Professional Documents
Culture Documents
Concurrent delay:
Time does not always equal money
Andrew Bayne, Partner, Centra Consult
In contrast to City Inn, Walter Lilly & Co Ltd v Mackay (2012) EWHC
1773 (TCC) reafrmed what had been the established position. At
paragraph 370 of the judgment, Mr Justice Akenhead states:
where are we up to? A period of project overrun which is caused by two or more
effective causes of delay which are of approximately equal
causative potency.
additional works but it may still result concurrent delay was operative and where
in critical path delay. The contractor may costs were being incurred pursuant to the
be experiencing delay which is its own failings of the contractor. However, where
responsibility (shortage of labour is an two concurrent issues exist, it should be
example used in the above judgments) but possible for the chain of causation to be
where does this result with regards to an established whereby costs arising from the
extension of time being due? Perhaps to effect of relevant events can be recovered
an employer or contract administrator, the by the contractor. An example would be
shortage of labour may be the effective where the relevant event has prolonged
cause of critical delay. However, if the the period that a tower crane was needed
impact of the relevant event results in on site. Site staff costs are perhaps less
a chain of causation upon the critical easily disentangled for the purpose of
path which delays completion, then a attributing to a relevant event so a
contractor would feel somewhat aggrieved degree of apportionment would perhaps
if the employer is still entitled to deduct be understandable. If an extension of time
liquidated and ascertained damages. is granted, it does not necessarily result
in a situation whereby the contractor can
Time v money recover all of its time-related costs. But
It is important to emphasise the distinction in relation to time, if a chain of causation
between time and money. It is entirely can be established where a relevant event
possible that an extension of time may has delayed completion, albeit during a
be due, but that no loss and expense period of concurrent delay, should the
is payable and vice-versa. The chain employer be entitled to deduct damages
of causation should apply to loss and for contractor delay during this period?
expense as well. However, perhaps the Under a traditional standard form
apportionment approach described in the contract, where assessment of extension of
City Inn case is more appropriate with time is undertaken retrospectively, the full
regards to loss and expense? effect of a relevant event may already be
In general, time related costs such as known at the point in time an extension
preliminaries would not be payable to the of time is granted. It may be that, in
contractor during a period of concurrent retrospect, the contract administrator takes
delay. The contractor would still need the view that the effective cause of critical
to be on site for the period where its delay during the period the relevant event
2016 Delay 65