reactors, temporary overvoltages (TOV) are more likely to
occur in a cable than in an overhead line of equivalent length and
voltage level [22,40]. As a result, phenomena such as the energisa-
4.4. Summary of cable modelling tion of transformers and cables, fault clearances, load shedding and
system islanding can result in TOV with longer duration because of
The most prominent results are that todays state-of-the-art the low frequency [22]. Surge arresters are typically used as coun-
cable models can be trusted for most transient simulation stud- termeasures to TOVs and their energy absorption capabilities must
ies related to overvoltage magnitudes. Todays cable model(s) have be evaluated for these longer TOVs when compared with OHLs.
been proven to be inaccurate when it comes to modelling the inter-
sheath mode. The actual physical layout of the screen is modelled 5.2. Series resonance
more accurately by use of a layered screen, thus resulting in a
more accurate damping of the lower frequencies (below 10 kHz). A scenario that may result in a TOV is the energisation of a
The proximity effect is also included, resulting in more accurate cable near a series resonance circuit, created by the capacitance
simulation results at higher frequencies (above 10 kHz) [17]. of another cable and the inductance of a transformer (Fig. 14).

Fig. 14. Left: Example of series resonance for a cable energisation. Blue dashed line shows the propagation of the voltage into the series resonance circuit: Right: Equivalent
circuit using lumped parameters.
C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994 993

Fig. 16. Example of a parallel resonance circuit created by the parallel of the cable capacitance with the inductance of the shunt reactor, excited by the transformers inrush
current.

Fig. 17. Equivalent circuit of system islanding [19].


Fig. 18. Overvoltage caused by bus fault leading to system islanding [19].

The energisation of a cable generates a transient voltage wave


The equation shows that the resonance component is larger
which frequencies depend on the cables electric parameters,
for low resonance frequencies. Island networks are typically weak
length and bonding arrangements, as well as the busbar short-
networks, meaning a high value of L0 and lower resonance fre-
circuit power [18,22,41]. The voltage waves generated at the
quency (0 ). Under these conditions, a large resonance voltage is
switching propagate both into the cable being energised and the
present, adding to the steady-state voltage resulting in an oscilla-
surrounding system; the magnitude of the voltage in each depend-
tory overvoltage as observed in Fig. 18.
ing on the respective surge impedances. Under these conditions, a
System islanding is unlikely (but not impossible) to occur in
TOV may appear if the natural frequency of a series resonance cir-
meshed networks, such as the European transmission networks,
cuit present in the network is excited by the dominant frequency of
because of their strong redundancy. An exception is the connection
the transient voltage. Fig. 15 shows an example of the phenomenon.
to offshore wind farms. An example of this is the TOV registered
due to system islanding for the Horns Rev 1 offshore wind farm
5.3. Parallel resonance and respective transmission cable after a disconnection of the land
connection [42]. The overvoltage was unusually large because of
A TOV may also be generated by a parallel resonance circuit cre- the converters in the wind turbines [43], but the phenomenon may
ated by a cables capacitance and the inductance of a shunt reactor. also occur with synchronous generators.
A classic example is the energisation of a transformer connected to
a long cable in a weak network (Fig. 16). This generates current har- 6. Conclusions
monics with low frequency, low damping and long duration [19]
that may excite the resonance frequency of the parallel resonance The conclusions are to be found in High voltage AC under-
circuit. Other possible sources of current harmonics are power elec- ground cable systems for power transmission A review of the
tronics, and, in the case of the transmission network, HVDC links. Danish experience, part 2.
Parallel resonances are associated with high impedances and
the circulation of the harmonic currents in the parallel resonance References
circuit is not expected. The exceptions are systems with low short-
[1] E. Kuffel, W.S. Zaengl, J. Kuffel, High Voltage Engineering: Fundamentals, 2nd
circuit power, e.g., a system during a network restoration or weak
edition, Newnes, 2006.
grids. In this case, the impedance of the network seen from the [2] http://www.siemens.com/innovation/en/news/2012/e inno 1204 1.htm.
busbar increases (L0 in Fig. 16) and part of the inrush current ows [3] R.G. Foxall, K. Bjrlw-Larsen, G. Bazzi, Design, manufacture and installation
into the parallel resonance circuit, originating a TOV. of a 525 kV alternating current submarine cable link from mainland Canada to
Vancouver Island, in: Cigre Session, 1984.
[4] http://www.fujikura.co.jp/00/gihou/gihou32e/pdf32e/32e 06.pdf.
5.4. Fault clearing and system islanding [5] M. Rebolini, L. Colla, F. Iliceto, 400 kV AC new submarine cable links between
Sicily and the Italian mainland. Outline of project and special electrical studies,
in: Cigre Session, 2008.
System islanding creates a transient voltage with two compo- [6] R. Benato, A. Paolucci, EHV AC Undergrounding Electrical Power Performance
nents, one at power frequency and a second at resonance frequency, and Planning, 1st edition, Springer, 2010.
which dependents on the grid parameters (e.g., cables capacitance, [7] L. Colla, M. Gabrieli, A. Iliceto, M. Rebolini, S. Lauria, P. Grima, J. Vassallo, B.
Zecca, A. Venturini, HVAC submarine cable links between Italy and Malta. Fea-
short-circuit power, reactive power compensation, etc.), similar to sibility of the project and system electrical design studies, in: 43rd International
an energisation. Fig. 17 shows the single-line diagram of a possible Conference on Large High Voltage Electric Systems, Cigr, 2010.
system islanding which voltage is given by (1). [8] C.G. Henningsen, K.B. Mller, K. Polster, R.G. Schroth, New 400 kV XLPE long
distance cable systems, their rst application for the power supply of Berlin,
in: Cigre Session, 1998.
V (t) = Vm sin(t) sin(0 t)
0 [9] R. Benato, D. Napolitano, Overall cost comparison between cable and overhead
 (1)
line including the costs for repair after random failures, IEEE Trans. Power Deliv.
Em L 1 1 27 (3) (2012) 12131222.
with : Vm = , 0 = + [10] Cigr JWG B3/B1.27, Factors for Investment Decision GIL vs. Cables for AC
L0 (1 2 LC) + L L0 C LC Transmission, Cigr, 2015.
994 C.L. Bak, F. Faria da Silva / Electric Power Systems Research 140 (2016) 984994

[11] K. Sgaard, C.L. Bak, W. Wiechowski, S.D. Mikkelsen, Analysis and simula- [28] Cigr WG C4.501, Guideline for Numerical Electromagnetic Analysis Method
tion of switching surge generation when disconnecting a combined 400 kV and its Application to Surge Phenomena, Cigr, 2013.
cable/overhead line with shunt reactor, in: IPST, 2007. [29] R. Zeng, P. Kang, B. Zhang, J. He, Lightning transient performances analysis of
[12] C.L. Bak, K. Sgaard, Switching overvoltage when disconnecting a combined substation based on complete transmission line model of power network and
400 kV cable/overhead line with permanently connected shunt reactor, in: grounding systems, IEEE Trans. Magn. 42 (April (4)) (2006).
POWER 08, 2008. [30] R. Benato, S. Lauria, F.M. Gatta, L. Colla, M. Rebolini, F. Renaud, Steady-state
[13] C.L. Bak, H. Baldursson, A. Oumarou, Switching overvoltages in 60 kV reactor and transient EHV ac cable shunt reactive compensation assessment, in: Cigr
compensated cable grid due to resonance after disconnection, in: POWER 08, Session, 2010.
2008. [31] T. Ohno, C.L. Bak, A. Ametani, Derivation of theoretical formulas of sequence
[14] C.L. Bak, K. Sgaard, Single-phase AutoReClosure ARC failure on 400 kV com- currents on underground cable system, in: IPST, 2011.
bined cable/overhead line with permanently connected shunt reactor, in: [32] A. Pagnetti, Cable modelling for electromagnetic transients in power systems
POWER08, 2008. (PhD thesis), Blaise Pascal University and University of Bologna, 2012.
[15] F. Faria da Silva, W. Wiechowski, U.S. Gudmundsdottir, C.L. Bak, Full scale test [33] A. Morched, B. Gustavsen, M. Tartibi, A universal model for accurate calculation
on a 100 km, 150 kV AC cable, in: Cigr Session, 2010. of electromagnetic transients on overhead lines and underground cables, IEEE
[16] Technical report on the future expansion and undergrounding of the elec- Trans. Power Deliv. 14 (July (3)) (1999).
tricity transmission grid, Energinet.dk, 2008 https://selvbetjening.preprod. [34] U.S. Gudmundsdottir, B. Gustavsen, C.L. Bak, W. Wiechowski, Field test and
energinet.dk/NR/rdonlyres/CC966C3A-FE78-41D8-9DC7-6B455210B502/0/ simulation of a 400 kV cross-bonded cable system, IEEE Trans. Power Deliv. 26
TechnicalReportSummary.pdf. (July (3)) (2011).
[17] U.S. Gudmundsdottir, Modelling of long high voltage AC cables in the trans- [35] U.S. Gudmundsdottir, C.L. Bak, W. Wiechowski, K. Sgaard, M. Knardrupgrd,
mission system (PhD thesis), Aalborg University Department of Energy Measurements for validation of high voltage underground cable modelling, in:
Technology, 2010. IPST, 2009.
[18] F. Faria da Silva, Analysis and simulation of electromagnetic transients in HVAC [36] B. Gustavsen, J. Sletbak, T. Henriksen, Simulation of transient sheath overvolt-
cable transmission grids (PhD thesis), Aalborg University Department of ages in the presence of proximity effects, IEEE Trans. Power Deliv. 10 (April (2))
Energy Technology, 2011. (1995) 10661075.
[19] T. Ohno, Dynamic study on the 400 kV 60 km Kyndbyvrket Asnsvrket [37] I. Lafaia, Y. Yamamoto, A. Ametani, J. Mahseredjian, M.T. Correia de Barros, I.
line (PhD thesis), Aalborg University Department of Energy Technology, 2012. Kocar, A. Naud, Propagation of intersheath modes on underground cables, in:
[20] C.F. Jensen, Online location of faults on AC cables in underground transmission IPST, 2015.
systems (PhD thesis), Aalborg University Department of Energy Technology, [38] U.S. Gudmundsdottir, C.L. Bak, W.T. Wiechowski, Modeling of long high voltage
2013. AC underground cables, in: The Danish PhD Seminar on Detailed Modelling and
[21] F. Faria da Silva, C.L. Bak, Electromagnetic Transients in Power Cables, 1st edi- Validation of Electrical Components and Systems, 2010.
tion, Springer, 2013. [39] U.S. Gudmundsdottir, J. De Silva, C.L. Bak, W. Wiechowski, Double layered
[22] Cigr WG C4.502, Power System Technical Performance Issues Related to the sheath in accurate HV XLPE cable modeling, in: IEEE-PES GM, 2010.
Application of Long HVAC Cables, Cigr, 2013. [40] L. Leljestrand, A. Sannino, H. Breder, S. Thorburn, Transients in collection grids
[23] Cigr WG B1.03, Large Cross-Sections and Composite Screens Design, Cigr, of large offshore wind parks, Wind Energy (2008).
2005. [41] L.M. Wedepohl, D.J. Wilcox, Transient analysis of underground power-
[24] R. Benato, A. Paolucci, Multiconductor cell analysis of skin effect in Milliken transmission systems system-model and wave-propagation characteristics,
type cables, Electr. Power Syst. Res. 90 (September) (2012). Proc. IEEE 120 (2) (1973).
[25] R. Benato, L. Colla, S.D. Sessa, M. Marelli, Review of high current rating insulated [42] V. Akhmatov, Excessive overvoltage in long cables of large offshore wind farms,
cable solutions, Electr. Power Syst. Res. 133 (April) (2016). Wind Eng. (2006).
[26] G.F. Moore, Electric Cables Handbook/BICC Cables, 3rd edition, Blackwell Sci- [43] V. Akhmatov, B.C. Gellert, T.E. McDermott, W. Wiechowski, Risk of temporary
ence, 1997. over-voltage and high-voltage fault-ride-through of large wind power plants,
[27] C.L. Bak, K.E. Einarsdottir, E. Andresson, J.M. Rasmussen, J. Lykkegaard, W. in: 9th International Workshop on Large-Integration of Wind Power into Power
Wiechowski, Overvoltage protection of large power transformers a real-life Systems as well as on Transmission Networks for Offshore Wind Power Plants,
study case, IEEE Trans. Power Deliv. 23 (April (2)) (2008). 2010.

You might also like