You are on page 1of 11

LEAN SIX SIGMA IN SHIPBUILDING

I Radovic, Dr. B Inozu and B J MacClaren, University of New Orleans, USA

Accepted for presentation at European Shipbuilding and Repair Conference on November 2, 2004 in London.

SUMMARY

Recently, several major shipyards in the US have begun to implement a Lean Manufacturing strategy. During the last
two years Northrop Grumman Ship Systems (NGSS) has been transitioning their Lean Manufacturing program to a Lean
Six Sigma program in conjunction with the Lean Six Sigma in Shipbuilding project sponsored by Advanced Maritime
Technology Application Center (AMTAC) at University of New Orleans.

In this paper, we first describe the Lean Six Sigma approach used for process improvement at Avondale, Ingalls and
Gulfport shipyards of NGSS along with the training requirements for implementation. The workforce training strategy
will be described to help understand the prerequisites for shipyard implementation. Then domino effects and resulting
financial impact of defects are presented.

1. INTRODUCTION industry to become one of the driving process


improvement methodologies. However, this evolution
A few years ago, Lean Manufacturing strategy was occurred in the other industries as a way to improve
introduced in the US shipbuilding industry to help close productivity by reducing the product cycle time and
the productivity gap with the shipyards in the Far East. eliminating defects.
In the past two years, Lean implementations were
followed by the implementation of the Six Sigma Based on the Toyota production system [1], Lean
management strategy. During the 2000 - 2002 period, Manufacturing was first documented in the U.S. by
pilot Six Sigma studies were also conducted at Norfolk researchers from MITs International Motor Vehicle
Naval Shipyard, Northrop Grumman Newport News Program about 10 years ago. Their findings were
Shipyard, and Bollinger Shipyards, as well as the summarized in the book entitled, The Machine That
Central Region of the U.S. Maritime Administration, Changed The World [2][3]. The concepts of Lean
which operates some Ready Reserve Fleet ships. In the Manufacturing then became instrumental to the future
summer of 2002 Northrop Grumman Ship Systems of the world auto industry. Subsequently, principles of
(NGSS) started transitioning their Lean program to a lean were embraced by other industries including the
Lean Six Sigma (LSS) program in conjunction with the U.S. shipbuilding industry. On the other hand, the
LSS in Shipbuilding project sponsored by Advanced origin of Six Sigma can be traced back to the mid-
Maritime Technology Application Center (AMTAC) at 1980s when Motorola first introduced the concept. It
University of New Orleans (UNO). This project has originally focused on reducing variation in processes.
enabled implementation of LSS at NGSS However, Six Sigma then evolved into one of the most
approximately 12 months earlier than originally powerful management strategies to fundamentally
planned. Implementation areas include engineering, change the way corporations do business and improve
production and transactional processes including supply their bottom line. Implementation of Six Sigma is
chain management and finance. In the very short term, relatively new in the U.S. shipbuilding and marine
the LSS methodology evolved in the US shipbuilding industry as a whole.
biggest impact on product or process variation.
This paper first highlights the transformation of Lean Interestingly, experience has shown that in many cases
and Six Sigma methodologies into Lean Six Sigma these critical parameters are not intuitive.
strategy in shipbuilding. The workforce training
requirements are described to show the support needed One of the most powerful tools that Six Sigma offers to
for the shipyard implementation. Then the domino an organization is a structured approach to problem
impact of defects is presented on a shipbuilding solving. A projects success depends on the careful
example to help understand impact of work in process planning and completion of each phase. The core
defects on shipyard production. Finally an example of phases of the Six Sigma strategy are: define, measure,
ROI calculations will be presented to show a LSS analyze, improve and control (DMAIC). A process that
project impact on the bottom line along with culture attains Six Sigma level capability means it has 3.4
change requirements. defects per million opportunities, an almost perfect
process. Looking more closely at this reveals some
surprising revelations. For example, if a computer is
2. TRANSITIONING FROM LEAN TO restarted 500,000 times and it has a 99% chance of
LEAN SIX SIGMA successfully re-booting, it would crash 4,100 times.
With Six Sigma performance, it would crash less than
In the late 1990s Lean Manufacturing emerged to be twice [4]. More strikingly, the same performance level
one of the key methodologies for improvement in the can be applied to the airline industry. If airplane
US shipbuilding. Various research projects were funded maintenance practices only attained the three sigma
to support this initiative with a goal to improve level, a single airplane would experience 820
competitiveness of the US shipbuilding. As a proven mechanical failures in 100,000 flights. At Six Sigma
approach in the other industries, Lean was widely performance levels, there would not likely be a single
accepted to be the methodology to drive the process failure. This represents a situation where Six Sigma
improvement among US shipyards. Cycle times to performance is not a compromise. However, not all
build the ships were long and they needed to be processes need to be at the Six Sigma level.
reduced to meet both commercial and navy customer
requirements. After a few years of implementing Lean, In a broader business sense, Six Sigma is the pursuit of
some of the US shipyards went one step further by world-class quality. It is the quest for providing a
implementing Six Sigma. NGSS went even further by better product or service, faster, and at a lower cost
transitioning its Lean program to LSS process than the competition [4]. In particular, there are three
improvement strategy. Both Lean and Six Sigma were basic goals pertaining to business, technology, and
seen as methodologies that work in synergy improving culture that are part of this pursuit for world-class
the cycle time and reducing variation. To better quality. First, Six Sigma supports the long-term
describe this synergy we will first briefly explain both business plan to achieve customer satisfaction while
Six Sigma and Lean concepts. simultaneously increasing market share and profit
margin. Next, leaders are trained to use state-of-the-art
technology to meet performance goals. And finally,
2.1 SIX SIGMA Six Sigma breeds a world-class culture to maximize
competitive advantage. [5]
Six Sigma began as a quality improvement effort to
identify and reduce all sources of variation. It then
evolved into an overall management strategy for 2.2 LEAN MANUFACTURING
measuring and improving performance across different
processes. The main emphasis of Six Sigma is the Lean Manufacturing is focused on eliminating non-
application of statistical tools in a disciplined manner, value added activities and special cause issues, process
which requires data-driven decision-making. Six Sigma standardization, and reducing process noise. It is less
is about controlling processes to get the desired results. technical and more rapid when compared to Six Sigma.
The target process can be any process critical to Lean Manufacturing is excellent for developing a
customer satisfaction and bottom line benefits such as culture that accepts change and helps breed one focused
maintenance, supply chain management, manufacturing on continuous improvement, or so-called Kaizen [6].
products within specifications, or providing services Lean Manufacturing employs Kaizen methodology for
efficiently and effectively. Each process has a number continuous improvement and links it to processes to
of inputs and each input has various degrees of impact reduce lead time, increase flexibility, and eliminate
on the output. Inputs are given by process suppliers waste [6]. Lean Manufacturing eliminates non-value
and outputs are received by customers of the process. added activities according to The Seven Deadly
The challenge is to make the necessary adjustments in Wastes [7]. These are defined as the waste of:
processes so that the impact of noise or uncontrollable
input variables are minimized to limit variation, i.e., to
control your process. Six Sigma tools enable the
identification of critical input parameters with the
Overproduction producing more than the stakeholders focus on a process for up to a week to
customer will buy which leads to excessive reduce occurrences of waste.
inventories;
Inventory excess inventory of parts and 2.3 LEAN SIX SIGMA
materials before they are required;
Transportation the unnecessary movement of In the past two years many organizations realized that
material or product; Lean and Six Sigma methodologies compliment each
Processing unnecessary or inefficient other. The integration of Lean and Six Sigma provides
operations; a rapid process improvement strategy for attaining
Scrap excessive defects and rework of organizational goals. When separated, Lean
materials, labor and overhead; Manufacturing cannot bring a process under statistical
Motion non-value added movement of control, and Six Sigma cannot dramatically improve
workers and equipment; cycle time or reduce invested capital [6]. Together,
synergistic qualities are created to maximize the
Waiting excessive time waiting to proceed to
potential for process improvement. Figure 1 shows the
the next step in the process, or idle time. [7]
combined power of Lean and Six Sigma. M. L. George
describes LSS as a methodology that maximizes
Lean creates a self-sustaining culture by focusing on
shareholder value by achieving the fastest rate of
the Five Ss. These are Sort, Set & Order, Shine,
improvement in customer satisfaction, cost, quality,
Standardize, and Sustain. This system provides the
process speed, and invested capital[9].
motivation for a workforce to maintain a neat, clean,
and efficient workplace. Improvement projects are
called Lean Events where a team of process

Figure 1: Typical Process Results From LSS

Shipbuilding is a distinct manufacturing industry. enables LSS to be effectively applied to shipbuilding


Unlike other manufacturing industries, shipbuilding and to produce significant gains in process
does not produce mass quantities of its products in the performance.
U.S. It usually builds one ship for a long period of time
and most ships are different than the one before it. The large size of the ships being built requires great
Also, the scale in which it must be built is amounts of material, parts and equipment. As a result,
unprecedented compared with other industries. These inventory management is vital to a successful
are the largest moving structures built in the world. operation. Furthermore, as the amount of material,
However, one thing does make it alike most other parts and equipment increases so does the opportunity
manufacturing industries shipbuilding is a systematic for defects and variation within the shipbuilding
process. In this way, each ship may be unique but is process. The large volume of material, parts, and
built using the same processes as its predecessors. This equipment must also be moved from one place to the
next, until it finally makes its way to the ship. The cost Fortunately, all of the above elements are present in the
of waste and long lead time is potentially very high. shipbuilding. Benefiting from the favorable rollout
There are also a large number of different processes scenario, NGSS started its implementation by selecting
that must occur before a single piece of steel becomes a the highest visibility area. Reduction of defects in the
part of a ship. Likewise, the complexity of ship system factory processes was seen as the area that workforce
design and the cost to rework these defects leaves little will be able to embrace first. To make LSS happen a
room for error. A defect in some shipbuilding large amount of workforce training is required in
scenarios can result in serious setbacks, both in time several tiers. Top management, middle management,
and money. To maximize the benefits of LSS foremen, line employees all need to be trained to make
implementation, the concept rollout within a shipyard LSS a success. In the next section, workforce training
needs to be performed in stages. requirements are described.

As with like methodologies that require culture change,


LSS implementation should be approached in stages 3. LEAN SIX SIGMA SHIPBUILDING
that start in an area of high visibility, with high WORKFORCE TRAINING STRATEGY
potential for success and return on investment.
Examples of such areas would include Production, Through the collaborative effort, authors provide LSS
Engineering, and Information Systems. The nature of training to NGSS as well as mentoring for numerous
this work is highly compatible with the application of LSS projects. In addition, the group is conducting
LSS techniques, including: research projects on various aspects of LSS such as
refinement of a cost of poor quality system to drive
Repetitive processes, many associated with project selection, institutionalization of change, root
automated equipment cause corrective action for project delays, knowledge
Controlled Factory environment, under one management to replicate gains from LSS projects, data
roof quality assurance, critical equipment availability
High volume material and parts flow, with improvement, and Design for Six Sigma (DFSS).
families of similarity Extensive background in education and shipbuilding
Stable, team-based workforce, maximizing the experience of instructors is needed to provide a
return on investment of training learning experience that translates directly to on-the-job
High leverage on downstream operations by performance. Shipbuilding environment is different
improving quality and accuracy from the previous implementation of LSS. Translating
Highly visible and measurable in terms of the LSS in the language of shipbuilding was a
cycle time, work in process, and quality. challenge that shipyard was aware about from the
beginning. Figure 2 shows the timeline of LSS
implementation and UNO collaboration at NGSS.

Increasing Program Complexity Competitive Environment Opportunity to Excel

1985 1990 1993 1994 1995 1998 1999 2000 2001 2002 2003 2004

Lockheed Missile & NGSS Lean Six Sigma Kick-Off


Motorola Goodrich Boeing Space NGSS Infrastructure Development
Space - LM21 Six UNO / GCRMTC LSS Project Yr 1
Six Sigma Lean Enterprise Lean Six Sigma Self Sustaining Program
Sigma Structure with Black Belt / Champion Training starts
Design UNO / GCRMTC LSS Project Yr 3
Lean focus NGST Six Sigma Kick-off
IBM UNO starts GB/BB Training & Mentoring
Six Sigma KM initiative begins
Master Black Belt training Starts
Raytheon UNO / NGSS Six Sigma Pilot UNO / GCRMTC DFSS Pilot
Boeing Aerospace Allied Signal
Six Sigma on Avondale Cranes 60 BB/ 60 GB projects in progress
Lean Six Sigma General Electric
Honeywell Norfolk Naval Shipyard Six Sigma Pilot
NGSS expands LSS program
J&J Expands to Portsmouth, Puget Sound,
UNO / GCRMTC LSS Project Yr 2
Six Sigma Programs Pearl Harbor
Green Belt training kick-off
NGNN Six Sigma Pilot
45 projects completed
40 BB / 5 GB projects

Combining
CombiningSixSixSigma
SigmaQuality
Qualitywith
withLean
LeanSpeed
Speed
Reducing
Reducingcomplexity
complexitythrough
throughLean
Lean
Increasing
Increasingprocess
processcapability
capabilitythrough
throughSix
SixSigma
Sigma

1/27/04

Figure 2. UNO-NGSS LSS Collaboration

Getting the right project for the LSS training class is Companies which developed CoPQ systems can choose
essential for successful workforce education. the projects based on the bottom line impact. However,
many organizations implementing Six Sigma tend to where the defect was discovered. However, the excess
use a prioritization matrix [10]. These matrixes are costs attributed to the defect are much more extensive.
completed by utilizing customer data which, by its Upstream and downstream processes may be affected
nature, does not account for actual costs of poor by having to reschedule work. The rescheduling of
quality. work at one station may cause priorities at other
stations to change. When those stations priorities
More time needs to be spent training Champions, Black change still others will change, and so forth.
Belts, and Green Belts on the impact of CoPQ, Rescheduling costs include, expenses such as extra
including domino effects in the manufacturing setups and tear-downs, idle time, expediting costs for
process. The emphasis on expanding CoPQ coverage to transporting materials, the cost of planners and
include domino effects in training classes and schedulers needed to make the changes, and the costs
mentoring sessions can make project impact assessment of delivery delays to other products whose priorities
more realistic. were reduced.

The need to modify the existing Lean Manufacturing These problems are particularly severe in lean/Just-in-
implementation by introducing a Six Sigma toolbox time (JIT) systems due to the reduced amount of work-
was recognized in complex product manufacturing as a in-process (WIP) inventory. When a stations schedule
way of dealing with variation in a resource constrained changes and the inventory needed for the new highest
environment with an expanding workload. It was also priority job is available, the ripple effect is attenuated
discovered that CoPQ is more complex to quantify in or even terminated. However, in lean/JIT systems
this scenario. Where as domino effects are significant where a conscious effort has been made to reduce WIP
when quantifying CoPQ, a literature survey showed inventory, it is necessary to adjust the priorities at
that there is very little research done on this subject, supplying stations. Thus, the ripple continues, but the
also referred by some as snowball or ripple effects. energy in ripples can be absorbed by inventory.
The study of CoPQ and domino effects is needed to
clearly reap the benefits of integrating Lean and Six Accounting for the domino effect is difficult for
Sigma methodologies. CoPQ and domino effect many companies. By using the conventional unit-based
concepts should also be included in both Lean and Six cost systems, there is no one way to accurately
Sigma training courses. determine ripple effects [12]. A study was also done
using transition probabilities to explain how failure
As far as project selection is concerned, including costs flow and accumulate in the entire production
CoPQ assessment as a supplement to expert-opinion- system. The only problem with using transition
based project selection the matrix criteria will become probabilities is that they can be subjective in nature
more effective. An example of such a matrix is given [13].
in Figure 1, where AOR means Area of Responsibility
and BB means Black Belt [11]. As shown in Figure 1, The problem with Job cost systems is that they capture
even though Six Sigma is a data driven methodology, costs by having time and materials charged to the jobs
numerous organizations use subjective judgment and being processed. For instance, if a worker is setting up
expert-opinion-based weights as the primary method to work on Product A, their time is charged to Product
for project selection. The obstacle in using CoPQ data A. However, if a problem with Product B forces the
including domino effects for project selection is the worker to break the setup for Product A and do Product
missing link between CoPQ data and accounting chart B, the time spent tearing down and then later resetting
of accounts. If a company associates the accounting up for Product A is still charged to Product A.
system with the CoPQ system including domino Similarly, if a problem with Product B causes the
effects data, Six Sigma project selection can be based worker to have to stay late to finish work on Product A,
on hard data. that was interrupted by Product B, the overtime will be
charged to Product A. To better demonstrate impact of
the domino effects in manufacturing an example is
4. IMPACT OF DOMINO EFFECTS IN given in the next section.
SHIPBUILDING PROCESSES

This section discusses the domino effect of poor 4.1 SHIPBUILDING EXAMPLE
quality. First, a discussion of the typical breakdown of
the costs of poor quality (CoPQ) is presented. Next, The following example will help to better illustrate the
the often neglected domino effect costs are reviewed. domino effect in shipbuilding. The panel production
line in Figure 3 consists of three sequential production
When a failure occurs somewhere in the system, the stations: plate joining, stiffener positioning, and
effects ripple throughout the system in a manner similar stiffener welding. For simplicity, each station is
to that of an earthquake. Obviously rework must be assumed to have a lead-time of 2 hours for every panel
performed and scrap may be generated at all of the and a 1 hour setup to change from one panel to the
stations between where the defect was created and
next. Travel time between stations is considered (rework and scrap) are easily captured by many
negligible. accounting systems. However, consider the domino
effects of this problem. Using the schedule in Figure
A simple Gantt chart schedule by station appears in 4 where there is a 4 hour inventory buffer, note that the
Figures 4 and 5. The schedule in Figure 4 assumes plate joining station can rework Panel A from hours 3
there is a 4 hour buffer of WIP inventory in between to 5. Thus, Panel A will arrive at the stiffener
each of the stations. That means that the schedule is set positioning station at hour 5, which is 2 hours prior to
such that panels arrive at production stations 4 hours when it is needed. Therefore, no downstream
prior to when they are scheduled to be processed. As is rescheduling is needed. Note, however, that what was
shown below, this inventory helps buffer the panel a 4 hour buffer is now down to 2 hours. There is only
production from quality problems. However, there is a room now for one more such problem before the
significant cost associated with having that extra protective buffer is fully depleted. Assuming that the
inventory. plate joining station can work some overtime to get
caught back up, the WIP buffer can then be increased
Figure 5 shows the schedules for the stations assuming back to 4 hours. However, as noted before, the job that
no WIP buffers. This is essentially the ideal JIT gets charged for the overtime will likely not be Panel
environment. Certainly, few if any manufacturing A.
facilities have achieved this ideal. It is used here
merely to help illustrate how the domino effect is Now consider the ideal lean situation depicted in Figure
exacerbated by lean systems that still have quality 5. Here there is no protective buffer of WIP inventory.
disruptions. Thus, even if a problem occurs at the plate joining
station and is detected at the plate joining station,
significant domino effects are felt throughout the
Plate Stiffener Stiffener panel production. Since the plate joining station will
Joining Positioning Welding
have to spend time reworking Panel A, the stiffener
positioning and stiffener welding stations will have
holes in their schedules later where they were supposed
Plates &
WIP WIP Panel to be processing Panel A. However, the lack of
Stiffeners
material will cause them to go idle for 2 hours. Thus,
Panel A will be late by 2 hours. Depending on the
Figure 3. Panel Manufacturing Process situation this could result in lost incentives, delay
charges, expedited transportation/delivery costs, and/or
lost customer goodwill. Furthermore, the problem is
not just limited to Panel A. All successive panels will
incur the same CoPQ until some excess capacity (i.e.
overtime) is available that allows the panel production
to catch up.

An alternative to the above lean scenario is that when


Figure 4. Station Schedules for Panels A thru F with Panel A is found to be deficient, that panel is set aside
4 Hour WIP Buffer (S = setup) and not processed until excess capacity becomes
available. This will keeps successive panels from being
late. However, Panel A will be significantly later
(more than just 2 hours).

4.1(b) Delayed detection of defect scenario

What happens if a quality defect is created at the plate


joining station but not found until the stiffener
Figure 5. Station Schedules for Panels A thru F with
positioning station has completed processing Panel A?
No WIP Buffer (S = setup)
Looking at the 4 hour buffer schedule shown in Figure
4 reveals that the problem would not be discovered
until hour 9. If Panel A is immediately rerouted back
4.1(a) Timely detection of defect scenario
to the plate joining station it could be reworked from
hour 10 to 12 (hour 9 to 10 is needed for setup to do
The least disruption problem this panel production
Panel A). This will, of course, delay Panel D and all
would encounter is if a quality defect occurs at the plate
successive panels at the plate joining station by 2 hours
joining station and is detected during final inspection at
until some excess capacity is available. However, due
the plate joining station. Certainly, the plate joining
to the presence of the 4 hour WIP buffer, none of the
station will need to rework Panel As and those costs
panels coming off of the stiffener welding station are
delayed. Once again we see that the inventory buffer appears in many upstream and downstream production
acts to absorb the energy in the domino effect. This processes. Understanding the magnitude of the
scenario is illustrated in Figure 6. domino effect in large systems manufacturing can be
the key for quantum leaps in the process improvement
initiatives such as LSS, since a company would truly
understand the affect on the bottom line.

5. SHIPBUILDING LEAN SIX SIGMA


PROJECT EXAMPLES

Figure 6. New Schedule after Reworking Panel A (S Since 2000, authors have been involved in Six Sigma
= setup) implementation, starting the Continuous Improvement
of Drydocking Project sponsored by the Office of
Naval Research via the Gulf Coast Region Maritime
Figure 4 illustrated that without the 4 hour buffer a Technology Center at the University of New Orleans.
problem that goes undetected becomes more Pilot projects included reduction of growth work during
problematic. In this case the problem is found at hour drydocking, ship repair specification development,
5. The plate joining station is in the middle of crane availability improvement, paint cost reduction,
processing Panel B at this point. Therefore, it is ship repair contract development, error reduction in
necessary for the plate joining station to either break shipyard accounts payable process, as well as tow tank
the setup for Panel B and immediately do Panel A process improvement. The first wave of LSS
(Figure 7) or wait for Panel B to be completed and Implementations included accuracy of deflanging I-
insert Panel A (Figure 8). Based on meeting beams, and accuracy of stiffener fitting process at panel
completion times, not allowing setups to be broken line, which are led by the authors as well as numerous
(Figure 8) performs better. Figure 7 shows that Panel B pilot projects led by NGSS employees. Some of these
would be completed by the stiffener welding station on projects are summarized below.
time. However, Panel A would be late by 4 hours (hour
13 rather than hour 9), Panel C would be 3 hours late
(hour 16 rather than hour 13) and Panel D would also 5.1 ACCURACY OF DEFLANGING OF I-
be 3 hours late (hour 19 rather than 16). Thus, the BEAMS
CoPQ including the domino effect is the cost of
being late for panels A, C, and D; rework costs for A baseline study was conducted to identify the
Panel A at both plate joining and stiffener positioning performance of the current process and adherence to
stations; and idle time for the stiffener welding station. accepted hull standards. The focus of the project was
on deflanging I-beams after data collected from the
baseline study revealed excessive variation in the
process. This variation creates welding re-work and
results in added weight to the structure. The standard
procedure for the process was analyzed and found to be
inefficient in some areas. This tends to increase cycle
time and likely adds to process variation. Maintenance
practices are also studied to identify the effectiveness
of the current maintenance policy and to examine the
Figure 7. New Schedule to Rework A with Broken
availability of the machine. To reduce the variation of
Setups Allowed (S = Setup) the deflanging process and more effectively meet hull
standards, several improvement areas were identified.
A modification to the web sensor that controls the
plasma cutting torches was deemed necessary to reduce
deflanging variation. The modification significantly
improved process control limits and also reduced the
amount of material left on the structure after being cut
[15].

Figure 8. New Schedule to Rework Panel A with


Broken Setups Not Allowed (S = Setup) 5.2 ACCURACY OF STIFFENER FITTING
PROCESS AT PANEL LINE
The example has shown the domino effect
implications on both JIT and non-JIT manufacturing. In To improve the accuracy of structural placement and
the case of large systems manufacturing such as ships, neat edge alignment measurements, the researchers
airplanes, oil platforms, the CoPQ domino effects conducted several multifunctional department meetings
to come up with a new tool that will improve downtime will be minimized to achieve the NGSS
measurement accuracy. Several designs were presented target Availability. Furthermore, an important
and a decision was made to build a new tool. The deliverable of the Control phase will be to identify
application of the new measurement tool is expected to savings and cost avoidance as a result of this project.
significantly improve panel line accuracy. In addition, Due to the high level of criticality calculated for this
it was also decided to implement a Lean tool called crane, the return on investment for this project will
visual factory to help people working in the panel likely be very favorable [16].
line manage measurement data collection through
displaying the data as soon as collected. A bulletin Categorized "Crane" Downtime 2004

board displaying both neat edge alignment and January February March April May

structural placement measurements was placed in the 130


"Crane" Downtime 2004
panel line to help the production team see how the 110
200.0

process performs over time. The bulletin board will

Downtime (hrs)
150.0
90
also give management a picture of the processes 100.0

Downtime (hrs)
70
without interfering with production [15]. 50.0

0.0
50 January February March April May

30

5.3 CRANE AVAILABILITY 10


IMPROVEMENT

y
PM

m
or

ist
e

al
r

es

ts
-10

ve

we
the

lle
Tim

e
tric

o
t

Ho

ak
era
Tra

gn

Bo
Tro
Po
a

Br
We

Ma
p

Ele
Sto

Ge
LSS is now used extensively to improve the
Availability metrics of equipment at NGSS. One such
project is focusing on the Availability of a critical Figure 9 Crane Downtime Chart Indicating Total
crane, and uses data generated by the Production (Inset) and Categorized Downtime [16]
organization to identify common failure categories and
to work with the Maintenance organization to perform
root cause analysis and corrective actions (RCCA). 6. VALIDATION OF SAVINGS

The data collected by Production not only reports As mentioned in the section 4 of this paper, accounting
downtime due to mechanical failures, but also due to for all CoPQ costs represents a major challenge when
non-maintenance related events causing stop time. The trying to quantify the benefits of LSS projects.
data collection system also has a category to record Financial Indicators are based on investment and
weather related downtime since coastal weather savings. For shipyard LSS projects, there are two
regularly causes this particular crane to be idle. investors: shipyard and ship-owner (customer). If
Generally, these two categories are the portion of project is successful savings accrue to shipyard or ship-
downtime that is not related to mechanical failure or owner or both shipyard and ship-owner. This situation
any other maintenance related activity. results in two indications of financial worth, one to
each investor.
The chart in Figure 9 identifies common downtime
categories on a monthly basis beginning in January To better illustrate validation of savings we will show
2004. In this figure, the scale has been removed to the example stiffener welding project [17]. The actual
protect proprietary information. The data shows a five dollar amounts have been removed to protect
month period of corrective maintenance related proprietary information.
downtime is 47% whereas weather related and
operations related stop time are responsible for 22%
and 20% of downtime respectively. Figure 9 (inset) 6.1 SHIPYARD SAVINGS
shows how addressing the root causes of various
downtime categories has resulted in a significant Savings to shipyard include:
reduction of downtime for the crane for the January to
May time period. The total downtime has been reduced Reduced rejection of stiffener due to quality,
by 42%, but downtime due to only mechanical failure Increased processing speed allowing less labor,
has been reduced by 70%. Reduced cost of welding wire due to smaller weld size,
However, this LSS project is currently in the Improve Reduced cost of weld rework due to improved quality,
phase and there are several root cause categories and Reduced beam setup time (not yet determined ~ no
processes that still need to be addressed. It is evident estimate calculated), and
that this is causing some fluctuations in the cranes Reduced inspection time (not yet determined ~ no
monthly downtime. Once these additional RCCA tasks estimate calculated).
are completed, the project will progress into the Control
phase where an effective Control Plan will be It should be noted that weld-grind and grind costs were
developed to stabilize and monitor the cranes determined by timed experiment for sample panels
downtime. Based upon project objectives, the undergoing rework. Defects and defect rates with
associated cost before improvements and after amortized over the three projects. Supplies are also
improvements were computed. used on projects with a pro-rata absorption estimate.
The salary and training costs dominate. Some other
A summary of savings for shipyard results from these costs include the cost of hourly participants and
the project is shown in Table 1. material costs for the fabrication of test panels. Each of
these costs is determined in the order outlined here.
Table 1 Summary of Annual Cost Savings to
Shipyard [17] Table 2 summarized the costs experienced by the
Reduced rejection of stiffeners XXXXX* shipyard during the life of the project.
due to quality
Increased processing speed XXXXX Table 2 Summary of LSS Project Costs [17]
allowing less labor Type of Cost Amount
Reduced cost of welding wire XXXXX Black Belt Candidate XXXXX
due to smaller weld size Hourly Meeting Costs XXXXX
Reduced cost of weld rework XXXXX Fabrication Costs Labor XXXXX
due to improved quality Fabrication Costs Material XXXXX
Current Total Estimated XXXXX
Savings to Northrop Grumman The shipyard Return on Investment (ROI) for this
*Due to nondisclosure agreement the dollar values will project is calculated to be 2,409.7%. Clearly, this
not be shown. project has shown significant benefits to the shipyard.
The shipowner ROI is determined to be 486.7% as a
result of the stiffener welding LSS project. Clearly
6.2 SHIPOWNER SAVINGS booth shipyard and shipowner benefited. Ultimately, an
LSS project financial success depends on how the
Cost savings that are available to the ship-owner company culture is willing to change. In the next
include improved ownership costs, and in the case of section we will discuss impacts of culture on LSS
stiffener welding these ownership costs are principally implementations.
derived from reduced dead weight of the vessel. Using
methods developed by a ship program office to
estimate the beneficial effects of weight reduction, the 7. CULTURE CHANGE
savings to the ship-owner for that weight reduction can
be found, over the life of the ship. However, this is only LSS implementation requires culture change. This is
part of the weight reduction. Improvements to the especially important in shipbuilding were data driven
stiffener quality resulted in reducing its weight. A culture is relatively new. One of the characteristics of
formula developed by the ship program office includes successful LSS efforts is that top management thinks of
calculations of fuel savings for the ship-owner resulting LSS as a culture. It becomes a way of life where all
from the weight reduction. improvement efforts fit under the umbrella of LSS.
Although the LSS implementation is still relatively new
When the ship contract is a cost plus contract, savings in shipbuilding, the shipbuilder examples used in this
to the shipyard are also savings to the ship-owner. So, paper shows the full support for the LSS program.
the net savings to the ship-owner includes both the Expanding workforce training creates larger groups of
ownership costs, and the cost of construction. people that are able to speak in terms of LSS. All
However, the timing of these costs is different. Savings improvement activities start to fit under the LSS
from decreased ownership costs occur for every year of umbrella. Ultimately, the shipbuilder will reach the
ship operation, and savings from decreased cost of LSS sustainability goals once the LSS is no longer
construction represent one time savings, occurring referred to as a program. Furthermore, it may not even
when the ship is constructed. be referred to as LSS.

Using the research conducted by the authors, it was


6.3 PROJECT COST realized early that culture change takes time. Creating
data driven environment is critical for the success of
Project costs are principally salary costs and training LSS. As more people get educated that making decision
costs with a small amount of supplies expended. Since based on data is prudent way to develop good
employees may have multiple roles and multiple LSS improvement actions, the shipyard will be able to
projects, the time devoted to each project is applied benefit more on LSS. The other aspect of LSS success
used to develop a percent of time devoted to this is based on timely LSS project completion. As
project. This percent is then used to obtain a pro-rata mentioned before, LSS is based on small manageable
basis for the employee time. Each employee who is a projects that produce high returns. A small project
Black Belt candidate is expected to complete three six means that it should not last more that six months for
sigma projects, so the training cost is needs to be Black Belt projects and four months for Green Belt
projects. This time limits keep project teams focused on with potential for defects. This makes the application of
eliminating defects in the small manageable areas. LSS appealing to shipbuilding.

Last but not least is ability of people to work in teams.


Significant amount of time is spent training Green Belts 9. ACKNOWLEDGEMENTS
and Black Belts on how to work in teams. To keep the
project teams focused, Green Belts and Black Belts The authors gratefully acknowledge the contributions
need to create the environment of dependency where of the following groups and individuals for their
personal success is a team success and vice versa. The contribution to this paper through the research projects:
LSS team culture helps promote LSS methodology
throughout the organization. The more people become Office of Naval Research, Gulf Coast Region Maritime
part of LSS teams the bigger is the momentum and LSS Technology Center, Steve Strom, Dr. Marino (Nick)
become the way to operate a company. This was Niccolai, Steve Maguire, Dr. Clifford Whitcomb, Dr.
observed in our shipbuilding case described in this Anthony Patti, Kevin Jarvis, William Leonard, Nubia
paper. Westland, Donald Dorsey, Gene Reed, Regan
Hoffmayer, Prof. Will Lannes, Nicholas Skific, Joe
Snodgrass, Michael Garcia, Andrian Hanson, Dr. Alley
8. CONCLUSIONS Butler and Mark Pavkov.

LSS is essential for the success of any competitive


shipbuilder. The combined benefits of the two 10. REFERENCES
methodologies support the need for shipbuilders to
cope with the scale and complexity of its processes. 1. Ono, T., Toyota Production System: Beyond Large-
Together, Lean and Six Sigma are capable of Scale Production, Productivity Press, February 1998.
improving the performance of shipbuilding processes 2. Womack, J.P., Jones, D.T., and Roos, D., The
and cultivating a culture of continuous improvement. Machine That Changed the World : The Story of Lean
LSS enables merging process improvement initiative to Production, HarperCollins, Reprint edition, November
achieve greater improvements. 1991.
3. Womack, J.P. and Jones, D.T., Lean Thinking,
To improve any shipbuilding process, shipyards need to Simon & Schuster, 1st edition, January, 1996.
have good accounting for CoPQ. The largest moving 4. Mitchell, John. Physical Asset Management
structures in the world build in shipyards are produced Handbook, N.p, 2003.
in a systematic manner where thousands of processes 5. Air Academy Associates. Six Sigma Expert Volume
lead to building a ship. These processes are related and 1. N.p., 2002.
understanding of domino effects is critical to be able 6. Inozu B., et al., Lean Six Sigma in Shipbuilding
to prioritize improvement activities. Since LSS is a data AMTAC Interim Report Year 1, School of Naval
driven improvement methodology, it is essential to Architecture & Marine Engineering, University of New
make decisions on starting LSS projects using CoPQ Orleans, July 2003.
data. Shipyards that are implementing Lean and Six 7. Sturdavant, T. L. Lean Production Techniques for
Sigma and once that are thinking of starting LSS need the Shipbuilding/Ship Repair Coatings Industry, N.p.,
to build the CoPQ foundation. A good CoPQ system November 7, 2002.
that accounts for domino effects also helps validate 8. Campanella, J., ed., Principles of Quality Costs.
LSS project savings by having the financial baseline. Principles, Implementation and Use. ASQ Quality
Press: Milwaukee, 1999.
There are several lessons learned from the first 9. George, M. L., Lean Six Sigma: Combining Six
implementation of LSS in the shipbuilding Sigma Quality with Lean Speed. McGraw-Hill: New
environment: York, 2002.
LSS requires data accuracy to produce results 10. Kelly, W. M., Three Steps to Project Selection,
LSS project times needs to be monitored to Six Sigma Forum Magazine, Vol 2, No. 1, p p.15 17,
assure project focus and completion 2002.
LSS can produce favorable results for both 11. Husted, J., Six Sigma at Allstate, Six Sigma
shipyards and ship-owners Summit, Tucson, AZ, USA, September 2004.
Workforce education and time allocation for 12. Turney, P. B., How Activity-Based Costing Helps
the project is vital. Reduce Cost, in Engineering Practices in Cost
Management, Edited by B. J. Brinker, Warren,
In conclusion, LSS has a great potential to improve Gorman, and Larmont, New York, pp.11 19, 1991.
shipyard competitiveness by shortening process cycle 13. Sastri, T., Feiring, B. and Mongkolwana, P.,
and reducing WIP variation. Shipbuilding process deals Markov Chain Approach to Failure Cost Estimation in
with large amounts of WIP each representing products Batch Manufacturing, Quality Engineering, Vol. 13
No. 1, pp.43 49, 2000.
14. Inozu, B. and I. Radovic, Improving Dry-docking
Processes to Increase Profitability, Ship Management
Conference, London, October 2001.
15. Inozu B. and Radovic I., Implementation of Lean
Six Sigma in Shipbuilding and Ship Repair, Ege
Maritime Congress, Izmir, Turkey, June 2003.
16. Davis J., Inozu B., MacClaren B., and Radovic I,
Creating A Reliability Culture In the Maritime
Industry, SNAME Annual Conference, Washington
DC, September 2004.
17. Inozu, Bahadir, et al., Lean Six Sigma in
Shipbuilding AMTAC Interim Report Year 2,
School of Naval Architecture & Marine Engineering,
University of New Orleans, September 2004.

You might also like