17-0778
9/22/2017 7:10 PM
tex-19687946
SUPREME COURT OF TEXAS
BLAKE A. HAWTHORNE, CLERK
NO. 17-0778
Gerald Castillo
State Bar No. 24012399
Ricardo Palacios
State Bar No. 24010990
Criselda Palacios
State Bar No. 24067812
Palacios Garza & Thompson, P.C.
2724 West Canton Road
Edinburg, Texas 78539
(956) 318-0507 (Telephone)
(956) 318-0575
Emails: rpalacios@pgtlawfirm.com
and cpalacios@pgtlawfirm.com
ii
Identity of Parties and Counsel
is a list of all parties and counsel involved in this case. This list is included so that
the Justices of this Court may evaluate possible disqualification or recusal from
Gerald Castillo
State Bar No. 24012399
Ricardo Palacios
State Bar No. 24010990
Criselda Palacios
State Bar No. 24067812
iii
Appellant/Respondent IOC Company, LLC:
Pumarejo Law
4801 Safe Hen Dr.
Austin, Texas 78727
(512) 731-7869 (Telephone)
(512) 387-2556 (Facsimile)
Ricardo@pumarejolaw.com
Michael McGurk
State Bar No. 00797746
iv
Table of Contents
Identity of Parties and Counsel ................................................................................ iii
Table of Contents .......................................................................................................v
Argument....................................................................................................................9
A. The Texas Arbitration Act requires that the Award be vacated............9
v
D. The trial court did not err in vacating the Arbitrators Award
because the Award was obtained by undue means in violation
of 171.088(a)(1), since the Arbitrator acted in bad faith by
flagrantly disregarding statutory provisions and unambiguous
contractual terms ................................................................................ 16
vi
Table of Authorities
Cases
Ancor Holdings, LLC v. Peterson, Goldman & Villani, Inc.,
294 S.W.3d 818 (Tex. App.--Dallas 2009, no pet.).........................................12
Black v. Shor,
443 S.W.3d 154, 169 (Tex. App.Corpus Christi 2013, pet. denied) ...........17
vii
Werline v. E. Texas Salt Water Disposal Co., Inc.,
209 S.W.3d 888, 901 (Tex. App.Texarkana 2006), aff'd, 307 S.W.3d 267
(Tex. 2010).......................................................................................................17
Zachry Const. Corp. v. Port of Houston Auth. of Harris County,
449 S.W.3d 98, 10304, 11014 (Tex. 2014) ...................................... 8, 10, 17
Statutes
Tex. Util. Code Ann. 54.203 ....................................................................... 8, 14, 17
Tex. Civ. Prac. & Rem. Code 171.088 ....................................... 4, 9, 11, 16, 17, 20
Tex. Civ. Prac. & Rem. Code 171.091 ..................................................................23
Tex. Loc. Code Ann. 271.153 ..................... 6, 7, 8, 9, 10, 13, 14, 17, 19, 21, 23, 24
viii
NO. 17-0778
Petitioner and Appellee City of Edinburg, Texas (COE) files this petition
and road contractor and City of Edinburg, Texas (COE), a municipality. IOC
and COE entered into a formal contract entitled Pacing and Training
Subsequently, on or about June 2, 2009, IOC and COE entered in a formal contract
entitled Paving and Drainage Improvements for Sugar Road. (Sugar Road
project) (1C.R.:57). Pursuant to both contracts, Respondent initiated Arbitration
by making a written demand for Arbitration to the Petitioner with the American
lines, owned by others, namely AT&T, on the Canton Road project and the Sugar
(2) Arbitrator, William K. Andrews, issued and signed the Final Award of
(3) The Arbitration Award was for a total sum of $1,362,630 for the
Canton Road project and $673,092 for the Sugar Road project, plus attorney fees.
(5) Judge Mario Ramirez is the Presiding Judge of the 332nd Judicial
(7) Appellant and COE were the parties in the Court of Appeals.
(8) The Court of Appeals for the Thirteenth District of Texas heard the
2
(9) Justices Nelda V. Rodriguez, Gina M. Benavides, and Nora Longoria
were on the panel that heard the appeal in this case. Justice Gina M. Benavides
was the author of the opinion for the Court. There were no separate opinions.
(10) The citation for the opinion by the Court is IOC Co., LLC v. City of
(11) The Court of Appeals reversed the trial courts orders: (1) granting the
COEs Motion to Vacate the Arbitration Award; and (2) denying IOCs motion to
confirm the arbitration award. The Court of Appeals rendered a judgment: (1)
denying the COEs Motion to Vacate the Arbitration Award; and (2) granting
IOCs Motion to Confirm the Arbitration Award. The Court of Appeals denied
COEs Motion for Rehearing on August 10, 2017. (Exs. 4 & 5).
Exhibits
petition as exhibits:
Statement of Jurisdiction
The Court has jurisdiction over this petition for review under TEX. GOVT
CODE 22.001(a) because the appeal presents a question of law that is important to
the jurisprudence of the State. The opinion by Supreme Court of Texas will have a
business.
Issues Presented
(1) The Supreme Court of Texas should reverse the judgment of the Court
of Appeals and render judgment for COE because the Arbitrator exceeded his
immunity.
(2) The Supreme Court of Texas should reverse the judgment of the Court
of Appeals because the Arbitrator exceeded his powers since the Arbitrator ignored
and re-wrote the contract and ignored the essence of the contract.
(3) The Supreme Court of Texas should reverse the judgment of the Court
4
(4) The Supreme Court of Texas, in the alternative to reversing the
judgment of the Court of Appeals, should modify the Arbitrators Award for the
Sugar Road project to $191,090.82 pursuant to Tex. Civ. Prac. & Rem. Code Ann.
179.091 because Respondent cannot recover for delays that are not owner caused.
Statement of Facts
The underlying dispute arise from two (2) road construction and
Petitioner, City of Edinburg, Texas (COE). On or about April 1, 2008, COE and
IOC entered into a formal contract entitled Paving and Training Improvements for
Canton Road. (Canton Road project) (1C.R.:50). On or about June 2, 2009, COE
and IOC entered into a formal contract entitled Paving and Drainage
written demand for Arbitration to the Petitioner with the American Arbitration
Association. (3C.R.:117). Respondents only claim arises from alleged delays and
others, namely AT&T, on the Canton Road project and the Sugar Road project.
(3C.R.:118). Respondent admitted that it was paid for every unit of work
completed, as well as every amendment and/or change order. On July 18, 2014, an
5
Arbitration Award was issued by Arbitrator, William Andrews. The Arbitration
Award was for a total sum of $1,362,630 for the Canton Road project and
$673,093 for the Sugar Road project, plus attorney fees. (3C.R.:117-124).
On February 11, 2016, the Trial Court granted COEs requested relief.
Court of Appeals where the Trial Courts orders were reversed and rendered a
(1) The Court of Appeals erred in reversing the Trial Courts granting of
vacating the Arbitrators Award because the Arbitrator exceeded his authority and
acted by undue means. The Texas Arbitration Act (TAA) identifies specific
grounds for vacating an Arbitration Award. Two (2) grounds applicable in this
case are: (1) that the Arbitrator exceeded his authority, and (2) that the Arbitration
(2) The Court did not err in vacating the Arbitrators Award because the
Arbitrator exceeded his power by issuing an Arbitration Award that strays from the
line with the protections afforded to COE under Chapter 271, the contract
6
contained several provisions that informed Respondent that the utility lines that
were known and/or unknown to exist were owned by others. Despite the ample
evidence in the record that Respondents alleged damages were caused by others,
and not COE, the Arbitrator nonetheless issued an Arbitration Award for damages
caused by others.
contained in both the Canton Road project and Sugar Road project that dictated the
waiver of any right to additional compensation. The record reflects that not only
compensation pursuant to the contract but additionally failed to quantify its losses
(4) Thus, the Trial Courts vacatur of the Arbitration Award was proper
because the Arbitrator exceeded his power in issuing an Arbitration Award that
(5) By the same token, the Arbitrator acted by other undue means since
7
(6) The Arbitrator disregarded controlling and unambiguous statutory
provisions under Texas Government Code 271.153(a)(1) and Texas Utilities Code
54.203 and the contract terms, which is bad faith. The Texas Government Code
and Zachry clearly limit a citys liability to owner caused delays. The record
clearly shows that the Respondent and Respondents expert, Jens Baker,
others.
(7) Similarly, the contractual provision contained within the Sugar Road
project and Canton Road project clearly state that delays caused by others, namely
utility companies such as AT&T and Texas Gas, are not the responsibility of COE.
issued the Arbitration Award to Respondent for damages that were not owner
caused. Thus, once again the Arbitrator disregarded controlling law and
under 271.153(a)(1).
8
Argument
The Texas Arbitration Act (TAA) identifies specific grounds for vacating
an arbitration award. Tex. Civ. Prac. & Rem. Code 171.088. Two (2) of those
grounds are applicable here. Consequently, the question before this Court is
The law is clear that a party cannot recover damages from a local
government entity for delays that are not owner caused. Tex. Govt Code Ann.
delays due to the relocation of utility lines not owned by Petitioner. Rather, they
are owned by entities such as AT&T and Texas Gas. This established law makes
clear that COE cannot be held responsible for delays caused by others. Despite the
of Dallas, 197 S.W.3d 371, 374 (Tex. 2006); Tex. Loc. Gov't Code Ann.
9
271.151(3)(A). Sovereign immunity protects municipalities in two (2) ways: (1)
immunity from suit, which bars suit against a governmental entity altogether; and
governmental entity. City of Weslaco v. Borne, 210 S.W.3d 782, 789 (Tex. App.
Corpus Christi 2006, pet. denied). Immunity from suit remains unless the
Government Code, Chapter 271, waives immunity from contract suits for local
County, 449 S.W.3d 98, 106 (Tex. 2014) (The Port of Houston Authority, owner of
The Texas Supreme Court in Zachry held that 271.152 uses 271.153 to
further define to what extent immunity has been waived. Id. at 110. The Texas
waived to the extent that claimants damages arise from owner caused delays.
10
To allow Respondent to recover the Arbitration Award would ignore the
pragmatic purpose of governmental immunity: to shield the public from the costs
Mexia, 197 S.W.3d 325, 332 (Tex. 2006). Petitioner and their respective taxpayers
should be shielded from the costs of a claim that has not and cannot allege any
It is clear from the record that Respondent and the Arbitrator were aware
that the delays arising from the utility lines were not owner caused. Rather, the
delays were caused by others. 3C.R.:817 at (Pg. 183, Ln. 24-Pg. 184, Ln. 5; Pg.
184, Ln. 23-Pg. 184, Ln. 25); 3C.R.: 819 at (Pg. 189, Ln. 20-25); 3C.R.: 820 at
(Pg. 196, Ln. 4-23); 3C.R.: 825 at (Pg. 213, Ln. 19-Pg. 214, Ln. 11). The
Arbitrator actions clearly reflect that he exceeded his authority and acted in bad
faith.
vacated when arbitrators have exceeded their powers. TEX. CIV. PRAC. & REM.
CODE 171.088 (a)(3)(A); Townes Telecomms., Inc. v. Travis, Wolff & Co.,
L.L.C., 291 S.W.3d 490, 493-94 (Tex. App. Dallas 2009, pet. denied. Arbitrators
11
exceed their powers, and may render their awards unenforceable, when they stray
from interpretation and application of the parties contract. Id. (quoting Major
Leage Baseball Players Assn v. Garvey, 121 S. Ct. 1724, 1728 (2001) (per
curiam) (in turn quoting United Steelworkers of Am. v. Enter. Wheel & Car Corp.,
80 S. Ct. 1358, 1361 (1960))); Nafta Traders, Inc. v. Quinn, 339 S.W.3d 84, 93
(Tex. 2011).
Courts have held that in order to draw its essence from the contract, the
arbitrators award must have a basis that is at least rationally inferable, if not
must, in some logical way, be derived from the wording or purpose of the
contract. Id. (quoting Executone Info. Sys., Inc. v. Davis, 26 F.3d 1314, 1325 (5th
Cir. 1994)).
arbitrators powers, the Courts look only at the result. Id. The single question is
whether the award, however arrived at, is rationally inferable from the contract.
Id. (quoting Anderman/Smith Operating Co. v. Tenn. Gas Pipeline Co., 918 F.2d
1215, 1219 n. 3 (5th Cir.1990)); Ancor Holdings, LLC v. Peterson, Goldman &
Villani, Inc., 294 S.W.3d 818, 829 (Tex. App.Dallas 2009, no pet.) (The award
must be derived in some way from the wording and purpose of the contract, and
12
we look to the result reached to determine whether the award is rationally inferable
1. The Court of Appeals erred because the Arbitrator's Award does not
draw its essence from the contract since the Arbitrator ignored the
plain language of the contract that Petitioner would not be liable for the
acts or neglect of the utility providers.
CODE 271.153. The terms of the contract were written in such a way to conform
with the immunity afforded to the Petitioner as it relates to delays caused by others
There are four (4) Articles, 4.3, 4.4, 7.1, and 12.1(D), contained in the Sugar
Road project contract that clearly address to whom the duty and responsibility of
Under the plain language of the parties Contracts under Article 12.1(D), the
increase in the contract price or other damages arising out or resulting from the
following:
13
2. Delays beyond the control of both Owner and Contractor, including
but not limited to fires, floods, epidemics, abnormal weather
conditions, acts of God, or acts or neglect by those performing other
work including [utility owners]. (3C.R.:337).
These contractual provisions were written in this way because Texas law is
clear that rewards to claimants arising from a breach of contract are limited against
local government entity to those that directly result from owner caused delays.
relocating its utility lines upon notice by a city. This well-established law makes
clear that COE cannot be held responsible for the delays caused by others. The
evidence shows that Respondent had complete knowledge and understanding that
the utility lines were owned by others. Respondent admits that the movement or
Texas Gas lines (3) were the responsibility of either AT&T and/or Texas Gas, and
not COE. 3C.R.:817 at (Pg. 183, Ln. 24 - Pg. 184, Ln. 5; Pg. 184, Ln. 23-Pg. 184,
Ln. 25); 3C.R.: 819 at (Pg. 189, Ln. 20- 25); 3C.R.: 820 at (Pg. 196, Ln. 4-23);
completing its work on the Sugar Road project, which caused delays and
inefficiencies. (3C.R.: 781) (Pg. 38, Ln. 2-Pg. 39, Ln. 19). The contract under
responsibility of other entities, and not Petitioner to complete this work. Despite
the contract terms, the Arbitrator clearly ignored these contractual provisions by
stating that [t]he City failed to timely, reasonably, and properly manage the
removal of obstacles, conflicts, and obstructions in the areas in which IOC was to
perform the scope of work under the Sugar Road project contract. COE had the
duty and responsibility to manage the removal of these in areas which IOC was to
shows that the essence of the contract was to have the utility owners re-locate their
own utility lines. Thus, the Arbitration Award is not derived from the wording or
purpose of the contract because the Arbitrator awarded damages for delays that
15
D. The Trial Court did not err in vacating the Arbitrators Award because
the Award was obtained by undue means in violation of 171.088(a)(1),
since the Arbitrator acted in bad faith by flagrantly disregarding
statutory provisions and unambiguous contractual terms.
The Trial Court did not err in vacating the Arbitration Award because it was
obtained by undue means since the Arbitrator acted in bad faith in violation of
Tex. Civ. Prac. & Rem. Code 171.088(a)(1). First, the Arbitrator flagrantly
disregarded well established statutes that limit the award against local
provisions, including but not limited to, provisions regarding requests for
additional compensation, change orders, and differing site conditions. Thus, the
Trial Court correctly granted Petitioners Motion to Vacate because the Arbitrator
resulted in a decision that is arbitrary and capricious and implies bad faith.
award was obtained by fraud, corruption, or other undue means. Tex. Civ. Prac. &
Rem. Code 171.088(a)(1). The Texas Arbitration Act does not define other
undue means. Las Palmas Medical Center v. Moore, 349 S.W.3d 57, 70 (Tex.
App.El Paso 2010, pet. denied). Texas Courts have defined undue means to be
actions that are immoral, illegal, or bad-faith conduct. Good Times Stores, Inc. v.
Macias, 355 S.W.3d 240 (Tex. App.El Paso 2011, pet. denied).
16
A gross mistake is a mistake that implies bad faith or a failure to exercise
honest judgment and results in a decision that is arbitrary and capricious. Black v.
Shor, 443 S.W.3d 154, 169 (Tex. App.Corpus Christi 2013, pet. denied). A
gross mistake is shown when the arbitrator disregards and fails to apply the plain
terms of a contract and controlling law. Werline v. E. Texas Salt Water Disposal
Co., Inc., 209 S.W.3d 888, 901 (Tex. App.Texarkana 2006), aff'd, 307 S.W.3d
267 (Tex. 2010). Such egregious conduct warrants the inference that the arbitrator
acted in bad faith or failed to exercise honest judgment. Id. The questions to be
answered by the Court is merely whether the Arbitrator erred so egregiously that
It is obvious from the record that the Arbitrator disregarded the specific
mandates of the law and the plain terms of the contract. This egregious conduct
warrants the inference that the Arbitrator acted on bad faith. Thus, vacatur of the
As outlined previously in this Petition, the law is clear that a party cannot
recover damages from a local government entity for delays that are not owner
caused pursuant to the Texas Local Government Code 271.153(a)(1). The Texas
Supreme Court reiterated in Zachry that a claimant cannot recover for delays that
17
are not owner caused. In contravention of well-established Texas law, the
Arbitrator ignored the law and issued Respondent an Arbitration Award for delays
that were not caused by COE. Thus, Arbitrator, William Andrews, erred so
inefficiencies caused by other entities, namely AT&T and Texas Gas. The same
argument for the Canton Road project applies to the Sugar Road project with
respect to COEs liability for the actions of others. Despite this well-established
precedent and the testimony from Respondents own expert, the Arbitrator ignored
the statute.
At the Final Hearing on the Sugar Road project, Respondents own expert,
Jens Baker, testified that IOC complained that the delays were primarily caused by
AT&T. 3C.R.:813. Mr. Baker, further testified that he identified 384 days of
delays on the job, 174 of which were attributable to the late start and manhole
issues of AT&T, and 101 days, which were attributable to Texas Gas changes.
3C.R.:844 (P. 289, L. 6-25). He also testified that he could portion those damages
attributable to third parties versus those directly caused by COE. 3C.R.:844 (P.
that 71.61%, or 275 delay days out of the 384 alleged delay days, of Respondents
18
Despite Respondents expert own admission that the delays were caused by
others, the record shows Arbitrator, William Andrews, clearly ignored 271.153.
The Arbitrators Award states 271.153, Local Government Code, does not bar
IOCs claim for additional compensation arising out of the Canton Road project.
3C.R.:120.
Despite the clear statutory language and Texas Supreme Court precedent,
that a city cannot be liable for damages caused by others, the Arbitrator awarded
William Andrews, flagrantly disregarded 271.153 and based his Final Award of
Arbitrator on the premise that [t]he Citys material breaches are not excused
based on the failure of any third party to remove or re-locate their lines or utilities
3C.R.:120-121.
The result of the Arbitration Award, in this case, disregards what otherwise
has been a well settled principal between municipalities and contractors. The
Arbitrator did not merely make a mistake of law in this case, but his actions are so
contractors and municipalities do business, and moot Texas Law with respect to
the adjudication of awards against municipalities. The disregard of the law and
19
It is clear from the record the Arbitrator acted in bad faith because despite
the overwhelming evidence that the delays were caused by others nonetheless
Sugar Road project contract and Canton Road project contract. The Sugar Road
project contract clearly outlines that COE is not liable for damages caused by
others. The Canton Road project contract clearly outlined the manner in which
the terms was waiver of future claims for additional compensation. Thus, the
Arbitrator failed to apply the plain language of the contract, which implies bad
faith.
As stated previously, the Sugar Road project contract contains four (4)
Articles, 4.3(B), 4.4, 7.1, and 12.1(D), that clearly state that the duty and
responsibility of re-locating the utility lines belonged to the utility owners. They
20
Based on the articles in the Sugar Road project contract, COE is precluded
from liability resulting for damages or increased contract time due to the work of
that the alleged delays were caused by utility lines, man holes, and utility poles
Respondent concedes that the re-location of the utility encumbrances were either
Therefore, COE cannot be held responsible, even if these issues caused delays
responsible for re-locating the utility lines but only bore the responsibility to notify
AT&T that the lines needed to be re-located. Respondent did not proffer any
evidence or argument that Petitioner did not notify AT&T to re-locate its utility
lines.
Further, the contract terms of both the Sugar Road project and Canton Road
project clearly outlined the manner in which a contractor should have used to
Respondent claimed that COE delayed in re-locating the traffic switch at the Sugar
comply with Special Provision 20 of the Sugar Road project contract. Special
21
Provision 20 required that Respondent: (1) provide the Petitioner with written
notice, (2) obtain a change order agreed upon by COE, Contractor, and COEs
Engineer, and (3) after the work was completed, file a claim for extra
Respondent admitted that it had not at the time of the Final Hearing, and still
had not, quantified the amount of delay or inefficiency damage related to the traffic
switch. 3C.R.: 822-823 (Pg. 204, Ln. 21-Pg. 205, Ln. 24).
With regard to the Canton Road project, Special Provision and General
Special Provision 18 states in part: in cases where the contractor deems extra
compensation is due him for materials not clearly covered in the contract, or not
ordered by the engineer as an extra item, the contractor shall notify the engineer in
writing of his intention to make a claim for such extra compensation before he
used and paid for by Respondent, as well as the equipment used and paid for by
Respondent during the project time frame. Despite having the requirement under
Section 18 of the Special Provisions to submit any request for extra compensation
within a specified time period, Respondent failed to do this and, by contract, its
22
alleged damages have been waived. Even further, as stated previously, IOC had all
known encumbrances prior to beginning their work on the Canton Road project.
They chose not to submit an alternate sequence of construction and they chose not
After completing the construction of the roadway, IOC chose not to make a
detailed request with a specified amount or, in fact, any request at all prior to the
completion and closing out of the project. For these reasons, IOCs request for
E. In the alternative, the Arbitrators Award for the Sugar Road project
should be modified because Respondent cannot recover for delays that
are not owner caused.
COE maintains that IOC cannot recover any damages arising from the Sugar
Road project because the damages are not owner caused and the award
Code 271.153. However, should this Court find that the Arbitration Award is
proper, then COE requests that the Arbitration Award be modified under 171.091.
23
Texas law is clear that a party cannot recover damages from a local
government entity for delays that are not owner caused. Texas Government
Code 271.153(a)(1).
Respondents expert, Jens Baker, testimony during the Final Hearing on the
Sugar Road project further substantiates our position that IOCs complaints of
delays were primarily caused by others, namely AT&T. 3C.R.:813 (Pg. 238, Lns.
8-14). Mr. Baker testified that he identified 384 days of delays on the job of which
275 days were caused by others, specifically, AT&T and Texas Gas. 3C.R.:844
(Pg. 89, Lns. 6-25). He further testified that he could portion those damages
attributable to third parties versus those directly caused by COE. 3C.R.:844 (Pg.
290, Ln. 1 Pg. 291, Ln. 24). Thus, in essence, Respondent admitted that 71.61%
or 275 days out of the 384 alleged delay days were not directly caused by COE.
Therefore, since 28.39% of the delays days or 109 days were allegedly
caused by COE, the Arbitration Award must be reduced to $191,090.82. Thus, the
Conclusion
This Court should grant the petition for review, reverse the judgment of the
Court of Appeals and affirm the ruling of the trial court vacating the subject
Arbitration Award. In the alternative, the Arbitrators Award for the Sugar Road
24
project should be modified to $191,090.82 because the Respondent cannot recover
Respectfully submitted,
Ricardo Palacios
State Bar No. 24010990
Criselda Palacios
State Bar No. 24067812
25
Certificate of Compliance
/s/Gerald E. Castillo
Gerald E. Castillo
Certificate of Service
This will certify that a true and correct copy of this document has been
forwarded to all counsel of record pursuant to the Texas Rules of Appellate
Procedure on the 22nd day of September 2017.
Ricardo Pumarejo, Jr. Via E-Service
Pumarejo Law
4801 Sage Hen Dr.
Austin, Texas 78727
Counsel for Respondents
Ricardo Palacios
Palacios Garza & Thompson, P.C.
2724 West Canton Road
Edinburg, Texas 78539
Counsel for Petitioner
/s/Gerald E. Castillo
Gerald E. Castillo
26
NO. 17-0778
PETITIONERS APPENDIX
27
Exhibit ''1"
AMERICAN ARBITRATION ASSOCIATION
Construction Industry Arbitration Tribunal
Introduction
The parties to this proceeding are 100 Company, LLC f'IOC"), a highway and road
contractor, and City of Edinburg, Texas ("City"), a municipality. IOC and the City
agreed to my appointment as the arbitrator in this proceeding and made no objections to
my continued service as arbitrator after I made disclosures.
The claims and disputes the parties are arbitrating, arise out of two projects but
involve similar facts, agreements and scopes of work. In addition, the witnesses
testifying about the claims and disputes arising out of both projects were identical.
Previously, the parties agreed to consolidate these claims and disputes and present
them to me for resolution.
I conducted bifurcated hearings with respect to each project. I heard the claims
and disputes arising out of the Canton Road Project first at the evidentiary hearing
devoted to that project held on February 17 and 18, 2014 which, by consent of the
parties, was held open until the establishment of the post hearing submission schedule
set forth in the Order Regarding Post Hearing Briefing Schedule. Next, I heard the
claims and disputes arising out of the Sugar Road Project at the evidentiary hearing
held on Aprill6 and 17, 2014. The hearings were declared closed on June 18, 2014.
The post hearing briefing schedule required the submission of briefs and closing
statements, replies and attorneys' fees affidavits for both projects.
In accordance with the post hearing submission schedule as set forth in the above
described Order and discussions memorialized in the hearing transcript, I am now
rendering this Final Award with respect to the claims and disputes arising out of both
projects.
roo and the City entered into an agreement dated Aprill, 2008 under which roo
agreed to perform paving, drainage improvements and expansion of a portion of Canton
Road for the City in accordance with the plans, specifications and information the City
furnished to roc.
roo seeks recovery of damages in the form of additional compensation due to the
City's claimed breach of contract, essentially consisting of delays, interferences and
disruptions it alleges the City caused it to suffer. roo also seeks recovery of attorneys'
fees, prejudgment interest and reimbursement of arbitrator compensation and costs.
The City contests IOC's legal entitlement to recovery of damages and argues IOC's
claims are barred or excluded by the parties' agreement and 271.153, Local
Government Code. The City strongly denies it was responsible for owner-caused delays
that increased rOO's cost to perform the work for this project. In particular, the City
argues the City was not responsible for relocating utility lines, encumbrances and
obstructions that hindered, delayed or disrupted IOC's ability to timely, efficiently and
in a linear, logical and sequential manner perform the required scope of work in
accordance with its construction plan. The City further argues any delays roo suffered
were caused by third parties over whom it had no control or responsibility.
Similarly, IOC and the City entered into an agreement dated June 2, 2009 under
which roo agreed to perform paving, drainage improvements and expansion and
widening of a portion of Sugar Road for the City in accordance with the plans,
specifications and information the City furnished to IOC.
Essentially, IOC's claim and the types of damages it seeks mirror those described
for the Canton Road Project. The same generally holds true for the City's defenses
although the City emphasizes several provisions in the Canton Road Agreement which
it asserts preclude IOC's claim and damages.
Based on the evidence presented to me, the Canton Road Agreement and the law of
the State of Texas, I find the City materially breached this Agreement without excuse
and is liable to roc for damages in the form of additional compensation arising from
2
City-caused delays, disruptions and interferences. I further find IOC did not materially
breach the Agreement. I discuss the facts and reasons in support of these findings
below.
The evidence concerning IOC's efforts to perform the scope of work for the Canton
Road Project and the numerous, serious and costly City-caused delays, interferences
and disruptions it suffered in those efforts is compelling and supports my finding the
City materially breached the Agreement.
This evidence established the following facts and supports the following reasons
for my entering an award in IOC's favor on its claim arising out of the Canton Road
Project:
1. The City failed to timely and properly provide IOC with the lands necessary
for it to perform the scope of work under the Canton Road Agreement.
2. The City failed to provide IOC timely and proper access to the areas in
which it was to perform the scope of work under the Canton Road
Agreement.
3. The City failed to provide IOC with unhindered and unobstructed access to
the areas in which it was to perform the scope of work under the Canton
Road Agreement.
4. 'rhe City failed to timely, reasonably and properly manage the removal of
obstacles, conflicts and obstructions in the areas in which roc was to
perform the scope of work under the Canton Road Agreement. 'l'he City had
the duty and responsibility to manage the removal of these in the areas in
which roc was to perform the scope of work.
5. The City's preceding failures delayed IOC's ability to timely and efficiently
perform the scope of work under the Canton Road Agreement.
7, The City's preceding failures disrupted and interfered with IOC's ability to
timely and efficiently perform the scope of work under the Canton Road
Agteement.
8. The number and quality of the utility lines (underground and above
ground), power poles, splicing operations, gas lines and meters and
3
manholes which singularly and cumulatively delayed and disrupted IOC's
work performance are significant and compelling. These are City-caused
delays, disruptions and interferences.
9. The City also failed to timely acquire permits and easements from the local
drainage and irrigation districts which also delayed and disrupted IOC's
work performance. These, too, are City-caused delays, disruptions and
interferences.
10. As a result of the City-caused delays and the City's material breach of the
Agreement, roc suffered increased costs in the amount of $1,362,630 to
perform the scope of work under the Canton Road Agreement. These costs
consist of labor costs in the sum of $480,682, equipment costs in the sum of
$475,639, material escalation costs in the sum of $200,075, extended field
costs in the sum of $28,500 and mark-up of $177,734.
11. The City is liable to IOC for the increased costs totaling $1,362,630 (set
forth in the preceding subparagraph) as additional compensation.
12. The City is also liable to IOC for IOC's reasonable attorneys' fees in the sum
of $158,000.
13. 271.153, Local Government Code, does not bar rOC's claim for additional
compensation arising out of the Canton Road Project.
14. Special Provision 18 of the Canton Road Agreement is not applicable to the
claim asserted by IOC; roc did not breach or violate this provision.
Therefore, Special Provision 18 does not bar or preclude rOC's claim.
17. By its failures and conduct as described above, the City wrongfully
prevented roc from timely and efficiently performing its work.
18. IOC's further performance under the Agreement was excused by the City's
prior material breaches.
19. The City's material breaches are not excused based on the failure of any
4
third party to remove or relocate their lines or utilities that constitute
obstacles, conflicts and obstructions as described above.
20. The delays IOC experienced were City-caused and compensable to IOC.
IOC's fared no better on the Sugar Road Project in terms of the delays,
interferences and disruptions it suffered at the hands of the City. Once again, the
evidence, the Sugar Road Agreement and the law of the State of Texas compel me to find
the City materially breached the Sugar Road Agreement without excuse and is liable to
IOC for damages in the form of additional compensation arising from City-caused delays.
roc did not materially breach the Agreement. As before, I discuss the facts and reasons
in support of these findings below.
The evidence of IOC's efforts to perform the scope of work for the Sugar Road
Project and the numerous, serious and costly City caused delays, interferences and
disruptions it suffered in those efforts is similarly compelling and supports my finding
the City materially breached the Sugar Road Agreement.
Again, this evidence supports the following facts and reasons for my entering an
award in rOC's favor on its claim arising out of the Sugar Road Project:
1. The City failed to timely and properly provide IOC with the lands necessary
for it to perform the scope of work under the Sugar Road Agreement.
2. The City failed to provide rOC timely and proper access to the areas in
which it was to perform the scope of work under the Sugar Road Agreement.
3. The City failed to provide rOC with unhindered and unobstructed access to
the areas in which it was to perform the scope of work under the Sugar Road
Agreement.
4. The City failed to timely, reasonably and properly manage the removal of
obstacles, conflicts and obstructions in the areas in which roc was to
perform the scope of work under the Sugar Road Agreement. The City had
the duty and responsibility to manage the removal of these in the areas in
which IOC was to perform the scope of work.
5, 'rhe City's preceding failures delayed rOC's ability to timely and efficiently
perform the scope of work under the Sugar Road Agreement.
5
and efficiently perform the scope of work under the Sugar Road Agreement.
7. The City's preceding failures disrupted and interfered with IOC's ability to
timely and efficiently perform the scope of work under the Sugar Road
Agreement.
8. The number and quality of the gas lines, manholes, utility poles, and
subgrade access problems delayed and disrupted IOC's work performance
are significant and compelling. In addition, the City stopped IOC's
performance of work in one area south of Owassa Street which further
delayed and disrupted IOC's work. These are City-caused delays,
disruptions and interferences.
9. As a result of the City-caused delays and the City's material breach of the
Sugar Road Agreement, 100 suffered increased costs in the amount of
$673,092 to perform the scope of work under the Sugar Road Agreement.
These costs consist of labor costs in the sum of $219,191, equipment costs in
the sum of $290,944, material costs in the sum of $60,163, extended field
costs in the sum of $15,000 and mark-up in the sum of $87,794.
10. The City is liable to IOC for the increased costs set forth in the preceding
subparagraph in the sum of $673,093 (as set forth in the preceding
subparagraph) as additional compensation, none of which is barred by
271.153, Local Government Code.
11. The City is also liable to IOC for IOC's reasonable attorneys' fees in the sum
of $127,827.
12. 271.153, Local Government Code, does not bar IOC's claim for additional
compensation asserted by IOC against the City arising out of the Sugar
Road Project nor does it bar the damages I am awarding IOC in the amount
of $673,093.
15. By its failures and conduct as described above, the City wrongfully
prevented roc from timely and efficiently performing the scope of work
6
under the Sugar Road Agreement.
16. IOC's further performance under the Agreement was excused by the City's
prior material breaches.
17. The City's material breaches are not excused based on the failure of any
third party to remove or relocate their lines or utilities that constitute
obstacles, conflicts and obstructions as described above.
18. Art. 12.1(D) of the Sugar Road Agreement does not bar IOC's claims or
damages. Neither Special Provision 18 or 20 preclude IOC''s claims or
damages.
19. Art. 14.8A of the Sugar Road Agreement does not bar IOC's claim or
damages.
20. The delays IOC experienced were City-caused and compensable to IOC.
Award
a. The City shall pay IOC the sum of $1,362,630, the components
of which are set forth in finding number 10 under the Findings
Regarding the Canton Road Project set forth above; and
a. The City shall pay IOC the sum of $$673,092, the components
of which are set forth in finding number 9 under the Findings
Regarding the Sugar Road Project set forth above; ; and
7
The above sums are to be paid on or before 30 days from the date of this Award.
8
Exhibit ''2"
Electronically Filed
8/25/2014 2:39:22 PM
Hidalgo County District Clerks
Reviewed By: Jassia De La Paz
NOW COMES, City of Edinburg, and files this Amended Petition/Application to Vacate an
CIVIL PRACTICE& REMEDIES CODE and pursuantto Texas Common Law and would respectfully show
I.
PARTIES
IOC Company, L.L.C. is a Texas corporation organized and existing under the laws of the
State ofTexas and is authorized to do business in the State ofTexas. IOC Company, L.L.C. may
be served with Citation in this action by Service of Citation to: Jesus Garcia, Jr., TUCKER,
BARNES, GARCIA & DE LA GARZA, P.C., JP Morgan Chase Building, 712 Main, Suite 1600,
II.
VENUE
This Petition is filed as an initial application in Hidalgo County, the county in which the hearing
Ill.
REQUIREMENTS FOR A PETITION TO VACATE ARBITRATION AWARD
A Petition to Vacate an Arbitration Award must comply with the requirements set forth
by the Texas Civil Practice and Remedies Code 171.085(a) so that City of Edinburg must:
(3) Define the issue subject to arbitration between the parties under the
Agreement;
(4) Specify the status of the Arbitration before the arbitrator; and
(5) Show the need for the Court Order sought by the applicant.
IV.
JURISDICTION
The amount in controversy is with the jurisdictional limits of the District Court.
v.
AGREEMENT TO ARBITRATE
On or about April1, 2008, the City of Edinburg and IOC Company, L.L.C. entered into a
formal contract entitled 'Paving and Training Improvements for Canton Road' (Canton Road
Project). The Parties' Agreement is attached hereto as Exhibit "A" and incorporated by reference
as if set forth fully and at length. In Section 36 of the Agreement, the parties agreed to arbitrate
any dispute concerning the contract pursuant to the rules of the American Arbitration
Association.
- 2-
Electronically Filed
8/25/2014 2:39:22 PM
Hidalgo County District Clerks
Reviewed By: Jassia De La Paz
In addition, on or about June 2, 2009, the City of Edinburg and IOC Company, L.L.C.
entered into a formal contract entitled 'Paving and Drainage Improvements for Sugar Road'
(Sugar Road Project). The Parties Agreement is attached hereto as Exhibit "B" and incorporated
In paragraph IX of the Agreement, the parties agreed to arbitrate any dispute concerning
written demand for arbitration to the City of Edinburg and with the American Arbitration
Association. A copy of the parties' written agreement is attached as Exhibit "C" and incorporated
by reference.
IV.
ISSUE IN CONTROVERSY
IOC Company, L.L.C. seeks damages as a result of the City of Edinburg's alleged failure
to perform its duties under contracts with IOC for both the Sugar and Canton Road Projects. IOC
Company, L.L.C. claims that during the performance of both projects, the City of Edinburg's
unwillingness and inability to provide right-ofways, easements, and coordinate with third parties
caused significant delays and damages to IOC Company, L.L.C. As such, IOC Company, L.L.C.
filed a Demand for Arbitration asserting claims for breach of contract. The Arbitration Agreement
VII.
STATUS OF THE ARBITRATION
IOC Company, L.L.C. initiated an arbitration proceeding against the City of Edinburg for
two (2) projects referred to as the Canton Road Project and the Sugar Road Project. On July 18,
-3-
Electronically Filed
8/25/2014 2:39:22 PM
Hidalgo County District Clerks
Reviewed By: Jassia De La Paz
2014, an arbitration award was issued by William Andrews, Arbitrator. The arbitration award
was for a total sum $1,362,630 for the Canton Road Project and $673,093 for the Sugar Road
VIII.
NEED FOR COURT ORDER
The City of Edinburg hereby submits that the arbitration award needs to be vacated for
The City of Edinburg hereby submits that the arbitration award needs to be vacated as
the award was obtained by "undue means" so far so that the City of Edinburg's rights at the
hearing were affected and deprived them of a fair hearing. In addition, the arbitrator exceeded
his powers in granting of the award. Specifically, the arbitrator failed to honor and recognize
contractually agreed upon provisions between IOC Company, L.L.C. and the City of Edinburg,
including but not limited to, provisions regarding requests for additional compensation, change
orders, differing site conditions, and the responsibility of the City of Edinburg for the actions of
"others." Failure of the arbitrator to honor and recognize contractually agreed upon provisions
deprived the City of Edinburg a fair hearing. Implementing the arbitrator's award in this case
-4-
Electronically Filed
8/25/2014 2:39:22 PM
Hidalgo County District Clerks
Reviewed By: Jassia De La Paz
would stand for the proposition that contractors are not bound by contractually agreed upon
provisions in the handling of construction projects with the City of Edinburg andjor other
municipalities. Thus, the arbitrator exceeded his powers in granting the award.
Further, the City of Edinburg also submits that the arbitration award violates public policy
Government Code 271-153, that a municipality cannot be adjudicated an award for the
actions of others. The facts of this matter clearly illustrated that the problems that IOC
Company, L.L.C. complained of in the construction project of Canton Road and Sugar Road were
issues caused by others, specifically utility companies such as AT&T and Texas Gas Service.
Despite facts clearly illustrating this, the arbitrator disregarded this fact and issued the award
against the City of Edinburg contrary to established law. The results of such action in this case
would dictate that municipalities and contractors could no longer operate under the basic
principles that the state has mandated. The arbitrator did not merely make a mistake of law
in this case, but his actions are so contrary to established law and public policy that it would
change the manner in which contractors and municipalities do business, and moot Texas law
with respect to the adjudication of awards against municipalities. Therefore, vacating the award
WHEREFORE, PREMISES CONSIDERED, the City of Edinburg, Texas, requests that IOC
Company, L.L.C. be cited to appear and answer, and that on final trial, City of Edinburg, Texas,
Movant herein, have the Court enter a Judgment to Vacate the Arbitration Award given in
-5-
Electronically Filed
8/25/2014 2:39:22 PM
Hidalgo County District Clerks
Reviewed By: Jassia De La Paz
Respectfully submitted,
Ricardo Palacios
SBN:24010990
Griselda Palacios
SBN:24067812
2724 West Canton Road
Edinburg, Texas 78539
(956) 318-0507
FAX: (956) 318-0575
rpalacios@pgtlawfirm.com
cpalacios@pgtlawfirm.com
CERTIFICATE OF SERVICE
I hereby certify that a true and correct copy of the above and foregoing document has
been forwarded as a courtesy copy to attorney for Defendant via electronic mail, on this 25th day
of August, 2014.
Is/Gerald E. Castillo
Gerald E. Castillo
F:\data\WPDOCS\C\CITY OF EDINBURG\IOC v. COE\Petltlon application to vacate arbitration award 082014 1st amended.sm.wpd
- 6-
Exhibit u3"
Electronically Filed
1/5/2016 6:07:43 PM
Hidalgo County District Clerks
Reviewed By: Andrea Lopez
#70 441 Y 00190 12. The Court, after having heard the argument of counsel and having read
the pleadings on file, finds that the Amended Petition/Application to Vacate Arbitration Award
cc: Steven Gonzalez/Gerald E. Castillo, GONZALEZ CASTILLO, LLP, 1317 E. Quebec Ave., McAllen, Texas, FAX:
(956) 618-0445; email: law@valleyfirm.com and gcastillo@valleyfirm.com
Jesus Garcia, Jr., TUCKER, BARNES, GARCIA & DE LA GARZA, P.C., JP Morgan Chase Building, 712 Main,
Suite 1600, Houston, Texas 77002-3297; email: jgarcia@tuckervaughan.com
Gil Peralez, 1416 W. Dove Avenue, McAllen, Texas 78503; email: gpp@peralezfranzlaw.com
Michael A. McGurk, KITTLEMAN THOMAS, PLLC, 4900-B N. 10th St., McAllen, Texas 78504; Email
mmcgurk@ktattorneys.com
TB
Exhibit '' 4"
NUMBER 13-16-00117-CV
COURT OF APPEALS
v.
MEMORANDUM OPINION
Before Justices Rodriguez, Benavides, and Longoria
Memorandum Opinion by Justice Benavides
This appeal concerns the trial courts orders: (1) granting appellees, the City of
Edinburg (the City), motion to vacate an adverse arbitration award rendered in favor of
appellant, IOC Company, LLC (IOC); and (2) denying IOCs motion to confirm the same
arbitration award. By one issue, IOC contends that the trial court erred in vacating rather
than confirming the arbitration award. We reverse and render.
I. BACKGROUND
IOC is a Texas limited liability company that is in the business of highway and road
On April 1, 2008, IOC and the City entered into an agreement regarding
engineering and architectural construction for paving and drainage improvements for
Canton Road located in the City (the Canton Road Project). The Canton Road Project
agreement contained a section which required any controversy or claim arising out of or
relating to [the Canton Road Project], or the breach thereof which could not be resolved
On June 2, 2009, IOC and the City entered into a second, separate agreement
improvements for Sugar Road located in the City (the Sugar Road Project). The Sugar
Road Project agreement contained separate mediation and arbitration clauses. The
mediation clause called first for a quick resolution of any and all disputes, if any under
the contract, and the agreement provided that if the dispute failed to resolve at mediation,
Subsequently, claims and disputes by IOC against the City arose related to both
the Canton Road Project and the Sugar Road Project. Both matters were consolidated
and arbitrated by the same arbitrator, who conducted bifurcated evidentiary hearings for
each contract during the months of February 2014 and April 2014. The hearings were
2
closed on June 18, 2014.
According to the record, IOC sought recovery for damages in the form of
additional compensation due to the Citys claims breach of contract, essentially consisting
of delays, interferences, and disruptions caused by the City during its work on the Canton
Road Project. IOC also sought recovery of attorneys fees, prejudgment interest, and
damages under section 271.153 of the local government code. See TEX. LOCAL GOVT
CODE ANN. 271.153 (West, Westlaw through Ch. 49, 2017 R.S.) (placing limitations on
adjudication awards against local governmental entities for breach of contract). Further,
the arbitrators award notes that the City strongly denie[d] it was responsible for owner-
caused delays and claimed that it was not responsible for relocating utility lines,
timely, efficiently . . . perform the required scope of work under the Canton Road Project
construction plan. Further, the City argued that any delays that IOC suffered were
The arbitrator found that the City materially breached the Canton Road agreement
without excuse and was liable to IOC for damages in the form of additional
arbitrator found that IOC did not materially breach the agreement. To support these
3
(1) The City failed to timely and properly provide IOC with the lands
necessary for it to perform the scope of work . . . .
(2) The City failed to provide IOC timely and proper access to the areas
in which it was to perform the scope of work . . . .
(3) The City failed to provide IOC with unhindered and unobstructed
access to the areas in which it was to perform the scope of work . . . .
(4) The City failed to timely, reasonably[,] and properly manage the
removal of obstacles, conflicts[,] and obstructions in the areas in
which IOC was to perform the scope of work . . . . The City had the
duty and responsibility to manage the removal of these in the areas
in which IOC was to perform the scope of work.
(5) The Citys preceding failures delayed IOCs ability to timely and
efficiently perform the scope of work . . . .
(7) The Citys preceding failures disrupted and interfered with IOCs
ability to timely and efficiently perform the scope of work.
(8) The number and quality of the utility lines (underground and above
ground), power poles, splicing operations, gas lines and meters[,]
and manholes which singularly and cumulatively delayed and
disrupted IOCs work performance are significant and compelling.
These are City-caused delays, disruptions[,] and interferences.
(9) The City also failed to timely acquire permits and easements from
the local drainage and irrigation districts which also delayed and
disrupted IOCs work performance.
The arbitrator further concluded that section 271.153 of the local government code
was not a bar to IOCs recovery and found that as a result of the City-caused delays and
the Citys material breach of the Canton Road agreement, IOC incurred damages of
$200,075 in material escalation costs; $28,500 in extended field costs; and $177,734 in
mark-up costs. Furthermore, the arbitrator found the City liable for to IOC for $158,000
4
in reasonable attorneys fees.
The record shows that the arbitrator found IOCs claims and damages sought
under the Sugar Road Project agreement mirror[ed] those described for the Canton Road
Project agreement. The arbitrator also found that the City asserted the same defenses
as in the Canton Road Project dispute, although the City emphasize[d] several provisions
in the Canton Road Agreement to support its defense in the Sugar Road Project dispute.
The arbitrator found that the City materially breached the Sugar Road Project
agreement without excuse and was liable to IOC for damages. The arbitrator further
found that IOC did not materially breach the agreement. To support these general findings
(1) The City failed to timely and properly provide IOC with the lands
necessary for it to perform the scope of work . . . .
(2) The City failed to provide IOC timely and proper access to the areas
in which it was to perform the scope of work . . . .
(3) The City failed to provide IOC with unhindered and unobstructed
access to the areas in which it was to perform the scope of work . . .
.
(4) The City failed to timely, reasonably[,] and properly manage the
removal of obstacles, conflicts[,] and obstructions in the areas in
which IOC was to perform the scope of work . . . . The City had the
duty and responsibility to manage the removal of these in the areas
in which IOC was to perform the scope of work.
(5) The Citys preceding failures delayed IOCs ability to timely and
efficiently perform the scope of work . . . .
5
(6) The City is responsible for owner-caused delays to IOCs ability to
timely and efficiently perform the scope of work . . . .
(7) The Citys preceding failures disrupted and interfered with IOCs
ability to timely and efficiently perform the scope of work.
(8) The number and quality of the gas lines, manholes, utility poles, and
subgrade access problems delayed and disrupted IOCs work
performance are significant and compelling. In addition, the City
stopped IOCs performance of work in one area south of Owassa
Street which further delayed and disrupted IOCs work. These are
City-caused delays, disruptions[,] and interferences.
The arbitrator found that section 271.153 of the local government code did not bar
IOCs claim for additional compensation under the Sugar Road Project agreement, and
that as a result of the City-caused delays and the Citys material breach of the Sugar
Road agreement, found that IOC incurred damages of $673,092, consisting of $219,191
extended field cost; and $15,000 in mark-up costs. Furthermore, the arbitrator found the
Finally, the arbitrator ordered that administrative fees and expenses of the
American Arbitration Association totaling $11,450 shall be borne by the City and the
compensation and expenses of the arbitrator totaling $28,911.48 shall likewise be borne
by the City, requiring the City to reimburse IOC $25,905.74 representing IOCs portion of
said fees and expenses in excess of the apportioned costs previously incurred by IOC.
On August 14, 2014, the City filed a petition and application to vacate the entire
arbitration award. IOC subsequently answered the Citys petition, moved to deny the
Citys application to vacate, and filed its own petition and motion to confirm the arbitrators
6
award and for entry of final judgment.
In its brief in support of vacating the arbitration award, the City argued that the
award should be vacated under the following grounds: (1) under civil practice and
remedies code section 171.088(a)(1), see TEX. CIV. PRAC. & REM. CODE ANN.
171.088(a)(1) (West, Westlaw through Ch. 49, 2017 R.S.); (2) under civil practice and
remedies code section 171.088(a)(3)(A), see id. 171.088(a)(3)(A); (3) under civil
practice and remedies code section 171.091, see id. 171.091 (West, Westlaw through
Ch. 49, 2017 R.S.); and (4) pursuant to Texas common law. In support of its arguments,
the City attached several exhibits to its motion, including, in relevant part: (1) copies of
both contracts at issue; (2) depositions from Isael Posadas, the then-city engineer for the
City, who testified about the Canton Road and Sugar Road Projects; (3) depositions from
Oscar Cuellar, the managing member of IOC, who testified about the Canton Road and
On January 27, 2015, the trial court held a hearing on both parties motions, and
subsequently granted the Citys motion to vacate and denied IOCs motion to confirm.
By one issue, IOC asserts that the trial court erred in vacating rather than
A. Standard of Review
Texas law favors arbitration, and thus, judicial review of an arbitration award is
extraordinarily narrow. E. Tex. Salt Water Disposal Co. v. Werline, 307 S.W.3d 267, 271
(Tex. 2010). We review a trial court's ruling to vacate or confirm an arbitration award de
7
novo, and we review the entire record. OGrady v. Natl Union Fire Ins. Co. of Pittsburgh,
P.A., 506 S.W.3d 121, 124 (Tex. App.Corpus Christi 2016, pet. denied) (mem. op.).
The Texas Supreme Court has long held that an award of arbitrators upon matters
submitted to them is given the same effect as the judgment of a court of last resort, and
all reasonable presumptions are indulged in favor of the award, and none against it. Id.
award, it bears the burden in the trial court of bringing forth a complete record that
B. Discussion
As a preliminary matter, IOC contends that the City based its motion to vacate on
three grounds: (1) under Texas common law; (2) under section 171.088(a)(1) of the civil
practice and remedies code; and (3) under section 171.088(a)(3)(A). IOC further argues
that the Citys first ground in support of vacatur is untenable under the Texas Supreme
Courts 2016 decision in Hoskins v. Hoskins, which held that under the Texas Arbitration
Act (TAA), section 171.088 provides exclusive grounds for a vacatur of an arbitration
award. 497 S.W.3d 490, 497 (Tex. 2016); see also Hall Street Assocs. v. Mattel, Inc.,
552 U.S. 576, 578 (2008) (holding that statutory grounds for prompt vacatur under the
Federal Arbitration Act (FAA) are exclusive). The City responds to IOCs argument by
acknowledging the Hoskins opinion, and urges us to affirm the trial courts vacatur award
will address each ground in turn and will not address any arguments supporting vacatur
8
1. Section 171.088(a)(1)Other Undue Means
award was obtained by corruption, fraud, or other undue means. See TEX. CIV. PRAC.
& REM. CODE ANN. 171.088(a)(1). Courts have defined behavior amounting to undue
means as that which is immoral, illegal, or bad-faith conduct. Las Palmas Med Ctr. v.
Moore, 349 S.W.3d 57, 69 (Tex. App.El Paso 2010, pet. denied) (citing LeFoumba v.
Legend Classic Homes, Ltd., No. 14-08-00243-CV, 2009 WL 3109875 (Tex. App.
Houston [14th Dist.] 2009, no pet.) (mem. op.)); see also In re Arbitration Between Trans.
Chem., Ltd. & China Natl Machinery Import & Export Corp., 978 F. Supp. 266, 304 (S.D.
Tex. 1997) (defining undue means under the FAA as behavior that is immoral, if not
vacate an arbitration award on the basis of undue means. See Las Palmas, 349 S.W.3d
at 69.
The City first argues that the award in this case should be vacated because it was
obtained by undue means because the arbitrator: (1) flagrantly disregarded well[-
]established statutes that limit the award against local governments; and (2) disregarded
unambiguous contractual provisions, including but not limited to, provisions regarding
requests for additional compensation, change orders, and differing site conditions.
The Citys first argument concerns the applicability of section 271.153 of the local
government code to the arbitration award. Section 271.153(a)(1) permits a party, like
IOC, to recover in a breach of contract action against a local governmental entity, like the
City, the balance due and owed by the local governmental entity under the contract as it
may have been amended, including any amount owed as compensation for the increased
9
cost to perform the work as a direct result of owner-caused delays or acceleration. TEX.
LOCAL GOVT CODE ANN. 271.153(a)(1). The City directs us to testimony from the Sugar
Road Project arbitration proceeding by Jens Baker. Baker testified on behalf of IOC that
and determine fault for delays and inefficiencies during the contract. Baker explained
that delays in this project were caused by the City, manhole issues created by AT&T,
and unforeseen site conditions attributed to Texas Gas. Of these delays, Baker
testified at the arbitration proceeding that some of the delays were exclusively attributable
to either the City, AT&T, Texas Gas, or some combination of those parties. After this
testimony, however, IOCs attorney argued that the City is responsible for everything,
and they are the ones that have control over Texas Gas and all the utilities.
After reviewing the entire record in this case, we cannot conclude that the City met
its burden to establish that IOC obtained its award based upon undue meansthat is,
conduct amounting to immoral, illegal, or bad-faith conduct. See Las Palmas, 349
S.W.3d at 69. Even if the arbitrator made minor errors or misapplied section 271.153 of
the local government code to the facts of this case, as the City argues, such a mistake of
law is not enough to amount to undue means. See id. Accordingly, we conclude that
the City failed to meet is burden to vacate the arbitration award under section
On application of a party, the trial court shall vacate an award if the arbitrator
exceeded his powers. See TEX. CIV. PRAC. & REM. CODE ANN. 171.088(a)(3)(A). An
arbitrator exceeds his powers when he decides matters not properly before him. In re
10
Guardianship of Cantu de Villarreal, 330 S.W.3d 11, 23 (Tex. App.Corpus Christi 2010,
no pet.). When determining whether an arbitrator has exceeded his power, any doubts
concerning the scope of what is arbitrable should be resolved in favor of arbitration. Id.
It is only when the arbitrator departs from the agreement and, in effect, dispenses his own
The arbitrator in this case derived his authority from both agreements. The
Canton Road Project agreement stated that any controversy or claim arising out of or
relating to [the Canton Road Project], or the breach thereof would be submitted to
arbitration; and the Sugar Road Project agreement stated that any and all disputes
under the contract that failed to resolve by mediation would be submitted to arbitration.
IOC asserted its claims and disputes under both agreements through arbitration
proceedings. The record does not show that the City disputed IOCs efforts to do so or
that such claims were not subject to the arbitration clause. Instead, the City argues first
that the arbitrator ignored the plain language of the contract, which would entitle the City
to immunity from certain damages under section 271.153 of the local government code.
See TEX. LOCAL GOVT CODE 271.153. Secondly, the City argues that the arbitrator
ignored a provision of the Canton Road Project agreement which mandated that the
contractor was to give the City written notice of any extra costs related to the contract.
The record shows that both contracts in this case gave the arbitrator wide and full
authority to decide any and all controversies, claims, or disputes, arising out of the Canton
Road and Sugar Road agreements. Accordingly, IOCs breach of contract claims and
requests for damages were properly before the arbitrator. Although the arbitrator may
have resolved the disputes in a way that the City finds unfavorable, and the decision may
11
have been reached erroneously based on an alleged mistake of law or fact, this does not
mean that the arbitrator acted outside the scope of his authority. See Barton v. Fashion
Glass & Mirror, Ltd., 321 S.W.3d 641, 647 (Tex. App.Houston [14th Dist.] 2010, no
pet.); see also Framing v. BBL Builders, No. 05-15-01430-CV, 2016 WL 3346041, at *4
(Tex. App.Dallas 2016, pet. filed) (adopting the holding in Barton with regard to
situations where an arbitrator exceeds his authority). Therefore, we conclude that the
City failed to meet its burden to vacate the arbitration award under section
In its briefing, the City argues that if this Court were to find that the arbitration award
was proper, then the damages must be reduced pursuant to section 271.153(a)(1) of the
Section 171.091 of the civil practice and remedies code contains a provision for
modifying an award and specifies the grounds upon which a modification may be ordered.
See TEX. CIV. PRAC. & REM. CODE ANN. 171.091 (West, Westlaw through Ch. 49, 2017
R.S.). The City did not file a motion to modify at the trial court, and therefore, such a
request is not properly before this Court for our review. See TEX. R. APP. P. 33.1(a)(1).
4. Summary
Having concluded that the City failed to meet its burden to vacate the arbitration
12
III. CONCLUSION
We reverse the trial courts orders: (1) granting the Citys motion to vacate the
arbitration award; and (2) denying IOCs motion to confirm the arbitration award. We
render judgment: (1) denying the Citys motion to vacate the arbitration award; and (2)
GINA M. BENAVIDES,
Justice
13
FILE COPY
Court of Appeals
COURTHOUSE ANNEX III
NORA L. LONGORIA
100 E. CANO, 5TH FLOOR
LETICIA HINOJOSA
EDINBURG, TEXAS 78539
956-318-2405 (TEL)
CLERK
DORIAN E. RAMIREZ Thirteenth District of Texas 956-318-2403 (FAX)
www.txcourts.gov/13thcoa
Enclosed please find the opinion and judgment issued by the Court on this date.
Enc.
cc: 332nd District Court/Hidalgo County (DELIVERED VIA E-MAIL)
Hon. Laura Hinojosa, District Clerk (DELIVERED VIA E-MAIL)
Hon. Missy Medary, Presiding Judge, Fifth Administrative Region (DELIVERED
VIA E-MAIL)
THE THIRTEENTH COURT OF APPEALS
13-16-00117-CV
JUDGMENT
appeal, concludes the judgment of the trial court should be reversed and rendered. The
Court orders the judgment of the trial court REVERSED and RENDERS judgment that
the City's motion to vacate the arbitration award is denied and IOC's motion to confirm
the arbitration award is granted. Costs of the appeal are adjudged against appellee.
Court of Appeals
COURTHOUSE ANNEX III
NORA L. LONGORIA
100 E. CANO, 5TH FLOOR
LETICIA HINOJOSA
EDINBURG, TEXAS 78539
956-318-2405 (TEL)
CLERK
DORIAN E. RAMIREZ Thirteenth District of Texas 956-318-2403 (FAX)
www.txcourts.gov/13thcoa
Appellees motion for rehearing in the above cause was this day DENIED by this
Court.