2500GT Slipway Construction Gantt Chart

0 1 2
Totals
Relative Relative % Planned Actual 2014
# Scope of Works Cost Weight Done Start Duration Start Duration 0 8 9
Months 0 1 2
1 Site investigation/Hydrographic survey 100.00% 0 1 0 1
2 Site clearing, Lay-out, Bench Marking and Staking 0.00% 1 2
2.1 Sile clearing 0.00% 1 1
2.2 Staking 0.00% 1 1
2.3 Bench marking 0.00% 2 1
2.4 Layout 0.00% 2 1
3 Installation of Temporary Facilities 0.00% 1 2
3.1 Clearing 0.00% 1 1
3.2 continuation of fence 0.00% 1 1
3.3 Bunk houses 0.00% 1 2
4 Fabrication of carriage, rollers, sheave anchoring 0.00% 2 11
4.1 Pin
4.2 Roller
4.3 Roller house
4.4 Carriage
4.5 Sheave housing and sheave anchoring
4.6 Assmbly and installation of carriage on rails
5 Riprap Works 2 5
5.1 Above waterline
5.2 Below waterline
6 Earthworks 3 12
6.1 Excavation and grading of groundway
6.2 Backfilling
7 Casting/Purchase of RC piles 2 4
8 Causeway Works 3 12
8.1 Driving of reinforced concrete sheet piles
8.2 Driving of steel sheet piles including copperdam
8.3 Earth filling for causeway construction
8.4 install Rebars for Capping of RC Steel sheet piles
8.5 Install formworks
8.6 Pouring ready mix concrete
9 Rail foundation works including backhauling 5 12
9.1 Driving of RC piles for rail foundations
9.2 Cutting and Chipping of RC Piles
9.3 Sub base course in way of rail foundation
9.4 Lean concreting
9.5 Install Rebars
9.6 Install formworks
9.7 Install anchorbolts/anchoring for backhauling pulley
9.8 Pouring ready mix concrete
9.9 Install rails
10 Winch foundation and winch motor installation 10 6
10.1 Driving of RC piles for rail foundations
10.2 Cutting and Chipping of RC Piles
10.3 Sub base course in way of rail foundation
10.4 Lean concreting
10.5 install rebars and anchoring for mainhauling pulley
10.6 install formworks
10.7 Pouring ready mix concrete
10.8 Install winch
11 Cofferdam Works 12 6
11.1 Install whaler reinforcement
11.2 install dewatering pump
11.3 dewater for dry construction of rail foundation end
11.4 remove pump and reinforment
11.5 remove copperdam
12 Dredging Works 17 1
13 Site clearing and debris disposals 17 1
14 Final Inpection 18 1
15 Dry run and drydocking test 18 1
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

2014 2015 2016


10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
20 21 22 23 23

2016
3 4 5 6 7
20 21 22 23 24
Project : 2500 GRT SLIPWAY
Location : Cabu, Tambler, G.S.C.
Owner : SAFI SHIPYARD, INC.

COSTRUCTION GANTT CHART


0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Totals
% Planned Actual 2 0 1 4
# Scope of Works Done
Units
Start Duration Start Duration August September October November December January
Weeks####
##
### 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

0 PMT Status Meetings X XX

1 Site investigation/Hydrographic survey 0 1 0 1

2 Site clearing, Lay-out, Bench Marking and Staking 100% 1 7 1 7


done

2.1 Sile clearing 100% 1 2 1 2


done

2.2 Staking & Layout 100% 2 3 2 1


done

2.3 Bench marking 100% 4 4 4 2


done

3 Installation of Temporary Facilities 100% 2 7 2 7


done

3.1 Clearing 100% 2 1 2 0


done

3.2 Fencing (con't) 100% 2 6 2 2


done

3.3 Bunk houses 100% 2 6 2 5


done

3.4 Electrical Works 100% 4 5 7 2


done

4 Fabrication of carriage, rollers, sheave anchoring 9% 4 48 4 23

4.1 Pin ( cutting and machining ) 31% 240 4 8 4 23


on going

4.2 Pin lock ( cutting nd machining ) 19% 316 8 8 8 19


on going

4.3 Roller 23% 158 12 8 12 15


on going

4.4 Roller house 20 8 20 0

4.5 Carriage 28 8 28 0

4.6 Sheave housing and sheave anchoring 36 8 36 0

4.7 Assembly and installation of carriage on rails 44 8 44 0

5 Riprap Works ( Below & Above Water Line) 96% 21 48 7 20


stn. 6-18 RS facing the shore done

5.1 Base Preparation 96% 25 21 29 7 20


on going

5.2 Boulder Laying & Masonry Fillers 96% 25 25 44 7 20


on going

6 Casting/Purchase of RC piles 58% 7 38 7 20


on going

6.1 Poured/Casted 80% 7 38 7 12


on going

6.1.1 9.0 m long Sq. Piles 100% 60 7 38 7 15


done (january 9, 2015)

6.1.2 7.5 m long Sq. Piles 100% 113 10 35 10 14


done (january 20, 2015)
6.1.3 6.0 m long Sq. Piles 100% 56 13 32 13 10
done (january 13, 2015)

6.1.4 12.0 m long RC Sheet Piles (300) 19% 185 18 28 17 10

6.1.5 12.0 m long RC Sheet Piles (200) 100% 14 18 28 16 3


done

6.2 Fabrication of Steel Reinforcement 60% 7 36 7 20


on going

6.3 Fabrication /Assemble of Forms 50% 7 36 7 20


on going

6.4 Pouring sitemix concrete 50% 9 35 9 18


on going

6.5 Curing & removal of forms 50% 9 36 9 18


on going

7 Water System 91% 7 8 7 20

7.1 Fabrication of gravity tank 100% 7 8 7 12


done

7.2 Drilling 100% 8 2 8 2


done

7.3 Foundation/Erection of water tank 75% 10 4 10 17


wait lifting of H2O tank

7.4 Pipings / Installation of centrifugal pump 90% 14 1 14 13


wait h20 tank prior to pipings

8 Earthworks 15 55 12 15

8.1 Excavation and grading of groundway 44% 25 15 25 12 15


from stn. 8 to 11

8.2 Backfilling 40 23 17 10

9 Causeway Works 12 51 17 0

9.1 Earthfilling for causway construction 12 8 21 5

9.2 Driving of reinforced concrete sheet piles 18 8 0 0

9.3 Driving of steel sheet piles including copperdam 26 8 0 0

9.4 install Rebars for Capping of RC Steel sheet piles 18 33 0 0

9.5 Install & removal of forms (Formworks) 30 33 0 0

9.6 Pouring ready mix concrete 35 26 0 0

10 Construction of Second Gate 23 12 23 4

10 Rail foundation works including backhauling 20 53 17 10

11 Driving of RC piles for rail foundations 2% 428 20 8 17 10

11.1 9.0 m long Sq. Piles 15% 60 20 8 17 10

11.2 7.5 m long Sq. Piles 25% 113 20 8 17 10

11.3 6.0 m long Sq. Piles 0% 56 20 8 17

11.4 12.0 m long RC Sheet Piles (300) 0% 185 20 8 17

11.5 12.0 m long RC Sheet Piles (200) 0% 14 20 8 17

11.6 Cutting and Chipping of RC Piles 22 6 22 1


###

11.7 Sub base course in way of rail foundation 28 15 0 0

11.8 Lean concreting 32 12 0 0

11.9 Install Rebars 33 28 0 0


11.1 Install formworks 42 20 0 0

11.10 Install anchorbolts/anchoring for backhauling pulley 52 13 0 0

11.11 Pouring ready mix concrete 55 11 0 0

11.12 Install rails 63 10 0 0

12 Winch foundation and winch motor installation 40 24 24 3

12.1 Driving of RC piles . (7.5 m sq. pile) 100% 9 40 1 24 1

12.2 Cutting and Chipping of RC Piles 100% 9 41 1 27 1

12.3 Sub base course in way of rail foundation 42 1 0 0

12.4 Lean concreting 43 1 0 0

12.5 install rebars and anchoring for mainhauling pulley 44 6 0 0

12.6 install formworks 46 8 0 0

12.7 Pouring ready mix concrete 54 1 0 0

12.8 Install winch 55 9 0 0

13 Cofferdam Works 27 47 0 0

13.1 Install whaler reinforcement 27 6 0 0

13.2 install dewatering pump 33 1 0 0

13.3 dewater for dry construction of rail foundation end 34 36 0 0

13.4 remove pump and reinforment 70 2 0 0

13.5 remove copperdam 71 3 0 0

14 Electrical Works 69 12 0 0

15 Dredging Works 74 4 0 0

16 Site clearing and debris disposals 74 4 0 0

17 Final Inspection 78 4 0 0

18 Dry run and drydocking test 78 4 0 0

LEGENDS :
MAIN WORKS

SUB WORKS
Conforme :
26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70

2 0 1 5
February 2015 March 2015 April 2015 May 31 June 2015 July 2015 August 2015 September 2015 October 15 November 2015 Dece
26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70
70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 ###

2 0 1 6
December 2015 January February March April May June July
70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 ###