Phase -I Works
1. Intake Wells
The Superintending Engineer has reviewed the progress of Intake wells in
SRSP Adilabad ,Komarambheem ,Yellampally & Kaddam Segments . The
agency has explained the progress of each component and informed that all
works will be completed by March 2017.
The Superintending Engineer Nirmal has instructed the agency to
complete all civil works by March 2017, except rapid sand filter and
back wash water tank.
3.Pumping Main .
Pipe line in KM Valves
Sl. Procur Balan Procu Fixed
Descriptio Total L&J
No ed ce Total red
n Lengt Comple
. Lengt Valve
h in ted in
h in s
Km KM
KM
SRSP
1 19.8 19.8 19.8 0 42 42 0
Adilabad
Komaram
2 0.18 0.18 0.18 0 0 0 0
bheem
Total
1. SRSP Adilabad
A)Pipeline
The Superintending Enginer, TDWSP Nirmal has reviewed the Progress
on each component of SRSP-Adilabad segment.
Further SE,TDWSP Nirmal has reviewed the Pipeline Status in terms of
Procured ,Laid and balance Quantities .The Executive Engineer, Dy.EES
and Project Manager, MEIL has explained the Progress of MS,DI and
HDPE Pipelines.
Total
B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .
Type Milesto Not Target
No of
Sl.N of ne Complet Progr Start date of
Struct
o Struct ed ess ed complet
ures
ure ion
1 Sump III 22 10 9 3 June-17
Sumps IV 30 3 19 8 Sept-17
2 OHBR III 8 1 7 0 June-17
OHBR IV 10 0 7 3 Sept-17
3 GLBR IV 5 0 3 2 Sept-17
TOTAL 75 14 45 16
5. CROSSINGS:
The SE,TDWSP Nirmal has reviewed the status of all crossings under SRSP
ADilabad segment
Permission
1 NH(R&B) 13 7 0 6
accorded
Permssion
2 NHAI 29 0 1 28
accorded
Permssion
3 R&B 198 19 1 178
accorded
Permssion
4 Railways 7 0 1 6
accorded
Permssion
5 Canal 15 8 7 0
accorded
Major Permssion
6 0 - - -
Rivers accorded
Forest Permissions
Man power/Machinery
Sno Type Machinery Man Power Total No of Techni Remar
of Engaged(Nos) Engaged(Batches Manpower cal ks
Work ) working Staff
1 MS 13 6 92 5
2 DI 21 15 77 6
3 HDPE 17 17 67 11
4 Sump 21 8 13 3
5 OHBR 8 5 48 4
6 GLBR 1 1 10 1
7 WTP 1 - 110 6
8 Intake 1 - 20 2
1. Yellampally Segment
A)Pipeline
The Superintending Enginer, TDWSP Nirmal has reviewed the Progress
on each component of Yellamapally segment.
Further SE,TDWSP Nirmal has reviewed the Pipeline Status in terms of
Procured ,Laid and balance Quantities .The Executive Engineer, Dy.EES
and Project Manager, MEIL has explained the Progress of MS,DI and
HDPE Pipelines.
Total
The Agency has explained that the major parts of Pipeline is falling in
rock area hence, SE TDWSP Nirmal has reviewed in detail about laying
of pipeline in such areas. The following details has been submitted by
the agency in this regard.
B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .
. CROSSINGS:
Permission
1 NH 23 0 0 0
accorded
Permssion
2 R&B 18 0 8 0
accorded
Permssion
3 Railways 2 0 2 0
accorded
Permssion
4 Canal 31 1 3 0
accorded
Major Permssion
5 0 0 0 0
Rivers accorded
Total 74 1 13 0
6. Forest
Sn Ext. Structures in Pipeline in Forest
o of Forest
Segmen
Sub Segment Land Status Total Grounde Total in Laidin
t
in Ha d Kms Kms
Req.
Yellampa 23/1 Dharmaram Stage I 1 1 44.69 2.25
3.645
1 lly Gutta-RF Approved
Yellampa 23/2 Srirampur- 0 0 20.90 1.95
3.822 TS Govt Level
2 lly RF
Yellampa 23/3 Kotapally- TS Govt Level 1 1 10.61 1.75
3.386
3 lly WL/RF
Total
Manpower Details
1. Kadam Segment
A)Pipeline
The Superintending Enginer, TDWSP Nirmal has reviewed the Progress
on each component of Kadam segment.
Further SE,TDWSP Nirmal has reviewed the Pipeline Status in terms of
Procured ,Laid and balance Quantities .The Executive Engineer, Dy.EES
and Project Manager, MEIL has explained the Progress of MS,DI and
HDPE Pipelines.
22.63 518.6 0
Total 540.3 29.623 1465
1 69
SE TDWSP Nirmal instructed to the agency to accelerate the Progress in
pipe line by increasing the work force to complete within the Target
date.
The Agency has explained that the major parts of Pipeline is falling in
rock area hence, SE TDWSP Nirmal has reviewed in detail about laying
of pipeline in such areas. The following details has been submitted by
the agency in this regard.
B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .
. CROSSINGS:
The Superintending Engineer has reviewed the status of all crossings
under Kadam Segment.
1 NH 0 0 0 0 Permission accorded
6. Forest
Sn Ext. Structures in Pipeline in Forest
o of Forest
Segmen
Sub Segment Land Status Total Grounde Total in Laidin
t
in Ha d Kms Kms
Req.
20.41 7 0 169.00 0
Kadem 24-Kadem-WL/RF TS Govt Level
1 8
Manpower Details
Total
Total
B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .
. CROSSINGS:
total
Type of Compl Progre Not
Sn
Crossing eted ss Star Remarks
o
s Nos Nos ted
1 NH
2 R&B
3 Railways
4 Canal
Major
5
Rivers
Total
6. Forest
Sn Ext. Structures in Pipeline in Forest
o of Forest
Segmen
Sub Segment Land Status Total Grounde Total in Laidin
t
in Ha d Kms Kms
Req.
SRSP- Forwarded to 1 1 34.147 8.40
21/7- Madegaon-RF 4.945
1 Adilabad PCCF
SRSP- 2 2 20.83 0
21/1- Mavala-RF 4.145 Stage I approved
2 Adilabad
SRSP- 21/2 - Chenchughat- 6 4 44.69 2.25
4.698 Stage I approved
3 Adilabad RF
SRSP- 21/3 Babulodhole- 3 2 20.90 1.95
3.623 Stage I approved
4 Adilabad RF
SRSP- Stage I approved 1 1 10.61 1.75
21/4 Arepally-RF 3.838
5 Adilabad
SRSP- 21/5 - Neredi 2 2 15.64 3.65
3.06 Stage I approved
6 Adilabad gonad-RF
SRSP- 21/6 - Kartha wada- Stage I approved 0 0 24.62 2.95
3.029
7 Adilabad RF
SRSP- 21/8 Srichelma- 4.737 Forwarded to 0 0
8 Adilabad WL Central 40.11 0
Board(WL)
Total
Manpower Details