Professional Documents
Culture Documents
Document B
standards
rainscreen
aesthetics
20 Design considerations
wind resistance
thermal performance
colour
Design
considerations
22-23 Rainscreen cladding 32-33 Wind resistance
principles and benefits
34-35 Fire safety, acoustics,
24 Rainscreen and overcladding condensation and ventilation
Design considerations 21
Rainscreen cladding
Principles and benefits
The past
The rainscreen principle is not new, nor is the idea of rainscreen applied
to wall design.
Rainscreen cladding
Todays rainscreen systems offer unique aesthetic and performance
benefits:
22 Design considerations
Insulation Rainwater removal
Insulation of up to 240mm thickness can be accommodated Cladding prevents penetration of most rainwater
using a Marley Eternit framing system
Natural ventilation stack effect evaporates penetrating rain
All types of insulation can be used from rigid PUR to
Residual rainwater drains harmlessly and evacuates at base of system
mineral wool
Pressure equalised system naturally inhibits ingress of driven rain
Insulation positioned against substrate maximises heat retention
and minimises condensation issues
Any interstitial condensation kept to outside of structure Insulation is external, so no thermal breaks required to accommodate
internal structural elements such as floors and beams
Quickly removed via evaporation
Design considerations 23
Rainscreen and overcladding
The aesthetic, remedial and thermal solution Embodied energy for cladding materials
One of the key ways in which rainscreen can benefit existing buildings is The table below shows embodied energy for various cladding materials.
through overcladding. Lower embodied energy will allow the designer to achieve a higher
BREEAM rating.
Apartment and office blocks, retail, healthcare and commercial
establishments may well require both remedial and aesthetic work to
make them suitable for today's environment. Timber
On top of this, the thermal inefficiencies inherent in this legacy building Glass
stock will almost certainly need radically upgrading to meet todays
exacting regulations. Ceramic
panels
Overcladding with rainscreen cladding systems achieves all three key Terracotta
requirements: tiles
Decorative
Remedial fibre cement
Aesthetic Galvanised
steel
Thermal (with insulation) Polyester coated
aluminium
Balconies
Key features for overcladding
Balconies and walkways can be fully enclosed to create buffer
zones. If external wall insulation is not considered then enclosing Restoration of existing facade
the balconies will also reduce the effect of the thermal bridges Extending the life of the building
associated with them.
Improving appearance and image
Vandalism
Those external wall surfaces prone to vandalism and graffiti for Provide thermal insulation and weather-tightness
instance, at ground floor level can be clad with more suitable material
Improve acoustical performance of the building
or one such as Natura incorporating the UV Pro coating offering good
protection against graffiti and subsequent removal. Lower maintenance cost
Maintenance
Natura, Atkinsons Store, Sheffield
Building life
Whilst overcladding will not reinstate structural integrity of a building,
it will, if designed and installed correctly, extend its life by improving
weather resistance.
24 Design considerations
Rainscreen and wall insulation
Mineral wool
(rigid slab)
Glass wool
(felt or soft slab)
Glass wool
(rigid slab)
Foamed glass
insulation
Extruded
polystyrene (XPS)
Expanded
polystyrene (EPS)
GJ/m3 0 5 10 15
Design considerations 25
Aesthetics & colour
Colour in context
In some environments, colour has long been Colour as well as style of architecture is a Alternatively, it may be important to find regional
used to influence or create mood and powerful way of contextualising structures solutions that respect individual locations, by
atmosphere, to change perception of room making them harmonious with or deliberately selecting colours to match the tones of the
shape or size and where appropriate, to distinct from both large and small scale predominant local materials.
express function. environments. This process can be broadly
These kinds of influence can be extended to divided into 3 levels (see below).
the exterior on the larger scales both of locality
and the environment as a whole.
26 Design considerations
Panel fixings
The fixing method chosen can have a The 'visible fixing' systems screw and rivet
fundamental and dramatic effect upon the final fixing may be seen as providing an
appearance of the clad building. appearance somewhere between secret fix
Employing a secret fix method, for example, will and edge retention. The smooth facade of
result in a sheer, smooth facade unobstructed the cladding will be punctuated by the heads of
by fixings. the rivets or screws, although, in practice, these
low profile fixings are virtually unnoticeable.
An edge retention system, on the other hand, Visible fixing screw or rivet Secret fix
focuses the eye upon the panel joints and will Additionally, fixing methods can be combined
give the facade a geometric feel, especially to create interesting design detail.
when a contrasting colour is chosen for the For example, a minimal amount of mechanical
edge framing members. fixing can be combined with structural adhesive
bonding.
The illustrations, right, show a diagrammatic view of the
generic differences in appearance between some typical
fixing systems. Please contact our Technical Advisory Service
for further information.
Edge retention Adhesive fix with square
boss at each corner
Design considerations 27
Recommended
design procedure
Natura, Brunel University, Uxbridge
Reference should also be made to BS 8200 (The following information is provided for
Code of Practice for the design of guidance only. Designers should ensure that
non-loadbearing external vertical enclosures they make all the necessary calculations and
of buildings, also BS 6093 - Code of Practice take into account all aspects of the specific
for the design of joints and jointing in building project design and location.)
construction, and to BS 8000: Part 6:
Further information can also be found in:
Workmanship on Building Sites: Code of
CWCT Standard for systemised building
Practice for slating and tiling of roofs and
envelopes, and NHBC Standards 2008.
claddings.
1. Check
legislation and
planning issues
7. Determine fixing
28 Design considerations
Step 1: Legislation and planning Step 5: Cladding selection
Design considerations 29
Legislation, guidance
& reference
Scottish Technical
Handbooks
The sections referred to above
are contained in the two
The Scottish Building Standards
Scottish technical handbooks,
TECHNICAL HANDBOOK
NON-DOMESTIC one covering domestic
construction, the other
SCOTTISH BUILDING
STANDARDS AGENCY
non-domestic.
The Scottish Building Standards
TECHNICAL HANDBOOK
NON-DOMESTIC
DOMESTIC
SCOTTISH BUILDING
STANDARDS AGENCY
30 Design considerations
Building Regulations
These are mandatory regulations and, in Copies of the complete set of Handbooks that BS 476-6: 1989 Fire tests on building materials
England and Wales, are generated and accompany the Building (Scotland) Regulations and structures Method of Test for fire
approved by the Department for Communities 2004 for Scotland can be downloaded from the propagation for products.
and Local Government (DCLG). SBSA web site (www.sbsa.gov.uk). Follow the
BS476-7: 1997 Fire tests on building materials
links to 'Archive', 'Standards and Guidance'
In Scotland they are generated and approved and structures Method of test to determine
then 'Technical Standards'. They can also be
by the Scottish Executive and in Northern the classification of the surface spread of flame
obtained on a CD-Rom from the Scottish Building
Ireland, by The Office Estates and Building of products.
Standards Agency (SBSA), Denholm House,
Standards Division (OBD).
Almondvale Business Park, Livingston, EH54 6GA BS EN 12467: 2004 fibre cement flat sheets,
They must be complied with for all new-build (Tel 01506 600400, Fax 01506 600401. product specification and test methods.
and a great deal of refurbishment work. Provides information on the technical
They consist of the Building Regulations 2000 British Standards requirements.
(as amended) for England and Wales, the A British Standard is a published document
BS EN 13501-1: 2002 fire classification of
Building (Scotland) Regulations 2004, and the that contains a technical specification or other
construction products and building elements
Building Regulations (Northern Ireland) 2000. precise criteria designed to be used
Classification using test data from reaction to
consistently as a rule, guideline, or definition.
Compliance with these regulations is the fire tests.
They are a summary of best practice and are
responsibility of the building designer, who
created by bringing together the experience and BS 8000-6: Workmanship on building sites.
may be the owner of the building, his appointed
expertise of all interested parties the producers, Code of practice for slating and tiling of roofs
architect, a structural engineer appointed by
sellers, buyers, users and regulators of a and claddings. Applies to the laying and fixing
the owner or his architect or, in the case of
particular material, product, process or service. of claddings and their associated fixings and
small buildings, the actual builder.
accessories. Common Arrangement of Work
Standards are designed for voluntary use and
The increasing complexity of construction and Section (CAWS) classifications H60, H61
do not impose any regulations. However, laws
the codes that govern design has and H65.
and regulations may refer to certain standards
led many building designers to request the
and make compliance with them compulsory. BS 5250: Control of Condensation in Buildings
specialist services of a cladding or building
Describes the causes and effects of surface
envelope designer. The principal British Standards relevant to
and interstitial condensation in buildings and
this document are:
The Approved Documents of the Building gives recommendations for their control.
Regulations (England and Wales), the Technical BS 5534 Gives recommendations for the
Handbooks (domestic and non-domestic) design, materials, application, installation and Health and safety
(Scotland) and the Technical booklets (Northern performance of slates, tiles, shingles and To ensure safe working practices during
Ireland) provide practical guidance for some of shakes. It also covers their associated fittings construction, the designer should consider
the common building situations in respect of the and accessories for use in the construction of relevant safety regulations. These include the
requirements for materials and workmanship. pitched roofs and vertical cladding applications. Construction (Design and Management)
(BS 5534 should be read in conjunction with Regulations and the Health and Safety
Copies of the Approved Documents that
BS 8000-6) Executives approved code of practice for
accompany the Building Regulations 2000
management of health and safety at work.
(as amended) for England and Wales can be BS 5588 Fire precaution in the design,
downloaded from the the Department for construction and use of buildings. Certain advisory bodies such as the National
Communities and Local Government (DCLG) House Building Council (NHBC), Loss
BS 6093: 2006 Design of joints and
web site (www.communities.gov.uk) or obtained Prevention Council (LPC), Building Research
jointing in building construction.
from RIBA Bookshops, 15 Bonhill Street, Establishment Ltd (BRE) and Timber Research
London EC2P 2EA. (Tel 020 7256 7222, Fax BS 8200: 1985 Code of Practice for design and Development Association (TRADA) also
020 7374 2737). of non-loadbearing external vertical enclosures produce recommendations and guidance on
of buildings. construction which should be considered.
More
pages 120-123 Sitework
134 References
Design considerations 31
Wind resistance
Wind forces on buildings Design for wind loading to give design loadings for typical impermeable
Each year as many as 200,000 buildings in the The standard method in BS 6399-2 Loading buildings and do not provide data in the
UK may be damaged by gales. Roof damage for buildings Code of practice for wind loads required form to enable the loading on
represents by far the largest sector of the total should be used to determine the basic wind permeable overcladdings to be assessed.
number of building elements affected. speed of the site, which is then used to The response of the Ventisol overcladding
calculate the effective wind speed and dynamic system to wind loading has been determined by
Wind can affect a building in a pattern
wind pressure on the envelope, by applying a direct measurements. A system performance
determined not only by climate and topography,
series of factors to account for terrain, specification has been defined with which the
but also by wind direction, the shape of the
topography, building height and length etc. actual performance is shown to comply.
building and the pitch of the roof.
Wind loading Using this system performance, a computer
Wind blowing at 90 to a building is slowed
Calculate the dynamic pressures of the wind based numerical model of the behaviour of the
down when it hits the surface of the building,
(including the appropriate pressure coefficients system when installed on a building has been
with a consequent build-up of pressure. At the
for the building) in accordance with BS 6399-2 developed and run for a number of typical
same time, it is deflected around the end walls
wind loading or EN 1991-1-4. installations. It is concluded that the maximum
and over the roof, creating areas of negative
pressure or suction. The stronger the wind, the The spacing of the profiles and brackets is nett suction on the standard system without
greater the suction. determined by calculation once the wind forces fire-stops can be taken as one-half of the
on the structure have been determined. The design external wind pressure.
The force of the wind acting on the windward
Ventisol system has been wind tested by the
face of a building creates a positive pressure,
Building Research Establishment (BRE) and is
although, even here, there are areas where
classified as permeable when applied to
suction develops. Leeward faces are always
nominally impermeable walls. In this situation, a
subject to suction.
large proportion of the external wind pressure is
able to leak through the cladding to act directly
on the building wall, relieving the loads on the
cladding. The provisions of all current codes of
practice, including that for the UK are intended
Directions of pressures
generated by wind force Reaction of wind flow to obstruction
suction
+ zone
30 and
wind above
suction
zone
+
30 and
wind below
32 Design considerations
More
advice E-mail info@marleyeternit.co.uk
Tel 01283 722588
web marleyeternit.co.uk/cladding
Aircraft vortices
Cladding near airports can experience high local 29
28
wind load forces due to air vortices created
by certain aircraft when taking off and landing, 27
Inverness
Aberdeen
23
Dundee
Perth
Oban
25
Glasgow Edinburgh
26
25 Newcastle
Londonderry
24 Carlisle
Belfast
23 24
York Kingston
Preston Leeds upon-Hull
23
Liverpool Manchester
Sheffield
Stoke
Nottingham
22
21 Leicester Norwich
25
Birmingham
Aberystwyth Northampton
Ipswich
24
Bedford
20
Oxford 23
Swansea
LONDON
Cardiff Bristol
Brighton
Bournemouth
Plymouth
24
23
Design considerations 33
Fire safety, acoustics,
condensation & ventilation
Fire safety
Building Regulations Key to external wall surface classification
The relevant document is Relevant boundary Index (I) not more than 20 (National
Approved Document B, Fire class) or class C-s3 d2 or better
No provision in respect of the
Safety. (European class). Timber cladding
boundaries indicated
at least 9mm thick is also
Class 0 (National Class) or class acceptable. (The index I relates to
B-s3, d2 or better (European class) tests specified in BS 476: Part 6).
Up to 10m
above a roof or
Building any part of the
height building to
less which the public
than have access
Up to
18m 10m
above
ground
Notes:
The National classifications do not automatically equate
Any dimension
with the equivalent European classifications, therefore
over 18m
products cannot typically assume a European class
unless they have been tested accordingly.
When a classification includes s3, d2, this means that
there is no limit set for smoke production and/or flaming
Building droplets/particles.
height
less
than
18m Up to 18m
above ground
Scottish Regulations
A2 classified materials are
classified as non-combustible.
The Scottish Building Standards
TECHNICAL HANDBOOK Marley Eternit fibre cement
NON-DOMESTIC
cladding products are all
SCOTTISH BUILDING
STANDARDS AGENCY
A2-s1-d0.
Less than Less than 1000mm 1000mm
1000mm 1000mm or more or more
34 Design considerations
Acoustics
Building Regulations Resistance to the passage of sound
The relevant document governing Approved Document E deals with the
acoustic design, especially for resistance of both airborne and impact sound
dwellings, is Building Regulations generated within buildings, and requires that
Approved Document E dwellings, flats and rooms for residential
Resistance to the passage of purposes shall be designed and constructed
sound within which, the relevant in such a way that they provide reasonable
sections are: resistance to sound from other parts of the
same building and from adjoining buildings.
E1: Protection of sound from other parts of
Separate requirements apply to schools, where
the building and adjoining buildings.
each room or space in the building shall be
E2: Protection against sound within a dwelling designed so that it has the acoustic conditions
house. and the insulation against disturbance by noise
appropriate to its intended use.
Other documentation, such as (HTM) Health
and Technical Memoranda 56 and 2045 for Further information can be obtained by
hospitals and Building Bulletin (BB) 87 and reference to BS 8233 Sound insulation and
93 for schools, offers guidance on meeting noise reduction in buildings and BS EN ISO
Building Regulations for specific building types. 717-1 Acoustics Rating of sound insulation
BS 5821 detailing the methods for rating the in buildings and of building elements. Part 1
sound insulation in buildings and of building Airborne sound insulation, and BS EN ISO
elements, is also relevant. 717-2 Acoustics Rating of sound insulation
in buildings and of building elements. Part 1
Impact sound insulation.
Design considerations 35
Thermal insulation
Limiting U-value standards (W/m2 K) (Part L1A New Dwellings) * Excluding display windows and similar glazing. There is
no limit on design flexibility for these exclusions but their
Element Area-weighted average impact on CO2 emissions must be taken into account
in calculations.
Eternal wall 0.30
The U-values for roof windows and rooflights in this table
Party wall 0.20 are based on the U-value having been assessed with the
roof window or rooflight in the vertical position. If a particular
Roof 0.20
unit has been assessed in a plane other than vertical, the
Floor 0.25 standards given in the Approved Document should be
modified by making an adjustment that is dependent on
Windows 2.00 the slope of the unit following the guidance given in BR 443
'Conventions for U value calculations'. BRE.2006.
36 Design considerations
Part L2A - New non-dwellings Part L2B Existing non-dwellings Design considerations
There are 5 key criteria for compliance: This applies to extensions and subsequent fit There are a number of factors to consider when
out works, change of use, material changes, designing buildings that are to meet the new
1 CO2 emissions must be less than target value
work on controlled services etc. New building Part L requirements. These will involve the types
2 The thermal performance of building fabric fit outs for existing buildings should comply of windows, doors, rooflights, solar gain, frame
and services must satisfy minimum standards with new building regulations. factor, air infiltration, U-Values, type of glass,
3 Summer time solar gains must be controlled Part L 2006 introduces Consequential total area and aspect of the dwelling. The
Improvements which may in some situations designer will also be required to consider the
4 Pressure testing and Quality of Construction heating system, the impact of any mechanical
require the upgrading of windows, boilers,
will be mandatory ventilation systems, along with the controls, and
air-conditioning and lighting as well as the
5 Building users should be supplied with inclusion of energy metering systems. any low and zero carbon technologies, e.g.
sufficient information to operate the building solar PV, wind power. Credits will be achieved
For all parts for the use of low carbon and energy saving
in the most energy efficient manner.
Where possible, LZC (Low and Zero Carbon) products, which in many cases will be the
Significant improvements in carbon dioxide systems should be installed. preferred route to compliance. This will involve
emissions are required when comparing the an assessment of the whole building
Unit energy costs for each fuel type are
notional and actual results. In general terms performance and not just each individual value.
detailed in the Approved Document and should
these represent the improvements to the levels
be used for assessing the feasibility of various In order to improve the quality of design details,
stated in the 2006 regulations:
improvements. a set of Accredited Construction Details have
Heated and naturally ventilated: 23.5% been published to accompany the new Part L.
Heated and mechanically ventilated: 28% Airtightness/air leakage These are updated versions of 2002 Thermal
Air conditioned: 28% Part L 2010 provides requirements for buildings Robust Details, and if approved over
to be tested for air leakage once completed. specifications could limit the requirement for
Again, two phases of calculation for emissions
Testing is carried out using pressurised fans on-site testing.
rate are required:
and consultants, to ensure that as well as the
1 Design calculations presented in a report Attention is given to the provision of suitable
theoretical heat loss calculations, the building is
to Building Control insulation to prevent heat loss and cold bridges
not leaky and wasting energy through gaps and
in roof construction. Guidance measures to
cracks due to construction methods.
2 Following full building pressure testing, prevent moisture ingress, condensation and air
a final calculation to confirm that the Workmanship and detailing on site to ensure leakage are incorporated into the construction
building complies as built. that a permitted air leakage of 10m3/hour/m2 details for walls, floors and roofs, with particular
@ 50 Pa is not exceeded when tested. attention being given to the junctions of walls to
floors and walls to roofs.
The building designer has to make an
assumption of what the level of airtightness he As insulation levels increase so does the
can achieve from his building at the design potential risk of condensation, and so designers
stage. This is inputted into the calculation for his should consider the recommendations with
heat loss/SAP calculations. Should the building regard to the prevention of condensation in cold
be found to be higher in terms of air leakage, roof voids contained in BS 5250: 2002 AMD 1,
then remedial measures must be taken to ensure which is also referenced in Approved Document
the building meets the required design value. C of the Building Regulations.
Design considerations 37
Thermal design details
new structures housing
38 x 100mm batten 6
38 x 50mm batten 5
Air gap 7
Blockwork wall
Marley Eternit external cladding
0.25
u-value
38 x 50mm and 38 x 100mm 50 x 50mm counterbatten 4
Notes
Internal wall should be 12.5mm
plasterboard on dabs
Marley Eternit
Cladding 8
4 5 2 3 7 6 8
Fibre
Fibre cement
nt sheathing 5
1 2
38 x 50mm
timber
er batten 7
Marley Eter
Eternit
nit
cladding
ding 8
3 4 5 6 7 8
38 Design considerations
Thermal design details
new structures commercial, education or healthcare
Aluminium frame fixing system 8
Thermostop pad 7
120mm insulation 6
Lightweight
steel frame
0.23 Bluclad cement board 5
u-value
Marley Eternit external cladding
100 x 75mm C Sections 4
1 2 3 4 5
6mm gap 9
30mm gap 10
Marley Eternit
Cladding 11
6 7 8 9 10 11
Air gap 5
Concrete wall
construction
0.14 130mm PIR insulation 4
1 2
6mm gap 6
Marley Eternit
cladding 7
3 4 5 6 7
Design considerations 39
Thermal design details
upgrading existing structures and overcladding
80mm Rockwool
Rainscreen Duo-slab
Brickwork wall 0.35 mineral wool 3
Ventisol fixing system Fixing system 2
Marley Eternit
cladding 5
2 3 4 5
80mm Rockwool
Rainscreen Duo-slab
mineral wool 5
Air
Marley Eternit external cladding u-value Brickwork 3 gap 6
Ventisol fixing system
Empty cavity 2
Air gap
upgrade Blockwork 1
80mm Rockwool Rainscreen
Duo-slab mineral wool
1.50
Brick outer skin u-value
Cavity not insulated
Brick inner skin
Notes:
U-values of these types of un-insulated
wall are typically 1.0-1.6 W/m2k
Other fixing systems can also be used
Greater (or lesser) depths of insulant
can be accommodated
Marley Eternit
cladding 7
2 3 4 5 6 7
40 Design considerations
Design considerations
Natura, Barking Foyer, Barking
41