You are on page 1of 2

the answer is...

The Society is not responsible for any statement made or opinion expressed herein. Data and information developed by the authors
are for specific informational purposes only and are not intended for use without independent, substantiating investigation on the
part of potential users.

ANSWERED BY
KENNETH ERICKSON & KIP MANKENBERG

Q: We have an upcoming AWS D1.1 take advantage of the as-detailed toler- and loss of time.
project for which the project specifi- ances allowed by Figs. 3.3 and 3.4, and to Every potential crack condition needs
cation requires ultrasonic testing put those in the shop drawings. The to be researched and investigated to
(UT) to be performed on open root code then allows the as fit-up toler- determine the cause and corrective
butt splice joints (girth welds) in 8- ances to be applied to the dimensions action for proper resolution. The term
and 10-in. round tubular members. shown on the detail drawing. crack is at times overused and misun-
The thicknesses of these members derstood. Indications that appear to be
range from 12 to 1 in. Can this be per- Q: Recently on a high-profile build- cracks or crack like may, in reality, not
formed using the techniques ing project, I rejected a weld visual- be cracks at all. I have been witness to
required by Section 6 of the code? ly for a longitudinal surface crack. CWIs visually reporting grinding
The project structural engineer indi- scratches, surface delaminations, and
A: Though Section 6, paragraph 6.20.1, cated that I should not utilize the sharp areas of nonfusion as cracks. NDE
does not exclude this joint configuration term crack on any report or in inspectors have also reported cracks in
for the testing techniques required by conversation until this has been ver- welds that later were determined not to
Sections 6.21 through 6.26, this particu- ified through NDE inspection. This be cracks at all.
lar application would be better examined leaves me confused, as the AWS CWIs can and should report disconti-
using a Section 6.27/Annex K technique. visual acceptance criteria clearly nuities as cracks in accordance with the
To list two reasons why this is the case, indicate and reference crack prohi- visual acceptance criteria when factual
the diameters of the tubular members bition and the term crack as one evidence indicates that a crack is present.
involved would likely not permit full cou- of the discontinuity categories for CWIs can also request that further sur-
pling of the search units required by inspection. In addition, there was no face NDE testing, such as magnetic par-
paragraphs 6.22.6 and 6.22.7, and para- NDE required on this weld other ticle and/or liquid penetrant, be per-
graph 6.27.6 could require the use of than visual inspection. formed on any suspect weld to accurately
search unit angles that are not specified evaluate and verify that a crack is pre-
in Table 6.7. I would recommend that a A: I have heard this same comment from sent. Inspectors should believe what you
UT procedure be developed as stated in both project engineers and NDE Level see and be accurate in what you report.
the first paragraph of Section 6.27, and III individuals for many years. The term
that approval of the engineer be obtained crack raises a warning flag and consti- Q: Are building threshold inspec-
as required by paragraph 6.20.2. tutes a more serious situation than the tors able to visually inspect welds for
more common inherent welding discon- final visual compliance?
Q: Do the as-fit-up tolerances of the tinuities such as porosity or undercut. A
prequalified joint details of AWS crack indicates that there is a potential A: Yes, and the key word here is able.
D1.1 Figs. 3.3 and 3.4 add to the breakdown attributable to the welding This is happening to this day on projects
as-detailed tolerances? procedure, welder or welding operator, throughout the countr y. Threshold
materials, filler metal, assembly, heat inspectors are commonly confused as
A: The short answer to this question treatment, or a number of other vari- also being Certified Welding Inspectors
would be yes. Section 2 of the Code, with ables that may have contributed to this and thus accept welds routinely. There
regard to the Contractor, requires that condition. If the welding procedures and are threshold inspectors who also do
shop drawings shall clearly indicate by the welders have been qualified, and all possess a current CWI endorsement but
welding symbols or sketches the details other variables are correct, then it is most do not.
of groove welded joints and the prepara- hoped this is only an isolated condition Project specifications referencing
tion of base metal required to make and not a generic finding. structural steel quality control require-
them. The code also allows the use, Visual welding reports may be ments regarding personnel and testing
within certain limitations, of the prequal- reviewed by several individuals and the may not specifically call out for certified
ified joint details shown in Figs. 3.3 (par- information contained needs to stand individuals. Certain projects may only
tial joint penetration) and 3.4 (complete alone and be as accurate as possible. call out for a building threshold inspec-
joint penetration). There is a cost and time factor attributed tor to cover all required inspections
It would certainly seem to make to all rejected welds, and welds reported including welding and never reference
sense in most cases for the contractor to as cracked can lead to additional costs any personnel certifications. This has

Inspection Trends encourages question and answer submissions. Please mail to the editor (mjohnsen@aws.org).

KENNETH ERICKSON is manager of quality at National Inspection & Consultants, Inc., Ft. Myers, Fla. He is an AWS Senior
Certified Welding Inspector, an ASNT National NDT Level III Inspector in four methods, and provides expert witness review and
analysis for legal considerations.

CLIFFORD (KIP) MANKENBERG is a welding engineer/NDT Level III for Oldenburg Group, Inc., Rhinelander, Wis. He is an AWS
Senior Certified Welding Inspector and an ASNT National NDT Level III Inspector in five methods.

30 INSPECTION TRENDS
always been a discrepant issue for us as and uncertified inspection and testing Project specifications need to be clear
all the welders and welding procedures personnel on a project. and accurate on their requirements and
need to be qualified but not the welding Owners, engineering companies, and documentation process including
inspector. general contractors have all been subject personnel certifications. Companies and
Specifications may include statements to inadequate inspection and testing ser- individuals who are super vising and
such as a qualified testing agency or vices due to incomplete and inaccurate enforcing these requirements need
competent threshold inspector or even project specifications coupled with to be knowledgeable and recognize
a degreed engineer. All these are com- inspection companies that are skilled in which individuals and companies can
mon generic statements utilized that per- recognizing these so-called incomplete perform what services and for what
mit companies to provide less qualified and gray areas. applications.

SUMMER 2006 31

You might also like