Professional Documents
Culture Documents
Name of Work :- Mission Kakatiya - Minor Irrigation - Phase.III - Rekulacheru, Kunepally(V), Renjal (M),
Nizamabad( Dist ).
1 BUND 1085861.00
2 SLUICE 876138.00
3 WEIR 684962.00
total 3566448.00
TOTAL 4180906.00
35.25
Page 1 of 44
ABSTRACT
Name of Work :- Mission Kakatiya - Minor Irrigation - Phase.III - Rekulacheru, Kunepally(V), Renjal (M), Nizamabad( Dist).
1 Sub-Head : BUND
Clearing thick jungle growth ( less than 50 percent open space ) including
1 bushes upto 30 cm / parthenium and other weeds including burning or disposing 14250.000 2.20 Sqm 31350.00
off the same as directed etc., complete.
Excavation in all kinds of soil including boulders upto 0.3 m diameter for removal
of silt from Tank Bed required level and profile, cost of all materials, machinery,
2 labour, placing the excavated soil neatly in dump area or for the formation of 570.000 51.80 Cum 29526.00
service road/ emabankment as directed etc., complete with lead up to 10m and
lift upto 3m. Stripping
3 Benching old embankment slopes 0.45 x 0.45 for benching 3800.000 5.70 Rmt 21660.00
Providing homogeneous embankment using soil from approved borrow area in
layers of 25 to 30 cm before compaction including cost of all materials,
machinery, labour, all operations such as excavation, sorting out, transportation,
4 spreading soil in layer of specified thickness, breaking clods, sectioning, 5437.000 171.00 Cum 929727.00
watering, compacting to density control of not less than 95 percent or as
stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost
6 of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing 9.000 4818.00 Cum 43362.00
in position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.IRR-CCDW-2-5
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
7 machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, 5.810 5124.00 Cum 29770.00
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. IRR DAW 2-5
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost
2 of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing 34.920 4818.00 Cum 168245.00
in position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts. IRR-CCDW-2-5
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
3 machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, 92.970 5124.00 Cum 476378.00
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. IRR DAW 2-5
Page 2 of 44
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for deck slab & kerb including cost of
5 all materials,machinery, labour, formwork, scaffolding, cleaning, batching, 9.720 8702.00 Cum 84583.00
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (IRR - CCDW-2 -24).
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost
2 of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing 74.710 4818.00 Cum 359953.00
in position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.IRR-CCDW-2-5
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
3 machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, 40.980 5124.00 Cum 209982.00
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. IRR DAW 2-5
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for wearing coat including cost of all
materials,machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
4 placing in position, levelling, vibrating, finishing, curing etc., complete with initial 20.250 5335.00 Cum 108034.00
lead upto 50 m and all lifts. (IRR - CCDW-2 -26).
Page 3 of 44
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for foundation filling including cost
3 of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing 63.000 4818.00 Cum 303534.00
in position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.IRR-CCDW-2-5
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
4 machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, 37.500 5124.00 Cum 192150.00
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. IRR DAW 2-5
Excavation in all kinds of soil including boulders upto 0.3 m diameter for removal
of silt from Tank Bed required level and profile, cost of all materials, machinery,
4 labour, placing the excavated soil neatly in dump area or for the formation of 1500.000 40.00 Cum 60000.00
service road/ emabankment as directed etc., complete with lead up to 10m and
lift upto 3m. For Trench cutting
Sub- Total 396000.00
Excavation in all kinds of soil including boulders upto 0.3 m diameter for removal
of silt from Tank Bed required level and profile, cost of all materials, machinery,
1 labour, placing the excavated soil neatly in dump area or for the formation of 8400.000 31.50 cum 264600.00
service road/ emabankment as directed etc., complete. (Desilting)
Page 4 of 44
D A T A
Name of the Work :- Chinna Neeti Vanarula Punaruddarana - Nalla cheru (Kalan talab), Kotagiri
(V&M), Nizamabad Dist.
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated soil
neatly in dump area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts. IRR-CAW-1-1
DATA: RATE ANALYSIS UNIT : 832.00 cum
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 937.80 7502.40
2 Tippers 5 cum capacity 6 Nos Hour 48.00 446.70 0.00
Fuel / Energy charges Hour 48.00 322.20 0.00
Total hire charges of Machinery Rs: 21155.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 204.10 1632.80
2 Crew for Tipper Hour 48.00 153.10 0.00
3 work inspector Day 1.00 370.00 370.00
4 mazdoor Day 30.00 295.00 0.00
Total cost of Labour Rs: 2002.80
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 21155.20
C. Cost of Labour Rs: 2002.80
Total Rs: 23158.00
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 3140.22
Total cost for 832.00 cum Rs: 26298.22
Rate per cum (A+B+C+D)/925 Rs. 31.60
2 DISMANTLING clearing away and carefully stacking materials useful for reuse.
Stone masonry in cement mortar 1 Cum Rs. 305.00
Page 5 of 44
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 42.70
BMT-R.01-805 Total Rs. 347.70
Clearing thick jungle growth ( less than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same as
directed etc., complete. IRR-PMW-1-2
DATA: RATE ANALYSIS UNIT : 1000 sqm
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 370.00 185.00
2 mazdoor Day 5.00 295.00 1475.00
Total cost of Labour Rs: 1660.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1660.00
Total Rs: 1660.00
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 225.10
Total cost for 1000.00 sqm Rs: 1885.10
Rate per sqm (A+B+C+D)/1000.0 Rs. 1.90
Page 6 of 44
in Rs. in Rs.
work inspector day 0.32 370.00 118.40
Mazdoor day 8.00 295.00 2360.00
crew for excavator hour 6.00 204.10 1224.60
Total in Rs. 3703.00
Abstract
a) Material Rs 0.00
b) Machinery Rs 15866.40
c) Labour Rs 3703.00
Total Rs 19569.40
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 2653.61
Total cost for 240.00 cum Rs: 22223.01
Rate per cum (A+B+C+D)/240.0 Rs. 92.60
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.25 370.00 92.50
2 mazdoor Day 4.00 295.00 1180.00
Total cost of Labour Rs: 1272.50
ABSTRACT:
A. Cost of Materials Rs: 5386.50
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1272.50
Total Rs: 6659.00
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 932.26
Total cost for 15.00 cum Rs: 7591.26
E. Lead Charges / Seioniorage charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Sand cum 15.750 147.10 2316.83
3 Seioniorage charges cum 15.750 40.00 630.00
2946.83
10538.09
Page 7 of 44
Rate per cum (A+B+C+D)/15.0 Rs. 702.50
3 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) IRR-CCDW-2-5
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 85.30 682.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 85.30 42.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
Fuel / Energy charges Hour 1.00 322.20 322.20
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 21.50 172.00
Total hire charges of Machinery Rs: 2115.65
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 189.80 1518.40
2 Crew for Pump Hour 0.50 96.10 48.05
3 Crew for Water tanker Hour 1.00 153.10 153.10
4 Crew for Vibrator Hour 8.00 136.60 1092.80
5 Mason Class-I Day 1.00 385.00 385.00
6 work inspector Day 1.00 370.00 370.00
7 mazdoor
for batching materials Day 11.00 295.00 3245.00
Page 8 of 44
for loading mortar pans Day 4.00 295.00 1180.00
for laying Day 3.00 295.00 885.00
for conveying concrete Day 16.36 295.00 4826.20
8 for cleaning/ washing/ curing Day 1.00 295.00 295.00
9 Labour cost for shuttering sqm 16.36 75.30 1231.91
Total cost of Labour Rs: 15230.46
ABSTRACT:
A. Cost of Materials including seignorage charges Rs: 46107.77
B. Hire charges of Machinery Rs: 2115.65
C. Cost of Labour Rs: 15230.46
Total Rs: 63453.88
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 8604.35
Total cost for 16.36 cum Rs: 72058.23
E. Seignorage charges /Lead Charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
Lead Charges
1 Sand cum 6.544 147.10 962.62
2 Metal cum 14.724 399.10 5876.35
Seignorage charges
1 Sand cum 6.544 40.00 261.76
2 Metal cum 14.724 50.00 736.20
7836.93
Total cost for 16.36 cum Rs: 79895.16
Rate per cum (A+B+C+D+E)/16.36 Rs. 4883.60
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
Page 9 of 44
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.0 51.70 413.60
Fuel / Energy charges Hour 8.0 38.00 304.00
2 10 hp pump ( ele ) Hour 1.0 6.70 6.70
Fuel / Energy charges Hour 1.0 76.10 76.10
3 Needle vibrator 40 mm dia ( ele ) Hour 8.0 8.00 64.00
Fuel / Energy charges Hour 8.0 7.60 60.80
Total hire charges of Machinery Rs: 925.20
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 189.80 1518.40
2 Crew for Pump Hour 1.00 72.10 72.10
3 Crew for Needle vibrator Hour 8.00 136.60 1092.80
4 Mason Class-I Day 1.00 385.00 385.00
5 mazdoor 0.00
for batching cement ( cement handling Day 2.00 295.00 590.00
for batching other materials Day 9.00 295.00 2655.00
for loading mortar pans Day 4.00 295.00 1180.00
for laying Day 3.00 295.00 885.00
for conveying concrete Day 14.00 295.00 4130.00
for cleaning / washing / curing Day 1.00 295.00 295.00
6 Labour cost of shuttering sqm 14.00 75.30 1054.20
7 Labour cost of scaffolding @ 15% 0.00
Total cost of Labour Rs: 13857.50
ABSTRACT:
A. Cost of Materials Rs: 42896.92
B. Hire charges of Machinery Rs: 925.20
C. Cost of Labour Rs: 13857.50
Total Rs: 57679.62
D.Add for contractor's profit and overheads on (A+B+C) 13.56% Rs. 7821.36
Lead Charges for 1 Km for FA 5.60 cum @ 31.5 Rs./Cum 176.40
Lead Charges for 1 Km for CA 12.60 cum @ 30.4 Rs./Cum 383.04
Lead Charges for 1Km for Cement (including Loadin 3.68 tonne @ 124.6 Rs./Ton 458.78
Total cost for 14.00 cum Rs: 66519.20
E. Seignorage charges /Lead Charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
Lead Charges
1 Sand cum 5.600 147.10 823.76
2 Metal cum 12.600 399.10 5028.66
Seignorage charges
1 Sand cum 5.600 40.00 224.00
2 Metal cum 12.600 50.00 630.00
6706.42
Total cost for 14.00 cum Rs: 73225.62
Rate per cum (A+B+C+D+E)/14.0 Rs. 5230.40
5 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /
sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for wearing coat including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
and all lifts. IRR-CCDW-2-26
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Page 10 of 44
DATA: RATE ANALYSIS UNIT : 15.76 cum
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement for mix kg 5200.80 5.80 30164.64
Cement for incidentals @ 5 kg / cum kg 78.80 5.80 457.04
2 Coarse aggregate 20-10 mm cum 8.20 1210.00 9916.19
Coarse aggregate 10 mm below cum 4.41 875.00 3861.20
3 Fine aggregate (Un-Screened) cum 7.09 462.00 3276.50
4 Super Plasticizer kg 20.80 80.00 0.00
5 Use rate of shuttering sqm 7.88 244.56 1927.16
6 Sundries ( asphalt mortar etc ) LS 5.00 41.00 205.00
Total cost of Materials Rs: 49807.74
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 85.30 682.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 85.30 42.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 21.50 172.00
Total hire charges of Machinery Rs: 1390.95
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 189.80 1518.40
2 Crew for Pump Hour 0.50 96.10 48.05
3 Crew for Needle vibrator Hour 8.00 136.60 1092.80
4 Mason Class-I Day 2.00 385.00 770.00
5 work inspector Day 1.00 370.00 370.00
6 mazdoor
for batching materials Day 11.00 295.00 3245.00
for loading mortar pans Day 4.00 295.00 1180.00
for laying Day 4.00 295.00 1180.00
for conveying concrete Day 15.76 295.00 4649.20
for cleaning/ washing/ curing Day 2.00 295.00 590.00
7 Labour cost for shuttering sqm 7.88 75.30 593.36
Total cost of Labour Rs: 15236.81
ABSTRACT:
A. Cost of Materials Rs: 49807.74
B. Hire charges of Machinery Rs: 1390.95
C. Cost of Labour Rs: 15236.81
Total Rs: 66435.50
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 9008.65
Total cost for 15.76 cum Rs: 75444.15
E. Seignorage charges /Lead Charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
Lead Charges
1 Sand cum 7.092 147.10 1043.23
2 Metal cum 12.608 399.10 5031.85
Seignorage charges
1 Sand cum 7.092 40.00 283.68
2 Metal cum 12.608 50.00 630.40
6989.17
Page 11 of 44
82433.32
Rate per cum (A+B+C+D)/15.76 Rs. 5230.54
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum) IRR-CCDW-2-24
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 85.30 682.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 85.30 42.65
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 21.50 172.00
Total hire charges of Machinery Rs: 1390.95
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 189.80 1518.40
2 Crew for Pump Hour 0.50 96.10 48.05
3 Crew for Needle vibrator Hour 8.00 136.60 1092.80
4 Mason Class-I Day 2.00 385.00 770.00
5 work inspector Day 1.00 370.00 370.00
6 mazdoor 0.00
for batching materials Day 11.00 295.00 3245.00
for loading mortar pans Day 4.00 295.00 1180.00
for laying Day 4.00 295.00 1180.00
for conveying concrete Day 15.76 295.00 4649.20
for cleaning/ washing/ curing Day 1.00 295.00 295.00
7 Labour cost for shuttering sqm 39.40 75.30 2966.82
Labour cost for scaffolding @ 250% 7417.05
Total cost of Labour Rs: 24732.32
labour component/unit qty 1569.30
Add contractor's profit and overhead charges 0.14 219.70
labour component/unit qty (including contractor's profit) 1789.00
Page 12 of 44
ABSTRACT:
A. Cost of Materials Rs: 90413.24
B. Hire charges of Machinery Rs: 1390.95
C. Cost of Labour Rs: 24732.32
Total Rs: 116536.51
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 15802.35
Total cost for 15.76 cum Rs: 132338.86
E. Seignorage charges /Lead Charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
Lead Charges
1 Sand cum 7.092 147.10 1043.23
2 Metal cum 12.608 399.10 5031.85
Seignorage charges
1 Sand cum 7.092 40.00 283.68
2 Metal cum 12.608 50.00 630.40
6989.17
139328.03
Rate per cum (A+B+C+D)/15.76 Rs. 8840.60
Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts. IRR-CCDW-2-1
DATA: RATE ANALYSIS UNIT : 1000.00 kg
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Rein.Steel with 5 % wastage kg 1050.00 42.00 44100.00
2 Binding wire 1.25 mm dia kg 8.00 70.00 560.00
3 Sundries ( chairs / spacers etc ) LS 3.00 41.00 123.00
Total cost of Materials Rs: 44783.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 370.00 370.00
2 Bar bender Day 6.00 450.00 2700.00
3 mazdoor Day 11.00 295.00 3245.00
Total cost of Labour Rs: 6315.00
labour component/unit qty 6.30
Add contractor's profit and overhead charges 0.14 0.90
labour component/unit qty (including contractor's profit) 7.20
ABSTRACT:
A. Cost of Materials Rs: 44783.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 6315.00
Total Rs: 51098.00
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 6928.89
Total cost for 1000.00 kg Rs: 58026.89
Page 13 of 44
Rate per kg (A+B+C+D)/1000.0 Rs. 58.03
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 5.40 1715.50 9263.70
Fuel / Energy charges Hour 5.40 656.00 3542.40
2 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 937.80 7502.40
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 322.20 12888.00
4 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 38.00 152.00
5 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 322.20 2577.60
6 Vibratory Roller 8 tonne Hour 6.40 1342.20 8590.08
Fuel / Energy charges Hour 6.40 1108.30 7093.12
7 Sundries LS 2.00 41.00 82.00
Total hire charges of Machinery Rs: 86444.10
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 5.40 204.10 1102.14
2 Crew for Shovel Hour 8.00 204.10 1632.80
3 Crew for Tipper Hour 40.00 153.10 6124.00
4 Crew for Pump Hour 4.00 72.10 288.40
5 Crew for Water tanker Hour 8.00 153.10 1224.80
6 Crew for Roller Hour 6.40 227.80 1457.92
7 work inspector Day 2.00 370.00 740.00
8 mazdoor Day 4.00 295.00 1180.00
Total cost of Labour Rs: 13750.06
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 86444.10
C. Cost of Labour Rs: 13750.06
Total Rs: 100194.16
D.Add for contractor's profit and overheads on (A+B+C) 13.56% Rs. 13586.33
Total cost for 807.00 cum Rs: 113780.49
E. Lead Charges / Seioniorage charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
Page 14 of 44
1 Earth cum 807.000 71.50 57700.50
2 Deduct 1 km lead cum 807.000 -31.50 -25420.50
3 Seioniorage charges cum 807.000 22.00 17754.00
50034.00
Total cost for 807.00 cum Rs: 163814.49
Rate per cum (A+B+C+D)/807 Rs. 203.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 4.60 1715.50 7891.30
Fuel / Energy charges Hour 4.60 656.00 3017.60
2 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 937.80 7502.40
3 Tippers 5.00 cum capacity 5 Nos. Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 322.20 15465.60
4 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 38.00 152.00
5 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 322.20 2577.60
6 Vibratory Roller 8 tonne Hour 7.00 1342.20 9395.40
Fuel / Energy charges Hour 7.00 1108.30 7758.10
7 Sundries LS 5.00 41.00 205.00
Total hire charges of Machinery Rs: 92291.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 4.60 204.10 938.86
2 Crew for Shovel Hour 8.00 204.10 1632.80
3 Crew for Tipper Hour 48.00 153.10 7348.80
4 Crew for Pump Hour 4.00 72.10 288.40
5 Crew for Water tanker Hour 8.00 153.10 1224.80
6 Crew for Roller Hour 7.00 227.80 1594.60
7 work inspector Day 2.00 370.00 740.00
8 mazdoor Day 4.00 295.00 1180.00
Total cost of Labour Rs: 14948.26
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 92291.40
C. Cost of Labour Rs: 14948.26
Total Rs: 107239.66
Page 15 of 44
D.Add for contractor's profit and overheads on (A+B+C) 13.56% Rs. 14541.7
Total cost for 970.00 cum Rs: 121781.36
Rate per Cum (A+B+C+D)/970 Rs. 125.50
Deduct Rate for Proctar's density Control of 95% using 8T roller as per IRR-PMW-3-23 -46.10
Add Rate for Proctor's Density control of 90% using 2T Roller as per IRR-PMW-3-24 6.10
Rate per Cum 85.50
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 4.60 1715.50 7891.30
Fuel / Energy charges Hour 4.60 656.00 3017.60
2 Shovel 0.85 cum Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 937.80 7502.40
3 Tipper 5 cum Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 322.20 15465.60
4 Pump 5 hp ( ele ) Hour 4.00 3.00 12.00
Fuel / Energy charges Hour 4.00 38.00 152.00
5 Water tanker 8000 ltr Hour 8.00 402.50 3220.00
Fuel / Energy charges Hour 8.00 322.20 2577.60
6 Vibratory Roller 8 tonne Hour 7.00 1342.20 9395.40
Fuel / Energy charges Hour 7.00 1108.30 7758.10
7 Sundries LS 5.00 41.00 205.00
Total hire charges of Machinery Rs: 92291.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 4.60 204.10 938.86
2 Crew for Shovel Hour 8.00 204.10 1632.80
3 Crew for Tipper Hour 48.00 153.10 7348.80
4 Crew for Pump Hour 4.00 72.10 288.40
5 Crew for Water tanker Hour 8.00 153.10 1224.80
6 Crew for Roller Hour 7.00 227.80 1594.60
7 work inspector Day 2.00 370.00 740.00
8 mazdoor Day 4.00 295.00 1180.00
Total cost of Labour Rs: 14948.26
labour component/unit qty 15.40
Add contractor's profit and overhead charges 14% 2.20
labour component/unit qty (including contractor's profit) 17.60
Page 16 of 44
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 92291.40
C. Cost of Labour Rs: 14948.26
Total Rs: 107239.66
D.Add for contractor's profit and overheads on (A+B+C) 13.56% Rs. 14541.7
Total cost for 970.00 cum Rs: 121781.36
Rate per Cum (A+B+C+D)/970 Rs: 125.50
E. Lead Charges / Seioniorage charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
3 Seioniorage charges cum 970.000 22.00 21340.00
21340.00
Total cost for 970.00 cum Rs: 143121.36
Rate per cum (A+B+C+D)/970 Rs. 148.00
Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials,
labour, hand packing, finishing etc., complete
( rubble stones : 0.2475 cum/sqm) (For Maintenance Works) IRR-CAW-8-2-A
(New Item5 - 2011-12)
B. MACHINERY :
C. LABOUR :
ABSTRACT :
A. Cost of Materials Rs. 4720.00
B. Hire Charges of Machinery Rs. 0
C. Cost of Labour Rs. 8278.88
Total Rs: 12998.88
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 1762.65
Total cost for 100.00 Sqm. Rs: 14761.53
Rate per Sqm. (A+B+C+D)/100.0 Rs. 147.62
E. Lead Charges
Page 17 of 44
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Stone cum 24.750 71.50 1769.63
1769.63
Total cost for 100.00 cum Rs: 16531.15
Rate per cum (A+B+C+D)/807 Rs. 165.30
5 Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts. IRR-CCDW-6-1
(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 2.00 345.00 690.00
2 work inspector Day 1.00 370.00 370.00
3 mazdoor Day 3.00 295.00 885.00
Total cost of Labour Rs: 1945.00
ABSTRACT:
A. Cost of Materials Rs: 700.32
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1945.00
Total Rs: 2645.32
D. Add for contractor's profit and overheads on (A+B+C) 13.56% Rs: 358.71
Total cost for 10.00 Joints Rs: 3004.03
E. Lead Charges / Seioniorage charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Sand cum 0.100 71.50 7.15
3 Seioniorage charges cum 0.100 40.00 4.00
11.15
3015.18
Rate per joint (A+B+C+D)/10.0 Rs. 301.50
NP3 Pipe Add 10% 30.15
Rate per joint 331.65
Page 18 of 44
No. Cost of Cost of Laying &
pipe. Collar. Jointing.
1 2 3 4 5
1 Initial Rate 824.00 129.00
2 Conveyance charges
for 60 Kms.
Upto 5 Kms. 39.00
For 55 Kms. 58.85
921.85 129.00
4 Laying & Jointing. 331.65
921.85 129.00 331.65
Total length of pipes #REF!
No. of Collars #REF!
TOTAL COST
PIPES #REF!
COLLARS #REF!
JOINTING #REF!
#REF!
THROUGH RATE #REF!
Rate Per Rmt. #REF!
Or Say #REF!
Page 19 of 44
Detailed Estimate
Name of Work :- Mission Kakatiya - Minor Irrigation - Phase.III - Rekulacheru, Kunepally(V), Renjal (M), Nizamabad( Dist ).
Sl. L B D
Description of work Nos Quantity
No ( Mtrs ) ( Mtrs ) ( Mtrs )
1 SUB HEAD : BUND
Clearing thick jungle growth ( less than 50 percent open space ) including bushes upto 30 cm / parthenium and other weeds
1 including burning or disposing off the same as directed etc., complete.
From Km. 0.000 to Km. 0.950 1 x 1 950.00 15.00 --- 14250.000
Sqm 14250.000
Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seatingl,of embankment for field channels
etc., including dressing of bed and sides to required profile,cost of all materials, machinery, labour, placing the excavated stuff
2 for formation of service road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m. Stripping
From Km. 0.0 to Km. 0.100 1 x 1 100.00 ( 4.158 + 2.995 )/2 -- 357.650
From Ch. 0.100 to Ch. 0.200 1 x 1 100.00 ( 2.995 + 3.678 )/2 -- 333.650
From Ch. 0.200 to Ch. 0.300 1 x 1 100.00 ( 3.678 + 5.315 )/2 -- 449.650
From Ch. 0.300 to Ch. 0.400 1 x 1 100.00 ( 5.315 + 5.199 )/2 -- 525.700
From Ch. 0.400 to Ch. 0.500 1 x 1 100.00 ( 5.199 + 5.608 )/2 -- 540.350
From Ch. 0.500 to Ch. 0.600 1 x 1 100.00 ( 5.608 + 5.985 )/2 -- 579.650
From Ch. 0.600 to Ch. 0.700 1 x 1 100.00 ( 5.985 + 3.217 )/2 -- 460.100
From Ch. 0.700 to Ch. 0.800 1 x 1 100.00 ( 3.217 + 4.960 )/2 -- 408.850
From Ch. 0.800 to Ch. 0.900 1 x 1 100.00 ( 4.960 + 5.851 )/2 -- 540.550
From Ch. 0.900 to Ch. 0.950 1 x 1 50.00 ( 5.851 + 5.581 )/2 -- 285.800
Add Benching Qty 1 x 4 950.00 1./2 0.450 0.450 384.750
Add Stripping Qty 1 x 1 950.00 4.00 0.15 570.000
5436.700
Cum Or Say 5437.000
Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seatingl,of embankment for field channels
5 etc., including dressing of bed and sides to required profile,cost of all materials, machinery, labour, placing the excavated stuff
for formation of service road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m.
For Cutopen of Bund 1 x 1( 3.00 + 10.00 )/2 ( 3.00 + 15.00 )/2 3.00 175.500
For sluice portion 1 x 1 2.70 2.70 0.45 3.281
For Horn walls L/s 1 x 1 3.00 1.20 0.45 1.620
For Horn walls R/s 1 x 1 3.00 1.20 0.45 1.620
For Wingwall L/s 1 x 1 1.50 1.20 0.45 0.810
For Wingwall L/s 1 x 1 1.50 1.20 0.45 0.810
For Barrel portion 1 x 1 12.00 1.65 0.30 5.940
For Retaining wall 1 x 1 3.30 1.20 0.30 1.188
For Cistern 1 x 1 2.70 2.70 0.30 2.187
Cum 192.956
For sluice-1 192.956
For sluice-2 192.956
Total 385.912
Cum Or Say 385.920
2 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement
concrete using 40 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.IRR-CCDW-2-5
50% of Excavation qty 0.5 ( 3.00 + 10.00 )/2 ( 3.00 + 15.00 )/2 3.00 87.750
For sluice-1 87.750
For sluice-2 87.750
Total 175.500
Cum Or Say 175.500
Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction
including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in
layer of specified thickness, breaking clods, sectioning, watering, compacting to density control of not less than 95 percent or as
5
stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc., complete with initial lead upto 2 km and all
lifts.
50% of Excavation qty 0.5 ( 3.00 + 10.00 )/2 ( 3.00 + 15.00 )/2 3.00 87.750
For sluice-1 87.750
For sluice-2 87.750
Total 175.500
Cum Or Say 175.500
WEIR
1 Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seatingl,of embankment for field channels
etc., including dressing of bed and sides to required profile,cost of all materials, machinery, labour, placing the excavated stuff
for formation of service road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m.
For skinwall bodywall 1 x 1 45.00 0.90 0.45 18.225
For Wingwall L/s 1 x 1 4.30 1.20 0.45 2.322
For Wingwall R/s 1 x 1 4.30 1.20 0.45 2.322
For Returns L/s 1 x 2 1.50 1.20 0.45 1.620
For Returns R/s 1 x 2 1.50 1.20 0.45 1.620
For Apron 1 x 1 45.00 3.00 0.30 40.500
For cut-off wall 1 x 1 45.00 0.30 0.60 8.100
74.709
Cum Or Say 74.710
2 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10 N / sq mm ) grade cement
concrete using 40 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.IRR-CCDW-2-5
For skinwall bodywall 1 x 1 45.00 0.90 0.45 18.225
For Wingwall L/s 1 x 1 4.30 1.20 0.45 2.322
For Wingwall R/s 1 x 1 4.30 1.20 0.45 2.322
For Returns L/s 1 x 2 1.50 1.20 0.45 1.620
For Returns R/s 1 x 2 1.50 1.20 0.45 1.620
For Apron 1 x 1 45.00 3.00 0.30 40.500
For cut-off wall 1 x 1 45.00 0.30 0.60 8.100
74.709
Sl. L B D
Description of work Nos Quantity
No ( Mtrs ) ( Mtrs ) ( Mtrs )
Cum Or Say 74.710
3 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement
concrete using 40 mm down size approved, clean, hard, graded aggregates including cost of all materials, machinery, labour,
formwork, centering, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all lifts.
SSR-2016-17
1 Clearing thick jungle growth ( less than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same as
directed etc., complete. IRR-PMW-1-2
DATA: RATE ANALYSIS UNIT : 1000 sqm
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 0.50 460.00 230.00
2 mazdoor Day 5.00 350.00 1750.00
Total cost of Labour Rs: 1980.00
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1980.00
Total Rs: 1980.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 269.58
Total cost for 1000.00 sqm Rs: 2249.58
Rate per sqm (A+B+C+D)/1000.0 Rs. 2.20
2 Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seating
of embankment for field channels etc., including dressing of bed and sides to required profile,
cost of all materials, machinery, labour, placing the excavated stuff for formation of service
road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m. IRR-CAW-1-2
DATA: RATE ANALYSIS UNIT : 440.00 cum
A. MATERIALS:
Sl No particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.50 cum capacity Hour 8.00 985.90 7887.20
Page 25 of 44
Fuel / Energy charges Hour 8.00 484.40 3875.20
Total hire charges of Machinery Rs: 11762.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 237.90 1903.20
2 work inspector Day 1.00 460.00 460.00
3 mazdoor Day 17.00 350.00 5950.00
Total cost of Labour Rs: 8313.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 11762.40
C. Cost of Labour Rs: 8313.20
Total Rs: 20075.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2733.29
Total cost for 440.00 cum Rs: 22808.89
Rate per cum (A+B+C+D)/440 Rs. 51.80
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 5.40 1690.40 9128.16
Fuel / Energy charges Hour 5.40 621.30 3355.02
2 Shovel 0.85 cum capacity Hour 8.00 1677.40 13419.20
Fuel / Energy charges Hour 8.00 888.10 7104.80
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 440.50 17620.00
Fuel / Energy charges Hour 40.00 305.20 12208.00
4 Pump 5 hp ( ele ) Hour 4.00 2.90 11.60
Fuel / Energy charges Hour 4.00 38.50 154.00
5 Water tanker 8000 ltr Hour 8.00 396.90 3175.20
Fuel / Energy charges Hour 8.00 305.20 2441.60
6 Vibratory Roller 8 tonne Hour 6.40 1325.70 8484.48
Fuel / Energy charges Hour 6.40 1049.60 6717.44
7 Sundries LS 2.00 20.00 40.00
Total hire charges of Machinery Rs: 83859.50
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 5.40 237.90 1284.66
Page 26 of 44
2 Crew for Shovel Hour 8.00 237.90 1903.20
3 Crew for Tipper Hour 40.00 178.40 7136.00
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 178.40 1427.20
6 Crew for Roller Hour 6.40 263.60 1687.04
7 work inspector Day 2.00 460.00 920.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 16091.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 83859.50
C. Cost of Labour Rs: 16091.30
Total Rs: 99950.80
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 13608.3
Total cost for 807.00 cum Rs: 113559.10
E. Lead Charges / Seioniorage charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Seioniorage charges cum 807.000 30.00 24210.00
24210.00
Total cost for 807.00 cum Rs: 137769.10
Rate per cum (A+B+C+D)/807 Rs. 171.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 5.40 1690.40 9128.16
Fuel / Energy charges Hour 5.40 621.30 3355.02
2 Shovel 0.85 cum capacity Hour 8.00 1677.40 13419.20
Fuel / Energy charges Hour 8.00 888.10 7104.80
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 440.50 17620.00
Fuel / Energy charges Hour 40.00 305.20 12208.00
4 Pump 5 hp ( ele ) Hour 4.00 2.90 11.60
Fuel / Energy charges Hour 4.00 38.50 154.00
5 Water tanker 8000 ltr Hour 8.00 396.90 3175.20
Fuel / Energy charges Hour 8.00 305.20 2441.60
6 Vibratory Roller 8 tonne Hour 6.40 1325.70 8484.48
Fuel / Energy charges Hour 6.40 1049.60 6717.44
7 Sundries LS 2.00 20.00 40.00
Total hire charges of Machinery Rs: 83859.50
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 5.40 237.90 1284.66
2 Crew for Shovel Hour 8.00 237.90 1903.20
3 Crew for Tipper Hour 40.00 178.40 7136.00
4 Crew for Pump Hour 4.00 83.30 333.20
5 Crew for Water tanker Hour 8.00 178.40 1427.20
6 Crew for Roller Hour 6.40 263.60 1687.04
7 work inspector Day 2.00 460.00 920.00
Page 27 of 44
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 16091.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 83859.50
C. Cost of Labour Rs: 16091.30
Total Rs: 99950.80
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 13608.3
Total cost for 807.00 cum Rs: 113559.10
E. Lead Charges / Seioniorage charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Earth cum 807.000 44.10 35588.70
2 Deduct 1 km lead cum 807.000 -31.50 -25420.50
3 Seioniorage charges cum 807.000 30.00 24210.00
34378.20
Total cost for 807.00 cum Rs: 147937.30
Rate per cum (A+B+C+D)/807 Rs. 183.00
7 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum) IRR-CCDW-2-5
Page 28 of 44
RATE ANALYSIS UNIT : 16.36 cum
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement for mix kg 3599.20 5.90 21235.28
Cement for incidentals @ 3 kg / cum kg 49.08 5.90 289.57
2 Coarse aggregate 40-20 mm cum 7.36 1090.00 8024.58
Coarse aggregate 20-10 mm cum 4.42 1150.00 5079.78
Coarse aggregate 10 mm below cum 2.94 875.00 2576.70
3 Fine aggregate cum 6.54 560.00 3664.64
4 Super Plasticizer kg 14.40 45.00 647.86
5 Use rate of shuttering for 40 uses sqm 16.36 229.95 3762.01
Scaffolding @ of shuttering 10% 376.20
4 Sundries LS 0.50 20.00 10.00
Add seignorage charges on CA @ (Included in material rate Rs: 0.00
Add seignorage charges on FA @ (Included in material rate Rs: 0.00
Total cost of Materials Rs: 45666.61
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 52.80 422.40
Fuel / Energy charges Hour 8.00 80.70 645.60
2 5 hp pump ( diesel ) Hour 0.50 10.00 5.00
Fuel / Energy charges Hour 0.50 80.70 40.35
3 Water tanker 8000 ltr Hour 1.00 396.90 396.90
Fuel / Energy charges Hour 1.00 305.20 305.20
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.20 145.60
Total hire charges of Machinery Rs: 2021.85
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 178.40 178.40
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 460.00 460.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 16.36 350.00 5726.00
8 for cleaning/ washing/ curing Day 1.00 350.00 350.00
9 Labour cost for shuttering sqm 16.36 88.95 1455.22
Total cost of Labour Rs: 17993.37
ABSTRACT:
A. Cost of Materials including seignorage charges Rs: 45666.61
B. Hire charges of Machinery Rs: 2021.85
C. Cost of Labour Rs: 17993.37
Total Rs: 65681.84
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 8942.58
Total cost for 16.36 cum Rs: 74624.42
Page 29 of 44
4203.87
Total cost for 16.36 cum Rs: 78828.28
Rate per cum (A+B+C+D+E)/16.36 Rs. 4818.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.0 51.00 408.00
Fuel / Energy charges Hour 8.0 38.50 308.00
2 10 hp pump ( ele ) Hour 1.0 6.60 6.60
Fuel / Energy charges Hour 1.0 77.00 77.00
3 Needle vibrator 40 mm dia ( ele ) Hour 8.0 7.90 63.20
Fuel / Energy charges Hour 8.0 7.70 61.60
Total hire charges of Machinery Rs: 924.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 1.00 83.30 83.30
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 1.00 445.00 445.00
5 mazdoor 0.00
for batching cement ( cement handling Day 2.00 350.00 700.00
for batching other materials Day 9.00 350.00 3150.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 14.00 350.00 4900.00
for cleaning / washing / curing Day 1.00 350.00 350.00
6 Labour cost of shuttering sqm 14.00 88.95 1245.30
7 Labour cost of scaffolding @ 15% 186.80
Total cost of Labour Rs: 16533.60
ABSTRACT:
A. Cost of Materials Rs: 42513.67
B. Hire charges of Machinery Rs: 924.40
C. Cost of Labour Rs: 16533.60
Total Rs: 59971.67
Page 30 of 44
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8165.14
Total cost for 14.00 cum Rs: 68136.81
9 Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts. IRR-CCDW-2-1
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nil 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 work inspector Day 1.00 460.00 460.00
2 Bar bender Day 6.00 565.00 3390.00
3 mazdoor Day 11.00 350.00 3850.00
Total cost of Labour Rs: 7700.00
ABSTRACT:
A. Cost of Materials Rs: 34100.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 7700.00
Total Rs: 41800.00
D. Add for contractor's profit and overheads on (A+B 13.615% Rs: 5691.07
Total cost for 1000.00 kg Rs: 47491.07
Total cost for Per Kgs Rs: 47.50
10 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Page 31 of 44
etc., complete with initial lead upto 50 m and all lifts. IRR-CCDW-2-24
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.76 cum
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement for mix kg 5200.80 5.90 30684.72
Cement for incidentals @ 5 kg / cum kg 78.80 5.90 464.92
2 Coarse aggregate 20-10 mm cum 8.20 1150.00 9424.48
Coarse aggregate 10 mm below cum 4.41 875.00 3861.20
3 Fine aggregate (Un-Screened) cum 7.09 560.00 3971.52
4 Super Plasticizer kg 20.80 45.00
5 Use rate of shuttering for 30 uses sqm 39.40 277.94 10950.65
Scaffolding @ of shuttering 250% 27376.62
6 Sundries LS 1.00 20.00 20.00
Total cost of Materials Rs: 86754.11
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 52.80 422.40
Fuel / Energy charges Hour 8.00 80.70 645.60
2 5 hp pump ( diesel ) Hour 0.50 10.00 5.00
Fuel / Energy charges Hour 0.50 80.70 40.35
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.20 145.60
Total hire charges of Machinery Rs: 1319.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 460.00 460.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
7 Labour cost for shuttering sqm 39.40 88.95 3504.63
Labour cost for scaffolding @ 250% 8761.58
Total cost of Labour Rs: 29210.96
ABSTRACT:
A. Cost of Materials Rs: 86754.11
B. Hire charges of Machinery Rs: 1319.75
C. Cost of Labour Rs: 29210.96
Total Rs: 117284.82
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 15968.33
Total cost for 15.76 cum Rs: 133253.15
E. Lead Charges
Sl No Particulars Unit Quantity Rate Amount
1 Sand - Seignorage charges cum 7.092 40.00 283.68
2 Metal - Seignorage charges cum 12.608 75.00 945.60
1 Sand cum 7.092 159.60 1131.88
2 Metal cum 12.608 121.80 1535.65
3896.81
Total cost for 15.76 Cum Rs: 137149.96
Rate per (A+B+C+D+E)/ 15.76 Cum Rs: 8702.00
Page 32 of 44
11 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /
sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for wearing coat including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
and all lifts. IRR-CCDW-2-26
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
DATA: RATE ANALYSIS UNIT : 15.76 cum
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement for mix kg 5200.80 5.90 30684.72
Cement for incidentals @ 5 kg / cum kg 78.80 5.90 464.92
2 Coarse aggregate 20-10 mm cum 8.20 1150.00 9424.48
Coarse aggregate 10 mm below cum 4.41 875.00 3861.20
3 Fine aggregate (Un-Screened) cum 7.09 560.00 3971.52
4 Super Plasticizer kg 20.80 45.00 936.14
5 Use rate of shuttering sqm 7.88 229.95 1812.02
6 Sundries ( asphalt mortar etc ) LS 5.00 20.00 100.00
Total cost of Materials Rs: 51255.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 52.80 422.40
Fuel / Energy charges Hour 8.00 80.70 645.60
2 5 hp pump ( diesel ) Hour 0.50 10.00 5.00
Fuel / Energy charges Hour 0.50 80.70 40.35
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 18.20 145.60
Total hire charges of Machinery Rs: 1319.75
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Needle vibrator Hour 8.00 158.20 1265.60
4 Mason Class-I Day 2.00 445.00 890.00
5 work inspector Day 1.00 460.00 460.00
6 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 15.76 350.00 5516.00
for cleaning/ washing/ curing Day 2.00 350.00 700.00
7 Labour cost for shuttering sqm 7.88 88.95 700.93
Total cost of Labour Rs: 17995.68
ABSTRACT:
A. Cost of Materials Rs: 51255.00
B. Hire charges of Machinery Rs: 1319.75
C. Cost of Labour Rs: 17995.68
Total Rs: 70570.43
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9608.16
Total cost for 15.76 cum Rs: 80178.59
E. Seignorage charges /Lead Charges
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
Lead Charges
1 Sand cum 7.092 159.60 1131.88
2 Metal cum 12.608 121.80 1535.65
Seignorage charges
1 Sand cum 7.092 40.00 283.68
2 Metal cum 12.608 75.00 945.60
3896.82
Page 33 of 44
84075.41
Rate per cum (A+B+C+D)/15.76 Rs. 5335.00
Page 34 of 44
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 3.60 1690.40 6085.44
Fuel / Energy charges Hour 3.60 621.30 2236.68
2 Pump 5 hp ( diesel ) Hour 3.00 10.00 30.00
Fuel / Energy charges Hour 3.00 80.70 242.10
3 Water tanker 8000 ltr Hour 5.00 396.90 1984.50
Fuel / Energy charges Hour 5.00 305.20 1526.00
4 Vibratory Roller 8 tonne Hour 6.1 1325.70 8033.74
Fuel / Energy charges Hour 6.1 1049.60 6360.58
5 Sundries LS 5.00 20.00 100.00
Total hire charges of Machinery Rs: 26599.04
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 3.60 237.90 856.44
2 Crew for Pump Hour 3.00 111.10 333.30
3 Crew for Water tanker Hour 5.00 178.40 892.00
4 Crew for Roller Hour 6.1 263.60 1597.42
5 work inspector Day 2.00 460.00 920.00
6 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 5999.16
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 26599.04
C. Cost of Labour Rs: 5999.16
Total Rs: 32598.19
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 4438.24
Total cost for 600.00 cum Rs: 37036.43
13 Excavation in all kinds of soil including boulders upto 0.30 m dia for silt removal from tank bed and
bringing it to to required profile,cost of all materials, machinery, labour, placing the excavated
stuff for formation of service road / embankment as directed etc., complete with lead
upto 10 m and lift upto 3 m. (New item included in 2016-17) IRR-CAW-1-2A
Approve basic rate as per ENC(I) guidelines Rs 40.00
14 The Approved basic Rate for silt excavation and dumping with 1 km lead
for un-useful silt as per ENC(I) guidelines Rs 71.50
Page 35 of 44
Name of Work :- Mission Kakatiya - Minor Irrigation - Phase.III - Rekulacheru, Kunepally(V), Renjal (M),
Nizamabad( Dist ).
SS Rates for the year 2016-17
LEAD CHART
Lead charges
1 2 3 4 5 6 7 8 9 10 11 12 13
1 Sand Mondivagu 0.00 11.00 31.50 44.10 58.80 71.40 84.00 12.60 10.50 159.60 Per M3
2 Metal Navipet 0.00 8.00 30.40 42.60 58.80 71.40 84.00 12.60 10.50 121.80 Per M3
3 Earth / Gravel Local 0.00 1.00 31.50 44.10 58.80 71.40 84.00 12.60 10.50 31.50 Per M3
4 Cement 5900.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.90 per Kg
5 Steel 32000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.00 per Kg
SLUICE PLAN
0.9 1.5
0.6 1.8 A
0.6
0.9
3.00 C
2.40
3.00 C
0.9
0.6
Apron
1.2 1.2
M10
4.3 4.3
1.2 1.2
FOUNDATION PLAN
0.6 0.6
0.9 3.0 0.9
Apron
4.00 4.00
Bodywall
A A
0.9 0.9
0.6 0.6
B
0.6 0.6
1.8
M15 M15
0.45
0.90 0.9
0.9 0.9 M20 0.15
M10 0.3
0.45 M10 0.6
0.3
45.00 3
102.00
101.80 101.80 101.80
101.22 101.22
101.00
100.00
99.60
98.00
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
Working Workdone
S.NO Distance height Avg height width Area
levels levels FTL 100.00
1 -3.30 99.02 0.00 0.00 0.000 0.00 0.000 MWL 100.30
2 0.00 101.22 101.22 0.00 0.000 0.00 0.000 TBL 101.80
3 0.87 101.22 101.80 0.58 0.290 0.87 0.252 Top width 3
4 2.37 101.22 101.80 0.58 0.580 1.50 0.870 Side slopes 1.5:1&1.5:1
5 3.87 101.22 101.80 0.58 0.580 1.50 0.870
6 7.17 99.02 99.60 0.58 0.580 3.30 1.914
7 8.04 99.02 99.02 0.00 0.29 0.87 0.252
Banking 4.158
Cross Section at Ch: 100 m
103.00
102.00
101.44101.44
101.80 101.46
101.80 101.43
101.80
101.44
101.00
100.00
99.00
98.30 98.30
98.67 98.30
98.30
98.00
-5.00 -4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00
103.00
102.00
101.34 101.34
101.80 101.36
101.80 101.33
101.80
101.34
101.00
100.00
99.00
98.50
98.97 98.50
98.50
98.00
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Page 2 of 44
REKULA CHERU, KUNEPALLY(V), RENJAL (M), NZB(Dist)
Cross Section at Ch: 300 m
103.00
102.00
101.80 101.80 101.80
101.17 101.17 101.19 101.16
101.00 101.17
100.00
99.00
98.84
98.20 98.20
98.00 98.20
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
103.00
102.00
101.80 101.80
101.19 101.80
101.17 101.17 101.16
101.00 101.17
100.00
99.00
98.96
98.32 98.32 98.32
98.00 98.32
-5.00 -4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Working Workdone
S.NO Distance levels levels height Avg height width Area
FTL 100.00
1 -4.28 98.32 0.00 0.00 0.000 0.00 0.000 MWL 100.30
2 0.00 101.17 101.17 0.00 0.000 0.00 0.000 TBL 101.80
3 0.94 101.17 101.80 0.63 0.315 0.94 0.298 Top width 3
4 2.45 101.19 101.80 0.61 0.620 1.50 0.930 Side slopes 1.5:1&1.5:1
5 3.95 101.16 101.80 0.64 0.625 1.50 0.938
6 8.21 98.32 98.96 0.64 0.640 4.26 2.726
7 9.17 98.32 98.32 0.00 0.32 0.96 0.307
Banking 5.199
103.00
102.00
101.80 101.80 101.80
101.11 101.11 101.13 101.10
101.00 101.11
100.00
99.00 99.10
98.40 98.40
98.40
98.00
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Working Workdone
S.NO Distance levels levels height Avg height width Area
FTL 100.00
1 -4.06 98.40 0.00 0.00 0.000 0.00 0.000 MWL 100.30
2 0.00 101.11 101.11 0.00 0.000 0.00 0.000 TBL 101.80
3 1.04 101.11 101.80 0.69 0.345 1.04 0.357 Top width 3
4 2.54 101.13 101.80 0.67 0.680 1.50 1.020 Side slopes 1.5:1&1.5:1
5 4.04 101.10 101.80 0.7 0.685 1.50 1.028
6 8.08 98.40 99.10 0.70 0.700 4.05 2.835
7 9.13 98.40 98.40 0.00 0.35 1.05 0.368
Banking 5.608
Page 3 of 44
REKULA CHERU, KUNEPALLY(V), RENJAL (M), NZB(Dist)
Cross Section at Ch: 600 m
103.00
102.00
101.80 101.80 101.80
101.09 101.09 101.11 101.08
101.00
101.09
100.00
99.00
98.92
98.20 98.20
98.00 98.20
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
103.00
102.00
101.39 101.39
101.80 101.41
101.80 101.38
101.80
101.39
101.00
100.00
99.00
98.60
99.02 98.60
98.60
98.00
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
103.00
102.00
101.80 101.80 101.80
101.19 101.19 101.21 101.18
101.00 101.19
100.00
99.00
99.02
98.40 98.40
98.40
98.00
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Page 4 of 44
REKULA CHERU, KUNEPALLY(V), RENJAL (M), NZB(Dist)
Cross Section at Ch: 900 m
Page 5 of 44
REKULA CHERU, KUNEPALLY(V), RENJAL (M), NZB(Dist)
103.00
102.00
101.80 101.80 101.80
101.08 101.08 101.10 101.07
101.00
101.08
100.00
99.00 99.13
98.40 98.40 98.40
98.40
98.00
-5.00 -4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Working Workdone
S.NO Distance height Avg height width Area
levels levels FTL 100.00
1 -4.02 98.40 0.00 0.00 0.000 0.00 0.000 MWL 100.30
2 0.00 101.08 101.08 0.00 0.000 0.00 0.000 TBL 101.80
3 1.08 101.08 101.80 0.72 0.360 1.08 0.389 Top width 3
4 2.58 101.10 101.80 0.7 0.710 1.50 1.065 Side slopes 1.5:1&1.5:1
5 4.08 101.07 101.80 0.73 0.715 1.50 1.073
6 8.08 98.40 99.13 0.73 0.730 4.00 2.924
7 9.18 98.40 98.40 0.00 0.365 1.10 0.400
Banking 5.851
103.00
102.00
101.80 101.80 101.80
101.10 101.10 101.12 101.09
101.00 101.10
100.00
99.00 99.21
98.50 98.50 98.50
98.50
98.00
-4.00 -3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Working Workdone
S.NO Distance levels levels height Avg height width Area
FTL 100.00
1 -3.90 98.50 0.00 0.00 0.000 0.00 0.000 MWL 100.30
2 0.00 101.10 101.10 0.00 0.000 0.00 0.000 TBL 101.80
3 1.05 101.10 101.80 0.7 0.350 1.05 0.367 Top width 3
4 2.55 101.12 101.80 0.68 0.690 1.50 1.035 Side slopes 1.5:1&1.5:1
5 4.05 101.09 101.80 0.71 0.695 1.50 1.043
6 7.93 98.50 99.21 0.71 0.710 3.89 2.758
7 9.00 98.50 98.50 0.00 0.355 1.06 0.378
Banking 5.581
Cross Section at Ch: 1100 m
Page 6 of 44
STATEMENT SHOWING THE B.C RATIO
Name of the Work :- Mission Kakatiya - Minor Irrigatioin - Normal stateplan - Phase-III - Repairs to Arla Kunta, Binola (V), Navipet (M), Nizamabad Dist.
Exsisting Total
40 Acres 47 Acres
Ayacut Ayacut
Receieved Benefits through yeild Expenditure of the crop
Total Receipts Gross Cost of Cost of Hire /Labour Total Net Value
Sl.No Crop Cost of of
Aycut Gross Value of from value of seed/ Manure & cost Total cost
Yeild (Qtl) Rate/ Qtl P.P.
(Acres) Yeild (Qtl) Produce fodder produces Acres in Fertilizers in Measures /Acres in in Lakhs Produces
(Lakhs) (Lakhs) (Lakhs) Rs. Rs Machine Labour Rs.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
PARTICULARS BEFORE IMPLEMENTAION OF THE SCHEME
1 Paddy 40 18 720 1800 12.96 0.40 13.36 650 3000 2000 1000 700 7350 2.94 10.42
Rs 650 /
per 30 kg
Rs 1000/- bag per
per acre acre
PARTICULARS AFTER IMPLEMENTAION OF THE SCHEME
1 Paddy 47 28 1316 1800 23.69 0.47 24.16 650 3000 2000 1000 700 7350 3.45 20.70