You are on page 1of 54

Data centre energy efficiency metrics

Existing and proposed metrics to provide effective understanding and


reporting of data centre energy

Liam Newcombe Data Centre Specialist Group


Data centre energy efficiency metrics http://dcsg.bcs.org

1 Introduction ........................................................................................................................ 2
2 Summary ........................................................................................................................... 6
3 Overview of metrics ......................................................................................................... 12
4 Data centre energy efficiency .......................................................................................... 15
5 Estimation of fixed and proportional overheads .............................................................. 31
6 Metrics when selecting data centres and equipment ...................................................... 37
7 Monitoring and measurement.......................................................................................... 40
8 Impact of external temperature on data centre efficiency ............................................... 44
9 Glossary........................................................................................................................... 50
10 Acknowledgements ......................................................................................................... 52
11 References ...................................................................................................................... 53

Data centre energy efficiency metrics 1


Data centre energy efficiency metrics http://dcsg.bcs.org

1 Introduction
Whilst there is considerable coverage of IT energy use, despite the work of the European and
other government agencies there is still little hard information on the total size, power
consumption or efficiency of the data centre market. In the absence of this information it is
difficult to defend the data centre industry, predict growth or set effective metrics and targets.
To deal with these issues, properly understand the scale of the problem and deliver
improvements it is essential that an initial set of measurements and metrics is agreed upon
and data collection commenced on a large scale.

1.1 Demands and constraints upon data centre operators


In recent years the commercial, organisational and political landscape has changed
fundamentally for data centre operators due to a confluence of apparently incompatible
demands and constraints.
The energy use and environmental impact of data centres has recently become a
significant issue for both operators and policy makers. Public perception of climate change
and environmental impact has changed substantially, delivering real commercial impacts
for corporate environmental policy and social responsibility. Unfortunately, data centres
represent a relatively easy target due to the very high density of energy consumption and
ease of measurement in comparison to other, possibly more significant areas of IT energy
use. Policy makers have identified IT and specifically data centre energy use as one of the
fastest rising sectors. At the same time the commodity price of energy has risen faster than
many expectations. This rapid rise in energy cost has substantially impacted the business
models for many data centre operators and has already driven changes in the way data
centre capacity is charged for commercially. Energy security and availability is also fast
becoming an issue for data centre operators as the combined pressures of fossil fuel
availability, generation and distribution infrastructure capacity and environmental energy
policy make prediction of energy availability and cost difficult.

Figure 0-1 Demand and constraints on data centre operators

Opposing these constraints are demands from the business consumers of the data centre
services. The underlying growth in demand for IT services to the business is continuing and
now in addition many businesses are looking toward IT systems to reduce their

Data centre energy efficiency metrics 2


Data centre energy efficiency metrics http://dcsg.bcs.org

environmental impact in other areas, e.g. logistics systems for a road transport or tele-
commuting. As businesses have become more dependent upon IT services the
requirements for availability and continuity of services have increased, multiplying the
equipment requirements. This is a particular issue in sectors where regulators cover IT
systems. A failure to understand the relationship between the falling capital cost of IT
equipment and the rising costs of housing and powering it in the data centre is also creating
capacity and financial problems for many operators1.

1.2 Metrics
In this context of rising energy cost, energy security concerns, environmental pressure and
business demand data centre operators will soon be targeted, measured, grouped or
labelled by the efficiency of their facility. Many streams are currently underway both in the
European Union and worldwide to develop and apply efficiency metrics; specifically this
paper investigates the metrics suggested for the EU Data Centre Code of Conduct.
The scope of the metrics discussed in this paper is restricted to the data centre mechanical
and electrical infrastructure. These metrics do not reflect the efficiency with which IT
services, the end product, are delivered to users. This is a clear end goal for a metrics
development work streams and the capability to form part of a holistic set of system metrics
is a core consideration.

1.2.1 Methodology
The DCSG believes that for the industry to make real progress any data centre efficiency
metric will need to be part of a measurement methodology designed to calculate a
reasonable and fair approximation of the total environmental and financial cost of the
service provision from the data centre.

1.2.2 Reporting measures and metrics


Many parties have identified the need for measures or metrics to describe how efficiently
a data centre transfers power from the source to the IT equipment and define what
constitutes an IT load versus what is overhead. For example, the Green Grid have
defined the PUE (Power Usage Effectiveness) and DCiE (Data Centre infrastructure
Efficiency) metrics which have been useful in promoting both the understanding that
there is an issue and enabling further discussion of what effective metrics would need to
describe.

1.2.3 Analysis and diagnostic measures and metrics


Whilst the DCiE metric approach is effective in providing initial recognition of a problem
and helps justify the need to implement energy saving changes this is only half of the
solution. Once the issues are recognised there is a requirement for analysis metrics and
tools to determine why the efficiency is poor and to assist operators in selecting and
making effective financial and environmental improvements. This relationship between
reporting and analysis metrics is shown in Figure 0-2.
The BCS Data Centre Specialist Group has investigated these issues, specifically in a
European context and from the perspective of how the IT hardware interacts with the
data centre (building) infrastructure. In this paper the DCSG will discuss more detailed
proposed analysis metrics for operators that support detailed analysis and prediction of
the impacts of changes, specifically we will present a breakdown analysis of DCiE as;
Facility fixed overhead multiplier
Facility proportional overhead multiplier
These fixed and proportional metrics for the data centre are directly analogous to the
finance concepts of fixed and variable cost and we will use them in a similar way to
understand the real energy and cost behaviour of the data centre and how that impacts
the cost and energy use of operating IT equipment within the data centre.

Data centre energy efficiency metrics 3


Data centre energy efficiency metrics http://dcsg.bcs.org

1.2.4 Stability of metrics


The reporting measures and metrics are measures of performance at a point in time or
averaged performance over the measurement time frame. To show changes in
performance these measures are inherently sensitive to changes and the values are
volatile.
Analysis measures and metrics have the opposite requirement and should to be as
stable as possible for each data centre and as independent as possible of the varying IT
workloads and IT equipment contained within the facility to support effective decision
making and planning.

Figure 0-2 Roles of reporting and analysis metrics

1.3 Phases of metrics development


Many bodies within the industry see IT energy efficiency reporting metrics development for
the data centre in three distinct phases;
1. Data centre infrastructure, specifically how efficiently energy is delivered from the
power source to the IT equipment in the facility
2. IT equipment, how many units of computing (or storage and networking) work can
each IT device deliver per unit of energy consumed
3. Useful work, how many units of useful, end user work can each IT service deliver
per benchmark unit of computing work consumed
There are several development streams underway in phases 2 and 3, to describe the IT
equipment efficiencies (Green Grid DCP, SPECPowera etc) and IT useful work (DESTb)
and in additional metrics to deal with the stages beyond the data centre infrastructure as
shown in Figure 0-2. This paper concentrates on the first of these phases of metrics
although the analysis is informed by the DCSG work on holistic modelling of the data
centre.

a
http://www.spec.org/power_ssj2008/
b
http://www.elsparefonden.org

Data centre energy efficiency metrics 4


Data centre energy efficiency metrics http://dcsg.bcs.org

1.4 Driving behavioural change through per service accounting


To significantly reduce the environmental impact and inefficiency of current data centres
and housed IT services the BCS DCSG believes that it is necessary to enable and drive
change at the demand as well as the supply side of IT. The data centre only exists to house
the IT equipment whose purpose is to deliver IT services to support the business processes
of users or customers; it is not an end in itself. The BCS has been promoting the use of per
service accounting since November 2007.

1.4.1 Relating IT or useful work to business value


Even once metrics have been developed and the information required to calculate them
captured there will still be an issue relating these to business value or using them for
effective comparison of operators. How would we compare the value of a supercomputer
modelling protein synthesis with an online auction site or sales of insurance policies?

1.4.2 Targeting demand


Often facilities and IT departments have little control over the nature of the IT estate and
facility that they manage. This is because most of the services delivered and supported
and frequently the associated IT equipment are dictated by the business units they
support. Finance systems for finance department, HR systems for HR department, etc.
There have been a number of calls recently from pressure groups to make the IT
department pay the power bill for the data centre with the view that this would solve the
IT energy use problem. Unfortunately, applying targets, carbon taxes, incentives or
regulations to the IT departments increases the pressure on the IT department but this
will not necessarily translate effectively to changes in business policy as the IT
department will have to individually sell green solutions and change to each business
unit. To effectively reduce the carbon footprint of IT we should apply the cost and
therefore incentives to those who control or are responsible for the business processes
and creating the IT demand. If we are to transfer the power or carbon bill it needs to go
all the way to the consumer of the service to apply the behavioural change pressure at
the most effective point.

1.4.3 Per service financial and environmental costs


Many of the current approaches and metrics under development are intended to answer
the question what do I get out of my data centre for each unit of energy I put in?. The
DCSG proposes that the industry works instead towards metrics and models that can
answer the question what is the financial and environmental cost of each IT service that
my data centre delivers to support a business process?. Approaching the issue in this
way allows businesses to account effectively for the rising overall cost of IT services
(financial and environmental), rather than the coarse IT budget cost allocation formulas
frequently used. The per-service cost accounting approach allows direct comparison of
each IT service cost with its business benefit.
A common example of why the business unit or owner should be targeted is the issue of
retention of legacy systems, when an IT department requests permission to
decommission an existing service the business owner frequently objects and the service
is maintained. Where an external service provider is used the business unit will frequently
bear the cost of this service directly, thus it is more likely to be decommissioned,
virtualised, or archived to be made available if and when required.
This issue will become more significant with the implementation of business carbon
accounting where IT departments will have to justify their carbon budget alongside their
financial budget. If internal IT departments can be assisted to achieve per-service cost
and energy accounting the carbon and financial costs of each service can be effectively
allocated to the business units responsible for them using an internal market model. This
trend is already underway in the increased proportion of IT departments receiving their
power bill and working to pass this on through internal accounting processes2.

Data centre energy efficiency metrics 5


Data centre energy efficiency metrics http://dcsg.bcs.org

2 Summary
There has been considerable progress in the market in a relatively short time in identifying
data centre efficiency reporting metrics. There is a general consensus developing that the
devices directly involved in delivering the useful work of the facility, that is the IT equipment,
servers, storage, networking and appliances are the energy targets and that any other
consumption of energy such as power conditioning and distribution or cooling is overhead.

2.1 Recommendation to operators


The DCSG recommends to facility operators that energy measurements be taken for their
facility and a combination of the Green Grid DCiE and DCSG fixed and proportional
overheads be used to report on and understand the efficiency of the facility. Operators who
wish to achieve significant cost and carbon reduction should consider extending their
capability to full simulation modelling using an open, independent tool such as that being
developed by the BCS in partnership with the Carbon Trust3 as soon as possible.

2.1.1 DCiE reporting


A time averaged (energy reading) DCiE can be used to report to senior management the
current efficiency of a data centre in a form that can easily be understood Our DCiE is
0.5, which means that only 50 percent of the power we paid for actually went to IT
equipment. This is the primary utility of the DCiE measure.
The DCiE metric is not a fixed value for each data centre; it varies depending upon the IT
electrical load, which is a variable and site specific function of the IT software,
architecture, hardware, load and efficiency. Due to this variability the DCiE is not best
suited to predicting the impact of changes to the data centre or IT and DCiE should be
reported in the context of this caveat. DCiE is not a measure on which decisions or plans
should be based.

2.1.2 Fixed and proportional overhead


Whilst the DCiE provides a useful representation of the achieved efficiency of a data
centre, operators also need a set of analysis metrics that can be used to understand the
behaviour of the facility, its response to changes in M&E or IT equipment and the utility
power used to operate the IT equipment it supports.
To provide operators with an intuitive understanding of energy use the DCSG has found
it useful to represent the energy use of a data centre in two parts, the fixed and
proportional energy use as described in Section 4.6. The fixed energy use of a facility is
the power that would still be drawn from the utility feed if all of the IT equipment were
turned off (without reconfiguring the M&E equipment) whilst the proportional energy use
is the power drawn in response to IT equipment electrical load. These metrics can be
effectively used to determine the impact and ROI of changes such as consolidation and
virtualisation programs as well as select or compare data centre facilities.
The DCSG fixed and proportional overheads are reversible metrics and as stated in the
introduction, part of a measurement methodology that extends beyond the data centre
infrastructure which is designed to deliver per service cost and environmental accounting.

2.1.3 Estimating fixed and proportional losses


The measurements required to determine fixed and proportional losses are the same as
those to determine the time averaged DCiE, the utility power input and the IT power of
the facility at a number of time points. The simple spreadsheet supplied with this paper
can then estimate the fixed and proportional loss values for the facility as well as
analysing and forecasting the DCiE.

2.1.4 Implement energy measurement tools now


Due to the combined pressures of rising IT energy use, rising energy costs and rising
impact of environmental considerations all operators should develop a program of energy

Data centre energy efficiency metrics 6


Data centre energy efficiency metrics http://dcsg.bcs.org

measurement for their facilities. This should, at the very minimum be independent
metering of the utility power to the facility.
There are many sources of variability to the energy use and efficiency of a data centre
including the IT workload and external temperature. These can create quite significant
differences in the measured efficiency of the facility at different times of day or year. For
this reason it is important to measure the total energy used by the data centre and the
total energy delivered to the IT equipment as a long term average as well as recording
the individual data points to obtain useful information4.

2.1.5 Measurement frequency


The two parameters of DCiE, utility electrical energy use and IT electrical energy use
should be measured and logged on an hourly basis, even if this is only with temporary
equipment for a few days each quarter. This provides the basic information necessary to
understand the characteristics of the facility, both to determine the fixed overheads as
described in Section 5 Estimation of fixed and proportional overheads.

2.1.6 IT electrical load and workload


Information from the IT monitoring system should be used to compare hourly readings of
IT electrical load with IT workload as described in Section 7.3. How effectively the IT
electrical load tracks the applied workload provides useful information on the
effectiveness of any power management capabilities, technologies or processes in use in
the data centre. Many operators find that although equipment has power management
capability this is not activated or working correctly and that reconfiguration can yield
substantial benefits. This comparison is particularly relevant when old equipment is
replaced to determine how well the new equipment delivers on power management
promises.

2.1.7 Develop an energy measurement plan and approach


A phased approach to energy measurement, leading to integrated IT and energy
monitoring is described in section 7 Monitoring and .

2.1.8 Provision to the peak power of IT devices


Operators should avoid the legacy approach of provisioning power and cooling to the
nameplate power of IT devices. At a minimum, operators should move to provisioning for
the as configured peak power of each IT device if not statistical or dynamic provisioning
approaches.

2.2 Using metrics to understand marginal energy and cost


With the increasing commercial focus on the energy cost component of IT services there is
demand from IT management and business units to forecast the marginal energy cost of a
change to IT systems. This may be a cost reduction in the case of a decommissioning or
virtualisation program or a cost increase in the case of a new service.

2.2.1 DCiE
As DCiE does not contain any data to separate fixed and variable costs it cannot give
any useful information about the marginal energy or cost of new or reduced IT electrical
load. As a combined, point measure the DCiE of the data centre will change under any
significant change in load.

2.2.2 Fixed and proportional


The proportional overhead measure gives a direct understanding of the marginal energy
or cost of new or reduced IT electrical load.

Data centre energy efficiency metrics 7


Data centre energy efficiency metrics http://dcsg.bcs.org

2.3 Are the proposed metrics effective?


To determine whether the proposed metrics are effective we will assess them both against
their goals and under a range of common use cases to determine where they are effective
in terms of reporting, targets, education, analysis and decision support.

2.3.1 Goals of metrics


To determine whether a metric is effective and meaningful it is necessary to describe the
goal(s) for data centre energy efficiency metrics;

DCSG
Goal DCiE
F&P
Provide a clear, preferably intuitive understanding of the measure Y
Provide a clear, preferably intuitive direction of improvement Y
Describe a clearly defined part of the energy to useful work function of
Y Y
the IT services
Be persistent, i.e. the metrics should be designed to be stable and
extensible as the scope of efficiency measurement increases, rather Y Y
than confusing the market with rapid replacement
Demonstrate the improvements available in a modern design of facility Y Y
Demonstrate the improvements available through upgrade of existing
Y Y
facilities using more efficient M&E systems
Provide a clear, preferably intuitive understanding of the impacts of
Y
changes
Be reversible, i.e. it should be possible to determine the energy use at
the electrical input to the data centre for any specified device or group Y
of devices within the data centre
Be capable of supporting what if analysis for IT and data centre
operators in determining the energy improvement and ROI for
Y
improvements and changes to either the facility or the IT equipment it
houses
Table 2-1 Goals of metrics

As shown in the table neither the DCiE nor DCSG fixed and proportional metrics address
the full set of goals individually but complementary use of the two methods of analysis
meets all of the identified goals.

Data centre energy efficiency metrics 8


Data centre energy efficiency metrics http://dcsg.bcs.org

2.3.2 Comparison of metrics under common use cases


The following table provides an overview comparison of the DCiE/PUE, the DCSG fixed
& proportional metrics and full simulation modelling in a number of common use cases
for data centre and IT operators.

Fixed and Simulation


Task Averaged DCiE
proportional modelling
Effective business
Management Simple value, easy to Slightly more complex
reporting, more
reporting communicate to explain
complex to perform

More complex to More complex to


Assess an Reporting only as an understand but understand but
existing data averaged energy provides better provides detailed
centre reading. understanding, DCiE understanding, DCiE
can be calculated can be calculated
More complex to More complex to
Benchmark
Basic level, prone to understand but understand but
against other
significant errors provides better provides detailed
data centres
understanding understanding.

Cost and energy Weak, prone to


Good indicator of cost Strong indicator of
forecast a data significant errors of
and energy use cost and energy use
centre unknown scale

Marginal cost or Reasonable indicator


Strong indicator of
energy forecast Weak, prone to of cost and energy
cost and energy use
an IT service significant errors of use in conjunction
including effective IT
within a data unknown scale with effective IT
models
centre models
Good prediction of Strong prediction of
Single point indicator, energy use and energy use and
Select a new no information about efficiency under efficiency under
data centre IT load, equipment or varying IT load, varying IT load,
utilisation changes equipment and equipment and
utilisation scenarios utilisation scenarios

Very little information,


Assess changes Good indicator of the Strong indicator of the
difficult to predict the
to IT equipment impact of changes impact of changes
impact of changes

Assess changes
Very little information,
to IT power Good indicator of the Strong indicator of the
difficult to predict the
provisioning impact of changes impact of changes
impact of changes
processes
Weak indicator, ROI
Assess cost or Good indicator, Strong indicator,
likely to be
energy benefit effective ROI effective ROI
overestimated by
of Virtualisation prediction prediction
unknown margin
Assess M&E
Little information,
changes to Poor indicator of the Strong indicator of the
difficult to predict the
existing data impact of changes impact of changes
impact of changes
centre

Table 2-2 Use case comparison of metrics

Data centre energy efficiency metrics 9


Data centre energy efficiency metrics http://dcsg.bcs.org

As before this table shows that a combination of metrics and methods is required to
effectively support operators and improve the efficiency with which IT services are
delivered.

2.4 Efficiency targets for data centres


There have been a number of groups who have suggested that data centres or operators
should be ranked, grouped or targeted using a metric of data centre efficiency. The DCSG
has raised concerns regarding the use of DCiE targets for data centre operators as this
presents the risk of mixed incentives, specifically, the installation of more efficient IT
hardware is likely to reduce the measured DCiE efficiency.

2.4.1 Green Grid proposed DCiE ranking system


The Green Grid recently proposed a ranking system for data centres based on their DCiE
metric5, this ranged from recognised at a DCiE of 0.4 (PUE of 2.5) up to platinum for data
centres achieving a DCiE of between 0.8 and 0.9 (PUE 1.25 1.11). This is a
reasonable set of targets, not only differentiating between facilities on the basis of
achieved efficiency but also providing some high targets to differentiate the best
performing facilities.

2.4.2 Mixed incentives and weighting systems


One issue with the DCiE is that, as the metric is not stable, it presents the risk of mixed
incentives. Specifically, an operator carrying out an energy efficiency program and
reducing their total IT electrical load will probably find their DCiE getting worse due to the
impact of the fixed overheads of their facility.
Some proposals contain a mechanism of weighted bonuses against the DCiE type
measurement for operators who are impacted by this when reducing their IT electrical
load. The DCSG argues that these mixed incentives are simply an aspect of the ranking
system and that ranges of weightings will reduce the value of the rankings.

2.4.3 Resilience and compensation factors


Operators running higher resilience facilities of older design can suffer from higher fixed
overheads and therefore lower efficiency. There have been suggestions that higher
resilience facilities should have some fudge factor applied to improve their efficiency
score.
There are many issues with this proposal;
This weighting is unfair to operators who have taken the decision to build at
lower resilience levels to improve their energy efficiency.
We would not subsidise the capital cost of an operator choosing higher
resilience, this is a cost versus requirements decision. Equally the efficiency
penalty should remain as an incentive to only use effective and appropriate
designs justified by the business requirements
The combination of lower fixed losses in modern M&E equipment and modular
deployment substantially reduces the efficiency penalty of 2N+ resilience
The DCSG rejects the proposal of weightings based on resilience level as it would
substantially devalue any ranking system at the same time as creating greater mixed
incentives than those described above.

Data centre energy efficiency metrics 10


Data centre energy efficiency metrics http://dcsg.bcs.org

2.4.4 Age of the facility


The major differentiator in efficiency between facilities is the age of the facility and the
M&E equipment installed. As there is a substantial embedded manufacturing and
disposal energy cost in both the physical building and the infrastructure, ranking systems
that reward building a new facility when the overall environmental impact is negative
would be counterproductive.
To mitigate these issues, if targets are to be set for operators then separate targets for
existing and new build facilities should be set. These targets should then be
progressively tightened based on reporting data from the market. This also creates an
incentive for M&E component vendors and data centre builders to determine the
embedded energy costs of their products to justify the replacement of old facilities on
effective environmental grounds.

2.4.5 Geographic weighting


During the review period for this paper the DCSG received a significant number of
comments on the matter of Geographic weighting.
The external ambient temperature and humidity can substantially affect the available
efficiency of a data centre. Some operators who are already monitoring their energy
efficiency have been able to show significant seasonal variations in their efficiency due to
external temperature. See Figure 1 in Enabling the Energy-Efficient Data Center6 for an
example of this. The fresh air and economised cooling technologies are particularly
impacted as they require the external temperature to be lower than the set cooling plant
temperature to operate in their high efficiency modes.
Whilst some operators have flexibility in the location of their data centres this is not a
general case, a Telecom operator for example has very little choice. Due to this issue
there is considerable discussion over whether to apply external climate weighting factors
to data centre infrastructure efficiency targets. The concern is that un weighted targets
would unfairly penalise data centres in warmer climates
This is essentially a policy rather than a technical matter, therefore the DCSG makes no
recommendation.

2.4.6 DCSG recommendation


The DCSG recommends that the DCiE metric be understood as a partial metric
representing only the data centre infrastructure and that any ranking or targeting program
be provisional until effective, holistic systems of metrics or models have been
implemented. Weighting factors for level of resilience or improvement in overall IT
electrical load are unnecessary and will weaken any target or ranking system.
Operators should also separately report their total IT and Utility energy use, the
components of the DCiE to show any changes in their IT and overall energy use.

Data centre energy efficiency metrics 11


Data centre energy efficiency metrics http://dcsg.bcs.org

3 Overview of metrics
There is considerable opportunity for improvements in ICT and specifically data centre energy
efficiency, in order to realise these potential improvements it is important to provide not only
reporting measurements or targets but also analysis metrics and tools that assist operators in
understanding their facility and the impacts of their choices.
In this section we discuss the scope of current metrics, the development path to holistic
metrics and some of the issues with the DCiE metric, specifically why it is a reporting metric
and should not be used to make decisions about a data centre or to build a business case for
any data centre or IT changes.

3.1 Limited scope of metrics in this paper


The metrics described in this document focus on the data centre building and the
mechanical and electrical equipment housed within it. These efficiency measures and
metrics are therefore not intended to be an effective description of the efficiency with which
IT services are delivered from the facility and should not be mistaken for holistic metrics.

3.1.1 Comparing operators on data centre infrastructure metrics


It is not possible to compare the delivery efficiency of two operators based solely on
their data centre infrastructure measurement. This is only one component of the delivery
chain and does not reflect the efficiency achieved by the IT equipment, software or
systems architecture.

3.1.2 Metrics considered


In this paper we consider the current Green Grid metric, the data centre infrastructure
Efficiency (DCiE) along with the proposed DCSG analysis metrics, the data centre fixed
and proportional overheads.

3.2 Holistic IT efficiency metrics


There is a clear goal for IT efficiency metrics to be able to report and predict the energy and
financial costs of delivering IT services to the user base as described in the introduction.
Both business cost modelling and internal or external carbon markets will require this level
of capability to deliver effective management information about IT services. This goal
requires data centre infrastructure analysis metrics that are reversible and independent of
the IT equipment to determine the total energy use of an IT device or devices within the
measured data centre.

3.2.1 Chained component level metrics


There have been a number of chains of individual, single value, measures and metrics
proposed to indicate the efficiencies of the various layers of the IT delivery, software
efficiency, IT hardware utilisation, IT hardware efficiency and data centre efficiency.
Some of these have proposed that the product of the component metrics is descriptive of
the overall efficiency.
The DCSG argues that this is a flawed approach and should be avoided by operators as
the results are at best misleading. These metrics are particularly weak in any form of
economic analysis and should not be used to try and determine marginal cost. The BCS
DCSG has demonstrated by holistic system modelling that these layers interact in a
more complex way than is captured in these single value layered metrics.

3.3 Why we need analysis metrics in addition to reporting metrics


Effective sets of metrics should educate and inform the data centre operator and provide
enough information to predict the cost and energy impacts of equipment, load or process

Data centre energy efficiency metrics 12


Data centre energy efficiency metrics http://dcsg.bcs.org

changes. Once reporting metrics such as DCiE have identified an efficiency issue we
require metrics with analysis capabilities to enable operators to make the practical
decisions required in selecting a new, or improving the efficiency of an existing, data centre.

3.3.1 Why fixed and proportional overhead metrics?


Fixed overhead drives an understanding of the committed power to a facility. High fixed
overhead facilities should be upgraded, partially decommissioned or filled as close to
capacity as possible to minimise the impact of the fixed losses.
Proportional overhead provides the understanding of how the utility energy use will vary
with the IT equipment energy use, specifically what reductions can be expected if the IT
electrical load is reduced.
Fixed and proportional overhead scalars provide a more intuitive understanding of the
facility efficiency to operators, particularly where modular provisioning is used and these
scalars change incrementally as infrastructure is installed or enabled.

3.3.2 Vehicle metrics comparison


Whilst the DCiE and PUE metrics are attractive for their simplicity this also presents a
significant issue if we wish to take decisions based upon them. The metric is a
management report where three dimensions of data {time, IT load, utility load} have been
reduced to one and decision making information has, necessarily, been destroyed in the
process. If we take the analogy of the fuel efficiency and load carrying capacity of three
different vehicles we can demonstrate this issue. If we take three vehicles, a 38 ton
articulated lorry, a four ton Luton van and a family hatchback and multiply their miles per
gallon rating by their load capacity in tons we get their ton miles per gallon load transport
efficiency.

38 ton 4 ton Luton Family


articulated van hatchback
Fuel economy 8 30 60 MPG
Load weight 30 3 0.5 Tons
Ton miles per
Load economy 240 90 30
gallon

Table 3-1 Comparison of vehicle fuel economies and load capacities

In the above table, if we only consider the ton miles per gallon metric it is clear that we
should all buy 38 Ton articulated lorries to do our shopping. The issue is that we have
discarded the information that tells us which is appropriate for our use and the metrics
are now likely to lead us to the wrong conclusion.

3.3.3 IT equipment consolidation comparison


The DCiE metric can produce mixed incentives as we can show with an IT equipment
consolidation example. In this example an operator with a data centre with a design DCiE
of 0.6 expends significant capital, operational expense and tolerates migration risk to
reduce the power use of their primary service platform. This platform is several years old
and the IT equipment draws 200kW at the PSU, the new platform the service is migrated
to is significantly more efficient, drawing only 50kW at the PSU.

Data centre energy efficiency metrics 13


Data centre energy efficiency metrics http://dcsg.bcs.org

Before After
Design DCiE of facility 0.6 0.6
Fixed utility load of facility 100 100 kW
Rated IT load of facility 500 500 kW
Fixed loss multiplier 0.2 0.2 W/W
Proportional loss multiplier 1.5 1.5 W/W
Rated utility load of facility 850 850 kW

IT electrical load 200 50 kW


Proportional electrical load 300 75 kW
Total utility load 400 175 kW
Achieved DCiE 0.5 0.29
Table 3-2 Results of data centre consolidation program

As shown in the table and graphs the


facility has a fixed overhead of 100kW,
a rated IT electrical load of 500kW and
would draw 850kW from the utility feed
at full rated IT load.
The operator had measured their DCiE
at 0.5 before the program and
therefore predicted a 4:1 reduction in
utility power to match the reduction in
IT power, the power reduction
measured after the consolidation is
only 2.3:1 which impacts the business
case and ROI point.

This is due to the combination of the


fixed overhead of the data centre not
changing with the IT load and the IT
load multiplier being only 1.5 not 2 as
suggested by the DCiE. The final
problem for this energy conscious
operator is that when the expected
reductions in utility power are not
realised and the DCiE of the facility is
measured again it has fallen to 0.29
even though the utility power draw has
been reduced by more than half.
The fixed and proportional analysis technique provides a far more effective understanding
and forecast of the impacts of the response of the data centre to the consolidation exercise.
This both allows a more effective ROI prediction and clearly demonstrates the need to tune
the M&E infrastructure to unlock the full benefits of the IT equipment consolidation.

Data centre energy efficiency metrics 14


Data centre energy efficiency metrics http://dcsg.bcs.org

4 Data centre energy efficiency


A key part of national Market Transformation Programs and the EU Code of Conduct for Data
Centres is to create effective incentives and reporting measures for the efficient use of energy
in IT. It has been identified that a measure of data centre to IT equipment energy transfer
efficiency is key to driving understanding of the energy and cost inefficiencies in current data
centres and thus key to changing the behaviour of IT operators.

4.1 Power use in the data centre


The data centre is a complex environment that is designed to house IT equipment. Utility
power entering the data centre has to pass through a number of stages of voltage
transformation, distribution and cleaning before finally being delivered to the IT equipment.
Most of the power used within the facility is converted to heat, requiring significant cooling
system capacity which draws an additional load in a traditional, recirculating air data centre.
There are also a number of ancillary support systems in the data centre such as lighting,
generator pre-heaters, fire suppression systems as well as human occupied areas which
also require electrical power.

Figure 4-1 IT power delivery path and losses in the data centre

Figure 4-1 shows a simplified representation of the power delivery and loss path in a data
centre. Utility power enters the building on the left and passes through the power delivery
chain to the IT equipment on the right. Each stage in the delivery chain has inherent losses,
shown by the red arrows as well as the specific overheads shown as their own paths.
The actual implementation of a data centre is considerably more complex than in this
diagram and detail such as whether the CRAC units are fed from the UPS may vary. This
diagram is provided to provide a general understanding of how power flows through the
facility for the reader.

Data centre energy efficiency metrics 15


Data centre energy efficiency metrics http://dcsg.bcs.org

4.2 Green Grid data center infrastructure efficiency metric


The metric that is currently used in the working draft of the EU CoC is a version of the data
center infrastructure efficiency (DCiE) metric originally recommended by the Green Grid.
This metric has been selected as it does not consider the IT equipment or software
efficiency for which we do not yet have metrics or units and as such offers the possibility of
comparing the data centre buildings. This metric concentrates on the proportion of the utility
electrical load presented by the data centre that is delivered to the IT equipment housed by
that facility. In the EU Code of Conduct the measurements are of energy consumed per
month rather than instantaneous power readings.

4.2.1 DCiE definition


The Data Center infrastructure efficiency metric is defined as the fraction of the IT
equipment power divided by the total facility power;
IT Equipment Power
DCiE =
Total Facility Power
The total facility power is defined as the power measured at the incoming utility meter.
The IT equipment power is defined as the power consumed by the IT equipment
supported by the data centre as opposed to the power delivery and cooling components
and other miscellaneous loads. For a full description of DCiE see the Green Grid paper
on DCiE and PUE7.
There is a view that devices such as KVM switches and monitors represent overhead
and not devices directly involved in delivering the useful work output of the facility. The
DCSG supports this view in principle and agrees that such devices should, when
reporting granularity allows, be excluded from the IT equipment power part of the
calculation.

4.2.2 Power usage effectiveness


The PUE metric is simply the reciprocal of the DCE metric;
1 Total Facility Power
PUE = =
DCE IT Equipment Power

Data centre energy efficiency metrics 16


Data centre energy efficiency metrics http://dcsg.bcs.org

4.3 Data centre IT power to utility power relationship


As described above, in order to understand, measure or model the overall energy efficiency
of a data centre it is necessary to understand the relationship between electrical load of the
housed equipment and the utility power the facility draws to power and cool the housed
equipment.
The power used by the IT equipment in a data centre is delivered through a series of power
conditioning and distribution devices, each of these exhibits inefficiency and thus a certain
amount of power is lost. As this equipment is typically housed within the data centre these
losses, converted to heat, add to the heat output from the IT equipment. This total thermal
output must then be handled by the HVAC systems.
The graph in Figure 4-2 shows a power transfer function for a 2N+1 resilient (Tier 4) data
centre with a rated 1MW IT load. The power drawn by the data centre from the Utility feed
is determined by taking the IT power draw and then applying sequence the losses of each
component within the mechanical and electrical infrastructure. In this relatively simple
model the inefficiency loss of each component is composed of three factors;
Fixed losses, devices such as the CRACs and UPS have a fixed load component
as soon as they are turned on, before any IT equipment is supported. For example
in a UPS there is the battery charge maintenance power.
Proportional losses, these losses are proportional to the load drawn through the
device. In a chiller this would be the compressor pumps that switch on and off
dependent upon the cooling load.
2
Square law losses, these are frequently I R electrical losses which are
proportional to the square of the current carried. This type of loss occurs, for
instance, in transformers and cabling.
The example 2N+1 resilient data centre used in this paper is derived from the following data
centre equipment loss parameters;

Rated power Proportional Square law


Device Fixed losses
(Watts) losses losses
Cabling and switchgear 1,000,000 0.0% 0.0% 1.5%
Power distribution units 1,600,000 0.5% 0.0% 0.5%
Uninterruptible power
1,100,000 2.0% 2.5% 5.0%
supply
Computer room air
1,200,000 10.0% 1.5% 0.0%
conditionersc
Chiller plant 1,500,000 5.0% 30.0% 0.0%
Transformer 2,100,000 0.5% 0.0% 2.5%
Table 4-1 Data centre equipment loss parameters

The fixed losses are particularly significant in this type of design as the 2N+1 resilience
doubles the impact of the fixed losses of each component, although this is partially offset by
the reductions in square law losses achieved by running the equipment below rated loadd.

c
Note that this is a simplistic model for CRAC and chiller plant but provides a useful
approximation at this point. A more detailed model is used later in this paper
d
Note that as the fixed losses of data centre M&E equipment improve the reductions in
square law and other losses in 2N and 2N+1 facilities start to offset the increased fixed
losses, reducing the overheads inherent in 2N type infrastructure resilience.

Data centre energy efficiency metrics 17


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 4-2 Data centre overall power transfer function

The graph shows the increasing power requirements at each stage of the delivery chain,
note that due to the fixed loads in the delivery chain such as UPS battery maintenance
power and CRAC fan power the data centre would draw a significant proportion of its peak
power even if all of the IT equipment were turned off. For instance, the figure above shows
that at zero IT electrical load the data centre would draw around 670kW.

4.3.1 Fixed overheads drive proportional overheads


It is not only the fixed load overheads that impact the fixed load power draw at zero IT
electrical load. The fixed load overheads of devices in the power and cooling chains,
such as the UPS create an electrical load upon their parent devices as well as heat and
therefore drive further proportional and square law losses in the power and cooling
systems, increasing the zero load fixed overhead beyond that of the individual fixed
losses.

4.3.2 Chiller efficiency and external temperature


Most data centre HVAC systems are impacted by both the internal and external air
temperatures. The efficiency of the chiller pumps typically improves as the external
temperature falls. This is particularly significant where air or water side economisers or
fresh air cooling systems are used to reduce cooling energy use. The analysis presented
in this section uses an averaged external temperature for simplicity. Section 8 examines
the impacts of external temperature in more detail.

4.3.3 Reductions in fixed overhead through operator actions


The graph in Figure 4-2 does not represent the reductions in fixed overhead that can be
achieved in a data centre that is only partially filled where CRAC units or other M&E
infrastructure components may be turned off in unoccupied areas. However, it does
provide a reasonable representation for the purposes of evaluating the impact of lower
power or variable power equipment replacement programs within an existing facility.
There are very substantial efficiency gains possible in a partially occupied data centre
from such measures as well as modular UPS and chiller systems that are scaled as IT
equipment is installed. These measures are investigated later in this paper. See
Electrical Efficiency Modelling of Data Centers8 for a more detailed analysis and
description of these loss functions.

Data centre energy efficiency metrics 18


Data centre energy efficiency metrics http://dcsg.bcs.org

4.4 DCiE & PUE metrics


The data centre modelled in 4.3 would achieve a DCiE of 0.5 or a PUE of 2.0 at the full
1MW rated IT load. This, of course is unlikely to ever be achieved as this would require that
the facility IT electrical load be 100 percent of the rated IT electrical load. This would
require that the facility be fully provisioned at the IT equipment peak power rating, not
nameplate power ratings and that all IT equipment be at full power draw simultaneously
which would normally be recognised as a failure in capacity planning.

IT electrical load DCiE PUE


0% 0.00 5996226.8
5% 0.07 13.4
10% 0.14 7.4
15% 0.19 5.4
20% 0.23 4.4
25% 0.27 3.8
30% 0.30 3.4
35% 0.32 3.1
40% 0.35 2.9
45% 0.37 2.7
50% 0.39 2.6
55% 0.40 2.5
60% 0.42 2.4
65% 0.43 2.3
70% 0.44 2.3
75% 0.45 2.2
80% 0.46 2.2
85% 0.47 2.1
90% 0.48 2.1
95% 0.49 2.0
100% 0.50 2.0
Table 4-2 Data centre DCiE and PUE by IT electrical load

As shown in the table above and the graphs below, both the DCiE (Figure 4-3) and the
PUE (Figure 4-4) are non linear functions and are significantly influenced by the IT
electrical load in the data centre.

Figure 4-3 Data centre infrastructure efficiency by IT electrical load

Data centre energy efficiency metrics 19


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 4-4 Data centre power usage effectiveness by IT electrical load

This presents an issue with the use of DCiE and PUE metrics as the IT electrical load at
which they should they be measured for each facility is not defined.
If the DCiE or PUE is to be measured and reported by data centre operators there is an
incentive to measure this at maximum IT electrical load to optimise the result whilst if IT or
utility electrical load is to be reported as has also been suggested, the incentive would be to
measure at the lowest power point, where the DCiE is at its worst. This presents a conflict
in measurement objectives and approaches and would require the definition of some sort of
standard load profile which is unlikely to effectively represent the range of data centres
and their utilisation.

Point measurements of a non-linear function


The basic issue with the PUE and DCiE metrics is that they are point measurements of a
non linear function, a single data point is not sufficient to describe this function or
effectively compare between facilities. This issue is compounded by the varying
utilisation of the facilities and IT electrical load within each facility.
This can be addressed by measuring the total energy use of the data centre and IT
equipment as a long term average in addition to the point measurements. The level of
variation in the point measurements is useful and informative data in itself.

4.5 IT equipment power draw


Load to power linear IT equipment
Many component and system vendors are currently expending considerable effort in the
development of new IT devices whose power draw is far more linear with their IT
workload than currently installed equipment. This extends beyond hardware and into
software solutions such as VMWares VMotion which provides the capability to move
working virtual servers under load to optimise the IT load on servers or server blades and
shut down unused blades when aggregate workloads fall.
The use of virtualisation technologies can also provide significant benefits in reducing the
overall IT equipment power draw as well as the provisioned power to IT equipment.
Whilst these approaches reduce the IT equipment electrical load and the overall utility
load at the data centre they also, unfortunately, tend to reduce the measured DCiE of the
facility

Data centre energy efficiency metrics 20


Data centre energy efficiency metrics http://dcsg.bcs.org

Variable IT electrical load


As these new generation devices are installed by data centre operators the IT electrical
load will become more variable, spanning a larger minimum and maximum power
consumption range and exacerbating the problem of measuring overall data centre
performance with a single point measure such as DCiE.

4.6 Fixed and proportional overhead metrics


The key factor that influences the DCiE is the fixed load overhead of the facility. One
approach to clearly representing this issue in an easily understandable form that the DCSG
has used is to represent the facility power draw in two components, the fixed and variable
power draw. This is represented by the fixed and proportional overheads. Whilst there is
some non-linearity from the square law losses these are dominated by the fixed and
proportional losses, allowing this representation to be an effective indicator for operators as
shown in Figure 4-5.

Facility PowerZero The power drawn at the Utility feed at zero IT electrical load
Facility PowerFull The power drawn at the Utility feed at full IT electrical load
Rated IT Load The rated IT electrical load of the facility
Facility PowerZero
Fixed Overhead =
Rated IT Load
Fixed overhead has no units as the component units are Watts / Watts.

Facility PowerFull Facility PowerZero


Proportional Overhead =
Rated IT Load
Again, proportional overhead has no units as the component units are Watts / Watts.

Once these two values are determined for the facility the two loss components can be
plotted together, in the case of the data centre example from 4.3 these are;
Fixed Overhead = 0.65
Proportional Overhead = 1.41
Note that these two values sum to the PUE at full IT electrical load of 2.06.

Figure 4-5 Data centre power transfer as fixed and proportional losses

Data centre energy efficiency metrics 21


Data centre energy efficiency metrics http://dcsg.bcs.org

Slope and intercept measurement of the power transfer function


By considering the data centre overheads to be formed of a fixed and proportional
component we are able to approximate the power draw of the facility in terms of the IT
power draw with the two values of fixed overhead (intercept) and proportional overhead
(slope).
Whilst there are non-linear elements in the proportional power function these are
dominated by the linear elements. The linear proportional overhead is a useful estimator
to the true variable overhead as it provides an effective first-cut analysis and prediction of
the data centre behaviour. If additional accuracy is required then a full simulation model
such as that being developed by the BCS3 should be used.

4.7 IT equipment provisioned power and facility fixed overhead


When IT equipment is installed into a data centre power and cooling are provisioned or set
aside for that equipment. This is typically for the nameplate, or power supply maximum of
the equipment although this practice is being superseded by provisioning to the peak power
draw of the device in its installed configuration.
As each facility has a maximum total IT electrical load capacity, the power and cooling
provisioned to each device represents a proportion of this facility capacity and therefore can
be considered to represent a proportion of the facility fixed overhead. Our analysis shows
that in many existing facilities the fixed power overhead allocated to a server exceeds its
peak PSU power draw and can become the dominant factor in the server energy use and
cost.

Fixed overhead as a motivator to change provisioning processes


Representing this allocation of the fixed overheads in terms of the provisioned power to
the device is also an effective motivator to operators who are still nameplate power
provisioning to change their processes as there is a direct cost and energy benefit from
doing so as well as being able to fully utilise the rated IT electrical capacity of the facility.

4.8 IT device power under data centre overheads


The second significant use for data centre efficiency metrics is to allow operators to
understand the utility electrical load that an IT device such as a server is responsible for.
This will be of particular significance in the EU once carbon accounting and carbon cap and
trade mechanisms come into force as both IT departments and service providers will be
pushed toward carbon and cost accounting of the IT services they deliver.

IT Device power characteristics


For this example we will choose a commodity x86 1U rack server representative of those
from major manufacturers. This is a typical corporate server for a single application
deployment with two x86 processors and 2 local hard disks, although the power
characteristics are unsurprisingly similar to a dual processor blade.

Server power data


Server provisioned power (nameplate) 700 Watts
Server zero IT workload power 200 Watts
Server peak power 350 Watts
Table 4-3 Server power data

This server exhibits a fairly high minimum power though there are many significant and
useful efforts already underway within the industry to reduce this and produce devices
that exhibit a far more linear relationship between IT workload and PSU power draw as
described in 4.5.

Data centre energy efficiency metrics 22


Data centre energy efficiency metrics http://dcsg.bcs.org

4.8.1 IT device utility electrical load


The PSU power draw value is not sufficient to determine the overall energy used by an IT
device in delivering a service, for either device comparison or carbon accounting
purposes. What is necessary is to be able to determine the utility electrical load the
device is responsible for within the data centre housing it.
This can be approximated by breaking the device power into two components, the fixed
and proportional power draws at the utility feed.

Fixed Utility Draw = Fixed Overhead Provisioned Power


Proportional Utility Draw = Proportional Overhead PSU Drawn Power

These two values can then be summed for any workload value to determine the utility
electrical load required to power and cool the server in the data centre.

Figure 4-6 Server utility power draw by fixed and proportional overheads

Figure 4-6 above shows the power drawn by the server defined in Table 4-3 across the
range of applied IT workload, for the example data centre with a fixed overhead of 0.6
and proportional overhead of 1.4. The mauve area shows the servers power draw
ranging from 200W to 350W at the plug whilst the yellow area shows the proportional
losses of the data centre applied to the servers power draw curve, including the
proportional losses the server power now varies from 284W at idle to 497W at full load.
We can determine the fixed utility load of the server by allocating a proportion of the
facility fixed power draw based upon the proportion of the facility rated IT electrical load
that is provisioned to this servere. This server uses a standard, hot swap power supply
module rated at 700W, even though its peak draw, as configured is only 350W. With this
nameplate power of 700W the purple blue area shows that even when turned off, the
provisioned power multiplied by the fixed overhead gives a draw of 441W at the utility
feed, this is substantially more than the peak draw of the server.
To determine the overall utility power for this server we add the fixed and proportional
loads together. The servers total utility draw at the idle PSU draw of 200W is 737W
whilst at the full load PSU input of 350W the utility draw is 949W as shown by the blue
line.

e
Note that in the DCSG data centre model the overall utilisation of the facility is also taken
into account and that the fixed overheads of IT devices in a partially utilised data centre can
be much larger.

Data centre energy efficiency metrics 23


Data centre energy efficiency metrics http://dcsg.bcs.org

4.8.2 Prediction of IT device power savings


Another key use for any data centre power transfer efficiency metric is to assist in
forecasting the energy use and cost of operating an IT device as well as the savings
available from new, lower power or power linear equipment.

Figure 4-7 Server power draw by fixed and proportional overheads vs. PUE

Unfortunately, as shown in Figure 4-7 the fixed and proportional overhead approach
produces a significantly different result to simply multiplying the servers power draw by
the power usage effectiveness (PUE) of the data centre. This is shown for both the
design PUE by the red line and the achieved PUE at the operating IT electrical load by
the orange line. The PUE and DCiE are not able to account for the difference between
the provisioned power and the actual power drawn, or the fixed power floor of the data
centre and significantly underestimate the power drawn. Further the PUE and DCiE can
be misleading and may seriously overestimate the power savings at utility feed. This will
lead to overestimated ROI for low power IT equipment, which could damage operator
confidence in these technologies as described in 3.3.3.

4.8.3 Failure to achieve design PUE


It will be in the interests of any data centre designer to quote the best efficiency for a new
facility design, due to the presence of fixed overheads this is likely to be at 100% rated IT
electrical loadf. Unfortunately the data centre is unlikely to ever operate at full IT electrical
load as this would require that it was fully provisioned and that all equipment
simultaneously drew its full provisioned power which would, in most instances constitute
a failure in capacity planning. This is particularly unlikely in a nameplate provisioning
scenario where the IT devices will never reach their full provisioned power. The second,
orange line in Figure 4-7 shows the more likely achieved PUE of 3 (DCiE of 0.3 &) for this
facility once fully provisioned. As shown the server utility electrical load does intersect the
PUE calculated value at the mean IT workload but diverges significantly on either side.
This error will increase as vendors improve the power to load linearity of new IT
equipment.

f
For traditional chiller technologies, facilities with variable speed pumps, air or water side
economisers may achieve optimum performance below 100% rated IT electrical load.

Data centre energy efficiency metrics 24


Data centre energy efficiency metrics http://dcsg.bcs.org

4.9 Data centres run below capacity


When a new data centre is provisioned one of the defining measures is the total rated IT
equipment load, although this is also frequently expressed as Watts . It is not
m2
uncommon to build a data centre with sufficient capacity to meet several years worth of
expansion, resulting in the facility operating at a fraction of its rated IT electrical load for
considerable part of its operating life.
Much of the large infrastructure of a data centre such as the air conditioning and UPS only
achieves optimum efficiency at close to 100 percent load. If the load presented reduces
then the facility overhead increases. This issue is exacerbated by the high levels of
redundancy in a typical data centre with 2N or 2N+1 resilience, components such as UPS
are frequently operating at less than 30 percent of their rated load which substantially
increases the impact of the fixed loss overheads, see section 6.1.1 for an example of this
issue.

Allocation of fixed load overheads


The fixed load overhead of the data centre does not change with the IT equipment load.
To understand the energy use and cost for IT equipment in the data centre both the fixed
and proportional overheads must be considered in the same way that fixed and variable
costs would be treated elsewhere in business finance. There are two basic approaches
to the allocation of fixed load, one is the proportion of the rated IT electrical capacity that
is provisioned to the device and separate accounting for the overheads of the unused
capacity, the second is the proportion of the total provisioned capacity that is allocated to
the deviceg. Either of these approaches drives an understanding of the energy and cost
implications of a partially utilised facility with high fixed load overheads, thus driving
behavioural changes in operators.

Installed estate vs. efficient new M&E equipment


Whilst many M&E equipment vendors are now producing equipment with very
substantially improved fixed and proportional losses, these still have overheads and will
not replace the installed estate of equipment in working data centres for several years.

Failure to realise the benefits of load to power linear IT equipment


Another issue for both vendors and operators is to develop the operator understanding
that it is necessary to address the data centre fixed overheads in order to realise the full
benefits of the power savings offered by the new IT equipment they are installing.

4.9.1 Modular data centre infrastructure


Many M&E equipment vendors and data centre design and build specialists are now
producing modern, modular designs for data centres. These designs allow the operator
to scale their M&E infrastructure in a more linear fashion to meet the IT load and
utilisation of their facility. This represents a significant improvement in both the cost
profile and efficiency of these facilities as the equipment will be running closer to rated
load, thus minimizing the fixed loss overheads. An important secondary benefit of this
approach is that the M&E infrastructure is more likely to be of the same technology
generation as the IT equipment it supports and therefore more likely to deliver efficient
and effective service.
The graphs below, in Figure 4-8 and Figure 4-9 both show the same data centre,
measured with both DCiE and fixed & proportional overheads.

g
The DCSG data centre simulator provides both methods of cost allocation.

Data centre energy efficiency metrics 25


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 4-8 Data centre fixed and proportional losses under modular provisioning

The graph in Figure 4-8 shows the data centre from section 4.3 with the same inefficient
M&E equipment but this time the M&E equipment provider uses modular provisioning of
the PDU, UPS, CRAC and chiller systems in 200kWh steps for rated IT electrical load.
This provides substantial efficiency improvements in the early years of the facility
operation where the facility is at low utilisation as well as reducing initial capital costs and
improving flexibility. Whilst more complex than just the two values of fixed and
proportional, this graph is easy to visualise from an understanding that the fixed
overheads will increase in steps as the M&E infrastructure is provisioned.

Figure 4-9 DCiE under modular provisioning

The graph in Figure 4-9 shows the same modular provisioning approach in terms of the
facility New DCiE against the Base DCiE under monolithic provisioning as shown in
Figure 4-3. The DCiE function now varies significantly through the life of the facility with
distinct saw-tooth steps. Although the DCiE is significantly improved across much of the
IT load range, if this facility were to be measured purely on DCiE the results may be
confusing to the operator as well as difficult to explain to business management. This is
not a set of results that a facility operator would intuitively expect to see.

h
200kW IT load steps, the actual increments are larger for most devices due to the losses
further down the chain

Data centre energy efficiency metrics 26


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 4-10 Data centre fixed overhead under modular provisioning

To further illustrate the fixed and proportional overhead analysis for the modular
provisioning data centre Figure 4-10 shows the fixed overhead (Watts drawn / Watt
provisioned) and the proportional overhead (utility Watts drawn / IT Watts drawn) for the
facility at each of the 5 provisioning steps.
Note that in this facility with modular provisioning of the same M&E equipment, the
proportional overhead is very nearly constant whilst the fixed overhead is slightly higher
at the lower provisioned capacities. This is what one would intuitively expect to happen
within such a facility as there is no change in the nature of the equipment creating the
proportional losses and as the capacity increases the overheads of the 2N+1 resilience
reduce in proportion to the overall load.

4.9.2 Powering down existing CRAC units


In an existing data centre environment where consolidation or virtualisation is undertaken
or where there is still unused capacity there may be the opportunity to clear areas of the
data centre and turn off existing, fixed speed fan CRAC units where they are no longer
required. This would reduce not only the fixed load of the CRAC units but also the
proportional losses they drive.
The graph in Figure 4-11 shows the same inefficient facility as in 4.3 with all of the M&E
equipment provisioned from zero IT electrical load but with the CRAC units turned on in
200kWi steps.

i
Again, 200kW IT load steps

Data centre energy efficiency metrics 27


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 4-11 Fixed and proportional losses powering down unused CRACs

Whilst this does not produce as effective a reduction as modular provisioning of the
whole infrastructure, note that each 48kW step in CRAC fixed overhead produces more
than 65kW reduction in overall utility electrical load due to the reduction in proportional
overheads elsewhere in the infrastructure.

Figure 4-12 DCiE powering down unused CRACs

The graph in Figure 4-12 shows the same data, represented as the DCiE again against
the Base DCiE under monolithic provisioning as shown in Figure 4-3. The improvement is
smaller here than in the modular provisioning approach but this is action is available in an
existing facility at no capital cost. Note that whilst the curve is smoother and more
predictable the DCiE still varies significantly through the IT load range.

Data centre energy efficiency metrics 28


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 4-13 Fixed and proportional overheads powering down CRACs

Figure 4-13 shows the facility overheads for this scenario, as expected the proportional
overheads are nearly constant whilst the Fixed Overhead falls substantially as more of
the installed M&E equipment is utilised by IT equipment load and the fixed power draw
becomes a smaller fraction of the overall power draw.

4.10 Dynamic modular provisioning


As described in 4.5 many new IT devices are being developed whose PSU power draw is
more variable and related to the IT workload, from energy efficient servers to storage arrays
that power down when idle. This will result in the IT electrical and heat loads in working
data centres varying significantly through the day and week cycles as the IT workload
changes. This adds an additional efficiency issue to the data centre design as the M&E
equipment will be provisioned to meet the peak demands of the IT services delivered. With
the ability for devices to go into suspend and sleep modes IT electrical and heat load
variations in excess of 50 percent are not unlikely. This will, again, result in unnecessarily
high fixed overhead losses from the facility at low IT workloads, even under modular
provisioning, reducing the energy and cost benefits of this equipment.

Figure 4-14 DCiE curve family under modular provisioning

Many vendors, such as APC and Chloride, already produce modular M&E equipment which
can be installed in small increments to meet demands. Unfortunately once a unit of capacity
is provisioned the fixed overhead associated with that capacity is applied and instead of the
sawtooth efficiency curve of Figure 4-9 the facility is better described by the family of DCiE
curves shown in Figure 4-14.

Data centre energy efficiency metrics 29


Data centre energy efficiency metrics http://dcsg.bcs.org

We suggest that a natural extension of modular M&E equipment be equipment that self
tunes to the current electrical and thermal loads by turning off modular components when
the IT load drops. This would also allow for more flexible installation and more effective
management of modular provisioned solutions as additional modules could be installed
ahead of requirement and automatically provision themselves when the load breaks the set
threshold.
As for the previous examples fixed and proportional overheads will highlight these issues
more effectively and in a more intuitive manner that drives understanding of the issues and
the available mitigation strategies.

4.11 Ratio of fixed to proportional overhead


The curved shape of the DCiE graphs is due to the mixture of fixed and proportional
overhead. If the overheads of the data centre were purely proportional it would exhibit
constant efficiency with IT electrical load and the DCiE graph would be a flat, straight line.
The inclusion of a fixed overhead causes the DCiE to be zero at zero IT electrical load. This
requires that the DCiE increase from zero to the design DCiE of the facility at full IT
electrical load. The curvature of this line and how quickly the DCiE approaches the design
DCiE depends upon the ratio of fixed to proportional overhead.

Fixed 0 Fixed 0.1 Fixed 0.5 Fixed 0.9


Design PUE 2 2 2 2
Design DCiE 0.5 0.5 0.5 0.5
Fixed 0 0.1 0.4 0.9
Proportional 2 1.9 1.6 1.1

Table 4-4 Fixed, proportional and DCiE

This is illustrated in Figure 4-15 for the set of facilities, all with the same design DCiE of 0.5
described in Table 4-4.

Figure 4-15 DCiE curves by fixed overhead

Data centre energy efficiency metrics 30


Data centre energy efficiency metrics http://dcsg.bcs.org

5 Estimation of fixed and proportional overheads


It is important that facility operators be able to determine their fixed and proportional
Overheads to make these metrics useful. Whilst the most effective approach is to take
detailed measurements and develop an operating model of the data centre, the same
measurements used to determine the averaged DCiE can be used to estimate the fixed and
proportional overheads.

5.1 New facilities


It is expected that the data centre design and build contractor should be able to predict the
fixed and proportional overheads of the facility at design stage as we have done in this
paper. These parameters are key decision criteria in vendor and design selection. To
maintain control of the facility capital and operational costs the data centre operator must
specify efficiency targets whether the facility is built under their direction or via a contractor.
Apparent capital cost savings on M&E infrastructure can be outweighed by increased
operational costs in a matter of months.
More advanced data centre operators using simulation models such as that being
developed by the BCS should request the M&E device performance data and layout to
allow simulation of the facility to provide ongoing optimisation and management.

5.2 Existing facilities


In an existing facility there is a multi stage approach to initial estimation and subsequent
improvement of understanding of the fixed and proportional overheads leading toward
effective simulation of the facility.

5.3 Constraints on application


The estimation approach presented here for fixed and proportional overheads provides a
good estimate of facility performance for traditionally cooled data centres but is less
effective for facilities with step variability in load such as those using fresh air cooling or
significant amounts of air / water side economisation where temperature averaged values
are required. These can be handled in simulation models of the facility as in section 8 but
not from simple measurements.
It is also important to understand that the proportional overhead is a linear approximation to
a compound function of linear and non linear components. Whilst the overall power transfer
characteristic of the data centre is sufficiently linear for these approximations to be useful to
operators only full simulation will provide full detail for facilities with more dynamic power
transfer characteristics.
The primary target for the fixed and proportional estimations are operators who do not have
enough information to enter into a simulation tool, those with new build facilities should
have component and overall power loss functions for the data centre from the designer.
This analysis is intended as an approximation tool for operators to predict the response of
their data centre to changing IT electrical loads. Some facilities will experience more
substantial variation than shown in the example in their efficiency based on external
temperature, particularly those in more variable climates. For these facilities a multiple
regression technique including the external temperature is required.

5.3.1 Required measurements


The first stage is to take a range of measurements of the IT and utility electrical loads as
for the DCiE measure. The table of sample values below, representing 24 hourly
measurements across one day, is generated from a more detailed model than used in
section 4.3 including simulation of the variable cooling loads due to external temperature

Data centre energy efficiency metrics 31


Data centre energy efficiency metrics http://dcsg.bcs.org

variationj with the addition of 20 percent noise to simulate significant measurement


error.

External Data floor set IT electrical Utility


Measurement
temperature temperature load electrical load
1 8 21 348,087 1,163,344
2 8 21 352,853 1,191,991
3 8 21 355,194 1,150,685
4 9 21 357,512 1,226,698
5 11 21 375,301 1,078,595
6 13 21 396,073 1,268,379
7 16 21 419,348 1,303,868
8 17 21 471,575 1,388,577
9 18 21 493,588 1,347,376
10 19 21 496,626 1,379,983
11 20 21 481,173 1,340,160
12 22 21 471,575 1,235,116
13 22 21 490,524 1,467,842
14 22 21 499,638 1,464,687
15 21 21 493,588 1,267,441
16 20 21 468,318 1,263,546
17 18 21 451,582 1,215,708
18 17 21 415,578 1,329,254
19 16 21 400,067 1,110,475
20 14 21 379,572 1,079,568
21 12 21 357,512 1,058,440
22 11 21 352,853 1,030,307
23 10 21 352,853 1,202,706
24 9 21 348,087 1,132,554
Table 5-1 Set of IT and utility electrical load measurements

The graph, Figure 5-1 of the measured load data in Table 5-1 shows noticeable scatter
away from a straight line due to the random error used to simulate measurement errors
and other variations.

j
See section 8 for further analysis of the impacts of external temperature

Data centre energy efficiency metrics 32


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 5-1 Scatter plot of IT and utility load measurements

5.3.2 Regression analysis of measurements


The next step is to perform a regression analysis of these measurements; this is a simple
task in a spreadsheet. The graph in Figure 5-2 shows the scatter plot with the regression
line overlaid. The important aspect of this graph is that the line indicates a significant
utility electrical load at zero IT electrical load at the intersection with the vertical axis. This
is the approximation to the fixed overhead of the facility, dividing the utility electrical load
at the intercept by the rated IT electrical load of the facility gives the estimated fixed
overhead Watts per Watt of provisioned power for the data centre.

Figure 5-2 Scatter plot of IT and utility load measurements with regression line

In the Microsoft Excel spreadsheet provided to DCSG members9 this regression analysis
is achieved with the LINEST() function providing the following estimated values for the
fixed and proportional overhead as well as the 95th percentile upper and lower confidence
boundsk;

k
The upper and lower confidence bounds are determined by using the standard error and
degrees of freedom outputs of the LINEST function as inputs to a two tailed t-test

Data centre energy efficiency metrics 33


Data centre energy efficiency metrics http://dcsg.bcs.org

Proportional overhead Fixed overhead

Lower bound 1.102 0.304


Estimated value 1.665 0.541
Upper bound 2.228 0.779

Table 5-2 Estimated fixed and proportional overheads

These values are shown in the graph in Figure 5-3, the error bars show the 95th
percentile upper and lower confidence bounds for the estimation.

Figure 5-3 Estimation of fixed and proportional overheads

From these regression analysis values we can estimate the fixed and proportional
overheads for the facility to be;
Facility PowerZero 558,578
Fixed Overhead = = = 0.54
Rated IT Load 1,000,000
Facility PowerFull Facility PowerZero
Proportional Overhead = = 1.67
Rated IT Load
These values are a reasonable first approximation of the real values for this facility;

Fixed Proportional PUE DCiE


overhead overhead (100% IT load) (100% IT load)
Measured 0.54 1.67 2.2 0.45
Actual 0.65 1.41 2.1 0.47
Table 5-3 Measured vs. actual values for facility

Data centre energy efficiency metrics 34


Data centre energy efficiency metrics http://dcsg.bcs.org

5.3.3 Impact of external temperature on estimation


There is a tendency in a corporate data centre for the IT workload to be low when
external temperature is low overnight and higher when the external temperature rises
during the day. This can cause the regression analysis approach to underestimate the
fixed overhead of the facility as the utility power is rising through the influence of both
rising IT electrical load and external temperature. This effect is particularly visible when
the variance in IT electrical load is small.
This is shown in the sample simulation of the impact of workload and temperature across
a single day in Figure 5-4, the output power area shows the total thermal load presented
to the chillers which varies through the day, the proportional losses increase through the
warmer parts of the day where the IT workload is also higher. See section 8 Impact of
external temperature on data centre for a more detailed examination of these effects.
It is recommended that the external temperature and data floor set temperature are also
recorded in the spreadsheet supplied to BCS members9 to allow for later multiple
regression analysis including the impact of external temperature on the facility. This has
not been included in this initial, simplified version as temperature compensation requires
further information from the operator on the type of cooling system in use in their facility
and its performance characteristics.

Figure 5-4 Chiller plant power transfer by IT load and external temperature

As shown in Figure 5-4 the overhead of the data centre is influenced by the external
temperature. In many facilities this is a major influence on the overall utility load and
therefore the efficiency. In the context of this variability the fixed and proportional
overheads are considered to be instantaneously fixed or proportional. The fixed part of
the load is still that which would remain if all IT electrical load was removed and the
proportional still the remainder. This allows us to average the fixed and proportional
overheads of the facility over the operating temperature ranges.

Data centre energy efficiency metrics 35


Data centre energy efficiency metrics http://dcsg.bcs.org

5.3.4 Further analysis and modelling


To improve understanding of the data centre overheads there are two sets of additional
analysis that would yield useful data. Both of these approaches seek to break down the
overall loss values into the component losses of the data centre infrastructure. This data
would be input into a simulation model such as that being developed by the BCS3 of the
data centre M&E infrastructure to further understand the fixed and variable overheads,
where their primary sources are and what mitigation steps are available in that facility.

Equipment audit
An audit of the M&E equipment in the facility should be conducted, gathering the power
specifications of the components from the manufacturer, maintainer or specification
plates. This is particularly relevant in the case of fixed load items such as chilled water
pumps or fixed speed CRAC fans.

Component measurements
The second approach is to identify further measurement points within the facility to
isolate the power drawn by the M&E components as explained in section 7.1. Power
delivered to each part of the infrastructure such as the CRAC units and chiller plant
should be independently measured and monitored where the electrical layout allows.
Again, this data can be fed back into a model of the facility to further tune the analysis.

5.4 DCiE analysis


The fixed and proportional overhead analysis from the spreadsheet supplied to BCS
members can be used to estimate the DCiE of the facility across a wider range of operating
IT electrical loads, giving the predicted DCiE line in Figure 5-5. The DCiE is also calculated
at each measurement point and shown as a scatter plot on the same graph to illustrate the
working range of the facility as measured. The minimum, average and maximum values of
the DCiE are also determined and shown as the horizontal yellow, brown and blue lines
across the measurement range to provide a more effective understanding of the working
characteristics of the facility and the extent of DCiE variability in operation.

Figure 5-5 Estimated DCiE Curve, measurement points and bounds

Data centre energy efficiency metrics 36


Data centre energy efficiency metrics http://dcsg.bcs.org

6 Metrics when selecting data centres and equipment


Having analysed the performance and descriptive metrics for data centre infrastructure it is
appropriate to provide data centre and IT operators with some guidance on how to use this
information to select a data centre or equipment for their own facility.

6.1 Data for mechanical and electrical equipment


It is now common to see descriptions of mechanical and electrical equipment containing
efficiency claims such as 98 percent efficient UPS. Whilst it is encouraging that efficiency
is now perceived to be a key part of product marketing this sort of claim does not provide
enough information for effective selection of data centre infrastructure.
From a product marketing perspective it is preferable to quote the maximum achieved
efficiency of a product for comparison with competitors, however, due to the levels of
utilisation, provisioning overheads and redundancy levels in data centres it is not
uncommon for M&E components such as UPS to be running at 30 percent or less of their
rated capacity. At these utilisation levels the efficiency of most M&E components is
substantially reduced.
As an example considering an old, relatively inefficient UPS design approximated using the
following parameters;

Type of loss Loss


No load fixed losses 3.5%
Proportional losses 2%
Square law losses 5%

Table 6-1 UPS loss characteristics

These values would give a theoretical efficiency at 100% load of 89.3% for this UPS. If we
now examine the impact of these losses in the example data centre with 1MW rated IT
electrical load in 2N+1 redundancy configuration;

1% IT load 50% IT load 100% IT load


UPS power draw (kW) 87 593 1,120
Fixed losses (kW) 77 77 77
Proportional losses (kW) 0.2 10 20
Square law losses (kW) 0.002 5.7 22.7
Total losses (kW) 77.2 92.7 119.7
Efficiency 11.5% 84.4% 89.3%

Table 6-2 UPS losses in 2N data centre by IT electrical load

As shown in Table 6-2 and Figure 6-1 the efficiency of this UPS design and configuration
falls away quite rapidly as the electrical load of the data centre reduces. A facility using
nameplate provisioning is only likely to reach 50 percent load peak and many facilities take
considerable time to fill with equipment.

Data centre energy efficiency metrics 37


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 6-1 UPS performance by load

6.1.1 Full range performance data


As shown in Table 6-2 and Figure 6-1 an effective selection of M&E infrastructure
equipment can only be made once the full range of efficiency is understood in the target
facility. Full performance curves or descriptive parameters such as the fixed, proportional
and square law loss data needs to be made available to data centre operators and
designers. For more information on this issue see Electrical Efficiency Modeling of Data
Centers10.

6.1.2 EU Code of Conduct for UPS


As part of the European Union JRC work a Code of Conduct for UPS manufacturers has
been implemented, this sets minimum efficiency targets for products across the full load
range as well as defining a reporting format for efficiency at multiple load pointsl.

6.2 Intended use of the facility


The intended utilisation of the facility is an important consideration when selecting or
building a data centre. Just as for the vehicle selection comparison in Section 3.3.2 the
relative weighting of factors changes with the intended use.

6.2.1 Typical corporate facility


For a typical corporate data centre build where the capacity is to be slowly filled over a
number of years both the fixed and proportional overheads are of similar importance to
maintain an overall high DCiE through the entire production life of the building.
A low fixed overhead, preferably coupled with modular provisioning of M&E capacity is
important to achieve efficiency in the first few years of operation where utilisation is low.
This also has useful impacts on both the initial capital cost of the facility and the
operational cost and a supporting business case can be easily built for this approach.
Careful consideration of what levels of resilience are actually necessary for each
supported service can also reduce unnecessary capital cost and fixed overhead.
The proportional overheads are applicable through the entire life of the facility and will
directly impact the operational cost of the data centre. These can be reduced through the
selection of high efficiency M&E equipment combined with the adoption of effective data
centre management processes such as those described in the best practices of the EU
Code of Conduct for Data Centres11.

l
http://sunbird.jrc.it/energyefficiency/html/standby_initiative_UPS.htm

Data centre energy efficiency metrics 38


Data centre energy efficiency metrics http://dcsg.bcs.org

6.2.2 Business continuity facility


The requirements for a business continuity facility can be substantially different. Many BC
facilities are idle for the vast majority of their lifetime with only some storage and
networking devices active and operating to maintain state with their prime site. Much of
the IT equipment is actually turned off in some BC sites.
Low fixed overheads are the dominant requirement in this scenario as the IT electrical
loads will be low for most of the operating lifetime. As before modular provisioning,
appropriate selection of resilience levels (it is already a backup facility) and low fixed
overhead equipment are key to achieving this.
Proportional overheads are of significantly lower importance in this type of facility where
the operating time will be a small fraction of the overall lifetime and can be safely
compromised in favour of cost or reducing fixed overheads.

6.2.3 Co-location or managed services facility


A co-location or managed services facility shares the requirements of the corporate
facility but the cost impacts of high fixed overhead are of more direct significance to the
operators business model.
Low fixed overheads and modular M&E provisioning capability would allow the co-
location operator to achieve much lower operating costs through the fill out phase of the
facility. This moves both the cash flow and overall break even points significantly closer
to the build date of the facility and substantially reduces the levels of up front investment
and financial risk involved. The mitigation option for a co-location operator with a
monolithic facility is to substantially increase the power and provisioning costs to
represent the high M&E amortised cost and operating electrical costs of the design. The
time during which the facility is partially occupied is particularly significant to these
overheads.

6.2.4 Immediately filled facility


In the instance of a facility that will be filled to rated capacity almost immediately then the
proportional overheads are of greater significance than the fixed overheads as the facility
will be operating close to its peak DCiE from early in the life cycle.

Data centre energy efficiency metrics 39


Data centre energy efficiency metrics http://dcsg.bcs.org

7 Monitoring and measurement


It is recommended that facility operators have a power surveym carried out or install
energy monitoring and reporting equipment to record the energy use within the data
centre. The data recorded should include the utility feed power utilisation, the IT electrical
load and the major M&E infrastructure components at the level of granularity the facility
electrical design allows.

7.1 Facility measurement

Figure 7-1 Power measurements in the data centre

Figure 7-1 shows, at a high leveln, the points where energy use can be measured in the
data centre to assist in understanding the efficiency, losses and impacts of changes and
improvements. These are represented in three groups;
1. Simple measurements, these are the most basic level of measurement, required
to deliver a PUE/DCiE metric of the ratio of utility power to IT power for the
facility. These can be initially informative to the operator and are easy to perform
with portable equipment. It is important that the external and data floor set
temperatures are recorded along with the electrical measurements
2. Detailed measurements, these are the next level of measurement where we
specifically measure each of the points where power is lost in the delivery chain
or diverted to non IT loads. This provides more effective information on how to
improve the facility and can directly change relevant behaviour. This level may
be necessary dependent upon the electrical configuration, for example if the
CRAC units are fed from the UPS then CRAC power is a required measurement.

m
Some data centre consultancies such as Keysource,
http://www.keysource.co.uk/index.asp?ID=242 now offer free efficiency audits
n
The details of the electrical design will vary between facilities, as such the power delivery
path and measurement point(s) for each of the loads identified will vary. Expert advice should
be sought to determine the measurement points within each specific facility

Data centre energy efficiency metrics 40


Data centre energy efficiency metrics http://dcsg.bcs.org

3. IT measurements, there is some limited utility in measurement of IT device


power draw in situations where a physical device is dedicated to a specific task.
This utility disappears in a virtualised or grid infrastructure or where resources
such as network or storage are shared.
These three levels of measurement can be carried out at a number of frequencies
dependent upon the accuracy and granularity of measurement the operator requires;
1. Once, typically for a one off survey, though this is of limited value as a snapshot
measurement
2. Hourly for one week, again typically a one off survey, this provides a more
effective view of how the data centre responds to varying IT loads
3. Hourly for one week every three months, possibly a recurring survey delivered by
an M&E maintenance partner, this provides snapshots of how the data centre
responds to IT loads, climate and changes to equipment and processes
4. Continuous, this is a permanently installed monitoring and reporting system
providing a very effective view of the impacts of changes in IT load, equipment,
operating process, infrastructure and climate.

Development Measurement
Recording Frequency Output
stage points

Manual -
Simple survey Simple Once Report
Temporary

Extended simple Automated - Hourly for one


Simple Report
survey Temporary week

Hourly for one


Automated -
Repeated survey Simple week every 3 Report
Temporary
months

Simple & Manual -


Advanced survey Once Report
Detailed Temporary

Extended Simple & Automated - Hourly for one


Report
advanced survey Detailed Temporary week

Hourly for one


Repeated Simple & Automated -
week every 3 Report
advanced survey Detailed Temporary
months

M&E
Simple facility Automatic -
Simple 5 Minutes monitoring
monitoring Permanent
screen(s)
M&E
Advanced facility Simple & Automatic -
5 Minutes monitoring
monitoring Detailed Permanent
screen(s)

IT
Simple, Automatic -
Holistic monitoring 5 Minutes monitoring
Detailed & IT Permanent
screen(s)
Table 7-1 Stages of energy monitoring

Data centre energy efficiency metrics 41


Data centre energy efficiency metrics http://dcsg.bcs.org

The recording equipment can be either temporary or permanently installed. Many M&E
maintenance vendors have portable equipment that can be used to carry out a survey.
There is also a growing range of power reporting modules to be fitted to PDUs, UPS and
rack level power strips. Of significant impact to the effectiveness of the power metering is
how it is viewed by the facility operator;
1. Report, the results of a survey will be delivered as a report, this provides a one
time view, or reminder every reporting period if recurring under contract
2. M&E monitoring screen, where permanent power metering is in place the outputs
can be sent live to a monitoring screen for M&E staff to view or extract reports,
this suggests an organisational separation of the IT and M&E teams
3. IT monitoring screen, the most integrated and effective choice is to send the
power metering to the same monitoring screens as the IT monitoring data for an
integrated IT and M&E team response.

7.2 Granularity of measurement


It would be ideal to be able to include in the IT equipment power measurement only those
devices which are directly involved in the delivery of the useful work from the data centre
and exclude systems such as KVM switches and monitors. There are two significant issues
with this goal. Firstly much of this equipment is plugged into the same rack power strips and
therefore PDUs as the useful work equipment it supports and therefore the complexity and
expense of the metering infrastructure would be considerable in an existing facility,
although it would be possible to design new facilities with grey power for such devices
distributed separately. The second issue is that it will become difficult to agree on a
boundary of what is directly involved in the delivery, for example a backup platform is not
involved in the delivery, until it is required to restore data.

7.3 Reasons to measure variance of IT electrical load


One issue that is frequently not considered by M&E personnel is that of IT electrical load
variance. As described in section 4.5 rapid improvements in IT equipment are driving
significant variation in the applied electrical load in the data centre, as this trend continues
electrical load will track IT workload more effectively. This can create issues in thermal
management of the facility which need to be understood by M&E staff.

7.3.1 How effectively does the IT electrical load track the IT workload?
It is quite common during installation of IT equipment for engineers to either not enable or
actively disable all of the power management features of the servers and storage they
are installing. In a few instances this is for a valid operational reason but it is
inappropriate in many cases. Measurement of the IT electrical load at varying times of
day and analysis of the variance will reveal how effectively the IT electrical load tracks
the IT workload and whether it is necessary to audit the power management
configuration of the IT devices.
The correlation between IT workload and IT electrical load should also improve as the IT
equipment is replaced during normal end of life upgrade as new IT equipment exhibits
substantially better load to power linearity. This correlation is a key measure of the IT
platform and should be monitored.

7.3.2 Can you measure the variance in utility electrical load?


One issue reported by a number of data centre operators is the ability to measure
variance in the IT electrical power whilst experiencing difficulty detecting the
corresponding variance in utility power draw of the facility. This suggests that the facility
is dominated by the fixed overhead, masking the variance in IT electrical load and
proportional overhead. A facility with this issue will not be able to extract the full benefit of
IT changes such as virtualisation. Remedial actions to reduce the fixed overhead should
be undertaken immediately to reduce the power costs and energy use.

Data centre energy efficiency metrics 42


Data centre energy efficiency metrics http://dcsg.bcs.org

7.3.3 IT devices that report PSU power


A number of IT equipment vendors have started to produce chassis that are able to
report the PSU drawn power via IT monitoring. Unfortunately there is not yet
standardisation of this and simple measures such as an agreed SNMP MIB to be probed
are not available which fundamentally compromises the value of these capabilities.
Another issue with the power reporting from the enabled servers is that the report is
generally a gauge reporting instantaneous power rather than a counter reporting energy
use since last query which would be easy to achieve in hardware. The current gauge
approach would require the monitoring platform to integrate the snapshot power
measurement values retrieved by polling to estimate energy use and cost in software
which is likely to be inaccurate. This counter approach would provide a more useful
output, directly reporting energy use whilst still allowing a power measurement to be
taken by subtracting the previously reported value. A common example of this approach
is traffic monitoring on network switch ports.

Data centre energy efficiency metrics 43


Data centre energy efficiency metrics http://dcsg.bcs.org

8 Impact of external temperature on data centre efficiency


So far in this paper, for the purpose of simplicity and clarity, we have only considered the
impact of varying IT electrical load and M&E equipment specification on data centre energy
efficiency. However, as anything up to 50 percent of the utility power draw of a data centre
can be used in the cooling systems it is not surprising that the external temperature has an
impact on the energy efficiency of the facility. This is due to a number of causes and varies in
impact between different designs of facility and geographic location. A number of reviewers of
the EU Data Centre Code of Conduct (e.g. EYP) have suggested that the mechanical
(primarily cooling) and electrical losses be reported separately to capture these impacts.

8.1 External temperature influence on chiller plant efficiency


The data centre chiller plant receives the primary impact of variation in external
temperature. As the chiller plant is essentially a heat pump which has to transfer heat from
the data centre to the atmosphere this means that as the external temperature rises, the
work required from the compressor pump to move the heat rises. This is shown in a
simplified form in Figure 8-1. The chiller system is required to move heat from the
evaporator, whose set temperature depends upon the set data floor temperature, to the
condenser whose temperature depends on external climate conditions.

Figure 8-1 Simplified chiller schematic traditional cooling

8.1.1 Traditionally cooled facility


We will initially consider a traditionally cooled facility with a chilled water loop feeding
CRAC units on the data floor and direct to air, fan cooled evaporators. Using the same
simulation model for the facility used previously, but with a more advanced and realistic
model of the chiller plant and CRAC unit energy use, we can simulate chiller losses
under variation in external temperature to demonstrate the impact of external climate.

The graph in Figure 8-2 shows the joint impact of varying IT electrical load and external
temperature on the efficiency (DCiE) of the simulated data centre. As shown, the
efficiency of the data centre reduces noticeably with a rise in external temperature but the
IT electrical load is still the dominant influence on efficiency in this facility. This supports
the use of fixed and proportional overhead metrics derived from simple measurement
data for this class of facility.

Data centre energy efficiency metrics 44


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 8-2 DCiE by IT electrical load and external temperature, traditional cooling

8.1.2 Fresh air cooled facility


We will now consider a facility which uses fresh air cooling in place of the traditional re-
circulating closed loop approach. In this design of facility, when the external air
temperature is below the set data floor temperature, chillers are unnecessary as external
air is filtered and mixed with re-circulated air to achieve the required temperature. Whilst
the external air is between the set data floor temperature and the exhaust air temperature
energy is still saved by chilling external air instead of the re-circulated air. Once the
external temperature rises above the exhaust air temperature the facility reverts to the
normal mode of chilling re-circulated air.

Figure 8-3 Simplified layout of fresh air cooled data centre

As shown in Figure 8-3 humidity control is largely achieved through the intelligent use of
control systems to manage the re-circulating air flow and the use of evaporative adiabatic
humidifiers. For a more detailed explanation of fresh air cooling see Fresh Air Cooling12

Data centre energy efficiency metrics 45


Data centre energy efficiency metrics http://dcsg.bcs.org

In this analysis we use the same inefficient chiller plant but the CRAC units are replaced
by a central air mover. We do not model the potential fan efficiency improvements of the
central air handler over distributed CRAC units.
As shown in Figure 8-4 there is a distinct change in efficiency starting at the set data floor
temperature of 21 Celsius through to the exhaust air temperature of 31 Celsius. At the
new recommended ASHRAE data floor temperatures as specified in the EU Code of
Conduct11 the set temperature would be closer to 27 degrees and the facility would
spend more of its operating time in the higher efficiency region.

Figure 8-4 DCiE by IT electrical load and external temperature, fresh air cooling

When operated with a varying IT workload and external temperature this facility will
exhibit significant changes in overall efficiency through the working day. The graph in
Figure 8-5 shows the large impact in the middle of the day for this type of facility where
high IT workload coincides with high external temperature in the summer. Comparison
with Figure 5-4 for the traditionally cooled facility shows both the increase in variation and
the significant improvement in overall efficiency.

Figure 8-5 Chiller losses by external temperature, fresh air cooled

Data centre energy efficiency metrics 46


Data centre energy efficiency metrics http://dcsg.bcs.org

This joint impact of IT workload and external temperature gives the daily variance in
DCiE shown in Figure 8-6.

Figure 8-6 Daily data centre efficiency by hour, fresh air cooling

The models used in this section to demonstrate the external temperature impacts on
cooling power are relatively simple to demonstrate the effects and do not account for a
number of variables such as the external humidity, There has already been substantial
work demonstrating the application of more complex and effective models to data centre
cooling loads13.

8.1.3 Applying fixed and proportional overheads to fresh air cooling


With these significant variations in utility electrical load and efficiency due to the
combined variance in IT workload and external temperature we have to consider whether
the fixed and proportional loss analysis is still an effective indicator for operators with this
type of facility. The graph in Figure 8-7 shows the utility electrical load by IT electrical
load for this facility (Figure 8-4) as a weighted average across a typical year of external
temperatures in the southern United Kingdom. The utility power is also shown for 0
Celsius and 40 Celsius for comparison.

Figure 8-7 External temperature averaged utility electrical load by IT load

Data centre energy efficiency metrics 47


Data centre energy efficiency metrics http://dcsg.bcs.org

As shown in Figure 8-7 we can continue to use the fixed and proportional approximations
with this type of facility and receive effective analysis of their behaviour subject to
understanding the performance characteristics of the building.

8.1.4 Issues with regression analysis of fresh air cooled facilities


Taking the model for the fresh air cooled data centre and applying the same IT workload
and temperature parameters used in the example regression in section 5 and applying
the regression analysis to the output data in we see that there is a significant issue.

Figure 8-8 Scatter plot and regression line of IT and utility load fresh air cooling

Figure 8-8 shows that the simple regression against only the IT electrical load is
confused by the cluster of data points that occur at both high IT workload and
temperature and the regression suggests a near zero value for the fixed overhead which
is clearly in error when compared with Figure 8-7.
To perform a regression analysis of this type of facility it would be necessary to perform a
multivariate regression including the external temperature. To perform this effectively it
would be advantageous to obtain some performance and set point data about the cooling
system. Considering the additional complexity this involves it is recommended that a full
simulation model of the facility be calibrated against the measured data instead to
determine the working (average) fixed and proportional overheads. In the BCS data
centre model it is possible to consider the instantaneous fixed and proportional
overheads at each time point to obtain greater granularity and accuracy.

8.1.5 Dynamic free cooling


Dynamic free cooling provides many of the benefits of fresh air cooling using more
familiar chilled water loop technologies and presents significant retrofit opportunities. It is
possible to use an intelligent control system to optimise the use of free cooling in a chilled
water based system. At lower heat loads it is possible to run the free chilled water to the
CRAC units at a higher temperature than in a normal system whilst still achieving the
required cooling, this significantly extends the external temperature range through which
the facility can operate on the free cooling coils. When the heat load in the facility or the
external temperature exceeds the thresholds then the compressor pumps are started and
the system reverts to normal operation. See14 for more information.

Data centre energy efficiency metrics 48


Data centre energy efficiency metrics http://dcsg.bcs.org

Figure 8-9 Dynamic free cooling

8.2 Direct insolation heating


The other significant environmental impact on data centre efficiency is direct insolation
(incoming solar radiation) heating to the building. This varies by time of day, season and
geographic location from 0.1 kW in southern Sweden in January to 0.9 kW in
m2 m2
southern Spain in Julyo. This can become a significant contribution to the peak cooling
loads of the data centre for those with relatively low power densities and a low albedo
(proportion of incident sunlight reflected). Careful positioning and orientation of the building
and the cooling equipment can assist in reducing these insolation loads.

o
NASA Atmospheric Science Data Center, http://eosweb.larc.nasa.gov

Data centre energy efficiency metrics 49


Data centre energy efficiency metrics http://dcsg.bcs.org

9 Glossary
9.1 Power provisioning terms
The following terms are used in BCS Data Centre Specialist Group documents to refer to
the power and cooling capacity allocated to IT equipment within the data centre at the time
of provisioning.

Nameplate power
The Nameplate power of an IT device is defined as the rated power of the power supply
(or supplies where more than one is required to operate the device), this is frequently
substantially larger then the maximum power the equipment draws.

Peak power
The peak power is the maximum power that could be drawn at the power supply of the IT
equipment. This is determined by adding up the peak power requirement of each
component within the device plus overheads. For a server this would involve adding up
the power of the processor(s), memory, IO cards, main board, chassis and disks and
then factoring the losses of the voltage converters and power supplies.

Statistical provisioning
The statistical approach is frequently used in large Internet data centres where there are
large numbers of the same class of hardware under the same workloads. This allows the
operator to measure the peak power used by a rack of their standard servers and then
provision to this value15. This presents possible reliability issues and requires some
safety headroom as each server, rack or group could suffer a surge in workload, such as
under a DOS attack and draw substantially more power than is provisioned.

Smart or dynamic provisioning


An emerging approach to power provisioning is to install equipment that is capable of
responding to external requests to reduce its power consumption and then use an active
power management system. This allows an operator to fully utilise their data centre by
filling it with equipment and then protecting the facility by clamping the performance and
therefore power draw of individual or groups of systems when power and cooling
capacity is reached16. There are clear and significant reliability risks inherent to this
approach, particularly as the fault containment boundaries of the M&E infrastructure are
crossed by this approach generating the risk of a cascade or positive feedback failure of
the part or all of the facility.

9.2 Efficiency metrics and measures


The following terms for efficiency metrics are used in this paper;

PUE
This is the power usage effectiveness metric as defined by the Green Grid, the utility
electrical load of the data centre divided by the IT electrical load.

DCiE
This is the data center infrastructure efficiency metric as defined by the Green Grid, the
IT electrical load divided by the utility electrical load of the data centre.

Design DCiE/PUE
This is the DCiE or PUE measured at the IT electrical load (usually peak) that maximises
the metric by minimising the impact of the fixed load overheads.

Data centre energy efficiency metrics 50


Data centre energy efficiency metrics http://dcsg.bcs.org

Achieved DCiE/PUE
This is the DCiE or PUE measured when the facility is operating under the actual
production IT electrical load. This is a variable value and therefore represents a moving
target.

Fixed overhead
This is the BCS DCSG proposed metric to describe the utility electrical load of the data
centre that is present irrespective of IT equipment electrical load.

Proportional overhead
This is the BCS DCSG proposed approximating metric to describe the additional utility
electrical load of the data centre above the fixed overhead that is proportional to the IT
electrical load.

9.3 Power draw terms


There are a number of points at which it is useful to refer to the electrical power draw within
the data centre;

IT electrical load
This is the power drawn at the power supply input of the IT equipment housed within the
data centre.
This is also referred to as the IT equipment power.

Utility electrical load


This is the power drawn at the electric utility or onsite power generation input to the data
centre, including the IT electrical load, fixed and proportional overheads.
This is also referred to as the total facility power.

Data centre energy efficiency metrics 51


Data centre energy efficiency metrics http://dcsg.bcs.org

10 Acknowledgements
The DCSG would like to thank the following people for their input, review and comment on
this paper during the review phases;
The DCSG committee and membership
Paul Elliott, Future Tech
Ian Bitterlin, Chloride
Bernard Aebischer, ETH
Benjamin Petschke, Stulz
Victor Smith, Dell

Data centre energy efficiency metrics 52


Data centre energy efficiency metrics http://dcsg.bcs.org

11 References

1
Kenneth G Brill, The Invisible Crisis in the Data Center: The Economic Meltdown of Moores
Law
2
Going Green? The Reader Perspective, Dale Vile, Freeform Dynamics
3
Carbon Trust joins up with British Computer Society to cut carbon from data centres,
http://www.bcs.org/server.php?show=ConWebDoc.19925
4
Quoi de neuf dans le domaine de lefficacit nergtique des data centres?, Centre for
Energy Policy and Economics (CEPE), ETH Zrich, September 10, 2007, Aebischer, Bernard
5
http://www.thegreengrid.org/events/technical_forum/Day_1.Track_1._Rating_Systems_for_D
ata_Centers_P.pdf
6
Enabling the Energy-Efficient Data Center, C Belady, J Pflueger, Green Grid
http://www.dell.com/downloads/global/power/ps1q08-20080199-GreenGrid.pdf
7
THE GREEN GRID DATA CENTER POWER EFFICIENCY METRICS: PUE AND DCiE,
http://www.thegreengrid.org/gg_content/TGG_Data_Center_Power_Efficiency_Metrics_PUE_
and_DCiE.pdf
8
APC, Electrical Efficiency Modeling of Data Centers, Rasmussen, Neil,
http://www.apcmedia.com/salestools/NRAN-66CK3D_R1_EN.pdf
9
Analysis spreadsheet for data centre efficiency metrics white paper, DCSG members
repository,
http://dcsg.bcs.org//component/option,com_docman/task,cat_view/gid,22/Itemid,50/
10
APC, Electrical Efficiency Modeling of Data Centers, Rasmussen, Neil,
http://www.apcmedia.com/salestools/NRAN-66CK3D_R1_EN.pdf
11
EU Code of Conduct for Data Centres,
http://sunbird.jrc.it/energyefficiency/html/standby_initiative_data%20centers.htm
12
Fresh Air Cooling, Paul Elliott, Future Tech,
http://dcsg.bcs.org//component/option,com_docman/task,cat_view/gid,17/Itemid,50/
13
Model-Based Approach for Optimizing a Data Center Centralized
Cooling System, Beitelmal, Patel, http://www.hpl.hp.com/techreports/2006/HPL-2006-67.pdf
14
State of the Art Energy Efficient Data Centre Air Conditioning, Benjamin Petschke, Stulz
http://www.stulz.de/en/downloads/general-information/
15
Power Provisioning for a Warehouse-sized Computer, Fan, Weber, Barroso,
http://research.google.com/archive/power_provisioning.pdf
16
Dynamic Power Management has Significant Values, Intel,
http://communities.intel.com/openport/blogs/server/2008/04/11/dynamic-power-management-
has-significant-values-a-baidu-case-study

Data centre energy efficiency metrics 53

You might also like