Minutes of Meeting on Mission Bhagiratha Review meeting

conducted by Superintending Engineer at TDWSP Circle Nirmal held


on 15/03/2017

Officers Present :- Sri N Prasad Reddy, SE,TDWSP Nirmal .


Sri.P.Krishna Reddy , EE, TDWSP,Nirmal .
Sri. G.Venkata Ramana ,EE, TDWSP, Asifabad.
K. Madhusudhan, Dy.EE, TDWSP Adilabad
A.Sandeep ,Dy.EE, TDWSP ,Ichoda
M.Anjan Kumar, Dy.EE, TDWSP, Nirmal
K.V.G.Krishna, Dy.EE, TDWSP, Mancherial
K.Venkatapathi Dy.EE,TDWSP,Kadam
M.Sandeep,Dy.EE, TDWSP,ASifabad
P.Nageshwara Rao,Dy.EE TDWSP,Khagaznagar.
Mr. Ramesh Reddy. Sr.Project Manager, MEIL.
Mr.Subramani, Project Manager, L&T Ltd
All Project Managers and Deputy Project Managers of
Agencies.

The Superintending Engineer,TDWSP Nirmal has critically reviewed the


progress in detail on Mission Bhagiratha Project and instructed to achieve the mile
stones as per the targets communicated below.

Phase -I Works
1. Intake Wells
The Superintending Engineer has reviewed the progress of Intake wells in
SRSP Adilabad ,Komarambheem ,Yellampally & Kaddam Segments . The
agency has explained the progress of each component and informed that all
works will be completed by March 2017.
The Superintending Engineer Nirmal has instructed the agency to
complete all civil works by March 2017, except rapid sand filter and
back wash water tank.

Sl. Descripti Components Components Pending


No on Completed
Civil Works of Intake Finishings in Trashrack,Back side Railing
SRSP Structure,Appraoch ,Inside Flooring ,Outside Wearing Coat ,Foot
1
Adilabad Bridge ,Apraoch Bridge Wearing Coat ,Approach road
Road . retaining wall stone pitching
Civil Works of Intake Finsihing Works , Stari case in Intake,Trash
Komaram Structure,Appraoch Racks, Railing works ,Wearing coats,Inside
2
bheem Bridge ,Apraoch Flooring
Road .
Yellampall Approach Bridge Finishing works, Intake Well Brick work,
y trashrack, flooring, Retaining wall stone
3
Mancheri pitching, Wearing coat on approach bridge
al
4 Kaddam All Civil Works Finishing works ,Trash rack (3rd) ,Wearing
coat in intake and Approach road ,Approach
Road ,Retaining Wall and

2.Water Treatment Plants


S Descripti Components Components Pending
l. on Completed
N
o
Aerator,Stilling RSF -Inside Plastering for troughs ,Doors
Chamber,Pharshal Windows, Tiles and RSF to Sump Inlet,
Flume, Flash Electromechanical items Pipes,Valves and
Mixers,Clarifloccultors flooring . Pumphouse- Roof
, Slab,Brick works,Flooring Doors,Windows .
SRSP
1 Chemical&Chlorinatio Clear Water Sump Wearing coat for
Adilabad
n House are Raft ,Top Wearing Coat,Flooring & Finishing
completed in full works .Watchman Quarter . Internal Roads
shape including & Compound Wall .
Electro Mechanical
Works .
Aerator, Stilling Finishing,Painting,Hand Railing are in
Chamber,Pharshal Progress Clear Water Sump - Wearing
Flume, Flash coat for Raft ,Top Wearing Coat,Flooring &
Mixers,Clarifloccultors Finishing works . RSF Brick Work,
Komaram , Plastering,Doors Windows, Tiles and RSF
2
bheem Chemical&Chlorinatio to Sump Inlet, Electromechanical items
n House are Pipes,Valves and flooring .Pump House
completed in full Side Wall, Roof Slab,Brick works,Flooring
shape including Doors,Windows .
Electro Mechanical
Civil work of Aerator, Aerator Tiles work, Chemical & Chlorine
Stilling Chamber, House Plastering, Painting, Flooring work.
Yellampall
Flash Mixers, Pharshal Flume, CLF- Electromechanical
y
3 Clariflocculators, work, RSF Brick work, Wash water tank,
Mancheri
Clear water Sump, Plastering, Doors, Windows, Valves, Pump
al
Compound wall House Flooring, Doors, Windows
completed
Civil works RSF brick work, Plastering for troughs
Aerator,Stilling ,Doors Windows, Tiles and RSF to Sump
Chamber, , Inlet, Electromechanical items
Clarifloccultors, Pipes,Valves and flooring. Pumphouse-
Chemical&Chlorinatio Roof Slab,Brick works,Flooring
4 Kaddam
n House full shape Doors,Windows . Clear Water Sump
clear water sump, Wearing coat for Raft ,Top Wearing
Coat,Flooring & Finishing works
.Watchman Quarter , Internal Roads, Storm
water drains.

3.Pumping Main .
Pipe line in KM Valves
Sl. Procur Balan Procu Fixed
Descriptio Total L&J
No ed ce Total red
n Lengt Comple
. Lengt Valve
h in ted in
h in s
Km KM
KM
SRSP
1 19.8 19.8 19.8 0 42 42 0
Adilabad
Komaram
2 0.18 0.18 0.18 0 0 0 0
bheem

3 Yellampally 0.83 0 0 0.83 0 0 0

4 Kaddam 1.20 1.20 1.05 0.15 6 6 0

Total

Phase -II Works

1. SRSP Adilabad
A)Pipeline
The Superintending Enginer, TDWSP Nirmal has reviewed the Progress
on each component of SRSP-Adilabad segment.
Further SE,TDWSP Nirmal has reviewed the Pipeline Status in terms of
Procured ,Laid and balance Quantities .The Executive Engineer, Dy.EES
and Project Manager, MEIL has explained the Progress of MS,DI and
HDPE Pipelines.

Type Pipe line in KM Valves


of Procur Balan Procu Fixed
Sl. Pipe Total L&J
Descriptio ed ce Total red
No Lengt Comple
n Lengt Valve
. h in ted in
h in s
Km KM
KM
MS 102.04 53.456 34.497 67.543 102 0 0
DI 653.57
925.75 485.916 272.171 811 0 0
9
SRSP
1 HDPE 1376.4 1134.0
Adilabad 354.38 242.373 1793 0 0
0 27
BWSC
18.70 0 0 18.70 47 0 0

2422.89 893.75 1873.84 0


Total 0 2 549.041 9
SE TDWSP Nirmal instructed to the agency to accelerate the Progress in
pipe line by increasing the work force to complete within the Target
date.
At present 6 Batches for MS pipline is engaged and No valves are
Procured .
There are no Separate batches for construction of Pedestals it is
instructed by SE TDWSP Nirmal to increase batches in all aspects of
Laying MS Pipeline .
The Agency has explained that the major parts of Pipeline is falling in
rock area hence, SE TDWSP Nirmal has reviewed in detail about laying
of pipeline in such areas. The following details has been submitted by
the agency in this regard.
DI pipeline stretch in Ichoda SD is around 216 Kms out of Which 144
Kms is expected to come under Hard rock strata .The SE TDWSP Nirmal
has instructed to finish the DI line in clear stretches first and Increase
the Batches for the DI lines .
There is no Procurement of Valves in done till date for the Total Segment
of SRSP Adilabad hence it has been instructed to expedite the
procurement process .

Type Hard rock Details Pedestals


of Lengt Compl Progre
Sl Pipe Total
Total h in eted ss
. Descriptio Pedes
N n Lengt Hard Complete Progre
tals
o. h in rock d ss
Requir
Km portio ed
n
MS
DI
SRSP
1 HDPE
Adilabad
BWSC

Total

B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .
Type Milesto Not Target
No of
Sl.N of ne Complet Progr Start date of
Struct
o Struct ed ess ed complet
ures
ure ion
1 Sump III 22 10 9 3 June-17
Sumps IV 30 3 19 8 Sept-17
2 OHBR III 8 1 7 0 June-17
OHBR IV 10 0 7 3 Sept-17
3 GLBR IV 5 0 3 2 Sept-17
TOTAL 75 14 45 16

5. CROSSINGS:

The SE,TDWSP Nirmal has reviewed the status of all crossings under SRSP
ADilabad segment

Type of total Compl Progre Not


Sn
Crossing eted ss Star Remarks
o
s Nos Nos ted

Permission
1 NH(R&B) 13 7 0 6
accorded

Permssion
2 NHAI 29 0 1 28
accorded

Permssion
3 R&B 198 19 1 178
accorded

Permssion
4 Railways 7 0 1 6
accorded

Permssion
5 Canal 15 8 7 0
accorded

Major Permssion
6 0 - - -
Rivers accorded

Total 262 34 10 218

Forest Permissions

Sn Ext. Structures in Pipeline in Forest


o of Forest
Segmen
Sub Segment Land Status Total Grounde Total in Laidin
t
in Ha d Kms Kms
Req.
SRSP- Forwarded to 1 1 34.147 8.40
21/7- Madegaon-RF 4.945
1 Adilabad PCCF
SRSP- 2 2 20.83 0
21/1- Mavala-RF 4.145 Stage I approved
2 Adilabad
SRSP- 21/2 - Chenchughat- 6 4 44.69 2.25
4.698 Stage I approved
3 Adilabad RF
SRSP- 21/3 Babulodhole- 3 2 20.90 1.95
3.623 Stage I approved
4 Adilabad RF
Sn Ext. Structures in Pipeline in Forest
o Segmen of Forest
Sub Segment Land Status
t Total Grounde Total in Laidin
in Ha d Kms Kms
Req.
SRSP- Stage I approved 1 1 10.61 1.75
21/4 Arepally-RF 3.838
5 Adilabad
SRSP- 21/5 - Neredi 2 2 15.64 3.65
3.06 Stage I approved
6 Adilabad gonad-RF
SRSP- 21/6 - Kartha wada- Stage I approved 0 0 24.62 2.95
3.029
7 Adilabad RF
SRSP- 21/8 Srichelma- 4.737 Forwarded to 0 0
8 Adilabad WL Central 40.11 0
Board(WL)
Total

Man power/Machinery
Sno Type Machinery Man Power Total No of Techni Remar
of Engaged(Nos) Engaged(Batches Manpower cal ks
Work ) working Staff

1 MS 13 6 92 5

2 DI 21 15 77 6

3 HDPE 17 17 67 11

4 Sump 21 8 13 3

5 OHBR 8 5 48 4

6 GLBR 1 1 10 1

7 WTP 1 - 110 6

8 Intake 1 - 20 2
1. Yellampally Segment
A)Pipeline
The Superintending Enginer, TDWSP Nirmal has reviewed the Progress
on each component of Yellamapally segment.
Further SE,TDWSP Nirmal has reviewed the Pipeline Status in terms of
Procured ,Laid and balance Quantities .The Executive Engineer, Dy.EES
and Project Manager, MEIL has explained the Progress of MS,DI and
HDPE Pipelines.

Type Pipe line in KM Valves


of Procur Balan Procu Fixed
Sl. Pipe Total L&J
Descriptio ed ce Total red
No Lengt Comple
n Lengt Valve
. h in ted in
h in s
Km KM
KM
MS 18.73 18.53 1.83 16.7 55 0 0
DI 146.77 114 101.868 12.132 393 10 0
Yellampally
1 HDPE 395.12 52 41.85 10.15 1214 401 0
-Mancherial
BWSC
0 0 0 0 0 0 0

Total 560.62 184.53 145.548 38.982 1662 411


SE TDWSP Nirmal instructed to the agency to accelerate the Progress in
pipe line by increasing the work force to complete within the Target
date.
Type Hard rock Details Pedestals
of Lengt Compl Progre
Sl Pipe Total
Total h in eted ss
. Descriptio Pedes
N n Lengt Hard Complete Progre
tals
o. h in rock d ss
Requir
Km portio ed
n
MS 18.73 0.74 0 300 0 6
Yellampally DI
1 146.77 0.809 0.439 0 0 0
-Mancherial
HDPE 395.12 8.0 0 0 0 0
BWSC
0 0 0 0 0 0

Total
The Agency has explained that the major parts of Pipeline is falling in
rock area hence, SE TDWSP Nirmal has reviewed in detail about laying
of pipeline in such areas. The following details has been submitted by
the agency in this regard.

B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .

Type of No of Not Target date


Sl.N Complet Progre
Structu Structu Starte of
o ed ss
re res d completion
1 Sump 11 2 8 1 31-05-2017
2 OHBR 2 0 2 0 31-05-2017
3 GLBR 1 1 0 0 Completed
TOTAL 11 2 8 1

. CROSSINGS:

The Superintending Engineer has review the status of Crossings in


Yellampally Segment .
The Details of Crossings furnished are as follows .

Type of total Compl Progre Not


Sn
Crossing eted ss Star Remarks
o
s Nos Nos ted

Permission
1 NH 23 0 0 0
accorded

Permssion
2 R&B 18 0 8 0
accorded

Permssion
3 Railways 2 0 2 0
accorded

Permssion
4 Canal 31 1 3 0
accorded

Major Permssion
5 0 0 0 0
Rivers accorded

Total 74 1 13 0

6. Forest
Sn Ext. Structures in Pipeline in Forest
o of Forest
Segmen
Sub Segment Land Status Total Grounde Total in Laidin
t
in Ha d Kms Kms
Req.
Yellampa 23/1 Dharmaram Stage I 1 1 44.69 2.25
3.645
1 lly Gutta-RF Approved
Yellampa 23/2 Srirampur- 0 0 20.90 1.95
3.822 TS Govt Level
2 lly RF
Yellampa 23/3 Kotapally- TS Govt Level 1 1 10.61 1.75
3.386
3 lly WL/RF
Total

Manpower Details

S Type Length/N Machi Man Total Technical Remarks


n of os nery Power No of Staff
o Work Engag Engage Manp
ed(No d(Batc ower
s) hes) worki
ng
1 MS 18.73 11 2 35 3
2 DI 146.77 17 8 59 9
3 HDPE 395.12 2 2 12 2
4 Sump 11 8 8 51 8
5 OHBR 2 2 2 23 1
6 GLBR 1 1 1 7 1
7 WTP 1 3 5 83 1
8 Intake 1 1 1 11 1
576.62 45 29 281 26

1. Kadam Segment
A)Pipeline
The Superintending Enginer, TDWSP Nirmal has reviewed the Progress
on each component of Kadam segment.
Further SE,TDWSP Nirmal has reviewed the Pipeline Status in terms of
Procured ,Laid and balance Quantities .The Executive Engineer, Dy.EES
and Project Manager, MEIL has explained the Progress of MS,DI and
HDPE Pipelines.

Type Pipe line in KM Valves


of Procur Balan Procu Fixed
Sl. Pipe Total L&J
Descriptio ed ce Total red
No Lengt Comple
n Lengt Valve
. h in ted in
h in s
Km KM
KM
MS 0 0 0 0 0 0 0
DI 133.26
155.9 29.623 22.631 551 0 0
Yellampally 9
1 HDPE
-Mancherial 358.1 0 0 358.1 914 0 0
GI
26.3 0 0 26.3 0 0 0

22.63 518.6 0
Total 540.3 29.623 1465
1 69
SE TDWSP Nirmal instructed to the agency to accelerate the Progress in
pipe line by increasing the work force to complete within the Target
date.
The Agency has explained that the major parts of Pipeline is falling in
rock area hence, SE TDWSP Nirmal has reviewed in detail about laying
of pipeline in such areas. The following details has been submitted by
the agency in this regard.

Type Hard rock Details Pedestals


of Lengt Compl Progre
Sl Pipe Total
Total h in eted ss
. Descriptio Pedes
N n Lengt Hard Complete Progre
tals
o. h in rock d ss
Requir
Km portio ed
n
MS 0 0 01 0 0 0 0
DI 155..9 30 0 0 2800 0 0
1 Kadam HDPE 358.1 68 0 0 0 0 0
BWSC
26.3 0 0 0 0 0 0

Total 540.3 98 0 0 2800 0

B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .

Type of No of Not Target date


Complete
Sl.No Structur Structur Progress Started of
d
e es completion
1 Sump 11 2 2 7 30-06-2017
2 OHBR 4 0 1 3 30-062017
3 GLBR 0 0 0 0 -
TOTAL 15 2 3 10

. CROSSINGS:
The Superintending Engineer has reviewed the status of all crossings
under Kadam Segment.

total Compl Progre Not


Type of
Sno eted ss Star Remarks
Crossings
Nos Nos ted

1 NH 0 0 0 0 Permission accorded

2 R&B 80 1 0 79 Permssion accorded

3 Railways 0 0 0 0 Permssion accorded

4 Canal 80 0 0 80 Permssion accorded

5 Major Rivers 18 0 0 18 Permssion accorded

Total 178 1 0 177

6. Forest
Sn Ext. Structures in Pipeline in Forest
o of Forest
Segmen
Sub Segment Land Status Total Grounde Total in Laidin
t
in Ha d Kms Kms
Req.
20.41 7 0 169.00 0
Kadem 24-Kadem-WL/RF TS Govt Level
1 8

Manpower Details

S Type Length/N Machi Man Total Technical Remarks


n of os nery Power No of Staff
o Work Engag Engage Manp
ed(No d(Batc ower
s) hes) worki
ng
1 MS 0 0 0 0 0 0
2 DI 159.90 6 3 10 3 159.90
3 HDPE 358.10 0 0 0 0 358.10
4 Sump 11 0 1 10 1 11
5 OHBR 4 0 0 0 0 4
6 GLBR 0 0 0 0 0 0
7 WTP 1 2 4 90 3 1
8 Intake 1 1 1 15 1 1
Total 9 9 125 8 Total
1.Komaram Bheem Segment
A)Pipeline
The Superintending Enginer, TDWSP Nirmal has reviewed the Progress
on each component of Kadam segment.
Further SE,TDWSP Nirmal has reviewed the Pipeline Status in terms of
Procured ,Laid and balance Quantities .The Executive Engineer, Dy.EES
and Project Manager, MEIL has explained the Progress of MS,DI and
HDPE Pipelines.

Type Pipe line in KM Valves


of Procur Balan Procu Fixed
Sl. Pipe Total L&J
Descriptio ed ce Total red
No Lengt Comple
n Lengt Valve
. h in ted in
h in s
Km KM
KM
MS 36.79 36.79 26.75 10.04 78 78 0
DI 1024.8
742 541.90 2985 2320 6
0
Komarambh
1 HDPE 1733.0 1645.3
eem 261.35 88.00
3 2
BWSC
9.40 9.40 6.00 3.4

Total

SE TDWSP Nirmal instructed to the agency to accelerate the Progress in


pipe line by increasing the work force to complete within the Target date
and to increase the man power and Machinery in laying of HDPE Pipes .
Per day target for laying of pipeline is around 20 Kms to reach the taget
by jun 2017
Canal Crossing near WTP to be sorted out immediately .
All the pipeline stretches which are clear in all aspects are tobe taken up
immediately .
The Agency has explained that the major parts of Pipeline is falling in
rock area hence, SE TDWSP Nirmal has reviewed in detail about laying
of pipeline in such areas. The following details has been submitted by
the agency in this regard.
Duct chambers must be taken up simultaneously with OFC laying.
Pipelines in Agriculture lands must be expedited within the summer
season to avoid further delay in work.

Type Hard rock Details Pedestals


of Lengt Compl Progre
Sl Pipe Total
Total h in eted ss
. Descriptio Pedes
N n Lengt Hard Complete Progre
tals
o. h in rock d ss
Requir
Km portio ed
n
MS
DI
Komarambh
1 HDPE
eem
BWSC

Total

B) Structures
The Superintending Engineer, TDWSP Nirmal has reviewed the Progress
on each and every structure of SRSP-Adilabad segment in detail .

Type of No of Not Target date


Sl.N Complet Progre
Structu Structu Starte of
o ed ss
re res d completion
1 Sump
2 OHBR
3 GLBR
TOTAL

. CROSSINGS:

The Superintending Engineer has reviewed the status of all crossings


under Komarambheem, Segment.

total
Type of Compl Progre Not
Sn
Crossing eted ss Star Remarks
o
s Nos Nos ted

1 NH

2 R&B

3 Railways

4 Canal

Major
5
Rivers

Total

6. Forest
Sn Ext. Structures in Pipeline in Forest
o of Forest
Segmen
Sub Segment Land Status Total Grounde Total in Laidin
t
in Ha d Kms Kms
Req.
SRSP- Forwarded to 1 1 34.147 8.40
21/7- Madegaon-RF 4.945
1 Adilabad PCCF
SRSP- 2 2 20.83 0
21/1- Mavala-RF 4.145 Stage I approved
2 Adilabad
SRSP- 21/2 - Chenchughat- 6 4 44.69 2.25
4.698 Stage I approved
3 Adilabad RF
SRSP- 21/3 Babulodhole- 3 2 20.90 1.95
3.623 Stage I approved
4 Adilabad RF
SRSP- Stage I approved 1 1 10.61 1.75
21/4 Arepally-RF 3.838
5 Adilabad
SRSP- 21/5 - Neredi 2 2 15.64 3.65
3.06 Stage I approved
6 Adilabad gonad-RF
SRSP- 21/6 - Kartha wada- Stage I approved 0 0 24.62 2.95
3.029
7 Adilabad RF
SRSP- 21/8 Srichelma- 4.737 Forwarded to 0 0
8 Adilabad WL Central 40.11 0
Board(WL)
Total

Manpower Details

S Type Length/N Machi Man Total Technical Remarks


n of os nery Power No of Staff
o Work Engag Engage Manp
ed(No d(Batc ower
s) hes) worki
ng
1 MS
2 DI
3 HDPE
4 Sump
5 OHBR
6 GLBR
7 WTP
8 Intake
Total