You are on page 1of 43

DC VISIT 2017

DATA CENTRE : PLAZA VADS


DATE : 21/11/2017

CONFIDENTIAL
AZMIR AHMAD HASBULLAH ALI
MANAGER MANAGER
FM DCO3

AMMAR AMRI NADIA TAHZIR


ASST. MANAGER ASST. MANAGER
FM DCO3

NIK MOHD ZAIHAZREE MOHD RAZALI


TECHNICAL OFFICER SUPERVISOR
FM DCO3

ORGANIZATION CHART ABDUL MUTALIP TAJZELINA


TECHNICAL ASST. TECHNICAL ASST.
DCO3 DCO3 DCO3

AB. RAZAK KHAIRUDDIN


TECHNICAL ASST. TECHNICAL ASST.
MOHAMAD SYAFIQ DCO3 DCO3
TECHNICAL ASST.
DCO3 HER JOHARI NUR HIDAYAH
TECHNICAL ASST. TECHNICAL ASST.
DCO3 DCO3

NOR HASLIZA SITI NOOR HIDAYAH


TECHNICAL ASST. TECHNICAL ASST.
DCO3 DCO3
DC PERFORMANCE
1. Availability
This image cannot currently be displayed.

UPS Battery

LEVEL 7 Installed: 2016 PEC


Next Replace: 2021 PEC 1-3 (40kW)
Installed: 2000
Cooling Load

UPS-1 80kVA
PEC 4 (30kW)
Installed: 2010
150kW
Load: 32%
(23kW/68kW)
Installed: 2001
VS
IT Load
85kW
TNB
Parallel
Connection

PDU Server rack Level 7


UPS-2 80kVA Occupied Rack : 64
Generator 1500kVA (22kW/68kW) Free space for rack: 10
Installed: 2016
Load: 32%
Load: 33.3% Installed: 2001
(400kW/1200kW)
UPS Battery
Installed: 2016
Next Replace: 2021

Rectifier-1
(74A/180A)
Installed: 2017
Generator AT&T 400kVA Load: 41%
Installed: 2002 Rectifier Battery
Installed: 2016 Server / Comm. Rack Level 7
Load: 44% Next replace: 2021
(152kW/340kW)
Rectifier-2
(217A/360A)
Installed: 2017 Server / Comm. Rack
Load: 64% Level 7 & 8
Rectifier Battery
Installed: 2016
Next replace: 2021
Rectifier-3
(269A/600A) Server / Comm. Rack
Installed: 2007 Level 7 & 8
Load: 44%
Rectifier Battery
Installed: 2014
Next replace: 2019
This image cannot currently be displayed.

LEVEL 7
AT&T UPS Battery
Installed: 2015
Next Replace: 2020

UPS-1 30kVA
PDU A
Load: 32%
(9kW/25kW)
Installed: 2015
Source A
AT&T Cage
Occupied Rack: 15
TNB Space for Rack: NA

Source B

UPS-2 60kVA
Load: 18%
PDU B
(9kW/51kW)
Installed: 2002
Generator 1500kVA
Installed: 2016 UPS Battery
Load: 33.3% Installed: 2012
(400kW/1200kW) Next Replace: 2017

Generator AT&T 400kVA


Installed: 2002
Load: 44%
(152kW/340kW)
Data Center Operation Availability
LAYOUT - LEVEL 7

Space Available
This image cannot currently be displayed.

LEVEL 8 PEC
PEC 1 (30kW) PEC
Installed: 2005 PEC 1-4 ASTRO
(60kW)
UPS Battery Installed: 2008
PEC 2 (60kW)
Installed: 2016
Installed: 2005 Level 8 DC ASTRO DC
Next Replace: 2021
Generator 1500kVA Standby PEC 3 (60kW) Cooling Load Cooling Load
Installed: 2016 Installed: 2007
Load: 33.3% UPS-1 200kVA 210kW 240kW
(400kW/1200kW) Load: 43% PEC 4 & 5 (60kW)
PDU A Installed: 2012
(85kW/190kW)
Installed: 2016
VS VS
Source A
IT Load IT Load
112kW 140kW
TNB

Server rack Server rack


Source B Occupied Rack : 57 Occupied Rack : 79
Free Rack: 15 Free Rack: 14
Free Space:11 Racks
UPS-2 200kVA
Load: 38%
(63kW/190kW) PDU B
DC Level 8 ASTRO DC
Installed: 2008
Generator 1500kVA
Installed: 2016
Load: 25%
(300kW/1200kW)

UPS Battery
Installed: 2016
Next Replace: 2021

80% (Cooling Load) = x


(IT Load/x )100= y%
100 y = Availibility%
Availibility / x = Rack
Data Center Operation Availability
LAYOUT - LEVEL 8
This image cannot currently be displayed.

LEVEL 12 PEC
PEC
PEC 1 (60kW)
PEC 1 - 3(85kW) PEC2 (60kW) Standby
Standby PEC 4 (85kW) PEC 3(40kW)
UPS Battery Installed: 2009 PEC4 (40kW) Standby
Installed: 2015
Level 12 DC New Wing DC Installed: 2015
Next Replace: 2020
Generator 1500kVA Cooling Load Cooling Load
Installed: 2016
Load: 33.3% UPS-1 300kVA 255kW 100kW
(400kW/1200kW) Load: 33%
PDU A
(79kW/255kW)
Installed: 2009
VS VS
Source A
IT Load IT Load
69kW 51kW
TNB
Server rack
Server rack
Source B Containment area
Occupied Rack : 44
Fully Occupied
Free space for Rack: 0
COLO
UPS-2 300kVA Free Rack: 1
Load: 37% Ericsson cage
(88kW/255kW) Occupied Rack: 15
PDU B
Installed: 2009 Free space for Rack: 2

Generator 1500kVA
Installed: 2016
DC Level 12 New Wing DC
Load: 25%
(300kW/1200kW)

UPS Battery
Installed: 2015
Next Replace: 2020
Data Center Operation Availability
LAYOUT - LEVEL 12
0
5
10
15
20
25
30
35
1/1/2017
8/1/2017
15/1/2017
22/1/2017
LEVEL 7

29/1/2017
5/2/2017
12/2/2017
19/2/2017
26/2/2017
5/3/2017
12/3/2017
19/3/2017
26/3/2017
2/4/2017
9/4/2017
16/4/2017
23/4/2017
30/4/2017
7/5/2017
14/5/2017
21/5/2017
28/5/2017
4/6/2017
11/6/2017
18/6/2017
25/6/2017
2/7/2017
9/7/2017
16/7/2017
23/7/2017
Level 7_Temp

30/7/2017
6/8/2017
13/8/2017
20/8/2017
27/8/2017
3/9/2017
10/9/2017
Data Center Operation Temperature & Humidity Analysis

17/9/2017
24/9/2017
1/10/2017
8/10/2017
15/10/2017
22/10/2017
29/10/2017
Min

Max
Recommended
Recommended

THS-5(VZ)- Temp
THS-2(DC)- Temp
THS-1(DC)- Temp

THS-3(AT&T)- Temp
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
1/1/2017
8/1/2017
15/1/2017
22/1/2017
LEVEL 7

29/1/2017
5/2/2017
12/2/2017
19/2/2017
26/2/2017
5/3/2017
12/3/2017
19/3/2017
26/3/2017
2/4/2017
9/4/2017
16/4/2017
23/4/2017
30/4/2017
7/5/2017
14/5/2017
21/5/2017
28/5/2017
4/6/2017
11/6/2017
18/6/2017
25/6/2017
2/7/2017
9/7/2017
16/7/2017
23/7/2017
30/7/2017
Level 7_Humidity

6/8/2017
13/8/2017
20/8/2017
27/8/2017
3/9/2017
10/9/2017
Data Center Operation Temperature & Humidity Analysis

17/9/2017
24/9/2017
1/10/2017
8/10/2017
15/10/2017
22/10/2017
29/10/2017
Min

Max
Recommended
Recommended

THS-5(VZ)- Humd
THS-2(DC)- Humd
THS-1(DC)- Humd

THS-3(AT&T)- Humd
0
5
10
15
20
25
30
35
1/1/2017
8/1/2017
15/1/2017
22/1/2017
LEVEL 8

29/1/2017
5/2/2017
12/2/2017
19/2/2017
26/2/2017
5/3/2017
12/3/2017
Gas leaking

19/3/2017
26/3/2017
2/4/2017
9/4/2017
22/1/17 PEC3 (ASTRO)

16/4/2017
23/4/2017
30/4/2017
7/5/2017
14/5/2017
21/5/2017
28/5/2017
4/6/2017
leaking.

11/6/2017

relocation
18/6/2017
25/6/2017
2/7/2017
9/7/2017
24/4/17 PEC5 (DC)

16/7/2017
Compressor low alarm,
Level 8_Temp

23/7/2017
30/7/2017
6/8/2017
Temperature drop after the sensor

13/8/2017
20/8/2017
27/8/2017
3/9/2017
Data Center Operation Temperature & Humidity Analysis

10/9/2017
dirty.

17/9/2017
24/9/2017
1/10/2017
8/10/2017
15/10/2017
outdoor unit getting

22/10/2017
Sensor 1 increase due to

29/10/2017
Min

Max
Recommended
Recommended

L8-THS-5 (Temp)
L8-THS-4 (Temp)
L8-THS-3 (Temp)
L8-THS-2 (Temp)
L8-THS-1 (Temp)
0
10
20
30
40
50
60
70
80
90
1/1/2017
8/1/2017
15/1/2017
22/1/2017
LEVEL 8

29/1/2017
5/2/2017
12/2/2017
19/2/2017
26/2/2017
5/3/2017
12/3/2017
19/3/2017
26/3/2017
2/4/2017
9/4/2017
16/4/2017
23/4/2017
30/4/2017
7/5/2017
14/5/2017
21/5/2017
28/5/2017
4/6/2017
11/6/2017
18/6/2017
25/6/2017
2/7/2017
9/7/2017
16/7/2017
23/7/2017
Level 8_Humidity

30/7/2017
6/8/2017
13/8/2017
20/8/2017
27/8/2017
3/9/2017
Data Center Operation Temperature & Humidity Analysis

10/9/2017
17/9/2017
24/9/2017
1/10/2017
8/10/2017
15/10/2017
22/10/2017
29/10/2017
Min

Max
Recommended
Recommended

L8-THS-5 (Humd)
L8-THS-4 (Humd)
L8-THS-3 (Humd)
L8-THS-2 (Humd)
L8-THS-1 (Humd)
0
5
10
15
20
25
30
35
1/1/2017
8/1/2017
15/1/2017
22/1/2017
29/1/2017
LEVEL 12

5/2/2017
12/2/2017
19/2/2017
26/2/2017
5/3/2017
12/3/2017
19/3/2017
26/3/2017
2/4/2017
9/4/2017
16/4/2017
23/4/2017
30/4/2017
7/5/2017
14/5/2017
21/5/2017
28/5/2017
4/6/2017
11/6/2017
18/6/2017
25/6/2017
2/7/2017
9/7/2017
16/7/2017
23/7/2017
30/7/2017
6/8/2017
13/8/2017
20/8/2017
27/8/2017
3/9/2017
10/9/2017
Data Center Operation Temperature & Humidity Analysis

17/9/2017
24/9/2017
1/10/2017
8/10/2017
15/10/2017
22/10/2017
29/10/2017
Min

Max
Recommended
Recommended

L12-THS-8 (Temp)
L12-THS-7 (Temp)
L12-THS-6 (Temp)
L12-THS-5 (Temp)
L12-THS-4 (Temp)
L12-THS-3 (Temp)
L12-THS-2 (Temp)
L12-THS-1 (Temp)
0
10
20
30
40
50
60
70
80
90
1/1/2017
8/1/2017
15/1/2017
22/1/2017
29/1/2017
LEVEL 12

5/2/2017
12/2/2017
19/2/2017
26/2/2017
5/3/2017
12/3/2017
19/3/2017
26/3/2017
2/4/2017
9/4/2017
16/4/2017
23/4/2017
30/4/2017
7/5/2017
14/5/2017
21/5/2017
28/5/2017
4/6/2017
11/6/2017
18/6/2017
25/6/2017
2/7/2017
9/7/2017
16/7/2017
23/7/2017
30/7/2017
Level 12_Humidity

6/8/2017
13/8/2017
20/8/2017
27/8/2017
3/9/2017
Data Center Operation Temperature & Humidity Analysis

10/9/2017
17/9/2017
24/9/2017
1/10/2017
8/10/2017
15/10/2017
22/10/2017
29/10/2017
Min

Max
Recommended
Recommended

L12-THS-8 (Humd)
L12-THS-7 (Humd)
L12-THS-6 (Humd)
L12-THS-5 (Humd)
L12-THS-4 (Humd)
L12-THS-3 (Humd)
L12-THS-2 (Humd)
L12-THS-1 (Humd)
DC PERFORMANCE
2. Issue
Data Center Operation Issue

1. Issue : Customer Boxes


Customer left their boxes in DC.
Action:
DC staff informed and email the issue to customer service to ask customer to take out
their boxes from DC.
Status:
Waiting response from BT and CHINA Union Boxes had been transferred to Level 7 due
to AT&T expansion
Data Center Operation Issue

2. Issue : Colling at Level 7


High temperature at AT&T cage
Action: (Study)
Open the raised floor around 30 degree so that the air can be blow directly towards AT&T
cage since there are a lot of cable blockage under the raised floor. The air will be blow
on top of raised floor.
Status:
The temperature in AT&T cage is within the range.
Cooling Study
Temperature readings before open raised floor .
Cooling Study
Temperature readings after open raised floor.
Cooling Study
Temperature readings result comparison.

BEFORE AFTER
DC PERFORMANCE
3. Project
Data Center Operation Project

1. Rectifier replacement

Replacement of rectifier 1 and rectifier 2 at Level 7.


Replacement Date: Rec 1 19 Mac 2017 & Rec 2 2 April 2017
Data Center Operation Project

3. AT & T Expansion at Level 12

- AT&T had a plan to rent a new cage at Level 12


- AT&T personnel from AT&T Hong Kong already came for a site visit in Mac 2017
- Status: In progress
- Pending CCTV, IEMS, Door Access
- AT&T personnel had come to visit their new cage on 15/11/17
Data Center Operation Project

4. New Customer China Unicom Level 12

- 180 sqft cage at Level 12


- 4 occupied racks
- Empty space for 3 racks
- Not yet handover to DCO
DC PERFORMANCE
4. Incident / Service Request
Data Center Operation VMS & RHS

Month VMS RHS


Jan 128 31
Feb 115 31
Mac 150 41
April 128 25
May 131 34
June 127 27
July 163 33
Aug 96 28
Sep 119 45
Oct 90 21
Total 1247 316

VMS & RHS


VMS RHS

163
150
128 128 131 127
115 119
96 90

41 34 45
31 31 25 27 33 28 21

Jan Feb Mac April May June July Aug Sep Oct
Data Center Operation Incident & Service Request

2017 IM 2017 SR
2017
Breach/ Not Breach/
Units IM SR Total Ticket Total Ticket

Data Centre 100% 100% 0/17 141/141


Plaza VADS

IM 2017 SR 2017
High Temperature Hardware failure Aircond Alarm Jan Feb Mac Apr May Jun Jul Aug Sep Oct

Water Leak HSSD

6% 12% 11% 5% 7%
9%
14%
6%
53%
23%
13% 11%

6% 12% 12%
Data Center Operation Incident & Service Request
Partner Circuit
Partner Circuit
Provisioning Troubleshooting
14
13 13
11 11
10
8
7 7
5 5
3 3
2 2 2 2
1 1

Jan Feb Mac Apr May Jun Jul Aug Sep Oct

- Handover new provisioning by GSP


- Handover troubleshooting by GWSOC
- List of partner
AT&T
BT
SINGTEL
VERIZON
TATA
- List of Telco/Provider
TM (L7,L8,L12)
MAXIS (L7,L8)
TIME (L7,L8)
FIBERAIL (L7)
FIBERCOMM (L8)
Data Center Operation Incident & Service Request
MRC
Fiber UTP Coax
Jan 4 2 0
Feb 2 2 0
Mac 3 2 0
Apr 2 0 0
May 0 6 0
Jun 0 14 0
Jul 2 0 1
Aug 0 0 0
Sep 3 3 0
Oct 3 1 0

MRC/OTC - 2017
Fiber UTP Coax
14

4
3 3 3 3
2 2 2 2 2 2
1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Jan Feb Mac Apr May Jun Jul Aug Sep Oct
DC PERFORMANCE
5. Activity/Initiative
Data Center Operation Activity/Initiative
# Activity Picture/ Attachment Status
1 Training with GWSOC Done

2 Training with GSP Done

3 Covering window glass in DC Done


Gypsum wall installation

4 Monthly genset maintenance Ongoing


Able to reduce cost (RM40k per year)
Data Center Operation Activity/Initiative
# Activity Picture/ Attachment Status
5 Data Center Cleaning Ongoing

6 Data Center petting Ongoing


rack

7 UPS2 Level 8 - Done


Capacitor replacement
Data Center Operation Activity/Initiative
# Activity Picture/ Attachment Status
8 Cleaning outdoor condenser unit Done

9 Repairing data center raised floor Done

10 MRC Ongoing
Monthly Recurring Charges
Data Center Operation Activity/Initiative
# Activity Picture/ Attachment Status
11 Load balancing UPS1 & UPS2 Done
Level 12 & STS synchronization

Before After
12 Performing troubleshooting Ongoing
for partner circuit

13 Step down voltage at Done


Transformer 4
Data Center Operation Activity/Initiative
# Activity Picture/ Attachment Status
14 Training for ICTSD Done

15 Training MRC Done

16 Training UPS & CRAC by CE Done


Data Center Operation Activity/Initiative
# Activity Picture/ Attachment Status
17 Training UPS & CRAC by CSPM Done

15 Training UPS & CRAC by Done


VERTIV

16 Training PANDUIT Done


Data Center Operation Activity/Initiative
# Activity Picture/ Attachment Status
17 Shooting for IPDC Launching Done
Video

18 Audit by AT&T Done

19 Audit by ASTRO Done


DC PERFORMANCE
6. Initiative / Improvement Plan
Data Center Operation Initiative / Improvement Plan

1. RAISED FLOOR REPAIRING

2. DC CLEANING
Data Center Operation Initiative / Improvement Plan

3. WORK LIGHTING REPAIRING INSIDE DATA CENTER

4. SENSOR RELOCATION AT LEVEL 8


THANK YOU

CONFIDENTIAL