Professional Documents
Culture Documents
Lesson 4
INSPECTORS
ROLE
4-1
Learning Outcomes
4-2
Inspectors Role
Be a Recorder
Be a Reporter
4-3
Inspectors Role
4-4
Remember who you are representing and perform your job in a professional manner.
Use common sense- do not delay the Contractor unnecessarily or interfere with their
operations. They are responsible for constructing the project and any out of line delays
caused by the inspector can be cause for claims.
You and the Contractor both have the same goal- getting the project built. The
Contractor needs to construct it within the budget and schedule and you are there to
ensure that the state gets what it pays for and that the project is constructed in general
accordance with the approved plans and specifications.
Inspectors Role
4-5
Inspectors Role
KNOW THE
PLANS
KNOW THE
SPECIFICATIONS
4-6
In some projects, the Inspector is brought in at the last moment so it is imperative that
you become familiar with the details of the project as quickly as possible.
The Inspector should receive, in advance of the project starting, the approved Plans
and Pile Installation Plan. Review these documents for items that affect you.
This course is based upon the July 2014 Workbook Version of the Standard
Specifications and Supplements.
Inspectors
Inspectors Responsibilities
Responsibilities
Make
Make accurate
accurate and
and unbiased
unbiased
observations
observations
Be
Be aa Recorder
Recorder Document
Document events:
events: complete
complete &&
consistent
consistent
Perform
Perform your
your duties
duties promptly
promptly
Complete
Complete reports
reports && forms
forms
Be accurately
accurately
Be aa Reporter
Reporter
Keep
Keep forms
forms and
and diary
diary up-to-date
up-to-date
Keep
Keep Project
ProjectAdministrator
Administrator informed
informed
4-7
4-7
INSPECTOR ATTITUDE
The Inspector should be a recorder. In performing this function the inspector must
make accurate and unbiased observations of all important pile driving construction
events.
Document events in a complete and a consistent way. This is very important if
construction proceeds other than anticipated.
Perform your duties promptly.
The inspector is also a reporter. Complete the forms and reports accurately. Keep
the forms and diary up to date. The records kept by the Inspector are the only form of
tangible data to make an engineering judgment whenever installation problems arise.
Elimination of potential causes can best be made on the basis of accurate and
complete data observations.
Pre-Driving Meeting
4-9
It will alert the Inspector as to potential problem areas that could affect the installation.
This meeting will open up the communication between the team and enhance
communication.
With Contractor
4-10
The Inspector is NOT to direct the Contractors work. The Contractor is responsible for
building the project. Remember, in a sense, the site belongs to the Contractor, they
are the home owner, and the Inspector is, the Inspector.
If you observe potential non conformance and possible conflicts, notify the contractor
as soon as possible. Dont wait until the damage is done. Youll find that in some
cases, the Contractor will begin to appreciate the heads up.
With proper coordination and communication, you can avoid falling into situations that
can cause possible delays. For example, if rain is expected tomorrow and the
Contractor has their pile cushions stacked up but uncovered, remind the Contractor of
the potential for rain. It just may have slipped the Contractors mind about not getting
the pile cushions wet.
Casey
Casey
4-11
Prior to going out to the project, it is the Inspectors responsibility to ensure that they
have all of the up-to-date project documentation, forms, etc.
Just as any other type of work, you cant do the job properly if you dont have the
tools.
Tools Checklist
SAMPLE INSPECTORS TOOLS CHECKLIST
Testing Equipment
Saximeter
Spare batteries
Documentation Material
4-12
COMPONENT CHECK
Always check for revised sheets to see
Plan Revisions if there are any changes that affect the
pile construction.
4-13
COMPONENT CHECK
Does there appear to be any conflicts
Utilities with production or test piles? If so, are
there provisions for addressing these
conflicts?
4-14
STRUCTURAL
PLANS CHECK
Compare with the Pile Data Table. Do any
General Notes Notes contain changes to the
specifications or specification
applications?
4-15
STRUCTURAL
PLANS CHECK
Rpt. of Core Are groundwater tables/piezometric levels
Borings shown? Do the boring(s) extend beyond the
proposed pile tip elevations?
4-16
Pay Quantities
PAY
QUANTITIES
4-17
4-18
4-20
4-22
4-23
4-25
4-26
4-27
4-28
4-30
4-31
4-33
4-34
4-35
4-36
4-37
4-38
4-39
4-40
4-41
This table summarizes the way the quantities are determined for concrete piles. As
you can see most of the work items get converted into pile length quantities. For
example set-checks, re-drives, dynamic testing, splices, and preforming preforming.
Let us review these:
st
Click to show 1 arrow
Set-checks: They are paid as 10 ft of piling each. They are paid as test piling for test
piles and as production piling for production piles. However there are some free set-
checks. For example in test piles we have four set checks for free when:
The first two are performed within two hours of completion of the initial drive, and the
other two are done within the working day following the initial drive. For example,
today the contractor did the initial drive of the test pile. If we order to do two set-
checks today within two hours of finishing the initial drive, those are free. If in addition
we order another set-check at 5 pm tomorrow (a working day) then that is also free. If
we exceed the four free set-checks we will pay at 10 ft of test pile per set-check
above the free four.
In production piles we have two free set checks when they are done within the day
following the initial driving day. Beyond this time we pay at 10 feet of production pile.
Click to show 2nd arrow
Re-drives: If we order a redrive after one working day following the day of finishing
the initial drive we pay at 20 ft of test piling. They are paid as test piling for test piles
and as production piling for production piles.
4-42
Splices longer than 5 ft are paid as follows: 30 ft of piling to pay for the materials and
labor of attaching the two pieces. In addition we pay for whatever splice length we
authorize to attach to the original pile. We also pay for redriving of the splice if we
needed for concrete production piles. We will not pay for splice redrive on test piles
and on steel piles.
Splices up 5 ft in long are popularly known as build-ups, leaving the name of splice to
the extensions longer than 5 ft when you will need order a prefabricated section.
Splices 5 ft or shorter are cast in place. There will be also some labor and materials to
prepare for building up. In this case we pay 9 ft for manufacturing the splice and the
length of pile we are extending.
Please keep in mind that the quantity of feet to be paid of making a splice whether it
is for production pile or a test pile will be in terms of production pile. Just because it is
a test pile we dont pay the 30 ft as a test pile. The effort and cost of materials and
labor for drilling holes, placing dovels, placing a form, pouring epoxy and attaching the
sections must not be different between production piles and test piles. This means
that the 9 ft (for build ups up to 5 ft) and the 30 ft for the precast splice sections would
be as production piles.
The cost of the pile length ordered for the splice will be in terms of production pile for
production piles. For test piles, it will depends. If the splice is ordered to complete a
pile that went below cut-off, and does not be tested, we pay only as a production pile.
For example we have a test pile in a bent that did not reach capacity at the cut-off and
the engineer continued driving until he got satisfied with the bearing. The pile ended
up above ground but 10 below cutoff. He does not need to drive the pile anymore. All
he needs is to extend the pile to cutoff elevation of the plans. In this case we would
pay the 10 ft length of the extension as a production pile.
If the splice in a test pile is tested (driven) we would pay as a test pile item.
The reason this is important is that test piles are usually much more expensive than
production piles (2 to 3 times).
Preforming- 30% of
Drilled hole depth in ft 4-43
Driving of a splice in production pile is paid at 10 ft. Driving of a Test pile splice is not
paid.
Preforming- 30% of
Drilled hole depth in ft. 4-44
Learning Outcome
Concrete Production Pile
ITEM QUANTITY PAY- Piling Furnished
Pile Top
Actual Piling Dlvd. 60
- Cut-off Elev.
Predrill 15
-Drv. Splice
4 (within 1 day) 30
Set-check
-Splice
-4 Set-checks
Dynamic Load Test 0 -1 Redrive
Redrive 1
30
Splice length 60
Splice 1
Driving of Splice 1
Cut-off 1
Pile Tip
4-45
Learning Outcome
Concrete Test Pile
ITEM QUANTITY PAY- Piling Furnished
Pile Top
Test Pile:
Actual Piling Dlvd. 60 - Cut-off Elev.
Preform 15
10
Set-check 1 @ 1 hr.)
-Splice
Dynamic Load Test 1 (non-driven)
Redrive 0 -1Set-checks
Production Piling: -0 Redrives
Splice length 10 60
Splice 1
Driving of Splice
0
Cut-off 1 Pile Tip
4-46
Learning Outcome
Concrete Production Pile
ITEM QUANTITY PAY- Piling Furnished
- Cut-off Elev.
Splice N/A
Driving of Splice N/A
Build-up 1
Pile Tip
4-47
Learning Outcome
Concrete Test Pile
ITEM QUANTITY PAY- Piling Furnished
Pile Top
Actual Piling Dlvd. 80
- Cut-off Elev.
Predrill 15
Set-checks (all done within 1 day) 0
Dynamic Load Test*
-3 Set-checks
Redrive 0
80
Splice length 0
N/A
Splice
Driving of Splice N/A
Cut-off N/A
1
Pile Tip
4-48
Learning Outcome
Steel Production Pile
ITEM QUANTITY PAY- Piling Furnished
Pile Top
Actual Piling Dlvd. 60
- Cut-off Elev.
Preform 20
-Drv. Splice
3 (within 1 day) 30
Set-checks
-Splice
-3 Set-checks
Dynamic Load Test 0 -1 Redrive
Redrive 1 (All set
30 checks and
Splice length 60 redrive were
Splice 1 instrumented)
Driving of Splice 1
Cut-off 1
Pile Tip
4-49
Learning Outcome
Steel Test Pile
ITEM QUANTITY PAY- Piling Furnished
Test Pile:
Pile Top
Actual Piling Dlvd. 60
- Cut-off Elev.
Preform 20
-Drv. Splice
3 (within 1 day) 30
Set-checks
-Splice
Dynamic Load Test 0
-3 Set-checks
Redrive 1 -1 Redrive
30 (All set
Splice length
checks and
Production Pile: 60 redrive were
Splice 1 instrumented)
Driving of Splice 1
Cut-off 1
Pile Tip
4-50
Inspector Math
Inspector
Math
4-51
Inspector Math
Tip Elevation
Penetration
Length Driven
Cutoff Target
4-52
Inspector Math
4-53
Inspector Math
4-54
Problem 1- Penetration
50
Cutoff Determine Pile Penetration
4155
Elevation= +5.00 14
40
13 Pile Penetration is the lowest elev. minus
Reference
3125 the Tip Elevation.
Elevation= + 2.00 11
3100 Lowest of: 1. Ground Surface Elevation
Ground Surface 9
25 2. Bottom of Excavation
Elevation= +0.00 8 3. Scour
270
(No Scour) 6
155
Penetration = Ground Elev. - Tip Elev.
140
3
25
1 Penetration =
Tip Elev. = - 27.00
Penetration =
Penetration =
4-56
50
Cutoff Determine Driven Length
415
5
Elevation= +5.00 14
40
13 Length Driven is Cutoff elev. minus
Reference
3125 the Tip Elevation.
Elevation= +2.00 11
3100
Ground Surface 9
Elevation= +0.00 25
8
270
(No Scour) 6 Length Driven = Cutoff Elev. - Tip Elev.
155
140
3
2
5 Length Driven =
1
Tip Elev. = - 27.00
Length Driven =
Length Driven =
4-57
Tip Elev. = Ref. Elev. - [Length Below Ref. Elev. x Corr. Factor]
4-58
4-59
Tip Elev. = Ref. Elev. - [Length Below Ref. Elev. x Corr. Factor]
100 Year
Scour = +1.50
Tip Elev. =
Batter Ratio = 5:1 Tip Elev. =
5 Corr. Factor = 0.981
1 4-60
Problem 2- Penetration
4-61
Problem 2- Penetration
Cutoff Elev. = +10.00
Reference
Elev= +7.00 Determine Pile Penetration
Pile Penetration is the lowest
Ground Surface elev. minus the Tip Elevation.
Elev.= +4.00 Lowest of: 1. Ground Surface Elevation
2. Bottom of Excavation
3. Scour
100 Year
Scour = +1.50
Length Driven =
1
Driven Length =
4-63
Length Driven =
Tip Elev. = -29.79
To Calculate MTT:
MTT=
MTT=
MTT=
4-66
To Calculate SCT
Vertical Pile:
SCT= Pile Length 1 (Cut-off Elev. Ref. Elev.)
Batter Pile-
SCT= Pile Length 1 (Cut-off Elev. Ref. Elev.)
Corr. Factor
4-67
SCT=
SCT=
SCT=
4-68
Learning Outcomes
4-69
End of Lesson 4
ANY
QUESTIONS ?
4-70
- Production piles; 2 set-checks within initial driving and the 1 - No Payment 455-11.9.2
working day following the end of initial driving.
- Any additional set check within the 1 working day following the - 10 feet piling furnished bid price 455-11.9.2
end of initial driving.
- Re-drive Production Pile; After 1 working day following the initial - 20 feet piling furnished bid price 455-11.9.3
driving day.
Dynamic Load Tests
- Test Piles: Prices include instrumentation, materials and labor. - No Payment 455-11.5
455-12.5.1
- Production piles: Authorized by the Engineer for hooking up - 20 feet piling furnished bid price 455-11.5
the instrument and begin driving
Splices
Test Piles
- Splice Length Authorized Non driven - Length in feet of production pile bid price 455-11.8
- Splice Length Authorized - Driven for test purposes only - Length in feet of Test pile bid price 455-11.8
- Splice (Material and Labor) - 20 feet Production Pile bid price 455-11.8
- Driving of Splice - No Payment 455-11.2.6
Production Pile
- Splice Length Authorized - Length in feet of Production Pile bid price 455-11.8
- Driving of production pile splice - No Payment 455-11.2.6
- Splice (Material and Labor) - 20 feet Production Pile bid price 455-11.8
Static Load Tests
- static Load Tests - Static Load test bid price 455-11.12
Preforming - 30% of piling per foot 455-11.13