You are on page 1of 6

PROJECT TIMELINE PLAN

SR.NO. NAME OF PROJECT SCOPE 3D CONCEPT DAP 3D DATE 2D DATE TARGET DATE

LOADING PALLET BOSCH


1 DESIGN &MFG. 11/4/2017 11/7/2017 11/9/2017 11/10/2017 12/4/2017
REXOTH-NASHIK

2 DOSING FURNACE 1.2 TON DESIGN/3D/2D 11/10/2017 11/11/2017 11/22/2017 11/29/2017 11/30/2017

3 0.3TON FURNACE 3D/2D 11/2/2017 N/A 11/2/2017 11/8/2017 11/9/2017

4 INLED LIGHTING FURNACE 3D/2D 11/2/2017 N/A 11/2/2017 11/8/2017 11/9/2017

5 DIE PRESS MACHINES -2 QTY. 3D/2D 11/8/2017 11/8/2017 11/8/2017 11/10/2017 11/10/2017

6 ANODE CASTING PROJECT 3D CONCEPT 11/9/2017 11/9/2017 11/10/2017 N/A 11/11/2017

7 NITRIDING FURNACE 3D/2D 11/10/2017 11/11/2017 11/18/2017 11/29/2017 11/30/2017

8 MINI EXCAVATOR 3D/2D/ PROTO 12/7/2017 12/8/2017 12/15/2017 12/31/2017 1/31/2018 Click Here...!!!
DATE : 08-11-2017

REMARK

WAITING FOR DESIGN APPROVAL


DISPATCH WILL BE DONE ON TARGET
DATE.

EXCEPT ELECTRICAL & PNEUMATIC


DESIGN WORK.

EXCEPT ELECTRICAL & PNEUMATIC


DESIGN WORK.

PLEASE SEE ROADMAP OF MINI


ClickDEVELOPMENT.
EXCAVATOR Here...!!!
ROADMAP OF MINI-EXCAVATOR

SR. NO. CONTENTS DETAILS START DATE END DATE

A. Collect the information of product


competitor.
1 Product Competitor 1-Nov-17 2-Nov-17
B. Summaries the data of cost, capacity &
engine provider.
A. Study the sale volume of product.
2 Sale Volume & Forecast B. Study the forecast sale volume of 3-Nov-17 4-Nov-17
product.
A. Collect the information about the
product main assemblies.
B. Collect the Product catalogue with its
3 Product Details spare & maintenance manual. 6-Nov-17 9-Nov-17

C. Collect the information about assembly


parts (Assembly Exploded view).

A. Tracking Consultant / designer from


product competitor.
B. Find out product near by to make
4 Other information 10-Nov-17 14-Nov-17
reverse engineering.
C. Collecting information of product sale
volume region wise.
A. Engine Capacity
B. Operating weight
C. Bucket capacity
D. Dimensions (In transport condition)
5 Product Benchmarking E. Digging capacity 15-Nov-17 18-Nov-17
F. List out manufacturing assemblies
G. List out Brought out components & its
specification.
H. List out Hydraulics & its specification.
A. Design manufacturing assemblies.
B. Design/Brought out linkages.
6 3D Concept Design 20-Nov-17 7-Dec-17
C. Finalise Brought out components.
D. Simulation of product.
Concept design approval, review &
7 DAP 8-Dec-17 8-Dec-17
suggestions from expert.
A. Implementation of DAP Points.
B. Modification as per brought out
8 Final 3D Design 9-Dec-17 15-Dec-17
equipment.
C. Checkout aesthetic & robust design.
Drawing release for prototype product
9 2D Drawing 16-Dec-17 30-Dec-17
manufacturing.
A. Manufacturing parts as per 2d drawing.
B. Purchasing of Brought out items.
10 Proto Manufacturing C. Assembly of product. 1-Jan-18 31-Jan-18
D. Testing at Ideal condition.
E. On field testing.
A. Measure of testing parameters.
B. Analysis of testing result.
C. Modification in design depend on testing
11 Testing & Results 1-Feb-18 15-Feb-18
& analysis results, if required.
D. Final drawing release for batch
production.
REMARKS

Completed

Completed

Completed

WIP

WIP

Required 6 designer & 1


simulation expert till final 2d
drawing generation from 20-Nov-
17.

Required expert team for DAP.

Date may vary depend on 3D


Modification.