Calculate Price For Production One Cubic Meter Water

Project name
Location

Plant Water Production per day 34,000 m/d


Power Consumption Caleculator Cost For One Cubic Meter
Consuming (KWH) 2600 KWH
Price (KWH) 0.32 SAR

EXPENSES FOR PLANT COST PER EXPENSES IN HALALA


Remarks
M ITEMS COST NO. YEARS YEAR M ITEM COST
1 Capital Cost 80,000,000 25 3,200,000 1 Capital Cost 25.79
2 Operation And Maintenance 20,000,000 3 6,666,667 2 Operation And Maintenance 53.72
3 Chemicals 7,000,000 3 2,333,333 3 Chemicals 18.80
4 Power Consuption 7,288,320 4 Power Consuption 58.73
5 Transportation and Distribution 5 Transportation and Distribution 0.00
6 6 0 0.00
7 7 0 0.00
8 8 0 0.00
9 9 0 0.00
10 Indirect Cost ( %) 2 389,766 10 Indirect Cost ( %) 3.14

Total Cost per year in Operation 19,878,086 Total Cost per Cubic Meter 160.18 Halala

160.18 Halala
Fill yellow boxes only

* Cost depend on raw water Quality and chemical Dosing quantity, Type and price and treatment processes.
* Indirect cost can be put from 2- 10 % from Total cost.
* Price for KWH electrical consumption should be accurate. Chemist
* Diesel Consumption included in operation Maintenance when item work by diesel Engine no electerica; power. Tamer Hassan Mohammed
* Operation and Maintenance include Man power, spare parts and Development. 966549725841