ALBAWANICO.

16C22C
Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no. RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng. Oussama Souki
Consultant name AECOM Data Date 1-Nov-17
To the Engineer Report no. 588
School Name Sowaidi Complex School Code C26
Temperature 45C - 20C Site Hand-Over Day 17-Dec-15
Weather Humidity

Contractor's Manpower (including Subcontractors)* Plant/Equipment*


Status(Idle
Staff No. Direct Labor No Type Qty. Location orRepair)

Projt. MGR. 1 Supervisor/ Forem 1 Excavator/Poclain/Excavator 0


Engr. MGR. 1 Precast Man 5 Shovel/Loader/Grader 0
Contract MGR. 1 Eq. Operator 1 BOBCAT 0
Precast Manager 1 Carpenter 5 DumpTruck 0
Const. Manager 1 Welder 0 Roller/Compactor 0
Project Control Team 1 Steelfixer 2 PortableGenerator 1
QA/QC 1 MEP 20 MobileCrane 0
Tech. Support 1 Mason 4 TowerCrane 0
Purch & Procurement 1 Painter Labor 8 Pickup 0
Set. Manager 1 Plastering man 8 WaterTanker 0
Site Engineer 1 labor 47 WeldingMachine 1
General Contractor Safety/ HSE 1 ForkLift 0
Timekeeper 1 JCB 0
Electro Mechanical Engrs 1 WaterPump 0
Survayor Assistant 2 Bulldozer 0
Guard 3 LevellingMachine 0
Totalstation 0
Container 0
WaterTank 0
Portacabin 0
TemporaryGenset 0

SubTotal/Main 19 101 2
0
Subcontractors
Sub Total/Subcon 0 0 0

Grand Total 19 101 2


Activities and Tasks*
COMPLETEDACTIVITIES ONGOINGACTIVITIES
Percentage Finish
TypeofWork BuildingName StartDate FinishDate TypeofWork BuildingName Activityname StartDate
Complete Date
Excavation MainBuilding(A)GF 21Jan16 6Feb16 WaterProofing Canteen(A) MozaikoTiles 30.00% 28Oct17
MainBuilding(B)GF 5Mar16 17Mar16 Precast BoundaryWall(A) PrecastConcretPanelsforBoundaryWall 95.00% 4May17
Canteen(B) 19Nov16 22Nov16 BoundaryWall(B) PrecastConcretPanelsforBoundaryWall 95.00% 8Jun17
GuardHouse(A) 28Aug16 30Aug16 Mechanical MainBuilding(A)GF PlumbingFixtures 55.00% 11Jul17
GuardHouse(B) 14Nov16 19Nov16 AirDistributionSystem&Testing 98.00% 21Jun17
GateWork(A) 2Dec16 2Dec16 Diffusers&Grills 92.00% 11Jun17
GateWork(B) 20May17 22May17 SplitUnits 82.00% 10Jul17
Sitelayout(A) 17Apr16 24Apr16 MainBuilding(A)FF PlumbingFixtures 60.00% 3Aug17
WaterTank(A) 28Aug16 30Aug16 AirDistributionSystem&Testing 98.00% 21Jun17
BoundaryWall(A) 2Jun16 1Jan17 Diffusers&Grills 88.00% 28May17
Sitelayout(B) 17Apr16 24Apr16 SplitUnits 82.00% 10Jul17
WaterTank(B) 14Nov16 19Nov16 MainBuilding(A)SF PlumbingFixtures 50.00% 3Aug17
BoundaryWall(B) 11Jun16 1Jan17 AirDistributionSystem&Testing 98.00% 22May17
SubStructure MainBuilding(A)GF 11Feb16 30May16 Diffusers&Grills 87.00% 6Jul17
MainBuilding(B)GF 28Apr16 26Jul16 SplitUnits 85.00% 11Jul17
Canteen(A) 25Dec16 1Aug17 MainBuilding(A)RF ElevatedWaterTanks&Testing 70.00% 11Jun17
ElectricRoom(A) 1Jan17 20Feb17 BoosterWaterPumps&Testing 50.00% 12Jul17
ElectricRoom(B) 26Dec16 21Feb17 PipeFitting 60.00% 10Jul17
Canteen(B) 1Dec16 14Feb17 MainBuilding(B)GF HVACDuct 98.00% 24Jun17
GuardHouse(A) 25Dec16 1Aug17 AirDistributionSystem 98.00% 3Jul17
GuardHouse(B) 1Dec16 14Feb17 Diffusers&Grills 90.00% 4Jul17
GateWork(A) 26Dec16 21Feb17 SplitUnits 80.00% 12Jul17
GateWork(B) 4Jun17 9Aug17 PlumbingFixtures 23.00% 3Aug17
WaterTank(A) 4Dec16 2Apr17 MainBuilding(B)FF Diffusers&Grills 85.00% 4Jul17
BoundaryWall(A) 4Sep16 1Aug17 SplitUnits 78.00% 23Jul17
WaterTank(B) 4Dec16 2Apr17 PlumbingFixtures 23.00% 12Aug17
BoundaryWall(B) 6Jan16 1Aug17 HVACDuct 98.00% 24Jun17
Backfilling Canteen(A) 8Jul17 2Aug17 AirDistributionSystem 98.00% 3Jul17
ElectricRoom(A) 23Jan17 25Feb17 MainBuilding(B)SF PlumbingFixtures 23.00% 12Aug17
ElectricRoom(B) 23Jan17 25Feb17 HVACDuct 98.00% 25Jun17
Canteen(B) 4Feb17 15May17 AirDistributionSystem 98.00% 20Jun17
GuardHouse(A) 11Jul17 9Aug17 Diffusers&Grills 65.00% 12Aug17
GuardHouse(B) 23Jan17 15May17 SplitUnits 85.00% 22Jul17
GateWork(A) 23Jan17 4Mar17 MainBuilding(B)RF PipeFitting 75.00% 9Jul17
GateWork(B) 18Jul17 12Aug17 ElevatedWaterTanks&Testing 57.00% 12Aug17
Sitelayout(A) 19Apr16 26Apr16 BoosterWaterPumps&Testing 70.00% 5Jul17
BoundaryWall(A) 6Jun17 20Jul17 Canteen(A) FloorDrain 90.00% 12Aug17
Sitelayout(B) 19Apr16 26Apr16 RoofDrain 82.00% 18Jul17
BoundaryWall(B) 4Jul17 20Jul17 ElevatedWaterHeaters 81.00% 3Aug17
SlabOnGrade MainBuilding(A)GF 28May16 5Jun16 PlumbingFixtures 42.00% 12Aug17
MainBuilding(B)GF 6Aug16 13Dec16 FireExtinguisher 90.00% 12Aug17
Canteen(A) 17Jul17 9Aug17 SplitUnit 55.00% 12Aug17
ElectricRoom(A) 3Mar17 9Mar17 VentilationFans 60.00% 3Aug17
ElectricRoom(B) 3Mar17 9Mar17 Canteen(B) SplitUnit 65.00% 12Aug17
Canteen(B) 15Jul17 16Jul17 FloorDrain 95.00% 12Aug17
GuardHouse(A) 27Jul17 9Aug17 RoofDrain 85.00% 19Jul17
GuardHouse(B) 15Jul17 16Jul17 ElevatedWaterHeaters 80.00% 12Aug17
GateWork(A) 15Jul17 2Sep17 PlumbingFixtures 33.00% 12Aug17
GateWork(B) 6Aug17 23Aug17 FireExtinguisher 90.00% 12Aug17
WaterProofing MainBuilding(A)GF 22Mar16 13Jul16 GuardHouse(A) PlumbingFixtures 25.00% 12Aug17