You are on page 1of 24

5

CHAPTER
THE AIRSIDE
SYSTEM

The Airside
5System
5.1

THE AIRSIDE SYSTEM


Chapter 5

5 . 1 I N T RO DUC T IO N Canada. These regulations and system at Toronto Pearson that


standards are designed to ensure will offer a significant increase in
The airside and associated airspace
the safe operation of aircraft, but the overall airside capacity.
system is of paramount impor-
also place capacity limitations on
tance in guiding the long-term Significant expansion of the air-
an airports airside infrastructure.
development of Toronto Pearson side infrastructure beyond the
In addition, the Airport Zoning
International Airport. The ulti- plans discussed in this Master
Regulations associated with the
mate capacity of the Airport will Plan, including the construction
airside infrastructure restrict the
largely be defined by the capacity of any additional runways, is not
ability of the GTAA to develop
of the airside system that is already presently deemed possible due to
certain lands as will be described
in a relatively advanced state of the lack of available land and
in Chapter 14.
maturity. The development of the environmental impact constraints.
The operation of aircraft pro-
other major airport sub-systems
duces a number of environmen-
including passenger terminals,
tal impacts, including noise, air 5.2 EXISTING AIRSIDE
cargo facilities, groundside access
emissions and deicing/anti-icing SYSTEM
and various support functions will
fluid run-off. Efforts to mitigate
be undertaken in accordance with The primary components of the
these impacts have significantly
the airside infrastructure, to airside system are runways, naviga-
influenced the design and opera-
achieve a balanced system. tional aids, taxiways, aprons, air-
tional use of the current airside
side roads and deicing facilities.
The airside system is instrumental system as well as future expan-
These elements are described in
in defining the overall capacity of sion plans. A consequence of
Sections 5.2.1 through 5.2.6 and
the Airport for the following key environmental impact mitigation
are shown in Figure 5-1.
reasons: measures is often a reduction
Given the large land areas in the potential throughput
required for runways and their capability of the airside system.
associated taxiways, operational
In the early 1990s, an environ-
areas and navigational aids, a
mental assessment was carried out
finite number of runways can be
by Transport Canada for the
accommodated within the
addition of three new runways
Airports physical boundary.
at Toronto Pearson. Two of
As the regulator of aviation in
these runways have been
Canada, Transport Canada sets
constructed and commis-
the regulations and standards
sioned. The third new run-
that must be complied with by
way that was approved as
the GTAA as the airport opera-
part of this process repre-
tor and by Nav Canada as the air
sents the final remaining
navigation service provider in
element of the airside

Chapter 5 > T H E A I R S I D E S Y S T E M
5.2

Chapter 5 > T H E A I R S I D E S Y S T E M
5.3

also provided in Table 5-1. All


TABLE 5-1 RU N W AY L E N G T H S
runways at Toronto Pearson have a
Landing Distance
Runway Length Available width of 60 metres (200 feet).
Runway Runway Direction of
Orientation Name Metres Feet Operation Metres Feet
East/west 05-23 3,389 11,120 05 3,348 10,985 5.2.2 Navigational Aids
23 3,242 10,635
To support the Airports all-
06L-24R 2,956 9,697 06L 2,956 9,697
weather capability, Toronto Pearson
24R 2,896 9,500
is equipped with electronic naviga-
06R-24L 2,743 9,000 06R 2,743 9,000
tional and visual approach aids to
24L 2,743 9,000
North/south 15L-33R 3,368 11,050 15L 3,368 11,050 provide both precision and non-
33R 3,368 11,050 precision approaches to all
15R-33L 2,770 9,088 15R 2,591 8,500 runways. The existing navigational
33L 2,591 8,500 and communications equipment
at Toronto Pearson is listed below.
5.2.1 Runways of 05 and 23 are applied to pro- The GTAA makes land available
vide a unique runway name. for the on-site navigational and
The present runway system at
Toronto Pearson has five runways, In an approximate north/south communications equipment, how-
oriented under two perpendicular orientation, there are two parallel ever, Nav Canada owns, operates
alignments. runways. Runway 15L-33R is and maintains the equipment.
situated towards the easterly side of An air traffic control tower
In an approximate east/west orien- located in the Infield, from
the Airport, while Runway 15R-33L
tation, Runways 06L-24R and which aircraft on the runways
is located on the west side of the
06R-24L are closely spaced parallel and taxiways and in the airspace
airport site.
runways located on the south side in the immediate vicinity of the
of the Airport. Consistent with Table 5-1 provides the lengths of Airport are controlled. The
international practice, the runways all five runways. While the full tower offers controllers an eye-
are named based on their magnetic length of each runway is available level elevation of 61.9 metres
bearings. For example, the 06-24 for use by departing aircraft, some above ground level.
designation refers to magnetic of the runways have displaced Glide path equipment for each
bearings of approximately thresholds for landing aircraft. The runway that provides electronic
60 degrees and 240 degrees at resulting landing distance available vertical guidance to approaching
either end of these runways. When in each direction of operation is aircraft.
parallel runways exist, left and
right designations are added to the
runway names to distinguish
between them. Parallel to these
runways and located at the north
end of the Airport is a third east/
west runway, namely Runway
05-23. Although Runway 05-23
shares the same magnetic bearings
as Runways 06L-24R and 06R-
24L, the next closest designations View of the Airside System from Airport South

Chapter 5 > T H E A I R S I D E S Y S T E M
5.4

Additionally, Runways 06L and 05


are equipped with the appropriate
lighting and navigational aid sys-
tems to accommodate landings
under reduced visibility conditions
known as Category II and
Category IIIa conditions. All run-
ways at Toronto Pearson have cen-
treline lighting except for Runway
15R-33L.

View of the Airside System from Airport North In addition to the site-specific
navigational aids described above,
Localizer equipment for each voice communications from air-
Toronto Pearson is home to the
runway that provides electronic craft and vehicles.
Toronto Area Control Centre
lateral/horizontal guidance to Main and backup transmitter
(ACC), located in the Infield and
approaching aircraft. sites used by ATC staff to trans-
operated by Nav Canada. The
Two Doppler Very High mit voice communications to
ACC is responsible for the control
Frequency Omni-Directional aircraft and vehicles.
of aircraft across most of south-
Range/Distance Measurement Non-directional beacons (NDB)
central Ontario except landing and
Equipment (DVOR/DME) sta- marking the final approach fix
departing aircraft in the immediate
tions, one located near Runway for a number of runways.
vicinity of an airport. Control of
05 and the other near Runway DMEs collocated at either VOR
aircraft arriving at Toronto Pearson
06L; this equipment emits an or glide path sites, which provide
is transferred from the ACC to the
electronic signal that is used by slant range distance to equipped
Toronto Pearson control tower on
departing aircraft for naviga- aircraft in support of instrument
the final approach to the assigned
tional purposes. approaches.
runway. Conversely, control of
A Terminal Surveillance Radar
All of Toronto Pearsons existing aircraft departing from Toronto
(TSR) located near the west side
runways are equipped with the Pearson is transferred from the
of the Airport, just south of
necessary lighting and navigational Toronto Pearson control tower to
Runway 05-23, which is used by
aid systems to facilitate nighttime the ACC shortly after the aircraft
Air Traffic Control (ATC) staff
operations as well as operations in becomes airborne.
to monitor airborne aircraft.
Category I weather conditions.
Two Airport Surface Detection
Equipment (ASDE) radar units
used by air traffic control staff to
monitor aircraft and vehicle traf-
fic on the airport manoeuvering
surface, located on the north and
south ends of the Airport; the
data from the two ASDE units is
mosaiced to provide controllers
a single display of all airport
manoeuvering surfaces.
Main and backup receiver sites
used by ATC staff to receive Runway 05-23 and associated taxiways.

Chapter 5 > T H E A I R S I D E S Y S T E M
5.5

and servicing of all-cargo aircraft;


aprons associated with the airline
hangars for the maintenance of air-
craft; and aprons associated with
the business aviation hangars for
the unloading, loading and
servicing of corporate jets.

The new passenger terminal


apron built in conjunction with
South ASDE Tower
Terminal 1 had centreline lighting
incorporated into the design of
5.2.3 Taxiways incorporated into the design. In
the apron taxilanes to facilitate
addition, a program to replace taxi-
The Airports five runways are aircraft operations during low-
way edge lighting on older taxiways
supported by an extensive system visibility conditions. In addition, a
with preferred centreline lighting
of taxiways, with a total length of program to retrofit low-visibility
is essentially complete. As a result,
some 40 kilometres. The current centreline lighting on older apron
the vast majority of taxiways
taxiway infrastructure has been taxilanes is nearing completion.
at Toronto Pearson now have
developed incrementally over time Aircraft traffic on the passenger
centreline lighting.
in response to increased airside terminal aprons is controlled by
activity and the associated need the GTAA from two apron control
to improve the efficiency of the 5.2.4 Aprons
towers located on Terminal 1 and
airside system. Terminal 3. The control of arriving
A number of apron areas exist on
The taxiway system includes a the airside to accommodate the aircraft is handed over from the
number of high-speed exits on Airports aircraft parking require- Nav Canada control tower to the
each runway to allow landing air- ments. These include aprons asso- applicable GTAA apron control
craft to exit the runways expedi- ciated with the passenger terminals tower when the aircraft leaves the
tiously plus taxiways paralleling for the unloading, loading and taxiway system and enters the ter-
the runways to move aircraft servicing of passenger aircraft; minal apron. Conversely, the con-
between the runways and the aprons associated with the cargo trol of departing aircraft is handed
various passenger, cargo and facilities for the unloading, loading over from the GTAA apron
hangar aprons.

A key element of the taxiway sys-


tem is the provision of dual taxi-
ways around the busy passenger
terminal areas (Taxiways A, B, C
and D). The dual taxiways allow
bi-directional taxiway flows and
independent taxiway routings for
arriving and departing aircraft.

New taxiways constructed in recent


years at Toronto Pearson have had
low-visibility centreline lighting Nav Canada Air Trafc Controllers at Toronto Pearson

Chapter 5 > T H E A I R S I D E S Y S T E M
5.6

business aviation area aprons and


at the Central Deicing Facility
located in the infield area of the
Airport. Operations during
precipitation conditions (snow or
freezing rain) require the applica-
tion of both deicing and anti-icing
fluids and are carried out only at
the Central Deicing Facility. All
deicing operations at Toronto
Pearson employ proven truck-
control tower to the Nav Canada Terminal, catering trucks trans- based technology.
control tower when the aircraft porting meals from the infield As shown in Figure 5-2, the
leaves the apron and enters the flight kitchen to aircraft on the Central Deicing Facility consists of
taxiway system. passenger terminal aprons and six pads and an adjoining support
cargo tugs transporting cargo area. Each pad can accommodate
between aircraft on the passenger the deicing of two narrow-body
5.2.5 Airside Roads
terminal aprons and the infield aircraft in a side-by-side configura-
An extensive system of airside cargo facilities. tion, or a single wide-body aircraft,
roads is available on the airfield to including the capability to accom-
Another unique component of the
provide transportation routes modate Code F sized aircraft such
airside road system is the emer-
between airport facilities for rou- as the new Airbus A380. The fa-
gency infield access road, which is
tine operational and maintenance cility can deice up to 12 narrow-
closed under normal operations,
purposes, and to facilitate rapid body aircraft or six wide-body
but could provide backup ground-
access for fire and rescue service
side access to the infield area in the
vehicles. The main airside roads
unlikely event that public access to
are shown in Figure 5-1, although
the Infield along Britannia Road
many secondary airside roads also
East becomes temporarily unusable.
exist including those on the
aprons and those providing access
to navigational aid sites. 5.2.6 Deicing/Anti-icing
Facilities
A key element of the airside road
system is the tunnel located under Deicing of aircraft prior to depar-
Runway 15L-33R and Taxiways ture to remove any frost, snow or North ASDE Tower
A, B and E. The four-lane tunnel ice contamination from critical
allows for efficient vehicular trans- surfaces, and anti-icing to protect
portation between the passenger the aircraft from further contami-
terminal buildings on the east side nation is required to ensure the
of the Airport and the infield safe operation of aircraft. Frost
facilities, without the need to deicing, which requires the appli-
cross active runways or taxiways cation of relatively low volumes of
at grade. Users include buses deicing fluid, is undertaken on the
transporting passengers between aprons of Terminal 1 and Terminal Surveillance Radar

Terminals 1 and 3 and the Infield Terminal 3, on one of the north

Chapter 5 > T H E A I R S I D E S Y S T E M
5.7

aircraft simultaneously. In addi- operation. Under certain opera- which Central Deicing Facility
tion, each pad provides an equiva- tional circumstances, however, the operations are controlled. The
lent amount of staging area flow is reversed with the deicing operation of the Central Deicing
immediately behind the deicing and staging positions being inter- Facility has been contracted to
positions to expedite the movement changed. The Central Deicing Servisair by the GTAA.
of the next aircraft into deicing Facility support area immediately
The Central Deicing Facility was
position. west of the pads contains new gly-
designed and constructed with an
col storage tanks, underground
Figure 5-2 illustrates an east-to- extensive glycol recovery system to
spent glycol storage tanks, training
west flow of aircraft through the minimize the environmental
facilities, glycol recycling facilities,
Central Deicing Facility, which is impacts of spent glycol runoff.
a deicing vehicle maintenance
the most common direction of
facility and an ice house from

Chapter 5 > T H E A I R S I D E S Y S T E M
5.8

FIGURE 5-3
Capacity Coverage for the Existing Five-Runway System
140

126

120
108

100 1) 2)
East/ West East/West
Aircraft Movements Per Hour

Runways VMC Runways IMC


79% 14%
80 75

60 3)
North/South
Runways
6%
40

30
4)
20 Irregular
Operations
1%
0
79 93 99 100
Percentage of Time

5.2.7 Capacity of the Existing (plotted on the vertical axis) and runways under visual meteorologi-
Airside System the percentage of time each is typ- cal conditions (VMC), when the
ically available (plotted on the weather is such that pilots can
The airside capacity of Toronto
horizontal axis). make visual reference to the
Pearson is determined to a large
ground for navigational purposes.
extent by factors outside the The capacity coverage chart for
control of the GTAA. For example, Toronto Pearson includes four main Runways 06L-24R and 06R-24L
the airside capacities presented in types of runway operations, as des- do not have sufficient separation
this chapter are based upon cur- cribed in the following sections. between them to permit inde-
rent Transport Canada regulations pendent operations. As a result,
East/West Runway Operations
and Nav Canada air navigation arrivals are assigned to one of the
Visual Meteorological Conditions:
technology and practices. Should runways and departures to the
The first type of runway operation
regulatory, technological or proce- other. For both noise mitigation
corresponds to the simultaneous use
dural changes occur in the future, and operational reasons, arrivals
of the Airports three east/west
the airside capacities reflected in are assigned to the outer runway
this Master Plan may need to be
re-examined.

A capacity coverage chart is a tool


commonly used to quantify the
overall capacity of an airports air-
side system. The capacity coverage
chart reflecting the existing five-
runway system at Toronto Pearson
is shown in Figure 5-3. The chart
illustrates the hourly capacities
available at the Airport under dif- Aircraft taxiing to Runway 06L via Taxiway Delta adjacent to Etobicoke Creek
ferent wind and weather situations

Chapter 5 > T H E A I R S I D E S Y S T E M
5.9

(06R-24L) and departures are on the anticipated aircraft eet mix instrument meteorological condi-
assigned to the inner runway at T oronto Pearson and a balanced tions (IMC) that occur when
(06L-24R). Runway 05-23 is demand of arrivals and departures, visibility is such that instrumenta-
sufciently separated from the this type of operation has a capac- tion, rather than visual reference,
southern runway complex to be ity of approximately 126 aircraft is required for navigation. Under
operated independently, serving a movements per hour, including these conditions, larger separa-
mixture of arrivals and departures. 56 operations on Runway 05-23 tions between aircraft are required
and 70 operations on the closely compared to the separations
This type of runway operation is
spaced parallel runways, Runways applied under visual meteorologi-
shown in Figure 5-4. Aircraft
06L -24R and 06R -24L . T his cal conditions.
need to y into the wind when
capacity exceeds current demand
landing and taking off. As a Based on GTAA computer simula-
levels at Toronto Pearson. An
result, the rst diagram applies to tions, the capacity of the three east/
analysis of weather data suggests
a westerly wind situation with west runways decreases to approxi-
that this type of operation tends to
arrivals on Runways 23 and 24L, mately 108 aircraft movements per
be available approximately 79 per
and departures on Runways 23
cent of the time.
and 24R. The second diagram
applies to an easterly wind situa- East/West Runway Operations
tion with arrivals on Runways 05 Instrument Meteorological
and 06R, and departures on Conditions: The second type of
Runways 05 and 06L. operation also corresponds to the
use of the three east/west runways
Through GTAA computer simula-
in the same manner, but under
tions, it was determined that based Aircraft taxiing to departure runway

Chapter 5 > T H E A I R S I D E S Y S T E M
5.10

hour during instrument meteoro- G iven that the purpose of the ca- 15R-33L do not have sufcient
logical conditions, including pacity coverage chart is to quantify separation to permit independent
48 operations on Runway 05-23 the maximum capacity available operations. As a result, arrivals are
and 60 operations on the closely under given wind and weather assigned to one runway and
spaced parallel Runways 06L-24R conditions, it is not necessary to departures to the other. Arrivals,
and 06R-24L. This type of opera- reect these lower capacity congu-which require less runway length
tion tends to occur approximately rations in the chart. As air trafc than departures, are typically
14 per cent of the time. demand grows over time, the fre- assigned to 15R-33L, the shorter
quency of using all three east/west runway, and departures are typi-
Since using the east/west runways
runways simultaneously will cally assigned to 15L-33R, the
offers the highest capacity, these
increase toward the values given inlonger runway. Under this type of
rst two types of operations are
the capacity coverage chart. operation, it is not uncommon for
preferred during peak time peri-
arrivals of heavier aircraft to be
ods. However, since demand does North/South Runway Opera-
off-loaded onto 15L-33R to pro-
not currently require the simulta- tions: The third type of operation
vide a longer landing distance.
neous use of all three east/west reected in the capacity coverage
runways on a regular basis, air chart pertains to the use of the The resulting north/south runway
trafc control sometimes utilizes north/south runways when strong operation is shown in Figure 5-5.
only two of the east/west run- cross-wind conditions preclude T he rst diagram shows the opera-
ways, resulting in a lower capacity the use of the east/west runways. tions that would occur under
than presented in the capacity Similar to Runways 06L-24R and strong north wind conditions with
coverage chart. 06R-24L, Runways 15L-33R and 33L being used as the primary

Chapter 5 > T H E A I R S I D E S Y S T E M
5.11

Poor visibility conditions, that


limit operations to the runways
and to aircraft with appropriate
navigational equipment for such
conditions.
Other ad hoc circumstances that
require the temporary closure of
airside infrastructure, such as
during emergency situations.

Based on an analysis of historical


Terminal Apron Areas and Dual Taxiway System aircraft throughput data associated
with irregular operations, the aver-
arrival runway, and 33R being runway configuration, but rather
age throughput achieved during
used for departures and some could involve the use of any run-
these types of events is approxi-
possible off-loading of arrivals way(s) depending on operational
mately 30 movements per hour
from 33L. The second diagram circumstances.
and these conditions tend to occur
shows the operations that would
There are four primary types of approximately one per cent of
occur under strong south wind
events that comprise irregular the time.
conditions with 15R being used as
operations:
the primary arrival runway, and Average Hourly Capacity: Using
Snowstorms, that require the
15L being used for departures and the hourly capacity and frequency
periodic closure of runways and
some possible off-loading of information from each of the four
taxiways for snow removal and
arrivals from 15R. types of operations in the capacity
the need to deice/anti-ice aircraft
coverage chart, Toronto Pearsons
Through an analysis of historical prior to departure.
average hourly airside capacity can
aircraft movement data, the Thunderstorms, that result in an
be calculated as follows:
capacity of the north/south runways inability to load, unload or
(79% x 126) + (14% x 108) +
was found to be 75 movements per service aircraft on the apron due
(6% x 75) + (1% x 30) = 119
hour while the frequency of use to unsafe working conditions.
aircraft movements per hour
tends to be approximately five per
cent of the time in the 33 direc- TABLE 5-2 MAXIMUM AND PRACTICAL ANNUAL CAPACITIES
tion and approximately one per FOR THE EXISTING FIVE-RUNWAY SYSTEM
cent of the time in the 15 direc- Average Planning
tion for a total of approximately Number Typical Hourly Day
Hour Group Time Period(s) of Hours Demand Capacity Capacity
six per cent of the time.
Peak 6:30 a.m. 9:29 a.m. 10 x 1.00 x 119 = 1,190
Irregular Operations: The final 2:30 p.m. 9:29 p.m.
type of operation shown in the Off-Peak 9:30 a.m. 2:29 p.m. 5 x 0.80 x 119 = 476
capacity coverage chart is termed Transitional 9:30 p.m. 12:29 a.m. 3 x 0.55 x 119 = 196
irregular operations, which Night 12:30 a.m. 6:29 a.m. 6 Capacity dened by nighttime
operations budget 55
includes operational conditions
Planning Day Capacity 1,917
that typically result in an airside x 320
throughput significantly below the Maximum Annual Capacity 610,000
other three more regular types (Rounded) x 85%
of operations. Irregular operations Practical Annual Capacity 520,000
(Rounded)
do not relate to any specific

Chapter 5 > T H E A I R S I D E S Y S T E M
5.12

FIGURE 5-6
Aircraft Movements and Five-Runway Capacity
900
800
Aircraft Movements (000s)

700
600
Five-Runway Capacity Range
500
400
300
Historical Forecasted Demand
200
100
0
1990 1995 2000 2005 2010 2015 2020 2025 2030

Planning Day Capacity: Since the The sum of the resulting calcula- practical annual capacity offering a
demand for air travel is not con- tions for each of the four groups better level of service to airport
stant over the 24-hour day, it of hours provides the Airports air- users. The practical annual airside
would not be reasonable to multi- side capacity on a planning day, capacity for the existing five-
ply this average hourly capacity by which reflects a busy summer runway system is approximately
24 to obtain a daily capacity of the weekday. 520,000 movements.
airside system. Instead, as shown
Annual Capacity: Since the The maximum and practical
in Table 5-2, the day has been
demand for air travel is typically capacities can be used to create a
divided into four groups, namely
lower on weekends than on week- range of annual airside system
peak hours, off-peak hours, transi-
days, and lower in the fall, winter capacity with the maximum
tional hours (transitioning into the
and spring seasons than in the capacity value representing the
night period), and night hours.
summer, the multiplication of the upper limit of the range and the
During the peak hours, it is planning day capacity by 365 days practical capacity value represent-
assumed that the Airport could per year would yield an unrealisti- ing the lower limit of the range.
operate at the maximum capacity cally high annual airside system This annual airside system capac-
that wind and weather conditions capacity. Instead, analysis of week- ity range for the Airports existing
allow, as reflected in the average day versus weekend and seasonal five-runway system is depicted by
hourly capacity of 119 aircraft traffic data at Toronto Pearson sug- the horizontal band in Figure 5-6.
movements per hour. However, gests that a planning day to annual
during the off-peak and transi- factor of 320 is more appropriate,
5.2.8 Demand/Capacity
tional hours, a demand factor is generating a maximum annual air-
Assessment
used to reduce the expected side capacity of 610,000 aircraft
hourly throughput in recognition movements. Historical annual aircraft move-
of the lower demand levels that ment levels at Toronto Pearson up
Although the maximum annual
typically exist during those por-
capacity calculated above is an
tions of the day relative to peak
attainable level of throughput, sig-
period demand. The capacity of
nificant levels of congestion and
the nighttime hours has been set
delay would occur in the peak
in accordance with the annual
periods to achieve that traffic vol-
nighttime operations budget
ume. For this reason, the attain-
arrangement between the GTAA
ment of approximately 85 per cent
and Transport Canada, as
of the maximum annual capacity Terminal 1 Apron Control Tower
explained in Chapter 13.
is considered to be the Airports

Chapter 5 > T H E A I R S I D E S Y S T E M
5.13

to 2006 are plotted in Figure 5-6 5.3 FUTURE AIRSIDE


in the vertical bars. Aircraft move- DEVELOPMENT
ment levels at the Airport have
typically included periods of strong
5.3.1 Future Runway 05R-23L
growth followed by weaker periods An environmental assessment was
of declining aircraft movements, conducted in 1991-1992 for the
resulting in an overall upward addition of three new runways and
trend. A general description of Central Deicing Facility supporting taxiways and naviga-
this historical pattern over the past tional aids at Toronto Pearson, in
More recently, Toronto Pearson
two-and-a-half decades and some order to meet forecast demand.
has experienced yet another
of the reasons underlying the The environmental assessment
growth period in aircraft move-
fluctuations are provided below. encompassed the construction of
ments. In 2006, activity
the Airports two newest runways,
Following strong growth in the increased to 418,000 aircraft
namely Runway 15R-33L com-
1980s in which the number of movements, a growth of approxi-
pleted in 1997 to alleviate a
aircraft movements increased mately 12 per cent over the past
capacity shortfall in the north/
41 per cent, a slowdown in the three years.
south direction of operation, and
economy in the early 1990s
Transport Canadas forecast for Runway 06R-24L completed in
resulted in a decline in activity
aircraft movements at Toronto 2002 to increase the capacity of
to 305,000 in 1993, a decrease
Pearson from 2007 to the year the Airport in the primary (east/
of approximately 13 per cent
2025 is also shown in Figure 5-6 west) direction of operation.
over three years.
in the vertical bars.
After this decline, Toronto The third runway covered by the
Pearson experienced another sig- Based on the Transport Canada environmental assessment is
nificant growth of approximately aircraft movement forecasts, the another east/west runway, to be
39 per cent over the span of six practical annual capacity of the designated 05R-23L. Runway
years, in which the number of five-runway system of 520,000 air- 05R-23L would be located parallel
aircraft movements peaked in craft movements could be reached to and 408 metres south of exist-
1999, at 425,000 movements. in approximately 2013, while the ing Runway 05-23, as shown in
The next decline in aircraft maximum annual capacity of Figure 5-7. Existing Runway 05-23
movements was the result of 610,000 aircraft movements could would be renamed 05L-23R prior
several events including the be reached in approximately 2019. to the commissioning of planned
merger of Air Canada and Therefore, airside congestion Runway 05R-23L. Planned
Canadian Airlines, which could begin to develop in the Runway 05R-23L would be the
removed excess capacity from 2013-2019 time period, and final runway that could be accom-
the domestic market, as well as depending upon the level of delay modated on the airport site.
the terrorist attacks on airport users are willing to accept,
Since environmental approval has
September 11, 2001 and the additional airside infrastructure
already been obtained for planned
SARS outbreak, which both could be required sometime after
Runway 05R-23L, it could be
temporarily decreased the 2013. Ongoing monitoring of
constructed at the discretion of
demand for air travel. This traffic demand and airside conges-
the GTAA when warranted by
decline continued until 2003 tion will be required to determine
demand. A lead time of approxi-
when the number of aircraft the need for, and timing of, new
mately three to four years would
movements dropped to 372,000, airside facilities.
be required to design, construct
a decrease of 13 per cent over
and commission the new runway.
four years.

Chapter 5 > T H E A I R S I D E S Y S T E M
5.14

Chapter 5 > T H E A I R S I D E S Y S T E M
5.15

Two parcels of land on the west anticipated that the new creek beddepartures while existing Runway
side of the airport property were would be designed to meander, 23R (currently designated 23)
acquired by the GTAA in order to to enhance the quality of the would accommodate arrivals.
protect for the construction and aquatic habitat. O ccasionally, departing aircraft
operation of Runway 05R-23L requiring more takeofflength than
Similar to the existing pair of
and associated navigational aids. is available on Runway 23L could
closely spaced parallel runways at
be off-loaded onto Runway 23R
Construction of Runway 05R-23L the southern end of the aireld
between arriving aircraft. In the 05
would require the removal of the (06L-24R and 06R-24L), existing
direction of operation, planned
existing TSR radar facility. Nav Runway 05-23 and planned
Runway 05R would accommodate
Canada would identify replace- Runway 05R-23L would operate
arrivals while existing Runway 05L
ment requirements at that time, as a dependent parallel complex
(currently designated 05) would
including an investigation of with arrivals on one runway and
accommodate departures. O pera-
potential replacement technolo- departures on the other. However,
tions on Runways 06L-24R and
gies. Figure 5-7 identies an alter- due to the location of the cargo
06R -24L would remain unchanged
native TSR site west of Runway terminal facilities near the eastern
from the current situation.
15R-33L in the Etobicoke Creek end of planned Runway 05R-23L,
Valley that has been selected by the new runway would be utilized Supporting taxiway facilities
Nav Canada, and is being reserved only for takeoffs to the west and required for planned Runway
by the GTAA for this purpose. arrivals from the west. 05R-23L would not be as exten-
sive as for the other runways at the
A section of Etobicoke Creek will As shown in Figure 5-8, in the
Airport due to the operating
also require relocation to accom- 23 direction of operation, new
restrictions described above.
modate Runway 05R-23L. It is Runway 23L would accommodate

Chapter 5 > T H E A I R S I D E S Y S T E M
5.16

Existing runway exit C1 on


Runway 06L could be realigned
to convert it into a high-speed
runway exit. This improvement
would reduce the average runway
occupancy time for aircraft land-
ing on Runway 06L and enhance
safety by simplifying the taxiway
network.
The linking of Taxiways F and M
to provide a full-length parallel
Deicing Operations
taxiway for Runway 15R-33L
Taxiway construction would associated noise impacts on the could be provided to improve
include the completion of Taxi- west end of the runway would be airside access to the infield facili-
way N and high speed exits at the minimized. Given the operational ties and to minimize the need to
eastern end of the runway to be restrictions imposed on planned use Runway 15R-33L as a taxi-
used by aircraft landing on Runway 05R-23L by the obstruc- way. In conjunction with the
Runway 05R, and the construc- tion on the eastern end of the linking of Taxiways F and M,
tion of a taxiway connection to runway, the flight paths east of two new high-speed exits could
Taxiway H near the western end of the Airport would not change. be considered for Runway 15R-
the runway to be used to exit the 33L to decrease the distance that
runway in the event of an aborted smaller arriving aircraft would
5.3.2 Other Airside Development
departure on Runway 23L. have to taxi on the runway to
The addition of planned Runway reach an exit, thereby decreasing
The operating restrictions on the
05R-23L and associated facilities the average runway occupancy
use of the planned runway would
would be the final major element time.
also limit the requirements for
of the Toronto Pearson airside sys- An area at the north end of the
navigational aids to a localizer
tem. However, where warranted, infield area has been reserved for
and glide path for arrivals on
consideration will be given to a possible second deicing facility
Runway 05R.
implementing other airside to supplement the existing
Planned Runway 05R-23L would enhancements to improve the effi- Central Deicing Facility, if war-
have a landing distance of ciency of airport operations, ranted in the future. A deicing
2,718 metres (8,919 feet) available which in turn reduces fuel burn facility with three deicing pads
in the 05 direction. In the 23 and air emissions, or to meet any and associated support facilities,
direction, a 300 metre (984 feet) future regulatory changes. Given roughly half the size of the exist-
stopway and clearway would be the advanced state of maturity of ing Central Deicing Facility,
provided at the western end of the the airport site, other potential could be accommodated at this
runway in order to increase the airfield enhancements are likely to site. Continued monitoring of
takeoff distance available to be relatively modest in nature in throughput at the existing
3,018 metres (9,903 feet). comparison to the addition of Central Deicing Facility will be
Runway 05R-23L. A number of required as traffic demand
As a result of the close proximity
possible airfield enhancements are increases to determine if a sec-
of planned Runway 05R-23L to
described below, and conceptually ond deicing facility is required.
existing Runway 05-23, potential
illustrated in Figure 5-7.
changes to flight paths and

Chapter 5 > T H E A I R S I D E S Y S T E M
5.17

be widened and shoulders added the aircraft without restrictions.


to runways to accommodate However, when the A380 taxis
future Airbus A380 operations, between Runway 05-23 and the
as is discussed further in terminals, operations on adjacent
Section 5.3.3. taxiways would be restricted to spe-
cific aircraft sizes. Although the
In all cases, further assessment will
turning radius of the A380 is
be required to determine the need
Air Trafc Control Tower and Ineld tunnel entrance smaller than the Airbus A340-600,
(background)
for and the timing of additional
which already operates at Toronto
airside infrastructure.
Taxiway Echo could be extended Pearson, a limited number of
towards the north to Taxiway taxiway fillets could be widened at
Juliet to facilitate the movement 5.3.3 Airbus A380 Readiness key taxiway intersections for ease
of aircraft from the Central of manoeuverability.
The worlds largest commercial
Deicing Facility to Runway 15L.
passenger aircraft, the new Airbus As will be discussed further in
A high-speed exit could be con-
A380 entered service in October Chapter 6, Terminal 1 and its asso-
sidered on the west side of
2007. Although no carrier has ciated apron has been designed to
Runway 33R for arriving aircraft
stated an intention to operate this support A380 operations on two
destined for the infield area to
aircraft at Toronto Pearson yet, the of the Hammerhead F gates. One
decrease their average runway
GTAA considered the operational of the gates has been fully equip-
occupancy time.
requirements of the A380 in its ped to handle the A380, while the
The airside road system around
airport redevelopment plans to second gate would require some
the circumference of the airfield
ensure that the Airport will have modifications prior to accommo-
could be completed by connect-
the ability to accommodate the dating the A380. Terminal 3 and
ing the airside road at the west
aircraft when required without its associated apron could also
end of Runways 06L and 06R to
major reconstruction. However, a handle the A380, if required, on
the airside road adjacent to the
few modifications to Toronto two of the gates on Pier C, with
remote receiver. Such a connec-
Pearsons infrastructure would be some modifications.
tion would allow airport staff to
considered as outlined below.
travel between the north and
south airside areas on the west All runways at Toronto Pearson 5.3.4 Capacity of the Ultimate
side of the Airport without the are wide enough to accommodate Airside System
need to exit and re-enter the the A380. In addition, paved
Figure 5-9 provides the capacity
secure airside area. shoulders that are required for the
coverage chart pertaining to the
A380 have already been added to
Other possible airfield enhance- ultimate six-runway system. The
Runway 05-23, and are currently
ments that are not illustrated in four types of runway operations
being added to Runway 06L-24R
Figure 5-7 include: that are currently used under the
as part of a rehabilitation of the
Taxiway access to the recently existing five-runway system will
runway. Paved shoulders could be
acquired Boeing lands may be also be applicable to the future
added to other runways in the
required, depending on the type six-runway layout, and the fre-
future as required.
of future airport development quencies of use would also remain
undertaken on that site, as dis- Runway 05-23 has been identified unchanged. Therefore, the only
cussed further in Chapter 14. as the preferred runway for A380 changes required to the capacity
A number of taxiway fillets at operations as adequate lateral sepa- coverage chart to reflect the addi-
key taxiway intersections could ration exists between it and parallel tion of the sixth runway relate to
Taxiways H and J to accommodate

Chapter 5 > T H E A I R S I D E S Y S T E M
5.18

FIGURE 5-9
Capacity Coverage for the Six-Runway System
140
140

120
120

1) 2)
100 East/ West East/West
Runways VMC Runways IMC
79% 14%
Aircraft Movements Per Hour

80 75

60 3)
North/South
Runways
6%
40

30
4)
20 Irregular
Operations
1%
0
79 93 99 100
Percentage of Time

the hourly capacities of the first operation of the four east/west hourly capacity of 132 can be
two types of operations involving runways, Toronto Pearsons average translated into a maximum achiev-
the use of the east/west runways, hourly airside capacity for the six- able annual capacity of 680,000
which have been obtained through runway system would be calcu- and a practical annual capacity of
computer simulations. lated as follows: 580,000 as shown in Table 5-3.
(79% x 140) + (14% x 120) +
The capacity of the four east/west
(6% x 75) + (1% x 30) = 132
runways under the first type of 5.3.5 Demand/Capacity
aircraft movements per hour
operation, visual meteorological Assessment
conditions, is estimated to be 140 Following the same method as was
The resulting annual capacity
movements per hour. Under the used in Section 5.2.7, this average
range for the six-runway system is
second type of operation, instru-
ment meteorological conditions, TABLE 5-3 MAXIMUM AND PRACTICAL ANNUAL CAPACITIES
the capacity of the four east/west F O R T H E U LT I M AT E S I X- RU N W AY S Y S T E M
runways is estimated to be 120 Average Planning
Number Typical Hourly Day
movements per hour.
Hour Group Time Period(s) of Hours Demand Capacity Capacity
The capacities of the third and Peak 6:30 a.m. 9:29 a.m. 10 x 1.00 x 132 = 1,320
fourth type of operation would be 2:30 p.m. 9:29 p.m.
unchanged from the five-runway Off-Peak 9:30 a.m. 2:29 p.m. 5 x 0.80 x 132 = 528
Transitional 9:30 p.m. 12:29 a.m. 3 x 0.55 x 132 = 218
system because they are affected
Night 12:30 a.m. 6:29 a.m. 6 Capacity dened by nighttime
by the north/south runways and operations budget 62
weather/wind conditions rather Planning Day Capacity 2,128
than the number of east/west x 320
runways. Maximum Annual Capacity 680,000
(Rounded) x 85%
Applying the hourly capacities Practical Annual Capacity 580,000
associated with the simultaneous (Rounded)

Chapter 5 > T H E A I R S I D E S Y S T E M
5.19

F I G U R E 5 -10
Aircraft Movements and Six-Runway Capacity
900
800
Aircraft Movements (000s)

700
Six-Runway Capacity Range
600
500
400
300
Historical Forecasted Demand
200
100
0
1990 1995 2000 2005 2010 2015 2020 2025 2030

illustrated in Figure 5-10. Based aircraft movements thus far in this 90 passengers per aircraft at that
on Transport Canadas current chapter, is converted into an time. As calculated in Table 5-4,
aircraft movement forecasts, the approximate passenger volume for the annual six-runway system
practical capacity of 580,000 air- comparison to terminal and capacity range derived in
craft movements would be groundside development plans. Section 5.3.4 equates to a range
exceeded in approximately 2017 of approximately 46 million to
Based on future traffic projections,
and the maximum capacity of 54 million passengers per year.
it is anticipated that when traffic
680,000 aircraft movements These passenger volumes will be
demand approaches the capacity
would be exceeded in approxi- discussed further within the
of the six-runway system, approxi-
mately 2023. Therefore, airside context of the passenger terminal
mately 88 per cent of aircraft
congestion would begin to develop and groundside development
movements at Toronto Pearson
in the 2017-2023 time period. plans later in this document.
will be passenger aircraft using the
passenger terminals. The remain-
5 . 4 B A L A NC ING AIRSIDE ing 12 per cent of aircraft move- 5.5 OPPORTUNITIES TO
FAC I L I TIE S W IT H ments would be comprised of MAXIMIZE AIRSIDE
PA S S E NG E R T E RMINAL cargo freighter and business avia- CA PAC IT Y
A N D GRO UNDSIDE tion aircraft that do not use the
The airside capacities quantified in
FAC I L I TIE S passenger terminals.
this chapter are dependant upon a
It is important that the airside It is also estimated that given the number of assumptions and vari-
facilities at an airport are planned diverse range of markets served by ables. Given that the results of the
and developed in balance with the Toronto Pearson and the resulting demand/capacity assessment indi-
passenger terminal and groundside mix of aircraft sizes using the cate that Toronto Pearson will
facilities to ensure that the capacity Airport, the passenger aircraft will reach its airside capacity within
of one sub-system is not increased carry an average of approximately the planning horizon of this
to a level that cannot be sustained
by the others. TABLE 5-4 S I X- RU N W AY A I R S I D E CAPAC I T Y I N T E R M S
OF PA SSENGERS
To facilitate further discussion on Proportion Passenger Average Annual
Annual of Passenger Carrying Number of Passenger
this balancing issue later in the
Annual Aircraft Carrying Aircraft Passengers Capacity
document, the Airports ultimate Capacity Movements Aircraft Movements per Aircraft (Millions)
annual airside capacity, which has Practical 580,000 x 88% = 510,400 x 90 = 45.9
been defined only in terms of Maximum 680,000 x 88% = 598,400 x 90 = 53.9

Chapter 5 > T H E A I R S I D E S Y S T E M
5.20

preferred times to use non-peak capacity through the application


slots. Alternatively, in the absence of a planning day to an annual
of a traffic management system, factor of 320. This factor is lower
when traffic demand grows to the than 365 due to the fact that traf-
point of exceeding available capac- fic demand is typically lower on
ity in the peak hours, traffic would weekends than on weekdays and
incur delays and be pushed out lower in the fall, winter and spring
Airbus A380 into the non-peak periods. In seasons than in the summer.
either case, the end result is that
Master Plan, a discussion on Given the relatively inflexible
over time, an increasing number of
potential means of increasing the travel patterns associated with the
passengers would be forced to
airside capacity beyond the levels typical business week and time of
travel at non-preferred times of the
identified is warranted. year vacation planning, it is
day, use alternate airports, alterna-
unlikely that a significant propor-
tive modes of transportation, or
tion of passengers would be willing
5.5.1 Daily Traffic Peak not travel. Regardless of the mar-
to alter their weekly or seasonal
Spreading ket response, the result would
travel patterns on a sustained basis
be a significant economic and
The airside capacity calculations in response to congestion at the
social cost.
assume that the Airport operates Airport. As a result, this is not
at full capacity for a total of ten As an example of the overall poten- considered to be a viable means of
hours at the beginning and end of tial impact on capacity, an increase increasing passenger capacity at
the typical business day. It is also in the traffic demand during the Toronto Pearson.
assumed that the Airport operates off-peak and transitional hours to
at a lower throughput level of 90 per cent and 75 per cent of full
5.5.3 Increased Nighttime
80 per cent and 55 per cent of full capacity respectively, which would
Operations
capacity during the five off-peak represent a very significant travel
hours and three transitional hours pattern shift, would increase the The airside capacity calculations
respectively, in recognition of the annual passenger capacity of the assume that the number of aircraft
natural daily traffic patterns that airside system by approximately operations during the nighttime
are inherent in air travel demand. 3-4 million passengers. While such restricted period (12:30 a.m. to
a shift in traffic would be theoreti- 6:29 a.m.) will increase in propor-
This calculation already implies a
cally possible, and could be imple- tion to the overall increase in
significant degree of peak spread-
mented as a short-term measure in passenger traffic at the Airport,
ing, or traffic leveling during the
the absence of alternative aviation consistent with the Airport
ten peak hours of the day. How-
capacity, it would clearly not be an Authoritys annual nighttime oper-
ever, further spreading of traffic
optimal long-term solution, and, ations budget arrangement with
into the non-peak portions of the
depending on market response, Transport Canada. As a result, the
day would increase the aircraft and
may not be successful. calculations already incorporate a
passenger throughput. A shift in
significant future increase in
the daily traffic profile could be
nighttime traffic. Further increases
proactively achieved through the 5.5.2 Weekly/Seasonal Traffic
in the utilization of available
strict limitation and control of air- Patterns
capacity in the nighttime period
craft slots per hour, thereby forcing
The planning day airside capacity, would increase the overall airport
airlines that are not able to acquire
reflecting a busy summer weekday, capacity.
a sufficient number of slots at
has been converted into an annual

Chapter 5 > T H E A I R S I D E S Y S T E M
5.21

However, the impact of further the aircraft at Toronto Pearson will airport facilities, and the invest-
increases in nighttime operations be passenger carrying aircraft in ment in business aviation facilities
on a number of important issues the long term, with cargo freighter at Toronto Pearson. Therefore,
would need to be considered, and business aviation aircraft com- while modest passenger capacity
including the noise impact on the prising the remaining 12 per cent. increases are possible through the
surrounding communities, the size off-loading of business aviation
An increase in the proportion of
of the Airports noise contours in aircraft, no definitive conclusions
passenger carrying aircraft through
relation to the Airport Operating should be drawn at this time.
the off-loading of business aviation
Area and the impact on airport-
aircraft to other area airports
community relations. In addition,
would translate into a higher air- 5.5.5 Larger Aircraft
changes to the annual nighttime
side passenger capacity. Potential
operations budget arrangement The airside capacity calculations
mechanisms that could be
with Transport Canada would have assumed that the passenger
employed to off-load business
be required. carrying aircraft at Toronto
aviation traffic include pricing
Pearson in the long run will carry
Even if the above issues could be strategies and other demand man-
an average of 90 passengers, repre-
resolved, it is very questionable agement techniques.
senting a modest increase from the
whether significant numbers of
For every 1 per cent increase in current average. This assumes that
passengers would be willing to fly
the proportion of passenger carry- the trend towards smaller regional
during the restricted hours.
ing aircraft, the airside passenger jets over the past 10-15 years will
Although there may be some traffic
capacity would increase by eventually reverse as the Toronto
segments that could be somewhat
approximately 0.5 million passen- Pearson market matures and the
amenable to flying during the
gers. However, it must be noted Airport begins to become capacity
restricted hours, such as vacation
that only the off-loading of busi- constrained. It should also be
charter flights or long-haul flights
ness aviation traffic during the noted that new aircraft types such
that currently have difficulty com-
peak hours would increase the as the Airbus A380 and the
plying with nighttime restrictions
passenger capacity, as the opera- Boeing 787 have already been
at the Airport at the opposite end
tion of business aviation aircraft taken into consideration in the
of the route, it is unlikely that a
during non-peak times when sur- calculations.
large overall increase in passenger
plus capacity exists does not limit
volumes could be achieved on a A further increase in the long-term
passenger aircraft activity.
sustained basis. average number of passengers per
The relatively modest potential aircraft would translate into a
increase in passenger volumes that higher airside passenger capacity.
5.5.4 Off-loading Business
could be achieved through the off- For example, an increase to
Aviation Traffic
loading of business aviation traffic 100 passengers per aircraft would
The airside capacity calculations to other airports would need to be translate into an annual capacity
have assumed that 88 per cent of assessed against a number of other increase of 5-6 million passengers.
considerations when demand However, given the long typical
nears the Airports capacity. These life cycle of aircraft, the average
other considerations would aircraft size at Toronto Pearson in
include the importance of access 2020 will be largely determined by
to Toronto Pearson for the busi- aircraft fleet replacement decisions
ness aviation community, the made by the air carriers many years
availability and cost of alternative earlier. In addition, airlines plan

Chapter 5 > T H E A I R S I D E S Y S T E M
5.22

their aircraft fleet within the con- present and future capacity based the Airport, there is not sufficient
text of their overall route network, on information known at the evidence at this time to suggest
and as a result, the anticipated present time. that it will be both possible and
operating environment at any one practical to implement any of the
specific airport is likely to have a measures on a sustained basis to
5.5.7 Conclusion
limited impact on the overall fleet. significantly increase Toronto
A number of possible means of Pearsons practical capacity.
Therefore, the onset of congestion
increasing the ultimate airside
at Toronto Pearson in the long
capacity of Toronto Pearson have
term is unlikely to trigger a funda- 5 . 6 S U M M A RY
been identified and discussed in
mental change in the overall air-
this section, some of which appear Based on the analysis presented
craft size operating at the Airport.
to have a theoretical potential to in this chapter, the current five-
While capacity gains are possible
increase airside passenger capacity, runway airside system at Toronto
through the operation of larger
perhaps in the 5-10 per cent Pearson can accommodate
aircraft, it must be recognized that
range or more if considered in Transport Canadas forecast air-
the GTAA has little opportunity
combination. craft movement demand into the
to influence this variable.
2013-2019 time period. The exact
The key issue is the extent to
time that additional airside infra-
which the measures would be
5.5.6 Air Navigation Services structure is required will depend
practical to implement at Toronto
on not only future traffic growth
The hourly airside capacities Pearson in the future. While some
rates, but also on the willingness
quantified in this chapter are of the ideas could be effective to
of the aviation community to
based on existing Transport deal with a short-term capacity
accept airside congestion and
Canada regulations and Nav shortfall, it is not clear whether
delays as demand surpasses the
Canada air navigation technolo- they would be appropriate to
practical capacity of the existing
gies and practices. Nav Canada, implement on a sustained basis.
airside system and progresses
the air navigation service provider, Another fundamental considera-
toward its maximum capacity.
is currently beginning a compre- tion is that the GTAA does not
hensive three-year study to have unilateral control over the Plans for the provision of a sixth
examine the present air navigation measures, and in many cases, has and final runway and supporting
system in the Toronto area to only a limited ability to influence taxiway and navigational aid
ensure that their services are meet- the outcome. The successful infrastructure have been developed,
ing the needs of users in the most implementation of any of the including the completion of an
efficient manner. Should the measures would depend on the environmental assessment. The
results of Nav Canadas review actions and responses of a number addition of the sixth runway
lead to the future application of of other important players in the would provide an approximate
new technologies, procedures or aviation industry including the 10-15 per cent increase in capac-
practices that increase the hourly passengers, the airlines, the busi- ity, raising the Airports ultimate
airside throughput potential, the ness aviation community, Nav airside capacity to the 580,000 to
annual airside capacities calculated Canada, Transport Canada and 680,000 annual aircraft move-
in this chapter may need to be the surrounding communities. ments range, which equates to
reassessed. However, the capacities approximately 46-54 million
While some of the measures iden-
presented in this chapter have passengers annually.
tified are likely to warrant further
been reviewed by Nav Canada and
consideration in the future when
accurately reflect the Airports
congestion begins to develop at

Chapter 5 > T H E A I R S I D E S Y S T E M
5.23

A number of other potential air- operations will be required to be able to accommodate the
side improvements that would determine more precise require- demand at the Airport until
enhance the efficiency of airport ments for and timing of these or approximately the 2017-2023
operations have also been identi- other airside infrastructure time period. Beyond that time,
fied and described in this chapter, improvements with sufficient lead other solutions to accommodate
however, they are relatively modest time to design, construct and growth in the regional aircraft
in nature in comparison to the commission the facilities. traffic demand would be required,
addition of the sixth runway. as will be discussed in Chapter 15.
Based on Transport Canadas air-
Ongoing monitoring of airside
craft movement forecasts, the full
six-runway airside system would

Chapter 5 > T H E A I R S I D E S Y S T E M

You might also like